SlideShare une entreprise Scribd logo
1  sur  4
Télécharger pour lire hors ligne
Response to 60 Minutes, “Hanford Nuclear Facility Cleanup,” April 30, 2006
At Hanford in Eastern Washington, aside the Columbia River, Bechtel has been working
with the Department of Energy (DOE) since 2000 on the largest environmental cleanup
project in U.S. history – to safely dispose of 53 million gallons of highly radioactive
waste left over from the production of nuclear weapons during the Cold War.
Bechtel is building the world’s biggest and most technically sophisticated radiochemical
plant to sort the waste and encase it in glass so it can be permanently isolated from the
environment. This Waste Treatment Plant (WTP) will safeguard the people of
Washington by preventing these dangerous materials seeping out of temporary storage,
migrating through groundwater, and polluting the Columbia River.
On April 30, 2006, CBS 60 Minutes charged that “the U.S. government has botched the
clean-up.” It also claimed that Bechtel ignored warnings about the need to upgrade
seismic design standards, knowingly accepted defective processing tanks from a
manufacturer, and wasted hundreds of millions of dollars and years of effort by pushing a
“fast-track” approach to building before engineering was complete.
But to make its case, 60 Minutes misrepresented well-known facts, confused basic issues,
and drew unwarranted conclusions that could mislead the public and decision makers if
left unchallenged. It is remarkable that with all the investigative resources at their
disposal, 60 Minutes failed to shed light on the real issues that have made WTP such a
challenging project.
The seismic issue
The impact of changing seismic criteria on the project has long been a matter of public
record. The original ground motion criteria for the design were reviewed by numerous
independent experts and provided to Bechtel by DOE as part of its contract in 2000.
Bechtel did not independently evaluate those criteria but advised that any substantive
increase in predicted ground motion would have a significant impact on the design and
therefore the overall cost and schedule of the project.
One reviewing agency, the Defense Nuclear Facilities Safety Board, requested more
information about the characteristics of the soils under the WTP. After considerable
debate among experts, DOE decided to commission a study in early 2004, which resulted
in the department’s decision to increase the seismic requirements by nearly 40 percent.
Because its original plant design was conservative, Bechtel did not have to remove or
redo any construction work. But prudence dictated that we review tens of thousands of
design documents to ensure they meet the new standard. That’s not a mistake—it’s the
price of getting things right as scientific understanding of a complex issue has evolved.
Contrary to Leslie Stahl’s claim on 60 Minutes, this cost increase has absolutely nothing
to do with “pushing ahead with construction before the engineering is complete.”
The submerged bed scrubber vessel
60 Minutes also offered a misleading account of issues surrounding the quality of
stainless-steel tanks fabricated by an outside vendor for WTP and installed in November
2003 to hold and process radioactive wastes.
Stahl claimed that deficient welds in the vessel were missed by Bechtel and discovered
only “by independent inspectors for Washington state.” Not true. As documents available
to 60 Minutes clearly show, the inspector was a subcontractor to Bechtel, responsible for
helping to ensure that we comply with state environmental permits.
His careful checks were part of a system of multiple inspections and procedures that
Bechtel uses to catch engineering, procurement, or construction problems. We discovered
quality problems, we reported them to the Department of Energy, and we ensured that the
vendor fixed the defects. We also changed the procurement specifications to prevent
problems with other vessels and we strengthened our supplier quality program. Work on
the vessel was completed and accepted by DOE in July 2004. The claim of one WTP
critic quoted at length on 60 Minutes—that design and construction flaws on the scrubber
vessel prove that Bechtel and DOE both “failed”—is flatly contradicted by the record.
The same critic, Tom Carpenter of the Government Accountability Project, also claimed
that Bechtel “demanded” and received a $15 million “bonus” for installing the vessel,
implying that DOE must have been asleep at the switch to have rewarded such allegedly
poor performance. As Carpenter’s own documents show, the payment was simply a
contractual fee, not a special bonus, for reaching an agreed construction milestone on the
project. Under the terms of the contract, Bechtel had no deadline incentive to rush the
job. Stahl did note Bechtel’s clarification that the payment was a fee, but provided no
context or explanation, which left viewers to see it simply as a semantic distinction
without a difference.
“Fast-track” construction
The overarching thesis of the 60 Minutes show was that a mindless contractor, overseen
by an inept agency, has “squandered billions of dollars in taxpayers’ money” and years of
time by rushing to build major facilities before they are fully designed. Evidently the
producers were intent on justifying the show’s previous reporting on WTP; as Stahl
reminded viewers, “Fast track was singled out as a major problem five years ago when
we last reported on the cleanup.”
“Fast track,” Stahl explained, is the “practice of pushing ahead with construction before
the engineering is complete.” As noted above, the changed seismic criteria and the vessel
flaws were not caused by fast tracking the project. Remarkably, the only example Stahl
offered of a “fast-track” fiasco had nothing to do with WTP. It consisted of a nameless
building “at a similar site in Idaho,” allegedly constructed too small to hold the
equipment it was meant to house. In other words, a different place, a different time, a
different project, a different contractor.
The process used by Bechtel at WTP is commonly referred to as “design-build.” This
integration of engineering and construction is the industry approach of choice for a
complex nuclear project like WTP. Proper integration means that the design of a
particular component of an overall facility is completed before construction of that
component so that there is minimal risk of construction rework and inefficient starts and
stops. It does allow construction to begin before the entire facility is designed. Bechtel
and most other major contractors use this optimized design-build approach on projects
worldwide because it delivers projects faster and at less cost.
As of December 2005, design on the project was more than 60 percent done, more than
40 percent of the materials had been purchased and construction was more than 25
percent complete. If the design-build approach were not used for WTP:
• The facility would still be in a phase of design and redesign.
• There would have been no procurement or construction progress and the facility
would be 15-20 years from plant startup.
• There would still be no experience with the nuclear quality supply chain
challenges and as a result, the cost estimate would still be an order of magnitude
understated.
The design-build approach on WTP has worked. It has led to an earlier understanding of
what it will really cost to deliver this plant. And because of proper integration between
design and construction, all of the construction to date is sound.
The real issues
WTP has faced a number of serious issues, all ignored by 60 Minutes. The project team
has had to overcome dozens of major technical challenges in designing the world’s
largest and most complex radioactive waste processing plant. It has had to help revive the
nation’s atrophied nuclear industry production infrastructure and train a new generation
of employees to work to nuclear standards, as no major nuclear facility has been built in
the United States in over 20 years. It has struggled to anticipate the soaring cost of
equipment and supplies over the past few years.
As Tom Hash, chairman of Bechtel National, Inc., testified before a congressional panel
in April 2006, “In hindsight, the challenges were bigger than we expected. It has taken us
several years of experience—while overcoming major technical hurdles—to know
enough to forecast the likely cost and duration of this vital project.” But thanks to
Bechtel’s commissioning of two teams of industry and academic experts last year to
evaluate future technical risks and cost-and-schedule estimates, DOE and Congress now
have far greater assurances that the project faces no insurmountable technical hurdles and
that current estimates are defensible.
(http://www.bechtel.com/PDF/WTP_written_testimony.pdf)
Bechtel, DOE, and 60 Minutes at least see eye-to-eye on one issue: Nothing must stand in
the way of protecting public health and safety. As Christine Gregoire, governor of
Washington, concluded on camera, “the last thing we need is to send a message to this
country that it’s okay to walk away. It is not. . . . We need to get going.”

