SlideShare une entreprise Scribd logo
1  sur  14
IMPORTANT CONSIDERATIONS BEFORE STARTING ALIGNMENT
 MAKE SURE THAT RUNOUT AT THE SHAFT AS WELL AS COUPLING IS LESS THAN 0.05 mm ON
BOTH THE MACHINES . SEE FIGURE
RUNOUT SHOULD NOT EXCEED 0.05 MM
 DECIDE WHICH MACHINE WILL BE KEPT STATIOARY AND WHICH ONE WILL BE MOVED .
GENERALLY, FOR A MOTOR PUMP COMBINATION , PUMP IS KEPT STATIOARY ,FOR A TURBINE
PUMP COMBINATION , TURBINE IS KEPT STATIONARY.
 CHECK FOR RUSTY OR BROKEN SHIMS/TOO MANY SHIMS UNDER THE SUPPORT LEGS .NUMBER
OF SHIMS SHOULD NOT EXCEED FOUR.
 MAKE PROVISION FOR MOVING THE MACHINERY ( BOTH SIDEWISE AND UPDOWN MOTION ) FOR
SIDEWISE MOTION , USING JACK BOLTS IS THE PREFERRED METHOD. FOR UP-DOWN MOTION ,
WEDGING AT THE APPROPRIATE PLACE IS DONE AND THEN SHIMS ARE KEPT BELOW THE LEGS.
ALIGNMENT TOLERANCES
ALIGNMENT PROCEDURE (TAKING ALIGNMENT READINGS) – STEP NO. : 1
 DIAL POINTER SHOULD PREFRABLY BE KEPT ON THE MACINE TO BE MOVED.
 THE SUM TOTAL OF BOTH SIDE READINGS SHOULD BE SAME AS SUM TOTAL OF TOP BOTTOM
READINGS. IN ACTUAL PRACTICE ,WE CAN ALLOW A DIFFERENCE OF ABOUT 15%. THIS RULE IS
CALLED VALIDITY RULE.
SUM TOTAL OF SIDE READINGS = 0.15 + 0.25 = 0.40
SUM TOTAL OF TOP BOTTOM READINGS = 0.00 + 0.36 = 0.36
DIFFERENCE = 0.40 – 0.36 = 0.04
THIS DIFFERENCE SHOULD BE LESS THAN 15 %
15 % OF 0.40 = 0.06
THUS DIFFERENCE IS LESS THAN 15 %. HENCE ALIGNMENT READING IS VALID.
IMPORTANT :
ALIGNMENT CORRECTION SHOULD BE ATTEMPTED ONLY WHEN
SUM TOTAL OF SIDE READINGS AND TOP BOTTOM READINGS ARE
MATCHING WITHIN 15 % AS SHOWN IN THE ABOVE EXAMPLE.
0.00
0.36
0.15 0.25
RFOR
EXAMPLE
D
L1
L2
WHAT CHECKS TO DO IF ALIGNMENT READINGS ARE FOUND INVALID :
 CHECK THE CLAMP FOR LOOSENESS. IF FOUND LOOSE, TIGHTEN.
 CHECK THE DIAL POINTER IS LEAVING CONTACT DURING ROTATION. IF SO, DO ROUGH
ALIGNMENT WITH STRAIGHT EDGE FIRST.
 CHECK THE COUPLING FOR ECCENTRICITY / ELLIPTICITY AND SHAFT FOR RUNOUT. RECTIFY,
AND ROTATE BOTH SHAFTS TOGETHER.
IF STILL ALIGNMENT READINGS ARE FOUND INVALID, IT MEANS THAT THERE IS SAG IN THE DIAL
CLAMP.
12 O’CLOCK
6 O’CLOCK
ALIGNMENT PROCEDURE – STEP NO. : 1
SAG MEASUREMENT AND CORRECTION
IMPORTANT :
THIS STEP IS TO BE CARRIED OUT ONLY IF THE SUM TOTAL OF SIDE READINGS
IS NOT MATCHING WITH THE SUM TOTAL OF TOP-BOTTOM READINGS.
 WHAT IS SAG ? SEE FIGURE
 WHEN DIAL IS AT 12 O’CLOCK POSITION, THE CLAMP BENDS TOWARDS THE COUPLING.
 WHEN THE DIAL IS AT 6 O’CLOCK POSITION THE CLAMP BENDS AWAY FROM THE COUPLING.
 THIS MOVEMENT OF CLAMP CAUSES CHANGE IN DIAL READINGS. DUE TO THIS CHANGE, SUM
TOTAL OF TOP-BOTTOM READINGS DOES NOT MATCH WITH SUM TOTAL OF SIDE READINGS.
THIS EFFECT IS CALLED SAG.
0.00
+ 0.16
+ 0.12 + 0.12
FOR EXAMPLE ALIGNMENT READING IS
0.00
- 0.08
+ 0.08
+ 0.16
+ 0.12 + 0.12
ALIGNMENT PROCEDURE – STEP NO. : 2
 HOW TO REMOVE SAG ERROR
FROM THE ALIGNMENT READINGS :
 MEASURE THE VALUE OF
SAG WITH THE HELP OF
SAG MEASUREMENT
SETUP AS SHOWN IN FIGURE.
THIS SAG VALUE WILL BE NEGATIVE.
 ADD THE SAG VALUE TO THE ALIGNMENT READINGS
AS SHOWN IN THE FOLLOWING EXAMPLE.
 AS WE CAN SEE,SUM TOTAL OF TOP-BOTTOM READINGS
& SIDE READINGS IS NOT MATCHING. ALL THREE CHECKS,
GIVEN IN STEP NO.:1 HAVE BEEN DONE. STILL DIFFERENCE IS COMING
DIAL READINGS FROM THE SAG MEASUREMENT SETUP ARE AS FOLLOWS.
IT MEANS THERE IS SAG OF 0.08 MM.
 THIS SAG VALUE WILL BE ADDED TO THE ALIGNMENT
READING OF 12 O’CLOCK POSITION AFTER CHANGING
THE SIGN FROM MINUS TO PLUS. MODIFIED READING
IS AS FOLLOWS :
 NOW, SUM TOTAL OF SIDE READINGS AND TOP BOTTOM READINGS
IS MATCHING. NOW, WE CAN PROCEED TO STEP NO. : 3 OF ALIGNMENT PROCEDURE.
ALIGNMENT PROCEDURE – STEP NO. : 3
CALCULATING MACHINERY MOVEMENT
IMPORTANT :
FOR BEST RESULTS ,RADIAL AND AXIAL ALIGNMENT CORRECTIONS SHOULD
BE DONE TOGETHER. A TABLE FOR THIS PURPOSE IS SHOWN AS FOLLOWS :
AMOUNT OF SHIMS REQUIRED AT
FRONT LEG REAR LEG
FOR RADIAL ALIGNMENT A mm A mm
FOR AXIAL ALIGNMENT B mm C mm
FOR TOTAL ALIGNMENT CORRECTION A + B mm A + C mm
ALIGNMENT PROCEDURE – STEP NO. : 3A
CORRECTING RADIAL MISALIGNMENT
RADIAL CORRECTION VALUE IS HALF OF THE TOTAL INDICATOR READING.
FOR EXAMPLE :
 DIAL IS CLAMPED ON PUMP COUPLING AND POINTER IS ON MOTOR COUPLING.
 DIAL IS SET TO ZERO AT 12 O’CLOCK POSITION.
 DIAL IS READING +0.20 mm AT 6 O’CLOCK POSITION.
 THIS MEANS THAT MOTOR SHAFT IS DOWN ( + SIGN MEANS DIAL POINTER HAS GOT
COMPRESSED.)
