SlideShare une entreprise Scribd logo
1  sur  66
Télécharger pour lire hors ligne
Agenda
•   Who am I?
•   Batch Production vs. Lean Thinking
•   Principles of Lean Thinking
•   Benefits of Lean
•   Lean Manufacturing Techniques
Dumitru Lucian Arsene
•   Manager with 12 years experience in Production management,
    Strategic Planning and Lean Manufacturing implementation.
•   Successfully completed over 20 continuous improvements projects to
    increase productivity, reduce lead times, improve on-time delivery,
    reduce inventory, increase inventory turns, improve stock accuracy,
    eliminate wastes and fluctuation, exceed customer expectations.

   Professional Background
Pullmaster Winch       Plant Supervisor      09/07 – 05/09
Teleflex Canada        Production Supervisor 01/02 – 09/07
                       Promoted from Operator
Leoni Wiring Systems Plant Manager           01/00 – 11/01
Solectron              Production Manager 06/98 – 01/00
                       Promoted from Production Supervisor
Omnitex                Production Supervisor 08/94 – 06/98
                       Mechanical engineer
Lean Achievements
•   Increased on-time delivery from 40% to 90% at Pullmaster;
•   Reduced manufacturing lead-time from 4-6 weeks to 3-5 days,
    converting functional departments in work cells, at Pullmaster;
•   Increased inventory turnover from 5.5 to 10.2, reducing raw
    inventory from $3 million to 1.6 million at Pullmaster;
•   Improved stock accuracy from 60% to 90% at Teleflex and Leoni
    using Kanban and perpetual inventory stock;
•   Implemented 5S in Work cells: Pullmaster, Teleflex Canada, Leoni;
•   Reduced manpower required to operate work cells by 30% at
    Pullmaster and Teleflex Canada, by 15-20%: Leoni and Solectron;
•   Reduced WIP by 80% at Pullmaster, 50% to 70% at Teleflex by
    implementing small lots and one piece flow;
•   Improved efficiency by 25% at Leoni and Pullmaster using SMED
    and Group Technology and 20-30% at Teleflex using line
    balancing and Standardized work;
•   Reduced quality defects from 50,000 ppm to 300-4,000 ppm at
    Pullmaster, Teleflex, Leoni and Solectron using autonomation.
Lean Thinking and
Manufacturing Process
   Improvement

 Understanding the Problems,
Fixing the Processes, and Using
  Your People to Make it stick
Batch Manufacture

• Machine Utilisation Improved
  – Increasing the batch quantity produces the most
    effective use of the machine between changeovers

• Improved Quality
  – Small well defined tasks allow lower skilled operators to
    produce quality parts


    Best and most efficient use of people and
    machines;
Basic Characteristics of Batch Production

•   Production lot sizes as big as possible
•   Layout according to Machine type
•   Long changeover times
•   Holding safety inventory for production
    problems
•   Detailed work division
•   Single-skilled workers
•   Control based quality
•   Management based on central planning
•   Production planning based on sales
    forecasts
•   Point efficiencies
•   Priority of capacity utilization
Mass Production

          Process 1       A         B
        B B
B   B
        B B




              Process 2                         A+B

WITH SMALLER LOTS


         Process 1 A B A B A B A B



          Process 2       A+B A+B   A+B   A+B
Problems With Batch Production

•   Long delivery times
•   Weakness in responding to customer demands
•   Increase in inventories
•   Decrease in quality
•   Increase in non value adding activities
•   Work becoming more complex everyday
•   Increasing hierarchy and bureaucracy
•   Additional costs
•   Difficulty in adapting to variations
•   Long term planning necessity
•   More capital reqirement
Lean Thinking
• Focus change
  – Lean Thinking is an approach that aims
    to get rid of all the wastes (fats) that
    bring a burden to the system.
  – From machine and people utilisation to performing
    Value Adding operations,
  – Value adding: any operation that changes the
    component, as that is what the customer pays for.

 The components spend more of their time
 having value added
One Piece Flow
                    Batch and Push Manufacturing
     All processes are 1 minute, 3 consecutive processes and lot size ( batch ) of 10


                                            B       B   B BB                 B BB   B   C   C
                                                                                                C   C




    Process A: 10 minutes          Process B: 10 minutes                     Process C: 10 minutes

                      Lead Time : for the whole lot 30 ++ minutes



Continous Flow
“produce one,                                   B              C
                                                                             Lead Time: 12 minutes

  deliver one”



                                       3 min.                      12 min.
Which is best?

  Run factories, not machines

• The aim of factories is not to ensure all
  machines and people are constantly working

• The aim of factories is to produce
  components in the most efficient manner,
  and this achieved by spending the least time
  performing non-value adding activities.
The GOAL

•   As competition increases getting Lean is compulsory
•   Producing only the products demanded by the
    customer
•   At the exact time the customer demands
•   By consuming less resources
•   And focusing on the activities that create value for the
    customer
Basic Principle of Lean Thinking

Value is :
Product and/or service with definite specifications,
for which the customer is ready to pay for, and that
meets the customer’s requirements in a given period
of time, with a definite price.

Value is created by the producer and can only be
defined by the customer.
Value and WasteValue adding
                                                    work
                             Waste
                           ( Muda )

• 3 Types of Activities                               Unavoidable
                                                      waste
  in a Value Stream:                                  ( Incidental
                                                      work )
• Value Adding
   – Transformation of raw material
   to product according to the customers’ demands
                                                  DECREASE
• Necessary Non-Value Adding
   – Die change, adjustment, get/drop tool
• Non-Value Adding                                 ELIMINATE
   – waiting, counting, sorting, defect, rework
Wastes


• Overproduction
• Defects in product
• Inventories
• Unnecessary motion of people
• Excessive transportation of material
• Waiting people, machines and products
• Inappropriate processing
• Inappropriate use of people
WASTES

1. WASTE OF                                   2. WASTE OF A DEFECT
   OVERPRODUCTION
                                          •    This type of waste occurs when a
This waste is caused by producing more         product does not conform to
     product than the customer wants to        proper specifications. This can
     buy.                                      result in rework or scrap.

Primary Cause                                 Primary Cause

                                          •    Inadequate error-proofing and
•   Batch production
                                               quality checks
•   Building to a forecast (scheduled     •    Poor instructions and training
    production)                           •    Poor communication between
                                               customer and manufacturer
•   Traditional productivity              •    Lack of standard work
    measurements                          •    Inadequate supplier quality
                                          •    Need for adjustments
•   Long set-up times
WASTES
3. WASTE OF INVENTORY                   4. WASTE OF MOTION
                                        •   This is waste caused by non-value
•   This type of waste leads to waste       added movement of people and
    of materials, parts, and                machines.
    assembled goods.

Primary Causes
                                        Primary Causes

•   Batch production method             •   Inefficient flow design
•   Long set-up times
•   Lack of continuous flow of
                                        •   Inefficient procedures
    product and people
•   Push production system
                                        •   Lack of standardized work practices
•   Unnecessary product flow
•   Bottlenecks
WASTES
5. WASTE OF                           6. WASTE OF WAITING
   TRANSPORTATION
                                      •   This type of waste results from
•   This type of waste results from       the unnecessary delay of
    the unnecessary movement of           processing material or product.
    material or product.
                                      Primary Causes
Primary Causes

                                      •   Lack of continuous flow
•   Inefficient facility layout
                                      •   Non-value added operations
•   Lack of continuous flow
                                      •   Long set-up times
•   Non-value added operations
                                      •   Production runs too long
•   Batch mentality
                                      •   Poor scheduling
WASTES
7. WASTE OF                            8. WASTE OF A PERSON
   OVERPROCESSING
                                       •   This waste is caused whenever a
•   This is waste caused by                person engages in any of the previous
    unnecessary processes and              wastes.
    operations.

