Implementing data center best practices and using CFD models allowed Great Lakes to suggest a data center layout that would improve PUE and efficiency. Jason Hallenbeck, DCDC, explains the concepts behind how data center floor design can save or kill your PUE and cooling efficiency—as found in this proposal. Find Jason presenting at the BICSI Fall Conference on September 14th at 1:30 pm.
2024: Domino Containers - The Next Step. News from the Domino Container commu...
Data Center Floor Design - Your Layout Can Save of Kill Your PUE & Cooling Efficiency
1. WeRackYourWorld.com
Data Center Floor
Design – Your
Layout Can Save or
Kill Your PUE &
Cooling Efficiency
The following data center upgrade proposal
demonstrates how floor layout has a major
impact on data center performance.
Implementing best practices and validating
those practices through CFD models allowed
Great Lakes to suggest a new layout that
would provide an improved PUE, cooling
costs reduction, and increased ROI.
Jason Hallenbeck, DCDC, explains the
concepts behind how data center floor
design can save or kill your PUE and
cooling efficiency—as found in this
proposal. Find Jason presenting
at the BICSI Fall Conference on
September 14th at 1:30pm.
2. WeRackYourWorld.com
2
Executive Summary
Great Lakes began a recent dialogue with a customer regarding current operations and the potential for performance
improvement within the customer data center.
After a series of initial conversations, the customer expressed a desire to gain an assessment of the current
operational status of the company’s data center, along with data center infrastructure management (DCIM)
recommendations which could provide multi-generational support as the company’s IT needs continue to evolve.
Great Lakes Case & Cabinet was contracted to provide a comprehensive evaluation of the customer’s Data Center
and to conduct complete computational fluid dynamics (CFD) analysis of the facility in its current form. Numerous site
visits were conducted and numerous on-site measurements were taken. The operational capabilities of the current
data center were captured in a CFD to establish baseline standards against which any potential future improvements
might be measured.
Great Lakes was also asked to look at the short, medium and long term potential for increased density within the
data center as well as an expansion of IT operations within the space. As part of that effort, Great Lakes would offer
infrastructure recommendations, supported by CFD analysis which would create real world performance estimates of
future operations within the data center, as those recommendations might be implemented.
The following pages outline the scope of work performed by Great Lakes as well as the presentation of data
collected, infrastructure recommendations made to the management of the data center (along with estimates and
ROI for recommended solutions) as well as CFD modeling designed to estimate data center performance conditions
as those recommendations might be implemented.
3. WeRackYourWorld.com
3
Overview Phase 1
Recommended Action Plan:
The following recommendations are described to increase the performance and efficiency of the data center based
on the modeling data and discussions with the data center team.
Phase 1 includes:
• Network Core tile migration pg. 4-7
• Removing under-floor baffle pg. 8-9
• Migrating Floor Tiles pg. 10-11
• Cold aisle and enclosure containment pg. 12-19
• Eliminate air re-circulation in current enclosures
Deployment of cold aisle containment
Core switch migration pg. 20-25
• Increasing CRAC unit set point (as desired) pg. 26-27
Additional Information:
• Recommended action plan pg. 28
• PUE, Cooling Cost Reduction and ROI pg. 29
• Conclusion pg. 30
4. WeRackYourWorld.com
4
Network Core (Baseline)
Enclosure 207
Rendered view Rendered view with airflow patterns
Rendered view with
airflow patterns
Enclosure 207 was chosen for an internal view to demonstrate
the airflow patterns inside the enclosure. The excess air
introduced by the unsealed cable cut-out lowers the
temperatures inside the enclosures in the row protecting the
side-to-side airflow equipment from overheating.
6. WeRackYourWorld.com
6
Network Core (Phase 1)
Enclosure 207
Rendered view Rendered view with airflow patterns
Rendered view with airflow patterns
Enclosure 207 was chosen for an internal view to demonstrate
the airflow patterns inside the enclosure. The excess air
introduced by the unsealed cable cut-out lowers the
temperatures inside the enclosures in the row protecting the
side-to-side airflow equipment from overheating.
