Release cycle
(development process)
&
Delivery roadmap
the Goal:
• Design a well balanced Release Cycle in regard of your constraints
• Define your catalog of release cycles (one per User Story family) and your SLA
Release cycle (development process)& delivery roadmap
the key points: the development process, the different type of Test
Key Basics:
• A release cycle is a development macro process
• it’s build around the major steps: Business Requirement/Spec/Dev/Test/Prod setup
• Some steps are ‘Value Added’ for the End User, others are not
• The goal is
• to continuously reduce your constraints to an acceptable level (e.g. reduce your non
regression phase from 1 week to 1 day, …)
• to balance the steps to have an acceptable global ROI
• The base is your average ratio Spec/Dev/Test (in workload, in lead-time)
• This ratio is defined by family of User Story you find in your Backlog
• Each new request should match a family, follow its associated process
Case Study:
We propose to simulate a simplified case study where we’ll mix
• 3 different families of User Stories defined around the criteria of urgency & complexity
• Different levers of improvement: eliminate, improve, reorganise
Hypothesis regarding the Test:
• to simplify the exercise, we take only regression & UAT. Others (Unitary, Functional,
Integration,…) are not taken into account here but should be in the real world
• we also suppose Functional tests are done just after the dev and not only in UAT (too late)
the Goal:
• Design a well balanced Release Cycle in regard of your constraints
• Define your catalog of release cycles (one per User Story family) and your SLA
Release cycle (development process)& delivery roadmap
the key points: Value added for the client/End User
Key Understandings:
• Qualify the 3 steps (Spec/Dev/Test) in ‘Value Added’/’Non Value Added’ for the End User
Hypothesis simplified for the case study:
• Let’s say your backlog is composed by 3 families: standard urgent, standard non urgent and
complex
the Goal:
• Understand the dev process step in terms of ‘Value Added’, ‘Non Value Added’ for the User
Spec Dev Test
VA VA Non VA
Average workload Average
Leadtime
Spec Dev Reg UAT
Standard urgent 25%
2.5MD
50%
5MD
10%
1MD
15%
1.5MD
2 weeks
Standard non urgent 25%
2.5MD
50%
5MD
10%
1MD
15%
1.5MD
4 weeks
Complex 25%
10MD
25%
10MD
25%
10 MD
25%
10MD
8 weeks
Release cycle (development process)& delivery roadmap
the key points: workload, leadtime, ratio ROI
Key understanding
• Current situation: the 3 release cycles are totally sequential
• Assess the quality of each release cycle in terms of workload & leadtime
• (1): ratio just balanced 1MD of VA for 1MD of NVA. Instead for standard 3MD for 1MD
• (2): any steps can be done in parallel?
the Goal:
• Assess the current Release Cycles in terms of ROI regarding the workload, the leadtime
• For the leadtime, it’s key to get the Voice Of the Customer
Average workload Assessment Average
Leadtime
Assessment
Spec
(VA)
Dev
(VA)
Reg
(NVA)
UAT
(NVA)
VA/NVA
Standard urgent 25%
2.5MD
50%
5MD
10%
1MD
15%
1.5MD
OK 7.5/2.5 2 weeks KO (2)
Standard non urgent 25%
2.5MD
50%
5MD
10%
1MD
15%
1.5MD
OK 7.5/2.5 4 weeks KO (2)
Complex 25%
10MD
25%
10MD
25%
10 MD
25%
10 MD
KO
(1)
1/1 8 weeks KO (2)
Release cycle (development process)& delivery roadmap
the key points: User Story family
the Goal:
• Assess the current Release Cycles in terms of ROI regarding the workload, the leadtime
 Current situation
 Key understanding: what can be improved?
2 weeks
4 weeks
8 weeks
Release cycle (development process)& delivery roadmap
key point: pull the Flow, paralellisation
the Goal:
• To reduce your leadtime, you can reduce steps, do some steps in parallel
• Let’s try first to parallelize dev and spec when you can
 Lever: parallelisation (pull the flow)
 Key understanding: start the dev as soon as the spec is ready (don’t wait artificially). Do it
for any step.
< 2 weeks
< 4 weeks
< 8 weeks
Release cycle (development process)& delivery roadmap
key point: continuous integration, code factory (code for the code), Test Driven Development
the Goal:
• Let’s try now to parallelize regression and dev
• you need to reduce the effort & time doing build & regression. Can you automate?
 Lever: Continuous integration (Test Driven)
 Key understanding:
• Continuous Integration is regular build & regression test all along the dev process. The
coder code to automate the build & regression test (code factory).
• Discover problem early in the process cost less (less root cause analysis, less effort to solve)
< 2 weeks
3 weeks
6 weeks
Release cycle (development process)& delivery roadmap
key point: continuous improvement, Test methodology, Over Quality when not required
the Goal:
• Improve your most heavy steps with No Value Added (e.g. UAT for complex User Story)
• Test methodology is question of taking a Risk: Which tests are required, which are not?
 Lever: Continuous Improvement on UAT for complex User Stories
 Key understanding: in the continuous improvement activity, optimise the UAT process. Some
ideas: Test expert can bring you best practices to optimise your strategy, the data used, etc …
< 2 weeks
3 weeks
5 weeks
Release cycle (development process)& delivery roadmap
key point: continuous improvement, dynamic Team capacity management, Visual management
the Goal:
• build your delivery roadmap using your catalog of release cycles
• Define the best strategy (regular deliveries variable content, fix content ad-hoc deliveries, …)
 Best case: your flow of User Story is quite homogeneous, predictable & activities quite
independent. You’re able to build & present to your client a stable delivery roadmap for the
next months. Regular deliveries with variable content is more ‘Agile’ & ensure process stability.
Easier to define & apply a SLA. Your team capacity management is capacity planning.
Example: 4 team members working on 3 applications
 Key understanding: your reality is particular. Based on best practices/methodology, build
your own model.