•   Primary Causes
                                       Primary Cause
•   Use expensive high precision
    equipment where simpler tools
                                       •   Lack of effective relationships or
    would be sufficient.
                                           communication between employees,
•   Lack of attention to changes in
    what is needed                         supervisors and managers

•   Not properly identifying customer •    Lack of employee education,
    needs                                  awareness and involvement
•   Variations due to lack of standard
    work and due to variations in
    types of products produced
Examples of Waste

•   Watching a machine run
•   Waiting for parts
•   Counting parts
•   Producing parts that aren’t needed
•   Moving parts over long distances
•   Storing inventory
•   Looking for tools or parts
•   Machine breakdown
•   Rework and scrap
•   Products that don’t meet the needs of customers
The Causes of Waste


•   Insufficient working methods
•   Long changeovers
•   Insufficient processes
•   Lack of training
•   Insufficient maintenance
•   Long distances
•   Lack of leadership
Value Stream
Represents the 3 critical management tasks a
specific product ( goods and / or services )
should pass through :
• Problem Solving : Starting with concept,
  continuing with detailed design and engineering
  and ending with the launch of production
• Information Management : Starting with order,
  continuing with detailed scheduling and ending
  with delivery to the customer
• Physical Transformation : Starting with raw
  material, continuing with production and ending
  with the realization of the final product.
Model


R&D     Planning         Production          Distribution     Sales




      R&D   Planning      Production   Distribution   Sales


                       Lead Time
In Plant Value Stream

                                PLANLAMA
                                 PLANNING
              Sipariş
               ORDER
                                              Sipariş
                                               ORDER
TEDARİKÇİ      emri                            emri                   MÜŞTERİ
                             MRP
 SUPPLIER                                                              CUSTOMER




                           Production programme




          PROSES
          PROCESS                   PROSES
                                    PROCESS                 PROSES
                                                            PROCESS



      1                         1                       1


                        minutes
                        weeks
The GOAL


 design               production           delivery




                    Lead Time

  Value Adding Activity            Waste (Muda)



To Decrease Lead time
To Increase Value Added Time %
The GOAL
 When we decrease the lead time by eliminating
  wastes:
• Financial gains by freeing up resources
• Producing according to real demand instead
  of forecasts
• Providing customer satisfaction
• Providing traceability of quality
• Reducing unnecessary part inventories
• Reducing the risk of being outdated
• Reducing fluctuation due to promotions
Manufacturing Lead time
 A typical manufacturing company


                                               Time
                99 %                  1%

Improvement results with traditional methods


                                               Time
                99.5 %              0.5 %
Lean Manufacturing Approach
                                     Value Added
                                     Waste (Muda)
                         Time
    90 %          10 %
Continous Flow

Produce one - deliver one without waiting
• By performing the real value creating steps
  consecutively, transform the raw material into a
  product and deliver it to the end user
• Perfect every step (KAIZEN)
   – capable – right every time (6 SIGMA)
   – available – always available (TPM)
   – appropriate – flexible and at the desired scale ( LEAN )
One Piece Flow
                    Batch and Push Manufacturing
     All processes are 1 minute, 3 consecutive processes and lot size ( batch ) of 10


                                            B       B   B BB                 B BB   B   C   C
                                                                                                C   C




    Process A: 10 minutes          Process B: 10 minutes                     Process C: 10 minutes

                      Lead Time : for the whole lot 30 ++ minutes



Continous Flow
“produce one,                                   B              C
                                                                             Lead Time: 12 minutes

  deliver one”



                                       3 min.                      12 min.
Continous Flow

• Ford, 1913, model T
  –   Continous flow at the final assembly
  –   Sequential layout of machines
  –   90% resource savings
  –   Same model for 19 years
• Today;
  –   Demand for small lots
  –   Continous flow for all products
  –   Adaptation to fluctuations in customer demand
  –   High product variability demanded by the
      customer
Example : Batch Production

                                                     Semi
 Material     Cut to                               finished
                              Lathe   Welding      product
Warehouse     length
                                                  assembly



 Finished                                          Parts
  Goods       Semi Finished Product Warehouse    Warehouse
Warehouse


Packaging    Painted Parts Storage    Touch up     Final
                                                 Assembly

                       Painting
Example : Flow Production

Incom
                                 Space gained
         Product A Cell
ing                              for new
Parts                            products
Ware                      P
house                     A
         Product B Cell
                          I
                          N   Gains :
                          T
Finish                    I   50% decrease in workforce,
         Product C Cell
ed                        N
Goods
                              45% decrease in space
                          G
Wareh                         94% decrease in lead time
ouse
         Product D Cell
Pull

All steps demand from the previous
• Producing what the next process (customer)
  demands, at the desired quantity ( not more / not
  less ) and at the desired time ( not before or
  later ).
• Following all steps backwards starting from the
  end customer’s demand
• A simple way to put production under control
Pull System
      Value should flow, at the time,
                                for the products,
                                and at the speed,
                                demanded by the customer.
 I demand                               I need one          I need one
                   I need one           more                more
 one now           more
                                                     Here
                                                     you                 Here
            Here                 Here                are                 you
            you                  you                                     are
            are                  are




                                                                         RAW MATERIAL
CUSTOMER
Benefits of Pull Systems

• Resources are only allocated to products that are
  demanded
• No inventories are formed on the value chain
• Financial turnover ( cash flow ) speeds up
• Regulates the value stream according to the
  customer
• Problems like ; Obsolete finished goods
  inventory at hand; rework or scrapping of
  products due to design changes; discount
  campaigns for undemanded products, do not
  arise.
Lean Flow
     ... What if a machine breaks down?
     ... What if there are defective parts among the products?
     ... What if the deliveries are late?
                                                    Dealer

Welding                     Assembly


                                         Main Distributor
               Painting


    Stamping
                  Tier 1 Supplier          Tier 2 Supplier




          ALL STOP !!
Perfection

                                Perfection ( Ideal State )




                Future State




Current State                        Original State
Principles of Lean Thinking - Summary

1. VALUE : Specify value for the product
2. VALUE STREAM : Identify the value
  stream for every product family
3. FLOW : Make the identified value flow
4. PULL : Make the customer pull the value
5. PERFECTION : Manage towards
  perfection.

 To avoid focusing solely on the technics ,
      always repeat the principles !
Benefits
Parameters                 Gains
Product Design Lead Time   75%
Manufacturing Lead time    90%
Productivity               100%
Defects                    80%
Inventories                90%
Area used                  50%
Work Accidents             50%
New Investments            Too little
Gains

SHORT TERM                  MIDDLE TERM                   LONG TERM

Reduction in scrap         Increase in present product    New products
and rework                 sales
                                                          Utilization of freed up
Reduction in overtime      Bringing outsourced            space
                           production in the plant
Increase in delivery       Adding extra value to the      Reduction in
performance                products                       obsolete inventories
                                        New sales via better
Reduction in                            service
inventories
               Improvement in            Reduction in support
               cash flow                 function department
               Reduction in              costs
               manpower costs
Lean Company Model


                  LEAN LEADERSHIP



   Lean                   LEAN
                      MANUFACTURING                Lean Supply
organization             SYSTEM
    and         JIT                 AUTONOMATION      Chain
                                                   Development
 processes




         Respect for People and Mutual Trust
LEAN MANUFACTURING TECHNIQUES

                    VALUE STREAM MAPPING
                                         ONE PIECE FLOW-SMALL LOTS
REDUCING INVENTORY

   KANBAN                                                  STANDARDIZED
                                                              WORK
     SMED
                                                                  KAIZEN
VISUAL CONTROL
                                                                 5S
   STANDARD WIP
          WORK CELL                                      TAKT TIME
                              JIT/PULL            TPM
“The key to lean is in the thinking and not just in the tools”
                                                                 James WOMACK
5S

          The 5-S Workplace
SORT                           •Sort needed & unneeded items.
                                   Red tag unneeded items.
SET IN ORDER                   •Put things in proper places,
                                   arrange and label.
SHINE                          •Clean up the workplace.

