SlideShare une entreprise Scribd logo
1  sur  17
Télécharger pour lire hors ligne
REPORT ON
REDUCING THE CYCLE TIME OF THE FORGING PROCESS IN
THE MANUFACTURING OF ALUMINIUM WHEELS
BY
LAVA KUMAR 2012A4PS297G
SHREYAS RAJAGOPAL 2012B4A4726G
AT
WHEELS INDIA LTD., CHENNAI
BIRLA INSTITUTE OF TECHNOLOGY & SCIENCE, PILANI
(July, 2014)
2
ACKNOWLEDGEMENTS
We would like to thank Mr. Venkateshwarlu, the Deputy General Manager of
the Special Wheels Division (SWD) for suggesting us the project topic and
giving us various inputs regarding our project. We also express our gratitude to
Mr. Dillibabu (Assistant Manager-Methods) for guiding us through the project
and for the tremendous support we received from him. We would also like to
express our sincere thanks to Mr. B.S. Pallad and the various other employees
in the FAW department and to the operators of the forging machine who
answered our queries patiently and gave us all the information we needed.
3
Station: Wheels India Limited Centre: Padi, Chennai
Duration: 2 months Date of Start: 23rd
May, 2014
Date of Submission: 15th
July, 2014
Title of the Project: Reducing the cycle time of the Forging Process
ID No./Names/ : 2012A4PS297G Lava Kumar B.E Mechanical
Disciplines if the students 2012B4A4726G Shreyas Rajagopal MSc. Maths +
B.E Mechanical
Names and : Mr. Venkateshwarlu, Deputy General Manager (SWD)
Designations of the Mr Dillibabu, Assistant Manager – Methods
Experts
Name of the PS faculty: Mr. Sundaresan Raman
Key Words: Reduction, Cycle time, Forging, Spray, Double doors.
Project Areas: Manufacturing
Abstract: The report gives an idea of the various processes in Forged
Aluminium Wheels division of Wheels India Limited. Focussing on the process
called forging, the problem of it consuming a lot of time is being dealt with in
this report and the approach to acquiring the required data has been clearly
explained. The solutions to the identified problems have been illustrated and
attention has been paid to the problems that could arise in the in the
implementation of these solutions. The implementation of these solutions can
successfully save about 50 seconds per wheel manufactured.
Signatures of the Students Signature of PS faculty
Date Date
4
Table of Contents
Introduction 6
Working on the Project 9
The Solution 11
Conclusions and Recommendations 14
Appendix 15
References 16
Glossary 17
5
Introduction
The project pertains to a process in the FAW division. Hence a basic idea of the processes in
FAW is necessary for which the following rough outline of the processes in FAW has been
highlighted.
This is a rough outline of the process. At times, some wheels may be packed just after
machining or sometimes the polished wheels may be painted before packing. It all depends
on the requirements of the customers.
The main focus will be on forging process as the project deals with reducing the cycle time
for the process. This requires looking into the forging process in a little more detail. Forging
is defined as “a manufacturing process involving the shaping of metal using localized
Billet Cutting
•Al 6061 alloy is cut into
billets.
Billet Heating
•The cut billets are heated.
Forging
•The heated billets are
forged into a dis shape.
Bore Piercing
•A hole is made in the centre
of the disc.
Spinning
•The disc now goven the
shape of the wheel.
Heat Treatment
•All wheels should undergo
this process to attain the
required hardness for
machining.
Manchining
•The wheel is brought to the
proper dimensions and
holes are drilled as per the
design.
Polishing
•The machined wheels are
washed and polished to give
them a mirror like finish.
Packing
•The polished wheels, after
inspection are packed to be
shipped to the customers.
6
compressive forces.” Earlier this process was as simple as hammering a piece of hot metal
but nowadays this is achieved by using hydraulic presses.
Figure 1: Hydraulic Forging
Forging can again be classified into three categories depending on the temperature of the
billet used - hot, warm and cold forging. If the temperature is above the material's
recrystallization temperature it is deemed hot forging; if the temperature is below the
material's recrystallization temperature but above 30% of the recrystallization temperature
(on an absolute scale) it is deemed warm forging; if below 30% of the recrystallization
temperature (usually room temperature) then it is deemed cold forging. The main
advantage of hot forging is that as the metal is deformed work hardening effects are
negated by the recrystallization process. Cold forging typically results in work hardening of
the piece. The process used in Wheels India Limited is hot forging.
As mentioned earlier the project deals with reducing the cycle time for the forging process.
The reason behind selecting the forging process for reduction of the cycle time is that it is
the mother process that currently takes the maximum time. A mother process is one which
has only one station for processing i.e. there is only one forging press where all the wheels
are forged. The other mother process are billet cutting, billet heating, spinning and heat
treatment. The following chart shows the time taken by the mother processes:
7
Data regarding the heat treatment process were not shared since they had to be kept
confidential. But it was said that the heat treatment furnace has the capacity to handle
more demand. It is clear from the chart that forging takes a lot of time. Hence reducing the
cycle time of the forging process was chosen as the project topic. Such a project had been
undertaken by Mr.Dillibabu once earlier and a significant reduction of the processing time
was achieved. The earlier project successfully reduced the time from 325 sec/wheel to
about 202 sec/wheel (when run efficiently). This project aims at further reducing the time
by about 50 seconds per wheel.
0
50
100
150
200
250
300
Billet Cutting Billet Heating Forging Piercing Spinning
Cycle times of the "mother" processes
Cycle time (seconds)
8
Working on the Project
To reduce the cycle time, data pertaining to the current cycle time were required. For this
purpose a digital camera was provided using which a video of the forging process had to be
made. An eight minute long video was made which captured the forging of two wheels. The
video that was stored in the camera’s memory was made available to work on by the MIS
(Management Information System) department. Once the video could be accessed on the
computer, using the VLC media player the time duration for the various activities in the
forging process was calculated. The following is the tabulated form of the data collected:
S.No ACTIVITIES IN FORGING PROCESS TIME(sec) Percent time
1 Door closing 5 2.08%
2 Auto spraying 40 16.67
3 Door opening 5 2.08%
4 Manual spraying 65 27.08
5 Door closing 5 2.08%
6 Forging 60 25%
7 Door opening 5 2.08%
8 Ejection 25 10.42%
9 Unloading 30 12.5%
Table 1: Activity times of the forging process.
The activities that add value to the product are highlighted in red. The activities that have
been identified as “time consuming” have been highlighted as bold.
Forging is the only activity that adds value to the product during the process and the time
taken by it cannot be reduced any further. The above data indicates that manual spraying is
a huge time consumer. It is also an essential step in the process because though there is an
automatic spraying system in place, it is not able to spray the lubricant on the tool at a
