Contenu connexe
Similaire à Single Family Gantt Chart-John Mueller
Similaire à Single Family Gantt Chart-John Mueller (20)
Single Family Gantt Chart-John Mueller
- 1. Merlin Single Family Project Template
Excavation to Framing Phase
Administrative
Plans & Permit to Plumber 1d BG Scheduling
Gas Application 1d People's Gas
Review Survey 1d BG Scheduling
Excavation 1d
Start Date Milestone BG Development
Footer 1d
Foundation 3 days
Backfill & Stone 1d
Underground HVAC (BLAB) 1d Air Rite
Inspection: Underground HVAC (BLAB) 4 days HVAC Insp
Underground Plumbing 1d Dee
Inspection: Undeground Plumbing 2 days Plumb Insp; Dee
Slab 2 days
Sewer/Water Tap 3 days Dee
Gas Line Run 2 days People's Gas
Framing 2 weeks
Inspection: Framing 4 days NC Insp
Contact ComEd 1d ComEd
Electric Service Installed 1d
Electric Meter Installed 1d ComEd
Mechanicals to Drywall Phase
HVAC Rough 2 days Air Rite
Inspection: HVAC Rough 4 days
Mechanicals Milestone BG Development
Install Alarm 1d BG Site Crew
Plumbing Rough 2 days Dee
Roof 1d Dusable
Inspection: Plumbing Rough 2 days Plumb Insp; Dee
Spray Copper 1d BG Site Crew
Gas Meter 1d People's Gas
Electric Rough 3 days
Inspection: Electric Rough 4 days Elect Insp
Masonry 1 week Superior
Install Rain Barrel 1d
Siding 2 days Dusable
Insulation 2 days BG Insulation
Drywall Delivered 1d Gonzalo
Drywall 2 weeks Gonzalo
Measure For Carpet 1d
Flatwork 3 days
Porches 3 days
Fence 4 days Steel Guard
As-Built Survey 1d BG Development
As-Built Survey Milestone BG Development
Canopy Roof 1d Dusable
Finish Phase
Rough Paint 2 days DK Profile
Rough Paint Milestone BG Development
Electric Trim 2 days
Trim Carpentry 1 week BG Trim
Order Dishwasher and Hood 1d BG Punchlist Manager
Install Dishwasher 1d BG Site Crew
Trim Paint 2 days DK Profile
Shelving 1d Chicago Closet
HVAC Trim 1d Air Rite
Install Hood 1d BG Trim
Plumbing Trim 1d Dee
Electric: Hook up Disposal, Dishwasher, Doorbell, Hood 1d
Water Meter 1d Dee
Water Meter Sensor 1d City Water Dept
Carpet 1d Abel
Installs Doors and Locks 2 days BG Trim
Final Inspections
Inspection: Final Electric 1d
Inspection: Final Plumbing 1d
Inspection: Final HVAC 1d
Inspection: New Construction 1d?
Punchlist to Close
Development Walk 1d BG Development
Complete 1st Punchlist 1 week BG Punchlist Manager
1st Homeowner's Walk Window 1 week BG Punchlist
Complete Final Punchlist 2 weeks BG Punchlist Manager
Homowner's Final Walk 1d BG Punchlist
26 27 28 29 30 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
WK 35, August 2015 WK 36, September 2015 WK 37, September 2015 WK 38, September 2015 WK 39, September 2015 WK 40, October 2015 WK 41, October 2015 WK 42, October 2015 WK 43, October 2015 WK 44, October 2015 WK 45, November 2015 WK 46, November 2015 WK 47, November 2015 WK 48, November 2015 WK 49, December 2015 WK 50, December 2015 WK 51, December 2015 WK 52, December 2015
0 Merlin Single Family Project Te… 9/3/15 12/22/15 Inspector:… 0%
1 Excavation to Framing Phase 9/3/15 10/8/15 ComEd; BG… 0%
2 Administrative 9/3/15 9/3/15 People's G… 0%
3 Plans & Permit to Plumber 1d 9/3/15 9/3/15 BG Schedul… 0%
5 Gas Application 1d 9/3/15 9/3/15 People's Gas 0%
7 Review Survey 1d 9/3/15 9/3/15 BG Schedul… 0%
9 Excavation 1d 9/3/15 9/3/15 0%
10 Start Date Milestone 9/3/15 9/3/15 BG Develop… 0%
12 Footer 1d 9/4/15 9/4/15 0%
13 Foundation 3d 9/7/15 9/9/15 0%
14 Backfill & Stone 1d 9/10/15 9/10/15 0%
15 Underground HVAC (BLAB) 1d 9/11/15 9/11/15 Air Rite 0%
