SlideShare une entreprise Scribd logo
1  sur  1
Télécharger pour lire hors ligne
Merlin Single Family Project Template
Excavation to Framing Phase
Administrative
Plans & Permit to Plumber 1d BG Scheduling
Gas Application 1d People's Gas
Review Survey 1d BG Scheduling
Excavation 1d
Start Date Milestone BG Development
Footer 1d
Foundation 3 days
Backfill & Stone 1d
Underground HVAC (BLAB) 1d Air Rite
Inspection: Underground HVAC (BLAB) 4 days HVAC Insp
Underground Plumbing 1d Dee
Inspection: Undeground Plumbing 2 days Plumb Insp; Dee
Slab 2 days
Sewer/Water Tap 3 days Dee
Gas Line Run 2 days People's Gas
Framing 2 weeks
Inspection: Framing 4 days NC Insp
Contact ComEd 1d ComEd
Electric Service Installed 1d
Electric Meter Installed 1d ComEd
Mechanicals to Drywall Phase
HVAC Rough 2 days Air Rite
Inspection: HVAC Rough 4 days
Mechanicals Milestone BG Development
Install Alarm 1d BG Site Crew
Plumbing Rough 2 days Dee
Roof 1d Dusable
Inspection: Plumbing Rough 2 days Plumb Insp; Dee
Spray Copper 1d BG Site Crew
Gas Meter 1d People's Gas
Electric Rough 3 days
Inspection: Electric Rough 4 days Elect Insp
Masonry 1 week Superior
Install Rain Barrel 1d
Siding 2 days Dusable
Insulation 2 days BG Insulation
Drywall Delivered 1d Gonzalo
Drywall 2 weeks Gonzalo
Measure For Carpet 1d
Flatwork 3 days
Porches 3 days
Fence 4 days Steel Guard
As-Built Survey 1d BG Development
As-Built Survey Milestone BG Development
Canopy Roof 1d Dusable
Finish Phase
Rough Paint 2 days DK Profile
Rough Paint Milestone BG Development
Electric Trim 2 days
Trim Carpentry 1 week BG Trim
Order Dishwasher and Hood 1d BG Punchlist Manager
Install Dishwasher 1d BG Site Crew
Trim Paint 2 days DK Profile
Shelving 1d Chicago Closet
HVAC Trim 1d Air Rite
Install Hood 1d BG Trim
Plumbing Trim 1d Dee
Electric: Hook up Disposal, Dishwasher, Doorbell, Hood 1d
Water Meter 1d Dee
Water Meter Sensor 1d City Water Dept
Carpet 1d Abel
Installs Doors and Locks 2 days BG Trim
Final Inspections
Inspection: Final Electric 1d
Inspection: Final Plumbing 1d
Inspection: Final HVAC 1d
Inspection: New Construction 1d?
Punchlist to Close
Development Walk 1d BG Development
Complete 1st Punchlist 1 week BG Punchlist Manager
1st Homeowner's Walk Window 1 week BG Punchlist
Complete Final Punchlist 2 weeks BG Punchlist Manager
Homowner's Final Walk 1d BG Punchlist
26 27 28 29 30 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
WK 35, August 2015 WK 36, September 2015 WK 37, September 2015 WK 38, September 2015 WK 39, September 2015 WK 40, October 2015 WK 41, October 2015 WK 42, October 2015 WK 43, October 2015 WK 44, October 2015 WK 45, November 2015 WK 46, November 2015 WK 47, November 2015 WK 48, November 2015 WK 49, December 2015 WK 50, December 2015 WK 51, December 2015 WK 52, December 2015
0 Merlin Single Family Project Te… 9/3/15 12/22/15 Inspector:… 0%
1 Excavation to Framing Phase 9/3/15 10/8/15 ComEd; BG… 0%
2 Administrative 9/3/15 9/3/15 People's G… 0%
3 Plans & Permit to Plumber 1d 9/3/15 9/3/15 BG Schedul… 0%
5 Gas Application 1d 9/3/15 9/3/15 People's Gas 0%
7 Review Survey 1d 9/3/15 9/3/15 BG Schedul… 0%
9 Excavation 1d 9/3/15 9/3/15 0%
10 Start Date Milestone 9/3/15 9/3/15 BG Develop… 0%
12 Footer 1d 9/4/15 9/4/15 0%
13 Foundation 3d 9/7/15 9/9/15 0%
14 Backfill & Stone 1d 9/10/15 9/10/15 0%
15 Underground HVAC (BLAB) 1d 9/11/15 9/11/15 Air Rite 0%
17 Inspection: Underground HVAC (… 4d 9/14/15 9/17/15 Inspector:… 0%
