1. INTRODUCTION
2. TRANSFORMER CORE BUILDING
3. WINDING
4. COILASSEMBLY
5. POWER ASSEMBLY
6. CASE FITTING
7. INSULATION SHOP
8. TESTING
9. DISPATCH
10. REFERENCES
CONTENTS
BHEL, Bhopal established in 1964, is an integrated power plant
equipment manufacturer and one of the largest engineering and
manufacturing companies in India in terms of turnover.
It has 15 manufacturing divisions, two repair units, four regional
offices, eight service centers and 15 regional centers.
It has been acquiring and adapting some of the best technologies
from leading companies in the world including General Electric
Company, Alstom SA, Siemens AG and Mitsubishi Heavy
Industries Ltd.
INTRODUCTION TO BHEL BHOPAL
a) Block 1A :- Fabrication
b) Block 1B :- Hydro Turbine, Tanks
c) Block 2 :- Electrical Machine
d) Block 3 :- Transformer Manufacturing, Capacitor & Bushing
e) Block 4 :- Switchgear, Control gear
f) Block 5 :- Foundry Division
g) Block 6 :- Steam Turbine
h) Block 7 :- Factory Store
i) Block 8 :- Coils & Insulation
j) Block 9 :- Traction motor block
k) Block 10 :- Lamination Cutting
BLOCK DISCRIPTION
POWER TRANSFORMER CONSTRUCTION
Fig: Block Diagram representation of Transformer Construction
TRANSFORMER CORE BUILDING
Following steps are involved in power transformer core
construction:
1) Cutting & punching of CRGO
2) Stacking of CRGO
3) Fiber Glass End Frame insulation
4) Insulated Bolting of End Frame.
Fig: Cutting & punching of CRGO Fig: Stacking of CRGO
Fig: End Frame insulation & End Frame bolted Fig: Erecting of Core
WINDING
TYPES OF WINDING MACHINES
Winding Machines are of two types:
1) Horizontal Winding machines
2) Vertical Winding machines
Fig: Horizontal Winding machines Fig: Vertical Winding machines
TYPES OF WINDINGS:
1) Spiral Winding (L.V.L.C.)
2) Helical Winding (L.V.H.C.)
3) Disc Winding
4) Interleaved Disc Winding
Fig: Helical Winding
Fig: Interleaved Disc Winding
Fig: Disc Winding
The various types of conductors used in coil winding are
1) CTC (Continuously Transposed Conductor)
2) PICC (Paper Insulated Copper Conductor)
3) BPICC (Bunch Paper Insulated Copper Conductor)
TYPES OF WINDING CONDUCTORS
Fig: CTCFig: PICC Fig: BPICC
COILASSEMBLEY
Coil Sequence
L.V. Coil is placed adjacent to the CRGO steel core and
H.V coil outside, in order to minimize the amount of
insulation required.
While assembling the different coils (i.e. Tap coil, L.V. Coil
& H.V. Coil) tap coil can be placed in either of three positions
depending upon the length of tap coil i.e. if tap coil is small it
is placed inside of LV coil, if it is medium then between LV &
HV coil, and if large then outside of HV coil.
The coils are specified in the design may be of following types
on the basis of operating voltage:
1) L.V. Coil Winding
2) H.V. Coil Winding
3) Tap Coil Winding
Fig: Vertical Winding (HV)Fig: Horizontal Winding (LV & Tap)
Fig: Coil Assembly
Fig: Oven Baking
Fig: Hydraulic Press
POWER ASSEMBLEY
 Core - Coil Assembly 1
a) Unlatching of core
b) Fitting of bottom insulation
c) Core coil assembly as per drawing/electrical specification
 Core - Coil Assembly 2
a) Fitting of top insulation
b) Relacing of core
 Terminal Gear Mounting 1
a) Crimping & Brazzing
b) Insulation Wrapping
c) OLTC Connection
d) Electrical Circuit manufacturing
 Terminal Gear Mounting 2
a) Vapour Phase Drying
b) Servicing.
Steps involved in Power Assembly are :
Fig: Unlatching of core
Fig: Core coil assembly as per drawing
Fig: Relacing of core
CORE COILASSEMBLY 1 & 2
Fig: Electrical Circuit manufacturing
Fig:Vapour Phase Drying of core & winding alone
Fig: Vapour Phase Drying of Transformer
CASE FITTING
1) CT connections & Feed positions
2) Conservator
3) Bushing Connections
4) Magnetic Oil Gauge
5) Oil Temperature Indicator
6) Buchholz Relay
7) Radiator
8) Breather
9) Control panel
Case Fitting involves connecting accessories of transformer, these
accessories include following :
1. Transformer tank
2. High voltage bushing
3. Low voltage bushing
4. Cooling fins radiator
5. Cooling fans
6. Conservator tank
7. System ground terminal
8. Drain valve
9. Breather
10. Oil temperature gauge
11. Current xmer terminals
12. Control panel
Fig: Parts of Transformer
INSULATION MATERIALS
Fig: Press Board Material
Fig: Udel Wood
Fig: Bushing Insulation
Fig: Fiber Glass Material Fig: Oil Insulation
Fig: Bakellite
Items made up of PBM:-
1) Former Base Cylinder
2) DOF Separator
3) T-Block
4) Static Ring
Items made up of Udel Wood:-
1) T-Spacers
2) Full ring segment
3) Half ring segment
4) Shunts
Fig: Items made up of Udel Wood
Fig: Items made up of PBM
1) TESTING TO THE BRITISH STANDARDS
2) ROUTINE TEST FOR TRANSFORMER AS
PER IS 2026
TYPES OF TESTS
 Routine tests:
1) Voltage ratio and polarity.
2) Winding resistance.
3) Short-circuit impedance and load loss.
4) Dielectric test.
5) No-load losses and current.
6) On-load tap-changer.
 Type tests:
1) Temperature rise test.
2) Lightning impulse test.
TESTING TO THE BRITISH STANDARDS
1) Dimensional Check
2) Winding Resistance Test
3) Short Circuit Test
4) Open Circuit Test
5) Induced Over Voltage Test
6) Separate Source Voltage
7) Insulation Resistance Test
8) B.D.V of Oil
9) Turns Ratio Test
ROUTINE TEST FOR TRANSFORMER AS PER
IS 2026
DISPATCH
After successful completion of testing, transformer is handed over
to dispatch sections. At this stage after checking oil leakage,
dismantling of all bushings, turrets etc. and covered with the
blanking plates and the tank is fitted with nitrogen gas and then
the transformer is dispatched to the concerned site.
There are generally three separate shipments made:
1) The main tank c/w core and coils,
2) The accessories that have been removed and packaged, and
3) The insulating oil.
Fig: Dispatch of power transformer
[1] Dr. P. S. Bhimbra, “Electrical Machines”, Khanna
Publications, New Delhi.
[2] D. P. Kothari and I. J. Nagrath, “Electrical Machines” , 3rd
Edition, TMH, New Delhi.
[3] BHEL , “Transformers” 2nd Edition ,Tata Mcgraw Hill
Education Private Limited.
REFERENCES
THANK YOU