specific point where it is important that the lubricant is applied. Hence the manual spraying
process is required to overcome this problem. Since it is done manually the inefficiencies of
9
the operator add to the time of the manual spraying. Hence manual spraying is one
identified area of problem.
Another area that consumes a good deal of time is the opening/closing of the door. During
the processing of a single wheel, the door is opened/closed 4 times in totality: before and
after the automatic spraying and before and after the forging activity. Each time the door
takes 5 seconds to open/close. If the time of the opening/closing of the door is reduced, due
to the high frequency of opening and closing activities, a reduction in time can be achieved.
10
The Solution
Identifying the problem was one aspect of the project. An equally important part of the
project was to come up with solutions to the problems that solve the problems efficiently
and at the same time are feasible to be implemented. With the required data at hand, an
analysis was conducted as to which activities were to be targeted on to accomplish the goal.
The following are the ways in which time reduction in any process is generally achieved:
1) Simplify – eliminate unwanted steps (steps that do not add value to the product).
2) Combine – merge two or more simple or repetitive steps into one.
3) Modify – replace the existing system with a more efficient system
4) Rearrange – rearrange the order of the activities to eliminate processing of
extra/unwanted material and hence reduce the time taken
Keeping in mind the above methods, it was decided to modify the manual spraying system
since none of the other methods would reduce the time. The modification that was planned
was introduction of another automatic spraying system in the machine that would eliminate
the need of manual spraying by spraying exactly only at the point on the tool where the
operator has to manually apply the lubricant. A diagram of the proposed system has been
depicted in the figure below:
Figure 2: CAD model of the new spraying system.
11
Figure 3: Rack and pinion Figure 4: Pneumatic cylinder
The following is a rough sketch of the forging machine showing the cavity where the above
shown spraying system will be installed.
Figure 5: CAD model of the forging machine
The rack would be propelled by a pneumatic cylinder. The stroke length of the pneumatic
cylinder would be 50 mm but the required stroke length is only 41 mm (approx.)
(calculations in appendix 1). Hence a stopper will be introduced to restrict the stroke of the
cylinder to the required length. This rack will be in contact with a pinion of diameter 50 mm
which, for the calculated stoke length (see Appendix), will rotate by 90 degrees. This pinion
will house the nozzle that will spray the lubricant on the tool. When the automatic spraying
12
cycle starts, the existing spray system will spray the lubricant on the tool. Simultaneously
the nozzle, initially in the cavity, will be rotated by 90 degrees by the rack-and-pinion
mechanism and it will spray the lubricant on the inner side of the tool. Once that is done,
the nozzle will be rotated back into the cavity.
Another issue to be taken care of is the splashing of the lubricant on the system. The
graphite in the lubricant my get deposited in the rack-and-pinion mechanism and jam the
motion of the system or the deposition on the pneumatic system could again restrict the
movement of the parts. For this it was decided to cover the cavity with a metal sheet and
leave a gap only for the nozzle to project out of the cavity through the metal sheet.
The biggest advantage of introducing this that the cycle time gets reduced drastically since
the manual spraying has been eliminated. Apart from the time gain, the system is not only
easy to fabricate but also easy to maintain and the investment required is not heavy either.
The other area of time wastage that had been identified was the opening-closing of the
door. The solution is again a modification which involves replacing the single door by two
doors that operate simultaneously.
13
Conclusion and Recommendations
The solutions to the problem of time wastage in the forging process have been discussed
thoroughly in the previous section. The advantage of introducing the new spraying system is
that manual spraying will not be required. The direct effect of this on the cycle time would
be that it will reduce by 40 seconds roughly. But care needs to be taken to protect the spray
mechanism from the lubricant since exposure to the lubricant could lead to deposition of
the graphite particles in the lubricant on the rack and pinion mechanism and hinder the
functioning of the system.
The other solution of replacing the single doors by double doors would cut the activity time
by half meaning 10 seconds of the cycle time would be saved. The only point to be kept in
mind is that pneumatic operated doors function faster than motor operated doors. Hence
using motors to operate the two door mechanism would not show a time reduction as
significant as in the case of using pneumatic cylinders to operate the doors.
The life and efficiency of any system depends upon its usage and its maintenance. Usage
depends on the demand and hence cannot be controlled but to ensure that the above
suggested solutions give the best results, it is recommended that they be maintained
properly. This includes oiling the rack and pinion mechanism and cleaning it regularly to
prevent deposition of dust on the mechanism, cleaning the nozzle regularly to prevent
blockage and other such activities.
14
Appendix
Calculation of the stoke length of the pneumatic cylinder.
Diameter of the pinion (d): 50 mm
Circumference of the pinion (c): π x d = π x 50 = 157.08 mm
Distance covered on the circumference on rotation by 90 degrees: (c x 90)/ 360
= c x 0.25
= 157.08 x 0.25
= 39.27 mm
Hence the stoke length of the pneumatic cylinder must be 39.27 mm.
Calculation of the bore diameter of the pneumatic cylinder.
We know,
Pressure = Force/Area (Pressure is Force per unit Area)
Hence, area of the piston of the pneumatic cylinder will be given by:
Area = Force/Pressure (1)
Force applied in this case depends on the load that needs to be moved (rotated) which is
nothing but the mass of the pinion gear along with the spray assembly mounted on the
pinion. Let this mass be M kg. Hence the force applied would be Mg N where g is the
Gravitational constant.
Pressure data required for the calculation is the air pressure in the working area which is
given to be 4.5 bar or 4.5 x 10⁵ N/m².
Area of the piston can be written as πd²/4 where d is the diameter of the piston. Hence
formula (1) can be re-written as,
Πd²/4 = Mg/4.5 x 10⁵.
 d =√ (4Mg/π x 4.5 x 10⁵)
15
Once the value of the mass of the spraying mechanism and the pinion is available, M can be
calculated and hence the diameter of the required piston can be calculated using the above
formula. The bore diameter, d₁ is given by
d₁ = 1.5d
And thus the bore diameter of the pneumatic cylinder can be obtained.
16
References
IESCJ mechanisms: http://iescjmechanisms.wikispaces.com/RACK+AND+PINION+SYSTEM
Wikipedia: http://en.wikipedia.org/wiki/Forging
Bestex Engineering India Private Limited: http://www.bestexengg.com/forging.html
Vikram Hydraulic: http://www.vikramhydraulic.com/pneumatic_cylinder.html
17
Glossary
WIL – Wheels India Limited
FAW - Forged Aluminium Wheels
SWD – Special Wheels Division
CAD - Computer Aided Design

