LINE SIZING
Liquid Phase Case
Chemical Engineer
Juan Pablo Hernández Castillo
PROCESS ENGINEERS TASKS
 Process engineers play an important role in the design of plants.
Some of the most common activities process engineers do are relating to:
1. Design of pipelines
2. Design of equipments
3. Design of instruments, such as control and safety relieve valves.
4. P&ID’s construction
5. Design of control strategy of differents parts of the plant.
6. Checking As Built’s
7. Design of the philosophy of operation of a particular section of the plant.
Among others…
Today, i would like to share with all of you, the steps taken into account when
designing pipelines.
Currently, one the most known international standard to design pipelines is
provided by the American Petroleum Institute.
API 14E. Recommended Practice for Design and Installation of Offshore
Production Platform Piping Systems.
API 14E design for the following states:
1. Liquid phase
2. Single Phase Gas
3. Gas-Liquid Phase lines.
DESIGN OF PIPELINES
Considerations
 API 14E stablish that in order to have a accurate pipe design, two main
conditions must be met: Velocity and Pressure Drop
 Velocity: In order to avoid
Sedimentation of particles 𝟑
𝐟𝐭
𝐬
Erosion (due to high velocity) 15
𝐟𝐭
𝐬
 Pressure Drop: In order to meet pressure drop conditions.
API stablish 1
𝒑𝒔𝒊
𝟏𝟎𝟎 𝒇𝒕
<
Flow Diagram
Example
 A process engineer is asked to design a pump
which can transport water from one deposit to
another.
PARAMETER SYMBOL VALUE UNIT
TEMPERATURE T 77 °F
VISCOSITY µ 1,85E-05 lb/(ft.s)
DENSITY ρ 1,92 slugs/ft3
SPECIFIC GRAVITY s 1
VOLUMETRIC FLOW RATE 2 ft3/s
30776,9031 barrels/day
PIPE LENGHT L 60 ft
PIPE ROUGHNESS ε 1,50E-04 ft
PUMP EFICCIENCY %
POTENTIAL HEAD ∆z 50 ft
SPECIFIC WEIGHT γ 62,2 lb/ft3
Q
INITIAL DATA
Assumptions
 The area in which the system is located : Industry sector
 1 Month= 30 days
 The system works 24h/30 days/1 year
 Average kWh (according to CREG) =$599,722 COP
 Suction and discharge same pipe size
 Comercial Steel Schedule 40 and Schedule 80 design try
 Pipeline lenght of 60 ft
Results
For Schedule 40 Comercial Steel:
For Schedule 80 Comercial Steel:
V(ft/s) Elbows Valves Line
1 231,41 1154,72 6543,42 10836,53 18534,6789 18584,6789 19417 3134,56224 $ 4.901.665 $ 18.136.160.855
2 59,60 63,28 358,57 312,51 734,354596 784,354596 560 132,292212 $ 200.029 $ 740.108.907
3 27,05 12,35 69,99 40,35 122,686563 172,686563 72,29 29,1259687 $ 42.695 $ 157.971.260
4 15,71 3,93 22,29 9,97 36,1998787 86,1998787 17,87 14,5387975 $ 20.832 $ 77.077.751
5 10,00 1,50 8,50 3,15 13,1419988 63,1419988 5,64 10,6497683 $ 15.063 $ 55.733.044
6 6,92 0,67 3,82 1,24 5,7340002 55,7340002 2,22 9,40030725 $ 13.223 $ 48.925.559
8 4,00 0,21 1,19 0,31 1,7113024 51,7113024 0,56 8,72182383 $ 12.229 $ 45.247.677
10 2,54 0,08 0,48 0,10 0,6638566 50,6638566 0,18 8,54515766 $ 11.972 $ 44.295.237
Nominal Diameter(in)
hL(ft)
∑hL(ft) ha(ft) $COP$(USD)PA(kW)∆P(psi)
∆P(psi) PA(kW) $(USD) $COP
Elbows Valves Line
1 278,05 1666,98 9446,25 17548,38 28661,6114 28711,6114 31443,67 4842,60896 $ 7.610.740 $ 28.159.736.856
2 67,73 81,71 463,04 435,91 980,66872 1030,66872 781,08 173,836484 $ 264.039 $ 976.943.993
3 30,28 15,47 87,67 53,97 157,10938 207,10938 96,70 34,9318513 $ 51.469 $ 190.435.597
4 17,40 4,82 27,33 12,95 45,1058345 95,1058345 23,21 16,0409097 $ 23.076 $ 85.381.495
5 10,99 1,81 10,27 4,01 16,0918776 66,0918776 7,18 11,147306 $ 15.800 $ 58.461.385
6 7,67 0,83 4,69 1,61 7,12831215 57,1283121 2,88 9,63547718 $ 13.570 $ 50.208.479
8 4,38 0,25 1,43 0,39 2,07145528 52,0714553 0,70 8,78256857 $ 12.318 $ 45.576.435
10 2,78 0,10 0,58 0,13 0,8053278 50,8053278 0,23 8,56901872 $ 12.006 $ 44.423.454
ha(ft)V(ft/s)Nominal Diameter
hL(ft)
∑hL(ft)
Analysis
 From the previous results, it must be highlighted that the only schedule pipe which met the
velocity-pressure drop requierements was the Schedule 40.
Schedule 40
 Despite the velocity was aceptable from 5 to 8 in nominal diameter. It was noted that the only
diameter which met the requierement of pressure drop(∆P= below 0,6 psi) was the 8 in pipe.
 In the other hand, it was seen that the proper selection of the pipe size does affects the cost of
operation.
 If for example: A process engineer had chosen a 6 inch pipe without taking into account the
requirements, then the cost of operation would have exceed 994 USD per year of operation.
Schedule 40
 Although 5, 6 and 8 inch diameter did meet the velocity requirements, the pressure drop conditions
were not reached.
Bad decisions during the piping design and pump selection can lead to years of unnecessarily high
cost of operation.
Schedule 40- Conditions analysis
Schedule 40- Cost analysis
REFERENCES
[1] R. Mott, Mecánica de fluidos, Dayton: Pearson, 2006.
[2] A. 14E, Recommended Practice for Design and Installation of Offshore Production Platform
Piping Systems., Washington: American Pretroleum Institute, 1991.
[3] C. d. R. d. E. y. G. (CREG), «TARIFAS DE ENERGÍA ELÉCTRICA ($/kWh) REGULADAS POR LA
COMISIÓN DE REGULACIÓN DE ENERGÍAY GAS (CREG) JUNIO DE 2020,» ENEL CODENSA, 2020.
[4] B. d. l. R. d. Colombia, «Tasa Representativa de Mercado (TRM-Peso por dolar),» Banco de la
Republica de Colombia, Colombia, 2020.
¡THANKS FOR
WATCHING!
 Juan Pablo Hernández Castillo
Contact:
Email: juanpaheca@outlook.es
Cel: +57 304 395 5569
LinkedIn:
www.linkedin.com/in/juanhdezcastillo