19 Underground Plumbing 1d 9/14/15 9/14/15 Dee Plumbing 0%
21 Inspection: Undeground Plumbing 4d 9/15/15 9/16/15 Inspector:… 0%
24 Slab 2d 9/17/15 9/18/15 0%
25 Sewer/Water Tap 3d 9/11/15 9/15/15 Dee Plumbing 0%
27 Gas Line Run 2d 9/11/15 9/14/15 People's Gas 0%
29 Framing 10d 9/21/15 10/2/15 0%
30 Inspection: Framing 4d 10/5/15 10/8/15 Inspector:… 0%
32 Contact ComEd 1d 10/5/15 10/5/15 ComEd 0%
34 Electric Service Installed 1d 10/6/15 10/6/15 0%
35 Electric Meter Installed 1d 10/7/15 10/7/15 ComEd 0%
37 Mechanicals to Drywall Phase 10/5/15 11/4/15 Inspector:… 0%
38 HVAC Rough 2d 10/5/15 10/6/15 Air Rite 0%
40 Inspection: HVAC Rough 4d 10/7/15 10/12/15 0%
41 Mechanicals Milestone 10/5/15 10/5/15 BG Develop… 0%
43 Install Alarm 1d 10/7/15 10/7/15 BG Site Guys 0%
45 Plumbing Rough 2d 10/6/15 10/7/15 Dee Plumbing 0%
47 Roof 1d 10/8/15 10/8/15 Dusable 0%
49 Inspection: Plumbing Rough 4d 10/8/15 10/9/15 Inspector:… 0%
52 Spray Copper 1d 10/8/15 10/8/15 BG Site Guys 0%
54 Gas Meter 1d 10/8/15 10/8/15 People's Gas 0%
56 Electric Rough 3d 10/8/15 10/12/15 0%
57 Inspection: Electric Rough 4d 10/13/15 10/16/15 Inspector:… 0%
59 Masonry 5d 10/12/15 10/16/15 Superior M… 0%
61 Install Rain Barrel 1d 10/19/15 10/19/15 0%
62 Siding 2d 10/20/15 10/21/15 Dusable 0%
64 Insulation 2d 10/19/15 10/20/15 BG Insulation 0%
66 Drywall Delivered 1d 10/21/15 10/21/15 Gonzalo 0%
68 Drywall 10d 10/21/15 11/3/15 Gonzalo 0%
70 Measure For Carpet 1d 11/4/15 11/4/15 0%
71 Flatwork 3d 10/22/15 10/26/15 0%
72 Porches 3d 10/27/15 10/29/15 0%
73 Fence 4d 10/27/15 10/30/15 Steel Guard 0%
75 As-Built Survey 1d 11/2/15 11/2/15 BG Develop… 0%
77 As-Built Survey Milestone 11/2/15 11/2/15 BG Develop… 0%
79 Canopy Roof 1d 10/30/15 10/30/15 Dusable 0%
81 Finish Phase 11/5/15 12/22/15 D & K Profi… 0%
82 Rough Paint 2d 11/5/15 11/6/15 D & K Profil… 0%
84 Rough Paint Milestone 11/5/15 11/5/15 BG Develop… 0%
86 Electric Trim 2d 11/5/15 11/6/15 0%
87 Trim Carpentry 5d 11/9/15 11/13/15 BG Trim 0%
89 Order Dishwasher and Hood 1d 11/9/15 11/9/15 BG Punchlis… 0%
91 Install Dishwasher 1d 11/11/15 11/11/15 BG Site Guys 0%
93 Trim Paint 2d 11/16/15 11/17/15 D & K Profil… 0%
95 Shelving 1d 11/16/15 11/16/15 Chicago Cl… 0%
97 HVAC Trim 1d 11/16/15 11/16/15 Air Rite 0%
99 Install Hood 1d 11/16/15 11/16/15 BG Trim 0%
101 Plumbing Trim 1d 11/17/15 11/17/15 Dee Plumbing 0%
103 Electric: Hook up Disposal, Dish… 1d 11/18/15 11/18/15 0%
104 Water Meter 1d 11/18/15 11/18/15 Dee Plumbing 0%
106 Water Meter Sensor 1d 11/18/15 11/18/15 Chicago Wa… 0%
108 Carpet 1d 11/18/15 11/18/15 Abel Carpet 0%
110 Installs Doors and Locks 2d 11/19/15 11/20/15 BG Trim 0%
112 Final Inspections 11/23/15 11/23/15 0%
113 Inspection: Final Electric 1d 11/23/15 11/23/15 0%
114 Inspection: Final Plumbing 1d 11/23/15 11/23/15 0%
115 Inspection: Final HVAC 1d 11/23/15 11/23/15 0%
116 Inspection: New Construction 1d? 11/23/15 11/23/15 0%
117 Punchlist to Close 11/23/15 12/22/15 BG Develo… 0%
118 Development Walk 1d 11/23/15 11/23/15 BG Develop… 0%
120 Complete 1st Punchlist 5d 11/24/15 11/30/15 BG Punchlis… 0%
122 1st Homeowner's Walk Window 5d 12/1/15 12/7/15 BG Punchlis… 0%
124 Complete Final Punchlist 10d 12/8/15 12/21/15 BG Punchlis… 0%
126 Homowner's Final Walk 1d 12/22/15 12/22/15 BG Punchlis… 0%
%
Complete
Flag
Status
Assigned
Resources
Expected
End
Expected
Start
Given
Work
TitleInf
o
#

