SlideShare une entreprise Scribd logo
1  sur  14
Production Report
Production
Report
Helps managers
control their
departments
Provides cost
information for
financial
statements
Shows the flow
of units and costs
through work in
process
Becomes the
job cost sheet
in process
costing
Production Report
A computation of
cost per equivalent unit.
A computation of
cost per equivalent unit.
Section 1
Section 2
Section 3
Production Report
A quantity schedule
showing the flow of units
and the computation of
equivalent units.
A quantity schedule
showing the flow of units
and the computation of
equivalent units.
Production Report
 A reconciliation of cost
flows for the period,
including:
Total cost for units
completed and
transferred from the
processing department.
Total cost for partially
completed units
remaining in work in
process.
 A reconciliation of cost
flows for the period,
including:
Total cost for units
completed and
transferred from the
processing department.
Total cost for partially
completed units
remaining in work in
process.
Section 1
Section 2
Section 3
Production Report
Double Diamond Skis uses process costing to
determine unit costs in its Shaping and Milling
Department.
Double Diamond uses the weighted average
cost procedure.
Using the following information for the month of
May, let’s prepare a production report for
Shaping and Milling.
Double Diamond Skis uses process costing to
determine unit costs in its Shaping and Milling
Department.
Double Diamond uses the weighted average
cost procedure.
Using the following information for the month of
May, let’s prepare a production report for
Shaping and Milling.
Production Report Example
Work in process, May 1: 200 units
Materials: 55% complete. $ 9,600
Conversion: 30% complete. 5,575
Production started during May: 5,000 units
Production completed during May: 4,800 units
Costs added to production in May
Materials cost $ 368,600
Conversion cost 350,900
Work in process, May 31: 400 units
Materials 40% complete.
Conversion 25% complete.
Work in process, May 1: 200 units
Materials: 55% complete. $ 9,600
Conversion: 30% complete. 5,575
Production started during May: 5,000 units
Production completed during May: 4,800 units
Costs added to production in May
Materials cost $ 368,600
Conversion cost 350,900
Work in process, May 31: 400 units
Materials 40% complete.
Conversion 25% complete.
Production Report Example
Section 1: Quantity Schedule with Equivalent Units
Production Report Example
Units to be accounted for:
Work in process, May 1 200
Started into production 5,000
Total units 5,200
Equivalent units
Materials Conversion
Units accounted for as follows:
Completed and transferred 4,800 4,800 4,800
Work in process, May 31 400
Production Report Example
Units to be accounted for:
Work in process, May 1 200
Started into production 5,000
Total units 5,200
Equivalent units
Materials Conversion
Units accounted for as follows:
Completed and transferred 4,800 4,800 4,800
Work in process, May 31 400
Materials 40% complete 160
5,200 4,960
Section 1: Quantity Schedule with Equivalent Units
Production Report Example
Units to be accounted for:
Work in process, May 1 200
Started into production 5,000
Total units 5,200
Equivalent units
Materials Conversion
Units accounted for as follows:
Completed and transferred 4,800 4,800 4,800
Work in process, May 31 400
Materials 40% complete 160
Conversion 25% complete 100
5,200 4,960 4,900
Section 1: Quantity Schedule with Equivalent Units
Section 2: Compute cost per equivalent unit
Production Report Example
Total
Cost Materials Conversion
Cost to be accounted for:
Work in process, May 1 15,175$ 9,600$ 5,575$
Costs added in the Shipping
and Milling Department 719,500 368,600 350,900
Total cost 734,675$ 378,200$ 356,475$
Equivalent units 4,960 4,900
Cost per equivalent unit
Total
Cost Materials Conversion
Cost to be accounted for:
Work in process, May 1 15,175$ 9,600$ 5,575$
Costs added in the Shipping
and Milling Department 719,500 368,600 350,900
Total cost 734,675$ 378,200$ 356,475$
Equivalent units 4,960 4,900
Cost per equivalent unit 76.25$
Production Report Example
Section 2: Compute cost per equivalent unit
$378,200 ÷ 4,960 units = $76.25
Total
Cost Materials Conversion
Cost to be accounted for:
Work in process, May 1 15,175$ 9,600$ 5,575$
Costs added in the Shipping
and Milling Department 719,500 368,600 350,900
Total cost 734,675$ 378,200$ 356,475$
Equivalent units 4,960 4,900
Cost per equivalent unit 76.25$ 72.75$
Total cost per equivalent unit = $76.25 + $72.75 = $149.00
Production Report Example
$356,475 ÷ 4,900 units = $72.75
Section 2: Compute cost per equivalent unit
Section 3: Cost Reconciliation
Production Report Example
Total Equivalent Units
Cost Materials Conversion
Cost accounted for as follows:
Transferred out during May 4,800 4,800
Work in process, May 31:
Materials 160
Conversion 100
Total work in process, May 31
Total cost accounted for
Total Equivalent Units
Cost Materials Conversion
Cost accounted for as follows:
Transferred out during May 715,200$ 4,800 4,800
Work in process, May 31:
Materials 160
Conversion 100
Total work in process, May 31
Total cost accounted for
4,800 units @ $149.00
Production Report Example
Section 3: Cost Reconciliation
Total Equivalent Units
Cost Materials Conversion
Cost accounted for as follows:
Transferred out during May 715,200$ 4,800 4,800
Work in process, May 31:
Materials 12,200 160
Conversion 7,275 100
Total work in process, May 31 19,475
Total cost accounted for 734,675$
160 units @ $76.25
Production Report Example
Section 3: Cost Reconciliation
All costs
accounted for
100 units @ $72.75

