SlideShare une entreprise Scribd logo
1  sur  9
Télécharger pour lire hors ligne
Northern Technical University
Engineering Technical College of Mosul
Building & Construction
Technology Engineering Dept.
Estimation, Specifications and
Contracts
SECOND CLASS
Lecturer:
Dr. Muthanna Adil Najm ABBU
2017-2018
Estimation, Specifications
& Contracts Factors Lecture .2
1
Dr. Muthanna Adil Najm Northern Technical University
PROCEDURE OF ESTIMATING OR METHOD OF ESTIMATING.
Estimating involves the following operations
1. Preparing detailed Estimate.
2. Calculating the rate of each unit of work
3. Preparing abstract of estimate
DATA REQUIRED TO PREPARE AN ESTIMATE
1. Drawings i.e.plans, elevations, sections etc.
2. Specifications.
3. Rates.
DRAWINGS
If the drawings are not clear and without complete dimensions the preparation
of estimation become very difficult. So, It is very essential before preparing
an estimate.
SPECIFICATIONS
a) General Specifications:
This gives the nature, quality, class and work and materials in general terms to
be used in various parts of wok. It helps no form a general idea of building.
b) Detailed Specifications:
These gives the detailed description of the various items of work laying down
the Quantities and qualities of materials, their proportions, the method of
preparation workmanship and execution of work.
RATES:
For preparing the estimate the unit rates of each item of work are required.
1. For arriving at the unit rates of each item.
2. The rates of various materials to be used in the construction.
3. The cost of transport materials.
4. The wages of labour, skilled or unskilled of masons, carpenters, Mazdoor,
etc.,
Estimation, Specifications
& Contracts Factors Lecture .2
2
Dr. Muthanna Adil Najm Northern Technical University
LUMPSUM:
While preparing an estimate, it is not possible to workout in detail in case of
petty items. Items other than civil engineering such items are called
lumpsum items or simply L.S.Items. The following are some of L.S. Items
in the estimate.
1. Water supply and sanitary arrangements.
2. Electrical installations like meter, motor, etc.,
3. Architectural features.
4. Contingencies and unforeseen items.
Ingeneral, certain percentage on the cost of estimation is alloted for the above
L.S.Items.
Even if subestimates prepared or at the end of execution of work, the actual
cost should not exceed the L.S.amounts provided in the main estimate.
Factors affecting cost estimation:
There are three further factors that have a significant influence on how an
estimator
goes about preparing a construction estimate:
1. The type of project to be built
2. The delivery system used to move from the developer’s project idea to
a finished structure
3. The nature of the contract(s) used in the delivery system
Estimation, Specifications
& Contracts Factors Lecture .2
3
Dr. Muthanna Adil Najm Northern Technical University
Types of estimation:
A. Detailed Estimate
The most accurate and most reliable type of estimate. It consists of the quantities
and the cost of everything required in the project. This includes:-
(1) report, (2) technical specifications, (3) detailed drawings, (4) design data and
calculations, (5) basis of the rated prices adopted in estimation.
B. Approximate (Rough/Order of magnitude/Preliminary) Estimate
This method is based on comparative Cost of Structure. It is readily adaptable to
virtually every type of structure, including bridges, stadiums, schools, hospitals, and
offices. Very little information is required about the planned structure except that
the following general characteristics should be known:
1. Use — school, office, hospital, and so on
Estimation, Specifications
& Contracts Factors Lecture .2
4
Dr. Muthanna Adil Najm Northern Technical University
2. Kind of construction — wood, steel, concrete, and so on
3. Quality of construction — cheap, moderate, top grade
4. Locality — labor and material supply market area
5. Time of construction — year
By identifying a similar completed structure with nearly the same characteristics,
an order-of-magnitude estimate can be determined by proportioning cost according
to the appropriate unit for the structure.
There are several techniques to prepare the approximate estimate:-
(1) Service Unit or cost per unit Method
These units might be as follows:
• Schools — pupils
• Stadium — seats
• Hospital — beds
• Warehouses — cubic feet
(2) Unit-Area or Floor-Area Or plinth area
In this technique the cost of unit area of an already constructed building is
adapted as the basis to estimate the cost of a new similar building.
In the case of multi-storey buildings either one of the methods below may be
used:
I- consider the cost of the construction unit of area equal to all floors.
II- taking into account the different construction cost of some floors in
comparison to others.
(3) Unit - Volume or Cubic Rate Method
This is more accurate than its predecessor as it takes into account the third
