SlideShare une entreprise Scribd logo
1  sur  84
Télécharger pour lire hors ligne
BUILDING SERVICES
Aniket Khandelwal
9096871414
Email id- aniket.khandelwal@shapoorji.com
Imagine yourself in the most fabulous building in the
world. Now take away the lighting, heating and
ventilation, the lifts and escalators, acoustics,
plumbing, power supply and energy management
systems, the security and safety systems.
You are left with a cold, dark, uninhabitable shell !!!
BUILDING SERVICES
Everything inside a building which makes it safe and
comfortable to be in comes under the title of
'Building services'.
A building must do what it was designed to do - not
just provide shelter but also be an environment
where people can live, work and achieve.
Building services are what makes a building come to
life.
BUILDING SERVICES
MECHANICAL SERVICES PLUMBING SERVICES
ELECTRICAL SERVICES
MEP
CIVIL CO-ORDINATION
INTRODUCTION TO MEP
MECHANICAL SERVICES
1. HVAC – HEATING VENTILATION & AIR CONDITIONING
2. REFRIGERATION
3. FIRE PROTECTION
ELECTRICAL SERVICES
1. ELECTRICAL HT & LT POWER DISTRIBUTION
2. LIGHTING
3. EARTHING & LIGHTNING PROTECTION
4. FIRE DETECTION & ALARM SYSTEM
5. PUBLIC ADDRESS SYSTEM
6. ACCESS CONTROL SYSTEM
7. CCTV SYSTEM & MONITORING SYSTEM
8. BUILDING SECURITY SYSTEM
9. BUILDING MANAGEMENT SYSTEM
PLUMBING SERVICES
1. DOMESTIC WATER SYSTEM
2. FLUSHING WATER SYSTEM
3. SEWAGE WATER SYSTEM
4. RAIN WATER SYSTEM
5. SEWAGE TREATMENT PLANT
6. WATER TREATMENT PLANT
7. ALL PIPING & SANITARY FIXTURES THAT PROVIDE WATER FOR ANY
USE (Drinking, cooking, bathing, laundry, process, etc.)
ELECTRICAL SERVICES
CLASSIFICATION OF ELECTRICAL SYSTEMS
EXTERNAL INTERNAL
ELECTRICAL SYSTEMS
TRANSFORMERS
HT PANELS
BUSDUCTS
EXTERNAL CABLING
FLAME PROOF
ELECTRICAL
EQUIPMENTS
DG SETS
LIGHTING
ARRESTORS
SOLAR SYSTEMS
LT PANELS
DISTRIBUTION
BOARDS
EARTHING
CABLE
CONTAINMENT
LIGHTING WIRING
POWER WIRING
LT CABLING
RECEPTACLES
LUMINAIRES
CLASSIFICATION OF
ELECTRICAL SYSTEMS
DG SETS
UPS
POWER
LIGHTING PROCESS
TYPICAL ELECTRICAL SCHEMATIC
HT PANEL
HT CABLE
TRANSFORMERS
HT CABLE
LT PANELS
BUS DUCTS / CABLES
DISTRIBUTION
BOARDS
BUS DUCTS / CABLES
CAPACITOR
BANKS
CABLES
HT INCOMING SUPPLY
HT INCOMING SUPPLY
HT CABLE
METERING KIOSK
HT METERING KIOSK
HT PANEL
TRANSFORMERS
LT PANELS
DG SETS
DISTRIBUTION BOARDS
LIGHT FIXTURES
POWER SOCKETS
UPS
APFC PANEL
LOW VOLTAGE SYSTEMS
1. FIRE DETECTION & ALARM SYSTEM
2. PUBLIC ADDRESS SYSTEM
3. ACCESS CONTROL SYSTEM
4. CCTV SYSTEM & MONITORING SYSTEM
5. BUILDING SECURITY SYSTEM
6. BUILDING MANAGEMENT SYSTEM
FIRE DETECTION & ALARM SYSTEM
PUBLIC ADDRESS SYSTEM
ACCESS CONTROL SYSTEM
CCTV SYSTEM & MONITORING SYSTEM
BUILDING MANAGEMENT SYSTEM
FIRE DETECTION SYSTEM
• A FIRE ALARM SYSTEM IS NUMBER OF DEVICES WORKING TOGETHER
TO DETECT AND WARN PEOPLE THROUGH VISUAL AND AUDIO
APPLIANCES WHEN SMOKE, FIRE, CARBON MONOXIDE OR OTHER
EMERGENCIES ARE PRESENT. THESE ALARMS MAY BE ACTIVATED FROM
SMOKE DETECTORS, AND HEAT DETECTORS FIRE DETECTION & ALARM SYSTEM
PUBLIC ADDRESS SYSTEM
• A PUBLIC ADDRESS SYSTEM (PA SYSTEM) IS AN ELECTRONIC SOUND
AMPLIFICATION AND DISTRIBUTION SYSTEM WITH A MICROPHONE,
AMPLIFIER AND LOUDSPEAKERS, USED TO ALLOW A PERSON TO
ADDRESS A LARGE PUBLIC, FOR EXAMPLE FOR ANNOUNCEMENTS OF
MOVEMENTS AT LARGE AND NOISY AIR AND RAIL TERMINALS OR AT A
SPORTS STADIUM.
INTELLIGENT
ADDRESSABLE
FIRE ALARM
CONTROL
PANEL
REPEATER
PANEL
INPUT
MODULE
MCP
CONTROL
RELAY
MODULE
ADD. SMOKE
DETECTOR
FOR ROOM
ADD. SMOKE
DETECTOR
FOR CEILING
ADD. DUCT
DETECTOR
ADD. SMOKE
DETECTOR
FOR ROOM
ADD. SMOKE
DETECTOR
FOR CEILING
INPUT
MODULE
MCP
2Cx1.5 SQMM CABLE
WORKSTATION
FOR BMS SYSTEM
TO NEXT FACP
FROM PREVIOUS FACP
FIRE DETECTION SYSTEM
ACCESS CONTROL SYSTEM
• IN THE FIELDS OF PHYSICAL SECURITY AND INFORMATION
SECURITY, ACCESS CONTROL IS THE SELECTIVE RESTRICTION
OF ACCESS TO A PLACE OR OTHER RESOURCE
• ACCESS CONTROL REFERS TO SECURITY FEATURES THAT
CONTROL WHO CAN ACCESS RESOURCES IN THE OPERATING
SYSTEM. APPLICATIONS CALL ACCESS CONTROL FUNCTIONS
TO SET WHO CAN ACCESS SPECIFIC RESOURCES OR CONTROL
ACCESS TO RESOURCES PROVIDED BY THE APPLICATION.
ACCESS CONTROL SYSTEM
SCHEMATIC – ACCESS CONTROL SYSTEM
ENTRY
DOOR
EXIT
DOOR
EML EML
LAN CONNECTION
FIRE INTEGRATION
ENTRY READER WITH CONTROLLER
EMERGENCY DOOR RELEASE
EXIT PUSH BUTTON
EXIT READER
ELECTROMAGNETIC DOOR LOCK
CONTROL ROOM
WORK STATION WITH ACS SOFTWARE
LAN NETWORK
READER CUM CONTROLLER-1 READER CUM CONTROLLER-3
READER CUM CONTROLLER-2
CCTV & MONITORING SYSTEM
• CLOSED-CIRCUIT TELEVISION (CCTV), ALSO KNOWN AS VIDEO
SURVEILLANCE, IS THE USE OF VIDEO CAMERAS TO TRANSMIT A
SIGNAL TO A SPECIFIC PLACE, ON A LIMITED SET OF MONITORS
• IN INDUSTRIAL PLANTS, CCTV EQUIPMENT MAY BE USED TO OBSERVE
PARTS OF A PROCESS FROM A CENTRAL CONTROL ROOM, FOR
EXAMPLE WHEN THE ENVIRONMENT IS NOT SUITABLE FOR HUMANS.
• CCTV SYSTEMS MAY OPERATE CONTINUOUSLY OR ONLY AS REQUIRED
TO MONITOR A PARTICULAR EVENT.
CCTV SYSTEM & MONITORING SYSTEM
VIDEO WALL 4x2 CONFG.
CONTROL ROOM
VIDEO MANAGEMENT SOFTWARE &
CAMERA LICENSES
HIGH CONFIGURATION SERVER WITH
STORAGE
HIGH CONFIGURATION
CLIENT WORKSTATIONS
JOYSTICK
CONTROLLER
LAN/ OFC NETWORK POE SWITCHES
BULLET CAMERA
FIXED DOME
CAMERA
PTZ DOME CAMERA
BOX CAMERA
SCHEMATIC – CCTV & SURVEILLANCE SYSTEM
IBMS SYSTEM
• A Building Management System (BMS) or Building Automation
System (BAS) is a computer-based control system installed in
buildings that controls and monitors the building’s mechanical and
electrical equipment
• They help you plan operations and assess performance; make
operation easier; improve building comfort, enhance safety, improve
efficiency, save energy, and protect your assets.
• Their function is to control, monitor and optimize building services,
such as heating, ventilation, air conditioning, lighting, alarm systems
and certain electrical appliances. BUILDING MANAGEMENT SYSTEM
BMS DISPALY
BMS SEVER WITH BMS SOFTWARE &
LICENSE
TCP/IP NETWORK
DDC CONTROLER
WITH 3RD PARTY
INTEGRATION
DDC CONTROLER
WITH 3RD PARTY
INTEGRATION
HVAC SYSTEM
VENTILATION & EXHUST SYSTEMS
ELECTRICAL DISTRIBUTION SYSTEM
FIRE FIGHTING SYTEMS
PHE SYSTEMS
ELEVATOR SYSTEMS
FIELD DEVICES
LASER PRINTER
DDC CONTROLER
WITH 3RD PARTY
INTEGRATION
DDC CONTROLER
WITH 3RD PARTY
INTEGRATION
DDC CONTROLER
WITH 3RD PARTY
INTEGRATION
SCHEMATIC – IBMS SYSTEM
HVAC – HEATING VENTILATION & AIR CONDITIONING
HVAC – HEATING VENTILATION & AIR CONDITIONING
WHAT IS TR - TON OF REFRIGERATION
1 TR IS AMOUNT OF HEAT EXTRACTED FROM
ATMOSPHERE FOR MELTING 1 METRIC TONNE OF ICE IN 24
HOURS.
1 TR = BTU/HR
1 TR = 3025 KCAL/HR
FUNCTIONS OF HVAC
• CONTROL OF AIR TEMPERATURE
• CONTROL OF MOISTURE CONTENT IN THE AIR
• PROPER AIR MOVEMENT
• TO HOLD AIR CONTAMINATION WITHIN
ACCEPTABLE LIMITS
TYPES OF HVAC SYSTEMS
AIR CONDITIONING
NON DUCTED PRODUCTS DUCTABLE SYSTEMS
SPLIT AIR CONDITIONING WINDOW AIR CONDITIONING PACKAGED AIR CONDITIONING CENTRAL PLANT
FLOOR
MOUNTED
WALL
MOUNTED
CEILING
MOUNTED
EXPOSED
TYPE
CASSETTE
TYPE
HIDE AWAY
TYPE
FLOOR STANDING PACKAGED AC
AIR COOLED
DUCTABLE SPLITS
AIR COOLED
WATER
COOLED
DX SYSTEM
CHILLED WATER
SYSTEM
VAPOUR
COMPRESSION UNIT
VAPOUR
ABSORPTION UNIT
RECIPROCATING
UNITS AIR &
WATER COOLED
CENTRIFUGAL
UNITS WATER
COOLED
SCREW TYPE
UNITS AIR &
WATER COOLED
RECIPROCATING
UNITS AIR &
WATER COOLED
CENTRIFUGAL
UNITS WATER
COOLED
SCREW TYPE
UNITS AIR &
WATER COOLED
FIRE PROTECTION SYSTEM
WHAT IS FIRE ?
• An exothermic reaction resulting from combination of heat fuel
and oxygen.
• Fire involves rapid oxidation at high temperatures
accompanied by the evolution of highly heated gaseous
products of combustion and emission of visible and invisible
radiation.
• Initiation of fire requires combustible materials, oxygen and an
energy source (heat) to provide ignition. Three components -
fuel , oxygen & heat are referred as the fire triangle
CLASSIFICATION OF FIRE
• Class-A - Fires involving ordinary combustible materials like wood, paper, textiles, rubber
etc.
• Class-B -Fires involving flammable liquids or liquefiable solids, such as oils, solvents,
petroleum products, paints, varnishes etc.
• Class-C - Fire involving gases or liquefied gases under pressure for eg. LPG, Hydrogen
etc.
• Class-D Fire involving combustible metal such as Magnesium, sodium Zinc, Titanium etc.
PRINCIPLE OF FIRE EXTINCTION
• Starvation - Removing or blanketing the fuel
• Smothering - Cutting off the oxygen supply
• Cooling - Removing heat from the fire.
FIRE FIGHTING SYSTEM
• FIRE WATER RESERVOIR
• PUMPING UNITS
• FIRE WATER NETWORK
• FIRE FIGHTING HYDRANT SYSTEM
• FIRE FIGHTING SPRINKLER SYSTEM
• FIRE PROTECTION EQUIPMENT
FIRE WATER RESERVOIR
PUMPING UNITS
FIRE WATER NETWORK