Contenu connexe

Tendances

400kv sub-station-final-ppt-by-mohit
400kv sub-station-final-ppt-by-mohit400kv sub-station-final-ppt-by-mohit
400kv sub-station-final-ppt-by-mohit
Mohit Awasthi
 

Tendances (20)

Tan delta test for power transformers
Tan delta test for power transformersTan delta test for power transformers
Tan delta test for power transformers
 
132 33kv substation documentation
132 33kv substation documentation132 33kv substation documentation
132 33kv substation documentation
 
Testing of Transformers.
Testing of Transformers.Testing of Transformers.
Testing of Transformers.
 
Capacitive voltage transformer (1)
Capacitive voltage transformer (1)Capacitive voltage transformer (1)
Capacitive voltage transformer (1)
 
Areva "Manufacturing of transformer, uses & it’s accessories"
Areva "Manufacturing of transformer, uses & it’s accessories"Areva "Manufacturing of transformer, uses & it’s accessories"
Areva "Manufacturing of transformer, uses & it’s accessories"
 
Power Transformer Parts And Functions
Power Transformer Parts And FunctionsPower Transformer Parts And Functions
Power Transformer Parts And Functions
 
Substation Training presentation
Substation Training presentationSubstation Training presentation
Substation Training presentation
 
Power transformer
Power transformerPower transformer
Power transformer
 
400kv sub-station-final-ppt-by-mohit
400kv sub-station-final-ppt-by-mohit400kv sub-station-final-ppt-by-mohit
400kv sub-station-final-ppt-by-mohit
 
