SlideShare une entreprise Scribd logo
1  sur  1
Télécharger pour lire hors ligne
MATTHEW WARR PROFESSIONAL PORTFOLIO PROJECT OVERVIEW No.5 
RESUME/PORTFOLIO | CONFIDENTIAL 
 
 
 
Project Title    J P MORGAN CHASE ‐ ALDERMANBURY 
Client    J P MORGAN CHASE 
M&E Consultant    Cundall Johnston 
Main Contractor    Trinity Environmental Services Limited 
Value M&E Works    £2,000,000 
Duration    January 2011 – June 2011 (6months) 
Contract Type    JCT 05 Design and Build 
Trinity completed this prestigious £2million JP Morgan 
plant replacement project in September ‘11. Acting as 
the main contractor, the works involve extensive heavy 
crane  lifts  over  circa  8  weekends.  Pre‐construction 
activities/in‐depth surveys, validations and conditional 
reports.  
 
The  works  involved  the  replacement  of  the  existing 
four  roof  mounted  chillers  in  a  phased  manner  with 
four  new  units  and  associated  electrical  supply 
installations,  relocation  of  existing  roof  plant  and 
equipment  to  facilitate  the  new  and  revised  chiller 
gantry locations, modification to existing lighting, small 
power, fire alarm and security system services, test and 
commission all works. 
The  new  chiller  load  was  to  provide  3No.  chiller 
machines  each  rated  at  nominally  1,568kW  +  1No. 
standby  machine  rated  at  1,568kW  providing  N1 
resilience each chiller was supplied with two harmonic 
filter units. 
 
The  critical  parts  of  these  works  were  the  logistics 
regarding the craneage of materials/plant etc. on and 
off the roof. Due to road closures this had to be pre‐
booked and schedule 6‐8weeks in advance. The other 
critical  item  of  works  was  re‐routing  and  diversion  of 
existing  live  critical  mechanical  and  electrical  services 
whilst  maintaining  operation  of  the  building  and  the 
services retaining downtime to an absolute minimum. 
As  main  contractor  on  this  project  Trinity also 
incorporated  within  our  works  the  required  builders 
work,  steel  work,  visual  and  acoustic  screens, 
scaffolding  and  craneage.  With  these  elements  of 
works also came the responsibility of Health & Safety. 
 
During  the  whole  of  the  works  Trinity  worked  very 
closely with the clients team, consultants and in house 
maintenance  team  to  ensure  scheme  was  developed 
to provide sufficient access for maintenance. This also 
ensured  that  the  project  was  delivered  on  time  and 
without any major issues or instances. 

Contenu connexe

Tendances

Avanceon's Energy Management Solutions at work at Engro Fertilizer
Avanceon's Energy Management Solutions at work at Engro FertilizerAvanceon's Energy Management Solutions at work at Engro Fertilizer
Avanceon's Energy Management Solutions at work at Engro Fertilizer
Avanceon
 
2009 rammage
2009 rammage2009 rammage
2009 rammage
Ngy Ea
 
John Paul Hitt 10-20-2015
John Paul Hitt 10-20-2015John Paul Hitt 10-20-2015
John Paul Hitt 10-20-2015
John Hitt
 

Tendances (12)

Balpara Project Highlights 2015
Balpara Project Highlights 2015Balpara Project Highlights 2015
Balpara Project Highlights 2015
 
cv2
cv2cv2
cv2
 
Avanceon's Energy Management Solutions at work at Engro Fertilizer
Avanceon's Energy Management Solutions at work at Engro FertilizerAvanceon's Energy Management Solutions at work at Engro Fertilizer
Avanceon's Energy Management Solutions at work at Engro Fertilizer
 
Energy Management by Food&Beverage Industry
Energy Management by Food&Beverage IndustryEnergy Management by Food&Beverage Industry
Energy Management by Food&Beverage Industry
 
B4 - Successful Implementation of a Modular Geothermal Wellhead Strategy
B4 - Successful Implementation of a Modular Geothermal Wellhead StrategyB4 - Successful Implementation of a Modular Geothermal Wellhead Strategy
B4 - Successful Implementation of a Modular Geothermal Wellhead Strategy
 
2009 rammage
2009 rammage2009 rammage
2009 rammage
 
Sharma Resume
Sharma ResumeSharma Resume
Sharma Resume
 
Jaguar Land Rover
Jaguar Land RoverJaguar Land Rover
Jaguar Land Rover
 
osama dwedar ..
osama dwedar ..osama dwedar ..
osama dwedar ..
 