Contenu connexe

Tendances

Pressure Relief Devices_Presenation
Pressure Relief Devices_PresenationPressure Relief Devices_Presenation
Pressure Relief Devices_Presenation
sumit handa
 
Simple Piping design
Simple Piping designSimple Piping design
Simple Piping design
Musa Sabri
 
Piping engineering guide
Piping engineering guidePiping engineering guide
Piping engineering guide
ram111eg
 

Tendances (20)

PSV Sizing.pdf
PSV Sizing.pdfPSV Sizing.pdf
PSV Sizing.pdf
 
Pipe line sizing
Pipe line sizingPipe line sizing
Pipe line sizing
 
PSV Sizing - API Based
PSV Sizing - API BasedPSV Sizing - API Based
PSV Sizing - API Based
 
What is MAWP? Difference between MAWP , Design Pressure and Operating Pressure
What is MAWP? Difference between MAWP , Design Pressure and Operating Pressure  What is MAWP? Difference between MAWP , Design Pressure and Operating Pressure
What is MAWP? Difference between MAWP , Design Pressure and Operating Pressure
 
Accumulation and Over-pressure: difference between accumulation and overpressure
Accumulation and Over-pressure: difference between accumulation and overpressureAccumulation and Over-pressure: difference between accumulation and overpressure
Accumulation and Over-pressure: difference between accumulation and overpressure
 
Pressure Relief Devices_Presenation
Pressure Relief Devices_PresenationPressure Relief Devices_Presenation
Pressure Relief Devices_Presenation
 
Simple Piping design
Simple Piping designSimple Piping design
Simple Piping design
 
Selection of Shell and tube heat exchanger (STHE)
Selection of Shell and tube heat exchanger (STHE)Selection of Shell and tube heat exchanger (STHE)
Selection of Shell and tube heat exchanger (STHE)
 