 THUS MOTOR SHAFT WILL HAVE TO BE LIFTED UP BY +0.20/2 = 0.10 mm . THAT IS, SHIMMING OF
0.10 mm IS REQUIRED AT ALL THE FOUR LEGS.
IMPORTANT :
FOR RADIAL MISALIGNMENT CORRECTION , THE VALUE OF SHIMMING
REQUIRED WILL BE SAME FOR ALL THE FOUR LEGS, AS WE SAW IN
THE ABOVE EXAMPLE.
0.00
+ 0.20
ALIGNMENT PROCEDURE – STEP NO. : 3B
CORRECTING AXIAL MISALIGNMENT
SEE FIGURE :
 D = DIAMETER ON WHICH THE DIAL IS MOVING. ( APPROX. EQUAL TOCOUPLIND DIAMETER).
 L1 = DIAMETER AT FRONT LEG FROM MOTOR COUPLING.
 L2 = DISTANCE AT BACK LEG FROM THE MOTOR COUPLING.
SHIMING REQUIRED AT FRONT / BACK LEG = L1 OR L2 x DIAL READING / D
EXAMPLE :
 DIAMETER OF DIAL TRAVEL D = 100 mm
 DISTANCE OF FRONT LEG TO COUPLING L1 = 200 mm
 DISTANCE OF BACK LEG TO COUPLING L2 = 400 mm
NOW, DIAL IS SET TO ZERO AT 12 O’CLOCK POSITION. DIAL READS + 0.30 AT 6 O’CLOCK
POSITION
THIS MEANS THAT TOP GAP BETWEEN COUPLINGS IS MORE THAN BOTTOM GAP (+ SIGN MEANS
DIAL POINTER HAS GOT COMPRESSED)
0.00
+ 0.30
D
L1
ALIGNMENT PROCEDURE – STEP NO. : 3B
CORRECTING AXIAL MISALIGNMENT
SEE FIGURE :
 THUS MOTOR SHAFT WILL HAVE TO BE LIFTED UP.
 SHIMING REQUIRED AT FRONT LEG = L1 x DIAL READING / D
= 200 x 0.30 / 100 = 0.60 mm
 SHIMING REQUIRED AT BACK LEG = L2 x DIAL READING / D
= 400 x 0.30 / 100 = 1.20 mm
IMPORTANT :
FOR AXIAL MISALIGNMENT CORRECTION , THE AMOUNT OF SHIMS
REQUIRED TO BE ADDED OR REMOVED IS DIFFERENT FOR THE FRONT LEGS
AND BACK LEGS.
ALIGNMENT PROCEDURE – STEP NO. : 3C
CORRECTING TOTAL MISALIGNMENT
AS PER OUR EXAMPLE, THE TOP BOTTOM READINGS ARE :
SHIMING REQUIRED FOR RADIAL & AXIAL MISALIGNMENTS RESPECTIVELY HAVE BEEN CALCULATED
ON THE PREVIOUS SLIDES. THE TOTAL SHIMING REQUIRED IS CALCULATED AS FOLLOWS :
THUS, IN ORDER TO DO TOTAL (RADIAL + AXIAL ) ALIGNMENT, PUT SHIMS OF 0.70 mm IN FRONT LEG
AND 1.3 mm IN BACK LEG OF MOTOR IN OUR EXAMPLE.
0.00
0.20 mm
R
0.00
0.30 mm
A
AMOUNT OF SHIMS REQUIRED IN
FRONT LEG REAR LEG
TO CORRECT RADIAL ALIGNMENT + 0.10 mm + 0.10 mm
TO CORRECT AXIAL ALIGNMENT + 0.60 mm + 1.20 mm
TOTAL ALIGNMENT CORRECTION 0.10 + 0.60 = 0.70 mm 0.10 + 1.20 = 1.3 mm
ALIGNMENT PROCEDURE – STEP NO. : 4
MOVING THE MACHINERY
 FOR TOP-BOTTOM MOVEMENT SHIMS ARE ADDED OR REMOVED FROM BELOW THE FEET OF THE
MACHINE TO BE MOVED. FOR THIS PURPOSE, THE MACHINE IS LIFTED UP BY WEDGING, AND
THEN SHIMS ARE ADDED OR REMOVED.
 FOR SIDE WISE MOVEMENT, USING JACKBOLTS IS THE PREFERRED METHOD. A LIGHT HAMMER
CAN ALSO BE USED ON SMALL MACHINES. THE MOVEMENT SHOULD BE CLOSELY MONIORED
BY TWO DIAL GAUGES, AS SHOWN IN THE FIGURE.
IMPORTANT :
AFTER MAKING THE REQUIRED MOVEMENT, ONE FINAL ALIGNMENT READING
SHOULD BE TAKEN.
CONCLUSION
WHICH ALIGNMENT TO DO FIRST : TOP-BOTTOM OR SIDE WISE ALIGNMENT
 WE HAVE TO SEE THAT IT IS VERY CONVENIENT TO DO RADIAL AND AXIAL ALIGNMENT
CORRECTION TOGATHER.
 HENCE, WE CAN SAY THAT ULTIMATELY THERE ARE ONLY TWO TYPES OF MISALIGNMENTS –
TOP-BOTTOM (RADIAL + AXIAL) MISALIGNMENT AND SIDE WISE (RADIAL + AXIAL) MISALIGNMENT.
 FOR BEST RESULTS TOP-BOTTOM ALIGNMENT SHOULD BE DONE FIRST, FOLLOWED BY SIDE
WISE ALIGNMENT. THE REASON IS THAT IF YOU DO SIDE WISE ALIGNMENT FIRST, THEN WHILE
DOING TOP-BOTTOM ALIGNMENT, SIDE WISE ALIGNMENT WILL AGAIN GET DISTURBED.
 HOW EVER, IF DURING STEP NO. : 1 (TAKING ALIGNMENT READINGS) IT IS FOUND THAT SIDE
WISE MISALIGNMENT IS VERY LARGE AS COMPARE TO TOP-BOTTOM MISALGNMENT, THEN
ROUGH ALIGNMENT (OF SIDE WISE) SHOULD BE DONE FIRST. AFTER THAT FINAL TOP-BOTTOM
ALIGNMENT AND THEN FINAL SIDE WISE ALIGNMENT SHOULD BE DONE.
5.REMOVE COUPLING GAURDS AND COUPLING SPOOL PIECE IF NECESSARY.MEASURE
THE SHAFT AND COUPLING HUB RUN OUT ON BOTH UNITS. INSPECT COUPLING FOR
ANY DAMAGE OR WORN PARTS. KEEP TRACK OF THE COUPLIG PARTS AND LABEL
THEM IF NECESSARY.IF EQUIPMENT IS GOING TO BE REMOVED FOR SERVICING,
MAKE PUNCH MARKS ON CASING AND BASEPLATE AS A REFERENCE DURING
REINSTALLATION.
6.CHECK FOR SOFT FOOT,CASING OR FRAME WARPAGE, EXCESSIVE STATIC PIPING OR
CONDUIT FORCES,DAMAGED OR RUSTY SHIMS, LOOSE FOUNDATION BOLTS. ETC.
CORRECT ANY OF THE POTENTIAL PROBLEM AREAS.
7. TAKE AND RECORD A SET OF ALIGNMENT READINGS.
8.CALCULATE AND PERFORM THE NECESSARY AXIAL , VERTICAL AND HORIZONTALS
MOVE. RECHECK ALIGNMET, CALCULATE AND MOVE UNTILL EQUIPMENT IS WITHIN
ACCEPTABLE ALIGNMENT TOLERANCES.TORQUE FOUNDATION BOLTS TO REQURED
VALUES. RCORD FINAL ALIGNMENT READINGS.

