SlideShare une entreprise Scribd logo
1  sur  11
QUANTITY SURVEYING AND
VALUATION
Lecture #2
Types of Estimates
(1) Preliminary or Approximate estimate
(2) Rough cost estimate based on plinth area
(3) Rough cost estimate based on cubic contents
(4) Detailed estimate
(5) Annual repair estimate
(6) Special repair estimate
(7) Revised estimate
(8) Supplementary estimate
1. Preliminary or Approximate estimate
It is prepared after preliminary investigation and preliminary
surveying
Detailed surveying, design, drawings etc. are not required
Rates are determined either from practical knowledge or
from records for similar works
For example: To calculate approximate estimate for a
Hospital, per bed cost is calculated from the recent
completed hospital and is multiplied with the number of
beds required.
2. Rough cost estimate based on plinth area
Plinth area of a building shall be determined first
Plinth area of a building means Length x Breadth
Estimate of a building is calculated by multiplying the
plinth area of the building with plinth area rate of the
locality for similar buildings.
Example
Total cost of a building is Rs. 2 lac and its plinth area is 50 m2
Plinth area rate =2,00,000/50 = Rs.4000/- per m2
For a new building plan with 100m2, Total cost =4000x100 =
Rs.4,000,00/-
3. Rough cost estimate based on cubic content
Plinth area of a building shall be determined first
The cubic contents of a building means plinth area x height
of the building.
Estimate of a building is calculated by multiplying the cubic
content of the building with cubic rate of the locality for
similar buildings.
4. Detailed Estimate
After getting Administrative approval on rough cost
estimate, detailed estimates are prepared
Quantities of various items are calculated individually
An abstract of cost -giving quantities of each item and rate
of every item according to the sanctioned schedule of rates
Detailed specifications & report should also be attached
with the estimate.
Technical sanction is given on detailed estimate
5. Annual repair estimate
To keep building and roads in perfect condition, annual
repairs should be carried
11/2% to 2% of the capital cost of the building
6. Special repair estimate
If the work cannot be carried out of the annual repair funds
due to certain reasons resulting in the genuine increase in
cost, then special repairs estimate is to be prepared.
Eg. Replastering walls, new doors etc.
7. Revised estimate
If the sanctioned estimate exceeds by 5% either due to the
rate being found insufficient or due to some other reasons, a
fresh estimate is prepared which is called a Revised Estimate
A comparative statement on the last page of the estimate is
attached giving there in the reasons of the increase of cost in
case of each item.
7. Supplementary estimate
A fresh detailed estimate in addition to the original
sanctioned estimate prepared due to some changes in
structural design.
THANK YOU

Contenu connexe

Tendances

Types of resources in civil engineering field
Types of resources in civil engineering fieldTypes of resources in civil engineering field
Types of resources in civil engineering fieldswetha110
 
Estimating, administrative approval, technical sanction, budget provision
Estimating, administrative approval, technical sanction, budget provisionEstimating, administrative approval, technical sanction, budget provision
Estimating, administrative approval, technical sanction, budget provisionAshwiniChaudhari13
 
Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works  Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works ALI HYDER GADHI
 
Building code implementation
Building code implementationBuilding code implementation
Building code implementationPrabinDhakhwa
 
Erection of structural components in precast constructions
Erection of structural components in precast constructionsErection of structural components in precast constructions
Erection of structural components in precast constructionsParamaAthmeka
 
Construction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project ManagementConstruction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project Managementsrinivas2036
 
Valuation in Civil Engineering
Valuation in Civil EngineeringValuation in Civil Engineering
Valuation in Civil EngineeringKailash Chander
 
Chapter 2 construction project planning and scheduling
Chapter 2 construction project planning and schedulingChapter 2 construction project planning and scheduling
Chapter 2 construction project planning and schedulingSubash Bhattarai
 
Schedule of Rates
Schedule of RatesSchedule of Rates
Schedule of RatesRaj Shah
 
Estimating part 2
Estimating part 2Estimating part 2
Estimating part 2ArunRavi43
 
Estimation and costing of a commercial building
Estimation and costing of a commercial buildingEstimation and costing of a commercial building
Estimation and costing of a commercial buildinglckr117
 
QUANTITY SURVEYING
QUANTITY SURVEYINGQUANTITY SURVEYING
QUANTITY SURVEYINGlizwi nyandu
 
Purpose of estimation
Purpose of estimationPurpose of estimation
Purpose of estimationADARSH KUMAR
 