dimension (i.e., height of floors).
(4) Approximate Quantities
Estimation, Specifications
& Contracts Factors Lecture .2
5
Dr. Muthanna Adil Najm Northern Technical University
In this method approximate quantities of each item of the work are calculated
and priced then the approximate cost of the project is calculated.
Using approximate techniques of estimation one must consider the following
points: -
(1). Specification level & finishing requirements.
(2). Time & duration of construction and inflation effect.
(3). Site & location of the project.
(4). General & special requirements of project.
(5). The structural nature of the building.
(6). Shape & height of building compared to the prototype.
C- Quantity Survey or Quantity Estimate
This involves the calculation of the quantities of materials required to complete
the work in question.
D- Revised Estimate
This type of estimate is prepared during construction when the difference
between reality and prepared estimation exceeds 5% regardless the reason behind
this difference (except major structural changes).
E- Supplementary Estimate
Used for the additional works that may seem necessary during the construction
phase.
F- Complete Estimate
It is the cost estimation of each item of works related to the job. It includes:
1 - the cost of land or property including:
• the cost of purchasing the land or its monetary value.
Estimation, Specifications
& Contracts Factors Lecture .2
6
Dr. Muthanna Adil Najm Northern Technical University
• fees of surveyor and the delimitation of the property.
• the cost of testing and transfer of ownership of the property.
• real estate tax and making the required improvements, if any.
2 - necessary expenses for legal actions between the owner and the contractor.
3 - the basic amount of main contract ( materials, labor .... etc).
4 - Emergency and unexpected conditions: to be calculated as a percentage of
the work (≈ 5%) and added to the cost of the extra works and supervision.
5 - Engineering fees including:
• Preparation of plans, designs and estimation.
• supervising.
6 - water and electricity fees during the construction phase.
7 - others, if any.
G- Annual Maintenance or Repair Estimate
This type of estimate is pertinent to the repair works and maintenance works that
are necessary to keep the project usable.
Practical examples on approximate estimation:
Example 1: Assume that the current cost for a 120-pupil school constructed of wood
frame for a city is $1,800,000. We are asked to develop an order-of-magnitude
estimate for a 90-pupil school.
Solution:
The first step is to separate the per-pupil cost.
$1,800,000/ 120 = $15,000 pupil
Apply the unit cost to the new school.
$15,000 pupil x 90 pupils = $1,350,000
Estimation, Specifications
& Contracts Factors Lecture .2
7
Dr. Muthanna Adil Najm Northern Technical University
Example 2: The total cost of construction of a hospital with capacity of (50) beds
is150 million dinars.
Cost per bed (patient) = 150 ÷ 50 = 3 million dinars
We can use this number to estimate the cost of similar hospital but with 20 beds, as
follows:
20 x 3 = 60 million dinars.
Example 3: a 24x15 m building consisting of 6 floors including the basement,
ground and terrace. Calculate the cost of 1 m2
using both above-mentioned methods,
if the total cost of the building is (648) million dinars.
solution:
(1) first method:
Total construction area = 6x (24x15) = 2160 m2
Cost of 1 m2
= 648000000 ÷ 2160 = 300,000 ID
(2) second method: suppose the cost basement floor = 60% of the cost of any of the
other floors
The cost of terrace = 40% of the cost of any of the other floors (except for the
basement).
The equivalent area of the basement = 24x15x60% = 216 m2
The equivalent area of the terrace = 24x15x40% = 144 m2
Area of rest floors = 4x (24x15) = 1440 m2
Total area of construction =1800 m2
the cost of 1 m2
of construction for the (typical) floors
= 648000000 ÷ 1800 = 360000 dinars
The cost of 1 m2
of basement = 360000x60% = 216000 dinars
Finally, the cost of 1 m2
of the surface = 360000x40% = 144000 dinars
Estimation, Specifications
& Contracts Factors Lecture .2
8
Dr. Muthanna Adil Najm Northern Technical University
Example 4: A 60x40m building consists of basement (2.8 m high), three other
floors (each 3m high). The total cost of building 2250 million I. D.
Calculate the cost of unit volume of the building assuming: -
a- identical cost of 1m3
for all floors.
b- costs of basement & ground floor are 60% and 120% of the other floors
respectively.
Solution: a-
Vbasement = 40x60x2.8 = 6720 m3
Vothers = 40x60x3x3 = 21600 m3
__________
Total =28320 m3
 Cost of 1 m3
= 2250000000 / 28320 = 79450 I. D.
b- equivalent Vbas . = 40x60x208x0.6 = 4032 m3
equivalent VG. F. = 40x60x3x1.2 = 8640 m3
V others = 40x60x3x2 = 14400 m3
__________
Total = 27072 m3
 cost of 1m3
of typical floor = 2250000000 / 28320 = 83112 ID
cost of 1 m3
of basement = 83112x0.6 = 49867.2 I.D.
cost of 1 m3
ground floor = 83112x1.2 = 99734.4 I.D.