Contenu connexe

Tendances

Tendances (20)

Prealignment
PrealignmentPrealignment
Prealignment
 
Bearings and lubrications
Bearings and lubricationsBearings and lubrications
Bearings and lubrications
 
Bearing Description about basic, types, failure causes
Bearing Description about basic, types, failure causesBearing Description about basic, types, failure causes
Bearing Description about basic, types, failure causes
 
Steam Turbine Alignment
Steam Turbine AlignmentSteam Turbine Alignment
Steam Turbine Alignment
 
Soft foot
Soft footSoft foot
Soft foot
 
Bearing
Bearing Bearing
Bearing
 
Bearing and Lubrication
Bearing and LubricationBearing and Lubrication
Bearing and Lubrication
 
Bearing DESIGN
Bearing DESIGNBearing DESIGN
Bearing DESIGN
 
Bearings PPT
Bearings PPTBearings PPT
Bearings PPT
 
Bearing
BearingBearing
Bearing
 
Shaft alignment
Shaft alignmentShaft alignment
Shaft alignment
 
Fundamental and selection of bearings
Fundamental and selection of bearingsFundamental and selection of bearings
Fundamental and selection of bearings
 
Bearings
BearingsBearings
Bearings
 
Bearing failure and its Causes and Countermeasures
Bearing failure and its Causes and CountermeasuresBearing failure and its Causes and Countermeasures
Bearing failure and its Causes and Countermeasures
 
1.2 bearing life
1.2 bearing life1.2 bearing life
1.2 bearing life
 
Acutal Cycles and Their Analysis - Unit-I
Acutal Cycles and Their Analysis - Unit-IAcutal Cycles and Their Analysis - Unit-I
Acutal Cycles and Their Analysis - Unit-I
 
Misalignment
Misalignment Misalignment
Misalignment
 
Alignment
AlignmentAlignment
Alignment
 
Pumps_alignment_1684283213.pdf
Pumps_alignment_1684283213.pdfPumps_alignment_1684283213.pdf
Pumps_alignment_1684283213.pdf
 
Circulating Water Pump Overhauling Report (Capacity- 29,000 m3/hr)
Circulating Water Pump Overhauling Report (Capacity- 29,000 m3/hr)Circulating Water Pump Overhauling Report (Capacity- 29,000 m3/hr)
Circulating Water Pump Overhauling Report (Capacity- 29,000 m3/hr)
 

En vedette

Shaft Alignment Trainer [SAT] presentation
Shaft Alignment Trainer [SAT] presentationShaft Alignment Trainer [SAT] presentation
Shaft Alignment Trainer [SAT] presentationSpectra Quest Inc
 
Shaft alignment
Shaft alignmentShaft alignment
Shaft alignmentprasa1897
 
Transcat and Fluke Present: Precision Shaft Alignment Made Easy
Transcat and Fluke Present: Precision Shaft Alignment Made EasyTranscat and Fluke Present: Precision Shaft Alignment Made Easy
Transcat and Fluke Present: Precision Shaft Alignment Made EasyTranscat
 
Shaft alignment
Shaft alignmentShaft alignment
Shaft alignmentprasa1897
 
Alignment Systems July 2009 En
Alignment Systems July 2009 EnAlignment Systems July 2009 En
Alignment Systems July 2009 Enrobert_mr
 
Maintenance of Pumps
Maintenance of PumpsMaintenance of Pumps
Maintenance of PumpsHammad Akber
 
Welding qualification a
Welding qualification aWelding qualification a
Welding qualification aJithu John
 
An engineers guide 2012 making maintenance matter, pruftechnik
An engineers guide 2012 making maintenance matter, pruftechnikAn engineers guide 2012 making maintenance matter, pruftechnik
An engineers guide 2012 making maintenance matter, pruftechnikAkın Azmak
 