Resume- Plant Manager- Harish
Resume- Plant Manager- HarishResume- Plant Manager- Harish
Resume- Plant Manager- Harish
 
John Paul Hitt 10-20-2015
John Paul Hitt 10-20-2015John Paul Hitt 10-20-2015
John Paul Hitt 10-20-2015
 
Updated resume.pdf
Updated resume.pdfUpdated resume.pdf
Updated resume.pdf
 

En vedette (6)

Katherine Peterson’S Portfolio
Katherine Peterson’S PortfolioKatherine Peterson’S Portfolio
Katherine Peterson’S Portfolio
 
Portfolio- Jyoti Goswami (Interior designer)
Portfolio- Jyoti Goswami (Interior designer)Portfolio- Jyoti Goswami (Interior designer)
Portfolio- Jyoti Goswami (Interior designer)
 
EN_Gabriele Pelosi_Interior Design Portfolio
EN_Gabriele Pelosi_Interior Design PortfolioEN_Gabriele Pelosi_Interior Design Portfolio
EN_Gabriele Pelosi_Interior Design Portfolio
 
Nikhath's Portfolio
Nikhath's PortfolioNikhath's Portfolio
Nikhath's Portfolio
 
BCI Library Product Portfolio Presentation For Architects and Interior Design...
BCI Library Product Portfolio Presentation For Architects and Interior Design...BCI Library Product Portfolio Presentation For Architects and Interior Design...
BCI Library Product Portfolio Presentation For Architects and Interior Design...
 
Aruna - Interior Designing Profile
Aruna  -  Interior Designing  ProfileAruna  -  Interior Designing  Profile
Aruna - Interior Designing Profile
 

Similaire à 5. Brochure JPMC

Derek Dhonau resume
Derek Dhonau resumeDerek Dhonau resume
Derek Dhonau resume
Derek Dhonau
 
1-2 Broadgate Final Project Report
1-2 Broadgate Final Project Report1-2 Broadgate Final Project Report
1-2 Broadgate Final Project Report
Paul Warrington
 
Project Experience Rachel Byrne
Project Experience Rachel ByrneProject Experience Rachel Byrne
Project Experience Rachel Byrne
Rachel Byrne
 
3. Brochure Trilogy Swindon
3. Brochure Trilogy Swindon3. Brochure Trilogy Swindon
3. Brochure Trilogy Swindon
Matthew Warr
 
Terry CV June 2015
Terry CV June 2015Terry CV June 2015
Terry CV June 2015
Terry Harvey
 
Stewart Kane CV 2016
Stewart Kane CV 2016Stewart Kane CV 2016
Stewart Kane CV 2016
Stewart Kane
 
CV 160105 Paul Magee
CV 160105 Paul MageeCV 160105 Paul Magee
CV 160105 Paul Magee
Paul Magee
 
01 Redevelopment of the Proctor Hydroelectric Powerstation - Hydrovision Pape...
01 Redevelopment of the Proctor Hydroelectric Powerstation - Hydrovision Pape...01 Redevelopment of the Proctor Hydroelectric Powerstation - Hydrovision Pape...
01 Redevelopment of the Proctor Hydroelectric Powerstation - Hydrovision Pape...
Heather Martin, P.E.
 