 Worst case: your flow of User Story is heterogeneous, unpredictable & activities dependant.
You can’t build a stable delivery roadmap in advance. You build dynamically & regularly
depending of your new User request. Your team capacity management is also highly dynamic
and is eased by visual management. Think about what is best for you regarding your
constraints: ad-hoc/regular deliveries, fix/variable release content
Release cycle (development process)& delivery roadmap
key point: daily & weekly meeting should be complementary not redundant
the Goal:
• How to use a release cycle?
• Check your team capacity, build your weekly meeting agenda, ….
 Build your release cycle per activity/project
 Key understanding:
Check your team capacity:
• Team members are not developing at the same time on Appli2 and Appli3
• Book time for your team to do continuous improvement
Read on the roadmap the weekly team meeting agenda
• Depending on where the team is on the release cycle, the agenda can cover subjects
like post mortem, performance monitoring, Best Practice sharing, …
• If not adapted to your context, weekly might be fortnightly or monthly
2
1
4
3
Release cycle (development process)& delivery roadmap
the key points: Project management, methodologies, technical tools … should do a ONE consistent
the Goal:
• List of key topics to assess to improve your release cycle & delivery roadmap
• Assess your team, your development process, your code management, your test, …
Code factory
• Create transversal/product team (Spotify)
• Review the development process from the request initiation to production
• onshore-offshore & RA(CI)
• Review roles:
• Team lead, Tech Lead, Scrum master & Product Owner
• others on offshore side
Review project & team management with Agile & Scrum key concepts (events & roles)
• work with MVP (Minimum Viable Product)
• build your final product incrementally through short iterations (PDCA cycle)
• adjust the meeting cascade (hoshin-kanri) to be aligned with TOP management vision
• Implement an electronic dashboard for splitted team to visualize & ease the communication
Review development factory with Lean key concepts
• easily control your code: code management & coder community (GitHub)
• easily deploy technical environment (PaaS/IaaS)
• easily deploy the code: automated package building & deployment (DevOps)
• prove your code is working (Google):
• test methodology & strategy
• continuous integration (build & automated test)
• improve continuously your Code & Factory: architecture & refactoring (SaaS)
1. Build the team: do you empower people?
2. Build the Agile iteration: do you try & adapt in short iteration?
3. Build the Code Factory: do you ensure code quality & fluidity in the process?
Appendix
the key points: all tools available in the Lean tool kit
A few examples of analyses you can do to improve your process:
To help your team understand where is inefficiency
1. Workflow mapping combined with RA(CI)
2. Post Mortem to compare your worst project and a successful one
3. And many others in the Lean tool kit …
Appendix 1
the key points: team work, all tools available in the Lean tool kit
Workflow mapping combined with RA(CI):
• Be careful not to mix several families
Waste of
time
D0
leadtime
processing time
1 02
03
0
3
0
2
15
1
3
0
2
0
1 12
15
3
in %
in days
processing time
vs
leadtime
step
11
1
step
10
0
step
9
2
step
8
3
step
7
50
step
6
10
step
5
3
step
4
5
step
3
50
step
2
25
step
1
60
D29D10 D20
~ 33 % ~ 33 % ~33 %
80
20
waiting
time
processing
• Too many stakeholders
• 1 request is dependent on 2 decisions levels
• Lack of coordination to avoid waiting time
• Waiting time (~80%) vs Processing (~20%)
• Steps 6, 9 with stakeholder X, 5, 8 (CC), 1 may be the first to focus on but feasibility requires to be checked
 Team X – workflow mapping – process Y
Appendix 1
the key points: team work, workload, leatime, waiting time
Workflow mapping combined with RA(CI):
• Be careful not to mix several families
• Step C: one person is doing, 4 other people are validating. This split generates 70% of waiting time (14 working days)
• Step D: meeting, writing minutes and make all sign generates 97% of waiting time (7 working days)
• Questions:
• Is the split required?
• If the split is required, is it possible to reduce the waiting time?
process step
0 1 2 3 4
role Step A Step B Step C Step D Step E
Stakeholder 1 RA
Stakeholder 2 RA A RA
Stakeholder 3 R R RA
Stakeholder 4 A R
Stakeholder 5 A RA
Stakeholder 6 A RA
Processing time
(in days) 5.7 0.155 0.005
leadtime
(in days) 20 8 1
waiting time
(in days) 14.3 7.845 0.995
1 2
Lean Best Practice
• To avoid waiting time, R and A should be in the same box to
avoid potential waiting time
• To better visualise the problem, don’t put the C & I of the RACI
Legend:
R: Responsible. The person who is doing the action
A: Accountable. The person who is accountable for the action
1
2
 Team X – workflow mapping – process Y
Appendix 2
the key points: team work, workload, leadtime, waiting time
Post Mortem to compare your worst project and a successful one
• Be careful not to mix several families
 Team X – workflow mapping – process Y
Production
Release
Delay due to
technical operation
25 Feb 2011
Specs & Estimates Dev Prep UAT
17 Jan 2011
6
Amendment
Release Estimate
0,1
Project Start with
Release Content:
05 Jan 2011
0,1
2 6
0,2
2
71,4
1
Change Content
Release:
03 Feb 2011
Freeze Content
07 Feb 2011
3
2
17,3
4
1
6
0,5 6,5
3 2
1,5 1,5
15
23 April 2011
9,7
27
5,218
Bugs Fixing
Initial Prod Release:
09 April 2011
8 Mars 2011
UAT
38%
62%45%55%
Processing Time: 59 days
Lead Time: 108 days
Waiting time: 49 days
Workload: 113 md
Rework: 43,5 md
▪ Ratio processing vs total lead time = 55% | % Rework: 38 %
• Important Rework
• Delay in Release Date
• Several Bugs fixing
• Risk to release after shorter UAT to compensate delay
 lower quality of the release / bugs in prod
• Important Change in Release Content
• Missing Test Cases at specification time
• Development prior to Freeze Content to anticipate heavy
workload
• Late Freeze Content