Contenu connexe

En vedette

Sequence of general works of building construction
Sequence of general works of building constructionSequence of general works of building construction
Sequence of general works of building constructionChelluri Srihari
 
2015 Residential Construction Practices Fairfield County CT
2015 Residential Construction Practices Fairfield County CT 2015 Residential Construction Practices Fairfield County CT
2015 Residential Construction Practices Fairfield County CT tigerrealestate
 
Step by step process of construction
Step by step process of constructionStep by step process of construction
Step by step process of constructionMatt Webb
 
Picture Presentaion of Foundation construction
Picture Presentaion of Foundation constructionPicture Presentaion of Foundation construction
Picture Presentaion of Foundation constructionHarshit Kothari
 
Construction activities and Process
Construction activities and ProcessConstruction activities and Process
Construction activities and ProcessIbrahim Adhnan
 
Heathrow 3rd Runway Construction
Heathrow 3rd Runway ConstructionHeathrow 3rd Runway Construction
Heathrow 3rd Runway ConstructionDavid H Moloney
 
Construction Activities and Process
Construction Activities and ProcessConstruction Activities and Process
Construction Activities and ProcessJ.j. Hayashi
 
Construction process
Construction processConstruction process
Construction processMazen Al-Qadi
 
Construction Methods & Sequence
Construction  Methods & SequenceConstruction  Methods & Sequence
Construction Methods & SequenceDavid H Moloney
 
