Removing the
Barriers to
Potential
Mining Trends 2014
Are you ready for a seismic shift?
January 2014
DELOITTE – Tracking the trends 2014
1.Mining productivity hits new lows
2.Market imbalances wreak commodity price havoc
3.Exploring the innovation imperative
4.Debt up, deals down and juniors fight for survival
5.Record impairments call capital allocation practices into question
6.Local community demands intensify
7.Government relations marked by rising hostility
8.Zero tolerance regulatory environments complicate compliance
9.From zero harm to zero fatalities
10.The talent gap widens into executive suites
The top 10 issues mining companies will face in 2014
“It’s not a
pendulum
swing, it’s a
seismic shift”
Innovate or face the Consequences!
• Strategic Planning and Thinking
• Asset Allocation
• Government and Community Relations
• Ability to secure Funding for growth Projects
• Mitigate risk of Commodity Price fluctuations
• Cost Management
• Improved Management of People and
Processes
• Raise Productivity
• Improve Safety
• Reduce Operational Risk
• Innovative Talent strategies
There’s no doubt the mining industry is experiencing tremendous pressure on costs. But cost constraints often
lead to innovation. Mining has grown bigger over the past 200 years – bigger plants, bigger trucks, bigger blasts.
But the industry itself hasn’t evolved much. Now is the time to make fundamental and dramatic changes.
Glenn Ives, Americas Mining Leader
Responding to the Global Challenge
•Many Miners can no longer wait for Peaks in Commodity
Prices to make up for questionable Business Practices
•TMS has pioneered an innovative Approach to solving
Problems and continues to evolve this Approach through
Practice and Research
•Over the last decade TMS has helped
mining organizations address the
challenges outlined in the 2014
Deloitte report
•The challenges are not new but have
been exasperated by instability in
Commodity prices
•The Depletion of Resources is
causing Costs to rise while
Productivity is falling
Cost Cutting ≠ Cost Management
•Reactive cost cutting is not sustainable
•Cost Creep tends to reset spending to historical
levels
•Redundancies often need to get rehired at
additional costs
•Focus must be on Return on Capital Employed
(ROCE) and Shareholder Value
•Shifting from Asset Expansion to Operational
Excellence
•Maximize Cash Flow from existing Assets
•Improve Productivity through better Management,
Systems and Technology
Reducing costs over the long
term requires mining
companies to prepare for a
hard campaign of changing
the way they do work. This,
in turn, should spur them to
look closely at their culture
to determine if that needs
changing too.
Andy Clay, Managing
Director, Venmyn Deloitte,
South Africa
The TMS Solution to improve Asset Performance
• Cost Management to decrease all-in cost and improve cash flow
• Strategic Business Planning to optimise the capital allocation for long-term benefits
• Effective People Management to mitigate the long term skilled shortage
• Managerial Capability and Accountability at all levels to deliver the results expected and
reduce operational risk
• Quality Production Management at the mine level to improve a manageability of the
operations
• Detailed Knowledge of the primary and Support Value Streams to optimise the value
generated by the business
• Capital Project Management to ensure the delivery of essential capital projects
Systematic Improvement of Mine Business Effectiveness
Mine Effectiveness Improvement Programme
•Short term Financial Performance
• Improve short term Cash Flow with “quick wins”
• Increase Asset Value
•Sustaining Short Term gains over the Long Haul
• Introduce systemic Improvements to boost Effectiveness
• Cultural changes to raise Productivity and reduce Risk
•Better Management for better Results
• Effectively manage People, Structures and Work
• Improved Decision Making reducing Operational Risk
• Optimal Organisation Structures with clear Accountability from Top to Bottom
• Identification and Development of High Potential to fill Talent Gaps at all Levels
• Reduced Reliance on “foreign” Talent to cut Costs and improve Community
Relationships