FIRE FIGHTING HYDRANT SYSTEM
FIRE FIGHTING SPRINKLER SYSTEM
FIRE PROTECTION EQUIPMENT
MUNCIPAL WATER SUPPLY TANKER WATER / BORE WELL
FIRE TANK
HYDRANT SRINKLER
DP HP J
SP
J
B
DP – DIESEL PUMP
HP – HYDRANT PUMP
SP – SPRINKLER PUMP
J – JOCKEY PUMP
B – BOOSTER PUMP
EXTERNAL HYDRANT INTERNAL HYDRANT
BRIDGE INLET
TYPICAL FIRE PROTECTION SYSTEM SCHEMATIC
PUBLIC HEALTH ENGINEERING - PHE
DIFFERENT AREAS OF PHE
• SANITARY AND CP FITTINGS
• HOT & COLD WATER SUPPLY SYSTEM
• DRAINAGE & SEWAGE SYSTEM
• EXTERNAL WATER SUPPLY
• SEWAGE TREATMENT PLANT
• EXTERNAL SEWER NETWORK AND CONNECTION TO
SEWAGE TREATMENT PLANT/ MUNICIPAL NETWORK
What is a plumbing system
THE PLUMBING SYSTEM IS REALLY MADE UP OF TWO SYSTEMS:
• The supply system that brings in fresh water
• The drain-waste-vent system that takes out used water and sewage
• THE DRAIN-WASTE-VENT SYSTEM ALSO LETS AIR IN AND WASTE GASES OUT.
• BETWEEN THESE TWO SYSTEMS ARE THE FIXTURES (SINKS, TUBS, TOILETS, AND SO ON).
SCHEMATIC– PHE (WATER SUPPLY)
MUNCIPAL WATER SUPPLY TANKER WATER / BORE WELL
FIRE TANK
RAW WATER TANK
WTP
DOMESTIC WATER TANK
TOILETS & PANTRY/ KITCHEN
OVERFLOW FROM FIRE TANK
SCHEMATIC– PHE (SEWAGE & FLUSHING WATER)
SEWAGE FROM TOILETS
INSPECTION CHAMBER
STP
FLUSHING WATER TANK
FLUSHING WATER FOR TOILETS
PANTRY/ KITCHEN
GREASE TRAP
DISPOSAL TO MUNICIPAL LINE
TREATED WATER
SCHEMATIC– STP (MBBR )
P
TUBE DECK
MEDIA
DUAL
MEDIA
FILTER
ACTIVAT
ED
CARBON
FILTER
P EXCESS SLUDGE
SCREEN
CHAMBER
OIL & GREASE
TRAP EQUILISATION
TANK
TUBE SETTLER
TANK
FAB REACTOR CHLORINE
DOSING TANK
CHLORINE
DOSING
P
TREATED
WATER TANK
SLUDGE DISPOSAL TANK
TREATED WATER FOR USE
SEWAGE INLET
SLUDGE
DISPOSAL
BACKWASH
LINE
SQUEEZED
WATER
PIPING/ CONTAINMENT CATEGORISED
• HORIZONTAL PIPELINE
• VERTICAL PIPELINE
MEP SERVICE LINES - CATEGORISED
PIPELINE
CATEGORIES
HORIZONTAL
PIPELINE
VERTICAL
PIPELINE
EMBEDDED
PIPELINE
EXPOSED PIPELINE
Plumbing
Electrical
Telecommunications
Fire Protection
HVAC
Water Supply, Waste Water & Sewage, Vent,
Rainwater Recycling
Bus-ducts, Cable Containments, Generator
Exhaust & Cooling water Piping
CCTV, Network, Audio, Telecommunications
Fire Protection water Supply, Sprinklers
Air Duct, chilled water & Condensate water
(Supply & Return)
BEAM WEB
OPENINGS
UNDER
BEAMS
Lighting Conduits, Telecommunications
Conduits, Fire Alarm Conduits
Water Supply, Lighting Conduits, Waste
Water, Sewage, Fire Alarm & Fire Sprinkler
NEXT PAGE
PIPELINE LAYOUT CATEGORIES OF MEP SYSTEM
PIPELINE
CATEGORIES
VERTICAL
PIPELINE
EMBEDDED PIPELINE
(WITHIN PARTITION)
EXPOSED PIPELINE
(SHAFTS)
Plumbing
Electrical
Telecommunications
Fire Protection
HVAC
Water Supply, Waste Water & Sewage, Vent
Bus-ducts, Cable Containments, Generator
Exhaust & Cooling water Piping
CCTV, Network, CATV, Audio,
Telecommunications
Fire Protection water Supply, Sprinklers
Chilled water & Condensate water (Supply &
Return)
Plumbing
Electrical
Telecommunications
Water Supply, Waste Water & Sewage, Vent
Lighting & Sockets
CCTV, Network, CATV, Audio,
Telecommunications
PIPELINE LAYOUT CATEGORIES OF MEP SYSTEM
HORIZONTAL
PIPELINE
FA/VA, BMS
& Security
containment
LV Cable Trays
Lighting &
Power Trunking
Blockwork Walls
Slab
HV Ladder Rack
Soffit
Fire Protection
Pipe Work
Incoming
Water Mains
Drainage Pipe
Duct Work
Duct Work
Branch
Chilled
Water Pipes
• Typically a MEP Contractor each install their own supports from the
soffit.
• Followed by water mains, drainage and fire protection pipe work.
Generally MEP services that would not require any further access
once they had been installed, tested and insulated.
• Followed by the ductwork and its branches to adjacent rooms,
which would require testing and insulation.
• Then the chilled water pipework, which also branches off to
adjacent rooms and needs to be accessible.
• Electrical containment is always the lowest and final service to be
installed. Its completion and subsequent cable installation will be
dependent on the mechanical services completion.
• The coordinated installation sequence needs to prioritize the
earliest release for HV & LV cable installations.
MEP – TYPICAL SECTION OF CORRIDOR
CIVIL –MEP COORDINATION
CIVIL MEP
Foundation for MEP Heavy Equipment
Sleeves For MEP Services Wall Penetration
Note : It is very Important to Close this Sleeves with Fire sealant Post
Installation of Service Lines
Services within Sub-Structure of Building
Services before casting of Floor Slab
Services before casting of RCC Walls
Plaster after laying of wall services
Cut-outs for Pulling of Cables
Ceiling MEP Services before False Ceiling
Ceiling MEP Services before False Ceiling
Ceiling MEP Services before False Ceiling
Toilet Sunk drainage
MEP INTERFACING – PROBLEMS ASSOCIATED
According to the characteristics of the problem, integration requirements,
and construction necessities, the Interface Problems is divided in following eight classifications.
• Coordination with civil structure
• Safety aspects
• Functionality
• Constructability
• Economy
• Efficiency
• Expandability
• Maintainability
• This refers to the process of installing Services, which must be
well coordinated to embed the horizontal pipes and vertical
sleeves in advance.
• Electrical pipes, monitor control pipes, and vertical sleeves of
sewage pipes from the floor slab must be installed prior to slab
grouting.
• The work involving the first completed concrete mat for moisture
protection and vibration isolators must be executed in
conjunction with the embedded sleeves and architectural
construction works
COORDINATION WITH CIVIL STRUCTURE
• Safety refers to safety considerations during
installation.
• For example, safety is required to prevent
hazards such as a water pipe leakage if a water
pipe lies above an electrical pipe
SAFETY ASPECTS
• Functionality refers to ensuring that the function of
pipes is fully exploited while complying with building
codes.
• For example, drainage slopes and routes must be
taken into consideration for proper drainage of waste
water.
• The installation of fire protection equipment and
piping must be arranged prior to other systems in
order for the entire fire protection system to comply
with fire codes and fire protection permit drawings.
Consequently, this has an impact on passing the fire
protection inspection and obtaining the occupancy
permits.
FUNCTIONALITY
Constructability represents the factors influencing the sequence of installation. The conflicts can be
categorized as follows:
• Conflict of equipment in a space - Because of the crowded space, the routing and sequence of installation for
large equipment must be checked first.
• Conflict of pipeline in a space - Conditions for stacking and interlacing pipelines causes difficulty in installation
and maintenance due to over-crowded spaces and lack of advance coordination
• Crowded installation - Conflicts within the installation space, idle laborers, and poor installation quality can result
from problems such as crowded spaces or multiple workers operating simultaneously at a single site.
Furthermore, the attitude of “first come first win” or “first do first win” causes conflict in the arrangement of
pipelines.
• Pipe materials and dimensions - Installation suffers if the diameter of the pipe is oversized or if the material of
the pipe is inflexible or too rigid to be easily cut or molded. If these kinds of materials are applied for the works,
they should be installed earlier to prevent conflicts
• Installation of pipeline tiers - When the pipeline layout exceeds two layers, pipes
CONSTRUCTABILITY
• Economy refers to the cost estimates associated with
integration, which can increase due to a lack of
coordination.
• For instance, re-routing a pipeline increases the
lengths of the pipeline and associated costs.
ECONOMY
• Efficiency refers to a lack of integration causing descending
pressure and consuming capacity, which influences the basic
function of MEP systems.
• Additionally, venting conditions around equipment influences
equipment functionality, and should be noted during the
integration of the interface.
EFFICIENCY
Expandability refers to the lifecycle of the facility
causing a demand for the expansion of pipelines due to
the changes in usage or upgrades to the facility.
This increasing demand requires consideration prior to
the installation phase to ensure space for future
expansion of the pipeline.
EXPANDABILITY
• Maintainability refers to the convenience of
maintenance during the operation phase when
arranging the pipeline.
• Maintenance space and operation route must be
taken into consideration.
MAINTAINABILITY
• The major MEP installation projects require the identification of separate arrangements for
