Traffic Facility Works (PH-16) targeted for completion during 2022-23
S.No. Name of work Year of
Sanction
Total
Cost
(In Cr.)
Amount
spent till
30th June
(In Cr.)
Additional
funds required
[CAP/DPR/DF/
EBR]
(In Cr.)
Targeted
month of
completion
Status of Works/
Remarks
1. Development of stacking area
and Lighting facilities for
Automobile handling at
Bakshi ka Talab station.
2021-22 2.4746 0.8757 0 June 2022 Work awarded on 17.01.2022.
Work is in progress.
2. Gorakhpur Cantt.-
Remodeling of station for
developing as satellite
terminal.
2016-17 40.0415 0.8724 0 Dec. 2022 Platform surfacing & Station
building finishing work is in
progress. Existing service
buildings (except station & PI
building) have been dismantled
and relocated into newly
constructed buildings. Sheeting
work of pp shed on PF2/3 and 4/5
is in progress. NEW FOB
foundation works are under
progress.
3. Aishbagh-Manaknagar –
Independent bypass line.
2017-18 81.6300 21.4975 0 March2023 Estimate sanctioned By Rly.
Board on 01.08.2019. LOA issued
on 05.03.2020 for civil Engg.
work (All works except track
work). 3250 nos. protection pile,
construction of minor bridge no.3
and 35000 cum earth cutting
completed and work in progress.
Traffic Facility Works (PH-16) targeted for completion during 2022-23
S.No. Name of work Year of
Sanction
Total
Cost
(In Cr.)
Amount
spent till
30th June
(In Cr.)
Additional
funds required
[CAP/DPR/DF/
EBR]
(In Cr.)
Targeted
month of
completion
Status of Works/
Remarks
4. Remodeling of Farrukhbad
yard by providing dead end
for isolation on loop line and
converting line no. 07 to
running line etc.
2021-22 2.3367 0 1.0000
CAP
June 2022 Engg-Work in progress.
S&T- For S&T work contract
awarded. Indoor wiring work yet
to be started due to non-
availability of circuit diagram by
HQ. Outdoor signalling work
85% completed. CRS sanction
applied & awaited. Tentative NI
will be taken in IInd week of
June-22.
TRD-90% Work completed.TDC
10.06.2022.
5. Layout correction in Bhatni
& Deoria Sadar yard to
remove PSR/TSR.
2017-18 2.6456 0.5159 2.1297
RRSK
Feb. 2023 Bhatni- Work completed. At
Deoria Sadar - Work is in
progress.
S&T: -LOA issued on
28.01.2020 Work completed at
BTT. Work at DEOS will be
taken up after Engg work."
6. At Kusmhi – Modification
of yard.
2019-20 2.1000 0 2.1000
DF3
Dec. 2022 The work comprises of
modification of yard, shifting
crossovers at BSB end of
Kusumhi. The work shall be
executed along with 3rd line
Traffic Facility Works (PH-16) targeted for completion during 2022-23
S.No. Name of work Year of
Sanction
Total
Cost
(In Cr.)
Amount
spent till
30th June
(In Cr.)
Additional
funds required
[CAP/DPR/DF/
EBR]
(In Cr.)
Targeted
month of
completion
Status of Works/
Remarks
7. Improvement of approach
road of Rake handling
platform at Chhapra Gramin,
Siwan and Hathua.
2020-21 2.0020 0 2.0020
EBR
Feb. 2023 Work is in progress at Siwan.
Earth filling and brick soling in
stabling area done . Work at
Chhapra Gramin & Hathua will
be taken up.
8. Extension of line no. 8 and
shifting of Turn out at
Deoria Sadar yard.
2021-22 1.8873 0 1.8858
CAP
March2023 Scope- 50 m Extension of Line
no-8, Shifting of 1 T/O by 35
m and removal of 4 redundant
T/O.
Engg.- Material mobilization
under progress.
S&T: -LOA issued on 04.04.22.
Work under progress, SIP
approved, Selection table under
approval, CRS sanction application
will be sent up to 15.07.2022.
TDC-March’22.
9. Provision of 3rd running line
at Ghughli Station.
2021-22 8.8132 0 8.8131
DF3
Dec. 2023 Detailed estimate under
preparation.
S&T: -Detailed estimate given
to Engg dept for sanctioning.
Traffic Facility Works (PH-16) targeted for completion during 2022-23
S.No. Name of work Year of
Sanction
Total
Cost
(In Cr.)
Amount
spent till
30th June
(In Cr.)
Additional
funds required
[CAP/DPR/DF/
EBR]
(In Cr.)
Targeted
month of
completion
Status of Works/
Remarks
10. Bhatni-Peokol – Broad
gauge bypass line.
2012-13 49.1495 0.4808 5.0000
CAP
Dec. 2022 Ballast supply, Earthwork,
Blanketing work, Approach work
and Track linking work is in
progress.
11. Chhapra Jn – Interlocking of
goods lines 8, 9, 10, 11 and
provision of shunt signals
for stabling lines 12, 13, 14,
15 & pit lines.
2016-17 8.7367 1.9376 0 Dec. 2022 S&T-"LOA issued on 05.03.18
for outdoor work. Agency
awarded & work in progress,
Indoor execution work to be
done by BG/Con with EI. To be
commissioned by BG/Con
12. Chhapra- 2nd entry, 2nd home
platform, island platform, 3rd
new tracks & one stabling
line etc.
2017-18 24.6233 0 0 Dec. 2022 Work transferred to construction
on 30.03.2021. S&T and
SDEE/BSB : Electrical work to
be completed with civil work.