17 Inspection: Underground HVAC (… 4d 9/14/15 9/17/15 Inspector:… 0%
19 Underground Plumbing 1d 9/14/15 9/14/15 Dee Plumbing 0%
21 Inspection: Undeground Plumbing 4d 9/15/15 9/16/15 Inspector:… 0%
24 Slab 2d 9/17/15 9/18/15 0%
25 Sewer/Water Tap 3d 9/11/15 9/15/15 Dee Plumbing 0%
27 Gas Line Run 2d 9/11/15 9/14/15 People's Gas 0%
29 Framing 10d 9/21/15 10/2/15 0%
30 Inspection: Framing 4d 10/5/15 10/8/15 Inspector:… 0%
32 Contact ComEd 1d 10/5/15 10/5/15 ComEd 0%
34 Electric Service Installed 1d 10/6/15 10/6/15 0%
35 Electric Meter Installed 1d 10/7/15 10/7/15 ComEd 0%
37 Mechanicals to Drywall Phase 10/5/15 11/4/15 Inspector:… 0%
38 HVAC Rough 2d 10/5/15 10/6/15 Air Rite 0%
40 Inspection: HVAC Rough 4d 10/7/15 10/12/15 0%
41 Mechanicals Milestone 10/5/15 10/5/15 BG Develop… 0%
43 Install Alarm 1d 10/7/15 10/7/15 BG Site Guys 0%
45 Plumbing Rough 2d 10/6/15 10/7/15 Dee Plumbing 0%
47 Roof 1d 10/8/15 10/8/15 Dusable 0%
49 Inspection: Plumbing Rough 4d 10/8/15 10/9/15 Inspector:… 0%
52 Spray Copper 1d 10/8/15 10/8/15 BG Site Guys 0%
54 Gas Meter 1d 10/8/15 10/8/15 People's Gas 0%
56 Electric Rough 3d 10/8/15 10/12/15 0%
57 Inspection: Electric Rough 4d 10/13/15 10/16/15 Inspector:… 0%
59 Masonry 5d 10/12/15 10/16/15 Superior M… 0%
61 Install Rain Barrel 1d 10/19/15 10/19/15 0%
62 Siding 2d 10/20/15 10/21/15 Dusable 0%
64 Insulation 2d 10/19/15 10/20/15 BG Insulation 0%
66 Drywall Delivered 1d 10/21/15 10/21/15 Gonzalo 0%
68 Drywall 10d 10/21/15 11/3/15 Gonzalo 0%
70 Measure For Carpet 1d 11/4/15 11/4/15 0%
71 Flatwork 3d 10/22/15 10/26/15 0%
72 Porches 3d 10/27/15 10/29/15 0%
73 Fence 4d 10/27/15 10/30/15 Steel Guard 0%
75 As-Built Survey 1d 11/2/15 11/2/15 BG Develop… 0%
77 As-Built Survey Milestone 11/2/15 11/2/15 BG Develop… 0%
79 Canopy Roof 1d 10/30/15 10/30/15 Dusable 0%
81 Finish Phase 11/5/15 12/22/15 D & K Profi… 0%
82 Rough Paint 2d 11/5/15 11/6/15 D & K Profil… 0%
84 Rough Paint Milestone 11/5/15 11/5/15 BG Develop… 0%
86 Electric Trim 2d 11/5/15 11/6/15 0%
87 Trim Carpentry 5d 11/9/15 11/13/15 BG Trim 0%
89 Order Dishwasher and Hood 1d 11/9/15 11/9/15 BG Punchlis… 0%
91 Install Dishwasher 1d 11/11/15 11/11/15 BG Site Guys 0%
93 Trim Paint 2d 11/16/15 11/17/15 D & K Profil… 0%
95 Shelving 1d 11/16/15 11/16/15 Chicago Cl… 0%
97 HVAC Trim 1d 11/16/15 11/16/15 Air Rite 0%
99 Install Hood 1d 11/16/15 11/16/15 BG Trim 0%
101 Plumbing Trim 1d 11/17/15 11/17/15 Dee Plumbing 0%
103 Electric: Hook up Disposal, Dish… 1d 11/18/15 11/18/15 0%
104 Water Meter 1d 11/18/15 11/18/15 Dee Plumbing 0%
106 Water Meter Sensor 1d 11/18/15 11/18/15 Chicago Wa… 0%
108 Carpet 1d 11/18/15 11/18/15 Abel Carpet 0%
110 Installs Doors and Locks 2d 11/19/15 11/20/15 BG Trim 0%
112 Final Inspections 11/23/15 11/23/15 0%
113 Inspection: Final Electric 1d 11/23/15 11/23/15 0%
114 Inspection: Final Plumbing 1d 11/23/15 11/23/15 0%
115 Inspection: Final HVAC 1d 11/23/15 11/23/15 0%
116 Inspection: New Construction 1d? 11/23/15 11/23/15 0%
117 Punchlist to Close 11/23/15 12/22/15 BG Develo… 0%
118 Development Walk 1d 11/23/15 11/23/15 BG Develop… 0%
120 Complete 1st Punchlist 5d 11/24/15 11/30/15 BG Punchlis… 0%
122 1st Homeowner's Walk Window 5d 12/1/15 12/7/15 BG Punchlis… 0%
124 Complete Final Punchlist 10d 12/8/15 12/21/15 BG Punchlis… 0%
126 Homowner's Final Walk 1d 12/22/15 12/22/15 BG Punchlis… 0%
%
Complete
Flag
Status
Assigned
Resources
Expected
End
Expected
Start
Given
Work
TitleInf
o
#