Contenu connexe

En vedette

Conociendo las señales de transito
Conociendo las señales de transitoConociendo las señales de transito
Conociendo las señales de transitoGayaYbarra
 
Vitalité des musiques électroniques en Ile de France
Vitalité des musiques électroniques en Ile de FranceVitalité des musiques électroniques en Ile de France
Vitalité des musiques électroniques en Ile de FranceChristophe Vix-Gras
 
Liz Ward apis - travel tech - 14 sep 2013
Liz Ward   apis - travel tech - 14 sep 2013Liz Ward   apis - travel tech - 14 sep 2013
Liz Ward apis - travel tech - 14 sep 2013Liz Ward
 
Marily trabajo de contabilidad
Marily trabajo de contabilidadMarily trabajo de contabilidad
Marily trabajo de contabilidadmarilydjls
 
Speaking Out Spring 2014 low res
Speaking Out Spring 2014 low resSpeaking Out Spring 2014 low res
Speaking Out Spring 2014 low resSteven Halliday
 
Scala-Continuation
Scala-ContinuationScala-Continuation
Scala-Continuation성주 봉
 
El sistema operativo
El sistema operativoEl sistema operativo
El sistema operativogianellablog
 
Document
DocumentDocument
DocumentBoquera
 
Cadth 2015 c5 4. harkins.cadth.symposium.2015
Cadth 2015 c5 4. harkins.cadth.symposium.2015Cadth 2015 c5 4. harkins.cadth.symposium.2015
Cadth 2015 c5 4. harkins.cadth.symposium.2015CADTH Symposium
 