Multi Dimensional Nature of the Effectiveness
Improvement Programme
• а
Mine Planning
Effectiveness
Mine
Organisational
Effectiveness
Mine Technical
Effectiveness
Mine Economic
Effectiveness
Mine Long Term
Effectiveness
The Elements of Mine Long Term Business Effectiveness
Mine Short Term Effectiveness Management
Mine Long Term Effectiveness Management
Ensure maximum
economic return
from the planning,
organisational and
technical systems of
the mine
(quick wins) - short term activities that focus on identifying the opportunities for
optimising cost and increasing the value of the mines and their delivery within a short
period (up to 1 year). Such initiatives do not require system / cardinal changes
Ensure an availability of the
mine production management
system for improving the key
mine effectiveness indicators
on a constant basis every year
to sustain the short term
achievements
Long term activities that focus on sustaining quick, short term results and that will require systematic / cardinal
improvement of operational and management systems of the mines within the long term period (to 3-5 years)
Mine Effectiveness Improvement Programme
Tasks:
• Analyse and optimise the current initiatives in regard to
improvements in the effectiveness of the mines (cost
and value)
• Identify the shortfalls in the current approach to
manage the cost and value of the mines
• Define key strategic initiatives to improve the cost and
value of the mines with clear and feasible advantages of
the initiatives
• Train managers at all the levels of the mines on various
methods to improve cost and value
• Provide support to the managers in their practical
application of the methods learned and achievement of
feasible economic effect.
• Allocate accountabilities for managing cost and value
(effectiveness) among the Managers at all levels
Key Mine Effectiveness Indicators
Mine Planning
Effectiveness
Ensure effective planning of all functions of the mine at various
planning horizons, starting with hourly and finishing with long term
plans (life of mine)
M2P for the mine > 90% in all
planning horizons from hour
to 3-5 years
Mine Organisational
Effectiveness
Ensure minimum required conditions (structure, people,
management) of organisational effectiveness for delivering the mine
plans (short- and long-term) utilising mine employees at their full
potential
Mine Organisational
Effectiveness Index > 90%
Mine Technical
Effectiveness
Ensure efficient utilisation of the mine’s technical resources for an
achievement of maximum return on equipment and technologies
Mine Overall Equipment
Efficiency Index > 45%
Mine Economic
Effectiveness
Ensure maximum economic return from planning, organisational
and technical systems of the mine
General Economic
Effectiveness Index > 1
Mine Long Term
Effectiveness
Ensure an availability of the mine production management system
for improving the key mine effectiveness indicators on a constant
basis every year to sustain the short term achievements
Mine Production System
Effectiveness Index >90%
Objective: Define and deliver a set of improvement activities to optimise the cost and increase the value of the assets
to achieve feasible economic effects in short- and long-term perspectives
Activities
Feb,2014
Mar,2014
Apr,2014
May,2014
June,2014
July,2014
Aug,2014
Sept,2014
Oct,2014
Nov,2014
Dec,2014
Jan,2015
Feb,2015
Mar,2015
Apr,2015
May,2015
June,2015
July,2015
Aug,2015
Sept,2015
Oct,2015
Nov,2015
Dec,2015
Jan,2016
Feb,2016
MineShortTermEffectivenessmanagement
Express analysis of the Mine Business Effectiveness based one Mine
Stage 1 – Analysing and Optimising Mine Expense Profile
• Analysis and identification
• Implementing initiatives
Stage 2 – Expert Cost & Benefit Analysis
• Analysis and identification
• Implementing initiatives
Stage 3 – Accountable Cost & Benefit Management
• Module 1 – Developing Minimum Required Conditions of Organisational Effectiveness
• Module 2 – Back to Basics
• Module 3 - Optimisation
• Module 4 – Linking optimisation with budget
• Module 5 - Implementation
MineLongTermEffectivenessManagement
Phase 1 – Analysing the effectiveness of the current elements of the Mine Production management System