Pressure Safety Valve Sizing - API 520/521/526
Pressure Safety Valve Sizing - API 520/521/526Pressure Safety Valve Sizing - API 520/521/526
Pressure Safety Valve Sizing - API 520/521/526
 
Piping interview
Piping interviewPiping interview
Piping interview
 
Eng handbook crosby pressure relief valve engineering handbook
Eng handbook crosby pressure relief valve engineering handbookEng handbook crosby pressure relief valve engineering handbook
Eng handbook crosby pressure relief valve engineering handbook
 
Basics of two phase flow (gas-liquid) line sizing
Basics of two phase flow (gas-liquid) line sizingBasics of two phase flow (gas-liquid) line sizing
Basics of two phase flow (gas-liquid) line sizing
 
Piping ppt1
Piping ppt1Piping ppt1
Piping ppt1
 
fundamentals of Piping engineering
fundamentals of Piping engineeringfundamentals of Piping engineering
fundamentals of Piping engineering
 
Piping presentation part ii 2
Piping presentation part ii 2Piping presentation part ii 2
Piping presentation part ii 2
 
Design and Rating of Trayed Distillation Columns
Design and Rating  of Trayed Distillation ColumnsDesign and Rating  of Trayed Distillation Columns
Design and Rating of Trayed Distillation Columns
 
Piping engineering guide
Piping engineering guidePiping engineering guide
Piping engineering guide
 
Design of Gas and Oil Separator 2023.pdf
Design of Gas and Oil Separator 2023.pdfDesign of Gas and Oil Separator 2023.pdf
Design of Gas and Oil Separator 2023.pdf
 
Piping basics knowledge
Piping basics knowledgePiping basics knowledge
Piping basics knowledge
 
Api 2000 5th vs 6th final
Api 2000 5th vs 6th finalApi 2000 5th vs 6th final
Api 2000 5th vs 6th final
 

Similaire à Line sizing

Similaire à Line sizing (20)

Cge666 chapter 1-wk 1-2
Cge666 chapter 1-wk 1-2Cge666 chapter 1-wk 1-2
Cge666 chapter 1-wk 1-2
 
Project Management
Project ManagementProject Management
Project Management
 
line sizing-mustang.pdf
line sizing-mustang.pdfline sizing-mustang.pdf
line sizing-mustang.pdf
 
Engineering & Design of Pipe Supports
Engineering & Design of Pipe SupportsEngineering & Design of Pipe Supports
Engineering & Design of Pipe Supports
 
1st lect Fertilizers(1).pptx
1st lect Fertilizers(1).pptx1st lect Fertilizers(1).pptx
1st lect Fertilizers(1).pptx
 
Piping Hydraulics Fluid Flow Selection, Sizing and Troubleshooting
Piping Hydraulics Fluid Flow Selection, Sizing and Troubleshooting Piping Hydraulics Fluid Flow Selection, Sizing and Troubleshooting
Piping Hydraulics Fluid Flow Selection, Sizing and Troubleshooting
 
Plumbing Design
Plumbing DesignPlumbing Design
Plumbing Design
 
07-ENGINEERING_DESIGN_GUIDELINES_instrumentation_sizing_and_selection_rev_web...
07-ENGINEERING_DESIGN_GUIDELINES_instrumentation_sizing_and_selection_rev_web...07-ENGINEERING_DESIGN_GUIDELINES_instrumentation_sizing_and_selection_rev_web...
07-ENGINEERING_DESIGN_GUIDELINES_instrumentation_sizing_and_selection_rev_web...
 
Be project - PRDS (Pressure Reducing And Desuperheater Station)
Be project - PRDS (Pressure Reducing And Desuperheater Station)Be project - PRDS (Pressure Reducing And Desuperheater Station)
Be project - PRDS (Pressure Reducing And Desuperheater Station)
 
Itt grinnell pipe hanger design & engineering 2008
Itt grinnell pipe hanger design & engineering 2008 Itt grinnell pipe hanger design & engineering 2008
Itt grinnell pipe hanger design & engineering 2008
 
Compare cryogenic process
Compare cryogenic processCompare cryogenic process
Compare cryogenic process
 
Chemical_Process_Equipment_2.pptx
Chemical_Process_Equipment_2.pptxChemical_Process_Equipment_2.pptx
Chemical_Process_Equipment_2.pptx
 
