SlideShare une entreprise Scribd logo
1  sur  32
Télécharger pour lire hors ligne
Performing Against the Wall
SPI after Completion Date
Prepared by:
Mohamed Maged, MBA, PgDip, CCP, PMP
• Project Control Manager in Projects and Programs Management Office.
• B.Sc. Civil Engineering – Ain Shams University, Egypt.
• PGDIP in Construction Law – Salford University, Manchester, UK.
• Master of Business Administration (MBA) – UoPeople, US.
• SCE-Consultant, Saudi Council of Engineers, SA.
• CCP, Certified Cost Professional credential – AACE, US​.
• PMP, Project Management Professional credential – PMI, US​.
• Author of 50Qs- Construction Contracts Fundamentals & 50Qs- Scheduling Fundamentals.
• PPM Conference Organizer in AUC 2014, 2015 & Online since 2017 – ProfPlanner Groups.
• Practical experience more than 17 years in mega-projects in professions of cost estimation,
planning, cost control, procurement, project control, contract management and delay analysis.
Contents
Definition of Control
Performance M. Baseline
Why Earned Value?
Earned Schedule
Total Float vs SPI
Tricky or Misleading
Delay Indicators
4
What’s Control?
BASELINE
5
•What’s the Baseline Schedule?
The approved version of the schedule,
it’s a reference for progress reporting,
to measure the delays, to analyze any
EOT claim, and study time impact of
any event or change.
Baseline Schedule
Scope Cost Time
6
PMB and Budget
The integration of the technical scope, planning, scheduling, budgeting, and work
authorization results in the Performance Measurement Baseline (PMB).
Management Reserve (MR) is added to the PMB to reach the Contract Budget
Base. The Contract Budget Base, plus any profit or fees, equals the contract price.
Performance Measurement Baseline (PMB)
reflects the approved baseline of the project,
time phased and loaded to cost accounts into
which the program is managed. The baseline can
only be adjusted through an approved change,
via the change management program.
7
Cost Baseline
Planned Cash Flow.
The approved
version of the time-
phased project
budget, excluding
any management
reserves.
8
What is an updated schedule?
It’s a living copy schedule reflecting the project performance data
at a given data date regarding completed activities, in progress
activities, change in the logic, actual cost, and resources usage.
What is data date?
The data date is the date as of which all progress on the project is
reported.
Schedule Update
January 27, 2021
9
Outputs of Update
Baseline
Cash Flow:
Time phased
Budget Value
of Planned
Work
Schedule
Update:
Up to date
Actual Value
of Performed
Work &
remaining
January 27, 2021
10
➢ Earned Value Management
(EVM), started in 1800’s as a
method for integrated
project cost and schedule
control, then in the 1960’s, it
was redesigned by the U.S.
Air Force and named the
Cost/Schedule Planning and
Control System.
Earned Value History
11
Earned Value Management
This’s Why Earned Value…
EVM has been called
“ ”
January 27, 2021
12
Earned Value Analysis
➢ Earned Value (EV)
Analysis: Earned
Value analysis is an
integrated cost-
schedule approach
to monitor and
analyze the progress
of a project.
➢ EV =
Performance%*BAC
January 27, 2021
13
Earned Value Dimensions
➢ When is EV going
to be useless?
If the WP = WS
which happens for
sure at the project
completion if the
scope is the same.
BC-WS
BC-WP
AC-WP
14
Earned Value - Forecasting
(earned)
(actual)
(budgeted)
Forecasted cost variance (FCV) =
CV ∕ % Complete
Schedule variance in days (SV, days) =
SV ($) ∕ Daily planned budget ;
Daily planned budget =
total budget / total duration
Forecasted schedule variance (FSV) =
SV ∕ %Complete
15
15
(earned value)
(actual cost)
(planned value)
Cost baseline
Cash-out
SV= -1,067$
CV= +400$
Daily
planned
budget=
266.67
$ / day
FSV= -15 Days
FCV=
+1500$
% Complete = 26.7%
= - 4 days
16
What does happen at the
Practical Completion?
SPI = EV / PV = Performance% / Scheduled%
Performance%= EV / BAC, Scheduled% = PV / BAC
CPI = EV / AC
Example:
A project of BAC equals to $11M, has been completed with actual cost of $10M
and delayed by 60D additional to the original duration of 600D.
Solution:
BAC = 11M, PV = 11M, AC = 10M, EV = 100%*11M
CPI = EV / AC = 11M/10M = 1.1 … Below Budget (True)
SPI = EV / PV = 11M/11M = 1.0 … On Schedule regardless any delay (False)
17
Up to day 600, all calculations look correct. Let’s calculate it:
On day 600, PV = 11M, EV = 9M & AC = 8M.
CPI = EV / AC = 9M/8M = 1.125 … Below Budget (True)
SPI = EV / PV = 9M/11M = 0.82 … Behind Schedule (True)
One month later, PV = 11M, EV = 10M & AC = 9M.
CPI = EV / AC = 10M/9M = 1.11 … Below Budget (True)
SPI = EV / PV = 10M/11M = 0.91 … Behind Schedule (Improving??!!)
SPI vs CPI at the Contractual
Completion Date
January 27, 2021
18
Time-Based Measures:
Earned Schedule
SPI(time) = PT / AT
AT: Actual Time of Work
Performed (till Data date) (actual
time expended to date (ATE) for a
particular earned value)
PT: Planned Time of Work
Performed (originally planned
duration (OD) for that earned value)
PT
AT
January 27, 2021
19
Scope & Time Control
Time Control:
Schedule factors based
on time.
Forecast Time:
EAC(t) = BAC(t) / SPI (t)
Estimated
Duration
20
Earned Schedule at Completion
Assume the project completed at actual time (AT) of 3 years exceeded the
planned duration (PT) of 2 years by one year more which is 50% duration
