Client
Automation of Business
Process Management System
WNS Introduction
• Business process management
company.
• Headquarter is in Mumbai, India.
• The company serves over 200
Fortune 500 companies worldwide.
1
Net Present Value
2
Payback Period
Financial Models
Selected Methods
Multi Weighted Criteria
2
Project Portfolio Matrix
Non-Financial Models
Selected Methods
Why WNS Selected BPM Automation
(Global Star Travels Project)?
-Strategic Project with the highest Net Present Value (NPV) of $196,338
-We can recover the investment in 10.9 months
-Having the highest weight score of 72
-This project is technological breakthrough with highest commercial
payoff.
3
Defining  Planning  Executing  Delivering
2
Project Life Cycle
Defining the Project
4
Defining Project Scope
Objective
To design an automated Business Process Management System using
MS SQL Server and BI system within 12 months at a cost not to exceed
$700,000.
Priority Matrix
4
Specification
Hardware:
-Setup Database server
-Setup Web Server
-System down time < 4 hours
Software:
-BI system (middle and top
management)
-Web application system
(operation team)
4
Task
Deliverables:
-BI reports (Analytics tools) for
middle and top management
-Backend database system
-Interfaces / Middleware compatible
with existing front end solutions
-Technical reference document
Project Scope Checklist
5
Work Break Down Structure
3
Integration of WBS and OBS
Cost Account
-The intersection of WP- Hardware
Service and Organization IT
department creates a cost account.
-By rolling up Hardware Service
and Software License WP System
(deliverable) cost is calculated.
Planning
4
Bottom Up: Support Cost Est
6
Top-Down: Function Point
Contract Bid
Time and Cost Estimations
Contract Bid Summary Costs
Total Direct Cost $540,000.00
G&A overhead (10%) $54,000.00
Total Costs $594,000.00
Profit(17.5%) $103,950.00
Total Bid $697,950.00
PERT
6
Time and Cost Estimations
Risk Management
6
Contingency Funds
Managing Risk
Total direct cost $442,338
Budget Reserve + $23,950 (for specific critical activities)
Management Reserve + $13,712 (~3% of Total Budget)
Total Budget = $480,000
6
Gantt Chart
Resource Allocation
Before Levelling: 230 days
6
After Leveling: 237 days
Executing
4
3
Tracking Gantt Chart (Jul-16)
Earned Value Chart
6
Indexes Period
$0.00
$50,000.00
$100,000.00
$150,000.00
$200,000.00
$250,000.00
$300,000.00
Jan'16
Feb'16
Mar'16
Apr'16
May'16
Jun'16
Jul'16
Aug'16
Sep'16
Oct'16
Nov'16
Dec'16ACWP BCWP BCWS
Actual Cost Linear (ACWP)
0
0.2
0.4
0.6
0.8
1
1.2
Jan'16
Feb'16
Mar'16
Apr'16
May'16
Jun'16
Jul'16
Aug'16
Sep'16
Oct'16
Nov'16
Dec'16
SPI CPI
CPI <1 indicates over cost
SPI <1 indicates behind scheduled.
Percentage complete index PCIB: 52%
Percentage complete index PCIC: 52%
Status Report (Jul-16)
Forecast EAC
EAC: $452,130
The final project projected cost
forecast is $452,130 versus $ 240,256
originally planned.
To Complete Performance Index TCPI:
TCPI: 1.05
6
3
Crashing Activity
Activity 52, 53, 93, 97 are crashed. It
cost $7,400 and Project duration will
be reduce by 8days.
3
Control Chart
Period
Status
Report Task Name
Finish
Actual Finish Baseline
Start
Variance
Finish
Variance
Total
Variance
1 March 1st BPM Automation
Mon
11/28/16 Mon 11/28/16 0 days 0 days 0
2 July 1st BPM Automation Thu 12/8/16 Mon 11/28/16 0 days 8 days -8
3 Oct 1st BPM Automation
Mon
11/28/16 Thu 12/8/16 0 days -8 days 8
-20020
1 2 3
Variance
Time Period
3
Conclusion
-More time and cost should be spend in Planning Phase to avoid problems in
later stages.
-Resource allocation in definition need to be reconsider in Planning phase.
-Through out project life cycle to make any decision always project objective
and definition will be center of attention.
-Once project starts dedicated team has to monitor project performance for cost
and schedule evaluation periodically and if require have to revise time phased
schedule.
-Based on status report and performance indices required actions has to be
taken like crashing or scope creep.
Thank you for your attention!
Questions?
7