ASME Vessels, Pig Launchers, Strainers and More from Sweco Fab
ASME Vessels, Pig Launchers, Strainers and More from Sweco FabASME Vessels, Pig Launchers, Strainers and More from Sweco Fab
ASME Vessels, Pig Launchers, Strainers and More from Sweco Fab
 
Richard-Hock
Richard-HockRichard-Hock
Richard-Hock
 
Engineering design guideline hx rev 3
Engineering design guideline  hx rev 3Engineering design guideline  hx rev 3
Engineering design guideline hx rev 3
 
Pipe Support Engineering & Design - June
Pipe Support Engineering & Design - JunePipe Support Engineering & Design - June
Pipe Support Engineering & Design - June
 
Study of Time Reduction in Manufacturing of Screws Used in Twin Screw Pump
Study of Time Reduction in Manufacturing of Screws Used in Twin Screw PumpStudy of Time Reduction in Manufacturing of Screws Used in Twin Screw Pump
Study of Time Reduction in Manufacturing of Screws Used in Twin Screw Pump
 
Refrigerant Piping Handbook.pdf
Refrigerant Piping Handbook.pdfRefrigerant Piping Handbook.pdf
Refrigerant Piping Handbook.pdf
 
Process Plant design fundementals
Process Plant design fundementalsProcess Plant design fundementals
Process Plant design fundementals
 
Mechanical Constraints on Thermal Design of Shell and Tube Exchangers
Mechanical Constraints on Thermal Design of Shell and Tube ExchangersMechanical Constraints on Thermal Design of Shell and Tube Exchangers
Mechanical Constraints on Thermal Design of Shell and Tube Exchangers
 

Dernier

"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
mphochane1998
 
DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakes
MayuraD1
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
ssuser89054b
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Kandungan 087776558899
 
Verification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptxVerification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptx
chumtiyababu
 
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
jaanualu31
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
Neometrix_Engineering_Pvt_Ltd
 

Dernier (20)

GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLEGEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
 
DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakes
 
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxA CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdf
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech students
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
Verification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptxVerification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptx
 
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptx
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equation
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 
Computer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to ComputersComputer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to Computers
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdf
 