Contenu connexe

Similaire à Review of PH-16 With CRB.pptx

T13 Work Plan for Extension of time with financial target
T13 Work Plan for Extension of time  with financial targetT13 Work Plan for Extension of time  with financial target
T13 Work Plan for Extension of time with financial target
divyanshudahayat
 
Al Qasr Mall presentation
Al Qasr Mall presentationAl Qasr Mall presentation
Al Qasr Mall presentation
Mamdouh Attia
 
ANPARA D FGD PPT 07.06.2023-M (2).pptx
ANPARA D FGD PPT 07.06.2023-M (2).pptxANPARA D FGD PPT 07.06.2023-M (2).pptx
ANPARA D FGD PPT 07.06.2023-M (2).pptx
ssuser3797b9
 
M rly presentation_22.5.13
M rly presentation_22.5.13M rly presentation_22.5.13
M rly presentation_22.5.13
rdhyshym
 

Similaire à Review of PH-16 With CRB.pptx (20)

CV Sriinivas 1i doc
CV Sriinivas 1i docCV Sriinivas 1i doc
CV Sriinivas 1i doc
 
Project Review Meeting - 14.02.23.ppt
Project Review Meeting - 14.02.23.pptProject Review Meeting - 14.02.23.ppt
Project Review Meeting - 14.02.23.ppt
 
Building ssr 2013-14
Building ssr 2013-14Building ssr 2013-14
Building ssr 2013-14
 
5786 (1).pdf
5786 (1).pdf5786 (1).pdf
5786 (1).pdf
 
T13 Work Plan for Extension of time with financial target
T13 Work Plan for Extension of time  with financial targetT13 Work Plan for Extension of time  with financial target
T13 Work Plan for Extension of time with financial target
 
PPT to BPC.pptx
PPT to BPC.pptxPPT to BPC.pptx
PPT to BPC.pptx
 
Detailsh.pdf
Detailsh.pdfDetailsh.pdf
Detailsh.pdf
 
EMC e City - Rev meeting Aug 2018.ppt
EMC e City - Rev meeting Aug 2018.pptEMC e City - Rev meeting Aug 2018.ppt
EMC e City - Rev meeting Aug 2018.ppt
 
Projects Review Report
Projects  Review ReportProjects  Review Report
Projects Review Report
 
Al Qasr Mall presentation
Al Qasr Mall presentationAl Qasr Mall presentation
Al Qasr Mall presentation
 