Phase 2 – Designing the improved Mine Production Management System
Phase 3 – Implementing the improved Mine Production Mangement System
• Short Term Initiatives to improve Mine Production Management System
• Long Term Initiatives to improve Mine Production Management System
Phase 4 – Audit the Effectiveness of the Mine Production Management System implemented
Sample Implementation of such a Programme in one mining company
• The use of highly qualified external experts for auditing the key mine
systems and processes
• Total value of short term cost reduction and value benefit up to $263M,
including:
• $89M within one year (2014) – short term initiatives and additional benefits,
including $35M in the processing plants (improvements in extraction)
• $76M US additional benefits (2015)
• Optimising the number of employees in the underground mine (currently 850, target
450 employees) by optimising equipment and improving mine planning
• Strong downward trend in both cash costs and all-in sustaining costs, which were
down 17% and 7% respectively on Q2 2013 and 28% and 25% respectively on Q3
2012.
• Located in Africa
• 4 mines
• London Stock Exchange – FTSE250
• 5 000 employees
• Income - $1.087B
• 600 000 ounces per year
Activities
Feb,2014
Mar,2014
Apr,2014
May,2014
June,2014
July,2014
Aug,2014
Sept,2014
Oct,2014
Nov,2014
Dec,2014
Jan,2015
Feb,2015
Mar,2015
Apr,2015
May,2015
June,2015
July,2015
Aug,2015
Sept,2015
Oct,2015
Nov,2015
Dec,2015
Jan,2016
Feb,2016
MineShortTermEffectivenessmanagement
Express analysis of the Mine Business Effectiveness based one Mine
Stage 1 – Analysing and Optimising Mine Expense Profile
• Analysis and identification
• Implementing initiatives
Stage 2 – Expert Cost & Benefit Analysis
• Analysis and identification
• Implementing initiatives
Stage 3 – Accountable Cost & Benefit Management
• Module 1 – Developing Minimum Required Conditions of Organisational Effectiveness
• Module 2 – Back to Basics
• Module 3 - Optimisation
• Module 4 – Linking optimisation with budget
• Module 5 - Implementation
MineLongTermEffectivenessManagement
Phase 1 – Analysing the effectiveness of the current elements of the Mine Production management System
Phase 2 – Designing the improved Mine Production Management System
Phase 3 – Implementing the improved Mine Production Mangement System
• Short Term Initiatives to improve Mine Production Management System
• Long Term Initiatives to improve Mine Production Management System
Phase 4 – Audit the Effectiveness of the Mine Production Management System implemented
Sample Implementation of such a Programme in one mining company
• Implementing the Accountable Management System that focuses on improving
people, structure and work management
 Organisational structure - Significant changes to staffing structures and levels
resulting in a reduction of 27% of international employees in 2013 and a reduction
of 37% in contractors on site.
• Improving the system of integrated planning :
• Long term mine planning
• Capacity planning with constraints
• Short term planning and scheduling
• Integration of maintenance planning
• Delivery of the production plan for the first time in 3 years
• Reduction in cost below the planned indicator of $925 per ounce
• Located in Africa
• 4 mines
• London Stock Exchange – FTSE250
• 5 000 employees
• Income - $1.087B
• 600 000 ounces per year
If YOU had started last Year YOU would see the
Improvement now
1.October, 2012 - the start of the analysing the
current business effectiveness (operation review)
2.January, 2013 – the start of the implementation of
the mine effectiveness improvement programme
3.May, 2013 – the announcement of the first results of
the implementation of the programme
4.July, 2013 - the announcement of first Half year
(2013) result
5.October, 2013 – the announcement of the production
–financial results for the third quarter and
intermediate results of the implementation of the
effectiveness improvement programme (cost
reduction and additional benefits generation)
2 3 4
5
For more Information
go to
www.totalmanagementsys.com
or send Questions and/or Comments to:
info@totalmanagementsys.com

