SlideShare une entreprise Scribd logo
1  sur  12
Télécharger pour lire hors ligne
St
Peter’s
Church,
Bournemouth

Options
Appraisal



Report
prepared
for
the
St
Peter’s
Development
Group

By
Victoria
Pirie

January
2015



Executive
Summary

This
report
reviews
the
proposed
development
of
St
Peter’s
Church
in
the
context
of
making

a
capital
funding
application
to
the
Heritage
Lottery
Fund
(HLF)
for
conservation
and

restoration
work,
interpretation,
and
a
learning
and
community
programme.
The
report

reviews
the
elements
of
the
Development
Project
programme
and
makes
recommendations

taking
account
of
HLF
funding
requirements;
heritage
need;
conservation
and
restoration

outline
costs;
and
capacity
to
deliver.




The
Development
Project
aims
to:
1. “build‐up
community
in
our
town
centre;
and

2. make
our
building
fit
for
purpose
to
serve
both
the
Church
community
and
those

with
whom
it
shares
partnership.

The
church
building
needs
to
be
a
safe
space
in

which
the
building
of
community
can
thrive.”

(St
Peter’s
Development
Project
Minutes
29
April
2013)

Studies
and
reports
by
the
Diocesan
architect
in
2008,
2013
and
2014
consider
the
heritage

significance;
risks;
work
required
to
conserve,
restore
and
maintain
the
historic
fabric
of
St

Peter’s
and
the
Chapel
of
the
Resurrection,
and
possible
extensions
to
the
church
for
new

public
facilities.
The
Feasibility
Study
(2013:29)
indicates
approximate
gross
conservation

and
building
costs.
These
costs
do
not
include
all
proposed
or
suggested
building
works.



The
Literature
and
Music
Centre
building
and
running
costs
are
currently
not
known.

HLF

has
indicated
a
reluctance
to
fund
new
build
as
they
prioritise
existing
heritage
at
risk.


The
East
end
new
building
development
and
running
costs
are
currently
not
known.
As
the

heritage
need
being
met
by
the
new
building
is
not
defined
HLF
are
not
likely
to
consider

funding
support.



Governance,
legal
identity
and
accountabilities
are
structured
and
delivered
through
the

Parish
Church
Council.
St
Peter’s
has
small
paid
team
and
is
reliant
primarily
on
volunteer

time
and
commitment
to
drive
the
delivery
of
the
development
ambitions.
The
need
for
a

major
fundraising
campaign
is
recognised
and
work
is
underway
to
develop
fundraising

capacity
and
raise
monies.
HLF
commented
on
the
risk
of
underestimating
the
time
needed

to
fundraise.




The
scale
of
work
to
be
delivered
at
any
one
time
should
take
account
of
capacity
to

successfully
deliver
a
project.
HLF
have
commented
on
the
importance
of
this
and
take

account
of
it
in
their
assessment.




Two
options
are
identified:
Option
1
St
Peter’s
Church
and
Option
2
St
Peter’s
Church
and

the
Literature
and
Music
Centre.
Based
on
current
understanding
of
conservation
and

building
costs;
HLF
priorities
and
likely
grant
funds
available;
capacity
to
develop
fundraising

and
deliver
projects,
Option
1
is
the
most
achievable.
This
suggests
a
phased
approach
to

the
overall
Development
Project
plans.
Actions
and
a
timetable
for
this
are
outlined.

St Peter’s Church- Options Appraisal


 2

1
Purpose

This
report
reviews
the
proposed
development
of
St
Peter’s
Church
in
the
context
of

making
a
capital
funding
application
to
the
Heritage
Lottery
Fund
(HLF)
for

conservation
and
restoration
work,
interpretation,
and
a
learning
and
community

programme.
The
report
reviews
the
elements
of
the
Development
Project

programme
and
makes
recommendations
taking
account
of
HLF
funding

requirements;
heritage
need;
conservation
and
restoration
outline
costs;
and

capacity
to
deliver.
Visitor
and
participant
use
and
demand
is
not
considered
at
this

stage.
This
would
need
to
be
considered
in
the
context
of
Bournemouth’s
existing

museum,
music,
performing
arts,
library
and
festival
provision.





2
The
Development
Project

The
project
aims
to:
1. “build‐up
community
in
our
town
centre;
and

2. make
our
building
fit
for
purpose
to
serve
both
the
Church
community
and

those
with
whom
it
shares
partnership.

The
church
building
needs
to
be
a

safe
space
in
which
the
building
of
community
can
thrive.”

(St
Peter’s
Development
Project
Minutes
29
April
2013)

There
are
four
aspects
to
the
Development
Project:

1. Arts
and
Music;

2. Community
and
Health;

3. Heritage
and
Conservation;
and

4. SACRE
and
Churches
together;


(St
Peter’s
Development
Project
Minutes
29
April
2013)

Achieving
this
includes:



• expanding
the
Church’s
role
and
engagement
with
the
community
and

visitors
to
Bournemouth;


• conservation
and
restoration
the
historic
fabric
of
St
Peter’s
Church,
designed

by
the
eminent
Victorian
architect
George
Edmund
Street
and
Grade
I
listed;

and

• creating
a
vibrant
and
active
place
that
has
events
and
activities
throughout

the
year.

(Ken
Mantock
pers
comm
July
2014)



Studies
and
reports
by
the
Diocesan
architect
in
2008,
2013
and
2014
considered

possible
extensions
to
the
church
for
new
public
facilities;
work
required
to

conserve,
restore
and
maintain
the
historic
fabric
of
St
Peter’s
and
the
Chapel
of
the

Resurrection;
to
restore
the
organ,
and
a
improve
heating,
lighting
and
acoustics.



The
St
Peter’s
Development
Group
resolved
(minutes
9
June
2014)
to
focus
on:

• conservation
and
restoration
of
St
Peter’s
church;

• building
works,
including
improving
access
and
potential
use,
to
the
Chapel
of

the
Resurrection;

• developing
a
café
for
visitors
within
the
church;

St Peter’s Church- Options Appraisal


 3

• creating
a
new
build
Literary
and
Music
Centre.
Celebrating
St
Peter’s
and

Bournemouth’s
music
and
literary
heritage
in
an
extension
to
the
north
side

of
the
church
‐
the
‘shopfront’extension;

• building
a
separate
single
storey
building
for
music,
learning,
events
and

public
use
at
the
east
end
of
the
church;
and

• ground
clearance
and
improvement
works
to
the
Churchyard
grounds

including
remodeling
the
entrance.



The
building
works
to
the
Chapel
of
the
Resurrection
are
underway
and
due
to
be

completed
in
2015.
Volunteer
work
has
cleared
and
improved
the
churchyard

grounds.
Café
development
is
underway
and
due
to
open
in
2015.
A
fundraising

campaign,
activities,
appropriate
governance
and
management
are
in
development.



Music
development
is
being
pursued
in
partnership
with
Bournemouth
University.

St
Peter’s
Church
and
the
Chapel
of
the
Resurrection
were
venues
during
the
2014

Bournemouth
Arts
Festival
by
the
Sea.
There
are
plans
for
a
Shelley
Festival
in
2016

linked
to
the
bicentennial
of
Mary
Shelley’s
Frankenstein,
started
in
1816
and

published
in
1818.




St
Peter’s
has
and
is
developing
its
social
role
at
the
centre
of
the
town’s
diverse

community.
This
includes
the
well‐regarded
nightclub
chaplaincy,
interfaith

conferences
and
events,
and
supporting
work
with
homeless
people.
HLF

acknowledges
these
strengths,
which
can
form
core
elements
of
delivering
HLF

People
and
Community
outcomes
(see
below).



3
Heritage
Lottery
Fund


An
application
for
substantial
capital
and
programme
funding
is
central
to
achieving




the
development
ambitions.
Therefore
considering
HLF
priorities
and
availability
of

funding
is
critical.



At
the
core
of
the
HLF
assessment
process
is
how
a
project
delivers
a
range
of

defined
outcomes.
HLF
weight
these
and
expect
more
outcomes
to
be
delivered
the

larger
the
grant
request.
There
are
outcomes
for
Heritage,
People
and
Communities

(Heritage
Lottery
Fund
2013a).



Heritage‐
with
HLF
investment
heritage
will
be:

• better
managed‐
weighted
for
Heritage
Grants

• in
better
condition‐
weighted
for
Heritage
Grants

• better
interpreted
and
explained

• identified/recorded



People‐
with
HLF
investment,
people
will
have:

• developed
skills‐
weighted
for
Heritage
Grants

• learnt
about
heritage
‐weighted
for
Our
Heritage
and
Heritage
Grants

• changed
their
attitudes
and/or
behaviour

• had
an
enjoyable
experience

• volunteered
time

St Peter’s Church- Options Appraisal


 4



Communities‐
with
HLF
investment:

• negative
environmental
impacts
will
be
reduced‐
weighted
for
Heritage

Grants

• more
people
and
a
wider
range
of
people
will
have
engaged
with
heritage‐

weighted
for
Heritage
Grants

• your
local
area/community
will
be
a
better
place
to
live,
work
or
visit

• your
local
economy
will
be
boosted



Public
benefit
as
expressed
in
the
People,
Communities
and
Heritage
interpretation

outcomes
are
vital
to
HLF.
They
also
seek
value
for
money.