STANDARDIZE                    •Standardize the 1st 3 S’s.
                                   Document Methods &
                                   maintain cleanliness.
SUSTAIN                        •Make 5-S a part of the job.

          Stick to it! Grade it! Improve it!
5S Program
5-S
            Benefits                       Constraints
•   Remove unnecessary items.     • Daily workforce involvement,
•   Clear workplace.                sustained resource allocation.
•   Save space.                   • Minimal investment for storage
•   Save time for motion.           locations and identification.
                                  • Regular audits required to
•   Standardized procedures.
                                    sustain.
•   Organized activities.
•   Improve safety.
•   Improve up time.
•   Team building start point.
TAKT TIME
•   TAKT Time reflects the rate at which customers buy our
    products;
•   Takt time is calculated by dividing the real available time by the
    quantity of goods sold each day:

    Daily effective minute     = TAKT Time
    Daily customer demand

•   The actual amount of members needed to build a product at a
    given TAKT TIME:

    The sum of the Cycle Time = No. of operators required
    Divided by the TAKT TIME
TAKT Time benefits
Having a TAKT time affords the ability to do the following:

•   Compete in a marketplace where the demand and cost of
    product is being dictated by the customer.
•   Pull the product down the line.
•   Monitor the production rate at intervals that are much
    smaller than the TAKT time (pro-active approach). When
    issues are found that stop the series of work steps to be
    completed on time, they can be dealt with in a concise
    documented manner.
•   Build without overtime.
•   Determine the correct number of production workers
    required.
•   Affords targeted costing (both from labour and product).
•   Control cost more effectively.
Value Stream Mapping                                                                                                               Current State Value Stream
                                                                                                                                                                                     Production
                                                                                                                                                                  Forecast             Control                               Forecast
                                                                                                                                 Michigan                                                                                                          State Street
                                                                                                                                  Steel         Weekly Order                      MRP                      Daily Order                              Assembly

                                                                                                                                                                                Weekly Schedule

                                                                                                                                                                                                                    Daily Ship
                                                                                                                                                                                                                    Schedule
                                                                                                                      2 x Week                                                                                                                                Daily




                                                                                                                           Stamping                  S. Weld 1               S. Weld 2                 Assembly 1                    Assembly 2                   Shipping
                                                                                                                      I                     I                       I                        I                           I                            I

                          Future State Value Stream                                                                                                                                                                                                           Production
                                                                                                                                                                                                                                                              Lead Time
                                                                                                                                                                                                                                                              = 23.5 days
                                                                                                                                                                                                                                                              Value
                                                                                                                                                                                                                                                              Added Time
                                                                                                                                                                                                                                                              = 184 secs



                                           Forecast
                                                         Production
                                                           Control                      Forecast
                                                                                                                                                                                                                                         Check
               Michigan
                Steel        Daily Order                                  Daily Order
                                                                                                       State Street
                                                                                                        Assembly                                                                                                                      progress and
                                                                      Daily Order
                                                                                                                                                                                                                                        stabilise
            Daily                                                                                   Daily




                                                                                                            V S Manager Jim
                                                                                                                                            Value Stream Plan                                                                                     Product Family
                                                                                                            Date 03/02/2003                                                                                                                       Steering Brackets
                                                        Weld and
                           Stamping                   Assembly Cell                      Shipping
                                                                                                            Product        Value                                                                                                                                  Person
                                                                                                            Family         Stream                                Measurable                          Monthly Schedule                                             in
                                                                                                            Business       Objective                             Goal                                                                                             Charge
                                                                                                            Objective                                                                    1       2     3      4          5       6        7       8       9
                                                                                                      Production        Pacemaker
                                                                                                      Lead Time         *Continuous flow from
                                                                                                      = 4.5 days         weld to assembly                        Zero WIP                                                                                         John
                                                                                                                        *Kaizen to 168 secs                      < 168 s/t                                                                                        Dave
                                                                                                      Value             *Eliminate weld
                                                                                                      Added Time         changeover                              < 30 sec c/o                                                                                     Sam
                                                                                                      = 166 secs        *Uptime weld #2                          100%                                                                                             Mike
                                                                                                          Improve       *Finished goods pull                     2 days FG                                                                                        Sue
                                                                                                          Profitability *Materials handler                       Pull Schedule                                                                                    James
                                                                                                          In Steering    routes


 Ask the                                                                                                  Brackets      Stamping
                                                                                                                        *Stamping Pull                           1 day inventory
                                                                                                                                                                 + pull schedule
                                                                                                                                                                                                                                                                  Fred

                                                                                                                            *Stamping changeover                 batch size                                                                                       Tim

  key                                                                                                                                                            300/160 pieces
                                                                                                                                                                 c/o < 10 min

                                                                                                                            Supplier

questions                                                                                                                   *Pull coils with
                                                                                                                             daily deliveryr
                                                                                                                                                                 daily delivery
                                                                                                                                                                 < 1.5 days of
                                                                                                                                                                 coils at press
                                                                                                                                                                                                                                                                  Graham
Value Stream Mapping
  %                                                                                             ppm
              Amplification                                                                              Quality & Delivery        %
  40                                                                                            2000
  30
  20
                                   Current State                                                1500
                                                                                                1000
                                                                                                                                   10


                                                                                                                                     5
  10                                                                                             500
  0                                                                                                0                                 0

          F E D C B A                                                                                    F   E        C      A
                                                                                                                                                                                            Time reduced
                                            %                                                                                              ppm
                                            40
                                                         Amplification
                                                                                                                                           2000
                                                                                                                                                          Quality & Delivery        %
                                                                                                                                                                                             from 20 to 5
                                            30
                                            20
                                                                                      Future State 2                                       1500
                                                                                                                                           1000
                                                                                                                                                                                    10

                                                                                                                                                                                      5         days
                                            10                              Flow and Pull between Plants500
                                            0                                                                                                0                                        0

                                                    F E D C B A                                                             Dist. Centre              F       E        C      A
  Steel
                                                                                           %                                                                                                    ppm
                                                                                                   Amplification
                                                                                                                                   Ideal State                                                                Quality & Delivery            %
                                                                                           40                                                                                                   2000
                                                                                                                                                                                                                                            10
                                                                                           30                                                                                                   1500
                                                                                           20                                                                                                   1000                                          5
                                                                                           10                                                                                                       500
                              Warehouse                                  Cross Dock

                                                                                           0
                                                                                            Cross Dock
                                                                                                                        Value Stream Compression                                                      0                                       0
                Stamping                                Wipers                                                   Assembly
                                                                                                                                                                             Dist. Centre
                                                                                                 F E D C B A                                                                                                  F       E         C     A
                                            Steel                                                                                  Time
DELTA          GAMMA
STEEL         STAMPING                           BETA WIPERS                                             ALPHA MOTORS              44d
Steps                                                                                                                              55m
 73
  8       F        E              D                       C                            B                            A
                                                            Stamping                            Wipers                                                            Assembly

                                                                                                                                                                                    Time                                             Dist. Centre
                                          DELTA            GAMMA
                                                                                                                                                  Steel
                                          STEEL           STAMPING                         BETA WIPERS                                                    ALPHA MOTORS              16d
                                          Steps                                                                                                                                     55m

      Time                                 39
                                            8       F            E               D                 C                          B                                      A
                                                                                                                                                                                    Stamping         Wiper

    reduced                                                                                                                                                                            Cell          Cell
                                                                                                                                                                                                                          Assembly

                                                                                                                                                                                                                                            Time
                                                                                                                                           EPSILON

   from 49 to                                                                                                                      Steps
                                                                                                                                            STEEL                                  SUPPLIER PARK              ALPHA MOTORS                  3d
                                                                                                                                                                                                                                            55m


     20 days                                                                                                                         30
                                                                                                                                      8                         F                           E   D         C       B         A
WORK CELLS
                                           Original Process Layout
                                                         Assembly
•   Group dissimilar machines in
    manufacturing cell to produce    4              6               7             9
    family of parts
                                           5                               8

