Peshawar Cantonment and its Impacts on
the mobility in the city
by
Mian Abdul Qadeem and Ziaullah
Supervised by
Prof Dr. S. Akhtar Ali shah
Institute of Geography, Urban and Regional planning University
of Peshawar
TABLE OF CONTENTS
INTRODUCTION TO THE STUDY AREA
PROBLEM STATEMENT
AIM
OBJECTIVES
RESEARCH QUESTIONS
RESERCH METHODOLOGY
DATA COLLECTION
DATA ANALYSIS
FINDINGS AND SUGGESTION
Prelude
 The word cantonment is derived from the French
word canton meaning corner or subdivision.
 A cantonment is a military or police quarter.
 Cantonment in Pakistan is permanent military
stationed areas, which are administered by
cantonment board.
 All the Cantonment Board work under the
administrative control of the director general
military land and cantonment department
(MLCD), ministry of defense government of
Pakistan.
Source : http://en.wikipedia.org/wiki/Peshawar_Cantonment
PEAHAWAR CANTONMENT
 The Peshawar cantonment was established
by British government in the west side of
old walled city of Peshawar soon after
annexation of Punjab in 1848-49.
 It is also called Peshawar chhawni or
Peshawar sadder having the meaning of
encampment of presiding area.
 At that time this place was safe for the
officers, officials and other associates of
British regime.
 It originally occupied an area of 9.55 sq.
kilometers.
 The Peshawar cantt was established on
the remains of old town site and the
grave yard.
 Now it cover an area of 13 sq
kilometer, which is irregular and oblong
in shape
Source :http://en.wikipedia.org/wiki/Peshawar_Cantonment
Prepared by:Mian Abdul Qadeem
Problem Statement:
What are the impacts of existence of a Cantonment area in
propinquity to a densely populated settlement of Peshawar?
Aim
To identify the impacts of Peshawar cantonment on the
overall mobility in the city
OBJCTIVES
•To determine the traffic growth trend in the city during last
decade
•To determine the traffic volume entering and exiting from
the study area through different spatially distributed points
•To determine the impacts of delay in the city (in tangible
terms)
•To understand the people’s perception of the causes of the
problem
•To recommended a policy based on people’s perception
RESERCH QUESTIONS
 What are the causes of traffic delays
in the study area?
 What is the impact of these delays
on the people entering in the study
area?
 How the problem can be mitigated?
RESEARCH METHODOLOGY
•A case study approach – selecting a part of the study area to be a
representative of the whole
•Obtain map of Peshawar from Google earth
•Extract the study area from the map using GIS and prepare a base
map of Peshawar Cantonment.
•Collect the traffic volume data on selected points in the study area.
•Prepare the road network map of cantonment Peshawar by using
GIS.
•Collect the traffic volume data of Peshawar from the secondary
sources
•Draw the traffic growth curve of the city from the year 2002 to latest
available data.
•Carry out a delay study of traffic in the selected area.
•Analysis of data to determined causes of delay.
•Preparation of graphs and maps for displaying of the analytical work.
ZIAULLAH
DATA ANALYSIS
DATA COLLECTION:
Data was collected from both primary and secondary sources.
PRIMARY DATA:
was collected by traffic counts in the field. We collected the traffic
volume data on six main Roads enter to cantonment, Peshawar.
University Road, Bara Road, F.C. Square, Sadder Road, Khyber
Road and Warsak Road at different time period during a day.
SECONDARY DATA:
about the traffic volumes in the city was obtained from the office
of Director, General, Excise and Taxation Office, Khyber
pakhtunkhwa, Peshawar
Prepared by: Mian Abdul Qadeem and Ziaullah
Prepared by: Mian Abdul Qadeem and Ziaullah
0
100000
200000
300000
400000
500000
600000
YEAR 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011
NumberofVehicles
Vehicular volume in Peshawar (on Roads) 2002 - 2011
Source: Director General, Excise and Taxation, office, Khyber
Pakhtunkhwa, Peshawar
0
200
400
600
800
1000
1200
1400
7-8am 8-9am 9-10am 10-11am 11-12am 12-1pm 1-2pm 2-3pm 3-4pm 4-5pm 5-6pm 6-7pm
NumberofVehicles
Time
Bara Road In-Out Flow of Vehicles
inflow
Outflow
Source: Field survey Monday to Wednesday,8th,9th,10th,April,2013
o Maximum number of vehicles inflow between 7-8am
o Minimum number of inflow occurs between 4-5pm.
o Maximum number of outflow occur between 1-2pm
Minimum outflow between 11-12am
0
200
400
600
800
1000
1200
1400
7-8am 8-9am 9-10am 10-11am 11-12am 12-1pm 1-2pm 2-3pm 3-4pm 4-5pm 5-6pm 6-7pm
NumberofVehicles
Time
F.C Square In and Out flow of Vehicles
inflow
outflow
Source: Field survey 11th,12th,April, 2013
o Maximum number of vehicles inflow between 8-9am
o Minimum number of inflow occurs between 11-12am.
o Maximum number of outflow occur between 1-2pm
o Minimum outflow between 3-4pm.
0
200
400
600
800
1000
1200
1400
1600
1800
7-8am 8-9am 9-10am 10-11am 11-12am 12-1pm 1-2pm 2-3pm 3-4pm 4-5pm 5-6pm 6-7pm
Numberof
Vehicles
Time
Sadder Road(city side) In and Out flow of Vehicles
inflow
outflow
oMaximum number of vehicles inflow between 7-8am
oMinimum number of inflow occurs between 12-1pm.
oMaximum number of outflow occur between 7-8am
oMinimum outflow between 11-12am.
Source: Field survey, Monday andTuesday15th,16th April, 2013
0
500
1000
1500
2000
2500
3000
3500
4000
7-8am 8-9am 9-10am 10-11am 11-12am 12-1pm 1-2pm 2-3pm 3-4pm 4-5pm 5-6pm 6-7pm
NumberofVehicles
Time
Khyber Road In and Out flow of Vehicles
inflow
Outflow
Source: Field Survey, Wednesday to Friday17th, to 19th, April 2013
oMaximum number of vehicles inflow occur between 8-9am
o Minimum number of inflow occurs between 10-11am.
oMaximum number of outflow occur between 2-3pm
oMinimum outflow between 5-6pm.
0
200
400
600
800
1000
1200
1400
1600
1800
7-8am 8-9am 9-10am 10-11am 11-12am 12-1pm 1-2pm 2-3pm 3-4pm 4-5pm 5-6pm 6-7pm
NumberofVehicles
Time
Warsak Road In and Out Flow of Vehicles
inflow
outflow
Source: Field survey, Tuesday to Thursday 23rd ,24th ,25th April, 2013
oMaximum number of vehicles inflow between 1-2pm
o Minimum number of inflow occurs between 6-7pm
oMaximum number of outflow between 7-8am
oMinimum outflow between 11-12am.
0
500
1000
1500
2000
2500
3000
3500
4000
7-8am 8-9am 9-10am 10-11am 11-12am 12-1pm 1-2pm 2-3pm 3-4pm 4-5pm 5-6pm 6-7pm
Numberofvehicles
Time
In and out flow of Vehicles at University Road
Inflow of vehicle
Outflow of vehicle
Source: Field Survey, Wednesday to Friday,29th,30th,31st,April 2013
oMaximum number of vehicles inflow between 1-2pm
oMinimum number of inflow between 10-11am
oMaximum number of outflow occur between 8-9am
oMinimum outflow between 4-5pm.
Prepared by: Mian Abdul Qadeem and Ziaullah
Warsak Road
12%
Khyber Road
25%
University road
27%
Bara ROAD
9%
F.C CHOWK
8%
Saddar Road
19%
Percentage of Vehicles entering Cantonment
from selected points (7am to 7pm)
How many people have travelled with you in your vehicle today?
Respondents Frequency Percent Valid Percent
Only 24 48.0 48.0
Two 16 32.0 32.0