Bournemouth
is
currently
a
SW
HLF
priority
area
and
following
initial
discussions

with
HLF
they
acknowledge:

• St
Peter’s
heritage
value,
central
location
in
the
town
and
wider
role;
and

• the
interest
at
senior
Bournemouth
Borough
Council
level
in
the
role
and

place
of
St
Peter’s
in
the
town.



HLF
referred
to:

• demonstrating
need
for
the
project.
St
Peter’s
fulfilling
a
social
role
in
the

Town
centre
as
well
as
being
a
place
of
worship;

• the
need
to
have
an
appropriate
scale
project.
HLF
noted
the
overall

Development
Project;

• the
need
to
have
an
affordable
scheme
in
the
context
of
the
budget;


• that
enough
of
the
grant
needs
to
be
spent
on
the
heritage
in
need;

Conservation
is
a
priority,
as
is
securing
and
engaging
with
heritage.
New

build
needs
to
be
proportionate
within
the
overall
proposal
to
HLF;
and

• there
may
be
a
need
to
prioritise
work
and
proceed
in
stages.




Competition
for
funding
is
high
and
the
SW
Regional
Committee
has
around
£1.8
to

£1.9
million
to
allocate
each
quarter.
The
committee
allocates
around
£750,000
to

£1
million
per
project;
resources
make
it
difficult
to
allocate
more.
While
5%
is
the

minimum
matched
funding
required
in
practice
this
is
closer
to
30%
of
total
project

value.



Two
grant
schemes
are
of
relevance
to
St
Peter’s
Heritage
Grants
and
Our
Heritage.



Heritage
Grants
for
grants
over
£100,000.
Grant
application
under
£2
million
are

decided
by
the
regional
HLF
committee
and
grants
over
£2
million
by
the
national

committee.
To
achieve
an
award
of
over
£2
million
requires
heritage
of
substantive

national
significance.
St
Peter’s
has
significant
heritage
value
and
is
more
likely
to

compete
successfully
at
a
regional
level.




The
consultant
has
suggested
that
as
the
Chapel
of
Resurrection
building
work
is

underway
and
there
is
the
ambition
to
increase
use
and
access
to
the
chapel
an

application
to
the
HLF
Our
Heritage
grants
could
fund
a
learning
and
community

programme
in
the
chapel.
This
provides
an
opportunity
to
demonstrate
to
HLF

St Peter’s Church- Options Appraisal


 5

successful
project
delivery
and
test
St
Peter’s
capacity
to
deliver
an
HLF
funded

project
albeit
it
at
a
significantly
smaller
scale
than
the
Church.





4
Heritage
significance,
risk
and
need

St
Peter’s
Church
and
churchyard
includes
six
listed
buildings
and
monuments
(see

Appendix
One):



• St
Peter’s
Church‐
Grade
I
listed
and
one
of
three
Grade
I
listed
buildings
in

Bournemouth;


• The
Chapel
of
the
Resurrection‐
Grade
II
listed.
War
Memorial
and
mortuary

chapel;

• Gravestones
and
tombs
of
the
Shelley,
Tregonwell
and
Campbell
families

and
vicars
of
St
Peter’s‐
Grade
II
listed
monuments;


• Terrace
gravestones
to
the
east
of
St
Peter’s
Church‐
Grade
II
listed
tomb

chests
and
cross
headstones;

• The
Churchyard
Cross
‐
Grade
II
listed;
and


• The
Church
Lychgate
‐
Grade
II
listed.




The
2013
Feasibility
Study
identifies
heritage
significance,
risk,
need
and
works

required
to
address
St
Peter’s
Church
and
the
Chapel
of
the
Resurrection.



St
Peter’s
Church
heritage
significance
is
based
on
design,
architecture,
interior
wall

paintings,
stained
glass,
wood,
metal
and
stonework
and
role
in
Bournemouth’s

history.
There
is
significant
building
fabric
deterioration.
The
organ,
south
clerestory

windows
and
wall
paintings
are
in
greatest
need
of
work.
The
window
stonework
is

deteriorating
and
will
become
unsafe
and
there
is
continuing
deterioration
to
the

wall
paintings.




The
Chapel
of
the
Resurrection
was
built
as
a
mortuary
chapel
and
WW1
war

memorial.
The
interior
is
in
a
poor
state
of
repair
and
the
building
is
underused.



Music
and
literary
connections
form
the
more
‘intangible’
and
less
well
known

aspects
of
St
Peter’s
heritage.
HLF
have
an
increasing
focus
on
Intangible
Cultural

Heritage
(UNESCO
nd)
and
consequently
St
Peter’s
‘intangible’
heritage
is
of
interest

to
them.





5
Costs

The
Feasibility
Study
(2013:29)
indicates
approximate
gross
conservation
and

building
costs.
These
costs
do
not
include
all
proposed
or
suggested
building
works.



5.1
St
Peter’s
Church

Conservation
and
building
costs

Fabric
repair
and
conservation
 £405,000

Wallpainting
conservation
 
 £181,500

St Peter’s Church- Options Appraisal


 6

Organ
restoration
 
 
 £850,000

Lighting
and
sound
installation
 £152,250

Heating
 
 
 
 £421,250

Sub‐
division
of
the
Church
 
 costs
unknown

Total
 
 
 
 









£2,010,000
 
 
 
 



These
costs
include
professional
fees,
contigencies
and
VAT.
Builders
work
in

conjunction
with
electrical
and
sound
installations
are
not
included.
Work
to
the

electrical
infrastructure
is
not
included.
The
organ
costings
are
an
estimate
and
do

not
include
transportation.
VAT
on
approved
alterations
to
a
listed
building
may
be

recoverable
through
the
Listed
Places
of
Worship
Grant.
This
would
reduce
the
total

gross
costs
by
about
20%.



Other
costs


The
above
costs
do
not
include
delivering
interpretation,
learning
and
community

programmes
that
are
essential
in
any
HLF
application.
HLF
expect
that
a
minimum
of

10%
of
overall
project
costs
be
allocated
to
delivering
learning
and
community

outcomes.
Usually
this
is
a
programme
over
three
years
including
the
building
works

period.



These
costs
do
not
include
project
management
and
administration
costs
that
St

Peter’s
will
incur
to
develop
and
deliver
the
two
stage
HLF
application
process
and

project
delivery.




HLF
seek
to
secure
the
long
term
future
of
their
investment
of
what
is
essentially

‘public
money’.
They
require
a
costed
future
management
and
maintenance
plan
for

both
building
and
programme
aspects
of
the
project.

The
value
of
increased

management
and
maintenance
costs
for
up
to
five
years
after
the
building
works
are

completed
can
be
included
as
a
partnership
funding
contribution.



Churchyard
grounds
costs
may
be
incurred
as
part
of
the
building
works.



5.2
Chapel
of
the
Resurrection

Conservation
and
building
costs

Fabric
repair
and
alterations
 
 £185,772



These
costs
include
professional
fees,
contigencies
and
VAT.
Final
costs
depend
on
a

detailed
brief
and
requirements
VAT
on
approved
alterations
to
a
listed
may
be

recoverable
through
the
Listed
Places
of
Worship
Grant.
This
would
reduce
the
total

gross
costs
by
about
20%.



Other
costs

Costs
associated
with
developing
and
delivering
increased
use
of
the
building
have

not
been
identified.



As
suggested
above
these
costs
would
be
eligible
for
the
HLF
Our
Heritage

programme.

St Peter’s Church- Options Appraisal


 7



5.3
Literature
and
Music
Centre

Building
and
running
costs
are
currently
not
known.
It
is
suggested
volunteers
would

staff
the
centre.
However,
there
will
be
management,
building
and
programme

costs.




HLF
has
indicated
a
reluctance
to
fund
new
build
as
they
prioritise
existing
heritage

at
risk.
For
St
Peter’s,
the
conservation
and
building
needs
present
the
strongest

priority.
A
clear
and
strong
case
for
visitor
demand
and
use
of
the
Centre
would
be

required
for
the
Centre
to
be
included
as
part
of
an
HLF
proposal.
It
is
assumed
this

would
also
underpin
a
viable
business
plan
for
the
centre.
At
this
time
visitor
use
and

demand
has
not
been
investigated.
This
would
need
to
take
account
of
existing

museum,
music,
performing
arts,
library
and
festival
provision
and
use.
The
potential

for
more
events
in
the
Church
and
Chapel
of
the
Resurrection
and
links
to
existing

cultural
provision
should
be
explored
e.g.
the
concert
and
use
of
the
Chapel
for
a

visual
art
and
media
installation
as
part
of
the
2014
Arts
Festival
by
the
Sea.



5.4
East
end
new
building

Building
and
running
costs
are
currently
not
known,
but
are
likely
to
be
in
the
region

of
£2
million
(Ken
Mantock
pers
comm
January
2015).
As
the
heritage
need
being

met
by
the
new
building
is
not
defined
HLF
are
not
likely
to
consider
funding

support.



5.5
Churchyard
grounds

Improvements
to
the
grounds
and
remodeling
the
entrance
costs
are
currently
not

known.
As
noted
above
the
Churchyard
and
grounds
include
five
listed
buildings,

monuments
and
structures.
Apart
from
the
Chapel
it
is
not
clear
whether
there
are

condition
assessments
the
listed
monuments.