Contenu connexe

Tendances

Estimation (power point)
Estimation (power point)Estimation (power point)
Estimation (power point)
Waqas Aslam
 
Costing for-civil-engineering-project
Costing for-civil-engineering-projectCosting for-civil-engineering-project
Costing for-civil-engineering-project
hlksd
 

Tendances (20)

Types of estimates
Types of estimatesTypes of estimates
Types of estimates
 
Estimating part 2
Estimating part 2Estimating part 2
Estimating part 2
 
Basics of estimation
Basics of estimation Basics of estimation
Basics of estimation
 
Planning and cost analysis of the commercial building
Planning and cost analysis of the commercial buildingPlanning and cost analysis of the commercial building
Planning and cost analysis of the commercial building
 
Estimating and Costing
Estimating and CostingEstimating and Costing
Estimating and Costing
 
Planning and cost analysis of the commercial building
Planning and cost analysis of the commercial buildingPlanning and cost analysis of the commercial building
Planning and cost analysis of the commercial building
 
Preliminary estimate
Preliminary estimatePreliminary estimate
Preliminary estimate
 
Estimation (power point)
Estimation (power point)Estimation (power point)
Estimation (power point)
 
Types of estimate
Types of estimateTypes of estimate
Types of estimate
 
Estimating and costing
Estimating and costingEstimating and costing
Estimating and costing
 
2 types of estimates
2 types of estimates2 types of estimates
2 types of estimates
 
Costing for-civil-engineering-project
Costing for-civil-engineering-projectCosting for-civil-engineering-project
Costing for-civil-engineering-project
 
Costing_Actual spendings & pricing
Costing_Actual spendings & pricingCosting_Actual spendings & pricing
Costing_Actual spendings & pricing
 
2# types of estimate
2# types of estimate2# types of estimate
2# types of estimate
 
4.1 conceptual estimates
4.1 conceptual estimates4.1 conceptual estimates
4.1 conceptual estimates
 
Ppv ppt
Ppv pptPpv ppt
Ppv ppt
 
Factors affeccting cost estimates of a project
Factors affeccting cost estimates of a projectFactors affeccting cost estimates of a project
Factors affeccting cost estimates of a project
 
Approximate estimate
Approximate estimateApproximate estimate
Approximate estimate
 
5.1 quantity take-off
5.1 quantity take-off5.1 quantity take-off
5.1 quantity take-off
 
Quantity surveying drawing FNBE 2014
Quantity surveying drawing FNBE 2014Quantity surveying drawing FNBE 2014
Quantity surveying drawing FNBE 2014
 