Contenu connexe

Tendances

Lean Manufacturing PowerPoint Presentation Sample
Lean Manufacturing PowerPoint Presentation SampleLean Manufacturing PowerPoint Presentation Sample
Lean Manufacturing PowerPoint Presentation SampleAndrew Schwartz
 
8 Lean Wastes PowerPoint Presentation Slides
8 Lean Wastes PowerPoint Presentation Slides 8 Lean Wastes PowerPoint Presentation Slides
8 Lean Wastes PowerPoint Presentation Slides SlideTeam
 
Final year project report on Value stream mapping and Smed
Final year project report on Value stream mapping and SmedFinal year project report on Value stream mapping and Smed
Final year project report on Value stream mapping and SmedUmar Yazdani
 
cost calculation on forging
 cost calculation on forging  cost calculation on forging
cost calculation on forging NIAJ AHMED
 
Internship report of mechanical student
Internship report of mechanical studentInternship report of mechanical student
Internship report of mechanical studentRitika Vyas
 
Lean manufacturing
Lean manufacturingLean manufacturing
Lean manufacturingskchawla4
 
Polymer AM for end-use applications with focus on Vat Photopolymerization
Polymer AM for end-use applications with focus on Vat PhotopolymerizationPolymer AM for end-use applications with focus on Vat Photopolymerization
Polymer AM for end-use applications with focus on Vat PhotopolymerizationSirris
 
SMED - Single Minute Exchange of Dies
SMED - Single Minute Exchange of DiesSMED - Single Minute Exchange of Dies
SMED - Single Minute Exchange of Dies5S BALAMURUGAN
 
Value Stream Mapping: Case Studies
Value Stream Mapping: Case StudiesValue Stream Mapping: Case Studies
Value Stream Mapping: Case StudiesTKMG, Inc.
 
Seven wastes of lean operations management
Seven wastes of lean operations managementSeven wastes of lean operations management
Seven wastes of lean operations managementHriday Bora
 
Application of value stream mapping for reduction of cycle time in machining ...
Application of value stream mapping for reduction of cycle time in machining ...Application of value stream mapping for reduction of cycle time in machining ...
Application of value stream mapping for reduction of cycle time in machining ...Sumit Bhattacharya
 
Lean six sigma black belt project by iftakhar
Lean six sigma black belt project   by iftakharLean six sigma black belt project   by iftakhar
Lean six sigma black belt project by iftakharMohammad IFTAKHAR
 
8 WASTES IN LEAN MANUFACUTING & OVERVIEW OF VSM
8 WASTES IN LEAN MANUFACUTING & OVERVIEW OF VSM8 WASTES IN LEAN MANUFACUTING & OVERVIEW OF VSM
8 WASTES IN LEAN MANUFACUTING & OVERVIEW OF VSMSedhuSiddarth
 

Tendances (20)

Lean Manufacturing PowerPoint Presentation Sample
Lean Manufacturing PowerPoint Presentation SampleLean Manufacturing PowerPoint Presentation Sample
Lean Manufacturing PowerPoint Presentation Sample
 
8 Lean Wastes PowerPoint Presentation Slides
8 Lean Wastes PowerPoint Presentation Slides 8 Lean Wastes PowerPoint Presentation Slides
8 Lean Wastes PowerPoint Presentation Slides
 
Final year project report on Value stream mapping and Smed
Final year project report on Value stream mapping and SmedFinal year project report on Value stream mapping and Smed
Final year project report on Value stream mapping and Smed
 
cost calculation on forging
 cost calculation on forging  cost calculation on forging
cost calculation on forging
 
Poka Yoke Final Ppt
Poka Yoke  Final PptPoka Yoke  Final Ppt
Poka Yoke Final Ppt
 
Internship report of mechanical student
Internship report of mechanical studentInternship report of mechanical student
Internship report of mechanical student
 