Contenu connexe

Tendances

Multimedia project life cycle - wsolvt
Multimedia project life cycle - wsolvtMultimedia project life cycle - wsolvt
Multimedia project life cycle - wsolvt
Wsolvt
 

Tendances (20)

Software Development Tips
Software Development TipsSoftware Development Tips
Software Development Tips
 
SDLC
SDLCSDLC
SDLC
 
Phases of the Software Development Process - Meerakics
Phases of the Software Development Process - MeerakicsPhases of the Software Development Process - Meerakics
Phases of the Software Development Process - Meerakics
 
Dev11
Dev11Dev11
Dev11
 
software project management Software development life cycle
software project  management Software development life cyclesoftware project  management Software development life cycle
software project management Software development life cycle
 
Agile software development process
Agile software development processAgile software development process
Agile software development process
 
Deciphering Product Management Lingo
Deciphering Product Management LingoDeciphering Product Management Lingo
Deciphering Product Management Lingo
 
What Is Software Development Lifecycle?
What Is Software Development Lifecycle?What Is Software Development Lifecycle?
What Is Software Development Lifecycle?
 
Waterfall Model Life Cycle
Waterfall Model Life CycleWaterfall Model Life Cycle
Waterfall Model Life Cycle
 
Example_ProjectPlan.docx
Example_ProjectPlan.docxExample_ProjectPlan.docx
Example_ProjectPlan.docx
 
Azure dev ops
Azure dev opsAzure dev ops
Azure dev ops
 
Rad model
Rad modelRad model
Rad model
 
Process and methodolgy followed @ Top Guru Assistants
Process and methodolgy followed @ Top Guru AssistantsProcess and methodolgy followed @ Top Guru Assistants
Process and methodolgy followed @ Top Guru Assistants
 
Better project deployment follow up’s
Better project deployment follow up’sBetter project deployment follow up’s
Better project deployment follow up’s
 
Sdlc plan
Sdlc planSdlc plan
Sdlc plan
 
V model presentation
V model presentationV model presentation
V model presentation
 
Agile methodology
Agile methodologyAgile methodology
Agile methodology
 
2. project initiation
2. project initiation2. project initiation
2. project initiation
 