Cuban power werner
Cuban power wernerCuban power werner
Cuban power wernerpu5hok
 
NUESTRO CONGRESO EN IMAGENES
NUESTRO CONGRESO EN IMAGENESNUESTRO CONGRESO EN IMAGENES
NUESTRO CONGRESO EN IMAGENESASPM
 
Powerpoint midterm 1
Powerpoint midterm 1Powerpoint midterm 1
Powerpoint midterm 1studioart
 
Recurso la fotografia y camara digital pdf
Recurso la fotografia y camara digital pdfRecurso la fotografia y camara digital pdf
Recurso la fotografia y camara digital pdfYessica Paniagua
 
Android Testing Talk by Rebootd v2
Android Testing Talk by Rebootd v2Android Testing Talk by Rebootd v2
Android Testing Talk by Rebootd v2Re Bootd
 
Mi primera presentacion en slides
Mi primera presentacion en slidesMi primera presentacion en slides
Mi primera presentacion en slidespat9461
 

En vedette (19)

Conociendo las señales de transito
Conociendo las señales de transitoConociendo las señales de transito
Conociendo las señales de transito
 
Vitalité des musiques électroniques en Ile de France
Vitalité des musiques électroniques en Ile de FranceVitalité des musiques électroniques en Ile de France
Vitalité des musiques électroniques en Ile de France
 
ejemplo
ejemploejemplo
ejemplo
 
Liz Ward apis - travel tech - 14 sep 2013
Liz Ward   apis - travel tech - 14 sep 2013Liz Ward   apis - travel tech - 14 sep 2013
Liz Ward apis - travel tech - 14 sep 2013
 
Marily trabajo de contabilidad
Marily trabajo de contabilidadMarily trabajo de contabilidad
Marily trabajo de contabilidad
 
Hoja de vida
Hoja de vidaHoja de vida
Hoja de vida
 
Speaking Out Spring 2014 low res
Speaking Out Spring 2014 low resSpeaking Out Spring 2014 low res
Speaking Out Spring 2014 low res
 
Scala-Continuation
Scala-ContinuationScala-Continuation
Scala-Continuation
 
El sistema operativo
El sistema operativoEl sistema operativo
El sistema operativo
 
J2000
J2000J2000
J2000
 
Document
DocumentDocument
Document
 
Cadth 2015 c5 4. harkins.cadth.symposium.2015
Cadth 2015 c5 4. harkins.cadth.symposium.2015Cadth 2015 c5 4. harkins.cadth.symposium.2015
Cadth 2015 c5 4. harkins.cadth.symposium.2015
 
Fachadaaaa
FachadaaaaFachadaaaa
Fachadaaaa
 
Cuban power werner
Cuban power wernerCuban power werner
Cuban power werner
 
NUESTRO CONGRESO EN IMAGENES
NUESTRO CONGRESO EN IMAGENESNUESTRO CONGRESO EN IMAGENES
NUESTRO CONGRESO EN IMAGENES
 
Powerpoint midterm 1
Powerpoint midterm 1Powerpoint midterm 1
Powerpoint midterm 1
 
Recurso la fotografia y camara digital pdf
Recurso la fotografia y camara digital pdfRecurso la fotografia y camara digital pdf
Recurso la fotografia y camara digital pdf
 
Android Testing Talk by Rebootd v2
Android Testing Talk by Rebootd v2Android Testing Talk by Rebootd v2
Android Testing Talk by Rebootd v2
 
Mi primera presentacion en slides
Mi primera presentacion en slidesMi primera presentacion en slides
Mi primera presentacion en slides
 

Similaire à WTP_Response-to-60-Minutes(1)

CARGILLPROJOVERVIEW_rev1
CARGILLPROJOVERVIEW_rev1CARGILLPROJOVERVIEW_rev1
CARGILLPROJOVERVIEW_rev1Dan Caouette
 
2007 Koomey talk on historical costs of nuclear power in the US
2007 Koomey talk on historical costs of nuclear power in the US2007 Koomey talk on historical costs of nuclear power in the US
2007 Koomey talk on historical costs of nuclear power in the USJonathan Koomey
 