Three 10 20.0 20.0
Total 50 100.0 100.0
0
10
20
30
40
50
60
only Two Three
Percentage
Respondents
Persons travelled
Field Survey April, 2013
DO the checkpoints creates problems in cantonment Peshawar?
Respondents Frequency Percent Valid Percent
Yes
43 86.0 86.0
No
7 14.0 14.0
Total
50 100.0 100.0
86%
14%
Yes
No
Checkpoints creates problem
Field Survey April, 2013
Do you want to open the protected Roads for the general traffic?
Respondents Frequency Percent Valid Percent
Yes 42 84.0 84.0
No 8 16.0 16.0
Total 50 100.0 100.0
0
10
20
30
40
50
60
70
80
90
Yes No
Percentage
Respondents
Open the “protected” Roads
Field Survey April, 2013
suggestion in your mind to improve the mobility in cantonment, Peshawar?
Respondents Frequency Percent Valid Percent
Remove the Checkpoints 21 42.0 42.0
Open protected Roads 20 40.0 40.0
Encroachment 9 18.0 18.0
Total 50 100.0 100.0
0
5
10
15
20
25
30
35
40
45
Remove the Chckpoints Open link Roads Encroachment
Percentage
Respondents
Suggestion to improve traffic mobility
Field Survey April, 2013
One Vehicle average consumption , say
10km/liter of fuel
Assume that all vehicles coming from
Warsak road are heading to Gora bazar
Extra millage (old – new)=3 – 2=1km
So 15151 Vehicles come to our
destination via existing route (green)
will cover the extra millage as:
=1×15151= 15151 km
Thus extra fuel consumed =1515.1 liter
Besides this extra energy loss they also
cause environmental
pollution, congestion and time wastage.
If the new route (black) is available for
general transport, we can save this
extra bit of energy.
MIAN ABDUL QADEEM
FINDING AND SUGGESTION
Conclusions/findings
After the analysis of data it is concluded that :
The existing (available) roads transport network is insufficient to meet the
growing demand of its inhabitants
The rapidly growing city has engulfed the Cantonment area and the classical
structure can no longer support the current urban sprawl.
The existence of checkpoints at every nook and corner of the study area are
considered as an impediment to the free traffic flows by a large majority of the
respondents (86%).
Majority of the visitors to the Cantt area are travelling either single(48%) or with
one passenger (32%).
84% of the respondents believe that the presently unavailable or “protected”
cantt roads should be allowed for the general traffic.
A handful number of the respondents, that is 42% suggest that the checkpoints
in the cantt area should be removed while about similar number believe that
opening of the protected road can relieve congestion and improve overall traffic
flows in the study area.
This availability /provision of the new routes will save a significant amount of
fuel losses and improve the overall environment of the study area.
Suggestion:
To support the growing mobility needs of the city it
is suggested that:
 The cantonment area should be redesigned and removed to the
outskirts of the city
 All the protected roads should be made available of the general traffic to
take their due share in improving mobility in the city.
 The removal of checkpoint can improve the traffic flows and play a
positive role in improving the urban economy. However in the prevailing
security scenario these can be made more efficient with the properly
trained and efficient manpower.
 The general public should be made aware of the environmental
damages resulting from their trip that can be avoided or replaced with
an energy efficient mode like public transport, motorcycle etc.
THANKS……………………….