Lean manufacturing
Lean manufacturingLean manufacturing
Lean manufacturing
 
Polymer AM for end-use applications with focus on Vat Photopolymerization
Polymer AM for end-use applications with focus on Vat PhotopolymerizationPolymer AM for end-use applications with focus on Vat Photopolymerization
Polymer AM for end-use applications with focus on Vat Photopolymerization
 
Ppap training ppt
Ppap training   ppt Ppap training   ppt
Ppap training ppt
 
Qc story
Qc storyQc story
Qc story
 
Value Stream Mapping
Value Stream MappingValue Stream Mapping
Value Stream Mapping
 
Muri-Mura-Muda
Muri-Mura-MudaMuri-Mura-Muda
Muri-Mura-Muda
 
SMED - Single Minute Exchange of Dies
SMED - Single Minute Exchange of DiesSMED - Single Minute Exchange of Dies
SMED - Single Minute Exchange of Dies
 
Manufacturing wastes
Manufacturing wastesManufacturing wastes
Manufacturing wastes
 
Value Stream Mapping: Case Studies
Value Stream Mapping: Case StudiesValue Stream Mapping: Case Studies
Value Stream Mapping: Case Studies
 
Seven wastes of lean operations management
Seven wastes of lean operations managementSeven wastes of lean operations management
Seven wastes of lean operations management
 
Application of value stream mapping for reduction of cycle time in machining ...
Application of value stream mapping for reduction of cycle time in machining ...Application of value stream mapping for reduction of cycle time in machining ...
Application of value stream mapping for reduction of cycle time in machining ...
 
Line balancing
Line balancingLine balancing
Line balancing
 
Lean six sigma black belt project by iftakhar
Lean six sigma black belt project   by iftakharLean six sigma black belt project   by iftakhar
Lean six sigma black belt project by iftakhar
 
8 WASTES IN LEAN MANUFACUTING & OVERVIEW OF VSM
8 WASTES IN LEAN MANUFACUTING & OVERVIEW OF VSM8 WASTES IN LEAN MANUFACUTING & OVERVIEW OF VSM
8 WASTES IN LEAN MANUFACUTING & OVERVIEW OF VSM
 

En vedette

Just in time manufacturing ppt
Just in time manufacturing pptJust in time manufacturing ppt
Just in time manufacturing pptSwati Luthra
 
Updated cycle time_reduction_on_valve_body_ih_
Updated cycle time_reduction_on_valve_body_ih_Updated cycle time_reduction_on_valve_body_ih_
Updated cycle time_reduction_on_valve_body_ih_Shalini Rai
 
estee lauder - Productivity and Operational Capacity Improvement Plan
estee lauder - Productivity and Operational Capacity Improvement Planestee lauder - Productivity and Operational Capacity Improvement Plan
estee lauder - Productivity and Operational Capacity Improvement PlanTharanga Jayalal
 
Capacity enhancement cycle time_reduction
Capacity enhancement cycle time_reductionCapacity enhancement cycle time_reduction
Capacity enhancement cycle time_reductionimdiven
 
Public sector innovation: Increasing the capacity for change and improvement ...
Public sector innovation: Increasing the capacity for change and improvement ...Public sector innovation: Increasing the capacity for change and improvement ...
Public sector innovation: Increasing the capacity for change and improvement ...OECD Governance
 
Closed Die Forging Report_revisionsEve
Closed Die Forging Report_revisionsEveClosed Die Forging Report_revisionsEve
Closed Die Forging Report_revisionsEveS. Evelyn Cimesa
 
Heavy Engineering Corporation Limited, Ranchi
Heavy Engineering Corporation Limited, RanchiHeavy Engineering Corporation Limited, Ranchi
Heavy Engineering Corporation Limited, RanchiShyamakant Sharan
 
Just In Time Manufacturing Process
Just In Time Manufacturing ProcessJust In Time Manufacturing Process
Just In Time Manufacturing ProcessBoricha Jaydeep
 
Drop forging report
Drop forging reportDrop forging report
Drop forging reportRox Liberato
 
TALAT Lecture 3402: Forging Process
TALAT Lecture 3402: Forging ProcessTALAT Lecture 3402: Forging Process
TALAT Lecture 3402: Forging ProcessCORE-Materials
 
Project report on Bharat forge
Project report on Bharat forgeProject report on Bharat forge
Project report on Bharat forgeEshan Rastogi
 
HEC Project Report
HEC Project ReportHEC Project Report
HEC Project ReportAshish Raj
 
Forging Process. [Workshop Practices]
Forging Process. [Workshop Practices]Forging Process. [Workshop Practices]
Forging Process. [Workshop Practices]rgbimbochamp
 

En vedette (20)

JIT for manufacturing ppt
JIT for manufacturing pptJIT for manufacturing ppt
JIT for manufacturing ppt
 
Just in time manufacturing ppt
Just in time manufacturing pptJust in time manufacturing ppt
Just in time manufacturing ppt
 
Just In Time
Just In TimeJust In Time
Just In Time
 
Updated cycle time_reduction_on_valve_body_ih_
Updated cycle time_reduction_on_valve_body_ih_Updated cycle time_reduction_on_valve_body_ih_
Updated cycle time_reduction_on_valve_body_ih_
 
estee lauder - Productivity and Operational Capacity Improvement Plan
estee lauder - Productivity and Operational Capacity Improvement Planestee lauder - Productivity and Operational Capacity Improvement Plan
estee lauder - Productivity and Operational Capacity Improvement Plan
 
Capacity enhancement cycle time_reduction
Capacity enhancement cycle time_reductionCapacity enhancement cycle time_reduction
Capacity enhancement cycle time_reduction
 
sona
sonasona
sona
 
Public sector innovation: Increasing the capacity for change and improvement ...
Public sector innovation: Increasing the capacity for change and improvement ...Public sector innovation: Increasing the capacity for change and improvement ...
Public sector innovation: Increasing the capacity for change and improvement ...
 