White Paper: Shell Petrochemical Complex (“Cracker”) Project Overview
White Paper: Shell Petrochemical Complex (“Cracker”) Project OverviewWhite Paper: Shell Petrochemical Complex (“Cracker”) Project Overview
White Paper: Shell Petrochemical Complex (“Cracker”) Project OverviewMarcellus Drilling News
 
Delay Claims Mitigation for US Nuclear Power Plant Construction
Delay Claims Mitigation for US Nuclear Power Plant ConstructionDelay Claims Mitigation for US Nuclear Power Plant Construction
Delay Claims Mitigation for US Nuclear Power Plant ConstructionCharles Fournier
 
1.Use the following information to answer parts athrough h. Desc
1.Use the following information to answer parts athrough h. Desc1.Use the following information to answer parts athrough h. Desc
1.Use the following information to answer parts athrough h. Descdrennanmicah
 
Battelle Review of EPA Fracking Study Plan
Battelle Review of EPA Fracking Study PlanBattelle Review of EPA Fracking Study Plan
Battelle Review of EPA Fracking Study PlanMarcellus Drilling News
 
Case Study :: Small Wind Turbines in the Built Environment Decommissioning Guide
Case Study :: Small Wind Turbines in the Built Environment Decommissioning GuideCase Study :: Small Wind Turbines in the Built Environment Decommissioning Guide
Case Study :: Small Wind Turbines in the Built Environment Decommissioning GuideKimberly L. King
 
03/05: Multi-Industry Permit Streamlining Letter
03/05: Multi-Industry Permit Streamlining Letter03/05: Multi-Industry Permit Streamlining Letter
03/05: Multi-Industry Permit Streamlining Letterartba
 
Coating Solution Water Presentation
Coating Solution Water PresentationCoating Solution Water Presentation
Coating Solution Water PresentationFortGroup
 
Coating solution forum water
Coating solution forum waterCoating solution forum water
Coating solution forum waterFortGroup
 
Heal The Bay - Draft Environmental Impact Report Comments - Hermosa Beach Oil...
Heal The Bay - Draft Environmental Impact Report Comments - Hermosa Beach Oil...Heal The Bay - Draft Environmental Impact Report Comments - Hermosa Beach Oil...
Heal The Bay - Draft Environmental Impact Report Comments - Hermosa Beach Oil...StopHermosaBeachOil
 
Solar oven-development test-report
Solar oven-development test-reportSolar oven-development test-report
Solar oven-development test-reportH Janardan Prabhu
 
Electricity Journal Article
Electricity Journal ArticleElectricity Journal Article
Electricity Journal Articlejcarter1972
 
What can we learn from the hoover dam
What can we learn from the hoover damWhat can we learn from the hoover dam
What can we learn from the hoover damJasmine Tung
 

Similaire à WTP_Response-to-60-Minutes(1) (20)

CARGILLPROJOVERVIEW_rev1
CARGILLPROJOVERVIEW_rev1CARGILLPROJOVERVIEW_rev1
CARGILLPROJOVERVIEW_rev1
 
2007 Koomey talk on historical costs of nuclear power in the US
2007 Koomey talk on historical costs of nuclear power in the US2007 Koomey talk on historical costs of nuclear power in the US
2007 Koomey talk on historical costs of nuclear power in the US
 
White Paper: Shell Petrochemical Complex (“Cracker”) Project Overview
White Paper: Shell Petrochemical Complex (“Cracker”) Project OverviewWhite Paper: Shell Petrochemical Complex (“Cracker”) Project Overview
White Paper: Shell Petrochemical Complex (“Cracker”) Project Overview
 
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update March 12, ...
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update March 12, ...Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update March 12, ...
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update March 12, ...
 
Delay Claims Mitigation for US Nuclear Power Plant Construction
Delay Claims Mitigation for US Nuclear Power Plant ConstructionDelay Claims Mitigation for US Nuclear Power Plant Construction
Delay Claims Mitigation for US Nuclear Power Plant Construction
 
projects
projectsprojects
projects
 
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update March 12...
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update March 12...Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update March 12...
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update March 12...
 