Presentation on Power transformer
Presentation on Power transformerPresentation on Power transformer
Presentation on Power transformer
 
Transformers Protection
Transformers ProtectionTransformers Protection
Transformers Protection
 
Report on visiting 132/33 kv substation teliarganj allahabad
Report on visiting 132/33 kv substation teliarganj allahabad Report on visiting 132/33 kv substation teliarganj allahabad
Report on visiting 132/33 kv substation teliarganj allahabad
 
Operational description of 400kv switchyard NTPC Ramagundam RSTPS
Operational description of 400kv switchyard NTPC Ramagundam RSTPSOperational description of 400kv switchyard NTPC Ramagundam RSTPS
Operational description of 400kv switchyard NTPC Ramagundam RSTPS
 
Training report-in-a-132-k-v-substation
Training report-in-a-132-k-v-substationTraining report-in-a-132-k-v-substation
Training report-in-a-132-k-v-substation
 
Transformer
TransformerTransformer
Transformer
 
Testing and Condition Monitoring of Substation Equipments
Testing and Condition Monitoring of Substation EquipmentsTesting and Condition Monitoring of Substation Equipments
Testing and Condition Monitoring of Substation Equipments
 
Motor Control Centre
Motor Control CentreMotor Control Centre
Motor Control Centre
 
ppt
pptppt
ppt
 
Power transformer protection
Power transformer protectionPower transformer protection
Power transformer protection
 
Vacuum circuit breaker selection of circuit breakers
Vacuum circuit breaker selection of circuit breakersVacuum circuit breaker selection of circuit breakers
Vacuum circuit breaker selection of circuit breakers
 

En vedette

Transformer & OLTC
Transformer & OLTCTransformer & OLTC
Transformer & OLTC
Rohit Dave
 
Transformer design
Transformer designTransformer design
Transformer design
sulaim_qais
 

En vedette (20)

Power Transformer ( Summer Training presentation BHEL )
Power Transformer ( Summer Training presentation BHEL )Power Transformer ( Summer Training presentation BHEL )
Power Transformer ( Summer Training presentation BHEL )
 
Transformer construction,types and working
Transformer construction,types and workingTransformer construction,types and working
Transformer construction,types and working
 
transformer ppt
transformer ppttransformer ppt
transformer ppt
 
Power transformer
Power transformerPower transformer
Power transformer
 
Transformer Repair Workshop Report [EEE]
Transformer Repair Workshop Report [EEE] Transformer Repair Workshop Report [EEE]
Transformer Repair Workshop Report [EEE]
 
Transformer design by s u khaparkar
Transformer design by s u khaparkarTransformer design by s u khaparkar
Transformer design by s u khaparkar
 
Transformer
TransformerTransformer
Transformer
 
Substation overview
Substation overviewSubstation overview
Substation overview
 
Tansformer @dheeraj upadhyay
Tansformer @dheeraj upadhyayTansformer @dheeraj upadhyay
Tansformer @dheeraj upadhyay
 
Protection of power transformer
Protection of power transformerProtection of power transformer
Protection of power transformer
 
Power transformers
Power transformersPower transformers
Power transformers
 
POWER TRANSFORMER INSULATION REVITALIZATION
POWER TRANSFORMER INSULATION REVITALIZATIONPOWER TRANSFORMER INSULATION REVITALIZATION
POWER TRANSFORMER INSULATION REVITALIZATION
 
Impulse test for power transformers
Impulse test for power transformersImpulse test for power transformers
Impulse test for power transformers
 
the substation components study
the substation components study the substation components study
the substation components study
 
Presentation Design of Computer aided design of power transformer
Presentation Design of Computer aided design of power transformerPresentation Design of Computer aided design of power transformer
Presentation Design of Computer aided design of power transformer
 
Transformer protection
Transformer protectionTransformer protection
Transformer protection
 
Transformer & OLTC
Transformer & OLTCTransformer & OLTC
Transformer & OLTC
 
Transformer design
Transformer designTransformer design
Transformer design
 
Testing of transformer
Testing of transformerTesting of transformer
Testing of transformer
 
Transformer Designing
Transformer Designing Transformer Designing
Transformer Designing
 