increase, what will be the SPIcost vs Earned Schedule??
1-Cost-based Calculation:
SPI(cost) = EV/ PV=1
In case of the same scope, the earned
value will equal to the planned value
at the project completion, and any
delay or duration variance will not
show up like the project is on
schedule in spite of 1 year (50%)
delay.
Vs
2-Time-based Calculation:
Earned Schedule
SPI(time) = PT/ AT= 0.67 < 1
Here the delay shows up, behind
schedule , and the variance in
the duration is expresses, not
like the cost-based calculation
results.
21
Earned Schedule Vs Time
0.40
0.60
0.80
1.00
1.20
1.40
0 3 6 9 12 15 18 21 24 27 30 33 36
SPI (Cost Vs Time Calculations)
SPI ES
Months
On Schedule
Ahead of
Schedule
Behind
Schedule Behind
Schedule
Like On
Schedule
PV fixed at
Planned
Completion
(PT)
SPI(cost) = EV/ PV
ES (time) = PT/ AT
22
Critical Path Method. estimate the
minimum project duration and determine
the flexibility on the logical network paths.
Forward Pass. A critical path method
technique for calculating the early start
and early finish dates.
Backward Pass. calculating the late start
and late finish dates by working backward
from the project end date.
Total Float. The amount of time that a
schedule activity can be delayed or
extended from its early start date
without delaying the project finish date or
violating a schedule constraint.
Schedule Total Float
23
Negative Float - The total number of days that the start
or finish of an activity exceeds the time allowed.
Negative float indicates a delay in the schedule.
Out-of-Sequence Progress - Work completed for an
activity before it is logically scheduled to occur.
Schedule Update –
Quick Checks
January 27, 2021
24
Total Float Vs EVM
Schedule Factors
Misleading in Each:
1- Out of sequence can disturb the
results of EVM schedule factors specially
if the progress of critical path is different.
2- Availability of resources and resource
usage in remaining works can affect the
rationality of the total float specially if
many paths overlapped in the
remaining duration.
25
Some amount of knowledge brings more……
Earned Value Management
Tricky or Misleading
January 27, 2021
26
TF & SPI analysis
27
TF & SPI Examples
At early stage of a project, Scheduled%=4%, Performance%=2% & TF = Zero.
SPI = 2%/4% = 0.5 , Var.=-2% … Behind Schedule, but the delays are not on the CP
At middle of the project, Scheduled%=50%, Performance%=25% & TF = -20D out
of original duration 600D.
SPI = 25%/50% = 0.5 , Var.=-25% … Behind Schedule, but the delays on the CP
is not by a similar value (25%*600D=150D)
Another scenario, Scheduled%=50%, Performance%=55% & TF = -20D out of
original duration 600D.
SPI = 55%/50% = 1.1 , Var.=+5% … Ahead of Schedule, but there is a delay on
the CP while a high progress of non-critical
28
Delay Indicators
1- SPI
2- Variance
3- TF
4- CP logic
5- LOB
6- Trend analysis
0.9 = -30D
-5% = -15D
-50D
Hard logic
-60D
-20D
1.1 = +30D
+5% = +15D
-20D
Soft logic
N.A.
+5D/Similar Act.s
Case 01 (Mid.)
0.3 = -90D
-10% = -30D
-20D
Hard logic
-40D
-120D
Case 03 (Early)
Case 02 (Mid.)
29
Delay Analysis
11.2 Irrespective of which method of delay analysis is deployed, this is particularly relevant where
there is a significant risk that the remaining duration projections, logic links, calendars and constraints
within the baseline programme might produce anomalous results.
11. 7 Other methods, which may be reasonably deployed in particular circumstances having
considered the criteria in the choice of delay analysis technique, include: project wide retrospective as-
planned versus as-built analysis (i.e. not in windows), time chainage analysis, line of balance analysis,
resource curve analysis, and earned value analysis.
4.14 Although the Updated Programme should be the primary tool for guiding the CA in its
determination of an EOT, it should be used in conjunction with the contemporary evidence to ensure that
any resulting EOT is both reasonable and consistent with the factual circumstances … (common sense
and experience).
This highlights the importance of this logic process, but do not expect to perfect the logic at the
collapsed as-built method. However, this does not excuse the analyst from using a combination of
expert judgment, common sense, and extensive input from project personnel with first-hand
knowledge of the day-to-day events (witness).
References:
1- A GUIDE TO THE PROJECT MANAGEMENT BODY OF KNOWLEDGE
(PMBOK® Guide) – Fifth Edition.
2- Practice Standard for EARNED VALUE MANAGEMENT – PMI Global
STANDARD.
3- EARNED VALUE Project Management - QUENWT. FILEMNING and JOEL M.
KOPPELMAN.
4- Skills & Knowledge of Cost Engineering – AACE International.
5- EARNED VALUE MANAGEMENT APM GUIDELINE FOR THE UK.
6- Earned Value Professional (EVP) Certification Study Guide– AACE International.
7- CMPC Course Material – Construction Management Planning & Control
(Prof.Planner).
8- Construction Project Scheduling and Control - Saleh Mubarak.
9- Project Management, Planning, and Control - Albert Lester.
10- Rita Mulcahy’s PMP Exam Prep. – Eighth edition.
11- Other books, practices/RP, posts and slides from internet.
Study & Practice
AACEI Certificate:
• EVP – Earned Value Professional
My Related Courses:
• Project Control using EVM
• Delay Analysis and Claim Submittal
• Progress Reporting and Presentation
31
Thank You
Don’t Hesitate to contact….
M.Maged
magedkom@gmail.com
mobile : 00966-580264968