Contenu connexe

Similaire à Traffic Mobility in Peshawar

LAFINHAN O. O. FINAL YEAR PROJECT PRESENTATION
LAFINHAN O. O. FINAL YEAR PROJECT PRESENTATIONLAFINHAN O. O. FINAL YEAR PROJECT PRESENTATION
LAFINHAN O. O. FINAL YEAR PROJECT PRESENTATIONTobi Lafinhan
 
DESIGN OF A CIRCULAR COMPOSITE FOOTBRIDGE AT THE.pptx
DESIGN OF A CIRCULAR COMPOSITE FOOTBRIDGE AT THE.pptxDESIGN OF A CIRCULAR COMPOSITE FOOTBRIDGE AT THE.pptx
DESIGN OF A CIRCULAR COMPOSITE FOOTBRIDGE AT THE.pptxMrSJoe1
 
IRJET- Analysis of Saturation Flow at Signalized Intersections
IRJET-  	  Analysis of Saturation Flow at Signalized IntersectionsIRJET-  	  Analysis of Saturation Flow at Signalized Intersections
IRJET- Analysis of Saturation Flow at Signalized IntersectionsIRJET Journal
 
Existing Facilities And Deficiencies In A Busy Intersection At Dhaka Based On...
Existing Facilities And Deficiencies In A Busy Intersection At Dhaka Based On...Existing Facilities And Deficiencies In A Busy Intersection At Dhaka Based On...
Existing Facilities And Deficiencies In A Busy Intersection At Dhaka Based On...IJERA Editor
 
Study of Traffic Volume and Level of Service of Panjab University, Chandigarh
Study of Traffic Volume and Level of Service of Panjab University, ChandigarhStudy of Traffic Volume and Level of Service of Panjab University, Chandigarh
Study of Traffic Volume and Level of Service of Panjab University, ChandigarhIJERA Editor
 
Volume study presentation grp 04
Volume study presentation grp 04Volume study presentation grp 04
Volume study presentation grp 04Stone Rayhan
 
The Cause, Effect and Possible Solution to Traffic Congestion on Nigeria Road...
The Cause, Effect and Possible Solution to Traffic Congestion on Nigeria Road...The Cause, Effect and Possible Solution to Traffic Congestion on Nigeria Road...
The Cause, Effect and Possible Solution to Traffic Congestion on Nigeria Road...inventionjournals
 
Travel pattern in the near future
Travel pattern in the near futureTravel pattern in the near future
Travel pattern in the near futureHeemanish Midde
 
Transportation data-analysis-and-interpretation-1
Transportation data-analysis-and-interpretation-1Transportation data-analysis-and-interpretation-1
Transportation data-analysis-and-interpretation-1charliesdoremortel
 
Evaluation of parking provisions within the Ethekwini region
Evaluation of parking provisions within the Ethekwini regionEvaluation of parking provisions within the Ethekwini region
Evaluation of parking provisions within the Ethekwini regionTristan Wiggill
 
Traffic Volume Study
Traffic Volume StudyTraffic Volume Study
Traffic Volume StudyWaliur Rahman
 
Transport demand survey
Transport demand surveyTransport demand survey
Transport demand surveyBhishma Bhatti
 
RV 2014: Performance Measures People can Actually Understand by Hal R. Johnso...
RV 2014: Performance Measures People can Actually Understand by Hal R. Johnso...RV 2014: Performance Measures People can Actually Understand by Hal R. Johnso...
RV 2014: Performance Measures People can Actually Understand by Hal R. Johnso...Rail~Volution
 
Paper id 37201529
Paper id 37201529Paper id 37201529
Paper id 37201529IJRAT
 
Project Report Modified222
Project Report Modified222Project Report Modified222
Project Report Modified222Ratan Patil
 
Study on Pedestrian Behaviour near an Ashoka Road
Study on Pedestrian Behaviour near an Ashoka RoadStudy on Pedestrian Behaviour near an Ashoka Road
Study on Pedestrian Behaviour near an Ashoka RoadJournal For Research
 

Similaire à Traffic Mobility in Peshawar (20)

A2114065115
A2114065115A2114065115
A2114065115
 
LAFINHAN O. O. FINAL YEAR PROJECT PRESENTATION
LAFINHAN O. O. FINAL YEAR PROJECT PRESENTATIONLAFINHAN O. O. FINAL YEAR PROJECT PRESENTATION
LAFINHAN O. O. FINAL YEAR PROJECT PRESENTATION
 