Similaire à Summer traning on Power Transformer Construction

6 MONTHS INDUSTRIAL TRAINING PPT EE BY KHUSHI RAM BHARDWAJ(DAVIET JALANDHAR)
6 MONTHS INDUSTRIAL TRAINING PPT EE BY KHUSHI RAM BHARDWAJ(DAVIET JALANDHAR)6 MONTHS INDUSTRIAL TRAINING PPT EE BY KHUSHI RAM BHARDWAJ(DAVIET JALANDHAR)
6 MONTHS INDUSTRIAL TRAINING PPT EE BY KHUSHI RAM BHARDWAJ(DAVIET JALANDHAR)
KHUSHI9999
 

Similaire à Summer traning on Power Transformer Construction (20)

Bhel report block 4
Bhel report block 4Bhel report block 4
Bhel report block 4
 
IRJET- A Case Study: In-Situ Weld Repair of Steel Casting of Grade C12A AST...
IRJET- 	 A Case Study: In-Situ Weld Repair of Steel Casting of Grade C12A AST...IRJET- 	 A Case Study: In-Situ Weld Repair of Steel Casting of Grade C12A AST...
IRJET- A Case Study: In-Situ Weld Repair of Steel Casting of Grade C12A AST...
 
Faisal Presentation.pptx
Faisal Presentation.pptxFaisal Presentation.pptx
Faisal Presentation.pptx
 
PPT on Manufacturing process of TG 800 MW, Stator Winding bar by ADARSH SI...
 PPT on Manufacturing process of TG 800 MW,  Stator Winding bar  by ADARSH SI... PPT on Manufacturing process of TG 800 MW,  Stator Winding bar  by ADARSH SI...
PPT on Manufacturing process of TG 800 MW, Stator Winding bar by ADARSH SI...
 
BHEL Trainning Report
BHEL Trainning ReportBHEL Trainning Report
BHEL Trainning Report
 
TURBO GENERATOR
TURBO GENERATORTURBO GENERATOR
TURBO GENERATOR
 
500 MW synchronous generator rotor construction report
500 MW synchronous generator rotor construction report500 MW synchronous generator rotor construction report
500 MW synchronous generator rotor construction report
 
477 report spiral welded pipe Erdi Karaçal Mechanical Engineer University of...
477  report spiral welded pipe Erdi Karaçal Mechanical Engineer University of...477  report spiral welded pipe Erdi Karaçal Mechanical Engineer University of...
477 report spiral welded pipe Erdi Karaçal Mechanical Engineer University of...
 
6 MONTHS INDUSTRIAL TRAINING PPT EE BY KHUSHI RAM BHARDWAJ(DAVIET JALANDHAR)
6 MONTHS INDUSTRIAL TRAINING PPT EE BY KHUSHI RAM BHARDWAJ(DAVIET JALANDHAR)6 MONTHS INDUSTRIAL TRAINING PPT EE BY KHUSHI RAM BHARDWAJ(DAVIET JALANDHAR)
6 MONTHS INDUSTRIAL TRAINING PPT EE BY KHUSHI RAM BHARDWAJ(DAVIET JALANDHAR)
 
Spatter Reduction by Prateek Biswas
Spatter Reduction by Prateek BiswasSpatter Reduction by Prateek Biswas
Spatter Reduction by Prateek Biswas
 
Bhel,hardwar PPT by M R MEENA
Bhel,hardwar PPT by M R MEENA Bhel,hardwar PPT by M R MEENA
Bhel,hardwar PPT by M R MEENA
 
2 vgel technique specification
2 vgel technique specification2 vgel technique specification
2 vgel technique specification
 
API_510_for_Exam.pdf
API_510_for_Exam.pdfAPI_510_for_Exam.pdf
API_510_for_Exam.pdf
 
integral coach factory report
integral coach factory report integral coach factory report
integral coach factory report
 
06 - MCCB & ACB - Fuji Electric
06 - MCCB & ACB - Fuji Electric06 - MCCB & ACB - Fuji Electric
06 - MCCB & ACB - Fuji Electric
 
Ijmet 10 02_002
Ijmet 10 02_002Ijmet 10 02_002
Ijmet 10 02_002
 
Fuji thiet bi dien-cataloguemccbfuji-160413042900
Fuji thiet bi dien-cataloguemccbfuji-160413042900Fuji thiet bi dien-cataloguemccbfuji-160413042900
Fuji thiet bi dien-cataloguemccbfuji-160413042900
 