Contenu connexe

Tendances

Operations ppt
Operations pptOperations ppt
Operations ppt
Pritam RW
 
Aggregat planning stevenson
Aggregat planning stevensonAggregat planning stevenson
Aggregat planning stevenson
Piyush Vanjani
 
Aggragate planning1
Aggragate planning1Aggragate planning1
Aggragate planning1
arathymalz
 

Tendances (20)

Production planning techniques- aggregate planning
Production planning techniques- aggregate planningProduction planning techniques- aggregate planning
Production planning techniques- aggregate planning
 
(Productivity)
(Productivity)(Productivity)
(Productivity)
 
Aggregate planning
Aggregate planningAggregate planning
Aggregate planning
 
Production mgt(productivity ppt)
Production mgt(productivity ppt)Production mgt(productivity ppt)
Production mgt(productivity ppt)
 
Om presentation group 10 sec a
Om presentation group 10 sec aOm presentation group 10 sec a
Om presentation group 10 sec a
 
Ppt6
Ppt6Ppt6
Ppt6
 
Operations ppt
Operations pptOperations ppt
Operations ppt
 
Chapter 4_OM
Chapter 4_OMChapter 4_OM
Chapter 4_OM
 
Aggregat planning stevenson
Aggregat planning stevensonAggregat planning stevenson
Aggregat planning stevenson
 
Aggragate planning1
Aggragate planning1Aggragate planning1
Aggragate planning1
 
COST CONTROL
COST CONTROLCOST CONTROL
COST CONTROL
 
CAPACITY & AGGREGATE PLANNING
CAPACITY & AGGREGATE PLANNINGCAPACITY & AGGREGATE PLANNING
CAPACITY & AGGREGATE PLANNING
 
Techniques for measurement of productivity
Techniques for measurement of productivityTechniques for measurement of productivity
Techniques for measurement of productivity
 
Master planning
Master planningMaster planning
Master planning
 
Productivity concepts
Productivity conceptsProductivity concepts
Productivity concepts
 
Importance of Performance Management And Measurement of Productivity
Importance of Performance Management  And Measurement of ProductivityImportance of Performance Management  And Measurement of Productivity
Importance of Performance Management And Measurement of Productivity
 
Aggregate planning
Aggregate planningAggregate planning
Aggregate planning
 
Mba ii pmom_unit-2.4 aggregate planning a
Mba ii pmom_unit-2.4 aggregate planning aMba ii pmom_unit-2.4 aggregate planning a
Mba ii pmom_unit-2.4 aggregate planning a
 
Risk Management and Value Engineering _ Unit 4 _ Construction Management _ Fi...
Risk Management and Value Engineering _ Unit 4 _ Construction Management _ Fi...Risk Management and Value Engineering _ Unit 4 _ Construction Management _ Fi...
Risk Management and Value Engineering _ Unit 4 _ Construction Management _ Fi...
 
Seven Steps for Achieving Sustainable Cost Reduction
Seven Steps for Achieving Sustainable Cost ReductionSeven Steps for Achieving Sustainable Cost Reduction
Seven Steps for Achieving Sustainable Cost Reduction
 

En vedette

Essential Mag Article- A window onto the world
Essential Mag Article- A window onto the worldEssential Mag Article- A window onto the world
Essential Mag Article- A window onto the world
Tony Cassidy
 

En vedette (10)

7SAMAN#55
7SAMAN#557SAMAN#55
7SAMAN#55
 
Crime prevention via job creation
Crime prevention via job creationCrime prevention via job creation
Crime prevention via job creation
 
Grape golilath
Grape golilathGrape golilath
Grape golilath
 
23 tips to help with your video marketing strategy
23 tips to help with your video marketing strategy23 tips to help with your video marketing strategy
23 tips to help with your video marketing strategy
 
Căn hộ phố đông 653 trcăn mở bán đợt cuối bàn giao nhà 0989707653
Căn hộ phố đông 653 trcăn mở bán đợt cuối bàn giao nhà 0989707653Căn hộ phố đông 653 trcăn mở bán đợt cuối bàn giao nhà 0989707653
Căn hộ phố đông 653 trcăn mở bán đợt cuối bàn giao nhà 0989707653
 
Căn hộ phố đông 66 m2, 735tr, lh 0915.45.75.39
Căn hộ phố đông 66 m2, 735tr, lh 0915.45.75.39Căn hộ phố đông 66 m2, 735tr, lh 0915.45.75.39
Căn hộ phố đông 66 m2, 735tr, lh 0915.45.75.39
 
Attachments
AttachmentsAttachments
Attachments
 
Essential Mag Article- A window onto the world
Essential Mag Article- A window onto the worldEssential Mag Article- A window onto the world
Essential Mag Article- A window onto the world
 