Diagramming Product Management #1 - Requirements and Reality
Diagramming Product Management #1 - Requirements and Reality Diagramming Product Management #1 - Requirements and Reality
Diagramming Product Management #1 - Requirements and Reality
 
Multimedia project life cycle - wsolvt
Multimedia project life cycle - wsolvtMultimedia project life cycle - wsolvt
Multimedia project life cycle - wsolvt
 

En vedette

Firmware Improvement Roadmap
Firmware Improvement RoadmapFirmware Improvement Roadmap
Firmware Improvement Roadmap
Scott Sweeting
 
Securing the Digital Enterprise
Securing the Digital EnterpriseSecuring the Digital Enterprise
Securing the Digital Enterprise
Cybersecurity Education and Research Centre
 

En vedette (20)

Roadmap template
Roadmap templateRoadmap template
Roadmap template
 
How to Become a Thought Leader in Your Niche
How to Become a Thought Leader in Your NicheHow to Become a Thought Leader in Your Niche
How to Become a Thought Leader in Your Niche
 
The Impact of Switching to a Rapid Release Cycle on Integration Delay of Addr...
The Impact of Switching to a Rapid Release Cycle on Integration Delay of Addr...The Impact of Switching to a Rapid Release Cycle on Integration Delay of Addr...
The Impact of Switching to a Rapid Release Cycle on Integration Delay of Addr...
 
Avea Release Management IBM Innovate 2012
Avea Release Management IBM Innovate 2012Avea Release Management IBM Innovate 2012
Avea Release Management IBM Innovate 2012
 
Release Manager Data sheet
Release Manager Data sheetRelease Manager Data sheet
Release Manager Data sheet
 
Apereo OAE development and release process
Apereo OAE development and release processApereo OAE development and release process
Apereo OAE development and release process
 
Importance of connecting CRM with ERP
Importance of connecting CRM with ERPImportance of connecting CRM with ERP
Importance of connecting CRM with ERP
 
IT Service Management Concepts for Project Managers
IT Service Management Concepts for Project ManagersIT Service Management Concepts for Project Managers
IT Service Management Concepts for Project Managers
 
Service-Oriented Project Management (SOPM)
Service-Oriented Project Management (SOPM)Service-Oriented Project Management (SOPM)
Service-Oriented Project Management (SOPM)
 
Firmware Improvement Roadmap
Firmware Improvement RoadmapFirmware Improvement Roadmap
Firmware Improvement Roadmap
 
Roadmap For Improving Performance
Roadmap For Improving PerformanceRoadmap For Improving Performance
Roadmap For Improving Performance
 
Measuring The Service Provided By Project Management - Whitepaper
Measuring The Service Provided By Project Management - WhitepaperMeasuring The Service Provided By Project Management - Whitepaper
Measuring The Service Provided By Project Management - Whitepaper
 
Securing the Digital Enterprise
Securing the Digital EnterpriseSecuring the Digital Enterprise
Securing the Digital Enterprise
 
Pro's and Con's of Project Management as a Service
Pro's and Con's of Project Management as a ServicePro's and Con's of Project Management as a Service
Pro's and Con's of Project Management as a Service
 
BDD in Java using Cucumber
BDD in Java using CucumberBDD in Java using Cucumber
BDD in Java using Cucumber
 
Release Cycle Management Updates - Liberty Edition
Release Cycle Management Updates - Liberty EditionRelease Cycle Management Updates - Liberty Edition
Release Cycle Management Updates - Liberty Edition
 
How To Plan a Software Project
How To Plan a Software ProjectHow To Plan a Software Project
How To Plan a Software Project
 
Plm as a platform for smb companies
Plm as a platform for smb companiesPlm as a platform for smb companies
Plm as a platform for smb companies
 
Release process for a project
Release process for a projectRelease process for a project
Release process for a project
 
Professional Services Roadmap 2011 and beyond
Professional Services Roadmap 2011 and beyondProfessional Services Roadmap 2011 and beyond
Professional Services Roadmap 2011 and beyond
 

Similaire à IT Software - Release cycle & Delivery roadmap

Project management for qa manager
Project management for qa managerProject management for qa manager
Project management for qa manager
gaoliang641
 
SWT2_tim.pptx
SWT2_tim.pptxSWT2_tim.pptx
SWT2_tim.pptx
BnhT27
 
Lean Development Overview
Lean Development OverviewLean Development Overview
Lean Development Overview
dhawalm123
 

Similaire à IT Software - Release cycle & Delivery roadmap (20)

Visual management white board standard structures from waterfall to agile v3
Visual management   white board  standard structures from waterfall to agile v3Visual management   white board  standard structures from waterfall to agile v3
Visual management white board standard structures from waterfall to agile v3
 