Contenu connexe

Similaire à Project Management Analysis for WNS

projectmanagement-WNS
projectmanagement-WNSprojectmanagement-WNS
projectmanagement-WNS
Sayyed Z
 
Case Study: How Caixa Econômica in Brazil Uses IBM® Rational® Insight and Per...
Case Study: How Caixa Econômica in Brazil Uses IBM® Rational® Insight and Per...Case Study: How Caixa Econômica in Brazil Uses IBM® Rational® Insight and Per...
Case Study: How Caixa Econômica in Brazil Uses IBM® Rational® Insight and Per...
Paulo Lacerda
 
Symposium 2016 : CONF. 401 Jonathan Shriqui EVM: Go Beyond the Numbers
Symposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the NumbersSymposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the Numbers
Symposium 2016 : CONF. 401 Jonathan Shriqui EVM: Go Beyond the Numbers
PMI-Montréal
 

Similaire à Project Management Analysis for WNS (20)

projectmanagement-WNS
projectmanagement-WNSprojectmanagement-WNS
projectmanagement-WNS
 
Project Management. Automation BPM
Project Management. Automation BPM Project Management. Automation BPM
Project Management. Automation BPM
 
Resume, references and degrees
Resume, references and degreesResume, references and degrees
Resume, references and degrees
 
Effective scoping and execution of business process efforts in major system i...
Effective scoping and execution of business process efforts in major system i...Effective scoping and execution of business process efforts in major system i...
Effective scoping and execution of business process efforts in major system i...
 
Effective Cost Measurement through DMAIC.
Effective Cost Measurement through DMAIC.Effective Cost Measurement through DMAIC.
Effective Cost Measurement through DMAIC.
 
Rapid Economic Justifcation for Machine Learning in IoT
Rapid Economic Justifcation for Machine Learning in IoTRapid Economic Justifcation for Machine Learning in IoT
Rapid Economic Justifcation for Machine Learning in IoT
 
Case Study: How Caixa Econômica in Brazil Uses IBM® Rational® Insight and Per...
Case Study: How Caixa Econômica in Brazil Uses IBM® Rational® Insight and Per...Case Study: How Caixa Econômica in Brazil Uses IBM® Rational® Insight and Per...
Case Study: How Caixa Econômica in Brazil Uses IBM® Rational® Insight and Per...
 
Tim McKenzie_Project_Manager_2014
Tim McKenzie_Project_Manager_2014Tim McKenzie_Project_Manager_2014
Tim McKenzie_Project_Manager_2014
 
CNA’s Journey to Workday Accounting Center
CNA’s Journey to Workday Accounting CenterCNA’s Journey to Workday Accounting Center
CNA’s Journey to Workday Accounting Center
 
CCP_SEC4_Progress and Cost Control
CCP_SEC4_Progress and Cost ControlCCP_SEC4_Progress and Cost Control
CCP_SEC4_Progress and Cost Control
 
Skopos Description - Matthew Heidenreich
Skopos Description - Matthew HeidenreichSkopos Description - Matthew Heidenreich
Skopos Description - Matthew Heidenreich
 
Chap 7.4 Control Cost
Chap 7.4   Control CostChap 7.4   Control Cost
Chap 7.4 Control Cost
 
Soubouu_v1
Soubouu_v1Soubouu_v1
Soubouu_v1
 
A glimpse of business intelligence
A glimpse of business intelligenceA glimpse of business intelligence
A glimpse of business intelligence
 
AGILE PORTUGAL 2018: Changing global Quality operations: how Kanban did the t...
AGILE PORTUGAL 2018: Changing global Quality operations: how Kanban did the t...AGILE PORTUGAL 2018: Changing global Quality operations: how Kanban did the t...
AGILE PORTUGAL 2018: Changing global Quality operations: how Kanban did the t...
 
Investor roadshow presentation february 2016 final-v2
Investor roadshow presentation   february 2016 final-v2Investor roadshow presentation   february 2016 final-v2
Investor roadshow presentation february 2016 final-v2
 
New Brunswick's Public Service: Pursuing Performance Excellence
New Brunswick's Public Service: Pursuing Performance ExcellenceNew Brunswick's Public Service: Pursuing Performance Excellence
New Brunswick's Public Service: Pursuing Performance Excellence
 
Kishore panda resume 2
Kishore panda resume 2Kishore panda resume 2
Kishore panda resume 2
 
PF_EarnedValuePresentation.ppt
PF_EarnedValuePresentation.pptPF_EarnedValuePresentation.ppt
PF_EarnedValuePresentation.ppt
 