Improving Rotating Equipment Reliability and Machinery Health
Improving Rotating Equipment Reliability and Machinery HealthImproving Rotating Equipment Reliability and Machinery Health
Improving Rotating Equipment Reliability and Machinery HealthMexxusts
 
Maintainence OF STEAM TURBINE
Maintainence OF STEAM TURBINEMaintainence OF STEAM TURBINE
Maintainence OF STEAM TURBINESAI SHARATH GAMPA
 
Mechanical drives & power transmission
Mechanical drives & power transmissionMechanical drives & power transmission
Mechanical drives & power transmissionJames Shearer
 
Estimation of misalignment in bearing shaft by signal processing of acoustic ...
Estimation of misalignment in bearing shaft by signal processing of acoustic ...Estimation of misalignment in bearing shaft by signal processing of acoustic ...
Estimation of misalignment in bearing shaft by signal processing of acoustic ...IAEME Publication
 

En vedette (18)

Shaft Alignment Trainer [SAT] presentation
Shaft Alignment Trainer [SAT] presentationShaft Alignment Trainer [SAT] presentation
Shaft Alignment Trainer [SAT] presentation
 
Shaft alignment
Shaft alignmentShaft alignment
Shaft alignment
 
Ludeca a practical-guide-to-shaft-alignment
Ludeca a practical-guide-to-shaft-alignmentLudeca a practical-guide-to-shaft-alignment
Ludeca a practical-guide-to-shaft-alignment
 
Transcat and Fluke Present: Precision Shaft Alignment Made Easy
Transcat and Fluke Present: Precision Shaft Alignment Made EasyTranscat and Fluke Present: Precision Shaft Alignment Made Easy
Transcat and Fluke Present: Precision Shaft Alignment Made Easy
 
Shaft alignment
Shaft alignmentShaft alignment
Shaft alignment
 
Strentube
StrentubeStrentube
Strentube
 
Alignment Systems July 2009 En
Alignment Systems July 2009 EnAlignment Systems July 2009 En
Alignment Systems July 2009 En
 
Maintenance of Pumps
Maintenance of PumpsMaintenance of Pumps
Maintenance of Pumps
 
Alignment presentation
Alignment presentationAlignment presentation
Alignment presentation
 
Welding qualification a
Welding qualification aWelding qualification a
Welding qualification a
 
An engineers guide 2012 making maintenance matter, pruftechnik
An engineers guide 2012 making maintenance matter, pruftechnikAn engineers guide 2012 making maintenance matter, pruftechnik
An engineers guide 2012 making maintenance matter, pruftechnik
 
Shaft Lateral Analysis Overview
Shaft Lateral Analysis OverviewShaft Lateral Analysis Overview
Shaft Lateral Analysis Overview
 
Improving Rotating Equipment Reliability and Machinery Health
Improving Rotating Equipment Reliability and Machinery HealthImproving Rotating Equipment Reliability and Machinery Health
Improving Rotating Equipment Reliability and Machinery Health
 
Centrifugal Pump
Centrifugal PumpCentrifugal Pump
Centrifugal Pump
 
Maintainence OF STEAM TURBINE
Maintainence OF STEAM TURBINEMaintainence OF STEAM TURBINE
Maintainence OF STEAM TURBINE
 
PUMPS
 PUMPS PUMPS
PUMPS
 
Mechanical drives & power transmission
Mechanical drives & power transmissionMechanical drives & power transmission
Mechanical drives & power transmission
 
Estimation of misalignment in bearing shaft by signal processing of acoustic ...
Estimation of misalignment in bearing shaft by signal processing of acoustic ...Estimation of misalignment in bearing shaft by signal processing of acoustic ...
Estimation of misalignment in bearing shaft by signal processing of acoustic ...
 

Similaire à Alignment

Effects_of_Misalignment.pdf
Effects_of_Misalignment.pdfEffects_of_Misalignment.pdf
Effects_of_Misalignment.pdfstanleynyatondo
 
MACHINE ALIGNMENT.pptx. An Useful Presentation to understand Alignment Requir...
MACHINE ALIGNMENT.pptx. An Useful Presentation to understand Alignment Requir...MACHINE ALIGNMENT.pptx. An Useful Presentation to understand Alignment Requir...
MACHINE ALIGNMENT.pptx. An Useful Presentation to understand Alignment Requir...Manoj Mathur
 
Camshaft , Turbocharger and Supercharger, Rocker arm working
Camshaft , Turbocharger and Supercharger, Rocker arm workingCamshaft , Turbocharger and Supercharger, Rocker arm working
Camshaft , Turbocharger and Supercharger, Rocker arm workingSalman Jailani
 
Pressure Overview Of Measurement And Calibration
Pressure Overview Of Measurement And CalibrationPressure Overview Of Measurement And Calibration
Pressure Overview Of Measurement And CalibrationAsep Herman
 
Toyota 30-5FB18 Forklift Service Repair Manual
Toyota 30-5FB18 Forklift Service Repair ManualToyota 30-5FB18 Forklift Service Repair Manual
Toyota 30-5FB18 Forklift Service Repair Manualjksmelmdme
 
Toyota 5FB25 Forklift Service Repair Manual
Toyota 5FB25 Forklift Service Repair ManualToyota 5FB25 Forklift Service Repair Manual
Toyota 5FB25 Forklift Service Repair Manualjkkksemdme
 
Toyota 30-5FB20 Forklift Service Repair Manual
Toyota 30-5FB20 Forklift Service Repair ManualToyota 30-5FB20 Forklift Service Repair Manual
Toyota 30-5FB20 Forklift Service Repair Manualjkmdmd yksejkdmm
 
Toyota 5FB10 Forklift Service Repair Manual
Toyota 5FB10 Forklift Service Repair ManualToyota 5FB10 Forklift Service Repair Manual
Toyota 5FB10 Forklift Service Repair Manualpoikoi tygtrd
 
Toyota 30-5FB15 Forklift Service Repair Manual
Toyota 30-5FB15 Forklift Service Repair ManualToyota 30-5FB15 Forklift Service Repair Manual
Toyota 30-5FB15 Forklift Service Repair Manualjkseodlpled
 
Toyota 5 fb14 forklift service repair manual
Toyota 5 fb14 forklift service repair manualToyota 5 fb14 forklift service repair manual
Toyota 5 fb14 forklift service repair manualjkmsmns
 
Toyota 5 fb18 forklift service repair manual
Toyota 5 fb18 forklift service repair manualToyota 5 fb18 forklift service repair manual
Toyota 5 fb18 forklift service repair manualjksefmmsme
 