Estimating part 1
Estimating part 1Estimating part 1
Estimating part 1ArunRavi43
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project ManagementAravind Samala
 

Tendances (20)

Types of resources in civil engineering field
Types of resources in civil engineering fieldTypes of resources in civil engineering field
Types of resources in civil engineering field
 
Estimating, administrative approval, technical sanction, budget provision
Estimating, administrative approval, technical sanction, budget provisionEstimating, administrative approval, technical sanction, budget provision
Estimating, administrative approval, technical sanction, budget provision
 
Valuation
ValuationValuation
Valuation
 
Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works  Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works
 
Building code implementation
Building code implementationBuilding code implementation
Building code implementation
 
Erection of structural components in precast constructions
Erection of structural components in precast constructionsErection of structural components in precast constructions
Erection of structural components in precast constructions
 
Construction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project ManagementConstruction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project Management
 
Valuation in Civil Engineering
Valuation in Civil EngineeringValuation in Civil Engineering
Valuation in Civil Engineering
 
Chapter 2 construction project planning and scheduling
Chapter 2 construction project planning and schedulingChapter 2 construction project planning and scheduling
Chapter 2 construction project planning and scheduling
 
ESTIMATING AND COSTING
ESTIMATING AND COSTINGESTIMATING AND COSTING
ESTIMATING AND COSTING
 
Estimating and Costing
Estimating and CostingEstimating and Costing
Estimating and Costing
 
Schedule of Rates
Schedule of RatesSchedule of Rates
Schedule of Rates
 
Estimating part 2
Estimating part 2Estimating part 2
Estimating part 2
 
Estimation and costing of a commercial building
Estimation and costing of a commercial buildingEstimation and costing of a commercial building
Estimation and costing of a commercial building
 
Estimating and-costing
Estimating and-costingEstimating and-costing
Estimating and-costing
 
QUANTITY SURVEYING
QUANTITY SURVEYINGQUANTITY SURVEYING
QUANTITY SURVEYING
 
Rate analysis
Rate analysisRate analysis
Rate analysis
 
Purpose of estimation
Purpose of estimationPurpose of estimation
Purpose of estimation
 
Estimating part 1
Estimating part 1Estimating part 1
Estimating part 1
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Management
 

Similaire à 2# types of estimate

0111CE702-ESTIMATION AND QUANTITY SURVEYING VII SEMESTER E-LEARNING MATERIAL
0111CE702-ESTIMATION AND QUANTITY SURVEYING VII SEMESTER E-LEARNING MATERIAL0111CE702-ESTIMATION AND QUANTITY SURVEYING VII SEMESTER E-LEARNING MATERIAL
0111CE702-ESTIMATION AND QUANTITY SURVEYING VII SEMESTER E-LEARNING MATERIALNat Rice
 
Lec.2 binifits of estamations...Types of Estimation
Lec.2  binifits of estamations...Types of EstimationLec.2  binifits of estamations...Types of Estimation
Lec.2 binifits of estamations...Types of EstimationMuthanna Abbu
 
Estimating and costing I Chapter 2.pptx
Estimating and costing I Chapter 2.pptxEstimating and costing I Chapter 2.pptx
Estimating and costing I Chapter 2.pptxcricketreview
 
Introduction to estimation
Introduction to estimationIntroduction to estimation
Introduction to estimationDhavalMithaiwala
 
Estimation and Costing
Estimation and CostingEstimation and Costing
Estimation and CostingSakshi Kirar
 
Estimation Costing and Valuation Unit 2
Estimation Costing and Valuation Unit 2Estimation Costing and Valuation Unit 2
Estimation Costing and Valuation Unit 2Padmasinh Patil
 
Estimation (power Point).ppt
Estimation (power Point).pptEstimation (power Point).ppt
Estimation (power Point).pptNaumanIjaz12
 
estimation,its types and methods
estimation,its types and methodsestimation,its types and methods
estimation,its types and methodsgayu pandian
 
Fundamentals of estimating_and_costing
Fundamentals of estimating_and_costingFundamentals of estimating_and_costing
Fundamentals of estimating_and_costingPrasad Manerikar
 
Chapter 2 Approximate Estimates.pptx
Chapter 2 Approximate Estimates.pptxChapter 2 Approximate Estimates.pptx
Chapter 2 Approximate Estimates.pptxrikeshbisen
 
06 -Estimates, QS_CE, Mar 2021.pdf
06 -Estimates, QS_CE, Mar 2021.pdf06 -Estimates, QS_CE, Mar 2021.pdf
06 -Estimates, QS_CE, Mar 2021.pdfJunaidMughal34
 