Contenu connexe

Tendances

Consumables cost reduction project
Consumables cost reduction projectConsumables cost reduction project
Consumables cost reduction project
Lizile Xulu
 
Unit contract tracking in primavera contract management
Unit contract tracking in primavera contract managementUnit contract tracking in primavera contract management
Unit contract tracking in primavera contract management
p6academy
 

Tendances (16)

Costi di Processo: 2.Flussi dei Costi di Processo
Costi di Processo: 2.Flussi dei Costi di ProcessoCosti di Processo: 2.Flussi dei Costi di Processo
Costi di Processo: 2.Flussi dei Costi di Processo
 
Financial statement of Manufacturing Company
Financial statement of Manufacturing CompanyFinancial statement of Manufacturing Company
Financial statement of Manufacturing Company
 
Power switch case
Power switch casePower switch case
Power switch case
 
Exam 1 review
Exam 1 reviewExam 1 review
Exam 1 review
 
SAP-CO-PC - Product Cost Cycle
SAP-CO-PC - Product Cost CycleSAP-CO-PC - Product Cost Cycle
SAP-CO-PC - Product Cost Cycle
 
Cost sheet
Cost sheetCost sheet
Cost sheet
 
Job order costing
Job order costingJob order costing
Job order costing
 
Unit 2 of Cost Accounting
Unit 2 of Cost AccountingUnit 2 of Cost Accounting
Unit 2 of Cost Accounting
 
Make to stock po
Make to stock poMake to stock po
Make to stock po
 
Consumables cost reduction project
Consumables cost reduction projectConsumables cost reduction project
Consumables cost reduction project
 
Presentation on calculation_of_price_escalation
Presentation on calculation_of_price_escalationPresentation on calculation_of_price_escalation
Presentation on calculation_of_price_escalation
 
Costsheet final
Costsheet finalCostsheet final
Costsheet final
 
Unit contract tracking in primavera contract management
Unit contract tracking in primavera contract managementUnit contract tracking in primavera contract management
Unit contract tracking in primavera contract management
 
AC 330 Success Begins / snaptutorial.com
AC 330 Success Begins / snaptutorial.comAC 330 Success Begins / snaptutorial.com
AC 330 Success Begins / snaptutorial.com
 
Electrolux Consolidated Results 2017 - Presentation
Electrolux Consolidated Results 2017 - PresentationElectrolux Consolidated Results 2017 - Presentation
Electrolux Consolidated Results 2017 - Presentation
 
ACCT 102 Ch15
ACCT 102 Ch15ACCT 102 Ch15
ACCT 102 Ch15
 

Similaire à Costi di Processo: 4.Report della Produzione

ACG 2071 Managerial Accounting Process Costing Systems .docx
ACG 2071 Managerial Accounting Process Costing Systems .docxACG 2071 Managerial Accounting Process Costing Systems .docx
ACG 2071 Managerial Accounting Process Costing Systems .docx
bobbywlane695641
 
Hilton Products manufactures one product in two departments on a con.docx
Hilton Products manufactures one product in two departments on a con.docxHilton Products manufactures one product in two departments on a con.docx
Hilton Products manufactures one product in two departments on a con.docx
fideladallimore
 
Process cost systems
Process cost systemsProcess cost systems
Process cost systems
Khalid Aziz
 