6
Project
delivery
capacity

Governance,
legal
identity
and
accountabilities
are
structured
and
delivered
through

the
Parish
Church
Council.
St
Peter’s
has
small
paid
team
and
a
small
and
active

volunteer
team.
The
St
Peter’s
Development
Group
comprises
paid
and
volunteer

members
and
is
reliant
primarily
on
volunteer
time
and
commitment
to
drive
the

delivery
of
the
development
ambitions.



Additional
capacity
that
is
essential
for
delivering
any
conservation
and
building

work,
interpretation,
learning
and
community
programmes,
and
project

management
and
administration
can
be
costed
as
part
of
an
HLF
proposal.
However,

additional
staff
require
management,
workspace
and
integration
with
the
daily
work

of
St
Peter’s.
An
extensive
conservation
and
building
work
project
will
inevitably

disrupt
the
daily
work
of
St
Peter’s
and
access
to
the
Church
and
Churchyard.
This

will
require
active
management
and
communication.




The
need
for
a
major
fundraising
campaign
is
recognised
and
work
is
underway
to

develop
fundraising
capacity
and
raise
monies.
HLF
commented
on
the
risk
of

St Peter’s Church- Options Appraisal


 8

underestimating
the
time
needed
to
fundraise.
They
do
not
expect
all
partnership

funding
(HLF’s
term
for
matched
funding)
to
be
in
place
when
a
Round
One

application
is
submitted.

Partnership
funding
needs
to
be
in
place
at
Round
Two.

HLF
allow
up
to
two
years
between
Round
One
and
submission
of
Round
Two.



The
scale
of
work
to
be
delivered
at
any
one
time
should
take
account
of
capacity
to

successfully
deliver
a
project.
HLF
have
commented
on
the
importance
of
this
and

take
account
of
it
in
their
assessment.






7
Options
and
conclusions

In
the
context
of
HLF’s
focus
on
heritage
the
options
consider
St
Peter’s
Church
and

the
Literature
and
Music
Centre
in
relation
to
HLF
funding
requirements
and
scale
of

funding;
known
costs
and
St
Peter’s
delivery
capacity.
The
Chapel
of
Resurrection
is

not
included
as
building
work
is
underway
in
a
separate
project.



Option
1
St
Peter’s
Church

The
heritage
significance
of
St
Peter’s
building
and
interior
are
recognised
through

Grade
I
listed
status
and
the
2013
Feasibility
Study
identifies
the
heritage
risk
and

needs
of
the
building.
HLF
have
indicated
that
they
prioritise
heritage
at
risk.
There

are
approximate
gross
costings.
However,
not
all
building
costs
are
known
e.g.

building
sub
division
and
electrical
works.



Interpretation,
learning
and
community
programme
costs
are
yet
to
be
identified,

but
can
be
anticipated
to
be
around
£200,000
over
three
years
as
HLF
expect
these

elements
to
account
for
about
10%
of
total
project
costs.
Project
management
and

administration
costs
are
yet
to
be
identified.



There
are
likely
to
be
costs
associated
with
generating
the
plans
and
documentation

required
for
an
HLF
Round
One
application.
In
particular
conservation
and
building

plans
and
documentation
to
RIBA
Stage
1,
which
will
involve
architects
and
other

building
professionals
time.
Grant
funding
for
Round
Two
development
costs
form

part
of
the
Round
One
application.



Current
approximate
total
project
costs
£2,210,000
of
which
HLF
may
fund

£750,000‐
£1,000,000
of
eligible
costs.
The
funding
gap
based
on
the
lower
HLF
grant

is
£1,460,000.



Option
2
St
Peter’s
Church
and
the
Literature
and
Music
Centre

The
St
Peter’s
elements
are
as
in
option
1.
The
Literature
and
Music
Centre
does
not

specifically
have
elements
of
heritage
at
risk.
While
awareness
and
understanding
of

the
significance
of
Bournemouth’s
literary
and
music
heritage,
including
St
Peter’s

Shelley
family
connections,
are
not
as
well
known
as
they
could
be,
visitor
demand

and
use
of
a
centre
has
to
be
tested.




Known
approximate
project
costs
are
those
for
option
1
above
as
the
Centre

building,
running
and
programme
costs
have
not
yet
been
identified.

St Peter’s Church- Options Appraisal


 9



The
table
below
summarises
the
two
options.

Option
 Approx

Building

Costs

Approx

prog
costs

HLF

priority

yes

uncertain
no

Total
 Likely
HLF

grant

Funding

gap
based

on
£750K

grant

Issues
with

potential
costs

to
be
addressed

1
St

Peter’s


£2,010,000
 £200,000
 yes
 £2,210,00
 £750,00‐
£1,000,000

£1,460,000
 Updated

conservation

and
building

works
plans.



Project

management

and

Administration.



Round
One
and

Two
application

costs.



Churchyard

ground
works

may
also
be

needed



Disruption
to

use
of
the

Church.

2
St

Peter’s


and
the

Lit
and

Music

centre

£2
million

plus
as
costs

not
known

for
the
new

build

Min

£200,000

St
Peter’s

yes



Centre

uncertain/
no

Min

£2,210,00

£750,000‐
£1,000,000

Min

£1,460,000

Centre

unknown

As
above
for
St

Peter’s.



Time
and

possible
cost

implications
for

St
Peter’s
work

as
Centre
design

and
planning

work
is

undertaken.




Centre
design,

build
and
run

costs.



Additional

project

management

and
admin
costs.



Churchyard

ground
works

related
to
the

Centre
may
be

needed



Disruption
to

use
of
the

Church
from

Centre
building

works.



St Peter’s Church- Options Appraisal


 10



Conclusions

Option
1
is
the
most
achievable
option.
Based
on
current
understanding
of

conservation
and
building
costs;
HLF
priorities
and
likely
grant
funds
available;

capacity
to
develop
fundraising
and
deliver
projects.
This
suggests
a
phased

approach
to
the
overall
Development
Project
plans.



Phase
1‐
Improvement
works
to
the
Chapel
of
the
Resurrection
and
application
to

HLF
Our
Heritage
for
a
one
year
interpretation,
learning
and
community
programme.

Start
HLF
Heritage
Grants
Round
One
application
development
for
St
Peter’s
Church.

Start
five
year
fundraising
campaign.



Phase
2‐
Review
the
need
for
and
cost
improvements
works
to
the
Churchyard
and

determine
whether
these
form
part
of
Phase
2
or
are
a
separate
project.
Submit
HLF

Heritage
Grants
Round
One
and
Two
applications
for
St
Peter’s.
Deliver
the

conservation
and
restoration
of
St
Peter’s
Church
including
a
three
year

interpretation,
learning
and
community
programme.
This
could
include
elements

relating
to
St
Peter’s
literary
and
music
heritage.




Phase
3‐
Based
on
delivery
of
the
Phase
1
and
2
programmes
review
likely
visitor

demand
and
use
of
a
Literature
and
Music
Centre,
and
review
St
Peter’s
needs
for

additional
public
space
for
events.
Determine
the
scale,
cost,
and
running
costs
of

any
new
build.




Below
is
an
outline
timetable.
Issues
that
will
impact
on
this
are:

• fundraising;

• HLF
application
development
and
assessment;

• procurement;

• interdependencies
of
the
conservation
and
building
works
e.g.
the
organ;


“Waiting
lists
from
the
moment
of
contract
signing
are
typically
two
years.

Thereafter
the
work
might
be
expected
to
be
achieved
within
perhaps
nine
or

ten
months.”
(2013
Feasibility
Study:6)



Phase
 Action
 2015
 2016
 2017
 2018
 2019
 2020

1
 Chapel
of
Resurrection
building
works
 
 
 
 
 
 


 HLF
Our
Heritage
bid
and
programme
 
 
 
 
 
 


 HLF
Heritage
Grants
Round
1
bid
development
 
 
 
 
 
 


 Fundraising

 
 
 
 
 
 

2
 Review
need
for
and
cost
Churchyard
grounds

work
as
part
of
the
Heritage
Grants
bid
or

separate
project.



 
 
 
 
 


 HLF
Heritage
Grants
Round
1
submission
and

assessment.


 
 
 
 
 


 HLF
Heritage
Grants
Round
2
development
and

submission


 
 
 
 
 


 St
Peter’s
Conservation
Project
 
 
 
 
 
 

3
 Review
visitor
demand/use
of
a
Literature
and

Music
Centre.
Review
St
Peter’s
needs
for

additional
public
space


 
 
 
 
 

St Peter’s Church- Options Appraisal


 11

Sources

English
Heritage
The
National
Heritage
List
for
England

http://list.english‐heritage.org.uk/results.aspx




Heritage
Lottery
Fund
(December
2013a)
Heritage
Grants
Application
guidance

http://www.hlf.org.uk/looking‐funding/our‐grant‐programmes/heritage‐grants



Heritage
Lottery
Fund
(December
2013b)
Our
Heritage
Application
guidance

http://www.hlf.org.uk/looking‐funding/our‐grant‐programmes/our‐heritage



Ken
Mantock
July
2014
email
correspondence



Michael
Drury
Architects
(May
2008)
Bournemouth
St
Peter:
Church
Amenities



Michael
Drury
(March
2014)
The
Chapel
of
the
Resurrection
at
the
Church
of
St
Peter,

Bournemouth,
Dorset
Condition
Report.