Toyota 5FB30 Forklift Service Repair Manual
Toyota 5FB30 Forklift Service Repair ManualToyota 5FB30 Forklift Service Repair Manual
Toyota 5FB30 Forklift Service Repair Manualukjemm kjskmfm
 
Toyota 5FB20 Forklift Service Repair Manual
Toyota 5FB20 Forklift Service Repair ManualToyota 5FB20 Forklift Service Repair Manual
Toyota 5FB20 Forklift Service Repair Manualhksemd ukejkfm
 
2000 honda accord service repair manual
2000 honda accord service repair manual2000 honda accord service repair manual
2000 honda accord service repair manualfhjskemme
 
Toyota 52 6 fgcu20 forklift service repair manual
Toyota 52 6 fgcu20 forklift service repair manualToyota 52 6 fgcu20 forklift service repair manual
Toyota 52 6 fgcu20 forklift service repair manualjfskemsemm
 
Guide on fuel management technologies
Guide on fuel management technologiesGuide on fuel management technologies
Guide on fuel management technologiesOmnicomm
 
Internship at HONDA MOTOR CYCLE SCOOTER INDIA LIMITED
Internship at HONDA MOTOR CYCLE SCOOTER INDIA LIMITEDInternship at HONDA MOTOR CYCLE SCOOTER INDIA LIMITED
Internship at HONDA MOTOR CYCLE SCOOTER INDIA LIMITEDsgrsoni45
 
IG Tech Bootcamp-Tips & Tricks, Critical Features and Common Mistakes PV Elit...
IG Tech Bootcamp-Tips & Tricks, Critical Features and Common Mistakes PV Elit...IG Tech Bootcamp-Tips & Tricks, Critical Features and Common Mistakes PV Elit...
IG Tech Bootcamp-Tips & Tricks, Critical Features and Common Mistakes PV Elit...amolshinde464815
 

Similaire à Alignment (20)

Effects_of_Misalignment.pdf
Effects_of_Misalignment.pdfEffects_of_Misalignment.pdf
Effects_of_Misalignment.pdf
 
MACHINE ALIGNMENT.pptx. An Useful Presentation to understand Alignment Requir...
MACHINE ALIGNMENT.pptx. An Useful Presentation to understand Alignment Requir...MACHINE ALIGNMENT.pptx. An Useful Presentation to understand Alignment Requir...
MACHINE ALIGNMENT.pptx. An Useful Presentation to understand Alignment Requir...
 
Camshaft , Turbocharger and Supercharger, Rocker arm working
Camshaft , Turbocharger and Supercharger, Rocker arm workingCamshaft , Turbocharger and Supercharger, Rocker arm working
Camshaft , Turbocharger and Supercharger, Rocker arm working
 
Pressure Overview Of Measurement And Calibration
Pressure Overview Of Measurement And CalibrationPressure Overview Of Measurement And Calibration
Pressure Overview Of Measurement And Calibration
 
Toyota 30-5FB18 Forklift Service Repair Manual
Toyota 30-5FB18 Forklift Service Repair ManualToyota 30-5FB18 Forklift Service Repair Manual
Toyota 30-5FB18 Forklift Service Repair Manual
 
Toyota 5FB25 Forklift Service Repair Manual
Toyota 5FB25 Forklift Service Repair ManualToyota 5FB25 Forklift Service Repair Manual
Toyota 5FB25 Forklift Service Repair Manual
 
Toyota 30-5FB20 Forklift Service Repair Manual
Toyota 30-5FB20 Forklift Service Repair ManualToyota 30-5FB20 Forklift Service Repair Manual
Toyota 30-5FB20 Forklift Service Repair Manual
 
Toyota 5FB10 Forklift Service Repair Manual
Toyota 5FB10 Forklift Service Repair ManualToyota 5FB10 Forklift Service Repair Manual
Toyota 5FB10 Forklift Service Repair Manual
 
Toyota 30-5FB15 Forklift Service Repair Manual
Toyota 30-5FB15 Forklift Service Repair ManualToyota 30-5FB15 Forklift Service Repair Manual
Toyota 30-5FB15 Forklift Service Repair Manual
 
Toyota 5 fb14 forklift service repair manual
Toyota 5 fb14 forklift service repair manualToyota 5 fb14 forklift service repair manual
Toyota 5 fb14 forklift service repair manual
 
Toyota 5 fb18 forklift service repair manual
Toyota 5 fb18 forklift service repair manualToyota 5 fb18 forklift service repair manual
Toyota 5 fb18 forklift service repair manual
 
Toyota 5FB30 Forklift Service Repair Manual
Toyota 5FB30 Forklift Service Repair ManualToyota 5FB30 Forklift Service Repair Manual
Toyota 5FB30 Forklift Service Repair Manual
 
Toyota 5FB20 Forklift Service Repair Manual
Toyota 5FB20 Forklift Service Repair ManualToyota 5FB20 Forklift Service Repair Manual
Toyota 5FB20 Forklift Service Repair Manual
 
4 f27e 1 ford
4 f27e 1 ford4 f27e 1 ford
4 f27e 1 ford
 
2000 honda accord service repair manual
2000 honda accord service repair manual2000 honda accord service repair manual
2000 honda accord service repair manual
 
Toyota 52 6 fgcu20 forklift service repair manual
Toyota 52 6 fgcu20 forklift service repair manualToyota 52 6 fgcu20 forklift service repair manual
Toyota 52 6 fgcu20 forklift service repair manual
 
Kaizen
KaizenKaizen
Kaizen
 
Guide on fuel management technologies
Guide on fuel management technologiesGuide on fuel management technologies
Guide on fuel management technologies
 
Internship at HONDA MOTOR CYCLE SCOOTER INDIA LIMITED
Internship at HONDA MOTOR CYCLE SCOOTER INDIA LIMITEDInternship at HONDA MOTOR CYCLE SCOOTER INDIA LIMITED
Internship at HONDA MOTOR CYCLE SCOOTER INDIA LIMITED
 
IG Tech Bootcamp-Tips & Tricks, Critical Features and Common Mistakes PV Elit...
IG Tech Bootcamp-Tips & Tricks, Critical Features and Common Mistakes PV Elit...IG Tech Bootcamp-Tips & Tricks, Critical Features and Common Mistakes PV Elit...
IG Tech Bootcamp-Tips & Tricks, Critical Features and Common Mistakes PV Elit...
 