Jiambalvo text book solutions (2)
Jiambalvo text book solutions (2)Jiambalvo text book solutions (2)
Jiambalvo text book solutions (2)
Mvs Krishna
 

Similaire à Costi di Processo: 4.Report della Produzione (19)

Product costing
Product costingProduct costing
Product costing
 
ACN3101 TOPIC 9 211224.ppt
ACN3101 TOPIC 9 211224.pptACN3101 TOPIC 9 211224.ppt
ACN3101 TOPIC 9 211224.ppt
 
Process Costing
Process CostingProcess Costing
Process Costing
 
ACG 2071 Managerial Accounting Process Costing Systems .docx
ACG 2071 Managerial Accounting Process Costing Systems .docxACG 2071 Managerial Accounting Process Costing Systems .docx
ACG 2071 Managerial Accounting Process Costing Systems .docx
 
yitu
yituyitu
yitu
 
Hilton Products manufactures one product in two departments on a con.docx
Hilton Products manufactures one product in two departments on a con.docxHilton Products manufactures one product in two departments on a con.docx
Hilton Products manufactures one product in two departments on a con.docx
 
| Managerial Accounting | Chapter 4 | Systems Design: Process Costing | Intro...
| Managerial Accounting | Chapter 4 | Systems Design: Process Costing | Intro...| Managerial Accounting | Chapter 4 | Systems Design: Process Costing | Intro...
| Managerial Accounting | Chapter 4 | Systems Design: Process Costing | Intro...
 
Cost accounting
Cost accountingCost accounting
Cost accounting
 
Bus 7800 week 6 absorption costing
Bus 7800 week 6 absorption costingBus 7800 week 6 absorption costing
Bus 7800 week 6 absorption costing
 
Acc mgt noreen04 systems design process costing
Acc mgt noreen04 systems design process costingAcc mgt noreen04 systems design process costing
Acc mgt noreen04 systems design process costing
 
5. process cost systems
5. process cost systems5. process cost systems
5. process cost systems
 
Process Costing- Chapter Four
Process Costing- Chapter FourProcess Costing- Chapter Four
Process Costing- Chapter Four
 
Akuntansi Manajemen Edisi 8 oleh Hansen & Mowen Bab 6
Akuntansi Manajemen Edisi 8 oleh Hansen & Mowen Bab 6Akuntansi Manajemen Edisi 8 oleh Hansen & Mowen Bab 6
Akuntansi Manajemen Edisi 8 oleh Hansen & Mowen Bab 6
 
Process cost systems
Process cost systemsProcess cost systems
Process cost systems
 
Bsr3 a unit 1 2016
Bsr3 a unit 1   2016Bsr3 a unit 1   2016
Bsr3 a unit 1 2016
 
Jiambalvo text book solutions (2)
Jiambalvo text book solutions (2)Jiambalvo text book solutions (2)
Jiambalvo text book solutions (2)
 
ACCT 505 Education Counseling--acct505.com
ACCT 505 Education Counseling--acct505.com ACCT 505 Education Counseling--acct505.com
ACCT 505 Education Counseling--acct505.com
 
ACCT 505 Redefined Education--acct505.com
ACCT 505 Redefined Education--acct505.comACCT 505 Redefined Education--acct505.com
ACCT 505 Redefined Education--acct505.com
 
ACCT 505 Achievement Education--acct505.com
ACCT 505 Achievement Education--acct505.comACCT 505 Achievement Education--acct505.com
ACCT 505 Achievement Education--acct505.com
 

Plus de Manager.it

Plus de Manager.it (20)

Gestione del Tempo 4. I sei Consigli di valutazione del Tempo
Gestione del Tempo 4. I sei Consigli di valutazione del Tempo Gestione del Tempo 4. I sei Consigli di valutazione del Tempo
Gestione del Tempo 4. I sei Consigli di valutazione del Tempo
 
Gestione del Tempo 3. I Quadranti del Tempo per Gestire le attività
Gestione del Tempo 3. I Quadranti del Tempo per Gestire le attivitàGestione del Tempo 3. I Quadranti del Tempo per Gestire le attività
Gestione del Tempo 3. I Quadranti del Tempo per Gestire le attività
 
Gestione del Tempo 1. I sei passi della gestione del tempo
Gestione del Tempo 1. I sei passi della gestione del tempoGestione del Tempo 1. I sei passi della gestione del tempo
Gestione del Tempo 1. I sei passi della gestione del tempo
 
Esecuzione di Strategie 5. il cuore
Esecuzione di Strategie 5.  il cuoreEsecuzione di Strategie 5.  il cuore
Esecuzione di Strategie 5. il cuore
 