207
Perforated floor tiles have been moved to provide a higher flow of conditioned air to the equipment. A high flow tile was place
7. WeRackYourWorld.com
7
207
Network Core (Baseline)
• Side to side airflow equipment creating a
cascading heat elevation scenario
Unblocked cable cutouts provide a supply of
cool air inside the enclosure
This reduces the temperature cascading
effect
Network Core
(Rearranged floor tiles)
• Floor tiles reorganized providing higher flow
of air directly in front of the enclosures
• High flow tile installed in front of #207 to
provide additional airflow to core switches in
nearby enclosures
• Sampling the temperatures at enclosure #204
we can see a 7.1o Fahrenheit decline in
temperature.
Temp at 81.5o F
Temp at 74.4o F
8. WeRackYourWorld.com
8
Under-floor (Baseline)
207
Entrance
With the under-floor plenum installed, the secondary zone created is highly pressurized.
In addition, there is minimal to no load in the secondary zone. This greatly reduces the
efficiency of the two CRAC units installed in the zone. It is recommended that this barrier
be removed to allow the two units to supply additional cooling to the entire room.
9. WeRackYourWorld.com
9
Under-floor (Phase 1)
207
With the plenum barrier removed, the CRAC units airflow from the secondary zone can travel to the
entire data center supporting IT loads where needed. This is especially significant when utilizing
cold aisle containment. With the cold aisle contained the proximity of the CRAC unit in a data center
to the load becomes less critical. Every unit in the data center can supply conditioned air to the
entire facility. In the event of unit(s) failures(s) provided that the overall cooling capacity does not fall
below the IT load the equipment will continue to operate without interruption. This increases uptime
by reducing the criticality of any one unit, and makes unit maintenance more manageable.
Entrance
10. WeRackYourWorld.com
10
Tile Migration
207
Tile migration for phase 1 development. By removing tiles in the hot aisle and locations not directly
near IT equipment the under-floor pressure increases creating a higher velocity of airflow to the
equipment providing better cooling. In addition, by reducing the amount of conditioned air mixing
with exhaust air the return temperature to the CRAC units increases which increases the efficiency
of the entire HVAC system.
Entrance
11. WeRackYourWorld.com
11
Equipment Orientation - Baseline
207
Shown is the current layout of enclosures and floor tiles in the data center. The red X
on the CRAC unit indicates that it is currently non-operational.
Entrance
12. WeRackYourWorld.com
12
Aisle Completion with Enclosures
207
The following enclosures are recommended to complete the rows. These were based on
discussions with IT and their future expansion plans.
GL840ES-2442 enclosures - qty 13 (2 enclosures will replace enclosures highlighted in red)
· #1— Qty. 2
· #2— Qty. 6
· #3— Qty. 5
GL840ENT-3242MSS enclosures—qty 3
· #4— Qty. 3
1
2
3
4
13. WeRackYourWorld.com
13
Equipment Orientation – Phase 1
207
Phase 1 layout shows the completed rows, migrated tiles overhead panels and aisle doors are
hidden to show cold aisles.
Entrance
14. WeRackYourWorld.com
14
Server Farm (Baseline)
• Unfinished rows increase potential for
recirculation of hot air
• Open rack spaces create short circuits inside the
enclosure, allowing conditioned air to bypass
equipment and hot aisle to recirculate back into the
equipment intakes
Server Farm (Phase 1)
• Additional enclosures complete rows and segregate
hot and conditioned air
• Open rack spaces have filler panels installed to
reduce short circuits
• Cisco 6500 switches migrated from EMC
enclosure to 30” wide enclosure
• Floor tiles have been moved from other areas in the
datacenter to complete cold aisle
• Model temperature comparison shows a 10.9o F
71.9oF
61.1oF
15. WeRackYourWorld.com
15
Server Farm Cold Aisle Containment
207
Shown is an overhead view of the complete aisles with containment doors at the end of the aisles
and overhead containment panels containing conditioned air in the cold aisle. This design was
tested based on discussion with the data center team based on its ability to reduce the criticality of
any one CRAC unit failure, eliminates hot air re-circulation improving the performance and
extending the life of the equipment.