HVAC, power supply, plumbing, fire protection, telecommunications, and other related
systems.
• Specialized consultants and contractors design and construct these systems. Currently,
according to technical specifications, each specialty or trade subcontractor is assigned the
responsibility of integrating MEP systems.
• Coordination of mechanical and electrical systems to detail their configuration provides a
major challenge for complex building and industrial projects
• The knowledge required for MEP integration must be integrated to our System because
specialty subcontractors of each system perform tasks individually, proposing a layout
according to their own needs, leading to the fragmentation of MEP.
MEP INTEGRATION
• Improper integration at the equipment/pipeline interface results in interference and
inappropriate sequence of jobs during installation can negatively influence the entire project.
• Moreover, the complete integration of the interface reduces the numbers of changes in the
design, decreases the work requiring demolition, addresses problems resulting from
installation error, and increases the overall construction quality of projects.
• Hence, the purpose of integrating the interface is to recognize problems, resolve conflicts,
and perfect the layout of the system for these mechanisms to serve their functions fully.
MEP INTEGRATION
The discussed eight criteria are considered as MEP integration items because they are closely related to considerations of
installation integration.
To facilitate comparison, let us subcategorized these eight criteria according to three levels INTEGRATION SEQUENCING
The three levels are described as follows:
1. Basic Requirements and Coordination with Civil Structure Works
Functionality of the 8 criteria fall under this first level of the integration sequencing.
2. Construction Requirements
This is a second level integration task, comprising the evaluation of installation difficulty, problems associated with
the installation of circulation interfaces, and the arrangement of sequencing
3. Cost and Operations Requirements
This refers to the examination of the price of installation, cost-benefit ratio, and factors related to maintenance and
expansion during the life circle of the facility.
INTEGRATION SEQUENCING
MEP
INTEGRATION
SEQUENCING
LEVEL 1
Basic
Requirements
&
Coordination
with
Civil
&
Structure
Works
SAFETY
FUNCTIONALITY
COORDINATION
Supply Side - Separate High Voltage Equipment's from water Pumps
Trans. Side - Separate Water Pipes & Electrical Conduits from
telecommunication cable.
Place Electric Conduits above water Pipes to avoid water leaking
over conduits
Term. Side - Keep Safe Distance between sensors & Vents to avoid sensing
interference
Supply Side - Comply with Fire Regulations for selection of Equipment.
Separate Fire Pumps from Generators.
Isolate Oxygen Tanks from Fire Protected Areas
Trans. Side - Consider Slopes For Gravity Drainages
Comply with Fire Regulations for Pipes
Term. Side - Keep Safe Distance between HVAC Vents, intakes, Fire Protection
sensors & Sprinklers
Supply Side - First Set Equipment Concrete Foundations.
Trans. Side - Pre-bury and layout Pipes on Slabs
Openings on beams & Partitions must match Pipe Positions
Equipment mobilization & Installation cannot interfere with
partitions construction
Term. Side - Installation for illumination lights, vents, fire hydrants must be
consistent with civil construction
Basic Requirements and Coordination with Civil Structure Works
Construction Requirements
MEP
INTEGRATION
SEQUENCING
LEVEL 2
CONSTRUCTION
REQUIREMENTS
CONSTRUCTIBILITY
Supply Side - Consider Movement Circulation & Space For Large Equipment
Layouts
Trans. Side - Maintain Sufficient Orientation Space.
Avoid Conflicts & Multi Layers Overlap when Pipeline Space Is Not
enough
Consider Pipeline Sizes & Material Flexibility
Install Top Layers Pipelines first
Term. Side - Check Whether Terminal Side Equipment's are obscured by other
equipment that causes Conflicts
Check Ceiling Heights & Match Ceiling horizontal layouts
MEP
INTEGRATION
SEQUENCING
LEVEL 3
Cost
and
Operations
Requirements
ECONOMY
EFFICIENCY
EXPANDIBILITY
Supply Side - Keep Adequate Distance between large equipment
Centralised Equipment design is generally more economic then
scattered formats
Equipment Position need to be close to load centre
Trans. Side - Apply Shortest, Closest Route Principle to pipeline layouts.
Term. Side - Keep adequate distance among terminal side equipment.
Maintain Consistency with Ceiling Or Partition Plans
Supply Side - Consider Surrounding Environmental Factors & Ventilation
Problems for Major Equipment
Trans. Side - Straight Pipes are preferable. Avoid Bend in Pipes
Term. Side - Keep Distance between HVAC Vents & intakes
Supply Side - Reserve Space for future Equipment Expansion & Possible Flexible
Adjustments
Trans. Side - Reserve Space for Future Pipeline Distribution
Term. Side - Consider Reservation, disbanding, flexible adjustments
Cost and Operations Requirements
MAINTAINABILITY CONSIDER MAINTAINANCE & MANAGEMENT SPACE & MOVEMENT LINES
STEPS TO DEVELOP WORKSTATION AREAS
STEP 1 – Laying of Under Floor Services
• Slab surface to be uniform for raceway laying
• FFL to be decided prior to any installations
• Raceway marking to be provided as per
approved workstation layout
• Placing the Raceway & Junction Boxes on the
floor.
• Clamping to be done on the floor end cover
the Junction Boxes by thermocoal.
• Care to be taken for JB’s during concreting
• After concrete thermocoals to be removed
from JB’s
STEP 2 – SCREEDING/ IPS WORKS
STEP 3 – CEILING TENDON MARKING
STEP 4 – MEP FIRST FIX
LV CABLES-1
FIRE LINE- 2
DUCTS-3
ELECTRICAL CONDUITS-1
STEP 4 – MEP FIRST FIX - Inclusions
1. Conduit to be installed on ceiling and wall as per
approved point wiring.
2. Clamps to be fixed after proper drilling on ceiling (Tendon
marking to be avoided.)
3. LV Cables to installed as per Layout with clamping
4. Parallel fire line works to start.
5. For Fire line installation area to be surveyed
6. Main header line to be installed with clamps (Clamps to
be provided as per NFPA)
7. Sub header and branch pipes to be installed at ground
level and overhauled to ceiling
8. Clamps to be provided
9. After installation of sub header welding to the main
header to be welded
10. All welding to be properly executed with absolute perfection.
11. All pipes to be surface cleaned, primer applied and painting
done in RED.
12. Hydro testing to be conducted at 1.5 times the Pump
pressure
13. Duct to be fabricated in-situ with profiling
14. Hangers to be installed as per duct passage and tendon
markings to be taken care of.
Header duct to be installed as per BOD
15. Branches to be added to main header as per BOD
16. Sealing to be done so that no gaps are observed
17. Light test to be conducted before ceiling clearance
STEP 4 – MEP FIRST FIX - Requirements
• Civil structure to be ready
• Tendon markings to be provided
• Proper cutouts for services bypass
• FFL level to be decided prior to any installations
• Cutouts to be mentioned in MEP penetration plan
• BOP, BOD, BOCT to be exact as per ceiling height
STEP 5 – MEP FIRST FIX - Wall
REQUIREMENTS FOR WALL FIX:
1. ROUTING TO BE MENTIONED.
2. SURFACE OR CONCEALED TO BE MENTIONED
3. INTERCONNECTIVITY OF ROOMS THROUGH CONDUITS/
FLEXIBLE TO BE DECIDED.
STEP 6 – Floor Tiling Works
STEP 7 – MEP SECOND FIX
What is done during 2nd fix?
1. Fire- Flexible and sprinklers are fixed
2. HVAC- Spigot are fixed
3. Electrical- All wiring to be done in conduits
4. LV- Above ceiling detector boxes and related
cabling
STEP 8 – GRIDWORK FOR CEILING
STEP 9 – MEP FINAL FIX
STEP 9 – MEP FINAL FIX - Requirements
• BOD, BOP, BOC should be inline with False ceiling levels
• Grid ceiling gap should be maintained as per fixtures.
• Special attention required for any gravity flow line such as drains
What is done in 3rd Fix?
1. Fire- Sprinklers are fixed on ceiling
2. HVAC- Grills/ Diffusers are fixed on grid of ceiling
3. Electrical- Light Fixtures/ Switch sockets on ceiling and wall
4. LV- All LV Fixtures such as detectors/ RI/ Hooters/ CR/ Speakers on wall/ceiling/
doors
STEP 10 – Cable Pulling & Area Clearance
STEP 11 – Final Ceiling Works
STEP 11 – Final Fixtures
STEP 12 – Workstation Installation
Following activities proceed after workstation
installation works:
1. All Data cables to be brought to surface and Data
plates to be fixed
2. All UPS/ RAW power wiring works to surface and
switch plates are fixed
3. All Plates are tagged
4. JB opening to close using SS/ Aluminum sheet
Thank You