Fuji thiet bi dien-cataloguemccbfuji-160413042900 dienhathe.org
Fuji thiet bi dien-cataloguemccbfuji-160413042900 dienhathe.orgFuji thiet bi dien-cataloguemccbfuji-160413042900 dienhathe.org
Fuji thiet bi dien-cataloguemccbfuji-160413042900 dienhathe.org
 
Fuji thiet bi dien-catalogue-mccb-fuji
Fuji thiet bi dien-catalogue-mccb-fujiFuji thiet bi dien-catalogue-mccb-fuji
Fuji thiet bi dien-catalogue-mccb-fuji
 
Fuji thiet bi dien-catalogue-mccb-fuji dienhathe.org
Fuji thiet bi dien-catalogue-mccb-fuji dienhathe.orgFuji thiet bi dien-catalogue-mccb-fuji dienhathe.org
Fuji thiet bi dien-catalogue-mccb-fuji dienhathe.org
 

Dernier

Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Kandungan 087776558899
 
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
HenryBriggs2
 
Digital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxDigital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptx
pritamlangde
 
DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakes
MayuraD1
 

Dernier (20)

Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxOrlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
 
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best ServiceTamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptx
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdf
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna Municipality
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
 
💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...
💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...
💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...
 
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
 
Digital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxDigital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptx
 
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxA CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
 
DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakes
 

Summer traning on Power Transformer Construction

  • 1. INDUSTRIAL TRAINING SEMINAR ON “TRANSFORMER CONSTRUCTION” AT BHEL BHOPAL DURATION: 29TH MAY – 25TH JUNE, 2014 HEAD OF DEPARTMENT Dr. Deepak Nagaria PRESENTED BY Mandeep Singh EE Final Yr B.I.E.T Jhansi Roll No: 1104320020 UNDER GUIDENCE OF Shri Shailendra Kumar Somi Sr. Er. TRM Div BHEL Bhopal
  • 2. 1. INTRODUCTION 2. TRANSFORMER CORE BUILDING 3. WINDING 4. COILASSEMBLY 5. POWER ASSEMBLY 6. CASE FITTING 7. INSULATION SHOP 8. TESTING 9. DISPATCH 10. REFERENCES CONTENTS
  • 3. BHEL, Bhopal established in 1964, is an integrated power plant equipment manufacturer and one of the largest engineering and manufacturing companies in India in terms of turnover. It has 15 manufacturing divisions, two repair units, four regional offices, eight service centers and 15 regional centers. It has been acquiring and adapting some of the best technologies from leading companies in the world including General Electric Company, Alstom SA, Siemens AG and Mitsubishi Heavy Industries Ltd. INTRODUCTION TO BHEL BHOPAL
  • 4. a) Block 1A :- Fabrication b) Block 1B :- Hydro Turbine, Tanks c) Block 2 :- Electrical Machine d) Block 3 :- Transformer Manufacturing, Capacitor & Bushing e) Block 4 :- Switchgear, Control gear f) Block 5 :- Foundry Division g) Block 6 :- Steam Turbine h) Block 7 :- Factory Store i) Block 8 :- Coils & Insulation j) Block 9 :- Traction motor block k) Block 10 :- Lamination Cutting BLOCK DISCRIPTION
  • 5. POWER TRANSFORMER CONSTRUCTION Fig: Block Diagram representation of Transformer Construction
  • 6. TRANSFORMER CORE BUILDING Following steps are involved in power transformer core construction: 1) Cutting & punching of CRGO 2) Stacking of CRGO 3) Fiber Glass End Frame insulation 4) Insulated Bolting of End Frame.
  • 7. Fig: Cutting & punching of CRGO Fig: Stacking of CRGO Fig: End Frame insulation & End Frame bolted Fig: Erecting of Core
  • 8. WINDING TYPES OF WINDING MACHINES Winding Machines are of two types: 1) Horizontal Winding machines 2) Vertical Winding machines Fig: Horizontal Winding machines Fig: Vertical Winding machines
  • 9. TYPES OF WINDINGS: 1) Spiral Winding (L.V.L.C.) 2) Helical Winding (L.V.H.C.) 3) Disc Winding 4) Interleaved Disc Winding Fig: Helical Winding Fig: Interleaved Disc Winding Fig: Disc Winding
  • 10. The various types of conductors used in coil winding are 1) CTC (Continuously Transposed Conductor) 2) PICC (Paper Insulated Copper Conductor) 3) BPICC (Bunch Paper Insulated Copper Conductor) TYPES OF WINDING CONDUCTORS Fig: CTCFig: PICC Fig: BPICC
  • 11. COILASSEMBLEY Coil Sequence L.V. Coil is placed adjacent to the CRGO steel core and H.V coil outside, in order to minimize the amount of insulation required. While assembling the different coils (i.e. Tap coil, L.V. Coil & H.V. Coil) tap coil can be placed in either of three positions depending upon the length of tap coil i.e. if tap coil is small it is placed inside of LV coil, if it is medium then between LV & HV coil, and if large then outside of HV coil. The coils are specified in the design may be of following types on the basis of operating voltage: 1) L.V. Coil Winding 2) H.V. Coil Winding 3) Tap Coil Winding
  • 12. Fig: Vertical Winding (HV)Fig: Horizontal Winding (LV & Tap) Fig: Coil Assembly Fig: Oven Baking Fig: Hydraulic Press
  • 13. POWER ASSEMBLEY  Core - Coil Assembly 1 a) Unlatching of core b) Fitting of bottom insulation c) Core coil assembly as per drawing/electrical specification  Core - Coil Assembly 2 a) Fitting of top insulation b) Relacing of core  Terminal Gear Mounting 1 a) Crimping & Brazzing b) Insulation Wrapping c) OLTC Connection d) Electrical Circuit manufacturing  Terminal Gear Mounting 2 a) Vapour Phase Drying b) Servicing. Steps involved in Power Assembly are :
  • 14. Fig: Unlatching of core Fig: Core coil assembly as per drawing Fig: Relacing of core CORE COILASSEMBLY 1 & 2
  • 15. Fig: Electrical Circuit manufacturing
  • 16. Fig:Vapour Phase Drying of core & winding alone Fig: Vapour Phase Drying of Transformer
  • 17. CASE FITTING 1) CT connections & Feed positions 2) Conservator 3) Bushing Connections 4) Magnetic Oil Gauge 5) Oil Temperature Indicator 6) Buchholz Relay 7) Radiator 8) Breather 9) Control panel Case Fitting involves connecting accessories of transformer, these accessories include following :
  • 18. 1. Transformer tank 2. High voltage bushing 3. Low voltage bushing 4. Cooling fins radiator 5. Cooling fans 6. Conservator tank 7. System ground terminal 8. Drain valve 9. Breather 10. Oil temperature gauge 11. Current xmer terminals 12. Control panel Fig: Parts of Transformer
  • 19. INSULATION MATERIALS Fig: Press Board Material Fig: Udel Wood Fig: Bushing Insulation Fig: Fiber Glass Material Fig: Oil Insulation Fig: Bakellite
  • 20. Items made up of PBM:- 1) Former Base Cylinder 2) DOF Separator 3) T-Block 4) Static Ring Items made up of Udel Wood:- 1) T-Spacers 2) Full ring segment 3) Half ring segment 4) Shunts Fig: Items made up of Udel Wood Fig: Items made up of PBM
  • 21. 1) TESTING TO THE BRITISH STANDARDS 2) ROUTINE TEST FOR TRANSFORMER AS PER IS 2026 TYPES OF TESTS
  • 22.  Routine tests: 1) Voltage ratio and polarity. 2) Winding resistance. 3) Short-circuit impedance and load loss. 4) Dielectric test. 5) No-load losses and current. 6) On-load tap-changer.  Type tests: 1) Temperature rise test. 2) Lightning impulse test. TESTING TO THE BRITISH STANDARDS
  • 23. 1) Dimensional Check 2) Winding Resistance Test 3) Short Circuit Test 4) Open Circuit Test 5) Induced Over Voltage Test 6) Separate Source Voltage 7) Insulation Resistance Test 8) B.D.V of Oil 9) Turns Ratio Test ROUTINE TEST FOR TRANSFORMER AS PER IS 2026
  • 24. DISPATCH After successful completion of testing, transformer is handed over to dispatch sections. At this stage after checking oil leakage, dismantling of all bushings, turrets etc. and covered with the blanking plates and the tank is fitted with nitrogen gas and then the transformer is dispatched to the concerned site. There are generally three separate shipments made: 1) The main tank c/w core and coils, 2) The accessories that have been removed and packaged, and 3) The insulating oil.
  • 25. Fig: Dispatch of power transformer