Phases in Agile Development- 9.pptx
Phases in Agile Development- 9.pptxPhases in Agile Development- 9.pptx
Phases in Agile Development- 9.pptx
 
Project management for qa manager
Project management for qa managerProject management for qa manager
Project management for qa manager
 
SAFe and DevOps - better together
SAFe and DevOps - better togetherSAFe and DevOps - better together
SAFe and DevOps - better together
 
Applying both of waterfall and iterative development
Applying both of waterfall and iterative developmentApplying both of waterfall and iterative development
Applying both of waterfall and iterative development
 
Test Planning and Test Estimation Techniques
Test Planning and Test Estimation TechniquesTest Planning and Test Estimation Techniques
Test Planning and Test Estimation Techniques
 
Agile software development
Agile software developmentAgile software development
Agile software development
 
Key items for a digital enterprise
Key items for a digital enterpriseKey items for a digital enterprise
Key items for a digital enterprise
 
Scrum Process Overview
Scrum Process OverviewScrum Process Overview
Scrum Process Overview
 
SWT2_tim.pptx
SWT2_tim.pptxSWT2_tim.pptx
SWT2_tim.pptx
 
Agile methodology and Scrum Framewwork
Agile methodology and Scrum FramewworkAgile methodology and Scrum Framewwork
Agile methodology and Scrum Framewwork
 
Application Lifecycle Management with Visual Studio 2013
Application Lifecycle Management  with Visual Studio 2013Application Lifecycle Management  with Visual Studio 2013
Application Lifecycle Management with Visual Studio 2013
 
Methodology: IT test
Methodology: IT testMethodology: IT test
Methodology: IT test
 
Agile Model & Methodology
Agile Model & MethodologyAgile Model & Methodology
Agile Model & Methodology
 
The Dashlane Agile Journey
The Dashlane Agile JourneyThe Dashlane Agile Journey
The Dashlane Agile Journey
 
To successfully deliver your IT project: build your team, build your Agile it...
To successfully deliver your IT project: build your team, build your Agile it...To successfully deliver your IT project: build your team, build your Agile it...
To successfully deliver your IT project: build your team, build your Agile it...
 
Agile Methodology - Software Engineering
Agile Methodology - Software EngineeringAgile Methodology - Software Engineering
Agile Methodology - Software Engineering
 
Lean Development Overview
Lean Development OverviewLean Development Overview
Lean Development Overview
 
Scaled agile implementation
Scaled agile implementationScaled agile implementation
Scaled agile implementation
 
Agile for product owners v12
Agile for product owners  v12Agile for product owners  v12
Agile for product owners v12
 

Plus de Jean-François Nguyen

Plus de Jean-François Nguyen (20)

Methodology: to build your product build your team your agile iteration your ...
Methodology: to build your product build your team your agile iteration your ...Methodology: to build your product build your team your agile iteration your ...
Methodology: to build your product build your team your agile iteration your ...
 
Methodology: agile@scale what is a 'PI Zero'
Methodology: agile@scale what is a 'PI Zero'Methodology: agile@scale what is a 'PI Zero'
Methodology: agile@scale what is a 'PI Zero'
 
Management 3 0: tip to guide manager to delegate and coach
Management 3 0: tip to guide manager to delegate and coachManagement 3 0: tip to guide manager to delegate and coach
Management 3 0: tip to guide manager to delegate and coach
 
Methodology: feature epic and user story
Methodology:  feature epic and user storyMethodology:  feature epic and user story
Methodology: feature epic and user story
 
Methodology - Agile@Scale
Methodology - Agile@ScaleMethodology - Agile@Scale
Methodology - Agile@Scale
 
Rex Sprint 0 - how build the data model with 2 BA and 3 IT architects
Rex Sprint 0 - how build the data model with 2 BA and 3 IT architectsRex Sprint 0 - how build the data model with 2 BA and 3 IT architects
Rex Sprint 0 - how build the data model with 2 BA and 3 IT architects
 
Rex - How User Stories can help you manage standard components of an IT project
Rex - How User Stories can help you manage standard components of an IT projectRex - How User Stories can help you manage standard components of an IT project
Rex - How User Stories can help you manage standard components of an IT project
 
Methodology - Design Sprint
Methodology - Design SprintMethodology - Design Sprint
Methodology - Design Sprint
 
Methodology - design thinking
Methodology - design thinkingMethodology - design thinking
Methodology - design thinking
 
Scrum product owner: how build a project charter & frame the project?
Scrum product owner: how build a project charter & frame the project?Scrum product owner: how build a project charter & frame the project?
Scrum product owner: how build a project charter & frame the project?
 
