Maax Hydro Swirl
Group 1: Dustin Berman, Youngha Kim, Joe Glithero, Justin Parson
Company History
The Bellingham production facility was opened in 2000 and serves as a production facility as well
as a distribution point for raw materials and finished goods between other factories. This facility
has been utilizing lean principles since 2004.
Products
● Three main demographics
○ The home owner
○ The interior designer
○ The builder
● Six different product lines
● Popular product families include:
○ bathtubs, showers, shower doors, sinks, and jacuzzi
tubs.
Bellingham Facility Overview
● Products produced:
○ Various traditional bathtubs & spa style
● Size and Employment
○ Smallest production facility
○ 21 employees
● Lean Practices
○ Implemented TPS 10 years ago
○ Heijunka board, moonshining, 6S, 2 bin system, JIT
- Takt Time: 226.77 seconds ~
3min 45 sec
- Available Work Time:
28,800 seconds
- Demand: 127 Tubs
Current Layout
Suggested Improvements
● Oven Size
● Ventilation
● Conveyor belt
● Second Raw Materials
rack
● Shipping
● Carts
● Improving startup time
after break
Conclusion
● 10 years of lean implementation
○ Already implemented many lean measures
● Most efficient facility of Maax
○ 1.34 Direct labor hours per tub, next closest was 3
hours
● Next big step is to improve the facility in
terms of spacing, shipping and equipment
Thank You
We would like to extend a sincere thank you to
both Professor Haug and Brendan Gair as well
as the entire Bellingham facility for their
willingness to work with us.
References
● "History." MAAX Collection Hot Tubs by MAAX Spas History Comments. N.p., n.d. Web. 05 June 2015.
● "MAAX Brands & Series." About MAAX. N.p., n.d. Web. 05 June 2015.
● "Maax Story." About MAAX. N.p., n.d. Web. 05 June 2015.
● "People & Environment." About MAAX -. N.p., n.d. Web. 05 June 2015.

Contenu connexe

En vedette (7)

elg project 2 brief
elg project 2 briefelg project 2 brief
elg project 2 brief
 
IRMOS_SPIE_2006
IRMOS_SPIE_2006IRMOS_SPIE_2006
IRMOS_SPIE_2006
 
Professional Profile
Professional ProfileProfessional Profile
Professional Profile
 
Angel fish-Pterophyllum scalare
Angel fish-Pterophyllum scalareAngel fish-Pterophyllum scalare
Angel fish-Pterophyllum scalare
 
CV of Rong Chen
CV of Rong ChenCV of Rong Chen
CV of Rong Chen
 
HH Technical Services, LLC
HH Technical Services, LLCHH Technical Services, LLC
HH Technical Services, LLC
 
Kevala solar deployment by income vote solar webinar 01 20-16 v2
Kevala solar deployment by income vote solar webinar 01 20-16 v2Kevala solar deployment by income vote solar webinar 01 20-16 v2
Kevala solar deployment by income vote solar webinar 01 20-16 v2
 

Similaire à OPS460

Proterra Internship Profile
Proterra Internship ProfileProterra Internship Profile
Proterra Internship Profile
John Biske
 
GSC meeting PM - Final
GSC meeting  PM - FinalGSC meeting  PM - Final
GSC meeting PM - Final
David Nderimo
 
Commercial presentation jan 2013
Commercial presentation   jan 2013Commercial presentation   jan 2013
Commercial presentation jan 2013
Solmatix Renewables
 
DJC Top Projects 2015 - Breathe Building Project Description - Final
DJC Top Projects 2015 - Breathe Building Project Description - FinalDJC Top Projects 2015 - Breathe Building Project Description - Final
DJC Top Projects 2015 - Breathe Building Project Description - Final
Chris Humphries
 
Britco_Changing_The_Way_The_World_Builds_Introduction_August 2014
Britco_Changing_The_Way_The_World_Builds_Introduction_August 2014Britco_Changing_The_Way_The_World_Builds_Introduction_August 2014
Britco_Changing_The_Way_The_World_Builds_Introduction_August 2014
Simon Amesbury
 
Michael_NAJARIAN_resume_5-2016
Michael_NAJARIAN_resume_5-2016Michael_NAJARIAN_resume_5-2016
Michael_NAJARIAN_resume_5-2016
Michael Najarian
 

Similaire à OPS460 (20)

Proterra Internship Profile
Proterra Internship ProfileProterra Internship Profile
Proterra Internship Profile
 
GSC meeting PM - Final
GSC meeting  PM - FinalGSC meeting  PM - Final
GSC meeting PM - Final
 
Automotive Insulations Limited - the digital journey, Paul Walker
Automotive Insulations Limited - the digital journey, Paul WalkerAutomotive Insulations Limited - the digital journey, Paul Walker
Automotive Insulations Limited - the digital journey, Paul Walker
 