Closed Die Forging Report_revisionsEve
Closed Die Forging Report_revisionsEveClosed Die Forging Report_revisionsEve
Closed Die Forging Report_revisionsEve
 
Forging process
Forging processForging process
Forging process
 
Heavy Engineering Corporation Limited, Ranchi
Heavy Engineering Corporation Limited, RanchiHeavy Engineering Corporation Limited, Ranchi
Heavy Engineering Corporation Limited, Ranchi
 
Just In Time Manufacturing Process
Just In Time Manufacturing ProcessJust In Time Manufacturing Process
Just In Time Manufacturing Process
 
Forging Process
Forging ProcessForging Process
Forging Process
 
Drop forging report
Drop forging reportDrop forging report
Drop forging report
 
TALAT Lecture 3402: Forging Process
TALAT Lecture 3402: Forging ProcessTALAT Lecture 3402: Forging Process
TALAT Lecture 3402: Forging Process
 
Project report on Bharat forge
Project report on Bharat forgeProject report on Bharat forge
Project report on Bharat forge
 
Just in time
Just in timeJust in time
Just in time
 
HEC Project Report
HEC Project ReportHEC Project Report
HEC Project Report
 
Forging processes
Forging processesForging processes
Forging processes
 
Forging Process. [Workshop Practices]
Forging Process. [Workshop Practices]Forging Process. [Workshop Practices]
Forging Process. [Workshop Practices]
 

Similaire à Report on Solution for reduction of cycle time in the manufacturing of Al Wheels

The Impact of Lean Production on the Cycle Time: A Case Study of a Welding As...
The Impact of Lean Production on the Cycle Time: A Case Study of a Welding As...The Impact of Lean Production on the Cycle Time: A Case Study of a Welding As...
The Impact of Lean Production on the Cycle Time: A Case Study of a Welding As...ijsrd.com
 
Development of fixture_to_reduce_the_cycle_time_of_c_8_griding_machine
Development of fixture_to_reduce_the_cycle_time_of_c_8_griding_machineDevelopment of fixture_to_reduce_the_cycle_time_of_c_8_griding_machine
Development of fixture_to_reduce_the_cycle_time_of_c_8_griding_machineLaukik Raut
 
VSM (Lean Manufacturing) Project PPT
VSM (Lean Manufacturing) Project PPTVSM (Lean Manufacturing) Project PPT
VSM (Lean Manufacturing) Project PPTFASI93
 
IRJET- Development of Ejection System to Improve Productivity
IRJET-  	  Development of Ejection System to Improve ProductivityIRJET-  	  Development of Ejection System to Improve Productivity
IRJET- Development of Ejection System to Improve ProductivityIRJET Journal
 
IRJET- Development of Ejection System to Improve Productivity
IRJET- Development of Ejection System to Improve ProductivityIRJET- Development of Ejection System to Improve Productivity
IRJET- Development of Ejection System to Improve ProductivityIRJET Journal
 
Rapid injection moulding
Rapid injection mouldingRapid injection moulding
Rapid injection mouldinganil mangalan
 
Improvement in the Design of the Fixture and Pattern
Improvement in the Design of the Fixture and PatternImprovement in the Design of the Fixture and Pattern
Improvement in the Design of the Fixture and PatternIRJET Journal
 
A case study on productivity improvement of wearing insert and cutting ring
A case study on productivity improvement of wearing insert and cutting ringA case study on productivity improvement of wearing insert and cutting ring
A case study on productivity improvement of wearing insert and cutting ringIJECSJournal
 
Implementation of a Cellular Manufacturing Tool for Minimization of Non Value...
Implementation of a Cellular Manufacturing Tool for Minimization of Non Value...Implementation of a Cellular Manufacturing Tool for Minimization of Non Value...
Implementation of a Cellular Manufacturing Tool for Minimization of Non Value...IJERA Editor
 
Reducing manufacturing lead time of steam turbine casing
Reducing manufacturing lead time of steam turbine casingReducing manufacturing lead time of steam turbine casing
Reducing manufacturing lead time of steam turbine casingeSAT Publishing House
 
BrakesIndia_IntReport_CK_SSN_June2015
BrakesIndia_IntReport_CK_SSN_June2015BrakesIndia_IntReport_CK_SSN_June2015
BrakesIndia_IntReport_CK_SSN_June2015CHANDRA SHEKHAR KUMAR
 
IRJET- Project on Time Study to Increase the Overall Productivity
IRJET- Project on Time Study to Increase the Overall ProductivityIRJET- Project on Time Study to Increase the Overall Productivity
IRJET- Project on Time Study to Increase the Overall ProductivityIRJET Journal
 
Ring Free Machining Case Study
Ring Free Machining Case StudyRing Free Machining Case Study
Ring Free Machining Case StudyDave Rees
 
IRJET- Design of Manufacture of Fixtures for CNC Machine to Improve Productiv...
IRJET- Design of Manufacture of Fixtures for CNC Machine to Improve Productiv...IRJET- Design of Manufacture of Fixtures for CNC Machine to Improve Productiv...
IRJET- Design of Manufacture of Fixtures for CNC Machine to Improve Productiv...IRJET Journal
 
PRODUCTIVITY IMPROVEMENT OF PRE-TREATMENTS & POWDER COATING PROCESS.
PRODUCTIVITY IMPROVEMENT OF PRE-TREATMENTS & POWDER COATING PROCESS.PRODUCTIVITY IMPROVEMENT OF PRE-TREATMENTS & POWDER COATING PROCESS.
PRODUCTIVITY IMPROVEMENT OF PRE-TREATMENTS & POWDER COATING PROCESS.Raheem Arif
 

Similaire à Report on Solution for reduction of cycle time in the manufacturing of Al Wheels (20)

The Impact of Lean Production on the Cycle Time: A Case Study of a Welding As...
The Impact of Lean Production on the Cycle Time: A Case Study of a Welding As...The Impact of Lean Production on the Cycle Time: A Case Study of a Welding As...
The Impact of Lean Production on the Cycle Time: A Case Study of a Welding As...
 