Major Project ppt.pptx
Major Project ppt.pptxMajor Project ppt.pptx
Major Project ppt.pptx
 
DESIGN OF A CIRCULAR COMPOSITE FOOTBRIDGE AT THE.pptx
DESIGN OF A CIRCULAR COMPOSITE FOOTBRIDGE AT THE.pptxDESIGN OF A CIRCULAR COMPOSITE FOOTBRIDGE AT THE.pptx
DESIGN OF A CIRCULAR COMPOSITE FOOTBRIDGE AT THE.pptx
 
IRJET- Analysis of Saturation Flow at Signalized Intersections
IRJET-  	  Analysis of Saturation Flow at Signalized IntersectionsIRJET-  	  Analysis of Saturation Flow at Signalized Intersections
IRJET- Analysis of Saturation Flow at Signalized Intersections
 
Existing Facilities And Deficiencies In A Busy Intersection At Dhaka Based On...
Existing Facilities And Deficiencies In A Busy Intersection At Dhaka Based On...Existing Facilities And Deficiencies In A Busy Intersection At Dhaka Based On...
Existing Facilities And Deficiencies In A Busy Intersection At Dhaka Based On...
 
Study of Traffic Volume and Level of Service of Panjab University, Chandigarh
Study of Traffic Volume and Level of Service of Panjab University, ChandigarhStudy of Traffic Volume and Level of Service of Panjab University, Chandigarh
Study of Traffic Volume and Level of Service of Panjab University, Chandigarh
 
Volume study presentation grp 04
Volume study presentation grp 04Volume study presentation grp 04
Volume study presentation grp 04
 
Ijetr021237
Ijetr021237Ijetr021237
Ijetr021237
 
The Cause, Effect and Possible Solution to Traffic Congestion on Nigeria Road...
The Cause, Effect and Possible Solution to Traffic Congestion on Nigeria Road...The Cause, Effect and Possible Solution to Traffic Congestion on Nigeria Road...
The Cause, Effect and Possible Solution to Traffic Congestion on Nigeria Road...
 
Travel pattern in the near future
Travel pattern in the near futureTravel pattern in the near future
Travel pattern in the near future
 
Transportation data-analysis-and-interpretation-1
Transportation data-analysis-and-interpretation-1Transportation data-analysis-and-interpretation-1
Transportation data-analysis-and-interpretation-1
 
Evaluation of parking provisions within the Ethekwini region
Evaluation of parking provisions within the Ethekwini regionEvaluation of parking provisions within the Ethekwini region
Evaluation of parking provisions within the Ethekwini region
 
Volume study (group 5)
Volume study (group  5)Volume study (group  5)
Volume study (group 5)
 
Traffic Volume Study
Traffic Volume StudyTraffic Volume Study
Traffic Volume Study
 
Transport demand survey
Transport demand surveyTransport demand survey
Transport demand survey
 
RV 2014: Performance Measures People can Actually Understand by Hal R. Johnso...
RV 2014: Performance Measures People can Actually Understand by Hal R. Johnso...RV 2014: Performance Measures People can Actually Understand by Hal R. Johnso...
RV 2014: Performance Measures People can Actually Understand by Hal R. Johnso...
 
Paper id 37201529
Paper id 37201529Paper id 37201529
Paper id 37201529
 
Project Report Modified222
Project Report Modified222Project Report Modified222
Project Report Modified222
 
Study on Pedestrian Behaviour near an Ashoka Road
Study on Pedestrian Behaviour near an Ashoka RoadStudy on Pedestrian Behaviour near an Ashoka Road
Study on Pedestrian Behaviour near an Ashoka Road
 

Dernier

CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxRoyAbrique
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppCeline George
 
Concept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfConcept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfUmakantAnnand
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxNirmalaLoungPoorunde1
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdfssuser54595a
 
MENTAL STATUS EXAMINATION format.docx
MENTAL     STATUS EXAMINATION format.docxMENTAL     STATUS EXAMINATION format.docx
MENTAL STATUS EXAMINATION format.docxPoojaSen20
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application ) Sakshi Ghasle
 