Contenu connexe

Tendances (20)

Laurie baker..
Laurie baker..Laurie baker..
Laurie baker..
 
Low Cost Housing
Low Cost HousingLow Cost Housing
Low Cost Housing
 
Intelligent building library study
Intelligent building library studyIntelligent building library study
Intelligent building library study
 
Kerala vernacular architecture
Kerala vernacular architectureKerala vernacular architecture
Kerala vernacular architecture
 
Csir -STRUCTURAL ENGINEERING RESEARCH CENTRE (SERC) CHENNAI,INDIA.
Csir -STRUCTURAL ENGINEERING RESEARCH CENTRE (SERC) CHENNAI,INDIA.Csir -STRUCTURAL ENGINEERING RESEARCH CENTRE (SERC) CHENNAI,INDIA.
Csir -STRUCTURAL ENGINEERING RESEARCH CENTRE (SERC) CHENNAI,INDIA.
 
Ar.Ananth raje
Ar.Ananth rajeAr.Ananth raje
Ar.Ananth raje
 
Architecture in Kashmir
Architecture in KashmirArchitecture in Kashmir
Architecture in Kashmir
 
Vernacular architecture approaches and concepts
Vernacular architecture approaches and conceptsVernacular architecture approaches and concepts
Vernacular architecture approaches and concepts
 
Kerala architecture
Kerala architectureKerala architecture
Kerala architecture
 
Laurie baker.edited
Laurie baker.editedLaurie baker.edited
Laurie baker.edited
 
Dlf the crest gurgaon
Dlf the crest gurgaonDlf the crest gurgaon
Dlf the crest gurgaon
 
Uttam
UttamUttam
Uttam
 
Hollow Floor Slab
Hollow Floor SlabHollow Floor Slab
Hollow Floor Slab
 
Laurie baker
Laurie bakerLaurie baker
Laurie baker
 
Laurie baker
Laurie bakerLaurie baker
Laurie baker
 
PREVI HOUSING
PREVI HOUSINGPREVI HOUSING
PREVI HOUSING
 
Laurie Baker
Laurie BakerLaurie Baker
Laurie Baker
 
Architect Laurie Baker
 Architect Laurie Baker Architect Laurie Baker
Architect Laurie Baker
 
Vernacular architecture of bohra houses
Vernacular architecture of bohra housesVernacular architecture of bohra houses
Vernacular architecture of bohra houses
 
Vinay M
Vinay MVinay M
Vinay M
 

Similaire à Building vertival transport.pdf

Bs ii-presentation
Bs ii-presentationBs ii-presentation
Bs ii-presentationLee Chun Yee
 
UNIT-V FIRE SAFETY INSTALLATION
UNIT-V    FIRE SAFETY INSTALLATIONUNIT-V    FIRE SAFETY INSTALLATION
UNIT-V FIRE SAFETY INSTALLATIONkarthi keyan
 
Building Services II Presentation Slides
Building Services II Presentation SlidesBuilding Services II Presentation Slides
Building Services II Presentation Slidesashleyyeap
 
Bs ii presentation slides
Bs ii   presentation slidesBs ii   presentation slides
Bs ii presentation slidesArissa Loh
 
L3 Unit 11 LO 3 Fire Systems Master .pptx
L3 Unit 11 LO 3 Fire Systems Master .pptxL3 Unit 11 LO 3 Fire Systems Master .pptx
L3 Unit 11 LO 3 Fire Systems Master .pptxMarkWootton11
 
BasicAirportOperation - TerminalFacilities&Care
BasicAirportOperation - TerminalFacilities&CareBasicAirportOperation - TerminalFacilities&Care
BasicAirportOperation - TerminalFacilities&CareAiDY
 