Blowing Performance Spa parts
Blowing Performance Spa partsBlowing Performance Spa parts
Blowing Performance Spa parts
 
7SAMAN#56
7SAMAN#567SAMAN#56
7SAMAN#56
 

Similaire à Mining trends 2014 eng

Productivity in Mining[998]
Productivity in Mining[998]Productivity in Mining[998]
Productivity in Mining[998]
Lily Kehoe
 
Lecture-3-Introduction to Maintenance Management.ppt
Lecture-3-Introduction to Maintenance Management.pptLecture-3-Introduction to Maintenance Management.ppt
Lecture-3-Introduction to Maintenance Management.ppt
Thushan9
 
resume_Sid Persaud_Dec 9 2015
resume_Sid Persaud_Dec 9 2015resume_Sid Persaud_Dec 9 2015
resume_Sid Persaud_Dec 9 2015
Sid Persaud
 
Value oriented Maintenance - Improvement of O.E.E. and cost efficiency
Value oriented Maintenance - Improvement of O.E.E. and cost efficiency Value oriented Maintenance - Improvement of O.E.E. and cost efficiency
Value oriented Maintenance - Improvement of O.E.E. and cost efficiency
ConMoto Consulting Group
 
Charles New Resume 4
Charles New Resume 4Charles New Resume 4
Charles New Resume 4
Charles Wade
 

Similaire à Mining trends 2014 eng (20)

Operations Excellence in the Management of Ageing Assets
Operations Excellence in the Management of Ageing AssetsOperations Excellence in the Management of Ageing Assets
Operations Excellence in the Management of Ageing Assets
 
Accelerate Mining Operations Excellence
Accelerate Mining Operations ExcellenceAccelerate Mining Operations Excellence
Accelerate Mining Operations Excellence
 
GVK- Resume
GVK- ResumeGVK- Resume
GVK- Resume
 
Introduction to Process Thinking
Introduction to Process ThinkingIntroduction to Process Thinking
Introduction to Process Thinking
 
Introduction to Process Thinking (for Energy company)
Introduction to Process Thinking (for Energy company)Introduction to Process Thinking (for Energy company)
Introduction to Process Thinking (for Energy company)
 
Production Planning and Control in Materials Management
Production Planning and Control in Materials ManagementProduction Planning and Control in Materials Management
Production Planning and Control in Materials Management
 
Sudhir Niphadkar 1007-S
Sudhir Niphadkar 1007-SSudhir Niphadkar 1007-S
Sudhir Niphadkar 1007-S
 
Introduction to operations management
Introduction to operations managementIntroduction to operations management
Introduction to operations management
 
Tosin Fasidi
Tosin FasidiTosin Fasidi
Tosin Fasidi
 
Productivity in Mining[998]
Productivity in Mining[998]Productivity in Mining[998]
Productivity in Mining[998]
 
Fundamentals of managing business operation
Fundamentals of managing business operationFundamentals of managing business operation
Fundamentals of managing business operation
 
aggregate planning.ppt
aggregate planning.pptaggregate planning.ppt
aggregate planning.ppt
 
pip.ppt
pip.pptpip.ppt
pip.ppt
 
Lecture-3-Introduction to Maintenance Management.ppt
Lecture-3-Introduction to Maintenance Management.pptLecture-3-Introduction to Maintenance Management.ppt
Lecture-3-Introduction to Maintenance Management.ppt
 
resume_Sid Persaud_Dec 9 2015
resume_Sid Persaud_Dec 9 2015resume_Sid Persaud_Dec 9 2015
resume_Sid Persaud_Dec 9 2015
 
Operational Excellence.pptx
Operational Excellence.pptxOperational Excellence.pptx
Operational Excellence.pptx
 
CHAPTER 3 System and design Capacity.pptx
CHAPTER 3 System and design Capacity.pptxCHAPTER 3 System and design Capacity.pptx
CHAPTER 3 System and design Capacity.pptx
 