1.Use the following information to answer parts athrough h. Desc
1.Use the following information to answer parts athrough h. Desc1.Use the following information to answer parts athrough h. Desc
1.Use the following information to answer parts athrough h. Desc
 
Gds Trans Actions Vol411
Gds Trans Actions Vol411Gds Trans Actions Vol411
Gds Trans Actions Vol411
 
Battelle Review of EPA Fracking Study Plan
Battelle Review of EPA Fracking Study PlanBattelle Review of EPA Fracking Study Plan
Battelle Review of EPA Fracking Study Plan
 
Case Study :: Small Wind Turbines in the Built Environment Decommissioning Guide
Case Study :: Small Wind Turbines in the Built Environment Decommissioning GuideCase Study :: Small Wind Turbines in the Built Environment Decommissioning Guide
Case Study :: Small Wind Turbines in the Built Environment Decommissioning Guide
 
03/05: Multi-Industry Permit Streamlining Letter
03/05: Multi-Industry Permit Streamlining Letter03/05: Multi-Industry Permit Streamlining Letter
03/05: Multi-Industry Permit Streamlining Letter
 
51664
5166451664
51664
 
Coating Solution Water Presentation
Coating Solution Water PresentationCoating Solution Water Presentation
Coating Solution Water Presentation
 
Coating solution forum water
Coating solution forum waterCoating solution forum water
Coating solution forum water
 
Heal The Bay - Draft Environmental Impact Report Comments - Hermosa Beach Oil...
Heal The Bay - Draft Environmental Impact Report Comments - Hermosa Beach Oil...Heal The Bay - Draft Environmental Impact Report Comments - Hermosa Beach Oil...
Heal The Bay - Draft Environmental Impact Report Comments - Hermosa Beach Oil...
 
Solar oven-development test-report
Solar oven-development test-reportSolar oven-development test-report
Solar oven-development test-report
 
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update June 4, ...
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update June 4, ...Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update June 4, ...
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update June 4, ...
 
Electricity Journal Article
Electricity Journal ArticleElectricity Journal Article
Electricity Journal Article
 
What can we learn from the hoover dam
What can we learn from the hoover damWhat can we learn from the hoover dam
What can we learn from the hoover dam
 

WTP_Response-to-60-Minutes(1)

