3. 4 phases, 9 stages for Land Use Planning
Phase 1: Stage 1 to 5 (to complete land zoning and land management plans that
can be used for follow-on land registration and extension purposes)
Stage 1: Stage 2: Stage 3: Delineation Stage 4: Village Stage 5: Village and
Preparation data of village and village and agriculture agriculture and forest
collection cluster boundaries and forest land land management
use zoning plans
Phase 2: Stage 6 (to secure the data and produce the accurate digital maps
required for rural land registration)
Phase 3: Stage 7 (to undertake communal individual and state land registration
within village management areas)
Phase 4: Stages 8 and 9 (to establish a framework for inter-village management
and use of agriculture and forest resources after PLUP is implemented and to
asses the impacts of the PLUP activity)
4. PLUP implementation Process
Supporting the
key processes and MONRE NUDP
MOAF PONRE PAFO
developing their NU-IRDP
Potential LMC
Doing the Preparation for Participatory Land Use Planning Indicators
key tasks
at district Socio-economic, Land and Forest Data Collection
-In at least 130 of a total of 231 villages,
participatory land use plans have been
level that prepared in line with national guidelines
Together -80% of the communal and private land in
contribute to Delineation of Village and Village Cluster Boundaries at least 100 out of 231 villages has been
measured, legally allocated and
reduced registered systematically according to
poverty in Village and Village Cluster F and A Land Use Zoning national guidelines
Target -In at least 100 of altogether 231 villages,
at least 80% of the female and male
Area
Village and Village Cluster Land Management Plans villagers know their land rights, such as
maximum land areas, provisions on
compensation, land acquisition and
Land Data Record Keeping and Digital Mapping settlement of land disputes.
Driving
the key process,
enabling the LPB HP PSL
district partners
and providing the
3target 3target 3target Cluster
link to the impac district district district village
Teams Teams Teams Commit
5. PLUP Main achievements
PLUP Training
First PLUP training - fiscal year 2010-11
PLUP training for Luang Prabang target areas - November/December 2010
PLUP training in Phongsaly - February – March 2011
PLUP training in Houaphan - March – April 2011
Second PLUP training - fiscal year 2011-12
PLUP training for Luang Prabang target areas - February 2012
PLUP training in Phongsaly - March 2012
PLUP training in Houaphan - March 2012
PLUP orientation meeting at kumban level
PLUP orientation meeting in 3 kumban in Luang Prabang - May 2012
PLUP orientation meeting in 3 kumban in Phongsaly - May 2012
PLUP orientation meeting in 3 kumban in Houaphanh - May 2012
6. PLUP Main achievements
Handed over equipment to 9 PLUP Teams
Item Purpose PLUP Amount Total
Desktop Computer & Office-work, GIS, database 1 3
Flat Screen PLUP
Digital Camera Picture documentation surveying PLUP 1 3
Laptop Computer Support field-work of PLUP and LR PLUP 1 3
External HDD Back-up data storage, exchange of data PLUP 1 3
with GIZ
GPS Garmin 60CSX Take GPS-points of village boundaries and PLUP 2 6
Handheld land use categories, support work of
DLMAs
Netbook Computer Save and process mapped parcels in the field PLUP 2 6
A4 Portable Printer Printing of survey extracts in the field PLUP 2 6
A3 color printer Printing of survey extracts in the field PLUP 1 3
Motorcycle PLUP 1 1
Generator PLUP 1 1
7. PLUP Complete in 63 villages
Viengxay district
Houaphanh Phonthong kumban 5 villages
province
villages Houamuang district Soplao kumban 7 villages
Viengthong district Doaheung kumban 7 villages
Vienkham district
Lungphabang Samsum kumban 9 villages
province
23 villages Pakxeng district Soplcheck kumban 8 villages
Phonxay district Phonthong kumban 6 villages
Samphan district
Phongsaly Asur kumban 6 villages
province
Mai district Pakphee kumban 7 villages
21 villages
Khua district Senlath kumban 8 villages
8. Annual work plan fiscal year 2012 - 13
Handed over equipment to 9 PLUP Teams
Item Purpose PLUP Amount Total
Laptop Computer PAFO coordinators PLUP 1 3
Laptop Computer DAFO technician / PLUP team member PLUP 1 9
LCD DAFO / PLUP team member PLUP 1 9
3G DAFO / PLUP team member PLUP 1 9
Motorcycle DAFO / PLUP team member PLUP 1 9
Sleeping back Field work PLUP 6 36
9. Annual work plan fiscal year 2012 - 13
PLUP activities
Activities 2012 2013
Month 10 11 12 1 2 3 4 5 6 7 8 9
PLUP training for 9 DPLUP teams
IT training for 9 DPLUP teams
9 cluster villages meeting
PLUP implementation 15 village in Luangphabang province
PLUP implementation 15 village in Houaphanh province
PLUP implementation 15 village in Phongsaly province
Study tour abroat and inter interior
PLUP Lesson workshop
AWP fiscal year 2013-14