16. WeRackYourWorld.com
16
Server Farm Cold Aisle Containment
207
Great Lakes enclosures were added to rows of enclosures already installed in the server farm
area of the data center. The completed rows allow better hot and cold air segregation.
Completed rows would also allow the installation of aisle containment doors.
Enclosures
already
installed in the
data center
Great Lakes
enclosures
17. WeRackYourWorld.com
17
Server Farm Cold Aisle Containment
207
Each aisle in the server
farm was contained using a
single, custom aisle door
(model shows two doors
which represents standards
aisle doors offered by Great
Lakes).
18. WeRackYourWorld.com
18
Server Farm Cold Aisle Containment
207
In addition to single aisle doors, Polargy Polarplex panels were installed across the top of the
rows to trap cool air in. Floor tiles from other locations in the data center were moved to the
aisles to create a row of fully perforated floor tiles (a mixture of standard and high flow tiles).
Single, custom
aisle door
Polargy
PolarPlex
Panels
Perforated
floor tile
High flow
floor tile
19. WeRackYourWorld.com
19
Server Farm Cold Aisle Containment
207
Because there was a height difference between the existing enclosures and the new Great
Lakes enclosures, a custom support bar was designed to create a level service to properly
mount the Polargy PolarPlex Panels to.
Height difference between the
existing enclosures (left) and
Great Lakes enclosures (right).
Custom support bar
20. WeRackYourWorld.com
20
San Switch Migration: Phase 1
207
Cisco Catalyst 6509-E core switches are migrated to two of the GL840ES-3048 enclosures in the 700 row. Baffle kits are installed to
prevent air recirculation from one switch to the next eliminating the potential for cascading heat issues.
21. WeRackYourWorld.com
21
San Switch: Phase 1
(Phase one)
207
Baffles reduce recirculation by directing conditioned air toward the intake side and exhausting the hot air toward the cold aisle. Used
in conjunction with a brush grommet kit, side-to-side airflow operates efficiently in a hot aisle/cold aisle configuration.
Intake side
(baffle side hidden) Exhaust side
22. WeRackYourWorld.com
22
Baseline: Top View
207
1. Highest temp in the cold aisle currently. Model
data average temp 73.6F
2. Network core temps outside of the enclosure
reach upwards of 75F
Entrance
CRAC Unit Specifications
Set Point 72° F
Supply Temp. 61° F
23. WeRackYourWorld.com
23
Phase 1: Top View
Polargy panels hidden to make cold aisle visible
207
1. Cold aisle temp consistent at 62.2°F
2. Network core temps outside of the enclosure at 73.4°F
3. Migrated SAN switches are active and exhausting temps at 82°F
By implementing containment, cold aisle temperatures are within a
few degrees of under-floor tile supply. This allows the CRAC units to
be increased in one degree increments and cold aisle temps will increase accordingly.
CRAC Unit Specifications
Set Point 72° F
Supply Temp. 61° F
Entrance
26. WeRackYourWorld.com
26
CRAC Unit Failure Analysis: Baseline
207
90.1°F Temp
When the CRAC unit with the highest load on it (conditioning the most air in the data center) is
shutdown, the hot air from the server farm (specifically the blade server enclosures) travels to
the next nearest unit. This increases the load on that unit as well as increases the cold aisle
temperatures. This scenario creates massive short cycling of hot air, increasing the
equipment intake temperatures, resulting in equipment “thermal-ing down/off” or failing.
27. WeRackYourWorld.com
27
CRAC Unit Failure Analysis: Phase 1
207
When cold aisle containment is implemented and the CRAC unit is shut down the hot air
continues to travel to the nearest available unit. However, with the cold aisle contained a
consistent flow of conditioned air is supplied into the aisle equipment intakes; no hot air short
cycling can occur, resulting in uninterrupted service in the event of a single unit failure.