Value oriented Maintenance - Improvement of O.E.E. and cost efficiency
Value oriented Maintenance - Improvement of O.E.E. and cost efficiency Value oriented Maintenance - Improvement of O.E.E. and cost efficiency
Value oriented Maintenance - Improvement of O.E.E. and cost efficiency
 
Introduction to Productivity SA presentation with GAD
Introduction to Productivity SA presentation with GADIntroduction to Productivity SA presentation with GAD
Introduction to Productivity SA presentation with GAD
 
Charles New Resume 4
Charles New Resume 4Charles New Resume 4
Charles New Resume 4
 

Dernier

Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
lizamodels9
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usage
Matteo Carbone
 
Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
amitlee9823
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
dollysharma2066
 
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
dlhescort
 
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
dollysharma2066
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
daisycvs
 
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
amitlee9823
 

Dernier (20)

Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service AvailableCall Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
 
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
 
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League City
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usage
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMAN
 
Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and pains
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
Uneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration PresentationUneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration Presentation
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Century
 
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
 
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
 
RSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataRSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors Data
 
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
 
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with Culture
 

Mining trends 2014 eng

  • 1. Removing the Barriers to Potential Mining Trends 2014 Are you ready for a seismic shift? January 2014
  • 2. DELOITTE – Tracking the trends 2014 1.Mining productivity hits new lows 2.Market imbalances wreak commodity price havoc 3.Exploring the innovation imperative 4.Debt up, deals down and juniors fight for survival 5.Record impairments call capital allocation practices into question 6.Local community demands intensify 7.Government relations marked by rising hostility 8.Zero tolerance regulatory environments complicate compliance 9.From zero harm to zero fatalities 10.The talent gap widens into executive suites The top 10 issues mining companies will face in 2014 “It’s not a pendulum swing, it’s a seismic shift”
  • 3. Innovate or face the Consequences! • Strategic Planning and Thinking • Asset Allocation • Government and Community Relations • Ability to secure Funding for growth Projects • Mitigate risk of Commodity Price fluctuations • Cost Management • Improved Management of People and Processes • Raise Productivity • Improve Safety • Reduce Operational Risk • Innovative Talent strategies There’s no doubt the mining industry is experiencing tremendous pressure on costs. But cost constraints often lead to innovation. Mining has grown bigger over the past 200 years – bigger plants, bigger trucks, bigger blasts. But the industry itself hasn’t evolved much. Now is the time to make fundamental and dramatic changes. Glenn Ives, Americas Mining Leader
  • 4. Responding to the Global Challenge •Many Miners can no longer wait for Peaks in Commodity Prices to make up for questionable Business Practices •TMS has pioneered an innovative Approach to solving Problems and continues to evolve this Approach through Practice and Research •Over the last decade TMS has helped mining organizations address the challenges outlined in the 2014 Deloitte report •The challenges are not new but have been exasperated by instability in Commodity prices •The Depletion of Resources is causing Costs to rise while Productivity is falling
  • 5. Cost Cutting ≠ Cost Management •Reactive cost cutting is not sustainable •Cost Creep tends to reset spending to historical levels •Redundancies often need to get rehired at additional costs •Focus must be on Return on Capital Employed (ROCE) and Shareholder Value •Shifting from Asset Expansion to Operational Excellence •Maximize Cash Flow from existing Assets •Improve Productivity through better Management, Systems and Technology Reducing costs over the long term requires mining companies to prepare for a hard campaign of changing the way they do work. This, in turn, should spur them to look closely at their culture to determine if that needs changing too. Andy Clay, Managing Director, Venmyn Deloitte, South Africa