Development of fixture_to_reduce_the_cycle_time_of_c_8_griding_machine
Development of fixture_to_reduce_the_cycle_time_of_c_8_griding_machineDevelopment of fixture_to_reduce_the_cycle_time_of_c_8_griding_machine
Development of fixture_to_reduce_the_cycle_time_of_c_8_griding_machine
 
Joined document 24_5
Joined document 24_5Joined document 24_5
Joined document 24_5
 
VSM (Lean Manufacturing) Project PPT
VSM (Lean Manufacturing) Project PPTVSM (Lean Manufacturing) Project PPT
VSM (Lean Manufacturing) Project PPT
 
Plant Layout
Plant LayoutPlant Layout
Plant Layout
 
IRJET- Development of Ejection System to Improve Productivity
IRJET-  	  Development of Ejection System to Improve ProductivityIRJET-  	  Development of Ejection System to Improve Productivity
IRJET- Development of Ejection System to Improve Productivity
 
IRJET- Development of Ejection System to Improve Productivity
IRJET- Development of Ejection System to Improve ProductivityIRJET- Development of Ejection System to Improve Productivity
IRJET- Development of Ejection System to Improve Productivity
 
Rapid injection moulding
Rapid injection mouldingRapid injection moulding
Rapid injection moulding
 
Improvement in the Design of the Fixture and Pattern
Improvement in the Design of the Fixture and PatternImprovement in the Design of the Fixture and Pattern
Improvement in the Design of the Fixture and Pattern
 
A case study on productivity improvement of wearing insert and cutting ring
A case study on productivity improvement of wearing insert and cutting ringA case study on productivity improvement of wearing insert and cutting ring
A case study on productivity improvement of wearing insert and cutting ring
 
PROJECT
PROJECTPROJECT
PROJECT
 
Implementation of a Cellular Manufacturing Tool for Minimization of Non Value...
Implementation of a Cellular Manufacturing Tool for Minimization of Non Value...Implementation of a Cellular Manufacturing Tool for Minimization of Non Value...
Implementation of a Cellular Manufacturing Tool for Minimization of Non Value...
 
Reducing manufacturing lead time of steam turbine casing
Reducing manufacturing lead time of steam turbine casingReducing manufacturing lead time of steam turbine casing
Reducing manufacturing lead time of steam turbine casing
 
BrakesIndia_IntReport_CK_SSN_June2015
BrakesIndia_IntReport_CK_SSN_June2015BrakesIndia_IntReport_CK_SSN_June2015
BrakesIndia_IntReport_CK_SSN_June2015
 
_TUBES.pptx
_TUBES.pptx_TUBES.pptx
_TUBES.pptx
 
Ijmet 10 02_042
Ijmet 10 02_042Ijmet 10 02_042
Ijmet 10 02_042
 
IRJET- Project on Time Study to Increase the Overall Productivity
IRJET- Project on Time Study to Increase the Overall ProductivityIRJET- Project on Time Study to Increase the Overall Productivity
IRJET- Project on Time Study to Increase the Overall Productivity
 
Ring Free Machining Case Study
Ring Free Machining Case StudyRing Free Machining Case Study
Ring Free Machining Case Study
 
IRJET- Design of Manufacture of Fixtures for CNC Machine to Improve Productiv...
IRJET- Design of Manufacture of Fixtures for CNC Machine to Improve Productiv...IRJET- Design of Manufacture of Fixtures for CNC Machine to Improve Productiv...
IRJET- Design of Manufacture of Fixtures for CNC Machine to Improve Productiv...
 
PRODUCTIVITY IMPROVEMENT OF PRE-TREATMENTS & POWDER COATING PROCESS.
PRODUCTIVITY IMPROVEMENT OF PRE-TREATMENTS & POWDER COATING PROCESS.PRODUCTIVITY IMPROVEMENT OF PRE-TREATMENTS & POWDER COATING PROCESS.
PRODUCTIVITY IMPROVEMENT OF PRE-TREATMENTS & POWDER COATING PROCESS.
 