Contenu connexe

Tendances

Baseline Schedules 2
Baseline Schedules 2Baseline Schedules 2
Baseline Schedules 2Chris Carson
 
Dealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
Dealing With A Schedule That Cannot Be Approved - AACE 2012 MeetingDealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
Dealing With A Schedule That Cannot Be Approved - AACE 2012 MeetingChris Carson
 
Avoiding unrealistic schedules
Avoiding unrealistic schedulesAvoiding unrealistic schedules
Avoiding unrealistic schedulesHatem Hegazi
 
Project management using Primavera 6.x by Karim Ragab
Project management using Primavera 6.x by Karim RagabProject management using Primavera 6.x by Karim Ragab
Project management using Primavera 6.x by Karim RagabKarim Ragab
 
Schedule Design AACE
Schedule Design AACESchedule Design AACE
Schedule Design AACEChris Carson
 
Favorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEIFavorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEIChris Carson
 
Delay, dispute (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
Delay, dispute  (1st annual conf. of planning in cairo 23-8-2014) engr. m magedDelay, dispute  (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
Delay, dispute (1st annual conf. of planning in cairo 23-8-2014) engr. m magedM Maged Hegazy, LLM, MBA, CCP, P3O
 
Primavera P6 Tips and Tricks
Primavera P6 Tips and TricksPrimavera P6 Tips and Tricks
Primavera P6 Tips and Tricksp6academy
 
Update Delay Analysis
Update Delay AnalysisUpdate Delay Analysis
Update Delay AnalysisChris Carson
 
Chap 7.3 Determine budget
Chap 7.3   Determine budgetChap 7.3   Determine budget
Chap 7.3 Determine budgetAnand Bobade
 
PMP Chap 4 - Project Integration Management - Part1
PMP Chap 4 - Project Integration Management - Part1PMP Chap 4 - Project Integration Management - Part1
PMP Chap 4 - Project Integration Management - Part1Anand Bobade
 

Tendances (20)

Delay Analysis and Concurrent Delay
Delay Analysis and Concurrent DelayDelay Analysis and Concurrent Delay
Delay Analysis and Concurrent Delay
 
Eot claims hr__may2012
Eot claims hr__may2012Eot claims hr__may2012
Eot claims hr__may2012
 
Pmp Final Review - M Maged
Pmp Final Review - M MagedPmp Final Review - M Maged
Pmp Final Review - M Maged
 
Top10 planning fundamentals...
Top10 planning fundamentals...Top10 planning fundamentals...
Top10 planning fundamentals...
 