Fire safety in hospitals
Fire safety in hospitalsFire safety in hospitals
Fire safety in hospitalsKomal Gupta
 
BASICS OF FIRE PROTECTION SYSTEM, HYDRANT SYSTEM.ppt
BASICS OF FIRE PROTECTION SYSTEM, HYDRANT SYSTEM.pptBASICS OF FIRE PROTECTION SYSTEM, HYDRANT SYSTEM.ppt
BASICS OF FIRE PROTECTION SYSTEM, HYDRANT SYSTEM.pptRajeshKannan579711
 
Bs ii presentation finale
Bs ii presentation finaleBs ii presentation finale
Bs ii presentation finaleTee Joanne
 
Fire safety of Bank Premises
Fire safety of Bank PremisesFire safety of Bank Premises
Fire safety of Bank PremisesRanjeet Kumar
 
BUILDING SERVICE GROUP ASSIGNMENT
BUILDING SERVICE GROUP ASSIGNMENTBUILDING SERVICE GROUP ASSIGNMENT
BUILDING SERVICE GROUP ASSIGNMENTXinYee Khoo
 
BS2 group assignment
BS2 group assignment BS2 group assignment
BS2 group assignment jk tan
 
Bs powerpoint slides
Bs powerpoint slidesBs powerpoint slides
Bs powerpoint slideslohwenjun
 
Indoor environmental quality
Indoor environmental qualityIndoor environmental quality
Indoor environmental qualityjeff_ranson
 
Indoor environmental quality - greg allen
Indoor environmental quality - greg allenIndoor environmental quality - greg allen
Indoor environmental quality - greg allenToronto 2030 District
 

Similaire à Building vertival transport.pdf (20)

Bs ii-presentation
Bs ii-presentationBs ii-presentation
Bs ii-presentation
 
UNIT-V FIRE SAFETY INSTALLATION
UNIT-V    FIRE SAFETY INSTALLATIONUNIT-V    FIRE SAFETY INSTALLATION
UNIT-V FIRE SAFETY INSTALLATION
 
UNIT-5.pptx
UNIT-5.pptxUNIT-5.pptx
UNIT-5.pptx
 
Building Services II Presentation Slides
Building Services II Presentation SlidesBuilding Services II Presentation Slides
Building Services II Presentation Slides
 
Bs ii presentation slides
Bs ii   presentation slidesBs ii   presentation slides
Bs ii presentation slides
 
L3 Unit 11 LO 3 Fire Systems Master .pptx
L3 Unit 11 LO 3 Fire Systems Master .pptxL3 Unit 11 LO 3 Fire Systems Master .pptx
L3 Unit 11 LO 3 Fire Systems Master .pptx
 
BasicAirportOperation - TerminalFacilities&Care
BasicAirportOperation - TerminalFacilities&CareBasicAirportOperation - TerminalFacilities&Care
BasicAirportOperation - TerminalFacilities&Care
 
Fire safety in hospitals
Fire safety in hospitalsFire safety in hospitals
Fire safety in hospitals
 
MEP & Construction Package
MEP & Construction PackageMEP & Construction Package
MEP & Construction Package
 
BASICS OF FIRE PROTECTION SYSTEM, HYDRANT SYSTEM.ppt
BASICS OF FIRE PROTECTION SYSTEM, HYDRANT SYSTEM.pptBASICS OF FIRE PROTECTION SYSTEM, HYDRANT SYSTEM.ppt
BASICS OF FIRE PROTECTION SYSTEM, HYDRANT SYSTEM.ppt
 
Bs ii presentation finale
Bs ii presentation finaleBs ii presentation finale
Bs ii presentation finale
 
Firefighting & HVAC.pdf
Firefighting & HVAC.pdfFirefighting & HVAC.pdf
Firefighting & HVAC.pdf
 
Fire safety of Bank Premises
Fire safety of Bank PremisesFire safety of Bank Premises
Fire safety of Bank Premises
 
BUILDING SERVICE GROUP ASSIGNMENT
BUILDING SERVICE GROUP ASSIGNMENTBUILDING SERVICE GROUP ASSIGNMENT
BUILDING SERVICE GROUP ASSIGNMENT
 
Fire safety
Fire safety Fire safety
Fire safety
 
PWD training
PWD trainingPWD training
PWD training
 
BS2 group assignment
BS2 group assignment BS2 group assignment
BS2 group assignment
 
Bs powerpoint slides
Bs powerpoint slidesBs powerpoint slides
Bs powerpoint slides
 
Indoor environmental quality
Indoor environmental qualityIndoor environmental quality
Indoor environmental quality
 
Indoor environmental quality - greg allen
Indoor environmental quality - greg allenIndoor environmental quality - greg allen
Indoor environmental quality - greg allen
 

Dernier

(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsRussian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdfankushspencer015
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfKamal Acharya
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdfKamal Acharya
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...ranjana rawat
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 

Dernier (20)

(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsRussian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 