Similaire à Lec.2 binifits of estamations...Types of Estimation

fuw5fomwrucbh1ojdlxe-signature-b01f2df686b9c053f2f9f35a62a4a1f12d0e812f6cbea3...
fuw5fomwrucbh1ojdlxe-signature-b01f2df686b9c053f2f9f35a62a4a1f12d0e812f6cbea3...fuw5fomwrucbh1ojdlxe-signature-b01f2df686b9c053f2f9f35a62a4a1f12d0e812f6cbea3...
fuw5fomwrucbh1ojdlxe-signature-b01f2df686b9c053f2f9f35a62a4a1f12d0e812f6cbea3...
Deepak37004
 
Green Building Awareness HVAC
Green Building Awareness HVAC Green Building Awareness HVAC
Green Building Awareness HVAC
AKSHAY SHARMA
 

Similaire à Lec.2 binifits of estamations...Types of Estimation (20)

Lec05.pptx
Lec05.pptxLec05.pptx
Lec05.pptx
 
EstimationandCosting.ppt
EstimationandCosting.pptEstimationandCosting.ppt
EstimationandCosting.ppt
 
Estimation_and_Costing.ppt
Estimation_and_Costing.pptEstimation_and_Costing.ppt
Estimation_and_Costing.ppt
 
EstimationandCosting.ppt
EstimationandCosting.pptEstimationandCosting.ppt
EstimationandCosting.ppt
 
Quantity Surveying & valuation.ppt
Quantity Surveying & valuation.pptQuantity Surveying & valuation.ppt
Quantity Surveying & valuation.ppt
 
Estimation Costing and Valuation Unit 2
Estimation Costing and Valuation Unit 2Estimation Costing and Valuation Unit 2
Estimation Costing and Valuation Unit 2
 
Introduction to Quantity Surveying .pptx
Introduction to Quantity Surveying .pptxIntroduction to Quantity Surveying .pptx
Introduction to Quantity Surveying .pptx
 
Introduction to estimation
Introduction to estimationIntroduction to estimation
Introduction to estimation
 
Estimation and costing of a commercial building
Estimation and costing of a commercial buildingEstimation and costing of a commercial building
Estimation and costing of a commercial building
 
CE6704_uw.pdf
CE6704_uw.pdfCE6704_uw.pdf
CE6704_uw.pdf
 
Estimation and Costing
Estimation and CostingEstimation and Costing
Estimation and Costing
 
Estimating and costing I Chapter 2.pptx
Estimating and costing I Chapter 2.pptxEstimating and costing I Chapter 2.pptx
Estimating and costing I Chapter 2.pptx
 
0111CE702-ESTIMATION AND QUANTITY SURVEYING VII SEMESTER E-LEARNING MATERIAL
0111CE702-ESTIMATION AND QUANTITY SURVEYING VII SEMESTER E-LEARNING MATERIAL0111CE702-ESTIMATION AND QUANTITY SURVEYING VII SEMESTER E-LEARNING MATERIAL
0111CE702-ESTIMATION AND QUANTITY SURVEYING VII SEMESTER E-LEARNING MATERIAL
 
Estimation (power Point).ppt
Estimation (power Point).pptEstimation (power Point).ppt
Estimation (power Point).ppt
 
Approximate estimate
Approximate estimateApproximate estimate
Approximate estimate
 
fuw5fomwrucbh1ojdlxe-signature-b01f2df686b9c053f2f9f35a62a4a1f12d0e812f6cbea3...
fuw5fomwrucbh1ojdlxe-signature-b01f2df686b9c053f2f9f35a62a4a1f12d0e812f6cbea3...fuw5fomwrucbh1ojdlxe-signature-b01f2df686b9c053f2f9f35a62a4a1f12d0e812f6cbea3...
fuw5fomwrucbh1ojdlxe-signature-b01f2df686b9c053f2f9f35a62a4a1f12d0e812f6cbea3...
 