The Network Diagram and Critical Path
The Network Diagram and Critical PathThe Network Diagram and Critical Path
The Network Diagram and Critical Pathdmdk12
 
Project Execution Plan for High Rise Building
Project Execution Plan for High Rise BuildingProject Execution Plan for High Rise Building
Project Execution Plan for High Rise BuildingDavid H Moloney
 
A study on the construction process (Precast concrete, In-situ cast concrete,...
A study on the construction process (Precast concrete, In-situ cast concrete,...A study on the construction process (Precast concrete, In-situ cast concrete,...
A study on the construction process (Precast concrete, In-situ cast concrete,...Bhaddin Al-Naqshabandi
 

En vedette (20)

CFC Day 25
CFC Day 25CFC Day 25
CFC Day 25
 
CFC Day 22
CFC Day 22CFC Day 22
CFC Day 22
 
CFC Day 31
CFC Day 31CFC Day 31
CFC Day 31
 
CFC Dat 39
CFC Dat 39CFC Dat 39
CFC Dat 39
 
CFC Day 34
CFC Day 34 CFC Day 34
CFC Day 34
 
CFC Day 18
CFC Day 18 CFC Day 18
CFC Day 18
 
Sequence of general works of building construction
Sequence of general works of building constructionSequence of general works of building construction
Sequence of general works of building construction
 
2015 Residential Construction Practices Fairfield County CT
2015 Residential Construction Practices Fairfield County CT 2015 Residential Construction Practices Fairfield County CT
2015 Residential Construction Practices Fairfield County CT
 
Step by step process of construction
Step by step process of constructionStep by step process of construction
Step by step process of construction
 
Picture Presentaion of Foundation construction
Picture Presentaion of Foundation constructionPicture Presentaion of Foundation construction
Picture Presentaion of Foundation construction
 
Cost Estimate Development Sequence
Cost Estimate Development SequenceCost Estimate Development Sequence
Cost Estimate Development Sequence
 
Masonry part 3
Masonry part 3Masonry part 3
Masonry part 3
 
Construction activities and Process
Construction activities and ProcessConstruction activities and Process
Construction activities and Process
 
Heathrow 3rd Runway Construction
Heathrow 3rd Runway ConstructionHeathrow 3rd Runway Construction
Heathrow 3rd Runway Construction
 
Construction Activities and Process
Construction Activities and ProcessConstruction Activities and Process
Construction Activities and Process
 
Construction process
Construction processConstruction process
Construction process
 
Construction Methods & Sequence
Construction  Methods & SequenceConstruction  Methods & Sequence
Construction Methods & Sequence
 
The Network Diagram and Critical Path
The Network Diagram and Critical PathThe Network Diagram and Critical Path
The Network Diagram and Critical Path
 
Project Execution Plan for High Rise Building
Project Execution Plan for High Rise BuildingProject Execution Plan for High Rise Building
Project Execution Plan for High Rise Building
 
A study on the construction process (Precast concrete, In-situ cast concrete,...
A study on the construction process (Precast concrete, In-situ cast concrete,...A study on the construction process (Precast concrete, In-situ cast concrete,...
A study on the construction process (Precast concrete, In-situ cast concrete,...
 

Similaire à Single Family Gantt Chart-John Mueller

Antara Dashboard-002.pptx
Antara Dashboard-002.pptxAntara Dashboard-002.pptx
Antara Dashboard-002.pptxTalebAlfihan
 
House by the Waters
House by the WatersHouse by the Waters
House by the WatersYi Jie Ng
 
C&I July-2022.pptx
C&I July-2022.pptxC&I July-2022.pptx
C&I July-2022.pptxPowerMurugan
 
Block estimate.ppt (1)
Block estimate.ppt (1)Block estimate.ppt (1)
Block estimate.ppt (1)kumud singh
 