                                           2                          10             12
•   Work flows in one direction
    through cell                     1              3                      11


                                    A      B        C    Raw materials

•   One worker tends several               Cellular Layout Solution
                                                               Assembly
    machines
                                           8        10            9              12
•   Cycle time adjusted by
                                                                                          11
    changing number of workers        4                           6
                                          Cell1                                 Cell 3
                                                         Cell 2
                                                                                          7


                                           2        1             3              5

                                    Raw materials          A      C        B
WORK CELLS Benefits
•   Cellular manufacturing achieves the benefits of flow
    based manufacturing
•   This simplifies material flow compared to a traditional
    process layout
•   Ownership and responsibility for a product rests with the
    operators of the cell
•   Shorter Lead Time
•   Improved Quality - Quicker problem identification
•   Improved Quality - Less potential rework or scrap
•   Less Material Handling
•   Improved Coordination
•   Reduced Inventory
•   Departmental conflicts eliminated
•   Simplified Scheduling
•    Less Space Required
STANDARDIZED WORK
There can be no improvement without the basis of standard work.
                 .
When normal and abnormal work activities are undifferentiated, waste
almost inevitably occurs. Standardized Work, on the other hand, provides
an efficient framework in which to perform our jobs.

‘Standardized Work’ is a general phrase which refers to all of the
standards (quality, safety, procedural) used in the process of carrying out
routine operations.

Standard work provides a consistent routine and a basis for improvement.

Three elements are important: Takt time/Cycle time, Work sequence and
Standard Work in Process (SWIP).
Standard Work-in-Process
•   The MINIMUM amount of Work-In-Process required to allow the
    operator continued performance of Standard Work.
•   By standardizing the WIP, we can find a way to reduce it.
•   Shortened LEAD Time
•   Quick capture of quality problems
•   Unnecessary WIP eliminated
•   Potentially less staffing in cell
•   Members do more of VA process
•   Members become multi-functional

•   The aim is one-piece-flow
Reducing Inventory
•   Reducing Inventories

•   In traditional manufacturing, inventories are seen as assets

•   Inventories provide a safety buffer, and result from maximizing
    machine utilization

•   JIT views inventory as waste

•   Inventory is evidence of poor design, poor coordination, and
    poor operation of a manufacturing system

•   Inventory Hides Problems
Reducing Inventory

                                                   supply /
                     Inventory level               material
defects
/ rework                                           flow


                set-up                      downtime


                                       labour
     capacity             planning     force
KANBAN
•   Kanban card indicates standard quantity of production
•   Derived from two-bin inventory system
•   Kanban maintains discipline of pull production
•   Production kanban authorizes production
•   Withdrawal kanban authorizes movement of goods
•   Used when one-piece flow cannot be achieved
Kanban
•   Visual Refill /Replenishment Systems:

•   A visual replenishment system is one in which tools such
•   as cards, lights, grids, squares, flags or other visual means
•   are used to signal the need for re-supply of materials, parts
•   or supplies. (“KANBAN” = Signal to control WIP)
Determining Number of Kanbans



                 average demand during lead time + safety stock
No. of Kanbans =
                                container size

                                dL + S
                          N =
   where                          C

           N      = number of kanbans or containers
           d      = average demand over some time period
           L      = lead time to replenish an order
           S      = safety stock
           C      = container size
Line balancing
•   Time and labour variables are the basis of line balancing.
•   They are interrelated and are determining the cost of the
    producing a product.
•   If one person is doing a part, the processes are done in
    sequence. By adding persons, the throughput time will be
    reduce and all the operations are done in the same time. The
    throughput time is the longest operation time.
•   To balance the line, one operator may do 2 faster operation or
    we may move some steps from the longest operation to other
    operations.
SMED
•   SMED is a process for dramatically and methodically reducing
    set-up or changeover times.
•   Will enable significant reduction of lot sizes.

    SMED Principles

•   Setup time is the time between parts when the machine is idle
    and operator is doing a changeover.
•   Separate internal setup from external setup
•   Convert internal setup to external setup
•   Streamline all aspects of setup
•   Perform setup activities in parallel or eliminate them.
SMED

• Set-up delays causes:

     Searching;
     Walking;
     Poor Schedule information;
     No checklist;
     Lack of calibration;
     Missing tools
     Waiting;
SMED

Setup Reduction methods:
 - Parallel setup tasks: ideally, two people can do the job in half
 the time.
 - Using quick-attachment devices: one-turn bolt attachment
 devices, attachments with fixed holders and pins, clamping
 devices,
 - Eliminate adjustments: shims with fixed-position holders on
 machines, accommodating variable-height dies without making
 adjustments,
 - Improve external setups: store fixtures, holders, plates, tools
 near machines, prepare setup kits and carts, improve material
 handling.
TPM
•   Small lot production with little inventory requires
    equipment that:
      – Doesn’t break down
      – Doesn’t produce defects
      – Performs well
•   Breakdown maintenance
      – Repairs to make failed machine operational
•   Preventive maintenance
      – System of periodic inspection & maintenance to keep
         machines operating
•   TPM combines preventive maintenance & total quality concepts
•   TPM seeks to find the root causes of equipment problems, and
    fix them
TPM
Preventive Maintenance Elements
Maintain normal operating conditions
• Maintain equipment requirements
• Keep equipment and facilities clean and organized
• Monitor equipment daily
• Schedule preventive maintenance
• Manage maintenance information
• Use predictive (condition-based) maintenance
Role of Operators
   –   Keep machine clean
   –   Routine lubrication and adjustments
   –   Visual inspection (cracks, oil leaks)
   –   Be aware of unusual sounds, heat, vibration, etc.
Benefits Of Lean Production
1. Reduced             7.  Greater flexibility
   inventory           8.  Better relations with
2. Improved quality        suppliers
3. Lower costs         9. Simplified scheduling
4. Reduced space           and control activities
   requirements        10. Increased capacity
5. Shorter lead time   11. Better use of human
6. Increased               resources
   productivity        12. More product variety
Metrics / Expectations (examples)
•   Item                       potential improvement
•   Floor Space                         29%
•   Scrap                               46%
•   QC Rejects                          95%
•   Rework                              72%
•   Work-in-Process                     59%
•   Setup Time                          66%
•   Manpower                            32%
•   Equipment Required                  34%
•   Lead Time                           56%
•   Distance Parts Travel               54%
•   Cycle Time                          18%
•   Finished Goods Inventory            43%
•   Down Time                           52%
                                              (Source: Kaizen Institute)

Contenu connexe

Tendances

Lean Manufacturing Overview - MBA Consulting Class
Lean Manufacturing Overview - MBA Consulting ClassLean Manufacturing Overview - MBA Consulting Class
Lean Manufacturing Overview - MBA Consulting Class
Sam Bishop
 
Lean manufacturing (1)
Lean manufacturing (1)Lean manufacturing (1)
Lean manufacturing (1)
Arup Dey
 

Tendances (19)

Jit
JitJit
Jit
 
Lean manufacturing
Lean manufacturingLean manufacturing
Lean manufacturing
 
How does Kanban work? - ADDVALUE - Nilesh Arora
How does Kanban work? - ADDVALUE - Nilesh AroraHow does Kanban work? - ADDVALUE - Nilesh Arora
How does Kanban work? - ADDVALUE - Nilesh Arora
 
Lean operations presentation
Lean operations   presentationLean operations   presentation
Lean operations presentation
 
Waste
WasteWaste
Waste
 
Lean Manufacturing Overview - MBA Consulting Class
Lean Manufacturing Overview - MBA Consulting ClassLean Manufacturing Overview - MBA Consulting Class
Lean Manufacturing Overview - MBA Consulting Class
 
Lean manufacturing, lean development and kanban - Lean Development and Agile ...
Lean manufacturing, lean development and kanban - Lean Development and Agile ...Lean manufacturing, lean development and kanban - Lean Development and Agile ...
Lean manufacturing, lean development and kanban - Lean Development and Agile ...
 