Develop a good product - 3 phases 3 methodologies - detail
Develop a good product - 3 phases 3 methodologies - detailDevelop a good product - 3 phases 3 methodologies - detail
Develop a good product - 3 phases 3 methodologies - detail
 
How develop a GOOD product: 3 phases, 3 methodologies
How develop a GOOD product: 3 phases, 3 methodologiesHow develop a GOOD product: 3 phases, 3 methodologies
How develop a GOOD product: 3 phases, 3 methodologies
 
Methodology: Agile introduction for deciders
Methodology: Agile introduction for decidersMethodology: Agile introduction for deciders
Methodology: Agile introduction for deciders
 
Tool digital meeting room solutions for efficient cross border meeting v1....
Tool   digital meeting room  solutions for efficient cross border meeting v1....Tool   digital meeting room  solutions for efficient cross border meeting v1....
Tool digital meeting room solutions for efficient cross border meeting v1....
 
Case: apply Agile principles to front office credit analyst activity
Case: apply Agile principles to front office credit analyst activityCase: apply Agile principles to front office credit analyst activity
Case: apply Agile principles to front office credit analyst activity
 
Methodology dimension voice of customer
Methodology   dimension voice of customerMethodology   dimension voice of customer
Methodology dimension voice of customer
 
Methodology lean IT transformation mission
Methodology   lean IT transformation missionMethodology   lean IT transformation mission
Methodology lean IT transformation mission
 
Case: build an IT pool
Case: build an IT poolCase: build an IT pool
Case: build an IT pool
 
Methodology scrum white board simulation
Methodology   scrum white board simulationMethodology   scrum white board simulation
Methodology scrum white board simulation
 
Methodology kanban
Methodology   kanbanMethodology   kanban
Methodology kanban
 

Dernier

Artificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsArtificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and Myths
Joaquim Jorge
 
Histor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slideHistor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slide
vu2urc
 

Dernier (20)

Artificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsArtificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and Myths
 
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 
Tech Trends Report 2024 Future Today Institute.pdf
Tech Trends Report 2024 Future Today Institute.pdfTech Trends Report 2024 Future Today Institute.pdf
Tech Trends Report 2024 Future Today Institute.pdf
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day Presentation
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organization
 
Histor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slideHistor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slide
 
Understanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdfUnderstanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdf
 
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
 
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, AdobeApidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
 
AWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of TerraformAWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of Terraform
 
Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)
 
Strategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherStrategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a Fresher
 
Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024
 
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
 
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
 
TrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
TrustArc Webinar - Unlock the Power of AI-Driven Data DiscoveryTrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
TrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
 
Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...
 
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot TakeoffStrategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
 