ER. PRASHANT'S CV pdf
ER. PRASHANT'S CV pdfER. PRASHANT'S CV pdf
ER. PRASHANT'S CV pdf
 
Presentation 1
Presentation 1Presentation 1
Presentation 1
 
ANPARA D FGD PPT 07.06.2023-M (2).pptx
ANPARA D FGD PPT 07.06.2023-M (2).pptxANPARA D FGD PPT 07.06.2023-M (2).pptx
ANPARA D FGD PPT 07.06.2023-M (2).pptx
 
Gude Landfill Remediation - June 15, 2017
Gude Landfill Remediation - June 15, 2017Gude Landfill Remediation - June 15, 2017
Gude Landfill Remediation - June 15, 2017
 
Sadab
SadabSadab
Sadab
 
TRAINING REPORT A PROJECT ON ROAD WIDENI...
                       TRAINING REPORT              A PROJECT  ON ROAD WIDENI...                       TRAINING REPORT              A PROJECT  ON ROAD WIDENI...
TRAINING REPORT A PROJECT ON ROAD WIDENI...
 
GDRPL Company Profile - .pptx
GDRPL Company Profile - .pptxGDRPL Company Profile - .pptx
GDRPL Company Profile - .pptx
 
M rly presentation_22.5.13
M rly presentation_22.5.13M rly presentation_22.5.13
M rly presentation_22.5.13
 
updated Presentation for NCC-FFP Meeting -Keyal HPP.pptx
updated Presentation  for NCC-FFP Meeting -Keyal HPP.pptxupdated Presentation  for NCC-FFP Meeting -Keyal HPP.pptx
updated Presentation for NCC-FFP Meeting -Keyal HPP.pptx
 
ramakant_23.9.2016 (1)
ramakant_23.9.2016 (1)ramakant_23.9.2016 (1)
ramakant_23.9.2016 (1)
 

Dernier

Whitefield Call Girls Service: 🍓 7737669865 🍓 High Profile Model Escorts | Ba...
Whitefield Call Girls Service: 🍓 7737669865 🍓 High Profile Model Escorts | Ba...Whitefield Call Girls Service: 🍓 7737669865 🍓 High Profile Model Escorts | Ba...
Whitefield Call Girls Service: 🍓 7737669865 🍓 High Profile Model Escorts | Ba...
amitlee9823
 
Verified Trusted Call Girls Adugodi💘 9352852248 Good Looking standard Profil...
Verified Trusted Call Girls Adugodi💘 9352852248  Good Looking standard Profil...Verified Trusted Call Girls Adugodi💘 9352852248  Good Looking standard Profil...
Verified Trusted Call Girls Adugodi💘 9352852248 Good Looking standard Profil...
kumaririma588
 
RT Nagar Call Girls Service: 🍓 7737669865 🍓 High Profile Model Escorts | Bang...
RT Nagar Call Girls Service: 🍓 7737669865 🍓 High Profile Model Escorts | Bang...RT Nagar Call Girls Service: 🍓 7737669865 🍓 High Profile Model Escorts | Bang...
RT Nagar Call Girls Service: 🍓 7737669865 🍓 High Profile Model Escorts | Bang...
amitlee9823
 
Brookefield Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
Brookefield Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...Brookefield Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
Brookefield Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
amitlee9823
 
Escorts Service Basapura ☎ 7737669865☎ Book Your One night Stand (Bangalore)
Escorts Service Basapura ☎ 7737669865☎ Book Your One night Stand (Bangalore)Escorts Service Basapura ☎ 7737669865☎ Book Your One night Stand (Bangalore)
Escorts Service Basapura ☎ 7737669865☎ Book Your One night Stand (Bangalore)
amitlee9823
 
Escorts Service Nagavara ☎ 7737669865☎ Book Your One night Stand (Bangalore)
Escorts Service Nagavara ☎ 7737669865☎ Book Your One night Stand (Bangalore)Escorts Service Nagavara ☎ 7737669865☎ Book Your One night Stand (Bangalore)
Escorts Service Nagavara ☎ 7737669865☎ Book Your One night Stand (Bangalore)
amitlee9823
 