Water pipe Lines Progress Planned Vs actual.pptx
Water pipe Lines  Progress Planned Vs actual.pptxWater pipe Lines  Progress Planned Vs actual.pptx
Water pipe Lines Progress Planned Vs actual.pptxDILIP KUMAR M.Tech (ACT)
 
ADCO Time plan.pdf
ADCO Time plan.pdfADCO Time plan.pdf
ADCO Time plan.pdfabdo badr
 
ADIB Time Schedule V4.0
ADIB Time Schedule V4.0ADIB Time Schedule V4.0
ADIB Time Schedule V4.0Ahmed Khaled
 
Nbourdier-lab2-gantt chart with activities-
Nbourdier-lab2-gantt chart with activities-Nbourdier-lab2-gantt chart with activities-
Nbourdier-lab2-gantt chart with activities-Nixzalis Bourdier
 
WC-14-NXE-007-00-Sch Rev 0.0 (29 May,2015)
WC-14-NXE-007-00-Sch Rev 0.0  (29 May,2015)  WC-14-NXE-007-00-Sch Rev 0.0  (29 May,2015)
WC-14-NXE-007-00-Sch Rev 0.0 (29 May,2015) Ali Yousef
 
ICI FINAL REPORT PDF
ICI FINAL REPORT PDFICI FINAL REPORT PDF
ICI FINAL REPORT PDFClement Seong
 
West Podium .2015.05.18 schedule
West Podium .2015.05.18 scheduleWest Podium .2015.05.18 schedule
West Podium .2015.05.18 scheduleRick Sommerfeld
 
CICPA Updated Schedule Dtd 130816
CICPA Updated Schedule Dtd 130816CICPA Updated Schedule Dtd 130816
CICPA Updated Schedule Dtd 130816Manish Shah
 
Zewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdfZewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdfAhmed Mehrem
 
VVGBJNRGGGGTGTGTGHTHGTGTGTJGNUGNURIEGNRIEUGBUBG
VVGBJNRGGGGTGTGTGHTHGTGTGTJGNUGNURIEGNRIEUGBUBGVVGBJNRGGGGTGTGTGHTHGTGTGTJGNUGNURIEGNRIEUGBUBG
VVGBJNRGGGGTGTGTGHTHGTGTGTJGNUGNURIEGNRIEUGBUBGIndrani7
 

Similaire à Single Family Gantt Chart-John Mueller (20)

MS project Sample gantt chart
MS project Sample  gantt chartMS project Sample  gantt chart
MS project Sample gantt chart
 
CPM
CPMCPM
CPM
 
Antara Dashboard-002.pptx
Antara Dashboard-002.pptxAntara Dashboard-002.pptx
Antara Dashboard-002.pptx
 
House by the Waters
House by the WatersHouse by the Waters
House by the Waters
 
01. P269 - Project Implementation Programme - Rev 00
01. P269 - Project Implementation Programme -  Rev 0001. P269 - Project Implementation Programme -  Rev 00
01. P269 - Project Implementation Programme - Rev 00
 
C&I July-2022.pptx
C&I July-2022.pptxC&I July-2022.pptx
C&I July-2022.pptx
 
Block estimate.ppt (1)
Block estimate.ppt (1)Block estimate.ppt (1)
Block estimate.ppt (1)
 
Water pipe Lines Progress Planned Vs actual.pptx
Water pipe Lines  Progress Planned Vs actual.pptxWater pipe Lines  Progress Planned Vs actual.pptx
Water pipe Lines Progress Planned Vs actual.pptx
 
ADCO Time plan.pdf
ADCO Time plan.pdfADCO Time plan.pdf
ADCO Time plan.pdf
 
ADIB Time Schedule V4.0
ADIB Time Schedule V4.0ADIB Time Schedule V4.0
ADIB Time Schedule V4.0
 
Nbourdier-lab2-gantt chart with activities-
Nbourdier-lab2-gantt chart with activities-Nbourdier-lab2-gantt chart with activities-
Nbourdier-lab2-gantt chart with activities-
 