St
Anne’s
Gate
Architects
(March
2013)
Feasibility
Study
The
Church
of
St
Peter

Bournemouth
2013
Appeal.



St
Peter’s
Development
Project
Minutes
29
April
2013



St
Peter’s
Development
Group
Minutes
9
June
2014



UNESCO
(nd)
What
is
Intangible
Cultural
Heritage?
UNESCO

http://www.unesco.org/culture/ich/doc/src/01851‐EN.pdf

St Peter’s Church- Options Appraisal


 12



Appendix
One



Heritage
Significance

St
Peter’s
Church
and
churchyard
includes
six
listed
buildings
and
monuments:



St
Peter’s
Church1

a
Grade
I
listed
church
is
one
of
only
three
Grade
I
listed
buildings

in
Bournemouth.
The
other
two,
also
churches,
are
St
Stephen’s
and
St
Clement’s.

The
eminent
architect
George
Edmund
Street2

designed
St
Peter’s.
He
was
known
for

his
use
of
Gothic
style
and
famous
for
designing
the
Royal
Courts
of
Justice
in
The

Strand,
London.




The
church
was
built
between
1856
and
1879
replacing
an
earlier
building.
The
south

aisle
of
which
was
retained
as
it
was
only
built
in
1853.
The
spire
is
an
important

landmark
and
the
highly
decorated
interior
has
fine
stained
glass,
wall
painting,

wood,
metal
and
stone
work
by
the
notable
craft
workshops
of
the
day
including

Clayton
and
Bell3
,
and
Morris,
Marshal,
Faulkner
and
Co.
The
vestry
buildings
and

crypt
by
the
eminent
late
Victorian
architect
Sir
T.G.
Jackson
are
later.



The
Chapel
of
the
Resurrection4

is
Grade
II
listed.
Built
in
1925‐26
the
chapel
was

designed
by
the
noted
late
Victorian/early
twentieth
century
architect
Sir
Ninian

Comper5
.
Originally
a
mortuary
chapel
for
the
church
it
is
now
used
once
a
week
for

Holy
Communion.



Gravestones
and
tombs
of
the
Shelley,
Tregonwell
and
Campbell
families
and

vicars
of
St
Peter’s6
.
Grade
II
listed
monuments.
The
Shelley
monument
erected
by

Percy
Bysshe
Shelley
contains
the
poet’s
heart
and
bodies
of
his
parents‐
in‐law

William
and
Mary
Godwin
and
his
wife
Mary
Wollstonecraft
Shelley.
The
Tregonwell

tomb
commemorates
Lewis
Tregonwell
the
founder
of
Bournemouth.



Terrace
gravestones
to
the
east
of
St
Peter’s
Church7
.
Grade
II
listed
tomb
chests

and
cross
headstones.



The
Churchyard
Cross8

is
Grade
II
listed.
Designed
by
George
Edmund
Street
and

carved
by
TW
Earp.



The
Lychgate9

is
Grade
II
listed
and
was
designed
by
George
Edmund
Street.




























































1

http://list.english‐heritage.org.uk/resultsingle.aspx?uid=1153014

2
http://www.architecture.com/Explore/Architects/GeorgeEdmundStreet.aspx

3

Alfred
Bell
was
born
at
Silton,
Dorset
http://stainedglass.llgc.org.uk/person/18

4

http://list.english‐heritage.org.uk/resultsingle.aspx?uid=1324705

5

http://www.scottisharchitects.org.uk/architect_full.php?id=200370

6
http://list.english‐heritage.org.uk/resultsingle.aspx?uid=1108868

7
http://list.english‐heritage.org.uk/resultsingle.aspx?uid=1304485

8

http://list.english‐heritage.org.uk/resultsingle.aspx?uid=1108867

9
http://list.english‐heritage.org.uk/results.aspx?index=151




Contenu connexe

Similaire à St Peters Options Appraisal Jan 2015

Long Term Integrated Community Facilities Plan 2015
Long Term Integrated Community Facilities Plan 2015Long Term Integrated Community Facilities Plan 2015
Long Term Integrated Community Facilities Plan 2015Council2016
 
Routes to success: achieving quality environments for care at end of life
Routes to success: achieving quality environments for care at end of lifeRoutes to success: achieving quality environments for care at end of life
Routes to success: achieving quality environments for care at end of lifeNHS IQ legacy organisations
 
The Way Forward Presentation 10/09/2010
The Way Forward Presentation 10/09/2010The Way Forward Presentation 10/09/2010
The Way Forward Presentation 10/09/2010parish of chester
 
Trent_SIF_Proposal_FINAL_9May2016
Trent_SIF_Proposal_FINAL_9May2016Trent_SIF_Proposal_FINAL_9May2016
Trent_SIF_Proposal_FINAL_9May2016Maya Chaddah
 
Adrians Job ApplicationRecent 2015
Adrians Job ApplicationRecent 2015Adrians Job ApplicationRecent 2015
Adrians Job ApplicationRecent 2015Adrian Taylor
 
Chris Charlton PwC Cv V5
Chris Charlton PwC Cv V5Chris Charlton PwC Cv V5
Chris Charlton PwC Cv V5CjjC001
 
Final portfolio michael voit 140130
Final portfolio michael voit 140130Final portfolio michael voit 140130
Final portfolio michael voit 140130voit1
 
Creative Hubs: Understanding The New Economy (BC, 2016)
Creative Hubs: Understanding The New Economy (BC, 2016)Creative Hubs: Understanding The New Economy (BC, 2016)
Creative Hubs: Understanding The New Economy (BC, 2016)Rony Octavianto
 
Vrc regeneration framework 14 april 2014 technical report
Vrc regeneration framework 14 april 2014 technical reportVrc regeneration framework 14 april 2014 technical report
Vrc regeneration framework 14 april 2014 technical reportShahid Solomon
 
SpokaneCC-Completion-Final-Concept-Design.pdf
SpokaneCC-Completion-Final-Concept-Design.pdfSpokaneCC-Completion-Final-Concept-Design.pdf
SpokaneCC-Completion-Final-Concept-Design.pdfBinhabSultan
 
Leith economic framework presentation dec14
Leith economic framework presentation dec14Leith economic framework presentation dec14
Leith economic framework presentation dec14Greener Leith
 
Version 3 St Peter's review presentation no animation-1
Version 3   St Peter's review presentation no animation-1Version 3   St Peter's review presentation no animation-1
Version 3 St Peter's review presentation no animation-1parish of chester
 
Thinking about EU funding?
Thinking about EU funding?Thinking about EU funding?
Thinking about EU funding?Amplified Events
 
Omaio governance and leadership development program
Omaio governance and leadership development programOmaio governance and leadership development program
Omaio governance and leadership development programKaramea Insley
 
CHP Business Plan 2015_16_Summary
CHP Business Plan 2015_16_SummaryCHP Business Plan 2015_16_Summary
CHP Business Plan 2015_16_SummaryJane Batchelor
 
Presentation of Mr. José Manuel Fernández Riveiro - Secretariat of the Union ...
Presentation of Mr. José Manuel Fernández Riveiro - Secretariat of the Union ...Presentation of Mr. José Manuel Fernández Riveiro - Secretariat of the Union ...
Presentation of Mr. José Manuel Fernández Riveiro - Secretariat of the Union ...FIREMED project
 

Similaire à St Peters Options Appraisal Jan 2015 (20)

Long Term Integrated Community Facilities Plan 2015
Long Term Integrated Community Facilities Plan 2015Long Term Integrated Community Facilities Plan 2015
Long Term Integrated Community Facilities Plan 2015
 
Routes to success: achieving quality environments for care at end of life
Routes to success: achieving quality environments for care at end of lifeRoutes to success: achieving quality environments for care at end of life
Routes to success: achieving quality environments for care at end of life
 
The Way Forward Presentation 10/09/2010
The Way Forward Presentation 10/09/2010The Way Forward Presentation 10/09/2010
The Way Forward Presentation 10/09/2010
 
State Of LCR April2010
State Of LCR April2010State Of LCR April2010
State Of LCR April2010
 
Trent_SIF_Proposal_FINAL_9May2016
Trent_SIF_Proposal_FINAL_9May2016Trent_SIF_Proposal_FINAL_9May2016
Trent_SIF_Proposal_FINAL_9May2016
 
Adrians Job ApplicationRecent 2015
Adrians Job ApplicationRecent 2015Adrians Job ApplicationRecent 2015
Adrians Job ApplicationRecent 2015
 
Chris Charlton PwC Cv V5
Chris Charlton PwC Cv V5Chris Charlton PwC Cv V5
Chris Charlton PwC Cv V5
 
Final portfolio michael voit 140130
Final portfolio michael voit 140130Final portfolio michael voit 140130
Final portfolio michael voit 140130
 
Creative Hubs: Understanding The New Economy (BC, 2016)
Creative Hubs: Understanding The New Economy (BC, 2016)Creative Hubs: Understanding The New Economy (BC, 2016)
Creative Hubs: Understanding The New Economy (BC, 2016)
 
Vrc regeneration framework 14 april 2014 technical report
Vrc regeneration framework 14 april 2014 technical reportVrc regeneration framework 14 april 2014 technical report
Vrc regeneration framework 14 april 2014 technical report
 
SpokaneCC-Completion-Final-Concept-Design.pdf
SpokaneCC-Completion-Final-Concept-Design.pdfSpokaneCC-Completion-Final-Concept-Design.pdf
SpokaneCC-Completion-Final-Concept-Design.pdf
 
Leith economic framework presentation dec14
Leith economic framework presentation dec14Leith economic framework presentation dec14
Leith economic framework presentation dec14
 
Version 3 St Peter's review presentation no animation-1
Version 3   St Peter's review presentation no animation-1Version 3   St Peter's review presentation no animation-1
Version 3 St Peter's review presentation no animation-1
 
Thinking about EU funding?
Thinking about EU funding?Thinking about EU funding?
Thinking about EU funding?
 