➥🔝 7737669865 🔝▻ dharamshala Call-girls in Women Seeking Men 🔝dharamshala🔝 ...
➥🔝 7737669865 🔝▻ dharamshala Call-girls in Women Seeking Men  🔝dharamshala🔝  ...➥🔝 7737669865 🔝▻ dharamshala Call-girls in Women Seeking Men  🔝dharamshala🔝  ...
➥🔝 7737669865 🔝▻ dharamshala Call-girls in Women Seeking Men 🔝dharamshala🔝 ...
amitlee9823
 

Dernier (20)

HiFi Call Girl Service Delhi Phone ☞ 9899900591 ☜ Escorts Service at along wi...
HiFi Call Girl Service Delhi Phone ☞ 9899900591 ☜ Escorts Service at along wi...HiFi Call Girl Service Delhi Phone ☞ 9899900591 ☜ Escorts Service at along wi...
HiFi Call Girl Service Delhi Phone ☞ 9899900591 ☜ Escorts Service at along wi...
 
Whitefield Call Girls Service: 🍓 7737669865 🍓 High Profile Model Escorts | Ba...
Whitefield Call Girls Service: 🍓 7737669865 🍓 High Profile Model Escorts | Ba...Whitefield Call Girls Service: 🍓 7737669865 🍓 High Profile Model Escorts | Ba...
Whitefield Call Girls Service: 🍓 7737669865 🍓 High Profile Model Escorts | Ba...
 
Verified Trusted Call Girls Adugodi💘 9352852248 Good Looking standard Profil...
Verified Trusted Call Girls Adugodi💘 9352852248  Good Looking standard Profil...Verified Trusted Call Girls Adugodi💘 9352852248  Good Looking standard Profil...
Verified Trusted Call Girls Adugodi💘 9352852248 Good Looking standard Profil...
 
Real service provider college girl Mira Road 8976425520
Real service provider college girl Mira Road 8976425520Real service provider college girl Mira Road 8976425520
Real service provider college girl Mira Road 8976425520
 
WhatsApp Chat: 📞 8617697112 Call Girl Baran is experienced
WhatsApp Chat: 📞 8617697112 Call Girl Baran is experiencedWhatsApp Chat: 📞 8617697112 Call Girl Baran is experienced
WhatsApp Chat: 📞 8617697112 Call Girl Baran is experienced
 
Q4-W4-SCIENCE-5 power point presentation
Q4-W4-SCIENCE-5 power point presentationQ4-W4-SCIENCE-5 power point presentation
Q4-W4-SCIENCE-5 power point presentation
 
Jordan_Amanda_DMBS202404_PB1_2024-04.pdf
Jordan_Amanda_DMBS202404_PB1_2024-04.pdfJordan_Amanda_DMBS202404_PB1_2024-04.pdf
Jordan_Amanda_DMBS202404_PB1_2024-04.pdf
 
call girls in Vasundhra (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝...
call girls in Vasundhra (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝...call girls in Vasundhra (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝...
call girls in Vasundhra (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝...
 
Booking open Available Pune Call Girls Nanded City 6297143586 Call Hot India...
Booking open Available Pune Call Girls Nanded City  6297143586 Call Hot India...Booking open Available Pune Call Girls Nanded City  6297143586 Call Hot India...
Booking open Available Pune Call Girls Nanded City 6297143586 Call Hot India...
 
Top Rated Pune Call Girls Koregaon Park ⟟ 6297143586 ⟟ Call Me For Genuine S...
Top Rated  Pune Call Girls Koregaon Park ⟟ 6297143586 ⟟ Call Me For Genuine S...Top Rated  Pune Call Girls Koregaon Park ⟟ 6297143586 ⟟ Call Me For Genuine S...
Top Rated Pune Call Girls Koregaon Park ⟟ 6297143586 ⟟ Call Me For Genuine S...
 
call girls in Kaushambi (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝...
call girls in Kaushambi (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝...call girls in Kaushambi (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝...
call girls in Kaushambi (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝...
 
RT Nagar Call Girls Service: 🍓 7737669865 🍓 High Profile Model Escorts | Bang...
RT Nagar Call Girls Service: 🍓 7737669865 🍓 High Profile Model Escorts | Bang...RT Nagar Call Girls Service: 🍓 7737669865 🍓 High Profile Model Escorts | Bang...
RT Nagar Call Girls Service: 🍓 7737669865 🍓 High Profile Model Escorts | Bang...
 