WC-14-NXE-007-00-Sch Rev 0.0 (29 May,2015)
WC-14-NXE-007-00-Sch Rev 0.0  (29 May,2015)  WC-14-NXE-007-00-Sch Rev 0.0  (29 May,2015)
WC-14-NXE-007-00-Sch Rev 0.0 (29 May,2015)
 
HOP Yick BD Ltd SMED
HOP Yick BD Ltd SMEDHOP Yick BD Ltd SMED
HOP Yick BD Ltd SMED
 
ICI FINAL REPORT PDF
ICI FINAL REPORT PDFICI FINAL REPORT PDF
ICI FINAL REPORT PDF
 
Dashboard
DashboardDashboard
Dashboard
 
West Podium .2015.05.18 schedule
West Podium .2015.05.18 scheduleWest Podium .2015.05.18 schedule
West Podium .2015.05.18 schedule
 
10. Overall Implementation Programme
10. Overall Implementation Programme10. Overall Implementation Programme
10. Overall Implementation Programme
 
CICPA Updated Schedule Dtd 130816
CICPA Updated Schedule Dtd 130816CICPA Updated Schedule Dtd 130816
CICPA Updated Schedule Dtd 130816
 
Zewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdfZewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdf
 
VVGBJNRGGGGTGTGTGHTHGTGTGTJGNUGNURIEGNRIEUGBUBG
VVGBJNRGGGGTGTGTGHTHGTGTGTJGNUGNURIEGNRIEUGBUBGVVGBJNRGGGGTGTGTGHTHGTGTGTJGNUGNURIEGNRIEUGBUBG
VVGBJNRGGGGTGTGTGHTHGTGTGTJGNUGNURIEGNRIEUGBUBG
 