  • 6. The TMS Solution to improve Asset Performance • Cost Management to decrease all-in cost and improve cash flow • Strategic Business Planning to optimise the capital allocation for long-term benefits • Effective People Management to mitigate the long term skilled shortage • Managerial Capability and Accountability at all levels to deliver the results expected and reduce operational risk • Quality Production Management at the mine level to improve a manageability of the operations • Detailed Knowledge of the primary and Support Value Streams to optimise the value generated by the business • Capital Project Management to ensure the delivery of essential capital projects Systematic Improvement of Mine Business Effectiveness
  • 7. Mine Effectiveness Improvement Programme •Short term Financial Performance • Improve short term Cash Flow with “quick wins” • Increase Asset Value •Sustaining Short Term gains over the Long Haul • Introduce systemic Improvements to boost Effectiveness • Cultural changes to raise Productivity and reduce Risk •Better Management for better Results • Effectively manage People, Structures and Work • Improved Decision Making reducing Operational Risk • Optimal Organisation Structures with clear Accountability from Top to Bottom • Identification and Development of High Potential to fill Talent Gaps at all Levels • Reduced Reliance on “foreign” Talent to cut Costs and improve Community Relationships
  • 8. Multi Dimensional Nature of the Effectiveness Improvement Programme • а Mine Planning Effectiveness Mine Organisational Effectiveness Mine Technical Effectiveness Mine Economic Effectiveness Mine Long Term Effectiveness The Elements of Mine Long Term Business Effectiveness Mine Short Term Effectiveness Management Mine Long Term Effectiveness Management Ensure maximum economic return from the planning, organisational and technical systems of the mine (quick wins) - short term activities that focus on identifying the opportunities for optimising cost and increasing the value of the mines and their delivery within a short period (up to 1 year). Such initiatives do not require system / cardinal changes Ensure an availability of the mine production management system for improving the key mine effectiveness indicators on a constant basis every year to sustain the short term achievements Long term activities that focus on sustaining quick, short term results and that will require systematic / cardinal improvement of operational and management systems of the mines within the long term period (to 3-5 years)
  • 9. Mine Effectiveness Improvement Programme Tasks: • Analyse and optimise the current initiatives in regard to improvements in the effectiveness of the mines (cost and value) • Identify the shortfalls in the current approach to manage the cost and value of the mines • Define key strategic initiatives to improve the cost and value of the mines with clear and feasible advantages of the initiatives • Train managers at all the levels of the mines on various methods to improve cost and value • Provide support to the managers in their practical application of the methods learned and achievement of feasible economic effect. • Allocate accountabilities for managing cost and value (effectiveness) among the Managers at all levels Key Mine Effectiveness Indicators Mine Planning Effectiveness Ensure effective planning of all functions of the mine at various planning horizons, starting with hourly and finishing with long term plans (life of mine) M2P for the mine > 90% in all planning horizons from hour to 3-5 years Mine Organisational Effectiveness Ensure minimum required conditions (structure, people, management) of organisational effectiveness for delivering the mine plans (short- and long-term) utilising mine employees at their full potential Mine Organisational Effectiveness Index > 90% Mine Technical Effectiveness Ensure efficient utilisation of the mine’s technical resources for an achievement of maximum return on equipment and technologies Mine Overall Equipment Efficiency Index > 45% Mine Economic Effectiveness Ensure maximum economic return from planning, organisational and technical systems of the mine General Economic Effectiveness Index > 1 Mine Long Term Effectiveness Ensure an availability of the mine production management system for improving the key mine effectiveness indicators on a constant basis every year to sustain the short term achievements Mine Production System Effectiveness Index >90% Objective: Define and deliver a set of improvement activities to optimise the cost and increase the value of the assets to achieve feasible economic effects in short- and long-term perspectives