IT Software - Release cycle & Delivery roadmap

  • 1. Release cycle (development process) & Delivery roadmap the Goal: • Design a well balanced Release Cycle in regard of your constraints • Define your catalog of release cycles (one per User Story family) and your SLA
  • 2. Release cycle (development process)& delivery roadmap the key points: the development process, the different type of Test Key Basics: • A release cycle is a development macro process • it’s build around the major steps: Business Requirement/Spec/Dev/Test/Prod setup • Some steps are ‘Value Added’ for the End User, others are not • The goal is • to continuously reduce your constraints to an acceptable level (e.g. reduce your non regression phase from 1 week to 1 day, …) • to balance the steps to have an acceptable global ROI • The base is your average ratio Spec/Dev/Test (in workload, in lead-time) • This ratio is defined by family of User Story you find in your Backlog • Each new request should match a family, follow its associated process Case Study: We propose to simulate a simplified case study where we’ll mix • 3 different families of User Stories defined around the criteria of urgency & complexity • Different levers of improvement: eliminate, improve, reorganise Hypothesis regarding the Test: • to simplify the exercise, we take only regression & UAT. Others (Unitary, Functional, Integration,…) are not taken into account here but should be in the real world • we also suppose Functional tests are done just after the dev and not only in UAT (too late) the Goal: • Design a well balanced Release Cycle in regard of your constraints • Define your catalog of release cycles (one per User Story family) and your SLA
  • 3. Release cycle (development process)& delivery roadmap the key points: Value added for the client/End User Key Understandings: • Qualify the 3 steps (Spec/Dev/Test) in ‘Value Added’/’Non Value Added’ for the End User Hypothesis simplified for the case study: • Let’s say your backlog is composed by 3 families: standard urgent, standard non urgent and complex the Goal: • Understand the dev process step in terms of ‘Value Added’, ‘Non Value Added’ for the User Spec Dev Test VA VA Non VA Average workload Average Leadtime Spec Dev Reg UAT Standard urgent 25% 2.5MD 50% 5MD 10% 1MD 15% 1.5MD 2 weeks Standard non urgent 25% 2.5MD 50% 5MD 10% 1MD 15% 1.5MD 4 weeks Complex 25% 10MD 25% 10MD 25% 10 MD 25% 10MD 8 weeks
  • 4. Release cycle (development process)& delivery roadmap the key points: workload, leadtime, ratio ROI Key understanding • Current situation: the 3 release cycles are totally sequential • Assess the quality of each release cycle in terms of workload & leadtime • (1): ratio just balanced 1MD of VA for 1MD of NVA. Instead for standard 3MD for 1MD • (2): any steps can be done in parallel? the Goal: • Assess the current Release Cycles in terms of ROI regarding the workload, the leadtime • For the leadtime, it’s key to get the Voice Of the Customer Average workload Assessment Average Leadtime Assessment Spec (VA) Dev (VA) Reg (NVA) UAT (NVA) VA/NVA Standard urgent 25% 2.5MD 50% 5MD 10% 1MD 15% 1.5MD OK 7.5/2.5 2 weeks KO (2) Standard non urgent 25% 2.5MD 50% 5MD 10% 1MD 15% 1.5MD OK 7.5/2.5 4 weeks KO (2) Complex 25% 10MD 25% 10MD 25% 10 MD 25% 10 MD KO (1) 1/1 8 weeks KO (2)
  • 5. Release cycle (development process)& delivery roadmap the key points: User Story family the Goal: • Assess the current Release Cycles in terms of ROI regarding the workload, the leadtime  Current situation  Key understanding: what can be improved? 2 weeks 4 weeks 8 weeks
  • 6. Release cycle (development process)& delivery roadmap key point: pull the Flow, paralellisation the Goal: • To reduce your leadtime, you can reduce steps, do some steps in parallel • Let’s try first to parallelize dev and spec when you can  Lever: parallelisation (pull the flow)  Key understanding: start the dev as soon as the spec is ready (don’t wait artificially). Do it for any step. < 2 weeks < 4 weeks < 8 weeks
  • 7. Release cycle (development process)& delivery roadmap key point: continuous integration, code factory (code for the code), Test Driven Development the Goal: • Let’s try now to parallelize regression and dev • you need to reduce the effort & time doing build & regression. Can you automate?  Lever: Continuous integration (Test Driven)  Key understanding: • Continuous Integration is regular build & regression test all along the dev process. The coder code to automate the build & regression test (code factory). • Discover problem early in the process cost less (less root cause analysis, less effort to solve) < 2 weeks 3 weeks 6 weeks
  • 8. Release cycle (development process)& delivery roadmap key point: continuous improvement, Test methodology, Over Quality when not required the Goal: • Improve your most heavy steps with No Value Added (e.g. UAT for complex User Story) • Test methodology is question of taking a Risk: Which tests are required, which are not?  Lever: Continuous Improvement on UAT for complex User Stories  Key understanding: in the continuous improvement activity, optimise the UAT process. Some ideas: Test expert can bring you best practices to optimise your strategy, the data used, etc … < 2 weeks 3 weeks 5 weeks
  • 9. Release cycle (development process)& delivery roadmap key point: continuous improvement, dynamic Team capacity management, Visual management the Goal: • build your delivery roadmap using your catalog of release cycles • Define the best strategy (regular deliveries variable content, fix content ad-hoc deliveries, …)  Best case: your flow of User Story is quite homogeneous, predictable & activities quite independent. You’re able to build & present to your client a stable delivery roadmap for the next months. Regular deliveries with variable content is more ‘Agile’ & ensure process stability. Easier to define & apply a SLA. Your team capacity management is capacity planning. Example: 4 team members working on 3 applications  Key understanding: your reality is particular. Based on best practices/methodology, build your own model.  Worst case: your flow of User Story is heterogeneous, unpredictable & activities dependant. You can’t build a stable delivery roadmap in advance. You build dynamically & regularly depending of your new User request. Your team capacity management is also highly dynamic and is eased by visual management. Think about what is best for you regarding your constraints: ad-hoc/regular deliveries, fix/variable release content