Office Lean Sample
Office Lean SampleOffice Lean Sample
Office Lean Sample
 
Continuous improvement and waste Savant Goup Connectivity Solutions
Continuous improvement and waste Savant Goup Connectivity SolutionsContinuous improvement and waste Savant Goup Connectivity Solutions
Continuous improvement and waste Savant Goup Connectivity Solutions
 
FREE DOWNLOAD - INTRODUCTION TO LEAN PRESENTATION
FREE DOWNLOAD - INTRODUCTION TO LEAN PRESENTATIONFREE DOWNLOAD - INTRODUCTION TO LEAN PRESENTATION
FREE DOWNLOAD - INTRODUCTION TO LEAN PRESENTATION
 
Lean management
Lean managementLean management
Lean management
 
Kanban
KanbanKanban
Kanban
 
Applications of lean manufacturing tools
Applications of lean manufacturing toolsApplications of lean manufacturing tools
Applications of lean manufacturing tools
 
Lean Process and Production
Lean Process and ProductionLean Process and Production
Lean Process and Production
 
WASTE ELIMINATION
WASTE ELIMINATIONWASTE ELIMINATION
WASTE ELIMINATION
 
Fundamentals of Lean
Fundamentals of LeanFundamentals of Lean
Fundamentals of Lean
 
16 lean manufacturing
16 lean manufacturing16 lean manufacturing
16 lean manufacturing
 
Lean Production
Lean ProductionLean Production
Lean Production
 
Lean manufacturing (1)
Lean manufacturing (1)Lean manufacturing (1)
Lean manufacturing (1)
 

En vedette

460 operations - 4.20
460   operations - 4.20460   operations - 4.20
460 operations - 4.20
Kyle Bakken
 
The future of OpenERP Warehouse management system: future improvements. Quent...
The future of OpenERP Warehouse management system: future improvements. Quent...The future of OpenERP Warehouse management system: future improvements. Quent...
The future of OpenERP Warehouse management system: future improvements. Quent...
Odoo
 
Supply Chain Management Basics: Inventory Picking Strategies
Supply Chain Management Basics: Inventory Picking StrategiesSupply Chain Management Basics: Inventory Picking Strategies
Supply Chain Management Basics: Inventory Picking Strategies
Angela Carver
 

En vedette (19)

Lean At The Dentist 2009
Lean At The Dentist   2009Lean At The Dentist   2009
Lean At The Dentist 2009
 
How to improve order picking efficiency
How to improve order picking efficiencyHow to improve order picking efficiency
How to improve order picking efficiency
 
Using Safety Drive Lean Implementation
Using Safety Drive Lean ImplementationUsing Safety Drive Lean Implementation
Using Safety Drive Lean Implementation
 
460 operations - 4.20
460   operations - 4.20460   operations - 4.20
460 operations - 4.20
 
The future of OpenERP Warehouse management system: future improvements. Quent...
The future of OpenERP Warehouse management system: future improvements. Quent...The future of OpenERP Warehouse management system: future improvements. Quent...
The future of OpenERP Warehouse management system: future improvements. Quent...
 
Open erp tutorial_basico
Open erp tutorial_basicoOpen erp tutorial_basico
Open erp tutorial_basico
 
MWV CONTROL VS SPEC
MWV CONTROL VS SPECMWV CONTROL VS SPEC
MWV CONTROL VS SPEC
 
Batch v Lean 1 piece flow training
Batch v Lean 1 piece flow trainingBatch v Lean 1 piece flow training
Batch v Lean 1 piece flow training
 
Supply Chain Management Basics: Inventory Picking Strategies
Supply Chain Management Basics: Inventory Picking StrategiesSupply Chain Management Basics: Inventory Picking Strategies
Supply Chain Management Basics: Inventory Picking Strategies
 
New Employee Lean Orientation
New Employee Lean OrientationNew Employee Lean Orientation
New Employee Lean Orientation
 
Kanban Pull System
Kanban Pull SystemKanban Pull System
Kanban Pull System
 
Cellular Manufacturing (Flexible Operations)
Cellular Manufacturing (Flexible Operations)Cellular Manufacturing (Flexible Operations)
Cellular Manufacturing (Flexible Operations)
 
POKA-YOKE - A Lean Strategy to Mistake Proofing
POKA-YOKE - A Lean Strategy to Mistake ProofingPOKA-YOKE - A Lean Strategy to Mistake Proofing
POKA-YOKE - A Lean Strategy to Mistake Proofing
 
Cellular LayOut
Cellular LayOutCellular LayOut
Cellular LayOut
 
Types of production system
Types of production systemTypes of production system
Types of production system
 
Lean presentation ppt
Lean presentation pptLean presentation ppt
Lean presentation ppt
 
Presentation Safety Management Systems & Lean Manufacturing
Presentation  Safety Management Systems & Lean ManufacturingPresentation  Safety Management Systems & Lean Manufacturing
Presentation Safety Management Systems & Lean Manufacturing
 
Types of layouts
Types of layoutsTypes of layouts
Types of layouts
 
types of production system
types of production systemtypes of production system
types of production system
 

Similaire à Lean DL Arsene

lean manufacturing.ppt cost profit accounts
lean manufacturing.ppt cost profit accountslean manufacturing.ppt cost profit accounts
lean manufacturing.ppt cost profit accounts
SabaKhalid48
 
Lean - PPT (Lean manufacturing and six sigma)
Lean - PPT (Lean manufacturing and six sigma)Lean - PPT (Lean manufacturing and six sigma)
Lean - PPT (Lean manufacturing and six sigma)
Blankdevil
 

Similaire à Lean DL Arsene (20)

Just in time
Just in timeJust in time
Just in time
 
Ch9 Jit
Ch9 JitCh9 Jit
Ch9 Jit
 
10. just in-time
10. just in-time10. just in-time
10. just in-time
 
Presentation on Just in Time
Presentation on Just in TimePresentation on Just in Time
Presentation on Just in Time
 
Introduction of Flow Management in Manufacturing - ADDVALUE - Nilesh Arora
Introduction of Flow Management in Manufacturing - ADDVALUE - Nilesh AroraIntroduction of Flow Management in Manufacturing - ADDVALUE - Nilesh Arora
Introduction of Flow Management in Manufacturing - ADDVALUE - Nilesh Arora
 
lean manufacturing.ppt cost profit accounts
lean manufacturing.ppt cost profit accountslean manufacturing.ppt cost profit accounts
lean manufacturing.ppt cost profit accounts
 
Just in time manufacturing ppt
Just in time manufacturing pptJust in time manufacturing ppt
Just in time manufacturing ppt
 
EngManagement - Lecture 8.pptx
EngManagement - Lecture 8.pptxEngManagement - Lecture 8.pptx
EngManagement - Lecture 8.pptx
 
Lean - PPT (Lean manufacturing and six sigma)
Lean - PPT (Lean manufacturing and six sigma)Lean - PPT (Lean manufacturing and six sigma)
Lean - PPT (Lean manufacturing and six sigma)
 
Lean management
Lean managementLean management
Lean management
 
Toyota production system
Toyota production systemToyota production system
Toyota production system
 
Lean manufacturing
Lean manufacturingLean manufacturing
Lean manufacturing
 
JIT and lean operations
JIT and lean operationsJIT and lean operations
JIT and lean operations
 
Just in time
Just in timeJust in time
Just in time
 
Lean manufacturing
Lean manufacturingLean manufacturing
Lean manufacturing
 
Production management
Production managementProduction management
Production management
 
Lean Management and Kanban System
Lean Management and Kanban SystemLean Management and Kanban System
Lean Management and Kanban System
 
LEAN
LEANLEAN
LEAN
 
Designing the Enterprise for Manufacturing
Designing the Enterprise for ManufacturingDesigning the Enterprise for Manufacturing
Designing the Enterprise for Manufacturing
 