Baseline Schedules 2
Baseline Schedules 2Baseline Schedules 2
Baseline Schedules 2
 
Dealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
Dealing With A Schedule That Cannot Be Approved - AACE 2012 MeetingDealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
Dealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
 
Avoiding unrealistic schedules
Avoiding unrealistic schedulesAvoiding unrealistic schedules
Avoiding unrealistic schedules
 
Project management using Primavera 6.x by Karim Ragab
Project management using Primavera 6.x by Karim RagabProject management using Primavera 6.x by Karim Ragab
Project management using Primavera 6.x by Karim Ragab
 
Schedule Design AACE
Schedule Design AACESchedule Design AACE
Schedule Design AACE
 
Fundamentals of Construction Contracts - English, ver. 2021
Fundamentals of Construction Contracts - English, ver. 2021Fundamentals of Construction Contracts - English, ver. 2021
Fundamentals of Construction Contracts - English, ver. 2021
 
50 qts مقابلة عمل planning
50 qts مقابلة عمل planning50 qts مقابلة عمل planning
50 qts مقابلة عمل planning
 
Favorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEIFavorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEI
 
Delay, dispute (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
Delay, dispute  (1st annual conf. of planning in cairo 23-8-2014) engr. m magedDelay, dispute  (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
Delay, dispute (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
 
Primavera P6 Tips and Tricks
Primavera P6 Tips and TricksPrimavera P6 Tips and Tricks
Primavera P6 Tips and Tricks
 
Performance Measurement and Weightage Systems
Performance Measurement and Weightage SystemsPerformance Measurement and Weightage Systems
Performance Measurement and Weightage Systems
 
CCP Technical Paper and Application
CCP Technical Paper and ApplicationCCP Technical Paper and Application
CCP Technical Paper and Application
 
Update Delay Analysis
Update Delay AnalysisUpdate Delay Analysis
Update Delay Analysis
 
Chap 7.3 Determine budget
Chap 7.3   Determine budgetChap 7.3   Determine budget
Chap 7.3 Determine budget
 
PM using P6
PM using P6PM using P6
PM using P6
 
PMP Chap 4 - Project Integration Management - Part1
PMP Chap 4 - Project Integration Management - Part1PMP Chap 4 - Project Integration Management - Part1
PMP Chap 4 - Project Integration Management - Part1
 

Similaire à Performing against the wall - SPI after completion

07.cost management updated
07.cost management updated07.cost management updated
07.cost management updatedShraddha PMP
 
07 projectcostmanagement
07 projectcostmanagement07 projectcostmanagement
07 projectcostmanagementDhamo daran
 
PMP Training - 07 project cost management
PMP Training - 07 project cost managementPMP Training - 07 project cost management
PMP Training - 07 project cost managementejlp12
 
2.07 cost management 1
2.07 cost management 12.07 cost management 1
2.07 cost management 1reddvise
 
160155061 project-monitoring-control
160155061 project-monitoring-control160155061 project-monitoring-control
160155061 project-monitoring-controleidalin95
 
The Project Management Process - Week 9 Performance Management
The Project Management Process - Week 9   Performance ManagementThe Project Management Process - Week 9   Performance Management
The Project Management Process - Week 9 Performance ManagementCraig Brown
 
Ch 9 project monitoring &amp; control updated
Ch 9 project monitoring &amp; control updatedCh 9 project monitoring &amp; control updated
Ch 9 project monitoring &amp; control updatedFarhana Rehman
 
Building a Credible Performance Measurement Baseline in Two Days
Building a Credible Performance Measurement Baseline in Two DaysBuilding a Credible Performance Measurement Baseline in Two Days
Building a Credible Performance Measurement Baseline in Two DaysGlen Alleman
 
Projects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part OneProjects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part OneWaleed Hamdy Albana
 
project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 waleed hamdy
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisBECM, RUET, Bangladesh
 
Sorge.les
Sorge.lesSorge.les
Sorge.lesNASAPMC
 
L06 cost management
L06 cost managementL06 cost management
L06 cost managementAsa Chan
 
Program Management 2.0: Work Breakdown Structure
Program Management 2.0: Work Breakdown StructureProgram Management 2.0: Work Breakdown Structure
Program Management 2.0: Work Breakdown StructureJohn Carter
 
Building a Credible Performance Measurement Baseline (v3)
Building a Credible Performance Measurement Baseline (v3)Building a Credible Performance Measurement Baseline (v3)
Building a Credible Performance Measurement Baseline (v3)Glen Alleman
 