Esecuzione di Strategie 4. L' Esecuzione non ammette deleghe alla leadership
Esecuzione di Strategie 4.  L' Esecuzione non ammette deleghe alla leadershipEsecuzione di Strategie 4.  L' Esecuzione non ammette deleghe alla leadership
Esecuzione di Strategie 4. L' Esecuzione non ammette deleghe alla leadership
 
Esecuzione di Strategie 1. abilità di dare seguito operativo alla strategia
Esecuzione di Strategie 1. abilità di dare seguito operativo alla strategiaEsecuzione di Strategie 1. abilità di dare seguito operativo alla strategia
Esecuzione di Strategie 1. abilità di dare seguito operativo alla strategia
 
Ipercompetizione 5. Capacità di creare delle Discontinuità
Ipercompetizione 5. Capacità di creare delle DiscontinuitàIpercompetizione 5. Capacità di creare delle Discontinuità
Ipercompetizione 5. Capacità di creare delle Discontinuità
 
Ipercompetizione 4. Predizione strategica
Ipercompetizione 4. Predizione strategicaIpercompetizione 4. Predizione strategica
Ipercompetizione 4. Predizione strategica
 
Ipercompetizione 2. Strategia della Discontinuità
Ipercompetizione 2. Strategia della DiscontinuitàIpercompetizione 2. Strategia della Discontinuità
Ipercompetizione 2. Strategia della Discontinuità
 
Ipercompetizione 1. Cos'è e cosa provoca l'Ipercompetizione
Ipercompetizione 1. Cos'è e cosa provoca l'IpercompetizioneIpercompetizione 1. Cos'è e cosa provoca l'Ipercompetizione
Ipercompetizione 1. Cos'è e cosa provoca l'Ipercompetizione
 
Sviluppare una Hr Scorecard
Sviluppare una Hr ScorecardSviluppare una Hr Scorecard
Sviluppare una Hr Scorecard
 
HR Management 5. Gestione delle Carriere
HR Management  5. Gestione delle Carriere HR Management  5. Gestione delle Carriere
HR Management 5. Gestione delle Carriere
 
HR Management 4. Gestione delle Performance
HR Management  4. Gestione delle PerformanceHR Management  4. Gestione delle Performance
HR Management 4. Gestione delle Performance
 
HR Management 3. Formazione e Sviluppo
HR Management  3. Formazione e SviluppoHR Management  3. Formazione e Sviluppo
HR Management 3. Formazione e Sviluppo
 
HR Management 2. Metodi di Selezione
HR Management  2. Metodi di SelezioneHR Management  2. Metodi di Selezione
HR Management 2. Metodi di Selezione
 
HR Management 1. I principi dell'HR management
HR Management  1. I principi dell'HR managementHR Management  1. I principi dell'HR management
HR Management 1. I principi dell'HR management
 
Gestione delle Competenze 5. Formazione e Sviluppo
Gestione delle Competenze 5. Formazione e SviluppoGestione delle Competenze 5. Formazione e Sviluppo
Gestione delle Competenze 5. Formazione e Sviluppo
 
Gestione delle Competenze 4. Pianificazione delle Carriere
Gestione delle Competenze 4. Pianificazione delle CarriereGestione delle Competenze 4. Pianificazione delle Carriere
Gestione delle Competenze 4. Pianificazione delle Carriere
 
Gestione delle Competenze 3. Intervista nelle Selezioni
Gestione delle Competenze 3. Intervista nelle Selezioni Gestione delle Competenze 3. Intervista nelle Selezioni
Gestione delle Competenze 3. Intervista nelle Selezioni
 
Gestione delle Competenze 2. Sviluppare il modello di competenza
Gestione delle Competenze 2. Sviluppare il modello di competenzaGestione delle Competenze 2. Sviluppare il modello di competenza
Gestione delle Competenze 2. Sviluppare il modello di competenza
 

Dernier

VIP Independent Call Girls in Taloja 🌹 9920725232 ( Call Me ) Mumbai Escorts ...
VIP Independent Call Girls in Taloja 🌹 9920725232 ( Call Me ) Mumbai Escorts ...VIP Independent Call Girls in Taloja 🌹 9920725232 ( Call Me ) Mumbai Escorts ...
VIP Independent Call Girls in Taloja 🌹 9920725232 ( Call Me ) Mumbai Escorts ...
dipikadinghjn ( Why You Choose Us? ) Escorts
 