Temps taken at enclosure 508 show a delta of 8 degrees Farenheit. In addition temps taken in
the cold remain a consistent
60-63 degrees F.
82.1°F Temp
28. WeRackYourWorld.com
28
Recommended Action Plan
207
Recommended Action Plan
• Network Core tile migration pg. 4-6
• Migrating floor tiles pg. 9
• Removing under-floor baffle pg. 7-8
• Cold aisle and enclosure containment pg. 10-14
o Completing aisles with enclosures pg. 11-13
o Eliminate air re-circulation in current
enclosures
o Install filler panels in open RMU
o Install solid top panels— IT3 Install
side panel blanks— IT4
• Deployment of cold aisle containment
o Install Polargy Polar-Plex panels-IT6
o Install aisle containment doors- IT1/IT2
• Core switch migration pg. 15-16
o Installation of Baffle Kits— ESSAB14
• Increasing CRAC unit set point (as desired) -For every degree the set point is raised 4% efficiency gain*
*Source: The American Society of Heating Refrigeration and Air Conditioning Engineers TC 9.9
29. WeRackYourWorld.com
29
PUE, Cooling Cost Reduction and ROI
207
PUE (Power Usage Effectiveness):
Average PUE for 2011 (based on data provided) 1.84
PUE estimate (after phase 1 completion) 1.39
Current and Projected cooling costs:
Current average monthly cooling cost (based on data provided) $4,153.38
Projected average monthly cooling cost $1,930.75
Estimated savings $2,222.63*
*Projected average savings and ROI can be improved by raising set point(s), reducing fan speed and cycling
CRAC units. Performance will vary based on system flexibility and tolerances
30. WeRackYourWorld.com
30
Conclusion
Great Lakes has designed and modeled a solution that provides the customer with a data center upgrade plan
designed to increase the energy efficiency and reliability of their current design by segregating hot and cold air
optimizing air delivery, and deploying cold aisle containment.
Recommendations:
1. Adjust the floor tiles providing airflow to the enclosures at the network core. Moving the tiles directly in front of
the enclosures will allow a greater supply of conditioned air to reach the equipment, greatly improving the
exhaust temperature of the airflow equipment installed in the racks and lowering the internal enclosure
temperatures. This effort will result in a decreased risk of thermal issues: performance degradation, thermal
shutdown, and early equipment
mortality.
2. Create and fully contain the cold aisles in the server farm. This can be achieved in several steps: redeploying
and consolidating floor tiles; completing the aisles with enclosures; installing filler panels in any unused RMU;
and containing the cold aisle through the use of end of row doors and overhead containment panels.
Through containment, the conditioned air is segregated from hot exhaust air. Contained conditioned air will remain at
delivered temperature until used by the equipment. Another advantage of cold aisle containment is consistency in
cold aisle temperatures which will be very close to the supply temperatures of the CRAC units. Any increase to the
set points of the CRAC unit should proportionally increase the conditioned air supplied to the cold aisle. This should
make it much easier to the deliver a consistent supply temperature to every piece of equipment.
Modeling revealed that the removal of the under floor baffle could increase the amount of cooling capacity to the
entire room. A fully open raised floor, in conjunction with cold aisle containment, could reduce the impact a single
CRAC unit failure will have on the data center. This scenario was modeled at the CRAC unit with the highest load in
the server farm. Hot aisle temperatures increased dramatically, while the cold aisle remained at supply temperatures.
31. WeRackYourWorld.com
31
Conclusion
By completing the Phase 1 recommendations, the data centers overall performance will be improved by:
Better utilizing the conditioned air
• Balancing the load per CRAC unit more effectively
• Increasing the available capacity (in RMU) on the datacenter floor space
• Significantly reducing recirculation in the enclosure
Improving reliability
• Reduced intake temperatures increasing equipment lifespan
• Balanced CRAC unit load reduces dependency on a single unit failure
• Cold aisle containment allows the server equipment to continue operation even when closest
proximity CRAC unit fails