Building vertival transport.pdf

  • 1. BUILDING SERVICES Aniket Khandelwal 9096871414 Email id- aniket.khandelwal@shapoorji.com
  • 2. Imagine yourself in the most fabulous building in the world. Now take away the lighting, heating and ventilation, the lifts and escalators, acoustics, plumbing, power supply and energy management systems, the security and safety systems. You are left with a cold, dark, uninhabitable shell !!! BUILDING SERVICES
  • 3. Everything inside a building which makes it safe and comfortable to be in comes under the title of 'Building services'. A building must do what it was designed to do - not just provide shelter but also be an environment where people can live, work and achieve. Building services are what makes a building come to life. BUILDING SERVICES
  • 4. MECHANICAL SERVICES PLUMBING SERVICES ELECTRICAL SERVICES MEP CIVIL CO-ORDINATION INTRODUCTION TO MEP
  • 5. MECHANICAL SERVICES 1. HVAC – HEATING VENTILATION & AIR CONDITIONING 2. REFRIGERATION 3. FIRE PROTECTION
  • 6. ELECTRICAL SERVICES 1. ELECTRICAL HT & LT POWER DISTRIBUTION 2. LIGHTING 3. EARTHING & LIGHTNING PROTECTION 4. FIRE DETECTION & ALARM SYSTEM 5. PUBLIC ADDRESS SYSTEM 6. ACCESS CONTROL SYSTEM 7. CCTV SYSTEM & MONITORING SYSTEM 8. BUILDING SECURITY SYSTEM 9. BUILDING MANAGEMENT SYSTEM
  • 7. PLUMBING SERVICES 1. DOMESTIC WATER SYSTEM 2. FLUSHING WATER SYSTEM 3. SEWAGE WATER SYSTEM 4. RAIN WATER SYSTEM 5. SEWAGE TREATMENT PLANT 6. WATER TREATMENT PLANT 7. ALL PIPING & SANITARY FIXTURES THAT PROVIDE WATER FOR ANY USE (Drinking, cooking, bathing, laundry, process, etc.)
  • 9. CLASSIFICATION OF ELECTRICAL SYSTEMS EXTERNAL INTERNAL ELECTRICAL SYSTEMS TRANSFORMERS HT PANELS BUSDUCTS EXTERNAL CABLING FLAME PROOF ELECTRICAL EQUIPMENTS DG SETS LIGHTING ARRESTORS SOLAR SYSTEMS LT PANELS DISTRIBUTION BOARDS EARTHING CABLE CONTAINMENT LIGHTING WIRING POWER WIRING LT CABLING RECEPTACLES LUMINAIRES CLASSIFICATION OF ELECTRICAL SYSTEMS
  • 10. DG SETS UPS POWER LIGHTING PROCESS TYPICAL ELECTRICAL SCHEMATIC HT PANEL HT CABLE TRANSFORMERS HT CABLE LT PANELS BUS DUCTS / CABLES DISTRIBUTION BOARDS BUS DUCTS / CABLES CAPACITOR BANKS CABLES HT INCOMING SUPPLY HT INCOMING SUPPLY HT CABLE METERING KIOSK HT METERING KIOSK HT PANEL TRANSFORMERS LT PANELS DG SETS DISTRIBUTION BOARDS LIGHT FIXTURES POWER SOCKETS UPS APFC PANEL
  • 11. LOW VOLTAGE SYSTEMS 1. FIRE DETECTION & ALARM SYSTEM 2. PUBLIC ADDRESS SYSTEM 3. ACCESS CONTROL SYSTEM 4. CCTV SYSTEM & MONITORING SYSTEM 5. BUILDING SECURITY SYSTEM 6. BUILDING MANAGEMENT SYSTEM FIRE DETECTION & ALARM SYSTEM PUBLIC ADDRESS SYSTEM ACCESS CONTROL SYSTEM CCTV SYSTEM & MONITORING SYSTEM BUILDING MANAGEMENT SYSTEM
  • 12. FIRE DETECTION SYSTEM • A FIRE ALARM SYSTEM IS NUMBER OF DEVICES WORKING TOGETHER TO DETECT AND WARN PEOPLE THROUGH VISUAL AND AUDIO APPLIANCES WHEN SMOKE, FIRE, CARBON MONOXIDE OR OTHER EMERGENCIES ARE PRESENT. THESE ALARMS MAY BE ACTIVATED FROM SMOKE DETECTORS, AND HEAT DETECTORS FIRE DETECTION & ALARM SYSTEM PUBLIC ADDRESS SYSTEM • A PUBLIC ADDRESS SYSTEM (PA SYSTEM) IS AN ELECTRONIC SOUND AMPLIFICATION AND DISTRIBUTION SYSTEM WITH A MICROPHONE, AMPLIFIER AND LOUDSPEAKERS, USED TO ALLOW A PERSON TO ADDRESS A LARGE PUBLIC, FOR EXAMPLE FOR ANNOUNCEMENTS OF MOVEMENTS AT LARGE AND NOISY AIR AND RAIL TERMINALS OR AT A SPORTS STADIUM.
  • 13. INTELLIGENT ADDRESSABLE FIRE ALARM CONTROL PANEL REPEATER PANEL INPUT MODULE MCP CONTROL RELAY MODULE ADD. SMOKE DETECTOR FOR ROOM ADD. SMOKE DETECTOR FOR CEILING ADD. DUCT DETECTOR ADD. SMOKE DETECTOR FOR ROOM ADD. SMOKE DETECTOR FOR CEILING INPUT MODULE MCP 2Cx1.5 SQMM CABLE WORKSTATION FOR BMS SYSTEM TO NEXT FACP FROM PREVIOUS FACP FIRE DETECTION SYSTEM
  • 14. ACCESS CONTROL SYSTEM • IN THE FIELDS OF PHYSICAL SECURITY AND INFORMATION SECURITY, ACCESS CONTROL IS THE SELECTIVE RESTRICTION OF ACCESS TO A PLACE OR OTHER RESOURCE • ACCESS CONTROL REFERS TO SECURITY FEATURES THAT CONTROL WHO CAN ACCESS RESOURCES IN THE OPERATING SYSTEM. APPLICATIONS CALL ACCESS CONTROL FUNCTIONS TO SET WHO CAN ACCESS SPECIFIC RESOURCES OR CONTROL ACCESS TO RESOURCES PROVIDED BY THE APPLICATION. ACCESS CONTROL SYSTEM
  • 15. SCHEMATIC – ACCESS CONTROL SYSTEM ENTRY DOOR EXIT DOOR EML EML LAN CONNECTION FIRE INTEGRATION ENTRY READER WITH CONTROLLER EMERGENCY DOOR RELEASE EXIT PUSH BUTTON EXIT READER ELECTROMAGNETIC DOOR LOCK CONTROL ROOM WORK STATION WITH ACS SOFTWARE LAN NETWORK READER CUM CONTROLLER-1 READER CUM CONTROLLER-3 READER CUM CONTROLLER-2
  • 16. CCTV & MONITORING SYSTEM • CLOSED-CIRCUIT TELEVISION (CCTV), ALSO KNOWN AS VIDEO SURVEILLANCE, IS THE USE OF VIDEO CAMERAS TO TRANSMIT A SIGNAL TO A SPECIFIC PLACE, ON A LIMITED SET OF MONITORS • IN INDUSTRIAL PLANTS, CCTV EQUIPMENT MAY BE USED TO OBSERVE PARTS OF A PROCESS FROM A CENTRAL CONTROL ROOM, FOR EXAMPLE WHEN THE ENVIRONMENT IS NOT SUITABLE FOR HUMANS. • CCTV SYSTEMS MAY OPERATE CONTINUOUSLY OR ONLY AS REQUIRED TO MONITOR A PARTICULAR EVENT. CCTV SYSTEM & MONITORING SYSTEM
  • 17. VIDEO WALL 4x2 CONFG. CONTROL ROOM VIDEO MANAGEMENT SOFTWARE & CAMERA LICENSES HIGH CONFIGURATION SERVER WITH STORAGE HIGH CONFIGURATION CLIENT WORKSTATIONS JOYSTICK CONTROLLER LAN/ OFC NETWORK POE SWITCHES BULLET CAMERA FIXED DOME CAMERA PTZ DOME CAMERA BOX CAMERA SCHEMATIC – CCTV & SURVEILLANCE SYSTEM
  • 18. IBMS SYSTEM • A Building Management System (BMS) or Building Automation System (BAS) is a computer-based control system installed in buildings that controls and monitors the building’s mechanical and electrical equipment • They help you plan operations and assess performance; make operation easier; improve building comfort, enhance safety, improve efficiency, save energy, and protect your assets. • Their function is to control, monitor and optimize building services, such as heating, ventilation, air conditioning, lighting, alarm systems and certain electrical appliances. BUILDING MANAGEMENT SYSTEM
  • 19. BMS DISPALY BMS SEVER WITH BMS SOFTWARE & LICENSE TCP/IP NETWORK DDC CONTROLER WITH 3RD PARTY INTEGRATION DDC CONTROLER WITH 3RD PARTY INTEGRATION HVAC SYSTEM VENTILATION & EXHUST SYSTEMS ELECTRICAL DISTRIBUTION SYSTEM FIRE FIGHTING SYTEMS PHE SYSTEMS ELEVATOR SYSTEMS FIELD DEVICES LASER PRINTER DDC CONTROLER WITH 3RD PARTY INTEGRATION DDC CONTROLER WITH 3RD PARTY INTEGRATION DDC CONTROLER WITH 3RD PARTY INTEGRATION SCHEMATIC – IBMS SYSTEM
  • 20. HVAC – HEATING VENTILATION & AIR CONDITIONING
  • 21. HVAC – HEATING VENTILATION & AIR CONDITIONING WHAT IS TR - TON OF REFRIGERATION 1 TR IS AMOUNT OF HEAT EXTRACTED FROM ATMOSPHERE FOR MELTING 1 METRIC TONNE OF ICE IN 24 HOURS. 1 TR = BTU/HR 1 TR = 3025 KCAL/HR
  • 22. FUNCTIONS OF HVAC • CONTROL OF AIR TEMPERATURE • CONTROL OF MOISTURE CONTENT IN THE AIR • PROPER AIR MOVEMENT • TO HOLD AIR CONTAMINATION WITHIN ACCEPTABLE LIMITS
  • 23. TYPES OF HVAC SYSTEMS AIR CONDITIONING NON DUCTED PRODUCTS DUCTABLE SYSTEMS SPLIT AIR CONDITIONING WINDOW AIR CONDITIONING PACKAGED AIR CONDITIONING CENTRAL PLANT FLOOR MOUNTED WALL MOUNTED CEILING MOUNTED EXPOSED TYPE CASSETTE TYPE HIDE AWAY TYPE FLOOR STANDING PACKAGED AC AIR COOLED DUCTABLE SPLITS AIR COOLED WATER COOLED DX SYSTEM CHILLED WATER SYSTEM VAPOUR COMPRESSION UNIT VAPOUR ABSORPTION UNIT RECIPROCATING UNITS AIR & WATER COOLED CENTRIFUGAL UNITS WATER COOLED SCREW TYPE UNITS AIR & WATER COOLED RECIPROCATING UNITS AIR & WATER COOLED CENTRIFUGAL UNITS WATER COOLED SCREW TYPE UNITS AIR & WATER COOLED
  • 25. WHAT IS FIRE ? • An exothermic reaction resulting from combination of heat fuel and oxygen. • Fire involves rapid oxidation at high temperatures accompanied by the evolution of highly heated gaseous products of combustion and emission of visible and invisible radiation. • Initiation of fire requires combustible materials, oxygen and an energy source (heat) to provide ignition. Three components - fuel , oxygen & heat are referred as the fire triangle
  • 26. CLASSIFICATION OF FIRE • Class-A - Fires involving ordinary combustible materials like wood, paper, textiles, rubber etc. • Class-B -Fires involving flammable liquids or liquefiable solids, such as oils, solvents, petroleum products, paints, varnishes etc. • Class-C - Fire involving gases or liquefied gases under pressure for eg. LPG, Hydrogen etc. • Class-D Fire involving combustible metal such as Magnesium, sodium Zinc, Titanium etc.
  • 27. PRINCIPLE OF FIRE EXTINCTION • Starvation - Removing or blanketing the fuel • Smothering - Cutting off the oxygen supply • Cooling - Removing heat from the fire.
  • 28. FIRE FIGHTING SYSTEM • FIRE WATER RESERVOIR • PUMPING UNITS • FIRE WATER NETWORK • FIRE FIGHTING HYDRANT SYSTEM • FIRE FIGHTING SPRINKLER SYSTEM • FIRE PROTECTION EQUIPMENT FIRE WATER RESERVOIR PUMPING UNITS FIRE WATER NETWORK FIRE FIGHTING HYDRANT SYSTEM FIRE FIGHTING SPRINKLER SYSTEM FIRE PROTECTION EQUIPMENT