Plus de Jithu John

2. Pharmacokinetics and dynamics - KK.pptx
2. Pharmacokinetics and dynamics - KK.pptx2. Pharmacokinetics and dynamics - KK.pptx
2. Pharmacokinetics and dynamics - KK.pptxJithu John
 
9 belzona-2 - compliant repairs
9 belzona-2 - compliant repairs9 belzona-2 - compliant repairs
9 belzona-2 - compliant repairsJithu John
 
2 eliminate hidden riskof cui
2 eliminate hidden riskof cui2 eliminate hidden riskof cui
2 eliminate hidden riskof cuiJithu John
 
Oil refinery processes
Oil refinery processesOil refinery processes
Oil refinery processesJithu John
 
Asme section ii c new
Asme section ii c newAsme section ii c new
Asme section ii c newJithu John
 
Asme sec. ix bkr - 051010
Asme sec. ix   bkr - 051010Asme sec. ix   bkr - 051010
Asme sec. ix bkr - 051010Jithu John
 
Asme sec viii div 2
Asme sec viii div 2Asme sec viii div 2
Asme sec viii div 2Jithu John
 
Asme sec viii div 1 s
Asme sec viii div 1 sAsme sec viii div 1 s
Asme sec viii div 1 sJithu John
 
Saudi aramco standards
Saudi aramco standardsSaudi aramco standards
Saudi aramco standardsJithu John
 
100661266 cswip-3-1-2009
100661266 cswip-3-1-2009100661266 cswip-3-1-2009
100661266 cswip-3-1-2009Jithu John
 
61769477 welding-inspection-cswip-gud
61769477 welding-inspection-cswip-gud61769477 welding-inspection-cswip-gud
61769477 welding-inspection-cswip-gudJithu John
 
Weld ability of the new generation stainless steels
Weld ability of the new generation stainless steelsWeld ability of the new generation stainless steels
Weld ability of the new generation stainless steelsJithu John
 

Plus de Jithu John (14)

2. Pharmacokinetics and dynamics - KK.pptx
2. Pharmacokinetics and dynamics - KK.pptx2. Pharmacokinetics and dynamics - KK.pptx
2. Pharmacokinetics and dynamics - KK.pptx
 
my ppt.pptx
my ppt.pptxmy ppt.pptx
my ppt.pptx
 
9 belzona-2 - compliant repairs
9 belzona-2 - compliant repairs9 belzona-2 - compliant repairs
9 belzona-2 - compliant repairs
 
2 eliminate hidden riskof cui
2 eliminate hidden riskof cui2 eliminate hidden riskof cui
2 eliminate hidden riskof cui
 
Oil refinery processes
Oil refinery processesOil refinery processes
Oil refinery processes
 
Asme section ii c new
Asme section ii c newAsme section ii c new
Asme section ii c new
 
Asme sec. ix bkr - 051010
Asme sec. ix   bkr - 051010Asme sec. ix   bkr - 051010
Asme sec. ix bkr - 051010
 
Asme sec viii div 2
Asme sec viii div 2Asme sec viii div 2
Asme sec viii div 2
 
Asme sec viii div 1 s
Asme sec viii div 1 sAsme sec viii div 1 s
Asme sec viii div 1 s
 
Saudi aramco standards
Saudi aramco standardsSaudi aramco standards
Saudi aramco standards
 
100661266 cswip-3-1-2009
100661266 cswip-3-1-2009100661266 cswip-3-1-2009
100661266 cswip-3-1-2009
 
61769477 welding-inspection-cswip-gud
61769477 welding-inspection-cswip-gud61769477 welding-inspection-cswip-gud
61769477 welding-inspection-cswip-gud
 
Weld ability of the new generation stainless steels
Weld ability of the new generation stainless steelsWeld ability of the new generation stainless steels
Weld ability of the new generation stainless steels
 
Weld defects
Weld defectsWeld defects
Weld defects
 

Dernier

UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsRussian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)simmis5
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxfenichawla
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduitsrknatarajan
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Glass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesGlass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesPrabhanshu Chaturvedi
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfKamal Acharya
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...ranjana rawat
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 

Dernier (20)

UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsRussian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
Glass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesGlass Ceramics: Processing and Properties
Glass Ceramics: Processing and Properties
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 