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.pptProfDrAnbalaganChinn
 
Smsvn pmp training_slides_chapter_7
Smsvn pmp training_slides_chapter_7Smsvn pmp training_slides_chapter_7
Smsvn pmp training_slides_chapter_7Nam Trung
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost ManagementSerdar Temiz
 

Similaire à Performing against the wall - SPI after completion (20)

PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSISPROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
 
07.cost management updated
07.cost management updated07.cost management updated
07.cost management updated
 
07 projectcostmanagement
07 projectcostmanagement07 projectcostmanagement
07 projectcostmanagement
 
PMP Training - 07 project cost management
PMP Training - 07 project cost managementPMP Training - 07 project cost management
PMP Training - 07 project cost management
 
2.07 cost management 1
2.07 cost management 12.07 cost management 1
2.07 cost management 1
 
160155061 project-monitoring-control
160155061 project-monitoring-control160155061 project-monitoring-control
160155061 project-monitoring-control
 
The Project Management Process - Week 9 Performance Management
The Project Management Process - Week 9   Performance ManagementThe Project Management Process - Week 9   Performance Management
The Project Management Process - Week 9 Performance Management
 
Ch 9 project monitoring &amp; control updated
Ch 9 project monitoring &amp; control updatedCh 9 project monitoring &amp; control updated
Ch 9 project monitoring &amp; control updated
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Building a Credible Performance Measurement Baseline in Two Days
Building a Credible Performance Measurement Baseline in Two DaysBuilding a Credible Performance Measurement Baseline in Two Days
Building a Credible Performance Measurement Baseline in Two Days
 
Projects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part OneProjects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part One
 
project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 project control using earned value analysis - Part 01
project control using earned value analysis - Part 01
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value Analysis
 
Sorge.les
Sorge.lesSorge.les
Sorge.les
 
L06 cost management
L06 cost managementL06 cost management
L06 cost management
 
Program Management 2.0: Work Breakdown Structure
Program Management 2.0: Work Breakdown StructureProgram Management 2.0: Work Breakdown Structure
Program Management 2.0: Work Breakdown Structure
 
Building a Credible Performance Measurement Baseline (v3)
Building a Credible Performance Measurement Baseline (v3)Building a Credible Performance Measurement Baseline (v3)
Building a Credible Performance Measurement Baseline (v3)
 
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
 
Smsvn pmp training_slides_chapter_7
Smsvn pmp training_slides_chapter_7Smsvn pmp training_slides_chapter_7
Smsvn pmp training_slides_chapter_7
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 

Plus de M Maged Hegazy, LLM, MBA, CCP, P3O

خمسون سؤال في إدارة عقود التشييد أو المقاولات -الإصدار الثاني
خمسون سؤال في إدارة عقود التشييد أو المقاولات -الإصدار الثاني خمسون سؤال في إدارة عقود التشييد أو المقاولات -الإصدار الثاني
خمسون سؤال في إدارة عقود التشييد أو المقاولات -الإصدار الثاني M Maged Hegazy, LLM, MBA, CCP, P3O
 
خمسون سؤال في إدارة عقود التشييد أو المقاولات -الإصدار الأول
خمسون سؤال في إدارة عقود التشييد أو المقاولات -الإصدار الأولخمسون سؤال في إدارة عقود التشييد أو المقاولات -الإصدار الأول
خمسون سؤال في إدارة عقود التشييد أو المقاولات -الإصدار الأولM Maged Hegazy, LLM, MBA, CCP, P3O
 
26 مؤتمر ادارة المشروعات contract relations management
26 مؤتمر ادارة المشروعات contract relations management26 مؤتمر ادارة المشروعات contract relations management
26 مؤتمر ادارة المشروعات contract relations managementM Maged Hegazy, LLM, MBA, CCP, P3O
 
4 أعوام الصفحة الرئيسية التابع لها جروبات Best Advice
4 أعوام الصفحة الرئيسية التابع لها جروبات Best Advice4 أعوام الصفحة الرئيسية التابع لها جروبات Best Advice
4 أعوام الصفحة الرئيسية التابع لها جروبات Best AdviceM Maged Hegazy, LLM, MBA, CCP, P3O
 

Plus de M Maged Hegazy, LLM, MBA, CCP, P3O (19)

Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
Concurrent Delay in Construction
Concurrent Delay in ConstructionConcurrent Delay in Construction
Concurrent Delay in Construction
 
Essentials of EOT Claims
Essentials of EOT ClaimsEssentials of EOT Claims
Essentials of EOT Claims
 
CCP Course - Introduction.pdf
CCP Course - Introduction.pdfCCP Course - Introduction.pdf
CCP Course - Introduction.pdf
 