Report on Solution for reduction of cycle time in the manufacturing of Al Wheels

  • 1. REPORT ON REDUCING THE CYCLE TIME OF THE FORGING PROCESS IN THE MANUFACTURING OF ALUMINIUM WHEELS BY LAVA KUMAR 2012A4PS297G SHREYAS RAJAGOPAL 2012B4A4726G AT WHEELS INDIA LTD., CHENNAI BIRLA INSTITUTE OF TECHNOLOGY & SCIENCE, PILANI (July, 2014)
  • 2. 2 ACKNOWLEDGEMENTS We would like to thank Mr. Venkateshwarlu, the Deputy General Manager of the Special Wheels Division (SWD) for suggesting us the project topic and giving us various inputs regarding our project. We also express our gratitude to Mr. Dillibabu (Assistant Manager-Methods) for guiding us through the project and for the tremendous support we received from him. We would also like to express our sincere thanks to Mr. B.S. Pallad and the various other employees in the FAW department and to the operators of the forging machine who answered our queries patiently and gave us all the information we needed.
  • 3. 3 Station: Wheels India Limited Centre: Padi, Chennai Duration: 2 months Date of Start: 23rd May, 2014 Date of Submission: 15th July, 2014 Title of the Project: Reducing the cycle time of the Forging Process ID No./Names/ : 2012A4PS297G Lava Kumar B.E Mechanical Disciplines if the students 2012B4A4726G Shreyas Rajagopal MSc. Maths + B.E Mechanical Names and : Mr. Venkateshwarlu, Deputy General Manager (SWD) Designations of the Mr Dillibabu, Assistant Manager – Methods Experts Name of the PS faculty: Mr. Sundaresan Raman Key Words: Reduction, Cycle time, Forging, Spray, Double doors. Project Areas: Manufacturing Abstract: The report gives an idea of the various processes in Forged Aluminium Wheels division of Wheels India Limited. Focussing on the process called forging, the problem of it consuming a lot of time is being dealt with in this report and the approach to acquiring the required data has been clearly explained. The solutions to the identified problems have been illustrated and attention has been paid to the problems that could arise in the in the implementation of these solutions. The implementation of these solutions can successfully save about 50 seconds per wheel manufactured. Signatures of the Students Signature of PS faculty Date Date
  • 4. 4 Table of Contents Introduction 6 Working on the Project 9 The Solution 11 Conclusions and Recommendations 14 Appendix 15 References 16 Glossary 17
  • 5. 5 Introduction The project pertains to a process in the FAW division. Hence a basic idea of the processes in FAW is necessary for which the following rough outline of the processes in FAW has been highlighted. This is a rough outline of the process. At times, some wheels may be packed just after machining or sometimes the polished wheels may be painted before packing. It all depends on the requirements of the customers. The main focus will be on forging process as the project deals with reducing the cycle time for the process. This requires looking into the forging process in a little more detail. Forging is defined as “a manufacturing process involving the shaping of metal using localized Billet Cutting •Al 6061 alloy is cut into billets. Billet Heating •The cut billets are heated. Forging •The heated billets are forged into a dis shape. Bore Piercing •A hole is made in the centre of the disc. Spinning •The disc now goven the shape of the wheel. Heat Treatment •All wheels should undergo this process to attain the required hardness for machining. Manchining •The wheel is brought to the proper dimensions and holes are drilled as per the design. Polishing •The machined wheels are washed and polished to give them a mirror like finish. Packing •The polished wheels, after inspection are packed to be shipped to the customers.
  • 6. 6 compressive forces.” Earlier this process was as simple as hammering a piece of hot metal but nowadays this is achieved by using hydraulic presses. Figure 1: Hydraulic Forging Forging can again be classified into three categories depending on the temperature of the billet used - hot, warm and cold forging. If the temperature is above the material's recrystallization temperature it is deemed hot forging; if the temperature is below the material's recrystallization temperature but above 30% of the recrystallization temperature (on an absolute scale) it is deemed warm forging; if below 30% of the recrystallization temperature (usually room temperature) then it is deemed cold forging. The main advantage of hot forging is that as the metal is deformed work hardening effects are negated by the recrystallization process. Cold forging typically results in work hardening of the piece. The process used in Wheels India Limited is hot forging. As mentioned earlier the project deals with reducing the cycle time for the forging process. The reason behind selecting the forging process for reduction of the cycle time is that it is the mother process that currently takes the maximum time. A mother process is one which has only one station for processing i.e. there is only one forging press where all the wheels are forged. The other mother process are billet cutting, billet heating, spinning and heat treatment. The following chart shows the time taken by the mother processes:
  • 7. 7 Data regarding the heat treatment process were not shared since they had to be kept confidential. But it was said that the heat treatment furnace has the capacity to handle more demand. It is clear from the chart that forging takes a lot of time. Hence reducing the cycle time of the forging process was chosen as the project topic. Such a project had been undertaken by Mr.Dillibabu once earlier and a significant reduction of the processing time was achieved. The earlier project successfully reduced the time from 325 sec/wheel to about 202 sec/wheel (when run efficiently). This project aims at further reducing the time by about 50 seconds per wheel. 0 50 100 150 200 250 300 Billet Cutting Billet Heating Forging Piercing Spinning Cycle times of the "mother" processes Cycle time (seconds)
  • 8. 8 Working on the Project To reduce the cycle time, data pertaining to the current cycle time were required. For this purpose a digital camera was provided using which a video of the forging process had to be made. An eight minute long video was made which captured the forging of two wheels. The video that was stored in the camera’s memory was made available to work on by the MIS (Management Information System) department. Once the video could be accessed on the computer, using the VLC media player the time duration for the various activities in the forging process was calculated. The following is the tabulated form of the data collected: S.No ACTIVITIES IN FORGING PROCESS TIME(sec) Percent time 1 Door closing 5 2.08% 2 Auto spraying 40 16.67 3 Door opening 5 2.08% 4 Manual spraying 65 27.08 5 Door closing 5 2.08% 6 Forging 60 25% 7 Door opening 5 2.08% 8 Ejection 25 10.42% 9 Unloading 30 12.5% Table 1: Activity times of the forging process. The activities that add value to the product are highlighted in red. The activities that have been identified as “time consuming” have been highlighted as bold. Forging is the only activity that adds value to the product during the process and the time taken by it cannot be reduced any further. The above data indicates that manual spraying is a huge time consumer. It is also an essential step in the process because though there is an automatic spraying system in place, it is not able to spray the lubricant on the tool at a specific point where it is important that the lubricant is applied. Hence the manual spraying process is required to overcome this problem. Since it is done manually the inefficiencies of