Estimating & costing of civil engineering structures
Estimating & costing of civil engineering structuresEstimating & costing of civil engineering structures
Estimating & costing of civil engineering structures
 
Unit 1 - General Items used for building
Unit 1 - General Items used for buildingUnit 1 - General Items used for building
Unit 1 - General Items used for building
 
estimation,its types and methods
estimation,its types and methodsestimation,its types and methods
estimation,its types and methods
 
Green Building Awareness HVAC
Green Building Awareness HVAC Green Building Awareness HVAC
Green Building Awareness HVAC
 

Plus de Muthanna Abbu

Plus de Muthanna Abbu (20)

Lec.5 earthworks for various engineering projects
Lec.5  earthworks for various engineering projectsLec.5  earthworks for various engineering projects
Lec.5 earthworks for various engineering projects
 
Lec.4 Excavation and fill works of wall footings
Lec.4 Excavation and fill works of wall footingsLec.4 Excavation and fill works of wall footings
Lec.4 Excavation and fill works of wall footings
 
Lec.3 General rules in quantitative survey. Quantity measuring. Rate analysis
Lec.3  General rules in quantitative survey. Quantity measuring. Rate analysisLec.3  General rules in quantitative survey. Quantity measuring. Rate analysis
Lec.3 General rules in quantitative survey. Quantity measuring. Rate analysis
 
Lec.2 statically determinate structures & statically indeterminate struct...
Lec.2 statically determinate structures & statically indeterminate struct...Lec.2 statically determinate structures & statically indeterminate struct...
Lec.2 statically determinate structures & statically indeterminate struct...
 
Lec.1 introduction to the theory of structures. types of structures, loads,
Lec.1   introduction to the theory of structures. types of structures, loads,Lec.1   introduction to the theory of structures. types of structures, loads,
Lec.1 introduction to the theory of structures. types of structures, loads,
 
Lec.9 strength design method doubly reinforced beams
Lec.9   strength design method doubly reinforced beamsLec.9   strength design method doubly reinforced beams
Lec.9 strength design method doubly reinforced beams
 
Lec.8 strength design method t beams
Lec.8   strength design method t beamsLec.8   strength design method t beams
Lec.8 strength design method t beams
 
Lec.7 strength design method rectangular sections 3
Lec.7   strength design method rectangular sections  3Lec.7   strength design method rectangular sections  3
Lec.7 strength design method rectangular sections 3
 
Lec.6 strength design method rectangular sections 2
Lec.6   strength design method rectangular sections  2Lec.6   strength design method rectangular sections  2
Lec.6 strength design method rectangular sections 2
 
Lec.5 strength design method rectangular sections 1
Lec.5   strength design method rectangular sections  1Lec.5   strength design method rectangular sections  1
Lec.5 strength design method rectangular sections 1
 
Lec.4 working stress 2
Lec.4   working stress 2Lec.4   working stress 2
Lec.4 working stress 2
 
Lec.3 working stress 1
Lec.3   working stress 1Lec.3   working stress 1
Lec.3 working stress 1
 
Lec.2 materials
Lec.2   materialsLec.2   materials
Lec.2 materials
 
Lec.1 introduction
Lec.1   introductionLec.1   introduction
Lec.1 introduction
 
Theory of Structures Syllabus
Theory of Structures SyllabusTheory of Structures Syllabus
Theory of Structures Syllabus
 
Analysis & Design of reinforced concrete structures (1) Syllabus
Analysis & Design of reinforced concrete structures (1) SyllabusAnalysis & Design of reinforced concrete structures (1) Syllabus
Analysis & Design of reinforced concrete structures (1) Syllabus
 
Analysis & Design of reinforced concrete structures (2) Syllabus
Analysis & Design of reinforced concrete structures (2) SyllabusAnalysis & Design of reinforced concrete structures (2) Syllabus
Analysis & Design of reinforced concrete structures (2) Syllabus
 
Design of Steel Structures Syllabus
Design of Steel Structures SyllabusDesign of Steel Structures Syllabus
Design of Steel Structures Syllabus
 