International Delay Analysis Approaches
International Delay Analysis ApproachesInternational Delay Analysis Approaches
International Delay Analysis Approaches
 
خمسون سؤال في إدارة عقود التشييد أو المقاولات -الإصدار الثاني
خمسون سؤال في إدارة عقود التشييد أو المقاولات -الإصدار الثاني خمسون سؤال في إدارة عقود التشييد أو المقاولات -الإصدار الثاني
خمسون سؤال في إدارة عقود التشييد أو المقاولات -الإصدار الثاني
 
Missing and modern necessary skills
Missing and modern necessary skillsMissing and modern necessary skills
Missing and modern necessary skills
 
Standard Forms of Construction Contracts
Standard Forms of Construction ContractsStandard Forms of Construction Contracts
Standard Forms of Construction Contracts
 
Introduction to construction contracts fundamentals
Introduction to construction contracts fundamentalsIntroduction to construction contracts fundamentals
Introduction to construction contracts fundamentals
 
خمسون سؤال في إدارة عقود التشييد أو المقاولات -الإصدار الأول
خمسون سؤال في إدارة عقود التشييد أو المقاولات -الإصدار الأولخمسون سؤال في إدارة عقود التشييد أو المقاولات -الإصدار الأول
خمسون سؤال في إدارة عقود التشييد أو المقاولات -الإصدار الأول
 
Procurement negotiation tips and phases
Procurement negotiation tips and phasesProcurement negotiation tips and phases
Procurement negotiation tips and phases
 
5th Anniversary of Planning & Project Control Group
5th Anniversary of Planning & Project Control Group5th Anniversary of Planning & Project Control Group
5th Anniversary of Planning & Project Control Group
 
26 مؤتمر ادارة المشروعات contract relations management
26 مؤتمر ادارة المشروعات contract relations management26 مؤتمر ادارة المشروعات contract relations management
26 مؤتمر ادارة المشروعات contract relations management
 
4 أعوام الصفحة الرئيسية التابع لها جروبات Best Advice
4 أعوام الصفحة الرئيسية التابع لها جروبات Best Advice4 أعوام الصفحة الرئيسية التابع لها جروبات Best Advice
4 أعوام الصفحة الرئيسية التابع لها جروبات Best Advice
 
Contracts classification
Contracts classificationContracts classification
Contracts classification
 
3 years acheivements
3 years acheivements3 years acheivements
3 years acheivements
 
PMP integration review
PMP integration reviewPMP integration review
PMP integration review
 
Pmp procurement rev
Pmp procurement revPmp procurement rev
Pmp procurement rev
 
FIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshopFIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshop
 

Dernier

Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 

Dernier (20)

Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 

Performing against the wall - SPI after completion

  • 1. Performing Against the Wall SPI after Completion Date Prepared by: Mohamed Maged, MBA, PgDip, CCP, PMP
  • 2. • Project Control Manager in Projects and Programs Management Office. • B.Sc. Civil Engineering – Ain Shams University, Egypt. • PGDIP in Construction Law – Salford University, Manchester, UK. • Master of Business Administration (MBA) – UoPeople, US. • SCE-Consultant, Saudi Council of Engineers, SA. • CCP, Certified Cost Professional credential – AACE, US​. • PMP, Project Management Professional credential – PMI, US​. • Author of 50Qs- Construction Contracts Fundamentals & 50Qs- Scheduling Fundamentals. • PPM Conference Organizer in AUC 2014, 2015 & Online since 2017 – ProfPlanner Groups. • Practical experience more than 17 years in mega-projects in professions of cost estimation, planning, cost control, procurement, project control, contract management and delay analysis.
  • 3. Contents Definition of Control Performance M. Baseline Why Earned Value? Earned Schedule Total Float vs SPI Tricky or Misleading Delay Indicators
  • 5. 5 •What’s the Baseline Schedule? The approved version of the schedule, it’s a reference for progress reporting, to measure the delays, to analyze any EOT claim, and study time impact of any event or change. Baseline Schedule Scope Cost Time
  • 6. 6 PMB and Budget The integration of the technical scope, planning, scheduling, budgeting, and work authorization results in the Performance Measurement Baseline (PMB). Management Reserve (MR) is added to the PMB to reach the Contract Budget Base. The Contract Budget Base, plus any profit or fees, equals the contract price. Performance Measurement Baseline (PMB) reflects the approved baseline of the project, time phased and loaded to cost accounts into which the program is managed. The baseline can only be adjusted through an approved change, via the change management program.
  • 7. 7 Cost Baseline Planned Cash Flow. The approved version of the time- phased project budget, excluding any management reserves.
  • 8. 8 What is an updated schedule? It’s a living copy schedule reflecting the project performance data at a given data date regarding completed activities, in progress activities, change in the logic, actual cost, and resources usage. What is data date? The data date is the date as of which all progress on the project is reported. Schedule Update
  • 9. January 27, 2021 9 Outputs of Update Baseline Cash Flow: Time phased Budget Value of Planned Work Schedule Update: Up to date Actual Value of Performed Work & remaining
  • 10. January 27, 2021 10 ➢ Earned Value Management (EVM), started in 1800’s as a method for integrated project cost and schedule control, then in the 1960’s, it was redesigned by the U.S. Air Force and named the Cost/Schedule Planning and Control System. Earned Value History
  • 11. 11 Earned Value Management This’s Why Earned Value… EVM has been called “ ”
  • 12. January 27, 2021 12 Earned Value Analysis ➢ Earned Value (EV) Analysis: Earned Value analysis is an integrated cost- schedule approach to monitor and analyze the progress of a project. ➢ EV = Performance%*BAC
  • 13. January 27, 2021 13 Earned Value Dimensions ➢ When is EV going to be useless? If the WP = WS which happens for sure at the project completion if the scope is the same. BC-WS BC-WP AC-WP
  • 14. 14 Earned Value - Forecasting (earned) (actual) (budgeted) Forecasted cost variance (FCV) = CV ∕ % Complete Schedule variance in days (SV, days) = SV ($) ∕ Daily planned budget ; Daily planned budget = total budget / total duration Forecasted schedule variance (FSV) = SV ∕ %Complete
  • 15. 15 15 (earned value) (actual cost) (planned value) Cost baseline Cash-out SV= -1,067$ CV= +400$ Daily planned budget= 266.67 $ / day FSV= -15 Days FCV= +1500$ % Complete = 26.7% = - 4 days
  • 16. 16 What does happen at the Practical Completion? SPI = EV / PV = Performance% / Scheduled% Performance%= EV / BAC, Scheduled% = PV / BAC CPI = EV / AC Example: A project of BAC equals to $11M, has been completed with actual cost of $10M and delayed by 60D additional to the original duration of 600D. Solution: BAC = 11M, PV = 11M, AC = 10M, EV = 100%*11M CPI = EV / AC = 11M/10M = 1.1 … Below Budget (True) SPI = EV / PV = 11M/11M = 1.0 … On Schedule regardless any delay (False)
  • 17. 17 Up to day 600, all calculations look correct. Let’s calculate it: On day 600, PV = 11M, EV = 9M & AC = 8M. CPI = EV / AC = 9M/8M = 1.125 … Below Budget (True) SPI = EV / PV = 9M/11M = 0.82 … Behind Schedule (True) One month later, PV = 11M, EV = 10M & AC = 9M. CPI = EV / AC = 10M/9M = 1.11 … Below Budget (True) SPI = EV / PV = 10M/11M = 0.91 … Behind Schedule (Improving??!!) SPI vs CPI at the Contractual Completion Date
  • 18. January 27, 2021 18 Time-Based Measures: Earned Schedule SPI(time) = PT / AT AT: Actual Time of Work Performed (till Data date) (actual time expended to date (ATE) for a particular earned value) PT: Planned Time of Work Performed (originally planned duration (OD) for that earned value) PT AT
  • 19. January 27, 2021 19 Scope & Time Control Time Control: Schedule factors based on time. Forecast Time: EAC(t) = BAC(t) / SPI (t) Estimated Duration