  • 1. Response to 60 Minutes, “Hanford Nuclear Facility Cleanup,” April 30, 2006 At Hanford in Eastern Washington, aside the Columbia River, Bechtel has been working with the Department of Energy (DOE) since 2000 on the largest environmental cleanup project in U.S. history – to safely dispose of 53 million gallons of highly radioactive waste left over from the production of nuclear weapons during the Cold War. Bechtel is building the world’s biggest and most technically sophisticated radiochemical plant to sort the waste and encase it in glass so it can be permanently isolated from the environment. This Waste Treatment Plant (WTP) will safeguard the people of Washington by preventing these dangerous materials seeping out of temporary storage, migrating through groundwater, and polluting the Columbia River. On April 30, 2006, CBS 60 Minutes charged that “the U.S. government has botched the clean-up.” It also claimed that Bechtel ignored warnings about the need to upgrade seismic design standards, knowingly accepted defective processing tanks from a manufacturer, and wasted hundreds of millions of dollars and years of effort by pushing a “fast-track” approach to building before engineering was complete. But to make its case, 60 Minutes misrepresented well-known facts, confused basic issues, and drew unwarranted conclusions that could mislead the public and decision makers if left unchallenged. It is remarkable that with all the investigative resources at their disposal, 60 Minutes failed to shed light on the real issues that have made WTP such a challenging project. The seismic issue The impact of changing seismic criteria on the project has long been a matter of public record. The original ground motion criteria for the design were reviewed by numerous independent experts and provided to Bechtel by DOE as part of its contract in 2000. Bechtel did not independently evaluate those criteria but advised that any substantive increase in predicted ground motion would have a significant impact on the design and therefore the overall cost and schedule of the project. One reviewing agency, the Defense Nuclear Facilities Safety Board, requested more information about the characteristics of the soils under the WTP. After considerable debate among experts, DOE decided to commission a study in early 2004, which resulted in the department’s decision to increase the seismic requirements by nearly 40 percent. Because its original plant design was conservative, Bechtel did not have to remove or redo any construction work. But prudence dictated that we review tens of thousands of design documents to ensure they meet the new standard. That’s not a mistake—it’s the price of getting things right as scientific understanding of a complex issue has evolved. Contrary to Leslie Stahl’s claim on 60 Minutes, this cost increase has absolutely nothing to do with “pushing ahead with construction before the engineering is complete.”
  • 2. The submerged bed scrubber vessel 60 Minutes also offered a misleading account of issues surrounding the quality of stainless-steel tanks fabricated by an outside vendor for WTP and installed in November 2003 to hold and process radioactive wastes. Stahl claimed that deficient welds in the vessel were missed by Bechtel and discovered only “by independent inspectors for Washington state.” Not true. As documents available to 60 Minutes clearly show, the inspector was a subcontractor to Bechtel, responsible for helping to ensure that we comply with state environmental permits. His careful checks were part of a system of multiple inspections and procedures that Bechtel uses to catch engineering, procurement, or construction problems. We discovered quality problems, we reported them to the Department of Energy, and we ensured that the vendor fixed the defects. We also changed the procurement specifications to prevent problems with other vessels and we strengthened our supplier quality program. Work on the vessel was completed and accepted by DOE in July 2004. The claim of one WTP critic quoted at length on 60 Minutes—that design and construction flaws on the scrubber vessel prove that Bechtel and DOE both “failed”—is flatly contradicted by the record. The same critic, Tom Carpenter of the Government Accountability Project, also claimed that Bechtel “demanded” and received a $15 million “bonus” for installing the vessel, implying that DOE must have been asleep at the switch to have rewarded such allegedly poor performance. As Carpenter’s own documents show, the payment was simply a contractual fee, not a special bonus, for reaching an agreed construction milestone on the project. Under the terms of the contract, Bechtel had no deadline incentive to rush the job. Stahl did note Bechtel’s clarification that the payment was a fee, but provided no context or explanation, which left viewers to see it simply as a semantic distinction without a difference. “Fast-track” construction The overarching thesis of the 60 Minutes show was that a mindless contractor, overseen by an inept agency, has “squandered billions of dollars in taxpayers’ money” and years of time by rushing to build major facilities before they are fully designed. Evidently the producers were intent on justifying the show’s previous reporting on WTP; as Stahl reminded viewers, “Fast track was singled out as a major problem five years ago when we last reported on the cleanup.” “Fast track,” Stahl explained, is the “practice of pushing ahead with construction before the engineering is complete.” As noted above, the changed seismic criteria and the vessel flaws were not caused by fast tracking the project. Remarkably, the only example Stahl offered of a “fast-track” fiasco had nothing to do with WTP. It consisted of a nameless building “at a similar site in Idaho,” allegedly constructed too small to hold the equipment it was meant to house. In other words, a different place, a different time, a different project, a different contractor.
  • 3. The process used by Bechtel at WTP is commonly referred to as “design-build.” This integration of engineering and construction is the industry approach of choice for a complex nuclear project like WTP. Proper integration means that the design of a particular component of an overall facility is completed before construction of that component so that there is minimal risk of construction rework and inefficient starts and stops. It does allow construction to begin before the entire facility is designed. Bechtel and most other major contractors use this optimized design-build approach on projects worldwide because it delivers projects faster and at less cost. As of December 2005, design on the project was more than 60 percent done, more than 40 percent of the materials had been purchased and construction was more than 25 percent complete. If the design-build approach were not used for WTP: • The facility would still be in a phase of design and redesign. • There would have been no procurement or construction progress and the facility would be 15-20 years from plant startup. • There would still be no experience with the nuclear quality supply chain challenges and as a result, the cost estimate would still be an order of magnitude understated. The design-build approach on WTP has worked. It has led to an earlier understanding of what it will really cost to deliver this plant. And because of proper integration between design and construction, all of the construction to date is sound. The real issues WTP has faced a number of serious issues, all ignored by 60 Minutes. The project team has had to overcome dozens of major technical challenges in designing the world’s largest and most complex radioactive waste processing plant. It has had to help revive the nation’s atrophied nuclear industry production infrastructure and train a new generation of employees to work to nuclear standards, as no major nuclear facility has been built in the United States in over 20 years. It has struggled to anticipate the soaring cost of equipment and supplies over the past few years. As Tom Hash, chairman of Bechtel National, Inc., testified before a congressional panel in April 2006, “In hindsight, the challenges were bigger than we expected. It has taken us several years of experience—while overcoming major technical hurdles—to know enough to forecast the likely cost and duration of this vital project.” But thanks to Bechtel’s commissioning of two teams of industry and academic experts last year to evaluate future technical risks and cost-and-schedule estimates, DOE and Congress now have far greater assurances that the project faces no insurmountable technical hurdles and that current estimates are defensible. (http://www.bechtel.com/PDF/WTP_written_testimony.pdf)
  • 4. Bechtel, DOE, and 60 Minutes at least see eye-to-eye on one issue: Nothing must stand in the way of protecting public health and safety. As Christine Gregoire, governor of Washington, concluded on camera, “the last thing we need is to send a message to this country that it’s okay to walk away. It is not. . . . We need to get going.”