Brookefield Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
Brookefield Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...Brookefield Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
Brookefield Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
 
Sector 104, Noida Call girls :8448380779 Model Escorts | 100% verified
Sector 104, Noida Call girls :8448380779 Model Escorts | 100% verifiedSector 104, Noida Call girls :8448380779 Model Escorts | 100% verified
Sector 104, Noida Call girls :8448380779 Model Escorts | 100% verified
 
Escorts Service Basapura ☎ 7737669865☎ Book Your One night Stand (Bangalore)
Escorts Service Basapura ☎ 7737669865☎ Book Your One night Stand (Bangalore)Escorts Service Basapura ☎ 7737669865☎ Book Your One night Stand (Bangalore)
Escorts Service Basapura ☎ 7737669865☎ Book Your One night Stand (Bangalore)
 
call girls in Vaishali (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝✔️✔️
call girls in Vaishali (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝✔️✔️call girls in Vaishali (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝✔️✔️
call girls in Vaishali (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝✔️✔️
 
💫✅jodhpur 24×7 BEST GENUINE PERSON LOW PRICE CALL GIRL SERVICE FULL SATISFACT...
💫✅jodhpur 24×7 BEST GENUINE PERSON LOW PRICE CALL GIRL SERVICE FULL SATISFACT...💫✅jodhpur 24×7 BEST GENUINE PERSON LOW PRICE CALL GIRL SERVICE FULL SATISFACT...
💫✅jodhpur 24×7 BEST GENUINE PERSON LOW PRICE CALL GIRL SERVICE FULL SATISFACT...
 
Escorts Service Nagavara ☎ 7737669865☎ Book Your One night Stand (Bangalore)
Escorts Service Nagavara ☎ 7737669865☎ Book Your One night Stand (Bangalore)Escorts Service Nagavara ☎ 7737669865☎ Book Your One night Stand (Bangalore)
Escorts Service Nagavara ☎ 7737669865☎ Book Your One night Stand (Bangalore)
 
UI:UX Design and Empowerment Strategies for Underprivileged Transgender Indiv...
UI:UX Design and Empowerment Strategies for Underprivileged Transgender Indiv...UI:UX Design and Empowerment Strategies for Underprivileged Transgender Indiv...
UI:UX Design and Empowerment Strategies for Underprivileged Transgender Indiv...
 
➥🔝 7737669865 🔝▻ dharamshala Call-girls in Women Seeking Men 🔝dharamshala🔝 ...
➥🔝 7737669865 🔝▻ dharamshala Call-girls in Women Seeking Men  🔝dharamshala🔝  ...➥🔝 7737669865 🔝▻ dharamshala Call-girls in Women Seeking Men  🔝dharamshala🔝  ...
➥🔝 7737669865 🔝▻ dharamshala Call-girls in Women Seeking Men 🔝dharamshala🔝 ...
 