VIP Independent Call Girls in Mumbai 🌹 9920725232 ( Call Me ) Mumbai Escorts ...
VIP Independent Call Girls in Mumbai 🌹 9920725232 ( Call Me ) Mumbai Escorts ...VIP Independent Call Girls in Mumbai 🌹 9920725232 ( Call Me ) Mumbai Escorts ...
VIP Independent Call Girls in Mumbai 🌹 9920725232 ( Call Me ) Mumbai Escorts ...
dipikadinghjn ( Why You Choose Us? ) Escorts
 
Call Girls in New Ashok Nagar, (delhi) call me [9953056974] escort service 24X7
Call Girls in New Ashok Nagar, (delhi) call me [9953056974] escort service 24X7Call Girls in New Ashok Nagar, (delhi) call me [9953056974] escort service 24X7
Call Girls in New Ashok Nagar, (delhi) call me [9953056974] escort service 24X7
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
➥🔝 7737669865 🔝▻ Malda Call-girls in Women Seeking Men 🔝Malda🔝 Escorts Ser...
➥🔝 7737669865 🔝▻ Malda Call-girls in Women Seeking Men  🔝Malda🔝   Escorts Ser...➥🔝 7737669865 🔝▻ Malda Call-girls in Women Seeking Men  🔝Malda🔝   Escorts Ser...
➥🔝 7737669865 🔝▻ Malda Call-girls in Women Seeking Men 🔝Malda🔝 Escorts Ser...
amitlee9823
 
CBD Belapur Expensive Housewife Call Girls Number-📞📞9833754194 No 1 Vipp HIgh...
CBD Belapur Expensive Housewife Call Girls Number-📞📞9833754194 No 1 Vipp HIgh...CBD Belapur Expensive Housewife Call Girls Number-📞📞9833754194 No 1 Vipp HIgh...
CBD Belapur Expensive Housewife Call Girls Number-📞📞9833754194 No 1 Vipp HIgh...
priyasharma62062
 
VIP Independent Call Girls in Bandra West 🌹 9920725232 ( Call Me ) Mumbai Esc...
VIP Independent Call Girls in Bandra West 🌹 9920725232 ( Call Me ) Mumbai Esc...VIP Independent Call Girls in Bandra West 🌹 9920725232 ( Call Me ) Mumbai Esc...
VIP Independent Call Girls in Bandra West 🌹 9920725232 ( Call Me ) Mumbai Esc...
dipikadinghjn ( Why You Choose Us? ) Escorts
 
VIP Call Girl in Mumbai 💧 9920725232 ( Call Me ) Get A New Crush Everyday Wit...
VIP Call Girl in Mumbai 💧 9920725232 ( Call Me ) Get A New Crush Everyday Wit...VIP Call Girl in Mumbai 💧 9920725232 ( Call Me ) Get A New Crush Everyday Wit...
VIP Call Girl in Mumbai 💧 9920725232 ( Call Me ) Get A New Crush Everyday Wit...
dipikadinghjn ( Why You Choose Us? ) Escorts
 
VIP Independent Call Girls in Andheri 🌹 9920725232 ( Call Me ) Mumbai Escorts...
VIP Independent Call Girls in Andheri 🌹 9920725232 ( Call Me ) Mumbai Escorts...VIP Independent Call Girls in Andheri 🌹 9920725232 ( Call Me ) Mumbai Escorts...
VIP Independent Call Girls in Andheri 🌹 9920725232 ( Call Me ) Mumbai Escorts...
dipikadinghjn ( Why You Choose Us? ) Escorts
 
( Jasmin ) Top VIP Escorts Service Dindigul 💧 7737669865 💧 by Dindigul Call G...
( Jasmin ) Top VIP Escorts Service Dindigul 💧 7737669865 💧 by Dindigul Call G...( Jasmin ) Top VIP Escorts Service Dindigul 💧 7737669865 💧 by Dindigul Call G...
( Jasmin ) Top VIP Escorts Service Dindigul 💧 7737669865 💧 by Dindigul Call G...
dipikadinghjn ( Why You Choose Us? ) Escorts
 
Call Girls Banaswadi Just Call 👗 7737669865 👗 Top Class Call Girl Service Ban...
Call Girls Banaswadi Just Call 👗 7737669865 👗 Top Class Call Girl Service Ban...Call Girls Banaswadi Just Call 👗 7737669865 👗 Top Class Call Girl Service Ban...
Call Girls Banaswadi Just Call 👗 7737669865 👗 Top Class Call Girl Service Ban...
amitlee9823
 