Computer Applications 2 Syllabus
Computer Applications 2 SyllabusComputer Applications 2 Syllabus
Computer Applications 2 Syllabus
 
هندسة المطارات والسكك 4
هندسة المطارات والسكك 4هندسة المطارات والسكك 4
هندسة المطارات والسكك 4
 

Dernier

Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Christo Ananth
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
ankushspencer015
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
Tonystark477637
 

Dernier (20)

Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
 
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGMANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsRussian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 

Lec.2 binifits of estamations...Types of Estimation

  • 1. Northern Technical University Engineering Technical College of Mosul Building & Construction Technology Engineering Dept. Estimation, Specifications and Contracts SECOND CLASS Lecturer: Dr. Muthanna Adil Najm ABBU 2017-2018
  • 2. Estimation, Specifications & Contracts Factors Lecture .2 1 Dr. Muthanna Adil Najm Northern Technical University PROCEDURE OF ESTIMATING OR METHOD OF ESTIMATING. Estimating involves the following operations 1. Preparing detailed Estimate. 2. Calculating the rate of each unit of work 3. Preparing abstract of estimate DATA REQUIRED TO PREPARE AN ESTIMATE 1. Drawings i.e.plans, elevations, sections etc. 2. Specifications. 3. Rates. DRAWINGS If the drawings are not clear and without complete dimensions the preparation of estimation become very difficult. So, It is very essential before preparing an estimate. SPECIFICATIONS a) General Specifications: This gives the nature, quality, class and work and materials in general terms to be used in various parts of wok. It helps no form a general idea of building. b) Detailed Specifications: These gives the detailed description of the various items of work laying down the Quantities and qualities of materials, their proportions, the method of preparation workmanship and execution of work. RATES: For preparing the estimate the unit rates of each item of work are required. 1. For arriving at the unit rates of each item. 2. The rates of various materials to be used in the construction. 3. The cost of transport materials. 4. The wages of labour, skilled or unskilled of masons, carpenters, Mazdoor, etc.,
  • 3. Estimation, Specifications & Contracts Factors Lecture .2 2 Dr. Muthanna Adil Najm Northern Technical University LUMPSUM: While preparing an estimate, it is not possible to workout in detail in case of petty items. Items other than civil engineering such items are called lumpsum items or simply L.S.Items. The following are some of L.S. Items in the estimate. 1. Water supply and sanitary arrangements. 2. Electrical installations like meter, motor, etc., 3. Architectural features. 4. Contingencies and unforeseen items. Ingeneral, certain percentage on the cost of estimation is alloted for the above L.S.Items. Even if subestimates prepared or at the end of execution of work, the actual cost should not exceed the L.S.amounts provided in the main estimate. Factors affecting cost estimation: There are three further factors that have a significant influence on how an estimator goes about preparing a construction estimate: 1. The type of project to be built 2. The delivery system used to move from the developer’s project idea to a finished structure 3. The nature of the contract(s) used in the delivery system
  • 4. Estimation, Specifications & Contracts Factors Lecture .2 3 Dr. Muthanna Adil Najm Northern Technical University Types of estimation: A. Detailed Estimate The most accurate and most reliable type of estimate. It consists of the quantities and the cost of everything required in the project. This includes:- (1) report, (2) technical specifications, (3) detailed drawings, (4) design data and calculations, (5) basis of the rated prices adopted in estimation. B. Approximate (Rough/Order of magnitude/Preliminary) Estimate This method is based on comparative Cost of Structure. It is readily adaptable to virtually every type of structure, including bridges, stadiums, schools, hospitals, and offices. Very little information is required about the planned structure except that the following general characteristics should be known: 1. Use — school, office, hospital, and so on