Review of PH-16 With CRB.pptx

  • 1. Traffic Facility Works (PH-16) targeted for completion during 2022-23 S.No. Name of work Year of Sanction Total Cost (In Cr.) Amount spent till 30th June (In Cr.) Additional funds required [CAP/DPR/DF/ EBR] (In Cr.) Targeted month of completion Status of Works/ Remarks 1. Development of stacking area and Lighting facilities for Automobile handling at Bakshi ka Talab station. 2021-22 2.4746 0.8757 0 June 2022 Work awarded on 17.01.2022. Work is in progress. 2. Gorakhpur Cantt.- Remodeling of station for developing as satellite terminal. 2016-17 40.0415 0.8724 0 Dec. 2022 Platform surfacing & Station building finishing work is in progress. Existing service buildings (except station & PI building) have been dismantled and relocated into newly constructed buildings. Sheeting work of pp shed on PF2/3 and 4/5 is in progress. NEW FOB foundation works are under progress. 3. Aishbagh-Manaknagar – Independent bypass line. 2017-18 81.6300 21.4975 0 March2023 Estimate sanctioned By Rly. Board on 01.08.2019. LOA issued on 05.03.2020 for civil Engg. work (All works except track work). 3250 nos. protection pile, construction of minor bridge no.3 and 35000 cum earth cutting completed and work in progress.
  • 2. Traffic Facility Works (PH-16) targeted for completion during 2022-23 S.No. Name of work Year of Sanction Total Cost (In Cr.) Amount spent till 30th June (In Cr.) Additional funds required [CAP/DPR/DF/ EBR] (In Cr.) Targeted month of completion Status of Works/ Remarks 4. Remodeling of Farrukhbad yard by providing dead end for isolation on loop line and converting line no. 07 to running line etc. 2021-22 2.3367 0 1.0000 CAP June 2022 Engg-Work in progress. S&T- For S&T work contract awarded. Indoor wiring work yet to be started due to non- availability of circuit diagram by HQ. Outdoor signalling work 85% completed. CRS sanction applied & awaited. Tentative NI will be taken in IInd week of June-22. TRD-90% Work completed.TDC 10.06.2022. 5. Layout correction in Bhatni & Deoria Sadar yard to remove PSR/TSR. 2017-18 2.6456 0.5159 2.1297 RRSK Feb. 2023 Bhatni- Work completed. At Deoria Sadar - Work is in progress. S&T: -LOA issued on 28.01.2020 Work completed at BTT. Work at DEOS will be taken up after Engg work." 6. At Kusmhi – Modification of yard. 2019-20 2.1000 0 2.1000 DF3 Dec. 2022 The work comprises of modification of yard, shifting crossovers at BSB end of Kusumhi. The work shall be executed along with 3rd line
  • 3. Traffic Facility Works (PH-16) targeted for completion during 2022-23 S.No. Name of work Year of Sanction Total Cost (In Cr.) Amount spent till 30th June (In Cr.) Additional funds required [CAP/DPR/DF/ EBR] (In Cr.) Targeted month of completion Status of Works/ Remarks 7. Improvement of approach road of Rake handling platform at Chhapra Gramin, Siwan and Hathua. 2020-21 2.0020 0 2.0020 EBR Feb. 2023 Work is in progress at Siwan. Earth filling and brick soling in stabling area done . Work at Chhapra Gramin & Hathua will be taken up. 8. Extension of line no. 8 and shifting of Turn out at Deoria Sadar yard. 2021-22 1.8873 0 1.8858 CAP March2023 Scope- 50 m Extension of Line no-8, Shifting of 1 T/O by 35 m and removal of 4 redundant T/O. Engg.- Material mobilization under progress. S&T: -LOA issued on 04.04.22. Work under progress, SIP approved, Selection table under approval, CRS sanction application will be sent up to 15.07.2022. TDC-March’22. 9. Provision of 3rd running line at Ghughli Station. 2021-22 8.8132 0 8.8131 DF3 Dec. 2023 Detailed estimate under preparation. S&T: -Detailed estimate given to Engg dept for sanctioning.
  • 4. Traffic Facility Works (PH-16) targeted for completion during 2022-23 S.No. Name of work Year of Sanction Total Cost (In Cr.) Amount spent till 30th June (In Cr.) Additional funds required [CAP/DPR/DF/ EBR] (In Cr.) Targeted month of completion Status of Works/ Remarks 10. Bhatni-Peokol – Broad gauge bypass line. 2012-13 49.1495 0.4808 5.0000 CAP Dec. 2022 Ballast supply, Earthwork, Blanketing work, Approach work and Track linking work is in progress. 11. Chhapra Jn – Interlocking of goods lines 8, 9, 10, 11 and provision of shunt signals for stabling lines 12, 13, 14, 15 & pit lines. 2016-17 8.7367 1.9376 0 Dec. 2022 S&T-"LOA issued on 05.03.18 for outdoor work. Agency awarded & work in progress, Indoor execution work to be done by BG/Con with EI. To be commissioned by BG/Con 12. Chhapra- 2nd entry, 2nd home platform, island platform, 3rd new tracks & one stabling line etc. 2017-18 24.6233 0 0 Dec. 2022 Work transferred to construction on 30.03.2021. S&T and SDEE/BSB : Electrical work to be completed with civil work.