  • 29. MUNCIPAL WATER SUPPLY TANKER WATER / BORE WELL FIRE TANK HYDRANT SRINKLER DP HP J SP J B DP – DIESEL PUMP HP – HYDRANT PUMP SP – SPRINKLER PUMP J – JOCKEY PUMP B – BOOSTER PUMP EXTERNAL HYDRANT INTERNAL HYDRANT BRIDGE INLET TYPICAL FIRE PROTECTION SYSTEM SCHEMATIC
  • 31. DIFFERENT AREAS OF PHE • SANITARY AND CP FITTINGS • HOT & COLD WATER SUPPLY SYSTEM • DRAINAGE & SEWAGE SYSTEM • EXTERNAL WATER SUPPLY • SEWAGE TREATMENT PLANT • EXTERNAL SEWER NETWORK AND CONNECTION TO SEWAGE TREATMENT PLANT/ MUNICIPAL NETWORK
  • 32. What is a plumbing system THE PLUMBING SYSTEM IS REALLY MADE UP OF TWO SYSTEMS: • The supply system that brings in fresh water • The drain-waste-vent system that takes out used water and sewage • THE DRAIN-WASTE-VENT SYSTEM ALSO LETS AIR IN AND WASTE GASES OUT. • BETWEEN THESE TWO SYSTEMS ARE THE FIXTURES (SINKS, TUBS, TOILETS, AND SO ON).
  • 33. SCHEMATIC– PHE (WATER SUPPLY) MUNCIPAL WATER SUPPLY TANKER WATER / BORE WELL FIRE TANK RAW WATER TANK WTP DOMESTIC WATER TANK TOILETS & PANTRY/ KITCHEN OVERFLOW FROM FIRE TANK
  • 34. SCHEMATIC– PHE (SEWAGE & FLUSHING WATER) SEWAGE FROM TOILETS INSPECTION CHAMBER STP FLUSHING WATER TANK FLUSHING WATER FOR TOILETS PANTRY/ KITCHEN GREASE TRAP DISPOSAL TO MUNICIPAL LINE TREATED WATER
  • 35. SCHEMATIC– STP (MBBR ) P TUBE DECK MEDIA DUAL MEDIA FILTER ACTIVAT ED CARBON FILTER P EXCESS SLUDGE SCREEN CHAMBER OIL & GREASE TRAP EQUILISATION TANK TUBE SETTLER TANK FAB REACTOR CHLORINE DOSING TANK CHLORINE DOSING P TREATED WATER TANK SLUDGE DISPOSAL TANK TREATED WATER FOR USE SEWAGE INLET SLUDGE DISPOSAL BACKWASH LINE SQUEEZED WATER
  • 36. PIPING/ CONTAINMENT CATEGORISED • HORIZONTAL PIPELINE • VERTICAL PIPELINE MEP SERVICE LINES - CATEGORISED
  • 37. PIPELINE CATEGORIES HORIZONTAL PIPELINE VERTICAL PIPELINE EMBEDDED PIPELINE EXPOSED PIPELINE Plumbing Electrical Telecommunications Fire Protection HVAC Water Supply, Waste Water & Sewage, Vent, Rainwater Recycling Bus-ducts, Cable Containments, Generator Exhaust & Cooling water Piping CCTV, Network, Audio, Telecommunications Fire Protection water Supply, Sprinklers Air Duct, chilled water & Condensate water (Supply & Return) BEAM WEB OPENINGS UNDER BEAMS Lighting Conduits, Telecommunications Conduits, Fire Alarm Conduits Water Supply, Lighting Conduits, Waste Water, Sewage, Fire Alarm & Fire Sprinkler NEXT PAGE PIPELINE LAYOUT CATEGORIES OF MEP SYSTEM
  • 38. PIPELINE CATEGORIES VERTICAL PIPELINE EMBEDDED PIPELINE (WITHIN PARTITION) EXPOSED PIPELINE (SHAFTS) Plumbing Electrical Telecommunications Fire Protection HVAC Water Supply, Waste Water & Sewage, Vent Bus-ducts, Cable Containments, Generator Exhaust & Cooling water Piping CCTV, Network, CATV, Audio, Telecommunications Fire Protection water Supply, Sprinklers Chilled water & Condensate water (Supply & Return) Plumbing Electrical Telecommunications Water Supply, Waste Water & Sewage, Vent Lighting & Sockets CCTV, Network, CATV, Audio, Telecommunications PIPELINE LAYOUT CATEGORIES OF MEP SYSTEM HORIZONTAL PIPELINE
  • 39. FA/VA, BMS & Security containment LV Cable Trays Lighting & Power Trunking Blockwork Walls Slab HV Ladder Rack Soffit Fire Protection Pipe Work Incoming Water Mains Drainage Pipe Duct Work Duct Work Branch Chilled Water Pipes • Typically a MEP Contractor each install their own supports from the soffit. • Followed by water mains, drainage and fire protection pipe work. Generally MEP services that would not require any further access once they had been installed, tested and insulated. • Followed by the ductwork and its branches to adjacent rooms, which would require testing and insulation. • Then the chilled water pipework, which also branches off to adjacent rooms and needs to be accessible. • Electrical containment is always the lowest and final service to be installed. Its completion and subsequent cable installation will be dependent on the mechanical services completion. • The coordinated installation sequence needs to prioritize the earliest release for HV & LV cable installations. MEP – TYPICAL SECTION OF CORRIDOR
  • 41. Foundation for MEP Heavy Equipment
  • 42. Sleeves For MEP Services Wall Penetration Note : It is very Important to Close this Sleeves with Fire sealant Post Installation of Service Lines
  • 44. Services before casting of Floor Slab
  • 45. Services before casting of RCC Walls
  • 46. Plaster after laying of wall services
  • 47. Cut-outs for Pulling of Cables
  • 48. Ceiling MEP Services before False Ceiling
  • 49. Ceiling MEP Services before False Ceiling
  • 50. Ceiling MEP Services before False Ceiling
  • 52. MEP INTERFACING – PROBLEMS ASSOCIATED According to the characteristics of the problem, integration requirements, and construction necessities, the Interface Problems is divided in following eight classifications. • Coordination with civil structure • Safety aspects • Functionality • Constructability • Economy • Efficiency • Expandability • Maintainability
  • 53. • This refers to the process of installing Services, which must be well coordinated to embed the horizontal pipes and vertical sleeves in advance. • Electrical pipes, monitor control pipes, and vertical sleeves of sewage pipes from the floor slab must be installed prior to slab grouting. • The work involving the first completed concrete mat for moisture protection and vibration isolators must be executed in conjunction with the embedded sleeves and architectural construction works COORDINATION WITH CIVIL STRUCTURE
  • 54. • Safety refers to safety considerations during installation. • For example, safety is required to prevent hazards such as a water pipe leakage if a water pipe lies above an electrical pipe SAFETY ASPECTS
  • 55. • Functionality refers to ensuring that the function of pipes is fully exploited while complying with building codes. • For example, drainage slopes and routes must be taken into consideration for proper drainage of waste water. • The installation of fire protection equipment and piping must be arranged prior to other systems in order for the entire fire protection system to comply with fire codes and fire protection permit drawings. Consequently, this has an impact on passing the fire protection inspection and obtaining the occupancy permits. FUNCTIONALITY
  • 56. Constructability represents the factors influencing the sequence of installation. The conflicts can be categorized as follows: • Conflict of equipment in a space - Because of the crowded space, the routing and sequence of installation for large equipment must be checked first. • Conflict of pipeline in a space - Conditions for stacking and interlacing pipelines causes difficulty in installation and maintenance due to over-crowded spaces and lack of advance coordination • Crowded installation - Conflicts within the installation space, idle laborers, and poor installation quality can result from problems such as crowded spaces or multiple workers operating simultaneously at a single site. Furthermore, the attitude of “first come first win” or “first do first win” causes conflict in the arrangement of pipelines. • Pipe materials and dimensions - Installation suffers if the diameter of the pipe is oversized or if the material of the pipe is inflexible or too rigid to be easily cut or molded. If these kinds of materials are applied for the works, they should be installed earlier to prevent conflicts • Installation of pipeline tiers - When the pipeline layout exceeds two layers, pipes CONSTRUCTABILITY
  • 57. • Economy refers to the cost estimates associated with integration, which can increase due to a lack of coordination. • For instance, re-routing a pipeline increases the lengths of the pipeline and associated costs. ECONOMY
  • 58. • Efficiency refers to a lack of integration causing descending pressure and consuming capacity, which influences the basic function of MEP systems. • Additionally, venting conditions around equipment influences equipment functionality, and should be noted during the integration of the interface. EFFICIENCY
  • 59. Expandability refers to the lifecycle of the facility causing a demand for the expansion of pipelines due to the changes in usage or upgrades to the facility. This increasing demand requires consideration prior to the installation phase to ensure space for future expansion of the pipeline. EXPANDABILITY
  • 60. • Maintainability refers to the convenience of maintenance during the operation phase when arranging the pipeline. • Maintenance space and operation route must be taken into consideration. MAINTAINABILITY