CV_2016
CV_2016CV_2016
CV_2016
 
Bitesize 2 - Sandra Turner EU Funding
Bitesize 2  - Sandra Turner EU FundingBitesize 2  - Sandra Turner EU Funding
Bitesize 2 - Sandra Turner EU Funding
 
4. Ian Triplow - developing good governance... GOV011015
4. Ian Triplow - developing good governance... GOV0110154. Ian Triplow - developing good governance... GOV011015
4. Ian Triplow - developing good governance... GOV011015
 
Omaio governance and leadership development program
Omaio governance and leadership development programOmaio governance and leadership development program
Omaio governance and leadership development program
 
CHP Business Plan 2015_16_Summary
CHP Business Plan 2015_16_SummaryCHP Business Plan 2015_16_Summary
CHP Business Plan 2015_16_Summary
 
Presentation of Mr. José Manuel Fernández Riveiro - Secretariat of the Union ...
Presentation of Mr. José Manuel Fernández Riveiro - Secretariat of the Union ...Presentation of Mr. José Manuel Fernández Riveiro - Secretariat of the Union ...
Presentation of Mr. José Manuel Fernández Riveiro - Secretariat of the Union ...
 

Plus de Kenneth Mantock FRSA

Plus de Kenneth Mantock FRSA (6)

CHAIRMANS REPORT TO AGM 2016
CHAIRMANS REPORT TO AGM 2016CHAIRMANS REPORT TO AGM 2016
CHAIRMANS REPORT TO AGM 2016
 
St Peter's Appeal Launch Leaflet
St Peter's Appeal Launch LeafletSt Peter's Appeal Launch Leaflet
St Peter's Appeal Launch Leaflet
 
CHAIRMAN'S REPORT TO AGM 2015
CHAIRMAN'S REPORT TO AGM 2015CHAIRMAN'S REPORT TO AGM 2015
CHAIRMAN'S REPORT TO AGM 2015
 
St Peters Display Boards
St Peters Display BoardsSt Peters Display Boards
St Peters Display Boards
 
St Peters Feasibility Study 2015
St Peters Feasibility Study  2015St Peters Feasibility Study  2015
St Peters Feasibility Study 2015
 
CHAIRMANS REPORT TO AGM 2014 v1
CHAIRMANS REPORT TO AGM 2014 v1CHAIRMANS REPORT TO AGM 2014 v1
CHAIRMANS REPORT TO AGM 2014 v1
 

St Peters Options Appraisal Jan 2015

  • 1. St
Peter’s
Church,
Bournemouth
 Options
Appraisal
 
 Report
prepared
for
the
St
Peter’s
Development
Group
 By
Victoria
Pirie
 January
2015
 
 Executive
Summary
 This
report
reviews
the
proposed
development
of
St
Peter’s
Church
in
the
context
of
making
 a
capital
funding
application
to
the
Heritage
Lottery
Fund
(HLF)
for
conservation
and
 restoration
work,
interpretation,
and
a
learning
and
community
programme.
The
report
 reviews
the
elements
of
the
Development
Project
programme
and
makes
recommendations
 taking
account
of
HLF
funding
requirements;
heritage
need;
conservation
and
restoration
 outline
costs;
and
capacity
to
deliver.

 
 The
Development
Project
aims
to: 1. “build‐up
community
in
our
town
centre;
and
 2. make
our
building
fit
for
purpose
to
serve
both
the
Church
community
and
those
 with
whom
it
shares
partnership.

The
church
building
needs
to
be
a
safe
space
in
 which
the
building
of
community
can
thrive.”
 (St
Peter’s
Development
Project
Minutes
29
April
2013)
 Studies
and
reports
by
the
Diocesan
architect
in
2008,
2013
and
2014
consider
the
heritage
 significance;
risks;
work
required
to
conserve,
restore
and
maintain
the
historic
fabric
of
St
 Peter’s
and
the
Chapel
of
the
Resurrection,
and
possible
extensions
to
the
church
for
new
 public
facilities.
The
Feasibility
Study
(2013:29)
indicates
approximate
gross
conservation
 and
building
costs.
These
costs
do
not
include
all
proposed
or
suggested
building
works.
 
 The
Literature
and
Music
Centre
building
and
running
costs
are
currently
not
known.

HLF
 has
indicated
a
reluctance
to
fund
new
build
as
they
prioritise
existing
heritage
at
risk.

 The
East
end
new
building
development
and
running
costs
are
currently
not
known.
As
the
 heritage
need
being
met
by
the
new
building
is
not
defined
HLF
are
not
likely
to
consider
 funding
support.
 
 Governance,
legal
identity
and
accountabilities
are
structured
and
delivered
through
the
 Parish
Church
Council.
St
Peter’s
has
small
paid
team
and
is
reliant
primarily
on
volunteer
 time
and
commitment
to
drive
the
delivery
of
the
development
ambitions.
The
need
for
a
 major
fundraising
campaign
is
recognised
and
work
is
underway
to
develop
fundraising
 capacity
and
raise
monies.
HLF
commented
on
the
risk
of
underestimating
the
time
needed
 to
fundraise.

 
 The
scale
of
work
to
be
delivered
at
any
one
time
should
take
account
of
capacity
to
 successfully
deliver
a
project.
HLF
have
commented
on
the
importance
of
this
and
take
 account
of
it
in
their
assessment.

 
 Two
options
are
identified:
Option
1
St
Peter’s
Church
and
Option
2
St
Peter’s
Church
and
 the
Literature
and
Music
Centre.
Based
on
current
understanding
of
conservation
and
 building
costs;
HLF
priorities
and
likely
grant
funds
available;
capacity
to
develop
fundraising
 and
deliver
projects,
Option
1
is
the
most
achievable.
This
suggests
a
phased
approach
to
 the
overall
Development
Project
plans.
Actions
and
a
timetable
for
this
are
outlined.

  • 2. St Peter’s Church- Options Appraisal
 
 2
 1
Purpose
 This
report
reviews
the
proposed
development
of
St
Peter’s
Church
in
the
context
of
 making
a
capital
funding
application
to
the
Heritage
Lottery
Fund
(HLF)
for
 conservation
and
restoration
work,
interpretation,
and
a
learning
and
community
 programme.
The
report
reviews
the
elements
of
the
Development
Project
 programme
and
makes
recommendations
taking
account
of
HLF
funding
 requirements;
heritage
need;
conservation
and
restoration
outline
costs;
and
 capacity
to
deliver.
Visitor
and
participant
use
and
demand
is
not
considered
at
this
 stage.
This
would
need
to
be
considered
in
the
context
of
Bournemouth’s
existing
 museum,
music,
performing
arts,
library
and
festival
provision.
 
 
 2
The
Development
Project
 The
project
aims
to: 1. “build‐up
community
in
our
town
centre;
and
 2. make
our
building
fit
for
purpose
to
serve
both
the
Church
community
and
 those
with
whom
it
shares
partnership.

The
church
building
needs
to
be
a
 safe
space
in
which
the
building
of
community
can
thrive.”
 (St
Peter’s
Development
Project
Minutes
29
April
2013)
 There
are
four
aspects
to
the
Development
Project:
 1. Arts
and
Music;
 2. Community
and
Health;
 3. Heritage
and
Conservation;
and
 4. SACRE
and
Churches
together;

 (St
Peter’s
Development
Project
Minutes
29
April
2013)
 Achieving
this
includes:


 • expanding
the
Church’s
role
and
engagement
with
the
community
and
 visitors
to
Bournemouth;

 • conservation
and
restoration
the
historic
fabric
of
St
Peter’s
Church,
designed
 by
the
eminent
Victorian
architect
George
Edmund
Street
and
Grade
I
listed;
 and
 • creating
a
vibrant
and
active
place
that
has
events
and
activities
throughout
 the
year.
 (Ken
Mantock
pers
comm
July
2014)
 
 Studies
and
reports
by
the
Diocesan
architect
in
2008,
2013
and
2014
considered
 possible
extensions
to
the
church
for
new
public
facilities;
work
required
to
 conserve,
restore
and
maintain
the
historic
fabric
of
St
Peter’s
and
the
Chapel
of
the
 Resurrection;
to
restore
the
organ,
and
a
improve
heating,
lighting
and
acoustics.
 