Lean manufacturing
Lean manufacturingLean manufacturing
Lean manufacturing
 
Heating and Hot Water Refurbishment at St Paul’s Cathedral
Heating and Hot Water Refurbishment at St Paul’s CathedralHeating and Hot Water Refurbishment at St Paul’s Cathedral
Heating and Hot Water Refurbishment at St Paul’s Cathedral
 
Greg Southorn CV 2017
Greg Southorn CV 2017Greg Southorn CV 2017
Greg Southorn CV 2017
 
Commercial presentation jan 2013
Commercial presentation   jan 2013Commercial presentation   jan 2013
Commercial presentation jan 2013
 
Barangaroo South District Cooling Plant (DCP) Fact Sheet
Barangaroo South District Cooling Plant (DCP) Fact SheetBarangaroo South District Cooling Plant (DCP) Fact Sheet
Barangaroo South District Cooling Plant (DCP) Fact Sheet
 
DJC Top Projects 2015 - Breathe Building Project Description - Final
DJC Top Projects 2015 - Breathe Building Project Description - FinalDJC Top Projects 2015 - Breathe Building Project Description - Final
DJC Top Projects 2015 - Breathe Building Project Description - Final
 
Britco_Changing_The_Way_The_World_Builds_Introduction_August 2014
Britco_Changing_The_Way_The_World_Builds_Introduction_August 2014Britco_Changing_The_Way_The_World_Builds_Introduction_August 2014
Britco_Changing_The_Way_The_World_Builds_Introduction_August 2014
 
Blake Lapthorn's green breakfast with guest speaker Keeran Jugdoyal, Faithful...
Blake Lapthorn's green breakfast with guest speaker Keeran Jugdoyal, Faithful...Blake Lapthorn's green breakfast with guest speaker Keeran Jugdoyal, Faithful...
Blake Lapthorn's green breakfast with guest speaker Keeran Jugdoyal, Faithful...
 
Upload
UploadUpload
Upload
 
Perth metro
Perth metroPerth metro
Perth metro
 
Scottish Textile & Leather Association Sharing Operational Excellence present...
Scottish Textile & Leather Association Sharing Operational Excellence present...Scottish Textile & Leather Association Sharing Operational Excellence present...
Scottish Textile & Leather Association Sharing Operational Excellence present...
 
MicroHomes product catalogue
MicroHomes product catalogueMicroHomes product catalogue
MicroHomes product catalogue
 
Vision and Mission
Vision and MissionVision and Mission
Vision and Mission
 
Microhomes.eu
Microhomes.euMicrohomes.eu
Microhomes.eu
 
Michael_NAJARIAN_resume_5-2016
Michael_NAJARIAN_resume_5-2016Michael_NAJARIAN_resume_5-2016
Michael_NAJARIAN_resume_5-2016
 
Chalcroft construction for the food & drink industry
Chalcroft construction for the food & drink industryChalcroft construction for the food & drink industry
Chalcroft construction for the food & drink industry
 
3 in 1-1.pptx
3 in 1-1.pptx3 in 1-1.pptx
3 in 1-1.pptx
 

OPS460

  • 1. Maax Hydro Swirl Group 1: Dustin Berman, Youngha Kim, Joe Glithero, Justin Parson
  • 2. Company History The Bellingham production facility was opened in 2000 and serves as a production facility as well as a distribution point for raw materials and finished goods between other factories. This facility has been utilizing lean principles since 2004.
  • 3. Products ● Three main demographics ○ The home owner ○ The interior designer ○ The builder ● Six different product lines ● Popular product families include: ○ bathtubs, showers, shower doors, sinks, and jacuzzi tubs.
  • 4. Bellingham Facility Overview ● Products produced: ○ Various traditional bathtubs & spa style ● Size and Employment ○ Smallest production facility ○ 21 employees ● Lean Practices ○ Implemented TPS 10 years ago ○ Heijunka board, moonshining, 6S, 2 bin system, JIT
  • 5. - Takt Time: 226.77 seconds ~ 3min 45 sec - Available Work Time: 28,800 seconds - Demand: 127 Tubs
  • 7. Suggested Improvements ● Oven Size ● Ventilation ● Conveyor belt ● Second Raw Materials rack ● Shipping ● Carts ● Improving startup time after break
  • 8. Conclusion ● 10 years of lean implementation ○ Already implemented many lean measures ● Most efficient facility of Maax ○ 1.34 Direct labor hours per tub, next closest was 3 hours ● Next big step is to improve the facility in terms of spacing, shipping and equipment
  • 9. Thank You We would like to extend a sincere thank you to both Professor Haug and Brendan Gair as well as the entire Bellingham facility for their willingness to work with us.
  • 10. References ● "History." MAAX Collection Hot Tubs by MAAX Spas History Comments. N.p., n.d. Web. 05 June 2015. ● "MAAX Brands & Series." About MAAX. N.p., n.d. Web. 05 June 2015. ● "Maax Story." About MAAX. N.p., n.d. Web. 05 June 2015. ● "People & Environment." About MAAX -. N.p., n.d. Web. 05 June 2015.