  • 20. 20 Earned Schedule at Completion Assume the project completed at actual time (AT) of 3 years exceeded the planned duration (PT) of 2 years by one year more which is 50% duration increase, what will be the SPIcost vs Earned Schedule?? 1-Cost-based Calculation: SPI(cost) = EV/ PV=1 In case of the same scope, the earned value will equal to the planned value at the project completion, and any delay or duration variance will not show up like the project is on schedule in spite of 1 year (50%) delay. Vs 2-Time-based Calculation: Earned Schedule SPI(time) = PT/ AT= 0.67 < 1 Here the delay shows up, behind schedule , and the variance in the duration is expresses, not like the cost-based calculation results.
  • 21. 21 Earned Schedule Vs Time 0.40 0.60 0.80 1.00 1.20 1.40 0 3 6 9 12 15 18 21 24 27 30 33 36 SPI (Cost Vs Time Calculations) SPI ES Months On Schedule Ahead of Schedule Behind Schedule Behind Schedule Like On Schedule PV fixed at Planned Completion (PT) SPI(cost) = EV/ PV ES (time) = PT/ AT
  • 22. 22 Critical Path Method. estimate the minimum project duration and determine the flexibility on the logical network paths. Forward Pass. A critical path method technique for calculating the early start and early finish dates. Backward Pass. calculating the late start and late finish dates by working backward from the project end date. Total Float. The amount of time that a schedule activity can be delayed or extended from its early start date without delaying the project finish date or violating a schedule constraint. Schedule Total Float
  • 23. 23 Negative Float - The total number of days that the start or finish of an activity exceeds the time allowed. Negative float indicates a delay in the schedule. Out-of-Sequence Progress - Work completed for an activity before it is logically scheduled to occur. Schedule Update – Quick Checks
  • 24. January 27, 2021 24 Total Float Vs EVM Schedule Factors Misleading in Each: 1- Out of sequence can disturb the results of EVM schedule factors specially if the progress of critical path is different. 2- Availability of resources and resource usage in remaining works can affect the rationality of the total float specially if many paths overlapped in the remaining duration.
  • 25. 25 Some amount of knowledge brings more…… Earned Value Management Tricky or Misleading
  • 26. January 27, 2021 26 TF & SPI analysis
  • 27. 27 TF & SPI Examples At early stage of a project, Scheduled%=4%, Performance%=2% & TF = Zero. SPI = 2%/4% = 0.5 , Var.=-2% … Behind Schedule, but the delays are not on the CP At middle of the project, Scheduled%=50%, Performance%=25% & TF = -20D out of original duration 600D. SPI = 25%/50% = 0.5 , Var.=-25% … Behind Schedule, but the delays on the CP is not by a similar value (25%*600D=150D) Another scenario, Scheduled%=50%, Performance%=55% & TF = -20D out of original duration 600D. SPI = 55%/50% = 1.1 , Var.=+5% … Ahead of Schedule, but there is a delay on the CP while a high progress of non-critical
  • 28. 28 Delay Indicators 1- SPI 2- Variance 3- TF 4- CP logic 5- LOB 6- Trend analysis 0.9 = -30D -5% = -15D -50D Hard logic -60D -20D 1.1 = +30D +5% = +15D -20D Soft logic N.A. +5D/Similar Act.s Case 01 (Mid.) 0.3 = -90D -10% = -30D -20D Hard logic -40D -120D Case 03 (Early) Case 02 (Mid.)
  • 29. 29 Delay Analysis 11.2 Irrespective of which method of delay analysis is deployed, this is particularly relevant where there is a significant risk that the remaining duration projections, logic links, calendars and constraints within the baseline programme might produce anomalous results. 11. 7 Other methods, which may be reasonably deployed in particular circumstances having considered the criteria in the choice of delay analysis technique, include: project wide retrospective as- planned versus as-built analysis (i.e. not in windows), time chainage analysis, line of balance analysis, resource curve analysis, and earned value analysis. 4.14 Although the Updated Programme should be the primary tool for guiding the CA in its determination of an EOT, it should be used in conjunction with the contemporary evidence to ensure that any resulting EOT is both reasonable and consistent with the factual circumstances … (common sense and experience). This highlights the importance of this logic process, but do not expect to perfect the logic at the collapsed as-built method. However, this does not excuse the analyst from using a combination of expert judgment, common sense, and extensive input from project personnel with first-hand knowledge of the day-to-day events (witness).
  • 30. References: 1- A GUIDE TO THE PROJECT MANAGEMENT BODY OF KNOWLEDGE (PMBOK® Guide) – Fifth Edition. 2- Practice Standard for EARNED VALUE MANAGEMENT – PMI Global STANDARD. 3- EARNED VALUE Project Management - QUENWT. FILEMNING and JOEL M. KOPPELMAN. 4- Skills & Knowledge of Cost Engineering – AACE International. 5- EARNED VALUE MANAGEMENT APM GUIDELINE FOR THE UK. 6- Earned Value Professional (EVP) Certification Study Guide– AACE International. 7- CMPC Course Material – Construction Management Planning & Control (Prof.Planner). 8- Construction Project Scheduling and Control - Saleh Mubarak. 9- Project Management, Planning, and Control - Albert Lester. 10- Rita Mulcahy’s PMP Exam Prep. – Eighth edition. 11- Other books, practices/RP, posts and slides from internet.
  • 31. Study & Practice AACEI Certificate: • EVP – Earned Value Professional My Related Courses: • Project Control using EVM • Delay Analysis and Claim Submittal • Progress Reporting and Presentation 31
  • 32. Thank You Don’t Hesitate to contact…. M.Maged magedkom@gmail.com mobile : 00966-580264968