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991RKavithamani
 
Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsKarinaGenton
 
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting DataJhengPantaleon
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxOH TEIK BIN
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxpboyjonauth
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon AUnboundStockton
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3JemimahLaneBuaron
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeThiyagu K
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityGeoBlogs
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsanshu789521
 

Dernier (20)

CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website App
 
Concept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfConcept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.Compdf
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptx
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
 
MENTAL STATUS EXAMINATION format.docx
MENTAL     STATUS EXAMINATION format.docxMENTAL     STATUS EXAMINATION format.docx
MENTAL STATUS EXAMINATION format.docx
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application )
 
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
 
Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its Characteristics
 
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptx
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptx
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon A
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and Mode
 
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha elections
 

Traffic Mobility in Peshawar

  • 1.
  • 2. Peshawar Cantonment and its Impacts on the mobility in the city by Mian Abdul Qadeem and Ziaullah Supervised by Prof Dr. S. Akhtar Ali shah Institute of Geography, Urban and Regional planning University of Peshawar
  • 3. TABLE OF CONTENTS INTRODUCTION TO THE STUDY AREA PROBLEM STATEMENT AIM OBJECTIVES RESEARCH QUESTIONS RESERCH METHODOLOGY DATA COLLECTION DATA ANALYSIS FINDINGS AND SUGGESTION
  • 4. Prelude  The word cantonment is derived from the French word canton meaning corner or subdivision.  A cantonment is a military or police quarter.  Cantonment in Pakistan is permanent military stationed areas, which are administered by cantonment board.  All the Cantonment Board work under the administrative control of the director general military land and cantonment department (MLCD), ministry of defense government of Pakistan. Source : http://en.wikipedia.org/wiki/Peshawar_Cantonment
  • 5. PEAHAWAR CANTONMENT  The Peshawar cantonment was established by British government in the west side of old walled city of Peshawar soon after annexation of Punjab in 1848-49.  It is also called Peshawar chhawni or Peshawar sadder having the meaning of encampment of presiding area.  At that time this place was safe for the officers, officials and other associates of British regime.
  • 6.  It originally occupied an area of 9.55 sq. kilometers.  The Peshawar cantt was established on the remains of old town site and the grave yard.  Now it cover an area of 13 sq kilometer, which is irregular and oblong in shape Source :http://en.wikipedia.org/wiki/Peshawar_Cantonment
  • 8. Problem Statement: What are the impacts of existence of a Cantonment area in propinquity to a densely populated settlement of Peshawar?
  • 9.
  • 10. Aim To identify the impacts of Peshawar cantonment on the overall mobility in the city OBJCTIVES •To determine the traffic growth trend in the city during last decade •To determine the traffic volume entering and exiting from the study area through different spatially distributed points •To determine the impacts of delay in the city (in tangible terms) •To understand the people’s perception of the causes of the problem •To recommended a policy based on people’s perception
  • 11. RESERCH QUESTIONS  What are the causes of traffic delays in the study area?  What is the impact of these delays on the people entering in the study area?  How the problem can be mitigated?