  • 61. • The major MEP installation projects require the identification of separate arrangements for HVAC, power supply, plumbing, fire protection, telecommunications, and other related systems. • Specialized consultants and contractors design and construct these systems. Currently, according to technical specifications, each specialty or trade subcontractor is assigned the responsibility of integrating MEP systems. • Coordination of mechanical and electrical systems to detail their configuration provides a major challenge for complex building and industrial projects • The knowledge required for MEP integration must be integrated to our System because specialty subcontractors of each system perform tasks individually, proposing a layout according to their own needs, leading to the fragmentation of MEP. MEP INTEGRATION
  • 62. • Improper integration at the equipment/pipeline interface results in interference and inappropriate sequence of jobs during installation can negatively influence the entire project. • Moreover, the complete integration of the interface reduces the numbers of changes in the design, decreases the work requiring demolition, addresses problems resulting from installation error, and increases the overall construction quality of projects. • Hence, the purpose of integrating the interface is to recognize problems, resolve conflicts, and perfect the layout of the system for these mechanisms to serve their functions fully. MEP INTEGRATION
  • 63. The discussed eight criteria are considered as MEP integration items because they are closely related to considerations of installation integration. To facilitate comparison, let us subcategorized these eight criteria according to three levels INTEGRATION SEQUENCING The three levels are described as follows: 1. Basic Requirements and Coordination with Civil Structure Works Functionality of the 8 criteria fall under this first level of the integration sequencing. 2. Construction Requirements This is a second level integration task, comprising the evaluation of installation difficulty, problems associated with the installation of circulation interfaces, and the arrangement of sequencing 3. Cost and Operations Requirements This refers to the examination of the price of installation, cost-benefit ratio, and factors related to maintenance and expansion during the life circle of the facility. INTEGRATION SEQUENCING
  • 64. MEP INTEGRATION SEQUENCING LEVEL 1 Basic Requirements & Coordination with Civil & Structure Works SAFETY FUNCTIONALITY COORDINATION Supply Side - Separate High Voltage Equipment's from water Pumps Trans. Side - Separate Water Pipes & Electrical Conduits from telecommunication cable. Place Electric Conduits above water Pipes to avoid water leaking over conduits Term. Side - Keep Safe Distance between sensors & Vents to avoid sensing interference Supply Side - Comply with Fire Regulations for selection of Equipment. Separate Fire Pumps from Generators. Isolate Oxygen Tanks from Fire Protected Areas Trans. Side - Consider Slopes For Gravity Drainages Comply with Fire Regulations for Pipes Term. Side - Keep Safe Distance between HVAC Vents, intakes, Fire Protection sensors & Sprinklers Supply Side - First Set Equipment Concrete Foundations. Trans. Side - Pre-bury and layout Pipes on Slabs Openings on beams & Partitions must match Pipe Positions Equipment mobilization & Installation cannot interfere with partitions construction Term. Side - Installation for illumination lights, vents, fire hydrants must be consistent with civil construction Basic Requirements and Coordination with Civil Structure Works
  • 65. Construction Requirements MEP INTEGRATION SEQUENCING LEVEL 2 CONSTRUCTION REQUIREMENTS CONSTRUCTIBILITY Supply Side - Consider Movement Circulation & Space For Large Equipment Layouts Trans. Side - Maintain Sufficient Orientation Space. Avoid Conflicts & Multi Layers Overlap when Pipeline Space Is Not enough Consider Pipeline Sizes & Material Flexibility Install Top Layers Pipelines first Term. Side - Check Whether Terminal Side Equipment's are obscured by other equipment that causes Conflicts Check Ceiling Heights & Match Ceiling horizontal layouts
  • 66. MEP INTEGRATION SEQUENCING LEVEL 3 Cost and Operations Requirements ECONOMY EFFICIENCY EXPANDIBILITY Supply Side - Keep Adequate Distance between large equipment Centralised Equipment design is generally more economic then scattered formats Equipment Position need to be close to load centre Trans. Side - Apply Shortest, Closest Route Principle to pipeline layouts. Term. Side - Keep adequate distance among terminal side equipment. Maintain Consistency with Ceiling Or Partition Plans Supply Side - Consider Surrounding Environmental Factors & Ventilation Problems for Major Equipment Trans. Side - Straight Pipes are preferable. Avoid Bend in Pipes Term. Side - Keep Distance between HVAC Vents & intakes Supply Side - Reserve Space for future Equipment Expansion & Possible Flexible Adjustments Trans. Side - Reserve Space for Future Pipeline Distribution Term. Side - Consider Reservation, disbanding, flexible adjustments Cost and Operations Requirements MAINTAINABILITY CONSIDER MAINTAINANCE & MANAGEMENT SPACE & MOVEMENT LINES
  • 67. STEPS TO DEVELOP WORKSTATION AREAS
  • 68. STEP 1 – Laying of Under Floor Services • Slab surface to be uniform for raceway laying • FFL to be decided prior to any installations • Raceway marking to be provided as per approved workstation layout • Placing the Raceway & Junction Boxes on the floor. • Clamping to be done on the floor end cover the Junction Boxes by thermocoal. • Care to be taken for JB’s during concreting • After concrete thermocoals to be removed from JB’s
  • 69. STEP 2 – SCREEDING/ IPS WORKS
  • 70. STEP 3 – CEILING TENDON MARKING
  • 71. STEP 4 – MEP FIRST FIX LV CABLES-1 FIRE LINE- 2 DUCTS-3 ELECTRICAL CONDUITS-1
  • 72. STEP 4 – MEP FIRST FIX - Inclusions 1. Conduit to be installed on ceiling and wall as per approved point wiring. 2. Clamps to be fixed after proper drilling on ceiling (Tendon marking to be avoided.) 3. LV Cables to installed as per Layout with clamping 4. Parallel fire line works to start. 5. For Fire line installation area to be surveyed 6. Main header line to be installed with clamps (Clamps to be provided as per NFPA) 7. Sub header and branch pipes to be installed at ground level and overhauled to ceiling 8. Clamps to be provided 9. After installation of sub header welding to the main header to be welded 10. All welding to be properly executed with absolute perfection. 11. All pipes to be surface cleaned, primer applied and painting done in RED. 12. Hydro testing to be conducted at 1.5 times the Pump pressure 13. Duct to be fabricated in-situ with profiling 14. Hangers to be installed as per duct passage and tendon markings to be taken care of. Header duct to be installed as per BOD 15. Branches to be added to main header as per BOD 16. Sealing to be done so that no gaps are observed 17. Light test to be conducted before ceiling clearance
  • 73. STEP 4 – MEP FIRST FIX - Requirements • Civil structure to be ready • Tendon markings to be provided • Proper cutouts for services bypass • FFL level to be decided prior to any installations • Cutouts to be mentioned in MEP penetration plan • BOP, BOD, BOCT to be exact as per ceiling height
  • 74. STEP 5 – MEP FIRST FIX - Wall REQUIREMENTS FOR WALL FIX: 1. ROUTING TO BE MENTIONED. 2. SURFACE OR CONCEALED TO BE MENTIONED 3. INTERCONNECTIVITY OF ROOMS THROUGH CONDUITS/ FLEXIBLE TO BE DECIDED.
  • 75. STEP 6 – Floor Tiling Works
  • 76. STEP 7 – MEP SECOND FIX What is done during 2nd fix? 1. Fire- Flexible and sprinklers are fixed 2. HVAC- Spigot are fixed 3. Electrical- All wiring to be done in conduits 4. LV- Above ceiling detector boxes and related cabling
  • 77. STEP 8 – GRIDWORK FOR CEILING
  • 78. STEP 9 – MEP FINAL FIX
  • 79. STEP 9 – MEP FINAL FIX - Requirements • BOD, BOP, BOC should be inline with False ceiling levels • Grid ceiling gap should be maintained as per fixtures. • Special attention required for any gravity flow line such as drains What is done in 3rd Fix? 1. Fire- Sprinklers are fixed on ceiling 2. HVAC- Grills/ Diffusers are fixed on grid of ceiling 3. Electrical- Light Fixtures/ Switch sockets on ceiling and wall 4. LV- All LV Fixtures such as detectors/ RI/ Hooters/ CR/ Speakers on wall/ceiling/ doors
  • 80. STEP 10 – Cable Pulling & Area Clearance
  • 81. STEP 11 – Final Ceiling Works
  • 82. STEP 11 – Final Fixtures
  • 83. STEP 12 – Workstation Installation Following activities proceed after workstation installation works: 1. All Data cables to be brought to surface and Data plates to be fixed 2. All UPS/ RAW power wiring works to surface and switch plates are fixed 3. All Plates are tagged 4. JB opening to close using SS/ Aluminum sheet