  • 10. Release cycle (development process)& delivery roadmap key point: daily & weekly meeting should be complementary not redundant the Goal: • How to use a release cycle? • Check your team capacity, build your weekly meeting agenda, ….  Build your release cycle per activity/project  Key understanding: Check your team capacity: • Team members are not developing at the same time on Appli2 and Appli3 • Book time for your team to do continuous improvement Read on the roadmap the weekly team meeting agenda • Depending on where the team is on the release cycle, the agenda can cover subjects like post mortem, performance monitoring, Best Practice sharing, … • If not adapted to your context, weekly might be fortnightly or monthly 2 1 4 3
  • 11. Release cycle (development process)& delivery roadmap the key points: Project management, methodologies, technical tools … should do a ONE consistent the Goal: • List of key topics to assess to improve your release cycle & delivery roadmap • Assess your team, your development process, your code management, your test, … Code factory • Create transversal/product team (Spotify) • Review the development process from the request initiation to production • onshore-offshore & RA(CI) • Review roles: • Team lead, Tech Lead, Scrum master & Product Owner • others on offshore side Review project & team management with Agile & Scrum key concepts (events & roles) • work with MVP (Minimum Viable Product) • build your final product incrementally through short iterations (PDCA cycle) • adjust the meeting cascade (hoshin-kanri) to be aligned with TOP management vision • Implement an electronic dashboard for splitted team to visualize & ease the communication Review development factory with Lean key concepts • easily control your code: code management & coder community (GitHub) • easily deploy technical environment (PaaS/IaaS) • easily deploy the code: automated package building & deployment (DevOps) • prove your code is working (Google): • test methodology & strategy • continuous integration (build & automated test) • improve continuously your Code & Factory: architecture & refactoring (SaaS) 1. Build the team: do you empower people? 2. Build the Agile iteration: do you try & adapt in short iteration? 3. Build the Code Factory: do you ensure code quality & fluidity in the process?
  • 12. Appendix the key points: all tools available in the Lean tool kit A few examples of analyses you can do to improve your process: To help your team understand where is inefficiency 1. Workflow mapping combined with RA(CI) 2. Post Mortem to compare your worst project and a successful one 3. And many others in the Lean tool kit …
  • 13. Appendix 1 the key points: team work, all tools available in the Lean tool kit Workflow mapping combined with RA(CI): • Be careful not to mix several families Waste of time D0 leadtime processing time 1 02 03 0 3 0 2 15 1 3 0 2 0 1 12 15 3 in % in days processing time vs leadtime step 11 1 step 10 0 step 9 2 step 8 3 step 7 50 step 6 10 step 5 3 step 4 5 step 3 50 step 2 25 step 1 60 D29D10 D20 ~ 33 % ~ 33 % ~33 % 80 20 waiting time processing • Too many stakeholders • 1 request is dependent on 2 decisions levels • Lack of coordination to avoid waiting time • Waiting time (~80%) vs Processing (~20%) • Steps 6, 9 with stakeholder X, 5, 8 (CC), 1 may be the first to focus on but feasibility requires to be checked  Team X – workflow mapping – process Y
  • 14. Appendix 1 the key points: team work, workload, leatime, waiting time Workflow mapping combined with RA(CI): • Be careful not to mix several families • Step C: one person is doing, 4 other people are validating. This split generates 70% of waiting time (14 working days) • Step D: meeting, writing minutes and make all sign generates 97% of waiting time (7 working days) • Questions: • Is the split required? • If the split is required, is it possible to reduce the waiting time? process step 0 1 2 3 4 role Step A Step B Step C Step D Step E Stakeholder 1 RA Stakeholder 2 RA A RA Stakeholder 3 R R RA Stakeholder 4 A R Stakeholder 5 A RA Stakeholder 6 A RA Processing time (in days) 5.7 0.155 0.005 leadtime (in days) 20 8 1 waiting time (in days) 14.3 7.845 0.995 1 2 Lean Best Practice • To avoid waiting time, R and A should be in the same box to avoid potential waiting time • To better visualise the problem, don’t put the C & I of the RACI Legend: R: Responsible. The person who is doing the action A: Accountable. The person who is accountable for the action 1 2  Team X – workflow mapping – process Y
  • 15. Appendix 2 the key points: team work, workload, leadtime, waiting time Post Mortem to compare your worst project and a successful one • Be careful not to mix several families  Team X – workflow mapping – process Y Production Release Delay due to technical operation 25 Feb 2011 Specs & Estimates Dev Prep UAT 17 Jan 2011 6 Amendment Release Estimate 0,1 Project Start with Release Content: 05 Jan 2011 0,1 2 6 0,2 2 71,4 1 Change Content Release: 03 Feb 2011 Freeze Content 07 Feb 2011 3 2 17,3 4 1 6 0,5 6,5 3 2 1,5 1,5 15 23 April 2011 9,7 27 5,218 Bugs Fixing Initial Prod Release: 09 April 2011 8 Mars 2011 UAT 38% 62%45%55% Processing Time: 59 days Lead Time: 108 days Waiting time: 49 days Workload: 113 md Rework: 43,5 md ▪ Ratio processing vs total lead time = 55% | % Rework: 38 % • Important Rework • Delay in Release Date • Several Bugs fixing • Risk to release after shorter UAT to compensate delay  lower quality of the release / bugs in prod • Important Change in Release Content • Missing Test Cases at specification time • Development prior to Freeze Content to anticipate heavy workload • Late Freeze Content