Alignment

  • 1. IMPORTANT CONSIDERATIONS BEFORE STARTING ALIGNMENT  MAKE SURE THAT RUNOUT AT THE SHAFT AS WELL AS COUPLING IS LESS THAN 0.05 mm ON BOTH THE MACHINES . SEE FIGURE RUNOUT SHOULD NOT EXCEED 0.05 MM  DECIDE WHICH MACHINE WILL BE KEPT STATIOARY AND WHICH ONE WILL BE MOVED . GENERALLY, FOR A MOTOR PUMP COMBINATION , PUMP IS KEPT STATIOARY ,FOR A TURBINE PUMP COMBINATION , TURBINE IS KEPT STATIONARY.  CHECK FOR RUSTY OR BROKEN SHIMS/TOO MANY SHIMS UNDER THE SUPPORT LEGS .NUMBER OF SHIMS SHOULD NOT EXCEED FOUR.  MAKE PROVISION FOR MOVING THE MACHINERY ( BOTH SIDEWISE AND UPDOWN MOTION ) FOR SIDEWISE MOTION , USING JACK BOLTS IS THE PREFERRED METHOD. FOR UP-DOWN MOTION , WEDGING AT THE APPROPRIATE PLACE IS DONE AND THEN SHIMS ARE KEPT BELOW THE LEGS.
  • 3. ALIGNMENT PROCEDURE (TAKING ALIGNMENT READINGS) – STEP NO. : 1  DIAL POINTER SHOULD PREFRABLY BE KEPT ON THE MACINE TO BE MOVED.  THE SUM TOTAL OF BOTH SIDE READINGS SHOULD BE SAME AS SUM TOTAL OF TOP BOTTOM READINGS. IN ACTUAL PRACTICE ,WE CAN ALLOW A DIFFERENCE OF ABOUT 15%. THIS RULE IS CALLED VALIDITY RULE. SUM TOTAL OF SIDE READINGS = 0.15 + 0.25 = 0.40 SUM TOTAL OF TOP BOTTOM READINGS = 0.00 + 0.36 = 0.36 DIFFERENCE = 0.40 – 0.36 = 0.04 THIS DIFFERENCE SHOULD BE LESS THAN 15 % 15 % OF 0.40 = 0.06 THUS DIFFERENCE IS LESS THAN 15 %. HENCE ALIGNMENT READING IS VALID. IMPORTANT : ALIGNMENT CORRECTION SHOULD BE ATTEMPTED ONLY WHEN SUM TOTAL OF SIDE READINGS AND TOP BOTTOM READINGS ARE MATCHING WITHIN 15 % AS SHOWN IN THE ABOVE EXAMPLE. 0.00 0.36 0.15 0.25 RFOR EXAMPLE D L1 L2
  • 4. WHAT CHECKS TO DO IF ALIGNMENT READINGS ARE FOUND INVALID :  CHECK THE CLAMP FOR LOOSENESS. IF FOUND LOOSE, TIGHTEN.  CHECK THE DIAL POINTER IS LEAVING CONTACT DURING ROTATION. IF SO, DO ROUGH ALIGNMENT WITH STRAIGHT EDGE FIRST.  CHECK THE COUPLING FOR ECCENTRICITY / ELLIPTICITY AND SHAFT FOR RUNOUT. RECTIFY, AND ROTATE BOTH SHAFTS TOGETHER. IF STILL ALIGNMENT READINGS ARE FOUND INVALID, IT MEANS THAT THERE IS SAG IN THE DIAL CLAMP.
  • 5. 12 O’CLOCK 6 O’CLOCK ALIGNMENT PROCEDURE – STEP NO. : 1 SAG MEASUREMENT AND CORRECTION IMPORTANT : THIS STEP IS TO BE CARRIED OUT ONLY IF THE SUM TOTAL OF SIDE READINGS IS NOT MATCHING WITH THE SUM TOTAL OF TOP-BOTTOM READINGS.  WHAT IS SAG ? SEE FIGURE  WHEN DIAL IS AT 12 O’CLOCK POSITION, THE CLAMP BENDS TOWARDS THE COUPLING.  WHEN THE DIAL IS AT 6 O’CLOCK POSITION THE CLAMP BENDS AWAY FROM THE COUPLING.  THIS MOVEMENT OF CLAMP CAUSES CHANGE IN DIAL READINGS. DUE TO THIS CHANGE, SUM TOTAL OF TOP-BOTTOM READINGS DOES NOT MATCH WITH SUM TOTAL OF SIDE READINGS. THIS EFFECT IS CALLED SAG.
  • 6. 0.00 + 0.16 + 0.12 + 0.12 FOR EXAMPLE ALIGNMENT READING IS 0.00 - 0.08 + 0.08 + 0.16 + 0.12 + 0.12 ALIGNMENT PROCEDURE – STEP NO. : 2  HOW TO REMOVE SAG ERROR FROM THE ALIGNMENT READINGS :  MEASURE THE VALUE OF SAG WITH THE HELP OF SAG MEASUREMENT SETUP AS SHOWN IN FIGURE. THIS SAG VALUE WILL BE NEGATIVE.  ADD THE SAG VALUE TO THE ALIGNMENT READINGS AS SHOWN IN THE FOLLOWING EXAMPLE.  AS WE CAN SEE,SUM TOTAL OF TOP-BOTTOM READINGS & SIDE READINGS IS NOT MATCHING. ALL THREE CHECKS, GIVEN IN STEP NO.:1 HAVE BEEN DONE. STILL DIFFERENCE IS COMING DIAL READINGS FROM THE SAG MEASUREMENT SETUP ARE AS FOLLOWS. IT MEANS THERE IS SAG OF 0.08 MM.  THIS SAG VALUE WILL BE ADDED TO THE ALIGNMENT READING OF 12 O’CLOCK POSITION AFTER CHANGING THE SIGN FROM MINUS TO PLUS. MODIFIED READING IS AS FOLLOWS :  NOW, SUM TOTAL OF SIDE READINGS AND TOP BOTTOM READINGS IS MATCHING. NOW, WE CAN PROCEED TO STEP NO. : 3 OF ALIGNMENT PROCEDURE.
  • 7. ALIGNMENT PROCEDURE – STEP NO. : 3 CALCULATING MACHINERY MOVEMENT IMPORTANT : FOR BEST RESULTS ,RADIAL AND AXIAL ALIGNMENT CORRECTIONS SHOULD BE DONE TOGETHER. A TABLE FOR THIS PURPOSE IS SHOWN AS FOLLOWS : AMOUNT OF SHIMS REQUIRED AT FRONT LEG REAR LEG FOR RADIAL ALIGNMENT A mm A mm FOR AXIAL ALIGNMENT B mm C mm FOR TOTAL ALIGNMENT CORRECTION A + B mm A + C mm
  • 8. ALIGNMENT PROCEDURE – STEP NO. : 3A CORRECTING RADIAL MISALIGNMENT RADIAL CORRECTION VALUE IS HALF OF THE TOTAL INDICATOR READING. FOR EXAMPLE :  DIAL IS CLAMPED ON PUMP COUPLING AND POINTER IS ON MOTOR COUPLING.  DIAL IS SET TO ZERO AT 12 O’CLOCK POSITION.  DIAL IS READING +0.20 mm AT 6 O’CLOCK POSITION.  THIS MEANS THAT MOTOR SHAFT IS DOWN ( + SIGN MEANS DIAL POINTER HAS GOT COMPRESSED.)  THUS MOTOR SHAFT WILL HAVE TO BE LIFTED UP BY +0.20/2 = 0.10 mm . THAT IS, SHIMMING OF 0.10 mm IS REQUIRED AT ALL THE FOUR LEGS. IMPORTANT : FOR RADIAL MISALIGNMENT CORRECTION , THE VALUE OF SHIMMING REQUIRED WILL BE SAME FOR ALL THE FOUR LEGS, AS WE SAW IN THE ABOVE EXAMPLE. 0.00 + 0.20