  • 9. 9 the operator add to the time of the manual spraying. Hence manual spraying is one identified area of problem. Another area that consumes a good deal of time is the opening/closing of the door. During the processing of a single wheel, the door is opened/closed 4 times in totality: before and after the automatic spraying and before and after the forging activity. Each time the door takes 5 seconds to open/close. If the time of the opening/closing of the door is reduced, due to the high frequency of opening and closing activities, a reduction in time can be achieved.
  • 10. 10 The Solution Identifying the problem was one aspect of the project. An equally important part of the project was to come up with solutions to the problems that solve the problems efficiently and at the same time are feasible to be implemented. With the required data at hand, an analysis was conducted as to which activities were to be targeted on to accomplish the goal. The following are the ways in which time reduction in any process is generally achieved: 1) Simplify – eliminate unwanted steps (steps that do not add value to the product). 2) Combine – merge two or more simple or repetitive steps into one. 3) Modify – replace the existing system with a more efficient system 4) Rearrange – rearrange the order of the activities to eliminate processing of extra/unwanted material and hence reduce the time taken Keeping in mind the above methods, it was decided to modify the manual spraying system since none of the other methods would reduce the time. The modification that was planned was introduction of another automatic spraying system in the machine that would eliminate the need of manual spraying by spraying exactly only at the point on the tool where the operator has to manually apply the lubricant. A diagram of the proposed system has been depicted in the figure below: Figure 2: CAD model of the new spraying system.
  • 11. 11 Figure 3: Rack and pinion Figure 4: Pneumatic cylinder The following is a rough sketch of the forging machine showing the cavity where the above shown spraying system will be installed. Figure 5: CAD model of the forging machine The rack would be propelled by a pneumatic cylinder. The stroke length of the pneumatic cylinder would be 50 mm but the required stroke length is only 41 mm (approx.) (calculations in appendix 1). Hence a stopper will be introduced to restrict the stroke of the cylinder to the required length. This rack will be in contact with a pinion of diameter 50 mm which, for the calculated stoke length (see Appendix), will rotate by 90 degrees. This pinion will house the nozzle that will spray the lubricant on the tool. When the automatic spraying
  • 12. 12 cycle starts, the existing spray system will spray the lubricant on the tool. Simultaneously the nozzle, initially in the cavity, will be rotated by 90 degrees by the rack-and-pinion mechanism and it will spray the lubricant on the inner side of the tool. Once that is done, the nozzle will be rotated back into the cavity. Another issue to be taken care of is the splashing of the lubricant on the system. The graphite in the lubricant my get deposited in the rack-and-pinion mechanism and jam the motion of the system or the deposition on the pneumatic system could again restrict the movement of the parts. For this it was decided to cover the cavity with a metal sheet and leave a gap only for the nozzle to project out of the cavity through the metal sheet. The biggest advantage of introducing this that the cycle time gets reduced drastically since the manual spraying has been eliminated. Apart from the time gain, the system is not only easy to fabricate but also easy to maintain and the investment required is not heavy either. The other area of time wastage that had been identified was the opening-closing of the door. The solution is again a modification which involves replacing the single door by two doors that operate simultaneously.
  • 13. 13 Conclusion and Recommendations The solutions to the problem of time wastage in the forging process have been discussed thoroughly in the previous section. The advantage of introducing the new spraying system is that manual spraying will not be required. The direct effect of this on the cycle time would be that it will reduce by 40 seconds roughly. But care needs to be taken to protect the spray mechanism from the lubricant since exposure to the lubricant could lead to deposition of the graphite particles in the lubricant on the rack and pinion mechanism and hinder the functioning of the system. The other solution of replacing the single doors by double doors would cut the activity time by half meaning 10 seconds of the cycle time would be saved. The only point to be kept in mind is that pneumatic operated doors function faster than motor operated doors. Hence using motors to operate the two door mechanism would not show a time reduction as significant as in the case of using pneumatic cylinders to operate the doors. The life and efficiency of any system depends upon its usage and its maintenance. Usage depends on the demand and hence cannot be controlled but to ensure that the above suggested solutions give the best results, it is recommended that they be maintained properly. This includes oiling the rack and pinion mechanism and cleaning it regularly to prevent deposition of dust on the mechanism, cleaning the nozzle regularly to prevent blockage and other such activities.
  • 14. 14 Appendix Calculation of the stoke length of the pneumatic cylinder. Diameter of the pinion (d): 50 mm Circumference of the pinion (c): π x d = π x 50 = 157.08 mm Distance covered on the circumference on rotation by 90 degrees: (c x 90)/ 360 = c x 0.25 = 157.08 x 0.25 = 39.27 mm Hence the stoke length of the pneumatic cylinder must be 39.27 mm. Calculation of the bore diameter of the pneumatic cylinder. We know, Pressure = Force/Area (Pressure is Force per unit Area) Hence, area of the piston of the pneumatic cylinder will be given by: Area = Force/Pressure (1) Force applied in this case depends on the load that needs to be moved (rotated) which is nothing but the mass of the pinion gear along with the spray assembly mounted on the pinion. Let this mass be M kg. Hence the force applied would be Mg N where g is the Gravitational constant. Pressure data required for the calculation is the air pressure in the working area which is given to be 4.5 bar or 4.5 x 10⁵ N/m². Area of the piston can be written as πd²/4 where d is the diameter of the piston. Hence formula (1) can be re-written as, Πd²/4 = Mg/4.5 x 10⁵.  d =√ (4Mg/π x 4.5 x 10⁵)
  • 15. 15 Once the value of the mass of the spraying mechanism and the pinion is available, M can be calculated and hence the diameter of the required piston can be calculated using the above formula. The bore diameter, d₁ is given by d₁ = 1.5d And thus the bore diameter of the pneumatic cylinder can be obtained.
  • 16. 16 References IESCJ mechanisms: http://iescjmechanisms.wikispaces.com/RACK+AND+PINION+SYSTEM Wikipedia: http://en.wikipedia.org/wiki/Forging Bestex Engineering India Private Limited: http://www.bestexengg.com/forging.html Vikram Hydraulic: http://www.vikramhydraulic.com/pneumatic_cylinder.html
  • 17. 17 Glossary WIL – Wheels India Limited FAW - Forged Aluminium Wheels SWD – Special Wheels Division CAD - Computer Aided Design