  • 10. Activities Feb,2014 Mar,2014 Apr,2014 May,2014 June,2014 July,2014 Aug,2014 Sept,2014 Oct,2014 Nov,2014 Dec,2014 Jan,2015 Feb,2015 Mar,2015 Apr,2015 May,2015 June,2015 July,2015 Aug,2015 Sept,2015 Oct,2015 Nov,2015 Dec,2015 Jan,2016 Feb,2016 MineShortTermEffectivenessmanagement Express analysis of the Mine Business Effectiveness based one Mine Stage 1 – Analysing and Optimising Mine Expense Profile • Analysis and identification • Implementing initiatives Stage 2 – Expert Cost & Benefit Analysis • Analysis and identification • Implementing initiatives Stage 3 – Accountable Cost & Benefit Management • Module 1 – Developing Minimum Required Conditions of Organisational Effectiveness • Module 2 – Back to Basics • Module 3 - Optimisation • Module 4 – Linking optimisation with budget • Module 5 - Implementation MineLongTermEffectivenessManagement Phase 1 – Analysing the effectiveness of the current elements of the Mine Production management System Phase 2 – Designing the improved Mine Production Management System Phase 3 – Implementing the improved Mine Production Mangement System • Short Term Initiatives to improve Mine Production Management System • Long Term Initiatives to improve Mine Production Management System Phase 4 – Audit the Effectiveness of the Mine Production Management System implemented Sample Implementation of such a Programme in one mining company • The use of highly qualified external experts for auditing the key mine systems and processes • Total value of short term cost reduction and value benefit up to $263M, including: • $89M within one year (2014) – short term initiatives and additional benefits, including $35M in the processing plants (improvements in extraction) • $76M US additional benefits (2015) • Optimising the number of employees in the underground mine (currently 850, target 450 employees) by optimising equipment and improving mine planning • Strong downward trend in both cash costs and all-in sustaining costs, which were down 17% and 7% respectively on Q2 2013 and 28% and 25% respectively on Q3 2012. • Located in Africa • 4 mines • London Stock Exchange – FTSE250 • 5 000 employees • Income - $1.087B • 600 000 ounces per year
  • 11. Activities Feb,2014 Mar,2014 Apr,2014 May,2014 June,2014 July,2014 Aug,2014 Sept,2014 Oct,2014 Nov,2014 Dec,2014 Jan,2015 Feb,2015 Mar,2015 Apr,2015 May,2015 June,2015 July,2015 Aug,2015 Sept,2015 Oct,2015 Nov,2015 Dec,2015 Jan,2016 Feb,2016 MineShortTermEffectivenessmanagement Express analysis of the Mine Business Effectiveness based one Mine Stage 1 – Analysing and Optimising Mine Expense Profile • Analysis and identification • Implementing initiatives Stage 2 – Expert Cost & Benefit Analysis • Analysis and identification • Implementing initiatives Stage 3 – Accountable Cost & Benefit Management • Module 1 – Developing Minimum Required Conditions of Organisational Effectiveness • Module 2 – Back to Basics • Module 3 - Optimisation • Module 4 – Linking optimisation with budget • Module 5 - Implementation MineLongTermEffectivenessManagement Phase 1 – Analysing the effectiveness of the current elements of the Mine Production management System Phase 2 – Designing the improved Mine Production Management System Phase 3 – Implementing the improved Mine Production Mangement System • Short Term Initiatives to improve Mine Production Management System • Long Term Initiatives to improve Mine Production Management System Phase 4 – Audit the Effectiveness of the Mine Production Management System implemented Sample Implementation of such a Programme in one mining company • Implementing the Accountable Management System that focuses on improving people, structure and work management  Organisational structure - Significant changes to staffing structures and levels resulting in a reduction of 27% of international employees in 2013 and a reduction of 37% in contractors on site. • Improving the system of integrated planning : • Long term mine planning • Capacity planning with constraints • Short term planning and scheduling • Integration of maintenance planning • Delivery of the production plan for the first time in 3 years • Reduction in cost below the planned indicator of $925 per ounce • Located in Africa • 4 mines • London Stock Exchange – FTSE250 • 5 000 employees • Income - $1.087B • 600 000 ounces per year
  • 12. If YOU had started last Year YOU would see the Improvement now 1.October, 2012 - the start of the analysing the current business effectiveness (operation review) 2.January, 2013 – the start of the implementation of the mine effectiveness improvement programme 3.May, 2013 – the announcement of the first results of the implementation of the programme 4.July, 2013 - the announcement of first Half year (2013) result 5.October, 2013 – the announcement of the production –financial results for the third quarter and intermediate results of the implementation of the effectiveness improvement programme (cost reduction and additional benefits generation) 2 3 4 5
  • 13. For more Information go to www.totalmanagementsys.com or send Questions and/or Comments to: info@totalmanagementsys.com