 The
St
Peter’s
Development
Group
resolved
(minutes
9
June
2014)
to
focus
on:
 • conservation
and
restoration
of
St
Peter’s
church;
 • building
works,
including
improving
access
and
potential
use,
to
the
Chapel
of
 the
Resurrection;
 • developing
a
café
for
visitors
within
the
church;

  • 3. St Peter’s Church- Options Appraisal
 
 3
 • creating
a
new
build
Literary
and
Music
Centre.
Celebrating
St
Peter’s
and
 Bournemouth’s
music
and
literary
heritage
in
an
extension
to
the
north
side
 of
the
church
‐
the
‘shopfront’extension;
 • building
a
separate
single
storey
building
for
music,
learning,
events
and
 public
use
at
the
east
end
of
the
church;
and
 • ground
clearance
and
improvement
works
to
the
Churchyard
grounds
 including
remodeling
the
entrance.
 
 The
building
works
to
the
Chapel
of
the
Resurrection
are
underway
and
due
to
be
 completed
in
2015.
Volunteer
work
has
cleared
and
improved
the
churchyard
 grounds.
Café
development
is
underway
and
due
to
open
in
2015.
A
fundraising
 campaign,
activities,
appropriate
governance
and
management
are
in
development.
 
 Music
development
is
being
pursued
in
partnership
with
Bournemouth
University.
 St
Peter’s
Church
and
the
Chapel
of
the
Resurrection
were
venues
during
the
2014
 Bournemouth
Arts
Festival
by
the
Sea.
There
are
plans
for
a
Shelley
Festival
in
2016
 linked
to
the
bicentennial
of
Mary
Shelley’s
Frankenstein,
started
in
1816
and
 published
in
1818.

 
 St
Peter’s
has
and
is
developing
its
social
role
at
the
centre
of
the
town’s
diverse
 community.
This
includes
the
well‐regarded
nightclub
chaplaincy,
interfaith
 conferences
and
events,
and
supporting
work
with
homeless
people.
HLF
 acknowledges
these
strengths,
which
can
form
core
elements
of
delivering
HLF
 People
and
Community
outcomes
(see
below).
 
 3
Heritage
Lottery
Fund

 An
application
for
substantial
capital
and
programme
funding
is
central
to
achieving



 the
development
ambitions.
Therefore
considering
HLF
priorities
and
availability
of
 funding
is
critical.
 
 At
the
core
of
the
HLF
assessment
process
is
how
a
project
delivers
a
range
of
 defined
outcomes.
HLF
weight
these
and
expect
more
outcomes
to
be
delivered
the
 larger
the
grant
request.
There
are
outcomes
for
Heritage,
People
and
Communities
 (Heritage
Lottery
Fund
2013a).
 
 Heritage‐
with
HLF
investment
heritage
will
be:
 • better
managed‐
weighted
for
Heritage
Grants
 • in
better
condition‐
weighted
for
Heritage
Grants
 • better
interpreted
and
explained
 • identified/recorded
 
 People‐
with
HLF
investment,
people
will
have:
 • developed
skills‐
weighted
for
Heritage
Grants
 • learnt
about
heritage
‐weighted
for
Our
Heritage
and
Heritage
Grants
 • changed
their
attitudes
and/or
behaviour
 • had
an
enjoyable
experience
 • volunteered
time

  • 4. St Peter’s Church- Options Appraisal
 
 4
 
 Communities‐
with
HLF
investment:
 • negative
environmental
impacts
will
be
reduced‐
weighted
for
Heritage
 Grants
 • more
people
and
a
wider
range
of
people
will
have
engaged
with
heritage‐
 weighted
for
Heritage
Grants
 • your
local
area/community
will
be
a
better
place
to
live,
work
or
visit
 • your
local
economy
will
be
boosted
 
 Public
benefit
as
expressed
in
the
People,
Communities
and
Heritage
interpretation
 outcomes
are
vital
to
HLF.
They
also
seek
value
for
money.
 
 Bournemouth
is
currently
a
SW
HLF
priority
area
and
following
initial
discussions
 with
HLF
they
acknowledge:
 • St
Peter’s
heritage
value,
central
location
in
the
town
and
wider
role;
and
 • the
interest
at
senior
Bournemouth
Borough
Council
level
in
the
role
and
 place
of
St
Peter’s
in
the
town.
 
 HLF
referred
to:
 • demonstrating
need
for
the
project.
St
Peter’s
fulfilling
a
social
role
in
the
 Town
centre
as
well
as
being
a
place
of
worship;
 • the
need
to
have
an
appropriate
scale
project.
HLF
noted
the
overall
 Development
Project;
 • the
need
to
have
an
affordable
scheme
in
the
context
of
the
budget;

 • that
enough
of
the
grant
needs
to
be
spent
on
the
heritage
in
need;
 Conservation
is
a
priority,
as
is
securing
and
engaging
with
heritage.
New
 build
needs
to
be
proportionate
within
the
overall
proposal
to
HLF;
and
 • there
may
be
a
need
to
prioritise
work
and
proceed
in
stages.

 
 Competition
for
funding
is
high
and
the
SW
Regional
Committee
has
around
£1.8
to
 £1.9
million
to
allocate
each
quarter.
The
committee
allocates
around
£750,000
to
 £1
million
per
project;
resources
make
it
difficult
to
allocate
more.
While
5%
is
the
 minimum
matched
funding
required
in
practice
this
is
closer
to
30%
of
total
project
 value.
 
 Two
grant
schemes
are
of
relevance
to
St
Peter’s
Heritage
Grants
and
Our
Heritage.
 
 Heritage
Grants
for
grants
over
£100,000.
Grant
application
under
£2
million
are
 decided
by
the
regional
HLF
committee
and
grants
over
£2
million
by
the
national
 committee.
To
achieve
an
award
of
over
£2
million
requires
heritage
of
substantive
 national
significance.
St
Peter’s
has
significant
heritage
value
and
is
more
likely
to
 compete
successfully
at
a
regional
level.
 

 The
consultant
has
suggested
that
as
the
Chapel
of
Resurrection
building
work
is
 underway
and
there
is
the
ambition
to
increase
use
and
access
to
the
chapel
an
 application
to
the
HLF
Our
Heritage
grants
could
fund
a
learning
and
community
 programme
in
the
chapel.
This
provides
an
opportunity
to
demonstrate
to
HLF

  • 5. St Peter’s Church- Options Appraisal
 
 5
 successful
project
delivery
and
test
St
Peter’s
capacity
to
deliver
an
HLF
funded
 project
albeit
it
at
a
significantly
smaller
scale
than
the
Church.
 
 
 4
Heritage
significance,
risk
and
need
 St
Peter’s
Church
and
churchyard
includes
six
listed
buildings
and
monuments
(see
 Appendix
One):
 
 • St
Peter’s
Church‐
Grade
I
listed
and
one
of
three
Grade
I
listed
buildings
in
 Bournemouth;

 • The
Chapel
of
the
Resurrection‐
Grade
II
listed.
War
Memorial
and
mortuary
 chapel;
 • Gravestones
and
tombs
of
the
Shelley,
Tregonwell
and
Campbell
families
 and
vicars
of
St
Peter’s‐
Grade
II
listed
monuments;

 • Terrace
gravestones
to
the
east
of
St
Peter’s
Church‐
Grade
II
listed
tomb
 chests
and
cross
headstones;
 • The
Churchyard
Cross
‐
Grade
II
listed;
and

 • The
Church
Lychgate
‐
Grade
II
listed.

 
 The
2013
Feasibility
Study
identifies
heritage
significance,
risk,
need
and
works
 required
to
address
St
Peter’s
Church
and
the
Chapel
of
the
Resurrection.
 
 St
Peter’s
Church
heritage
significance
is
based
on
design,
architecture,
interior
wall
 paintings,
stained
glass,
wood,
metal
and
stonework
and
role
in
Bournemouth’s
 history.
There
is
significant
building
fabric
deterioration.
The
organ,
south
clerestory
 windows
and
wall
paintings
are
in
greatest
need
of
work.
The
window
stonework
is
 deteriorating
and
will
become
unsafe
and
there
is
continuing
deterioration
to
the
 wall
paintings.

 
 The
Chapel
of
the
Resurrection
was
built
as
a
mortuary
chapel
and
WW1
war
 memorial.
The
interior
is
in
a
poor
state
of
repair
and
the
building
is
underused.
 
 Music
and
literary
connections
form
the
more
‘intangible’
and
less
well
known
 aspects
of
St
Peter’s
heritage.
HLF
have
an
increasing
focus
on
Intangible
Cultural
 Heritage
(UNESCO
nd)
and
consequently
St
Peter’s
‘intangible’
heritage
is
of
interest
 to
them.
 
 
 5
Costs
 The
Feasibility
Study
(2013:29)
indicates
approximate
gross
conservation
and
 building
costs.
These
costs
do
not
include
all
proposed
or
suggested
building
works.
 