Single Family Gantt Chart-John Mueller

  • 1. Merlin Single Family Project Template Excavation to Framing Phase Administrative Plans & Permit to Plumber 1d BG Scheduling Gas Application 1d People's Gas Review Survey 1d BG Scheduling Excavation 1d Start Date Milestone BG Development Footer 1d Foundation 3 days Backfill & Stone 1d Underground HVAC (BLAB) 1d Air Rite Inspection: Underground HVAC (BLAB) 4 days HVAC Insp Underground Plumbing 1d Dee Inspection: Undeground Plumbing 2 days Plumb Insp; Dee Slab 2 days Sewer/Water Tap 3 days Dee Gas Line Run 2 days People's Gas Framing 2 weeks Inspection: Framing 4 days NC Insp Contact ComEd 1d ComEd Electric Service Installed 1d Electric Meter Installed 1d ComEd Mechanicals to Drywall Phase HVAC Rough 2 days Air Rite Inspection: HVAC Rough 4 days Mechanicals Milestone BG Development Install Alarm 1d BG Site Crew Plumbing Rough 2 days Dee Roof 1d Dusable Inspection: Plumbing Rough 2 days Plumb Insp; Dee Spray Copper 1d BG Site Crew Gas Meter 1d People's Gas Electric Rough 3 days Inspection: Electric Rough 4 days Elect Insp Masonry 1 week Superior Install Rain Barrel 1d Siding 2 days Dusable Insulation 2 days BG Insulation Drywall Delivered 1d Gonzalo Drywall 2 weeks Gonzalo Measure For Carpet 1d Flatwork 3 days Porches 3 days Fence 4 days Steel Guard As-Built Survey 1d BG Development As-Built Survey Milestone BG Development Canopy Roof 1d Dusable Finish Phase Rough Paint 2 days DK Profile Rough Paint Milestone BG Development Electric Trim 2 days Trim Carpentry 1 week BG Trim Order Dishwasher and Hood 1d BG Punchlist Manager Install Dishwasher 1d BG Site Crew Trim Paint 2 days DK Profile Shelving 1d Chicago Closet HVAC Trim 1d Air Rite Install Hood 1d BG Trim Plumbing Trim 1d Dee Electric: Hook up Disposal, Dishwasher, Doorbell, Hood 1d Water Meter 1d Dee Water Meter Sensor 1d City Water Dept Carpet 1d Abel Installs Doors and Locks 2 days BG Trim Final Inspections Inspection: Final Electric 1d Inspection: Final Plumbing 1d Inspection: Final HVAC 1d Inspection: New Construction 1d? Punchlist to Close Development Walk 1d BG Development Complete 1st Punchlist 1 week BG Punchlist Manager 1st Homeowner's Walk Window 1 week BG Punchlist Complete Final Punchlist 2 weeks BG Punchlist Manager Homowner's Final Walk 1d BG Punchlist 26 27 28 29 30 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 WK 35, August 2015 WK 36, September 2015 WK 37, September 2015 WK 38, September 2015 WK 39, September 2015 WK 40, October 2015 WK 41, October 2015 WK 42, October 2015 WK 43, October 2015 WK 44, October 2015 WK 45, November 2015 WK 46, November 2015 WK 47, November 2015 WK 48, November 2015 WK 49, December 2015 WK 50, December 2015 WK 51, December 2015 WK 52, December 2015 0 Merlin Single Family Project Te… 9/3/15 12/22/15 Inspector:… 0% 1 Excavation to Framing Phase 9/3/15 10/8/15 ComEd; BG… 0% 2 Administrative 9/3/15 9/3/15 People's G… 0% 3 Plans & Permit to Plumber 1d 9/3/15 9/3/15 BG Schedul… 0% 5 Gas Application 1d 9/3/15 9/3/15 People's Gas 0% 7 Review Survey 1d 9/3/15 9/3/15 BG Schedul… 0% 9 Excavation 1d 9/3/15 9/3/15 0% 10 Start Date Milestone 9/3/15 9/3/15 BG Develop… 0% 12 Footer 1d 9/4/15 9/4/15 0% 13 Foundation 3d 9/7/15 9/9/15 0% 14 Backfill & Stone 1d 9/10/15 9/10/15 0% 15 Underground HVAC (BLAB) 1d 9/11/15 9/11/15 Air Rite 0% 17 Inspection: Underground HVAC (… 4d 9/14/15 9/17/15 