  • 9. ALIGNMENT PROCEDURE – STEP NO. : 3B CORRECTING AXIAL MISALIGNMENT SEE FIGURE :  D = DIAMETER ON WHICH THE DIAL IS MOVING. ( APPROX. EQUAL TOCOUPLIND DIAMETER).  L1 = DIAMETER AT FRONT LEG FROM MOTOR COUPLING.  L2 = DISTANCE AT BACK LEG FROM THE MOTOR COUPLING. SHIMING REQUIRED AT FRONT / BACK LEG = L1 OR L2 x DIAL READING / D EXAMPLE :  DIAMETER OF DIAL TRAVEL D = 100 mm  DISTANCE OF FRONT LEG TO COUPLING L1 = 200 mm  DISTANCE OF BACK LEG TO COUPLING L2 = 400 mm NOW, DIAL IS SET TO ZERO AT 12 O’CLOCK POSITION. DIAL READS + 0.30 AT 6 O’CLOCK POSITION THIS MEANS THAT TOP GAP BETWEEN COUPLINGS IS MORE THAN BOTTOM GAP (+ SIGN MEANS DIAL POINTER HAS GOT COMPRESSED) 0.00 + 0.30 D L1
  • 10. ALIGNMENT PROCEDURE – STEP NO. : 3B CORRECTING AXIAL MISALIGNMENT SEE FIGURE :  THUS MOTOR SHAFT WILL HAVE TO BE LIFTED UP.  SHIMING REQUIRED AT FRONT LEG = L1 x DIAL READING / D = 200 x 0.30 / 100 = 0.60 mm  SHIMING REQUIRED AT BACK LEG = L2 x DIAL READING / D = 400 x 0.30 / 100 = 1.20 mm IMPORTANT : FOR AXIAL MISALIGNMENT CORRECTION , THE AMOUNT OF SHIMS REQUIRED TO BE ADDED OR REMOVED IS DIFFERENT FOR THE FRONT LEGS AND BACK LEGS.
  • 11. ALIGNMENT PROCEDURE – STEP NO. : 3C CORRECTING TOTAL MISALIGNMENT AS PER OUR EXAMPLE, THE TOP BOTTOM READINGS ARE : SHIMING REQUIRED FOR RADIAL & AXIAL MISALIGNMENTS RESPECTIVELY HAVE BEEN CALCULATED ON THE PREVIOUS SLIDES. THE TOTAL SHIMING REQUIRED IS CALCULATED AS FOLLOWS : THUS, IN ORDER TO DO TOTAL (RADIAL + AXIAL ) ALIGNMENT, PUT SHIMS OF 0.70 mm IN FRONT LEG AND 1.3 mm IN BACK LEG OF MOTOR IN OUR EXAMPLE. 0.00 0.20 mm R 0.00 0.30 mm A AMOUNT OF SHIMS REQUIRED IN FRONT LEG REAR LEG TO CORRECT RADIAL ALIGNMENT + 0.10 mm + 0.10 mm TO CORRECT AXIAL ALIGNMENT + 0.60 mm + 1.20 mm TOTAL ALIGNMENT CORRECTION 0.10 + 0.60 = 0.70 mm 0.10 + 1.20 = 1.3 mm
  • 12. ALIGNMENT PROCEDURE – STEP NO. : 4 MOVING THE MACHINERY  FOR TOP-BOTTOM MOVEMENT SHIMS ARE ADDED OR REMOVED FROM BELOW THE FEET OF THE MACHINE TO BE MOVED. FOR THIS PURPOSE, THE MACHINE IS LIFTED UP BY WEDGING, AND THEN SHIMS ARE ADDED OR REMOVED.  FOR SIDE WISE MOVEMENT, USING JACKBOLTS IS THE PREFERRED METHOD. A LIGHT HAMMER CAN ALSO BE USED ON SMALL MACHINES. THE MOVEMENT SHOULD BE CLOSELY MONIORED BY TWO DIAL GAUGES, AS SHOWN IN THE FIGURE. IMPORTANT : AFTER MAKING THE REQUIRED MOVEMENT, ONE FINAL ALIGNMENT READING SHOULD BE TAKEN.
  • 13. CONCLUSION WHICH ALIGNMENT TO DO FIRST : TOP-BOTTOM OR SIDE WISE ALIGNMENT  WE HAVE TO SEE THAT IT IS VERY CONVENIENT TO DO RADIAL AND AXIAL ALIGNMENT CORRECTION TOGATHER.  HENCE, WE CAN SAY THAT ULTIMATELY THERE ARE ONLY TWO TYPES OF MISALIGNMENTS – TOP-BOTTOM (RADIAL + AXIAL) MISALIGNMENT AND SIDE WISE (RADIAL + AXIAL) MISALIGNMENT.  FOR BEST RESULTS TOP-BOTTOM ALIGNMENT SHOULD BE DONE FIRST, FOLLOWED BY SIDE WISE ALIGNMENT. THE REASON IS THAT IF YOU DO SIDE WISE ALIGNMENT FIRST, THEN WHILE DOING TOP-BOTTOM ALIGNMENT, SIDE WISE ALIGNMENT WILL AGAIN GET DISTURBED.  HOW EVER, IF DURING STEP NO. : 1 (TAKING ALIGNMENT READINGS) IT IS FOUND THAT SIDE WISE MISALIGNMENT IS VERY LARGE AS COMPARE TO TOP-BOTTOM MISALGNMENT, THEN ROUGH ALIGNMENT (OF SIDE WISE) SHOULD BE DONE FIRST. AFTER THAT FINAL TOP-BOTTOM ALIGNMENT AND THEN FINAL SIDE WISE ALIGNMENT SHOULD BE DONE.
  • 14. 5.REMOVE COUPLING GAURDS AND COUPLING SPOOL PIECE IF NECESSARY.MEASURE THE SHAFT AND COUPLING HUB RUN OUT ON BOTH UNITS. INSPECT COUPLING FOR ANY DAMAGE OR WORN PARTS. KEEP TRACK OF THE COUPLIG PARTS AND LABEL THEM IF NECESSARY.IF EQUIPMENT IS GOING TO BE REMOVED FOR SERVICING, MAKE PUNCH MARKS ON CASING AND BASEPLATE AS A REFERENCE DURING REINSTALLATION. 6.CHECK FOR SOFT FOOT,CASING OR FRAME WARPAGE, EXCESSIVE STATIC PIPING OR CONDUIT FORCES,DAMAGED OR RUSTY SHIMS, LOOSE FOUNDATION BOLTS. ETC. CORRECT ANY OF THE POTENTIAL PROBLEM AREAS. 7. TAKE AND RECORD A SET OF ALIGNMENT READINGS. 8.CALCULATE AND PERFORM THE NECESSARY AXIAL , VERTICAL AND HORIZONTALS MOVE. RECHECK ALIGNMET, CALCULATE AND MOVE UNTILL EQUIPMENT IS WITHIN ACCEPTABLE ALIGNMENT TOLERANCES.TORQUE FOUNDATION BOLTS TO REQURED VALUES. RCORD FINAL ALIGNMENT READINGS.