BBA UNIT -1 INTRODUCTION ABOUT PRODUCTION.ppt
BBA UNIT -1 INTRODUCTION ABOUT PRODUCTION.pptBBA UNIT -1 INTRODUCTION ABOUT PRODUCTION.ppt
BBA UNIT -1 INTRODUCTION ABOUT PRODUCTION.ppt
 

Lean DL Arsene

  • 1. Agenda • Who am I? • Batch Production vs. Lean Thinking • Principles of Lean Thinking • Benefits of Lean • Lean Manufacturing Techniques
  • 2. Dumitru Lucian Arsene • Manager with 12 years experience in Production management, Strategic Planning and Lean Manufacturing implementation. • Successfully completed over 20 continuous improvements projects to increase productivity, reduce lead times, improve on-time delivery, reduce inventory, increase inventory turns, improve stock accuracy, eliminate wastes and fluctuation, exceed customer expectations. Professional Background Pullmaster Winch Plant Supervisor 09/07 – 05/09 Teleflex Canada Production Supervisor 01/02 – 09/07 Promoted from Operator Leoni Wiring Systems Plant Manager 01/00 – 11/01 Solectron Production Manager 06/98 – 01/00 Promoted from Production Supervisor Omnitex Production Supervisor 08/94 – 06/98 Mechanical engineer
  • 3. Lean Achievements • Increased on-time delivery from 40% to 90% at Pullmaster; • Reduced manufacturing lead-time from 4-6 weeks to 3-5 days, converting functional departments in work cells, at Pullmaster; • Increased inventory turnover from 5.5 to 10.2, reducing raw inventory from $3 million to 1.6 million at Pullmaster; • Improved stock accuracy from 60% to 90% at Teleflex and Leoni using Kanban and perpetual inventory stock; • Implemented 5S in Work cells: Pullmaster, Teleflex Canada, Leoni; • Reduced manpower required to operate work cells by 30% at Pullmaster and Teleflex Canada, by 15-20%: Leoni and Solectron; • Reduced WIP by 80% at Pullmaster, 50% to 70% at Teleflex by implementing small lots and one piece flow; • Improved efficiency by 25% at Leoni and Pullmaster using SMED and Group Technology and 20-30% at Teleflex using line balancing and Standardized work; • Reduced quality defects from 50,000 ppm to 300-4,000 ppm at Pullmaster, Teleflex, Leoni and Solectron using autonomation.
  • 4. Lean Thinking and Manufacturing Process Improvement Understanding the Problems, Fixing the Processes, and Using Your People to Make it stick
  • 5. Batch Manufacture • Machine Utilisation Improved – Increasing the batch quantity produces the most effective use of the machine between changeovers • Improved Quality – Small well defined tasks allow lower skilled operators to produce quality parts Best and most efficient use of people and machines;
  • 6. Basic Characteristics of Batch Production • Production lot sizes as big as possible • Layout according to Machine type • Long changeover times • Holding safety inventory for production problems • Detailed work division • Single-skilled workers • Control based quality • Management based on central planning • Production planning based on sales forecasts • Point efficiencies • Priority of capacity utilization
  • 7. Mass Production Process 1 A B B B B B B B Process 2 A+B WITH SMALLER LOTS Process 1 A B A B A B A B Process 2 A+B A+B A+B A+B
  • 8. Problems With Batch Production • Long delivery times • Weakness in responding to customer demands • Increase in inventories • Decrease in quality • Increase in non value adding activities • Work becoming more complex everyday • Increasing hierarchy and bureaucracy • Additional costs • Difficulty in adapting to variations • Long term planning necessity • More capital reqirement
  • 9. Lean Thinking • Focus change – Lean Thinking is an approach that aims to get rid of all the wastes (fats) that bring a burden to the system. – From machine and people utilisation to performing Value Adding operations, – Value adding: any operation that changes the component, as that is what the customer pays for. The components spend more of their time having value added
  • 10. One Piece Flow Batch and Push Manufacturing All processes are 1 minute, 3 consecutive processes and lot size ( batch ) of 10 B B B BB B BB B C C C C Process A: 10 minutes Process B: 10 minutes Process C: 10 minutes Lead Time : for the whole lot 30 ++ minutes Continous Flow “produce one, B C Lead Time: 12 minutes deliver one” 3 min. 12 min.
  • 11. Which is best? Run factories, not machines • The aim of factories is not to ensure all machines and people are constantly working • The aim of factories is to produce components in the most efficient manner, and this achieved by spending the least time performing non-value adding activities.
  • 12. The GOAL • As competition increases getting Lean is compulsory • Producing only the products demanded by the customer • At the exact time the customer demands • By consuming less resources • And focusing on the activities that create value for the customer
  • 13. Basic Principle of Lean Thinking Value is : Product and/or service with definite specifications, for which the customer is ready to pay for, and that meets the customer’s requirements in a given period of time, with a definite price. Value is created by the producer and can only be defined by the customer.
  • 14. Value and WasteValue adding work Waste ( Muda ) • 3 Types of Activities Unavoidable waste in a Value Stream: ( Incidental work ) • Value Adding – Transformation of raw material to product according to the customers’ demands DECREASE • Necessary Non-Value Adding – Die change, adjustment, get/drop tool • Non-Value Adding ELIMINATE – waiting, counting, sorting, defect, rework
  • 15. Wastes • Overproduction • Defects in product • Inventories • Unnecessary motion of people • Excessive transportation of material • Waiting people, machines and products • Inappropriate processing • Inappropriate use of people
  • 16. WASTES 1. WASTE OF 2. WASTE OF A DEFECT OVERPRODUCTION • This type of waste occurs when a This waste is caused by producing more product does not conform to product than the customer wants to proper specifications. This can buy. result in rework or scrap. Primary Cause Primary Cause • Inadequate error-proofing and • Batch production quality checks • Building to a forecast (scheduled • Poor instructions and training production) • Poor communication between customer and manufacturer • Traditional productivity • Lack of standard work measurements • Inadequate supplier quality • Need for adjustments • Long set-up times
  • 17. WASTES 3. WASTE OF INVENTORY 4. WASTE OF MOTION • This is waste caused by non-value • This type of waste leads to waste added movement of people and of materials, parts, and machines. assembled goods. Primary Causes Primary Causes • Batch production method • Inefficient flow design • Long set-up times • Lack of continuous flow of • Inefficient procedures product and people • Push production system • Lack of standardized work practices • Unnecessary product flow • Bottlenecks
  • 18. WASTES 5. WASTE OF 6. WASTE OF WAITING TRANSPORTATION • This type of waste results from • This type of waste results from the unnecessary delay of the unnecessary movement of processing material or product. material or product. Primary Causes Primary Causes • Lack of continuous flow • Inefficient facility layout • Non-value added operations • Lack of continuous flow • Long set-up times • Non-value added operations • Production runs too long • Batch mentality • Poor scheduling
  • 19. WASTES 7. WASTE OF 8. WASTE OF A PERSON OVERPROCESSING • This waste is caused whenever a • This is waste caused by person engages in any of the previous unnecessary processes and wastes. operations. • Primary Causes Primary Cause • Use expensive high precision equipment where simpler tools • Lack of effective relationships or would be sufficient. communication between employees, • Lack of attention to changes in what is needed supervisors and managers • Not properly identifying customer • Lack of employee education, needs awareness and involvement • Variations due to lack of standard work and due to variations in types of products produced
  • 20. Examples of Waste • Watching a machine run • Waiting for parts • Counting parts • Producing parts that aren’t needed • Moving parts over long distances • Storing inventory • Looking for tools or parts • Machine breakdown • Rework and scrap • Products that don’t meet the needs of customers