 5.1
St
Peter’s
Church
 Conservation
and
building
costs
 Fabric
repair
and
conservation
 £405,000
 Wallpainting
conservation
 
 £181,500

  • 6. St Peter’s Church- Options Appraisal
 
 6
 Organ
restoration
 
 
 £850,000
 Lighting
and
sound
installation
 £152,250
 Heating
 
 
 
 £421,250
 Sub‐
division
of
the
Church
 
 costs
unknown
 Total
 
 
 
 









£2,010,000
 
 
 
 
 
 These
costs
include
professional
fees,
contigencies
and
VAT.
Builders
work
in
 conjunction
with
electrical
and
sound
installations
are
not
included.
Work
to
the
 electrical
infrastructure
is
not
included.
The
organ
costings
are
an
estimate
and
do
 not
include
transportation.
VAT
on
approved
alterations
to
a
listed
building
may
be
 recoverable
through
the
Listed
Places
of
Worship
Grant.
This
would
reduce
the
total
 gross
costs
by
about
20%.
 
 Other
costs

 The
above
costs
do
not
include
delivering
interpretation,
learning
and
community
 programmes
that
are
essential
in
any
HLF
application.
HLF
expect
that
a
minimum
of
 10%
of
overall
project
costs
be
allocated
to
delivering
learning
and
community
 outcomes.
Usually
this
is
a
programme
over
three
years
including
the
building
works
 period.
 
 These
costs
do
not
include
project
management
and
administration
costs
that
St
 Peter’s
will
incur
to
develop
and
deliver
the
two
stage
HLF
application
process
and
 project
delivery.

 
 HLF
seek
to
secure
the
long
term
future
of
their
investment
of
what
is
essentially
 ‘public
money’.
They
require
a
costed
future
management
and
maintenance
plan
for
 both
building
and
programme
aspects
of
the
project.

The
value
of
increased
 management
and
maintenance
costs
for
up
to
five
years
after
the
building
works
are
 completed
can
be
included
as
a
partnership
funding
contribution.
 
 Churchyard
grounds
costs
may
be
incurred
as
part
of
the
building
works.
 
 5.2
Chapel
of
the
Resurrection
 Conservation
and
building
costs
 Fabric
repair
and
alterations
 
 £185,772
 
 These
costs
include
professional
fees,
contigencies
and
VAT.
Final
costs
depend
on
a
 detailed
brief
and
requirements
VAT
on
approved
alterations
to
a
listed
may
be
 recoverable
through
the
Listed
Places
of
Worship
Grant.
This
would
reduce
the
total
 gross
costs
by
about
20%.
 
 Other
costs
 Costs
associated
with
developing
and
delivering
increased
use
of
the
building
have
 not
been
identified.
 
 As
suggested
above
these
costs
would
be
eligible
for
the
HLF
Our
Heritage
 programme.

  • 7. St Peter’s Church- Options Appraisal
 
 7
 
 5.3
Literature
and
Music
Centre
 Building
and
running
costs
are
currently
not
known.
It
is
suggested
volunteers
would
 staff
the
centre.
However,
there
will
be
management,
building
and
programme
 costs.

 
 HLF
has
indicated
a
reluctance
to
fund
new
build
as
they
prioritise
existing
heritage
 at
risk.
For
St
Peter’s,
the
conservation
and
building
needs
present
the
strongest
 priority.
A
clear
and
strong
case
for
visitor
demand
and
use
of
the
Centre
would
be
 required
for
the
Centre
to
be
included
as
part
of
an
HLF
proposal.
It
is
assumed
this
 would
also
underpin
a
viable
business
plan
for
the
centre.
At
this
time
visitor
use
and
 demand
has
not
been
investigated.
This
would
need
to
take
account
of
existing
 museum,
music,
performing
arts,
library
and
festival
provision
and
use.
The
potential
 for
more
events
in
the
Church
and
Chapel
of
the
Resurrection
and
links
to
existing
 cultural
provision
should
be
explored
e.g.
the
concert
and
use
of
the
Chapel
for
a
 visual
art
and
media
installation
as
part
of
the
2014
Arts
Festival
by
the
Sea.
 
 5.4
East
end
new
building
 Building
and
running
costs
are
currently
not
known,
but
are
likely
to
be
in
the
region
 of
£2
million
(Ken
Mantock
pers
comm
January
2015).
As
the
heritage
need
being
 met
by
the
new
building
is
not
defined
HLF
are
not
likely
to
consider
funding
 support.
 
 5.5
Churchyard
grounds
 Improvements
to
the
grounds
and
remodeling
the
entrance
costs
are
currently
not
 known.
As
noted
above
the
Churchyard
and
grounds
include
five
listed
buildings,
 monuments
and
structures.
Apart
from
the
Chapel
it
is
not
clear
whether
there
are
 condition
assessments
the
listed
monuments.
 
 
 6
Project
delivery
capacity
 Governance,
legal
identity
and
accountabilities
are
structured
and
delivered
through
 the
Parish
Church
Council.
St
Peter’s
has
small
paid
team
and
a
small
and
active
 volunteer
team.
The
St
Peter’s
Development
Group
comprises
paid
and
volunteer
 members
and
is
reliant
primarily
on
volunteer
time
and
commitment
to
drive
the
 delivery
of
the
development
ambitions.
 
 Additional
capacity
that
is
essential
for
delivering
any
conservation
and
building
 work,
interpretation,
learning
and
community
programmes,
and
project
 management
and
administration
can
be
costed
as
part
of
an
HLF
proposal.
However,
 additional
staff
require
management,
workspace
and
integration
with
the
daily
work
 of
St
Peter’s.
An
extensive
conservation
and
building
work
project
will
inevitably
 disrupt
the
daily
work
of
St
Peter’s
and
access
to
the
Church
and
Churchyard.
This
 will
require
active
management
and
communication.

 
 The
need
for
a
major
fundraising
campaign
is
recognised
and
work
is
underway
to
 develop
fundraising
capacity
and
raise
monies.
HLF
commented
on
the
risk
of

  • 8. St Peter’s Church- Options Appraisal
 
 8
 underestimating
the
time
needed
to
fundraise.
They
do
not
expect
all
partnership
 funding
(HLF’s
term
for
matched
funding)
to
be
in
place
when
a
Round
One
 application
is
submitted.

Partnership
funding
needs
to
be
in
place
at
Round
Two.
 HLF
allow
up
to
two
years
between
Round
One
and
submission
of
Round
Two.
 
 The
scale
of
work
to
be
delivered
at
any
one
time
should
take
account
of
capacity
to
 successfully
deliver
a
project.
HLF
have
commented
on
the
importance
of
this
and
 take
account
of
it
in
their
assessment.

 
 
 7
Options
and
conclusions
 In
the
context
of
HLF’s
focus
on
heritage
the
options
consider
St
Peter’s
Church
and
 the
Literature
and
Music
Centre
in
relation
to
HLF
funding
requirements
and
scale
of
 funding;
known
costs
and
St
Peter’s
delivery
capacity.
The
Chapel
of
Resurrection
is
 not
included
as
building
work
is
underway
in
a
separate
project.
 
 Option
1
St
Peter’s
Church
 The
heritage
significance
of
St
Peter’s
building
and
interior
are
recognised
through
 Grade
I
listed
status
and
the
2013
Feasibility
Study
identifies
the
heritage
risk
and
 needs
of
the
building.
HLF
have
indicated
that
they
prioritise
heritage
at
risk.
There
 are
approximate
gross
costings.
However,
not
all
building
costs
are
known
e.g.
 building
sub
division
and
electrical
works.
 
 Interpretation,
learning
and
community
programme
costs
are
yet
to
be
identified,
 but
can
be
anticipated
to
be
around
£200,000
over
three
years
as
HLF
expect
these
 elements
to
account
for
about
10%
of
total
project
costs.
Project
management
and
 administration
costs
are
yet
to
be
identified.
 
 There
are
likely
to
be
costs
associated
with
generating
the
plans
and
documentation
 required
for
an
HLF
Round
One
application.
In
particular
conservation
and
building
 plans
and
documentation
to
RIBA
Stage
1,
which
will
involve
architects
and
other
 building
professionals
time.
Grant
funding
for
Round
Two
development
costs
form
 part
of
the
Round
One
application.
 
 Current
approximate
total
project
costs
£2,210,000
of
which
HLF
may
fund
 £750,000‐
£1,000,000
of
eligible
costs.
The
funding
gap
based
on
the
lower
HLF
grant
 is
£1,460,000.
 
 Option
2
St
Peter’s
Church
and
the
Literature
and
Music
Centre
 The
St
Peter’s
elements
are
as
in
option
1.
The
Literature
and
Music
Centre
does
not
 specifically
have
elements
of
heritage
at
risk.
While
awareness
and
understanding
of
 the
significance
of
Bournemouth’s
literary
and
music
heritage,
including
St
Peter’s
 Shelley
family
connections,
are
not
as
well
known
as
they
could
be,
visitor
demand
 and
use
of
a
centre
has
to
be
tested.

 
 Known
approximate
project
costs
are
those
for
option
1
above
as
the
Centre
 building,
running
and
programme
costs
have
not
yet
been
identified.

  • 9. St Peter’s Church- Options Appraisal
 
 9
 
 The
table
below
summarises
the
two
options.
 Option
 Approx
 Building
 Costs
 Approx
 prog
costs
 HLF
 priority
 yes
 uncertain no
 Total
 Likely
HLF
 grant
 Funding
 gap
based
 on
£750K
 grant
 Issues
with
 potential
costs
 to
be
addressed
 1
St
 Peter’s

 £2,010,000
 £200,000
 yes
 £2,210,00
 £750,00‐ £1,000,000
 £1,460,000
 Updated
 conservation
 and
building
 works
plans.
 