Types of estimate - Estimation, Costing and Valuation Engineering
Types of estimate - Estimation, Costing and Valuation EngineeringTypes of estimate - Estimation, Costing and Valuation Engineering
Types of estimate - Estimation, Costing and Valuation EngineeringShanmugasundaram N
 
fuw5fomwrucbh1ojdlxe-signature-b01f2df686b9c053f2f9f35a62a4a1f12d0e812f6cbea3...
fuw5fomwrucbh1ojdlxe-signature-b01f2df686b9c053f2f9f35a62a4a1f12d0e812f6cbea3...fuw5fomwrucbh1ojdlxe-signature-b01f2df686b9c053f2f9f35a62a4a1f12d0e812f6cbea3...
fuw5fomwrucbh1ojdlxe-signature-b01f2df686b9c053f2f9f35a62a4a1f12d0e812f6cbea3...Deepak37004
 

Similaire à 2# types of estimate (20)

Lec05.pptx
Lec05.pptxLec05.pptx
Lec05.pptx
 
type of cost Estimation
type of cost Estimationtype of cost Estimation
type of cost Estimation
 
0111CE702-ESTIMATION AND QUANTITY SURVEYING VII SEMESTER E-LEARNING MATERIAL
0111CE702-ESTIMATION AND QUANTITY SURVEYING VII SEMESTER E-LEARNING MATERIAL0111CE702-ESTIMATION AND QUANTITY SURVEYING VII SEMESTER E-LEARNING MATERIAL
0111CE702-ESTIMATION AND QUANTITY SURVEYING VII SEMESTER E-LEARNING MATERIAL
 
Lec.2 binifits of estamations...Types of Estimation
Lec.2  binifits of estamations...Types of EstimationLec.2  binifits of estamations...Types of Estimation
Lec.2 binifits of estamations...Types of Estimation
 
Estimating and costing I Chapter 2.pptx
Estimating and costing I Chapter 2.pptxEstimating and costing I Chapter 2.pptx
Estimating and costing I Chapter 2.pptx
 
Introduction to estimation
Introduction to estimationIntroduction to estimation
Introduction to estimation
 
Estimation and Costing
Estimation and CostingEstimation and Costing
Estimation and Costing
 
Types of estimate
Types of estimateTypes of estimate
Types of estimate
 
Estimation Costing and Valuation Unit 2
Estimation Costing and Valuation Unit 2Estimation Costing and Valuation Unit 2
Estimation Costing and Valuation Unit 2
 
Estimation (power Point).ppt
Estimation (power Point).pptEstimation (power Point).ppt
Estimation (power Point).ppt
 
estimation,its types and methods
estimation,its types and methodsestimation,its types and methods
estimation,its types and methods
 
Fundamentals of estimating_and_costing
Fundamentals of estimating_and_costingFundamentals of estimating_and_costing
Fundamentals of estimating_and_costing
 
Chapter 2 Approximate Estimates.pptx
Chapter 2 Approximate Estimates.pptxChapter 2 Approximate Estimates.pptx
Chapter 2 Approximate Estimates.pptx
 
06 -Estimates, QS_CE, Mar 2021.pdf
06 -Estimates, QS_CE, Mar 2021.pdf06 -Estimates, QS_CE, Mar 2021.pdf
06 -Estimates, QS_CE, Mar 2021.pdf
 
IV -I - EQS - .pptx
IV -I - EQS - .pptxIV -I - EQS - .pptx
IV -I - EQS - .pptx
 
Types of estimates
Types of estimatesTypes of estimates
Types of estimates
 
Types of estimate - Estimation, Costing and Valuation Engineering
Types of estimate - Estimation, Costing and Valuation EngineeringTypes of estimate - Estimation, Costing and Valuation Engineering
Types of estimate - Estimation, Costing and Valuation Engineering
 
Preliminary estimate
Preliminary estimatePreliminary estimate
Preliminary estimate
 
Approximate estimate
Approximate estimateApproximate estimate
Approximate estimate
 
fuw5fomwrucbh1ojdlxe-signature-b01f2df686b9c053f2f9f35a62a4a1f12d0e812f6cbea3...
fuw5fomwrucbh1ojdlxe-signature-b01f2df686b9c053f2f9f35a62a4a1f12d0e812f6cbea3...fuw5fomwrucbh1ojdlxe-signature-b01f2df686b9c053f2f9f35a62a4a1f12d0e812f6cbea3...
fuw5fomwrucbh1ojdlxe-signature-b01f2df686b9c053f2f9f35a62a4a1f12d0e812f6cbea3...
 