  • 21. The Causes of Waste • Insufficient working methods • Long changeovers • Insufficient processes • Lack of training • Insufficient maintenance • Long distances • Lack of leadership
  • 22. Value Stream Represents the 3 critical management tasks a specific product ( goods and / or services ) should pass through : • Problem Solving : Starting with concept, continuing with detailed design and engineering and ending with the launch of production • Information Management : Starting with order, continuing with detailed scheduling and ending with delivery to the customer • Physical Transformation : Starting with raw material, continuing with production and ending with the realization of the final product.
  • 23. Model R&D Planning Production Distribution Sales R&D Planning Production Distribution Sales Lead Time
  • 24. In Plant Value Stream PLANLAMA PLANNING Sipariş ORDER Sipariş ORDER TEDARİKÇİ emri emri MÜŞTERİ MRP SUPPLIER CUSTOMER Production programme PROSES PROCESS PROSES PROCESS PROSES PROCESS 1 1 1 minutes weeks
  • 25. The GOAL design production delivery Lead Time Value Adding Activity Waste (Muda) To Decrease Lead time To Increase Value Added Time %
  • 26. The GOAL When we decrease the lead time by eliminating wastes: • Financial gains by freeing up resources • Producing according to real demand instead of forecasts • Providing customer satisfaction • Providing traceability of quality • Reducing unnecessary part inventories • Reducing the risk of being outdated • Reducing fluctuation due to promotions
  • 27. Manufacturing Lead time A typical manufacturing company Time 99 % 1% Improvement results with traditional methods Time 99.5 % 0.5 % Lean Manufacturing Approach Value Added Waste (Muda) Time 90 % 10 %
  • 28. Continous Flow Produce one - deliver one without waiting • By performing the real value creating steps consecutively, transform the raw material into a product and deliver it to the end user • Perfect every step (KAIZEN) – capable – right every time (6 SIGMA) – available – always available (TPM) – appropriate – flexible and at the desired scale ( LEAN )
  • 29. One Piece Flow Batch and Push Manufacturing All processes are 1 minute, 3 consecutive processes and lot size ( batch ) of 10 B B B BB B BB B C C C C Process A: 10 minutes Process B: 10 minutes Process C: 10 minutes Lead Time : for the whole lot 30 ++ minutes Continous Flow “produce one, B C Lead Time: 12 minutes deliver one” 3 min. 12 min.
  • 30. Continous Flow • Ford, 1913, model T – Continous flow at the final assembly – Sequential layout of machines – 90% resource savings – Same model for 19 years • Today; – Demand for small lots – Continous flow for all products – Adaptation to fluctuations in customer demand – High product variability demanded by the customer
  • 31. Example : Batch Production Semi Material Cut to finished Lathe Welding product Warehouse length assembly Finished Parts Goods Semi Finished Product Warehouse Warehouse Warehouse Packaging Painted Parts Storage Touch up Final Assembly Painting
  • 32. Example : Flow Production Incom Space gained Product A Cell ing for new Parts products Ware P house A Product B Cell I N Gains : T Finish I 50% decrease in workforce, Product C Cell ed N Goods 45% decrease in space G Wareh 94% decrease in lead time ouse Product D Cell
  • 33. Pull All steps demand from the previous • Producing what the next process (customer) demands, at the desired quantity ( not more / not less ) and at the desired time ( not before or later ). • Following all steps backwards starting from the end customer’s demand • A simple way to put production under control
  • 34. Pull System Value should flow, at the time, for the products, and at the speed, demanded by the customer. I demand I need one I need one I need one more more one now more Here you Here Here Here are you you you are are are RAW MATERIAL CUSTOMER
  • 35. Benefits of Pull Systems • Resources are only allocated to products that are demanded • No inventories are formed on the value chain • Financial turnover ( cash flow ) speeds up • Regulates the value stream according to the customer • Problems like ; Obsolete finished goods inventory at hand; rework or scrapping of products due to design changes; discount campaigns for undemanded products, do not arise.
  • 36. Lean Flow ... What if a machine breaks down? ... What if there are defective parts among the products? ... What if the deliveries are late? Dealer Welding Assembly Main Distributor Painting Stamping Tier 1 Supplier Tier 2 Supplier ALL STOP !!
  • 37. Perfection Perfection ( Ideal State ) Future State Current State Original State
  • 38. Principles of Lean Thinking - Summary 1. VALUE : Specify value for the product 2. VALUE STREAM : Identify the value stream for every product family 3. FLOW : Make the identified value flow 4. PULL : Make the customer pull the value 5. PERFECTION : Manage towards perfection. To avoid focusing solely on the technics , always repeat the principles !
  • 39. Benefits Parameters Gains Product Design Lead Time 75% Manufacturing Lead time 90% Productivity 100% Defects 80% Inventories 90% Area used 50% Work Accidents 50% New Investments Too little
  • 40. Gains SHORT TERM MIDDLE TERM LONG TERM Reduction in scrap Increase in present product New products and rework sales Utilization of freed up Reduction in overtime Bringing outsourced space production in the plant Increase in delivery Adding extra value to the Reduction in performance products obsolete inventories New sales via better Reduction in service inventories Improvement in Reduction in support cash flow function department Reduction in costs manpower costs
  • 41. Lean Company Model LEAN LEADERSHIP Lean LEAN MANUFACTURING Lean Supply organization SYSTEM and JIT AUTONOMATION Chain Development processes Respect for People and Mutual Trust
  • 42. LEAN MANUFACTURING TECHNIQUES VALUE STREAM MAPPING ONE PIECE FLOW-SMALL LOTS REDUCING INVENTORY KANBAN STANDARDIZED WORK SMED KAIZEN VISUAL CONTROL 5S STANDARD WIP WORK CELL TAKT TIME JIT/PULL TPM “The key to lean is in the thinking and not just in the tools” James WOMACK
  • 43. 5S The 5-S Workplace SORT •Sort needed & unneeded items. Red tag unneeded items. SET IN ORDER •Put things in proper places, arrange and label. SHINE •Clean up the workplace. STANDARDIZE •Standardize the 1st 3 S’s. Document Methods & maintain cleanliness. SUSTAIN •Make 5-S a part of the job. Stick to it! Grade it! Improve it!
  • 45. 5-S Benefits Constraints • Remove unnecessary items. • Daily workforce involvement, • Clear workplace. sustained resource allocation. • Save space. • Minimal investment for storage • Save time for motion. locations and identification. • Regular audits required to • Standardized procedures. sustain. • Organized activities. • Improve safety. • Improve up time. • Team building start point.
  • 46. TAKT TIME • TAKT Time reflects the rate at which customers buy our products; • Takt time is calculated by dividing the real available time by the quantity of goods sold each day: Daily effective minute = TAKT Time Daily customer demand • The actual amount of members needed to build a product at a given TAKT TIME: The sum of the Cycle Time = No. of operators required Divided by the TAKT TIME
  • 47. TAKT Time benefits Having a TAKT time affords the ability to do the following: • Compete in a marketplace where the demand and cost of product is being dictated by the customer. • Pull the product down the line. • Monitor the production rate at intervals that are much smaller than the TAKT time (pro-active approach). When issues are found that stop the series of work steps to be completed on time, they can be dealt with in a concise documented manner. • Build without overtime. • Determine the correct number of production workers required. • Affords targeted costing (both from labour and product). • Control cost more effectively.