Symposium 2016 : CONF. 401 Jonathan Shriqui EVM: Go Beyond the Numbers
Symposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the NumbersSymposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the Numbers
Symposium 2016 : CONF. 401 Jonathan Shriqui EVM: Go Beyond the Numbers
 

Project Management Analysis for WNS

  • 2. WNS Introduction • Business process management company. • Headquarter is in Mumbai, India. • The company serves over 200 Fortune 500 companies worldwide. 1
  • 3. Net Present Value 2 Payback Period Financial Models Selected Methods
  • 4. Multi Weighted Criteria 2 Project Portfolio Matrix Non-Financial Models Selected Methods
  • 5. Why WNS Selected BPM Automation (Global Star Travels Project)? -Strategic Project with the highest Net Present Value (NPV) of $196,338 -We can recover the investment in 10.9 months -Having the highest weight score of 72 -This project is technological breakthrough with highest commercial payoff. 3
  • 6. Defining  Planning  Executing  Delivering 2 Project Life Cycle
  • 8. Defining Project Scope Objective To design an automated Business Process Management System using MS SQL Server and BI system within 12 months at a cost not to exceed $700,000. Priority Matrix 4
  • 9. Specification Hardware: -Setup Database server -Setup Web Server -System down time < 4 hours Software: -BI system (middle and top management) -Web application system (operation team) 4 Task Deliverables: -BI reports (Analytics tools) for middle and top management -Backend database system -Interfaces / Middleware compatible with existing front end solutions -Technical reference document Project Scope Checklist
  • 10. 5 Work Break Down Structure
  • 11. 3 Integration of WBS and OBS Cost Account -The intersection of WP- Hardware Service and Organization IT department creates a cost account. -By rolling up Hardware Service and Software License WP System (deliverable) cost is calculated.
  • 13. Bottom Up: Support Cost Est 6 Top-Down: Function Point Contract Bid Time and Cost Estimations Contract Bid Summary Costs Total Direct Cost $540,000.00 G&A overhead (10%) $54,000.00 Total Costs $594,000.00 Profit(17.5%) $103,950.00 Total Bid $697,950.00
  • 14. PERT 6 Time and Cost Estimations
  • 15. Risk Management 6 Contingency Funds Managing Risk Total direct cost $442,338 Budget Reserve + $23,950 (for specific critical activities) Management Reserve + $13,712 (~3% of Total Budget) Total Budget = $480,000
  • 17. Resource Allocation Before Levelling: 230 days 6 After Leveling: 237 days
  • 20. Earned Value Chart 6 Indexes Period $0.00 $50,000.00 $100,000.00 $150,000.00 $200,000.00 $250,000.00 $300,000.00 Jan'16 Feb'16 Mar'16 Apr'16 May'16 Jun'16 Jul'16 Aug'16 Sep'16 Oct'16 Nov'16 Dec'16ACWP BCWP BCWS Actual Cost Linear (ACWP) 0 0.2 0.4 0.6 0.8 1 1.2 Jan'16 Feb'16 Mar'16 Apr'16 May'16 Jun'16 Jul'16 Aug'16 Sep'16 Oct'16 Nov'16 Dec'16 SPI CPI CPI <1 indicates over cost SPI <1 indicates behind scheduled. Percentage complete index PCIB: 52% Percentage complete index PCIC: 52% Status Report (Jul-16)
  • 21. Forecast EAC EAC: $452,130 The final project projected cost forecast is $452,130 versus $ 240,256 originally planned. To Complete Performance Index TCPI: TCPI: 1.05 6
  • 22. 3 Crashing Activity Activity 52, 53, 93, 97 are crashed. It cost $7,400 and Project duration will be reduce by 8days.
  • 23. 3 Control Chart Period Status Report Task Name Finish Actual Finish Baseline Start Variance Finish Variance Total Variance 1 March 1st BPM Automation Mon 11/28/16 Mon 11/28/16 0 days 0 days 0 2 July 1st BPM Automation Thu 12/8/16 Mon 11/28/16 0 days 8 days -8 3 Oct 1st BPM Automation Mon 11/28/16 Thu 12/8/16 0 days -8 days 8 -20020 1 2 3 Variance Time Period
  • 24. 3 Conclusion -More time and cost should be spend in Planning Phase to avoid problems in later stages. -Resource allocation in definition need to be reconsider in Planning phase. -Through out project life cycle to make any decision always project objective and definition will be center of attention. -Once project starts dedicated team has to monitor project performance for cost and schedule evaluation periodically and if require have to revise time phased schedule. -Based on status report and performance indices required actions has to be taken like crashing or scope creep.
  • 25. Thank you for your attention! Questions? 7