  • 12. RESEARCH METHODOLOGY •A case study approach – selecting a part of the study area to be a representative of the whole •Obtain map of Peshawar from Google earth •Extract the study area from the map using GIS and prepare a base map of Peshawar Cantonment. •Collect the traffic volume data on selected points in the study area. •Prepare the road network map of cantonment Peshawar by using GIS. •Collect the traffic volume data of Peshawar from the secondary sources •Draw the traffic growth curve of the city from the year 2002 to latest available data. •Carry out a delay study of traffic in the selected area. •Analysis of data to determined causes of delay. •Preparation of graphs and maps for displaying of the analytical work.
  • 15. DATA COLLECTION: Data was collected from both primary and secondary sources. PRIMARY DATA: was collected by traffic counts in the field. We collected the traffic volume data on six main Roads enter to cantonment, Peshawar. University Road, Bara Road, F.C. Square, Sadder Road, Khyber Road and Warsak Road at different time period during a day. SECONDARY DATA: about the traffic volumes in the city was obtained from the office of Director, General, Excise and Taxation Office, Khyber pakhtunkhwa, Peshawar
  • 16. Prepared by: Mian Abdul Qadeem and Ziaullah
  • 17. Prepared by: Mian Abdul Qadeem and Ziaullah
  • 18. 0 100000 200000 300000 400000 500000 600000 YEAR 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 NumberofVehicles Vehicular volume in Peshawar (on Roads) 2002 - 2011 Source: Director General, Excise and Taxation, office, Khyber Pakhtunkhwa, Peshawar
  • 19. 0 200 400 600 800 1000 1200 1400 7-8am 8-9am 9-10am 10-11am 11-12am 12-1pm 1-2pm 2-3pm 3-4pm 4-5pm 5-6pm 6-7pm NumberofVehicles Time Bara Road In-Out Flow of Vehicles inflow Outflow Source: Field survey Monday to Wednesday,8th,9th,10th,April,2013 o Maximum number of vehicles inflow between 7-8am o Minimum number of inflow occurs between 4-5pm. o Maximum number of outflow occur between 1-2pm Minimum outflow between 11-12am
  • 20. 0 200 400 600 800 1000 1200 1400 7-8am 8-9am 9-10am 10-11am 11-12am 12-1pm 1-2pm 2-3pm 3-4pm 4-5pm 5-6pm 6-7pm NumberofVehicles Time F.C Square In and Out flow of Vehicles inflow outflow Source: Field survey 11th,12th,April, 2013 o Maximum number of vehicles inflow between 8-9am o Minimum number of inflow occurs between 11-12am. o Maximum number of outflow occur between 1-2pm o Minimum outflow between 3-4pm.
  • 21. 0 200 400 600 800 1000 1200 1400 1600 1800 7-8am 8-9am 9-10am 10-11am 11-12am 12-1pm 1-2pm 2-3pm 3-4pm 4-5pm 5-6pm 6-7pm Numberof Vehicles Time Sadder Road(city side) In and Out flow of Vehicles inflow outflow oMaximum number of vehicles inflow between 7-8am oMinimum number of inflow occurs between 12-1pm. oMaximum number of outflow occur between 7-8am oMinimum outflow between 11-12am. Source: Field survey, Monday andTuesday15th,16th April, 2013
  • 22. 0 500 1000 1500 2000 2500 3000 3500 4000 7-8am 8-9am 9-10am 10-11am 11-12am 12-1pm 1-2pm 2-3pm 3-4pm 4-5pm 5-6pm 6-7pm NumberofVehicles Time Khyber Road In and Out flow of Vehicles inflow Outflow Source: Field Survey, Wednesday to Friday17th, to 19th, April 2013 oMaximum number of vehicles inflow occur between 8-9am o Minimum number of inflow occurs between 10-11am. oMaximum number of outflow occur between 2-3pm oMinimum outflow between 5-6pm.
  • 23. 0 200 400 600 800 1000 1200 1400 1600 1800 7-8am 8-9am 9-10am 10-11am 11-12am 12-1pm 1-2pm 2-3pm 3-4pm 4-5pm 5-6pm 6-7pm NumberofVehicles Time Warsak Road In and Out Flow of Vehicles inflow outflow Source: Field survey, Tuesday to Thursday 23rd ,24th ,25th April, 2013 oMaximum number of vehicles inflow between 1-2pm o Minimum number of inflow occurs between 6-7pm oMaximum number of outflow between 7-8am oMinimum outflow between 11-12am.
  • 24. 0 500 1000 1500 2000 2500 3000 3500 4000 7-8am 8-9am 9-10am 10-11am 11-12am 12-1pm 1-2pm 2-3pm 3-4pm 4-5pm 5-6pm 6-7pm Numberofvehicles Time In and out flow of Vehicles at University Road Inflow of vehicle Outflow of vehicle Source: Field Survey, Wednesday to Friday,29th,30th,31st,April 2013 oMaximum number of vehicles inflow between 1-2pm oMinimum number of inflow between 10-11am oMaximum number of outflow occur between 8-9am oMinimum outflow between 4-5pm.