  • 48. Value Stream Mapping Current State Value Stream Production Forecast Control Forecast Michigan State Street Steel Weekly Order MRP Daily Order Assembly Weekly Schedule Daily Ship Schedule 2 x Week Daily Stamping S. Weld 1 S. Weld 2 Assembly 1 Assembly 2 Shipping I I I I I I Future State Value Stream Production Lead Time = 23.5 days Value Added Time = 184 secs Forecast Production Control Forecast Check Michigan Steel Daily Order Daily Order State Street Assembly progress and Daily Order stabilise Daily Daily V S Manager Jim Value Stream Plan Product Family Date 03/02/2003 Steering Brackets Weld and Stamping Assembly Cell Shipping Product Value Person Family Stream Measurable Monthly Schedule in Business Objective Goal Charge Objective 1 2 3 4 5 6 7 8 9 Production Pacemaker Lead Time *Continuous flow from = 4.5 days weld to assembly Zero WIP John *Kaizen to 168 secs < 168 s/t Dave Value *Eliminate weld Added Time changeover < 30 sec c/o Sam = 166 secs *Uptime weld #2 100% Mike Improve *Finished goods pull 2 days FG Sue Profitability *Materials handler Pull Schedule James In Steering routes Ask the Brackets Stamping *Stamping Pull 1 day inventory + pull schedule Fred *Stamping changeover batch size Tim key 300/160 pieces c/o < 10 min Supplier questions *Pull coils with daily deliveryr daily delivery < 1.5 days of coils at press Graham
  • 49. Value Stream Mapping % ppm Amplification Quality & Delivery % 40 2000 30 20 Current State 1500 1000 10 5 10 500 0 0 0 F E D C B A F E C A Time reduced % ppm 40 Amplification 2000 Quality & Delivery % from 20 to 5 30 20 Future State 2 1500 1000 10 5 days 10 Flow and Pull between Plants500 0 0 0 F E D C B A Dist. Centre F E C A Steel % ppm Amplification Ideal State Quality & Delivery % 40 2000 10 30 1500 20 1000 5 10 500 Warehouse Cross Dock 0 Cross Dock Value Stream Compression 0 0 Stamping Wipers Assembly Dist. Centre F E D C B A F E C A Steel Time DELTA GAMMA STEEL STAMPING BETA WIPERS ALPHA MOTORS 44d Steps 55m 73 8 F E D C B A Stamping Wipers Assembly Time Dist. Centre DELTA GAMMA Steel STEEL STAMPING BETA WIPERS ALPHA MOTORS 16d Steps 55m Time 39 8 F E D C B A Stamping Wiper reduced Cell Cell Assembly Time EPSILON from 49 to Steps STEEL SUPPLIER PARK ALPHA MOTORS 3d 55m 20 days 30 8 F E D C B A
  • 50. WORK CELLS Original Process Layout Assembly • Group dissimilar machines in manufacturing cell to produce 4 6 7 9 family of parts 5 8 2 10 12 • Work flows in one direction through cell 1 3 11 A B C Raw materials • One worker tends several Cellular Layout Solution Assembly machines 8 10 9 12 • Cycle time adjusted by 11 changing number of workers 4 6 Cell1 Cell 3 Cell 2 7 2 1 3 5 Raw materials A C B
  • 51. WORK CELLS Benefits • Cellular manufacturing achieves the benefits of flow based manufacturing • This simplifies material flow compared to a traditional process layout • Ownership and responsibility for a product rests with the operators of the cell • Shorter Lead Time • Improved Quality - Quicker problem identification • Improved Quality - Less potential rework or scrap • Less Material Handling • Improved Coordination • Reduced Inventory • Departmental conflicts eliminated • Simplified Scheduling • Less Space Required
  • 52. STANDARDIZED WORK There can be no improvement without the basis of standard work. . When normal and abnormal work activities are undifferentiated, waste almost inevitably occurs. Standardized Work, on the other hand, provides an efficient framework in which to perform our jobs. ‘Standardized Work’ is a general phrase which refers to all of the standards (quality, safety, procedural) used in the process of carrying out routine operations. Standard work provides a consistent routine and a basis for improvement. Three elements are important: Takt time/Cycle time, Work sequence and Standard Work in Process (SWIP).
  • 53. Standard Work-in-Process • The MINIMUM amount of Work-In-Process required to allow the operator continued performance of Standard Work. • By standardizing the WIP, we can find a way to reduce it. • Shortened LEAD Time • Quick capture of quality problems • Unnecessary WIP eliminated • Potentially less staffing in cell • Members do more of VA process • Members become multi-functional • The aim is one-piece-flow
  • 54. Reducing Inventory • Reducing Inventories • In traditional manufacturing, inventories are seen as assets • Inventories provide a safety buffer, and result from maximizing machine utilization • JIT views inventory as waste • Inventory is evidence of poor design, poor coordination, and poor operation of a manufacturing system • Inventory Hides Problems
  • 55. Reducing Inventory supply / Inventory level material defects / rework flow set-up downtime labour capacity planning force
  • 56. KANBAN • Kanban card indicates standard quantity of production • Derived from two-bin inventory system • Kanban maintains discipline of pull production • Production kanban authorizes production • Withdrawal kanban authorizes movement of goods • Used when one-piece flow cannot be achieved
  • 57. Kanban • Visual Refill /Replenishment Systems: • A visual replenishment system is one in which tools such • as cards, lights, grids, squares, flags or other visual means • are used to signal the need for re-supply of materials, parts • or supplies. (“KANBAN” = Signal to control WIP)
  • 58. Determining Number of Kanbans average demand during lead time + safety stock No. of Kanbans = container size dL + S N = where C N = number of kanbans or containers d = average demand over some time period L = lead time to replenish an order S = safety stock C = container size
  • 59. Line balancing • Time and labour variables are the basis of line balancing. • They are interrelated and are determining the cost of the producing a product. • If one person is doing a part, the processes are done in sequence. By adding persons, the throughput time will be reduce and all the operations are done in the same time. The throughput time is the longest operation time. • To balance the line, one operator may do 2 faster operation or we may move some steps from the longest operation to other operations.
  • 60. SMED • SMED is a process for dramatically and methodically reducing set-up or changeover times. • Will enable significant reduction of lot sizes. SMED Principles • Setup time is the time between parts when the machine is idle and operator is doing a changeover. • Separate internal setup from external setup • Convert internal setup to external setup • Streamline all aspects of setup • Perform setup activities in parallel or eliminate them.
  • 61. SMED • Set-up delays causes: Searching; Walking; Poor Schedule information; No checklist; Lack of calibration; Missing tools Waiting;
  • 62. SMED Setup Reduction methods: - Parallel setup tasks: ideally, two people can do the job in half the time. - Using quick-attachment devices: one-turn bolt attachment devices, attachments with fixed holders and pins, clamping devices, - Eliminate adjustments: shims with fixed-position holders on machines, accommodating variable-height dies without making adjustments, - Improve external setups: store fixtures, holders, plates, tools near machines, prepare setup kits and carts, improve material handling.
  • 63. TPM • Small lot production with little inventory requires equipment that: – Doesn’t break down – Doesn’t produce defects – Performs well • Breakdown maintenance – Repairs to make failed machine operational • Preventive maintenance – System of periodic inspection & maintenance to keep machines operating • TPM combines preventive maintenance & total quality concepts • TPM seeks to find the root causes of equipment problems, and fix them
  • 64. TPM Preventive Maintenance Elements Maintain normal operating conditions • Maintain equipment requirements • Keep equipment and facilities clean and organized • Monitor equipment daily • Schedule preventive maintenance • Manage maintenance information • Use predictive (condition-based) maintenance Role of Operators – Keep machine clean – Routine lubrication and adjustments – Visual inspection (cracks, oil leaks) – Be aware of unusual sounds, heat, vibration, etc.
  • 65. Benefits Of Lean Production 1. Reduced 7. Greater flexibility inventory 8. Better relations with 2. Improved quality suppliers 3. Lower costs 9. Simplified scheduling 4. Reduced space and control activities requirements 10. Increased capacity 5. Shorter lead time 11. Better use of human 6. Increased resources productivity 12. More product variety
  • 66. Metrics / Expectations (examples) • Item potential improvement • Floor Space 29% • Scrap 46% • QC Rejects 95% • Rework 72% • Work-in-Process 59% • Setup Time 66% • Manpower 32% • Equipment Required 34% • Lead Time 56% • Distance Parts Travel 54% • Cycle Time 18% • Finished Goods Inventory 43% • Down Time 52% (Source: Kaizen Institute)