PIETER PORTFOLIO - UP TO 2016 (01-05-2016)
PIETER PORTFOLIO - UP TO 2016 (01-05-2016)PIETER PORTFOLIO - UP TO 2016 (01-05-2016)
PIETER PORTFOLIO - UP TO 2016 (01-05-2016)
Pieter Venter
 
ProTec Recent Projects Brochure
ProTec Recent Projects BrochureProTec Recent Projects Brochure
ProTec Recent Projects Brochure
Steven MacDonald
 
9. Brochure Centre Point
9. Brochure Centre Point9. Brochure Centre Point
9. Brochure Centre Point
Matthew Warr
 
JA CV 050915 (1) (1)
JA CV 050915 (1) (1)JA CV 050915 (1) (1)
JA CV 050915 (1) (1)
John Adams
 

Similaire à 5. Brochure JPMC (20)

Derek Dhonau resume
Derek Dhonau resumeDerek Dhonau resume
Derek Dhonau resume
 
John_Buckley_CV_Dec 2016
John_Buckley_CV_Dec 2016John_Buckley_CV_Dec 2016
John_Buckley_CV_Dec 2016
 
1-2 Broadgate Final Project Report
1-2 Broadgate Final Project Report1-2 Broadgate Final Project Report
1-2 Broadgate Final Project Report
 
Project Experience Rachel Byrne
Project Experience Rachel ByrneProject Experience Rachel Byrne
Project Experience Rachel Byrne
 
william-first-revision
william-first-revisionwilliam-first-revision
william-first-revision
 
3. Brochure Trilogy Swindon
3. Brochure Trilogy Swindon3. Brochure Trilogy Swindon
3. Brochure Trilogy Swindon
 
Terry CV June 2015
Terry CV June 2015Terry CV June 2015
Terry CV June 2015
 
John_Buckley_CV_V9
John_Buckley_CV_V9John_Buckley_CV_V9
John_Buckley_CV_V9
 
McConnell Dowell Mastermyne - Made to Mine
McConnell Dowell Mastermyne - Made to MineMcConnell Dowell Mastermyne - Made to Mine
McConnell Dowell Mastermyne - Made to Mine
 
Stewart Kane CV 2016
Stewart Kane CV 2016Stewart Kane CV 2016
Stewart Kane CV 2016
 
CV 160105 Paul Magee
CV 160105 Paul MageeCV 160105 Paul Magee
CV 160105 Paul Magee
 
william-second-revision (3)
william-second-revision (3)william-second-revision (3)
william-second-revision (3)
 
01 Redevelopment of the Proctor Hydroelectric Powerstation - Hydrovision Pape...
01 Redevelopment of the Proctor Hydroelectric Powerstation - Hydrovision Pape...01 Redevelopment of the Proctor Hydroelectric Powerstation - Hydrovision Pape...
01 Redevelopment of the Proctor Hydroelectric Powerstation - Hydrovision Pape...
 
PIETER PORTFOLIO - UP TO 2016 (01-05-2016)
PIETER PORTFOLIO - UP TO 2016 (01-05-2016)PIETER PORTFOLIO - UP TO 2016 (01-05-2016)
PIETER PORTFOLIO - UP TO 2016 (01-05-2016)
 
C.V.
C.V.C.V.
C.V.
 
R callaghan DT774 Energy and Retrofit Presentation
R callaghan DT774 Energy and Retrofit PresentationR callaghan DT774 Energy and Retrofit Presentation
R callaghan DT774 Energy and Retrofit Presentation
 
ProTec Recent Projects Brochure
ProTec Recent Projects BrochureProTec Recent Projects Brochure
ProTec Recent Projects Brochure
 
Rich Mathias CV 2016
Rich Mathias CV 2016Rich Mathias CV 2016
Rich Mathias CV 2016
 
9. Brochure Centre Point
9. Brochure Centre Point9. Brochure Centre Point
9. Brochure Centre Point
 
JA CV 050915 (1) (1)
JA CV 050915 (1) (1)JA CV 050915 (1) (1)
JA CV 050915 (1) (1)
 

