Areas of Expertise
∑ Rotating and static equipment installation
∑ Pre-Commissioning, Commissioning and Start up
∑ Running plant maintenance and shutdown
Professional Experience
Total - 12 Years Gulf - 4 Years
April 2014-Till date
Company
ONGC Mangalore Petrochemicals, Subsidiary of Mangalore Refinery
and Petrochemicals (MRPL)
Project Aromatic complex
Job title and description Mechanical Maintenance Sr. Supervisor
March 2012- March 2014
Company Eni Saipem, Abu Dhabi
Project Shah gas development project
Job title and description Mechanical Equipment installation and commissioning supervisor
Qualification
Address
Mobile No.
Date Of Birth
Marital Status
Passport No.
E-Mail
Skype ID
:
:
:
:
:
:
:
:
Diploma in Mechanical Engineering
Bachelor Of Engineering in Mechanical
Flat no - F1, Ramana Park, Lakshmi
Nagar Extension, Selaiyur - Chennai,
Tamil Nadu, India – 600073
91-9480822173
10-07-1986
Married
G-2901534
pnkarthik86@gmail.com
Natarajankarthik
2. Page 2 of 4
August 2009-July 2011
Company Tecnicas Reunidas Gulf co. Ltd, Saudi Arabia
Project ARAMCO Refinery
Job title and description Mechanical Equipment installation and commissioning supervisor
May2005-July 2009
Company Siemens (Flender Grafenstaden)
Project Power and Energy Division
Job title and description
High speed gear box Assembly, Testing, Maintenance and
commissioning engineer
Key responsibilities handled
1. Installation during construction
¸ Coordinating fabrication, shell course shifting and erection activities for the static
equipments
¸ Monitoring the job as per ITP and required by client
¸ Reviewing the approval documents about Inspection Test Plan of the project to ensure
inspection shall be in accordance with the required quality standard and procedures
¸ Executing and checking documentation works for static and rotating equipments to
assure that the required forms used in testing submitted are approved by client
representative as per ITP such as:-Installation checklist for static/rotating equipment-
levelling/alignment recording forms for horizontal and vertical package type-Axial/radial,
soft foot parallelism forms for pumps and compressors
¸ Regular surveillance checking at site to verify the preservation requirements for
anchor bolts during construction stage
¸ Checking the preservation status of equipments at site
¸ Obtaining complete check list of the assembling equipment and keep a record of same.
¸ Erection of equipments such as pumps, vessels, tanks and compressors and other
equipments as per the approved method statement
¸ Checking equipment orientation and shimming before and after erection
¸ Check the condition of pump alignment (axial/radial) without piping prior for
preparation for piping installation
3. Page 3 of 4
2. Pre- Commissioning and commissioning
¸ Preparation of document coding system, defining systems/subsystems, mechanical
completion package, setting milestones
¸ Preparation of commissioning package, procedures and check list of plant system and
sub-system divisions
¸ Inspection of static equipments hydro test and leak test
¸ System wise plant delivery, installation, hook-up and Operations readiness assurance,
operations Readiness assurance plans/methodology/management.
¸ Preparation of punch list and follow up of its completion
¸ Preparation of operation procedure according to the vendor recommendations
¸ Conduction of meetings with sub-contractor for pre-commissioning and commissioning
start-up activities
¸ Reviewing the installed equipment and its accessories as per P&ID
¸ Coordination and interface with other disciplines related issues
¸ Final inspection (Alignment and box up ) of rotary and static equipment
¸ Identification and rectification of start- up problems of rotary equipments
3. Maintenance
¸ Maintenance for different types of static and rotating equipment
¸ Rectification of leaks present at heat exchanger tubes, column vessel and reactor trays
¸ Problem fixing with the help of various measuring tools
¸ Conducting a root cause analysis at the time of breakdown of machines
¸ Recommending alternative solution when the execution of the given design becomes
difficult at site
¸ Tracking the maintenance work orders using SAP software
¸ Planning, preparation and execution of yearly and short term shutdown
Machineries handled
∑ Air fin coolers (Forced and induced type )FD and ID fans, Blowers
∑ All types of pumps
∑ Compressors and auxiliaries system
∑ Steam turbines and auxiliaries system
∑ Gearboxes (High speed gear boxes )
4. Page 4 of 4
Units worked on
∑ Petrochemical Aromatic complex - Mangalore Petrochemicals
∑ Vacuum gas oil Unit ( VGO ) - GGSR refinery
∑ Diesel hydro treated Unit (DHDT) - GGSR refinery / Aram co refinery
∑ Hydro Treated Unit, Hydrogen Unit, Gas storage Unit - Shah gas project Abu Dhabi
∑ Power plant, Cement plant , Sugar plant
Software skills
Mechanical CADD
Training and Certification
1. Training on Operations and Maintenance of Steam Turbine conducted by India Boiler
Dot Com from 10th
to 11th
November 2014.
2. Training on Fire and Safety conducted by ONGC Mangalore Petrochemicals on
29th
November 2014.
3. Training on Scaffolding Erection and Certification conducted by National Safety
Council, Karnataka Chapter on 18th
July 2015.
4. Training on The Proper Use of Selected Crosby Lifting & Rigging Products conducted
by Crosby Communication System on 2nd
December 2015.