Dernier (20)

Vip Call US 📞 7738631006 ✅Call Girls In Sakinaka ( Mumbai )
Vip Call US 📞 7738631006 ✅Call Girls In Sakinaka ( Mumbai )Vip Call US 📞 7738631006 ✅Call Girls In Sakinaka ( Mumbai )
Vip Call US 📞 7738631006 ✅Call Girls In Sakinaka ( Mumbai )
 
Technology industry / Finnish economic outlook
Technology industry / Finnish economic outlookTechnology industry / Finnish economic outlook
Technology industry / Finnish economic outlook
 
VIP Independent Call Girls in Taloja 🌹 9920725232 ( Call Me ) Mumbai Escorts ...
VIP Independent Call Girls in Taloja 🌹 9920725232 ( Call Me ) Mumbai Escorts ...VIP Independent Call Girls in Taloja 🌹 9920725232 ( Call Me ) Mumbai Escorts ...
VIP Independent Call Girls in Taloja 🌹 9920725232 ( Call Me ) Mumbai Escorts ...
 
VIP Independent Call Girls in Mumbai 🌹 9920725232 ( Call Me ) Mumbai Escorts ...
VIP Independent Call Girls in Mumbai 🌹 9920725232 ( Call Me ) Mumbai Escorts ...VIP Independent Call Girls in Mumbai 🌹 9920725232 ( Call Me ) Mumbai Escorts ...
VIP Independent Call Girls in Mumbai 🌹 9920725232 ( Call Me ) Mumbai Escorts ...
 
Kopar Khairane Russian Call Girls Number-9833754194-Navi Mumbai Fantastic Unl...
Kopar Khairane Russian Call Girls Number-9833754194-Navi Mumbai Fantastic Unl...Kopar Khairane Russian Call Girls Number-9833754194-Navi Mumbai Fantastic Unl...
Kopar Khairane Russian Call Girls Number-9833754194-Navi Mumbai Fantastic Unl...
 
Call Girls in New Ashok Nagar, (delhi) call me [9953056974] escort service 24X7
Call Girls in New Ashok Nagar, (delhi) call me [9953056974] escort service 24X7Call Girls in New Ashok Nagar, (delhi) call me [9953056974] escort service 24X7
Call Girls in New Ashok Nagar, (delhi) call me [9953056974] escort service 24X7
 
Kharghar Blowjob Housewife Call Girls NUmber-9833754194-CBD Belapur Internati...
Kharghar Blowjob Housewife Call Girls NUmber-9833754194-CBD Belapur Internati...Kharghar Blowjob Housewife Call Girls NUmber-9833754194-CBD Belapur Internati...
Kharghar Blowjob Housewife Call Girls NUmber-9833754194-CBD Belapur Internati...
 
➥🔝 7737669865 🔝▻ Malda Call-girls in Women Seeking Men 🔝Malda🔝 Escorts Ser...
➥🔝 7737669865 🔝▻ Malda Call-girls in Women Seeking Men  🔝Malda🔝   Escorts Ser...➥🔝 7737669865 🔝▻ Malda Call-girls in Women Seeking Men  🔝Malda🔝   Escorts Ser...
➥🔝 7737669865 🔝▻ Malda Call-girls in Women Seeking Men 🔝Malda🔝 Escorts Ser...
 
CBD Belapur Expensive Housewife Call Girls Number-📞📞9833754194 No 1 Vipp HIgh...
CBD Belapur Expensive Housewife Call Girls Number-📞📞9833754194 No 1 Vipp HIgh...CBD Belapur Expensive Housewife Call Girls Number-📞📞9833754194 No 1 Vipp HIgh...
CBD Belapur Expensive Housewife Call Girls Number-📞📞9833754194 No 1 Vipp HIgh...
 
Airport Road Best Experience Call Girls Number-📞📞9833754194 Santacruz MOst Es...
Airport Road Best Experience Call Girls Number-📞📞9833754194 Santacruz MOst Es...Airport Road Best Experience Call Girls Number-📞📞9833754194 Santacruz MOst Es...
Airport Road Best Experience Call Girls Number-📞📞9833754194 Santacruz MOst Es...
 