 Project
 management
 and
 Administration.
 
 Round
One
and
 Two
application
 costs.
 
 Churchyard
 ground
works
 may
also
be
 needed
 
 Disruption
to
 use
of
the
 Church.
 2
St
 Peter’s

 and
the
 Lit
and
 Music
 centre
 £2
million
 plus
as
costs
 not
known
 for
the
new
 build
 Min
 £200,000
 St
Peter’s
 yes
 
 Centre
 uncertain/ no
 Min
 £2,210,00
 £750,000‐ £1,000,000
 Min
 £1,460,000
 Centre
 unknown
 As
above
for
St
 Peter’s.
 
 Time
and
 possible
cost
 implications
for
 St
Peter’s
work
 as
Centre
design
 and
planning
 work
is
 undertaken.

 
 Centre
design,
 build
and
run
 costs.
 
 Additional
 project
 management
 and
admin
costs.
 
 Churchyard
 ground
works
 related
to
the
 Centre
may
be
 needed
 
 Disruption
to
 use
of
the
 Church
from
 Centre
building
 works.
 

  • 10. St Peter’s Church- Options Appraisal
 
 10
 
 Conclusions
 Option
1
is
the
most
achievable
option.
Based
on
current
understanding
of
 conservation
and
building
costs;
HLF
priorities
and
likely
grant
funds
available;
 capacity
to
develop
fundraising
and
deliver
projects.
This
suggests
a
phased
 approach
to
the
overall
Development
Project
plans.
 
 Phase
1‐
Improvement
works
to
the
Chapel
of
the
Resurrection
and
application
to
 HLF
Our
Heritage
for
a
one
year
interpretation,
learning
and
community
programme.
 Start
HLF
Heritage
Grants
Round
One
application
development
for
St
Peter’s
Church.
 Start
five
year
fundraising
campaign.
 
 Phase
2‐
Review
the
need
for
and
cost
improvements
works
to
the
Churchyard
and
 determine
whether
these
form
part
of
Phase
2
or
are
a
separate
project.
Submit
HLF
 Heritage
Grants
Round
One
and
Two
applications
for
St
Peter’s.
Deliver
the
 conservation
and
restoration
of
St
Peter’s
Church
including
a
three
year
 interpretation,
learning
and
community
programme.
This
could
include
elements
 relating
to
St
Peter’s
literary
and
music
heritage.

 
 Phase
3‐
Based
on
delivery
of
the
Phase
1
and
2
programmes
review
likely
visitor
 demand
and
use
of
a
Literature
and
Music
Centre,
and
review
St
Peter’s
needs
for
 additional
public
space
for
events.
Determine
the
scale,
cost,
and
running
costs
of
 any
new
build.

 
 Below
is
an
outline
timetable.
Issues
that
will
impact
on
this
are:
 • fundraising;
 • HLF
application
development
and
assessment;
 • procurement;
 • interdependencies
of
the
conservation
and
building
works
e.g.
the
organ;

 “Waiting
lists
from
the
moment
of
contract
signing
are
typically
two
years.
 Thereafter
the
work
might
be
expected
to
be
achieved
within
perhaps
nine
or
 ten
months.”
(2013
Feasibility
Study:6)
 
 Phase
 Action
 2015
 2016
 2017
 2018
 2019
 2020
 1
 Chapel
of
Resurrection
building
works
 
 
 
 
 
 
 
 HLF
Our
Heritage
bid
and
programme
 
 
 
 
 
 
 
 HLF
Heritage
Grants
Round
1
bid
development
 
 
 
 
 
 
 
 Fundraising

 
 
 
 
 
 
 2
 Review
need
for
and
cost
Churchyard
grounds
 work
as
part
of
the
Heritage
Grants
bid
or
 separate
project.

 
 
 
 
 
 
 
 HLF
Heritage
Grants
Round
1
submission
and
 assessment.
 
 
 
 
 
 
 
 HLF
Heritage
Grants
Round
2
development
and
 submission
 
 
 
 
 
 
 
 St
Peter’s
Conservation
Project
 
 
 
 
 
 
 3
 Review
visitor
demand/use
of
a
Literature
and
 Music
Centre.
Review
St
Peter’s
needs
for
 additional
public
space
 
 
 
 
 
 

  • 11. St Peter’s Church- Options Appraisal
 
 11
 Sources
 English
Heritage
The
National
Heritage
List
for
England
 http://list.english‐heritage.org.uk/results.aspx

 
 Heritage
Lottery
Fund
(December
2013a)
Heritage
Grants
Application
guidance
 http://www.hlf.org.uk/looking‐funding/our‐grant‐programmes/heritage‐grants
 
 Heritage
Lottery
Fund
(December
2013b)
Our
Heritage
Application
guidance
 http://www.hlf.org.uk/looking‐funding/our‐grant‐programmes/our‐heritage
 
 Ken
Mantock
July
2014
email
correspondence
 
 Michael
Drury
Architects
(May
2008)
Bournemouth
St
Peter:
Church
Amenities
 
 Michael
Drury
(March
2014)
The
Chapel
of
the
Resurrection
at
the
Church
of
St
Peter,
 Bournemouth,
Dorset
Condition
Report.
 
 St
Anne’s
Gate
Architects
(March
2013)
Feasibility
Study
The
Church
of
St
Peter
 Bournemouth
2013
Appeal.
 
 St
Peter’s
Development
Project
Minutes
29
April
2013
 
 St
Peter’s
Development
Group
Minutes
9
June
2014
 
 UNESCO
(nd)
What
is
Intangible
Cultural
Heritage?
UNESCO
 http://www.unesco.org/culture/ich/doc/src/01851‐EN.pdf

  • 12. St Peter’s Church- Options Appraisal
 
 12
 
 Appendix
One
 
 Heritage
Significance
 St
Peter’s
Church
and
churchyard
includes
six
listed
buildings
and
monuments:
 
 St
Peter’s
Church1 
a
Grade
I
listed
church
is
one
of
only
three
Grade
I
listed
buildings
 in
Bournemouth.
The
other
two,
also
churches,
are
St
Stephen’s
and
St
Clement’s.
 The
eminent
architect
George
Edmund
Street2 
designed
St
Peter’s.
He
was
known
for
 his
use
of
Gothic
style
and
famous
for
designing
the
Royal
Courts
of
Justice
in
The
 Strand,
London.

 
 The
church
was
built
between
1856
and
1879
replacing
an
earlier
building.
The
south
 aisle
of
which
was
retained
as
it
was
only
built
in
1853.
The
spire
is
an
important
 landmark
and
the
highly
decorated
interior
has
fine
stained
glass,
wall
painting,
 wood,
metal
and
stone
work
by
the
notable
craft
workshops
of
the
day
including
 Clayton
and
Bell3 ,
and
Morris,
Marshal,
Faulkner
and
Co.
The
vestry
buildings
and
 crypt
by
the
eminent
late
Victorian
architect
Sir
T.G.
Jackson
are
later.
 
 The
Chapel
of
the
Resurrection4 
is
Grade
II
listed.
Built
in
1925‐26
the
chapel
was
 designed
by
the
noted
late
Victorian/early
twentieth
century
architect
Sir
Ninian
 Comper5 .
Originally
a
mortuary
chapel
for
the
church
it
is
now
used
once
a
week
for
 Holy
Communion.
 
 Gravestones
and
tombs
of
the
Shelley,
Tregonwell
and
Campbell
families
and
 vicars
of
St
Peter’s6 .
Grade
II
listed
monuments.
The
Shelley
monument
erected
by
 Percy
Bysshe
Shelley
contains
the
poet’s
heart
and
bodies
of
his
parents‐
in‐law
 William
and
Mary
Godwin
and
his
wife
Mary
Wollstonecraft
Shelley.
The
Tregonwell
 tomb
commemorates
Lewis
Tregonwell
the
founder
of
Bournemouth.
 
 Terrace
gravestones
to
the
east
of
St
Peter’s
Church7 .
Grade
II
listed
tomb
chests
 and
cross
headstones.
 
 The
Churchyard
Cross8 
is
Grade
II
listed.
Designed
by
George
Edmund
Street
and
 carved
by
TW
Earp.
 
 The
Lychgate9 
is
Grade
II
listed
and
was
designed
by
George
Edmund
Street.
 
 























































 1 
http://list.english‐heritage.org.uk/resultsingle.aspx?uid=1153014
 2
http://www.architecture.com/Explore/Architects/GeorgeEdmundStreet.aspx
 3 
Alfred
Bell
was
born
at
Silton,
Dorset
http://stainedglass.llgc.org.uk/person/18
 4 
http://list.english‐heritage.org.uk/resultsingle.aspx?uid=1324705
 5 
http://www.scottisharchitects.org.uk/architect_full.php?id=200370
 6
http://list.english‐heritage.org.uk/resultsingle.aspx?uid=1108868
 7
http://list.english‐heritage.org.uk/resultsingle.aspx?uid=1304485
 8 
http://list.english‐heritage.org.uk/resultsingle.aspx?uid=1108867
 9
http://list.english‐heritage.org.uk/results.aspx?index=151