Plus de Matthew Warr

8. Brochure Luminaire
8. Brochure Luminaire8. Brochure Luminaire
8. Brochure Luminaire
Matthew Warr
 
4. Brochure M&R Towers
4. Brochure M&R Towers4. Brochure M&R Towers
4. Brochure M&R Towers
Matthew Warr
 
1. Brochure Soho Hotel
1. Brochure Soho Hotel1. Brochure Soho Hotel
1. Brochure Soho Hotel
Matthew Warr
 
2. Brochure Paramount Club
2. Brochure Paramount Club2. Brochure Paramount Club
2. Brochure Paramount Club
Matthew Warr
 
sse-enterprise-case-study-hinchingbrooke-hospital
sse-enterprise-case-study-hinchingbrooke-hospitalsse-enterprise-case-study-hinchingbrooke-hospital
sse-enterprise-case-study-hinchingbrooke-hospital
Matthew Warr
 

Plus de Matthew Warr (7)

Sunrise
SunriseSunrise
Sunrise
 
Roundhouse 1
Roundhouse 1Roundhouse 1
Roundhouse 1
 
8. Brochure Luminaire
8. Brochure Luminaire8. Brochure Luminaire
8. Brochure Luminaire
 
4. Brochure M&R Towers
4. Brochure M&R Towers4. Brochure M&R Towers
4. Brochure M&R Towers
 
1. Brochure Soho Hotel
1. Brochure Soho Hotel1. Brochure Soho Hotel
1. Brochure Soho Hotel
 
2. Brochure Paramount Club
2. Brochure Paramount Club2. Brochure Paramount Club
2. Brochure Paramount Club
 
sse-enterprise-case-study-hinchingbrooke-hospital
sse-enterprise-case-study-hinchingbrooke-hospitalsse-enterprise-case-study-hinchingbrooke-hospital
sse-enterprise-case-study-hinchingbrooke-hospital
 

5. Brochure JPMC

  • 1. MATTHEW WARR PROFESSIONAL PORTFOLIO PROJECT OVERVIEW No.5  RESUME/PORTFOLIO | CONFIDENTIAL        Project Title    J P MORGAN CHASE ‐ ALDERMANBURY  Client    J P MORGAN CHASE  M&E Consultant    Cundall Johnston  Main Contractor    Trinity Environmental Services Limited  Value M&E Works    £2,000,000  Duration    January 2011 – June 2011 (6months)  Contract Type    JCT 05 Design and Build  Trinity completed this prestigious £2million JP Morgan  plant replacement project in September ‘11. Acting as  the main contractor, the works involve extensive heavy  crane  lifts  over  circa  8  weekends.  Pre‐construction  activities/in‐depth surveys, validations and conditional  reports.     The  works  involved  the  replacement  of  the  existing  four  roof  mounted  chillers  in  a  phased  manner  with  four  new  units  and  associated  electrical  supply  installations,  relocation  of  existing  roof  plant  and  equipment  to  facilitate  the  new  and  revised  chiller  gantry locations, modification to existing lighting, small  power, fire alarm and security system services, test and  commission all works.  The  new  chiller  load  was  to  provide  3No.  chiller  machines  each  rated  at  nominally  1,568kW  +  1No.  standby  machine  rated  at  1,568kW  providing  N1  resilience each chiller was supplied with two harmonic  filter units.    The  critical  parts  of  these  works  were  the  logistics  regarding the craneage of materials/plant etc. on and  off the roof. Due to road closures this had to be pre‐ booked and schedule 6‐8weeks in advance. The other  critical  item  of  works  was  re‐routing  and  diversion  of  existing  live  critical  mechanical  and  electrical  services  whilst  maintaining  operation  of  the  building  and  the  services retaining downtime to an absolute minimum.  As  main  contractor  on  this  project  Trinity also  incorporated  within  our  works  the  required  builders  work,  steel  work,  visual  and  acoustic  screens,  scaffolding  and  craneage.  With  these  elements  of  works also came the responsibility of Health & Safety.    During  the  whole  of  the  works  Trinity  worked  very  closely with the clients team, consultants and in house  maintenance  team  to  ensure  scheme  was  developed  to provide sufficient access for maintenance. This also  ensured  that  the  project  was  delivered  on  time  and  without any major issues or instances.