8377087607, Door Step Call Girls In Kalkaji (Locanto) 24/7 Available
8377087607, Door Step Call Girls In Kalkaji (Locanto) 24/7 Available8377087607, Door Step Call Girls In Kalkaji (Locanto) 24/7 Available
8377087607, Door Step Call Girls In Kalkaji (Locanto) 24/7 Available
 
VIP Independent Call Girls in Bandra West 🌹 9920725232 ( Call Me ) Mumbai Esc...
VIP Independent Call Girls in Bandra West 🌹 9920725232 ( Call Me ) Mumbai Esc...VIP Independent Call Girls in Bandra West 🌹 9920725232 ( Call Me ) Mumbai Esc...
VIP Independent Call Girls in Bandra West 🌹 9920725232 ( Call Me ) Mumbai Esc...
 
VIP Call Girl in Mumbai 💧 9920725232 ( Call Me ) Get A New Crush Everyday Wit...
VIP Call Girl in Mumbai 💧 9920725232 ( Call Me ) Get A New Crush Everyday Wit...VIP Call Girl in Mumbai 💧 9920725232 ( Call Me ) Get A New Crush Everyday Wit...
VIP Call Girl in Mumbai 💧 9920725232 ( Call Me ) Get A New Crush Everyday Wit...
 
(Sexy Sheela) Call Girl Mumbai Call Now 👉9920725232👈 Mumbai Escorts 24x7
(Sexy Sheela) Call Girl Mumbai Call Now 👉9920725232👈 Mumbai Escorts 24x7(Sexy Sheela) Call Girl Mumbai Call Now 👉9920725232👈 Mumbai Escorts 24x7
(Sexy Sheela) Call Girl Mumbai Call Now 👉9920725232👈 Mumbai Escorts 24x7
 
VIP Independent Call Girls in Andheri 🌹 9920725232 ( Call Me ) Mumbai Escorts...
VIP Independent Call Girls in Andheri 🌹 9920725232 ( Call Me ) Mumbai Escorts...VIP Independent Call Girls in Andheri 🌹 9920725232 ( Call Me ) Mumbai Escorts...
VIP Independent Call Girls in Andheri 🌹 9920725232 ( Call Me ) Mumbai Escorts...
 
7 tips trading Deriv Accumulator Options
7 tips trading Deriv Accumulator Options7 tips trading Deriv Accumulator Options
7 tips trading Deriv Accumulator Options
 
( Jasmin ) Top VIP Escorts Service Dindigul 💧 7737669865 💧 by Dindigul Call G...
( Jasmin ) Top VIP Escorts Service Dindigul 💧 7737669865 💧 by Dindigul Call G...( Jasmin ) Top VIP Escorts Service Dindigul 💧 7737669865 💧 by Dindigul Call G...
( Jasmin ) Top VIP Escorts Service Dindigul 💧 7737669865 💧 by Dindigul Call G...
 
Webinar on E-Invoicing for Fintech Belgium
Webinar on E-Invoicing for Fintech BelgiumWebinar on E-Invoicing for Fintech Belgium
Webinar on E-Invoicing for Fintech Belgium
 
Call Girls Banaswadi Just Call 👗 7737669865 👗 Top Class Call Girl Service Ban...
Call Girls Banaswadi Just Call 👗 7737669865 👗 Top Class Call Girl Service Ban...Call Girls Banaswadi Just Call 👗 7737669865 👗 Top Class Call Girl Service Ban...
Call Girls Banaswadi Just Call 👗 7737669865 👗 Top Class Call Girl Service Ban...
 
Diva-Thane European Call Girls Number-9833754194-Diva Busty Professional Call...
Diva-Thane European Call Girls Number-9833754194-Diva Busty Professional Call...Diva-Thane European Call Girls Number-9833754194-Diva Busty Professional Call...
Diva-Thane European Call Girls Number-9833754194-Diva Busty Professional Call...
 