Inspector:… 0% 19 Underground Plumbing 1d 9/14/15 9/14/15 Dee Plumbing 0% 21 Inspection: Undeground Plumbing 4d 9/15/15 9/16/15 Inspector:… 0% 24 Slab 2d 9/17/15 9/18/15 0% 25 Sewer/Water Tap 3d 9/11/15 9/15/15 Dee Plumbing 0% 27 Gas Line Run 2d 9/11/15 9/14/15 People's Gas 0% 29 Framing 10d 9/21/15 10/2/15 0% 30 Inspection: Framing 4d 10/5/15 10/8/15 Inspector:… 0% 32 Contact ComEd 1d 10/5/15 10/5/15 ComEd 0% 34 Electric Service Installed 1d 10/6/15 10/6/15 0% 35 Electric Meter Installed 1d 10/7/15 10/7/15 ComEd 0% 37 Mechanicals to Drywall Phase 10/5/15 11/4/15 Inspector:… 0% 38 HVAC Rough 2d 10/5/15 10/6/15 Air Rite 0% 40 Inspection: HVAC Rough 4d 10/7/15 10/12/15 0% 41 Mechanicals Milestone 10/5/15 10/5/15 BG Develop… 0% 43 Install Alarm 1d 10/7/15 10/7/15 BG Site Guys 0% 45 Plumbing Rough 2d 10/6/15 10/7/15 Dee Plumbing 0% 47 Roof 1d 10/8/15 10/8/15 Dusable 0% 49 Inspection: Plumbing Rough 4d 10/8/15 10/9/15 Inspector:… 0% 52 Spray Copper 1d 10/8/15 10/8/15 BG Site Guys 0% 54 Gas Meter 1d 10/8/15 10/8/15 People's Gas 0% 56 Electric Rough 3d 10/8/15 10/12/15 0% 57 Inspection: Electric Rough 4d 10/13/15 10/16/15 Inspector:… 0% 59 Masonry 5d 10/12/15 10/16/15 Superior M… 0% 61 Install Rain Barrel 1d 10/19/15 10/19/15 0% 62 Siding 2d 10/20/15 10/21/15 Dusable 0% 64 Insulation 2d 10/19/15 10/20/15 BG Insulation 0% 66 Drywall Delivered 1d 10/21/15 10/21/15 Gonzalo 0% 68 Drywall 10d 10/21/15 11/3/15 Gonzalo 0% 70 Measure For Carpet 1d 11/4/15 11/4/15 0% 71 Flatwork 3d 10/22/15 10/26/15 0% 72 Porches 3d 10/27/15 10/29/15 0% 73 Fence 4d 10/27/15 10/30/15 Steel Guard 0% 75 As-Built Survey 1d 11/2/15 11/2/15 BG Develop… 0% 77 As-Built Survey Milestone 11/2/15 11/2/15 BG Develop… 0% 79 Canopy Roof 1d 10/30/15 10/30/15 Dusable 0% 81 Finish Phase 11/5/15 12/22/15 D & K Profi… 0% 82 Rough Paint 2d 11/5/15 11/6/15 D & K Profil… 0% 84 Rough Paint Milestone 11/5/15 11/5/15 BG Develop… 0% 86 Electric Trim 2d 11/5/15 11/6/15 0% 87 Trim Carpentry 5d 11/9/15 11/13/15 BG Trim 0% 89 Order Dishwasher and Hood 1d 11/9/15 11/9/15 BG Punchlis… 0% 91 Install Dishwasher 1d 11/11/15 11/11/15 BG Site Guys 0% 93 Trim Paint 2d 11/16/15 11/17/15 D & K Profil… 0% 95 Shelving 1d 11/16/15 11/16/15 Chicago Cl… 0% 97 HVAC Trim 1d 11/16/15 11/16/15 Air Rite 0% 99 Install Hood 1d 11/16/15 11/16/15 BG Trim 0% 101 Plumbing Trim 1d 11/17/15 11/17/15 Dee Plumbing 0% 103 Electric: Hook up Disposal, Dish… 1d 11/18/15 11/18/15 0% 104 Water Meter 1d 11/18/15 11/18/15 Dee Plumbing 0% 106 Water Meter Sensor 1d 11/18/15 11/18/15 Chicago Wa… 0% 108 Carpet 1d 11/18/15 11/18/15 Abel Carpet 0% 110 Installs Doors and Locks 2d 11/19/15 11/20/15 BG Trim 0% 112 Final Inspections 11/23/15 11/23/15 0% 113 Inspection: Final Electric 1d 11/23/15 11/23/15 0% 114 Inspection: Final Plumbing 1d 11/23/15 11/23/15 0% 115 Inspection: Final HVAC 1d 11/23/15 11/23/15 0% 116 Inspection: New Construction 1d? 11/23/15 11/23/15 0% 117 Punchlist to Close 11/23/15 12/22/15 BG Develo… 0% 118 Development Walk 1d 11/23/15 11/23/15 BG Develop… 0% 120 Complete 1st Punchlist 5d 11/24/15 11/30/15 BG Punchlis… 0% 122 1st Homeowner's Walk Window 5d 12/1/15 12/7/15 BG Punchlis… 0% 124 Complete Final Punchlist 10d 12/8/15 12/21/15 BG Punchlis… 0% 126 Homowner's Final Walk 1d 12/22/15 12/22/15 BG Punchlis… 0% % Complete Flag Status Assigned Resources Expected End Expected Start Given Work TitleInf o #