  • 25. Prepared by: Mian Abdul Qadeem and Ziaullah
  • 26. Warsak Road 12% Khyber Road 25% University road 27% Bara ROAD 9% F.C CHOWK 8% Saddar Road 19% Percentage of Vehicles entering Cantonment from selected points (7am to 7pm)
  • 27. How many people have travelled with you in your vehicle today? Respondents Frequency Percent Valid Percent Only 24 48.0 48.0 Two 16 32.0 32.0 Three 10 20.0 20.0 Total 50 100.0 100.0 0 10 20 30 40 50 60 only Two Three Percentage Respondents Persons travelled Field Survey April, 2013
  • 28. DO the checkpoints creates problems in cantonment Peshawar? Respondents Frequency Percent Valid Percent Yes 43 86.0 86.0 No 7 14.0 14.0 Total 50 100.0 100.0 86% 14% Yes No Checkpoints creates problem Field Survey April, 2013
  • 29. Do you want to open the protected Roads for the general traffic? Respondents Frequency Percent Valid Percent Yes 42 84.0 84.0 No 8 16.0 16.0 Total 50 100.0 100.0 0 10 20 30 40 50 60 70 80 90 Yes No Percentage Respondents Open the “protected” Roads Field Survey April, 2013
  • 30. suggestion in your mind to improve the mobility in cantonment, Peshawar? Respondents Frequency Percent Valid Percent Remove the Checkpoints 21 42.0 42.0 Open protected Roads 20 40.0 40.0 Encroachment 9 18.0 18.0 Total 50 100.0 100.0 0 5 10 15 20 25 30 35 40 45 Remove the Chckpoints Open link Roads Encroachment Percentage Respondents Suggestion to improve traffic mobility Field Survey April, 2013
  • 31. One Vehicle average consumption , say 10km/liter of fuel Assume that all vehicles coming from Warsak road are heading to Gora bazar Extra millage (old – new)=3 – 2=1km So 15151 Vehicles come to our destination via existing route (green) will cover the extra millage as: =1×15151= 15151 km Thus extra fuel consumed =1515.1 liter Besides this extra energy loss they also cause environmental pollution, congestion and time wastage. If the new route (black) is available for general transport, we can save this extra bit of energy.
  • 34. Conclusions/findings After the analysis of data it is concluded that : The existing (available) roads transport network is insufficient to meet the growing demand of its inhabitants The rapidly growing city has engulfed the Cantonment area and the classical structure can no longer support the current urban sprawl. The existence of checkpoints at every nook and corner of the study area are considered as an impediment to the free traffic flows by a large majority of the respondents (86%). Majority of the visitors to the Cantt area are travelling either single(48%) or with one passenger (32%). 84% of the respondents believe that the presently unavailable or “protected” cantt roads should be allowed for the general traffic. A handful number of the respondents, that is 42% suggest that the checkpoints in the cantt area should be removed while about similar number believe that opening of the protected road can relieve congestion and improve overall traffic flows in the study area. This availability /provision of the new routes will save a significant amount of fuel losses and improve the overall environment of the study area.
  • 35. Suggestion: To support the growing mobility needs of the city it is suggested that:  The cantonment area should be redesigned and removed to the outskirts of the city  All the protected roads should be made available of the general traffic to take their due share in improving mobility in the city.  The removal of checkpoint can improve the traffic flows and play a positive role in improving the urban economy. However in the prevailing security scenario these can be made more efficient with the properly trained and efficient manpower.  The general public should be made aware of the environmental damages resulting from their trip that can be avoided or replaced with an energy efficient mode like public transport, motorcycle etc.