Costi di Processo: 4.Report della Produzione

  • 1. Production Report Production Report Helps managers control their departments Provides cost information for financial statements Shows the flow of units and costs through work in process Becomes the job cost sheet in process costing
  • 2. Production Report A computation of cost per equivalent unit. A computation of cost per equivalent unit. Section 1 Section 2 Section 3 Production Report A quantity schedule showing the flow of units and the computation of equivalent units. A quantity schedule showing the flow of units and the computation of equivalent units.
  • 3. Production Report  A reconciliation of cost flows for the period, including: Total cost for units completed and transferred from the processing department. Total cost for partially completed units remaining in work in process.  A reconciliation of cost flows for the period, including: Total cost for units completed and transferred from the processing department. Total cost for partially completed units remaining in work in process. Section 1 Section 2 Section 3 Production Report
  • 4. Double Diamond Skis uses process costing to determine unit costs in its Shaping and Milling Department. Double Diamond uses the weighted average cost procedure. Using the following information for the month of May, let’s prepare a production report for Shaping and Milling. Double Diamond Skis uses process costing to determine unit costs in its Shaping and Milling Department. Double Diamond uses the weighted average cost procedure. Using the following information for the month of May, let’s prepare a production report for Shaping and Milling. Production Report Example
  • 5. Work in process, May 1: 200 units Materials: 55% complete. $ 9,600 Conversion: 30% complete. 5,575 Production started during May: 5,000 units Production completed during May: 4,800 units Costs added to production in May Materials cost $ 368,600 Conversion cost 350,900 Work in process, May 31: 400 units Materials 40% complete. Conversion 25% complete. Work in process, May 1: 200 units Materials: 55% complete. $ 9,600 Conversion: 30% complete. 5,575 Production started during May: 5,000 units Production completed during May: 4,800 units Costs added to production in May Materials cost $ 368,600 Conversion cost 350,900 Work in process, May 31: 400 units Materials 40% complete. Conversion 25% complete. Production Report Example
  • 6. Section 1: Quantity Schedule with Equivalent Units Production Report Example Units to be accounted for: Work in process, May 1 200 Started into production 5,000 Total units 5,200 Equivalent units Materials Conversion Units accounted for as follows: Completed and transferred 4,800 4,800 4,800 Work in process, May 31 400
  • 7. Production Report Example Units to be accounted for: Work in process, May 1 200 Started into production 5,000 Total units 5,200 Equivalent units Materials Conversion Units accounted for as follows: Completed and transferred 4,800 4,800 4,800 Work in process, May 31 400 Materials 40% complete 160 5,200 4,960 Section 1: Quantity Schedule with Equivalent Units
  • 8. Production Report Example Units to be accounted for: Work in process, May 1 200 Started into production 5,000 Total units 5,200 Equivalent units Materials Conversion Units accounted for as follows: Completed and transferred 4,800 4,800 4,800 Work in process, May 31 400 Materials 40% complete 160 Conversion 25% complete 100 5,200 4,960 4,900 Section 1: Quantity Schedule with Equivalent Units
  • 9. Section 2: Compute cost per equivalent unit Production Report Example Total Cost Materials Conversion Cost to be accounted for: Work in process, May 1 15,175$ 9,600$ 5,575$ Costs added in the Shipping and Milling Department 719,500 368,600 350,900 Total cost 734,675$ 378,200$ 356,475$ Equivalent units 4,960 4,900 Cost per equivalent unit
  • 10. Total Cost Materials Conversion Cost to be accounted for: Work in process, May 1 15,175$ 9,600$ 5,575$ Costs added in the Shipping and Milling Department 719,500 368,600 350,900 Total cost 734,675$ 378,200$ 356,475$ Equivalent units 4,960 4,900 Cost per equivalent unit 76.25$ Production Report Example Section 2: Compute cost per equivalent unit $378,200 ÷ 4,960 units = $76.25
  • 11. Total Cost Materials Conversion Cost to be accounted for: Work in process, May 1 15,175$ 9,600$ 5,575$ Costs added in the Shipping and Milling Department 719,500 368,600 350,900 Total cost 734,675$ 378,200$ 356,475$ Equivalent units 4,960 4,900 Cost per equivalent unit 76.25$ 72.75$ Total cost per equivalent unit = $76.25 + $72.75 = $149.00 Production Report Example $356,475 ÷ 4,900 units = $72.75 Section 2: Compute cost per equivalent unit
  • 12. Section 3: Cost Reconciliation Production Report Example Total Equivalent Units Cost Materials Conversion Cost accounted for as follows: Transferred out during May 4,800 4,800 Work in process, May 31: Materials 160 Conversion 100 Total work in process, May 31 Total cost accounted for
  • 13. Total Equivalent Units Cost Materials Conversion Cost accounted for as follows: Transferred out during May 715,200$ 4,800 4,800 Work in process, May 31: Materials 160 Conversion 100 Total work in process, May 31 Total cost accounted for 4,800 units @ $149.00 Production Report Example Section 3: Cost Reconciliation
  • 14. Total Equivalent Units Cost Materials Conversion Cost accounted for as follows: Transferred out during May 715,200$ 4,800 4,800 Work in process, May 31: Materials 12,200 160 Conversion 7,275 100 Total work in process, May 31 19,475 Total cost accounted for 734,675$ 160 units @ $76.25 Production Report Example Section 3: Cost Reconciliation All costs accounted for 100 units @ $72.75