From:    Brandon Valdez                  To: David Ficklin - OnGoal
                                                                          Rory O’Connor – OnGoal
                             Office: Kansas City                          Lee Turner – OnGoal
                             Date:    8.11.2010                           Andy Heitmann – Turner
                                                                          Dave Dudzik - Turner
                             Re:      Wizards Stadium Project
                                      Update – Week of
                                      8.9.2010



 Current Activities this Week:

 Mass Excavation:
 Backfilling of on-grade seating is ongoing in Area 3.

 Site Utilities:
 Storm Sewer Installation (Line 6000) is nearly complete
 on the east side of France Family Drive. Sanitary Sewer     Area 3 – Installation of Storm Line 6000 inlet
 Line E is underway.                                         boxes is complete on the east side of France
                                                             Family Drive.
  Foundations:
 Area 3 Field Level – Foundation installation continues on
 the east side of the site.

 Concrete Flatwork:
 Area 1 – Slab-on-grade is placed at field level to
 Column line 15. Concourse Level Slab-on-Metal deck is
 in place to Column line 6.

 Structural Steel Erection:
 Area 1 – Main Canopy Truss Erection is ongoing (Seq 1-8).
 Area 3 – Steel erection in Sequence 3-2 is complete.      Field Level Area 3 – Foundation walls for
 Installation of metal deck is ongoing in Sequence 3-2.    Elevator Pit 1 have been placed.

 Precast Concrete:
 Area 2 – Precast erection is ongoing and is currently set
 to Column Line 13.

 Underground MEP:
 Electrical for Electrical Room 01.12.01 is ongoing.



                                                             Area 2 – Precast erection is ongoing at the
Building the Future
                                                             south elevation. Currently being placed
                                                             between Column Lines 12.4 - 13.
MEP Rough-in:
 Area 2 – Shallow electrical and plumbing rough-in is
 ongoing. Ductwork installation on Suite and Press Levels
 are ongoing. Plumbing rough-in is ongoing on Suite and
 Press Levels. Fire Protection Mains are being installed on
 Suite Level.

 Metal Stud Framing:
 Area 1 – Metal stud framing for Concourse, Suite and Press     Area 1 – Canopy truss erection is ongoing
 Levels are ongoing.                                            and is currently set to Column Line 21.

 Masonry:
 Area 1 Field Level – Masonry wall installation is ongoing
 in Areas G and H.

 Area 1 Concourse Level – Picture framing is nearly complete
 for south concourse buildings. Layout for north buildings
 are ongoing.

 Projected Activities occurring next Week:

 Mass Excavation:
 Backfilling of foundations areas will continue in Area         Area 1 – Shot of the West Building from the
 3.                                                             east concourse.

 Site Utilities:
 Installation of the Storm Line 6000 on the East Side (France
 Family Drive) of the site will be complete. Sanitary Sewer
 installation will begin at locations where Storm Line 6000
 is complete.

 Deep Underground MEP:
 Deep Plumbing installation has started in Area 3.

 Foundations:
 Area 3 Field Level – Foundation installation will continue.
                                                                Field Level Area 1 – Masonry is ongoing at
 Concrete Flatwork:                                             the Field Level.
 Area 3 Concourse Level – Concrete placement for Slab-on
 Metal Deck will continue.



Building the Future
Area 1, 2 and 3 Field Level – Installation of on-grade seating
 risers and intermediate stairs will continue.

 Structural Steel Erection:
 Decking/Detailing of Structural Steel in Sequence 3-2 will
 continue.

 Erection of the Canopy Trusses will continue in                  Roof Level Area 1 – Installation of the West
 Sequence 1-8.                                                    Building roof has started. Protection board
                                                                  and vapor barrier installation seen here.
 Underground MEP:
 Deep underground plumbing will continue in Area 3.

 MEP Rough-in:
 MEP Rough-in at Suite and Press Levels will continue.
 Ductwork installation on Press Level will continue. Fire
 Sprinkler mains and branch line installation will continue on
 Suite Level.

 Metal Stud Framing:
 Area 1 – Metal stud framing for Concourse, Suite and Press       Area 1 – Stair 6 installation is ongoing and is
 Levels will continue.                                            currently erected to Suite Level.




Building the Future
Additional Photos:




Field Level Area 2 – Precast header installed   Press Level Area 1 – Ductwork installation
at Southeast Truck Drive.                       has started.




Concourse Level Area 1 – Southwest Terrace
Area concrete installation is nearly            Roof Level Area 1 – Mechanical Unit roof
complete.                                       curbs have been set.