Line sizing

  • 1. LINE SIZING Liquid Phase Case Chemical Engineer Juan Pablo Hernández Castillo
  • 2. PROCESS ENGINEERS TASKS  Process engineers play an important role in the design of plants. Some of the most common activities process engineers do are relating to: 1. Design of pipelines 2. Design of equipments 3. Design of instruments, such as control and safety relieve valves. 4. P&ID’s construction 5. Design of control strategy of differents parts of the plant. 6. Checking As Built’s 7. Design of the philosophy of operation of a particular section of the plant. Among others…
  • 3. Today, i would like to share with all of you, the steps taken into account when designing pipelines. Currently, one the most known international standard to design pipelines is provided by the American Petroleum Institute. API 14E. Recommended Practice for Design and Installation of Offshore Production Platform Piping Systems. API 14E design for the following states: 1. Liquid phase 2. Single Phase Gas 3. Gas-Liquid Phase lines. DESIGN OF PIPELINES
  • 4. Considerations  API 14E stablish that in order to have a accurate pipe design, two main conditions must be met: Velocity and Pressure Drop  Velocity: In order to avoid Sedimentation of particles 𝟑 𝐟𝐭 𝐬 Erosion (due to high velocity) 15 𝐟𝐭 𝐬  Pressure Drop: In order to meet pressure drop conditions. API stablish 1 𝒑𝒔𝒊 𝟏𝟎𝟎 𝒇𝒕 <
  • 6. Example  A process engineer is asked to design a pump which can transport water from one deposit to another. PARAMETER SYMBOL VALUE UNIT TEMPERATURE T 77 °F VISCOSITY µ 1,85E-05 lb/(ft.s) DENSITY ρ 1,92 slugs/ft3 SPECIFIC GRAVITY s 1 VOLUMETRIC FLOW RATE 2 ft3/s 30776,9031 barrels/day PIPE LENGHT L 60 ft PIPE ROUGHNESS ε 1,50E-04 ft PUMP EFICCIENCY % POTENTIAL HEAD ∆z 50 ft SPECIFIC WEIGHT γ 62,2 lb/ft3 Q INITIAL DATA
  • 7. Assumptions  The area in which the system is located : Industry sector  1 Month= 30 days  The system works 24h/30 days/1 year  Average kWh (according to CREG) =$599,722 COP  Suction and discharge same pipe size  Comercial Steel Schedule 40 and Schedule 80 design try  Pipeline lenght of 60 ft
  • 8. Results For Schedule 40 Comercial Steel: For Schedule 80 Comercial Steel: V(ft/s) Elbows Valves Line 1 231,41 1154,72 6543,42 10836,53 18534,6789 18584,6789 19417 3134,56224 $ 4.901.665 $ 18.136.160.855 2 59,60 63,28 358,57 312,51 734,354596 784,354596 560 132,292212 $ 200.029 $ 740.108.907 3 27,05 12,35 69,99 40,35 122,686563 172,686563 72,29 29,1259687 $ 42.695 $ 157.971.260 4 15,71 3,93 22,29 9,97 36,1998787 86,1998787 17,87 14,5387975 $ 20.832 $ 77.077.751 5 10,00 1,50 8,50 3,15 13,1419988 63,1419988 5,64 10,6497683 $ 15.063 $ 55.733.044 6 6,92 0,67 3,82 1,24 5,7340002 55,7340002 2,22 9,40030725 $ 13.223 $ 48.925.559 8 4,00 0,21 1,19 0,31 1,7113024 51,7113024 0,56 8,72182383 $ 12.229 $ 45.247.677 10 2,54 0,08 0,48 0,10 0,6638566 50,6638566 0,18 8,54515766 $ 11.972 $ 44.295.237 Nominal Diameter(in) hL(ft) ∑hL(ft) ha(ft) $COP$(USD)PA(kW)∆P(psi) ∆P(psi) PA(kW) $(USD) $COP Elbows Valves Line 1 278,05 1666,98 9446,25 17548,38 28661,6114 28711,6114 31443,67 4842,60896 $ 7.610.740 $ 28.159.736.856 2 67,73 81,71 463,04 435,91 980,66872 1030,66872 781,08 173,836484 $ 264.039 $ 976.943.993 3 30,28 15,47 87,67 53,97 157,10938 207,10938 96,70 34,9318513 $ 51.469 $ 190.435.597 4 17,40 4,82 27,33 12,95 45,1058345 95,1058345 23,21 16,0409097 $ 23.076 $ 85.381.495 5 10,99 1,81 10,27 4,01 16,0918776 66,0918776 7,18 11,147306 $ 15.800 $ 58.461.385 6 7,67 0,83 4,69 1,61 7,12831215 57,1283121 2,88 9,63547718 $ 13.570 $ 50.208.479 8 4,38 0,25 1,43 0,39 2,07145528 52,0714553 0,70 8,78256857 $ 12.318 $ 45.576.435 10 2,78 0,10 0,58 0,13 0,8053278 50,8053278 0,23 8,56901872 $ 12.006 $ 44.423.454 ha(ft)V(ft/s)Nominal Diameter hL(ft) ∑hL(ft)
  • 9. Analysis  From the previous results, it must be highlighted that the only schedule pipe which met the velocity-pressure drop requierements was the Schedule 40. Schedule 40  Despite the velocity was aceptable from 5 to 8 in nominal diameter. It was noted that the only diameter which met the requierement of pressure drop(∆P= below 0,6 psi) was the 8 in pipe.  In the other hand, it was seen that the proper selection of the pipe size does affects the cost of operation.  If for example: A process engineer had chosen a 6 inch pipe without taking into account the requirements, then the cost of operation would have exceed 994 USD per year of operation. Schedule 40  Although 5, 6 and 8 inch diameter did meet the velocity requirements, the pressure drop conditions were not reached. Bad decisions during the piping design and pump selection can lead to years of unnecessarily high cost of operation.
  • 11. Schedule 40- Cost analysis
  • 12. REFERENCES [1] R. Mott, Mecánica de fluidos, Dayton: Pearson, 2006. [2] A. 14E, Recommended Practice for Design and Installation of Offshore Production Platform Piping Systems., Washington: American Pretroleum Institute, 1991. [3] C. d. R. d. E. y. G. (CREG), «TARIFAS DE ENERGÍA ELÉCTRICA ($/kWh) REGULADAS POR LA COMISIÓN DE REGULACIÓN DE ENERGÍAY GAS (CREG) JUNIO DE 2020,» ENEL CODENSA, 2020. [4] B. d. l. R. d. Colombia, «Tasa Representativa de Mercado (TRM-Peso por dolar),» Banco de la Republica de Colombia, Colombia, 2020.