Plus de LIJI A

Estimation of one room building
Estimation of one room buildingEstimation of one room building
Estimation of one room buildingLIJI A
 
Estimation of wall
Estimation of  wallEstimation of  wall
Estimation of wallLIJI A
 
5#rate analysis problems
5#rate analysis   problems5#rate analysis   problems
5#rate analysis problemsLIJI A
 
4#Rate analysis
4#Rate analysis4#Rate analysis
4#Rate analysisLIJI A
 
3#specifications
3#specifications3#specifications
3#specificationsLIJI A
 
1# introduction to Quantity Surveying
1# introduction to Quantity Surveying1# introduction to Quantity Surveying
1# introduction to Quantity SurveyingLIJI A
 

Plus de LIJI A (6)

Estimation of one room building
Estimation of one room buildingEstimation of one room building
Estimation of one room building
 
Estimation of wall
Estimation of  wallEstimation of  wall
Estimation of wall
 
5#rate analysis problems
5#rate analysis   problems5#rate analysis   problems
5#rate analysis problems
 
4#Rate analysis
4#Rate analysis4#Rate analysis
4#Rate analysis
 
3#specifications
3#specifications3#specifications
3#specifications
 
1# introduction to Quantity Surveying
1# introduction to Quantity Surveying1# introduction to Quantity Surveying
1# introduction to Quantity Surveying
 

Dernier

CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptDineshKumar4165
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . pptDineshKumar4165
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfJiananWang21
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756dollysharma2066
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueBhangaleSonal
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfKamal Acharya
 
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VDineshKumar4165
 
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night StandCall Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Standamitlee9823
 

Dernier (20)

CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
NFPA 5000 2024 standard .
NFPA 5000 2024 standard                                  .NFPA 5000 2024 standard                                  .
NFPA 5000 2024 standard .
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night StandCall Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
 
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
 

2# types of estimate

  • 2. Types of Estimates (1) Preliminary or Approximate estimate (2) Rough cost estimate based on plinth area (3) Rough cost estimate based on cubic contents (4) Detailed estimate (5) Annual repair estimate (6) Special repair estimate (7) Revised estimate (8) Supplementary estimate
  • 3. 1. Preliminary or Approximate estimate It is prepared after preliminary investigation and preliminary surveying Detailed surveying, design, drawings etc. are not required Rates are determined either from practical knowledge or from records for similar works For example: To calculate approximate estimate for a Hospital, per bed cost is calculated from the recent completed hospital and is multiplied with the number of beds required.
  • 4. 2. Rough cost estimate based on plinth area Plinth area of a building shall be determined first Plinth area of a building means Length x Breadth Estimate of a building is calculated by multiplying the plinth area of the building with plinth area rate of the locality for similar buildings. Example Total cost of a building is Rs. 2 lac and its plinth area is 50 m2 Plinth area rate =2,00,000/50 = Rs.4000/- per m2 For a new building plan with 100m2, Total cost =4000x100 = Rs.4,000,00/-
  • 5. 3. Rough cost estimate based on cubic content Plinth area of a building shall be determined first The cubic contents of a building means plinth area x height of the building. Estimate of a building is calculated by multiplying the cubic content of the building with cubic rate of the locality for similar buildings.
  • 6. 4. Detailed Estimate After getting Administrative approval on rough cost estimate, detailed estimates are prepared Quantities of various items are calculated individually An abstract of cost -giving quantities of each item and rate of every item according to the sanctioned schedule of rates Detailed specifications & report should also be attached with the estimate. Technical sanction is given on detailed estimate
  • 7. 5. Annual repair estimate To keep building and roads in perfect condition, annual repairs should be carried 11/2% to 2% of the capital cost of the building
  • 8. 6. Special repair estimate If the work cannot be carried out of the annual repair funds due to certain reasons resulting in the genuine increase in cost, then special repairs estimate is to be prepared. Eg. Replastering walls, new doors etc.
  • 9. 7. Revised estimate If the sanctioned estimate exceeds by 5% either due to the rate being found insufficient or due to some other reasons, a fresh estimate is prepared which is called a Revised Estimate A comparative statement on the last page of the estimate is attached giving there in the reasons of the increase of cost in case of each item.
  • 10. 7. Supplementary estimate A fresh detailed estimate in addition to the original sanctioned estimate prepared due to some changes in structural design.