Area 1 – Shot (looking west) of the canopy      Suite Level Area 1 – Installation of fire
trusses at Column Lines 22 and 23.              sprinkler mains are ongoing on Suite Level.




Building the Future

Contenu connexe

En vedette

How Race, Age and Gender Shape Attitudes Towards Mental Health
How Race, Age and Gender Shape Attitudes Towards Mental HealthHow Race, Age and Gender Shape Attitudes Towards Mental Health
How Race, Age and Gender Shape Attitudes Towards Mental Health
ThinkNow
 
Social Media Marketing Trends 2024 // The Global Indie Insights
Social Media Marketing Trends 2024 // The Global Indie InsightsSocial Media Marketing Trends 2024 // The Global Indie Insights
Social Media Marketing Trends 2024 // The Global Indie Insights
Kurio // The Social Media Age(ncy)
 

En vedette (20)

2024 State of Marketing Report – by Hubspot
2024 State of Marketing Report – by Hubspot2024 State of Marketing Report – by Hubspot
2024 State of Marketing Report – by Hubspot
 
Everything You Need To Know About ChatGPT
Everything You Need To Know About ChatGPTEverything You Need To Know About ChatGPT
Everything You Need To Know About ChatGPT
 
Product Design Trends in 2024 | Teenage Engineerings
Product Design Trends in 2024 | Teenage EngineeringsProduct Design Trends in 2024 | Teenage Engineerings
Product Design Trends in 2024 | Teenage Engineerings
 
How Race, Age and Gender Shape Attitudes Towards Mental Health
How Race, Age and Gender Shape Attitudes Towards Mental HealthHow Race, Age and Gender Shape Attitudes Towards Mental Health
How Race, Age and Gender Shape Attitudes Towards Mental Health
 
AI Trends in Creative Operations 2024 by Artwork Flow.pdf
AI Trends in Creative Operations 2024 by Artwork Flow.pdfAI Trends in Creative Operations 2024 by Artwork Flow.pdf
AI Trends in Creative Operations 2024 by Artwork Flow.pdf
 
Skeleton Culture Code
Skeleton Culture CodeSkeleton Culture Code
Skeleton Culture Code
 
PEPSICO Presentation to CAGNY Conference Feb 2024
PEPSICO Presentation to CAGNY Conference Feb 2024PEPSICO Presentation to CAGNY Conference Feb 2024
PEPSICO Presentation to CAGNY Conference Feb 2024
 
Content Methodology: A Best Practices Report (Webinar)
Content Methodology: A Best Practices Report (Webinar)Content Methodology: A Best Practices Report (Webinar)
Content Methodology: A Best Practices Report (Webinar)
 
How to Prepare For a Successful Job Search for 2024
How to Prepare For a Successful Job Search for 2024How to Prepare For a Successful Job Search for 2024
How to Prepare For a Successful Job Search for 2024
 
Social Media Marketing Trends 2024 // The Global Indie Insights
Social Media Marketing Trends 2024 // The Global Indie InsightsSocial Media Marketing Trends 2024 // The Global Indie Insights
Social Media Marketing Trends 2024 // The Global Indie Insights
 
Trends In Paid Search: Navigating The Digital Landscape In 2024
Trends In Paid Search: Navigating The Digital Landscape In 2024Trends In Paid Search: Navigating The Digital Landscape In 2024
Trends In Paid Search: Navigating The Digital Landscape In 2024
 
5 Public speaking tips from TED - Visualized summary
5 Public speaking tips from TED - Visualized summary5 Public speaking tips from TED - Visualized summary
5 Public speaking tips from TED - Visualized summary
 
ChatGPT and the Future of Work - Clark Boyd
ChatGPT and the Future of Work - Clark Boyd ChatGPT and the Future of Work - Clark Boyd
ChatGPT and the Future of Work - Clark Boyd
 
Getting into the tech field. what next
Getting into the tech field. what next Getting into the tech field. what next
Getting into the tech field. what next
 
Google's Just Not That Into You: Understanding Core Updates & Search Intent
Google's Just Not That Into You: Understanding Core Updates & Search IntentGoogle's Just Not That Into You: Understanding Core Updates & Search Intent
Google's Just Not That Into You: Understanding Core Updates & Search Intent
 
How to have difficult conversations
How to have difficult conversations How to have difficult conversations
How to have difficult conversations
 
Introduction to Data Science
Introduction to Data ScienceIntroduction to Data Science
Introduction to Data Science
 
Time Management & Productivity - Best Practices
Time Management & Productivity -  Best PracticesTime Management & Productivity -  Best Practices
Time Management & Productivity - Best Practices
 
The six step guide to practical project management
The six step guide to practical project managementThe six step guide to practical project management
The six step guide to practical project management
 
Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...
Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...
Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...
 

Construction Update 08-11-2010

  • 1. From: Brandon Valdez To: David Ficklin - OnGoal Rory O’Connor – OnGoal Office: Kansas City Lee Turner – OnGoal Date: 8.11.2010 Andy Heitmann – Turner Dave Dudzik - Turner Re: Wizards Stadium Project Update – Week of 8.9.2010 Current Activities this Week: Mass Excavation: Backfilling of on-grade seating is ongoing in Area 3. Site Utilities: Storm Sewer Installation (Line 6000) is nearly complete on the east side of France Family Drive. Sanitary Sewer Area 3 – Installation of Storm Line 6000 inlet Line E is underway. boxes is complete on the east side of France Family Drive. Foundations: Area 3 Field Level – Foundation installation continues on the east side of the site. Concrete Flatwork: Area 1 – Slab-on-grade is placed at field level to Column line 15. Concourse Level Slab-on-Metal deck is in place to Column line 6. Structural Steel Erection: Area 1 – Main Canopy Truss Erection is ongoing (Seq 1-8). Area 3 – Steel erection in Sequence 3-2 is complete. Field Level Area 3 – Foundation walls for Installation of metal deck is ongoing in Sequence 3-2. Elevator Pit 1 have been placed. Precast Concrete: Area 2 – Precast erection is ongoing and is currently set to Column Line 13. Underground MEP: Electrical for Electrical Room 01.12.01 is ongoing. Area 2 – Precast erection is ongoing at the Building the Future south elevation. Currently being placed between Column Lines 12.4 - 13.
  • 2. MEP Rough-in: Area 2 – Shallow electrical and plumbing rough-in is ongoing. Ductwork installation on Suite and Press Levels are ongoing. Plumbing rough-in is ongoing on Suite and Press Levels. Fire Protection Mains are being installed on Suite Level. Metal Stud Framing: Area 1 – Metal stud framing for Concourse, Suite and Press Area 1 – Canopy truss erection is ongoing Levels are ongoing. and is currently set to Column Line 21. Masonry: Area 1 Field Level – Masonry wall installation is ongoing in Areas G and H. Area 1 Concourse Level – Picture framing is nearly complete for south concourse buildings. Layout for north buildings are ongoing. Projected Activities occurring next Week: Mass Excavation: Backfilling of foundations areas will continue in Area Area 1 – Shot of the West Building from the 3. east concourse. Site Utilities: Installation of the Storm Line 6000 on the East Side (France Family Drive) of the site will be complete. Sanitary Sewer installation will begin at locations where Storm Line 6000 is complete. Deep Underground MEP: Deep Plumbing installation has started in Area 3. Foundations: Area 3 Field Level – Foundation installation will continue. Field Level Area 1 – Masonry is ongoing at Concrete Flatwork: the Field Level. Area 3 Concourse Level – Concrete placement for Slab-on Metal Deck will continue. Building the Future
  • 3. Area 1, 2 and 3 Field Level – Installation of on-grade seating risers and intermediate stairs will continue. Structural Steel Erection: Decking/Detailing of Structural Steel in Sequence 3-2 will continue. Erection of the Canopy Trusses will continue in Roof Level Area 1 – Installation of the West Sequence 1-8. Building roof has started. Protection board and vapor barrier installation seen here. Underground MEP: Deep underground plumbing will continue in Area 3. MEP Rough-in: MEP Rough-in at Suite and Press Levels will continue. Ductwork installation on Press Level will continue. Fire Sprinkler mains and branch line installation will continue on Suite Level. Metal Stud Framing: Area 1 – Metal stud framing for Concourse, Suite and Press Area 1 – Stair 6 installation is ongoing and is Levels will continue. currently erected to Suite Level. Building the Future
  • 4. Additional Photos: Field Level Area 2 – Precast header installed Press Level Area 1 – Ductwork installation at Southeast Truck Drive. has started. Concourse Level Area 1 – Southwest Terrace Area concrete installation is nearly Roof Level Area 1 – Mechanical Unit roof complete. curbs have been set. Area 1 – Shot (looking west) of the canopy Suite Level Area 1 – Installation of fire trusses at Column Lines 22 and 23. sprinkler mains are ongoing on Suite Level. Building the Future