  • 5. Estimation, Specifications & Contracts Factors Lecture .2 4 Dr. Muthanna Adil Najm Northern Technical University 2. Kind of construction — wood, steel, concrete, and so on 3. Quality of construction — cheap, moderate, top grade 4. Locality — labor and material supply market area 5. Time of construction — year By identifying a similar completed structure with nearly the same characteristics, an order-of-magnitude estimate can be determined by proportioning cost according to the appropriate unit for the structure. There are several techniques to prepare the approximate estimate:- (1) Service Unit or cost per unit Method These units might be as follows: • Schools — pupils • Stadium — seats • Hospital — beds • Warehouses — cubic feet (2) Unit-Area or Floor-Area Or plinth area In this technique the cost of unit area of an already constructed building is adapted as the basis to estimate the cost of a new similar building. In the case of multi-storey buildings either one of the methods below may be used: I- consider the cost of the construction unit of area equal to all floors. II- taking into account the different construction cost of some floors in comparison to others. (3) Unit - Volume or Cubic Rate Method This is more accurate than its predecessor as it takes into account the third dimension (i.e., height of floors). (4) Approximate Quantities
  • 6. Estimation, Specifications & Contracts Factors Lecture .2 5 Dr. Muthanna Adil Najm Northern Technical University In this method approximate quantities of each item of the work are calculated and priced then the approximate cost of the project is calculated. Using approximate techniques of estimation one must consider the following points: - (1). Specification level & finishing requirements. (2). Time & duration of construction and inflation effect. (3). Site & location of the project. (4). General & special requirements of project. (5). The structural nature of the building. (6). Shape & height of building compared to the prototype. C- Quantity Survey or Quantity Estimate This involves the calculation of the quantities of materials required to complete the work in question. D- Revised Estimate This type of estimate is prepared during construction when the difference between reality and prepared estimation exceeds 5% regardless the reason behind this difference (except major structural changes). E- Supplementary Estimate Used for the additional works that may seem necessary during the construction phase. F- Complete Estimate It is the cost estimation of each item of works related to the job. It includes: 1 - the cost of land or property including: • the cost of purchasing the land or its monetary value.
  • 7. Estimation, Specifications & Contracts Factors Lecture .2 6 Dr. Muthanna Adil Najm Northern Technical University • fees of surveyor and the delimitation of the property. • the cost of testing and transfer of ownership of the property. • real estate tax and making the required improvements, if any. 2 - necessary expenses for legal actions between the owner and the contractor. 3 - the basic amount of main contract ( materials, labor .... etc). 4 - Emergency and unexpected conditions: to be calculated as a percentage of the work (≈ 5%) and added to the cost of the extra works and supervision. 5 - Engineering fees including: • Preparation of plans, designs and estimation. • supervising. 6 - water and electricity fees during the construction phase. 7 - others, if any. G- Annual Maintenance or Repair Estimate This type of estimate is pertinent to the repair works and maintenance works that are necessary to keep the project usable. Practical examples on approximate estimation: Example 1: Assume that the current cost for a 120-pupil school constructed of wood frame for a city is $1,800,000. We are asked to develop an order-of-magnitude estimate for a 90-pupil school. Solution: The first step is to separate the per-pupil cost. $1,800,000/ 120 = $15,000 pupil Apply the unit cost to the new school. $15,000 pupil x 90 pupils = $1,350,000
  • 8. Estimation, Specifications & Contracts Factors Lecture .2 7 Dr. Muthanna Adil Najm Northern Technical University Example 2: The total cost of construction of a hospital with capacity of (50) beds is150 million dinars. Cost per bed (patient) = 150 ÷ 50 = 3 million dinars We can use this number to estimate the cost of similar hospital but with 20 beds, as follows: 20 x 3 = 60 million dinars. Example 3: a 24x15 m building consisting of 6 floors including the basement, ground and terrace. Calculate the cost of 1 m2 using both above-mentioned methods, if the total cost of the building is (648) million dinars. solution: (1) first method: Total construction area = 6x (24x15) = 2160 m2 Cost of 1 m2 = 648000000 ÷ 2160 = 300,000 ID (2) second method: suppose the cost basement floor = 60% of the cost of any of the other floors The cost of terrace = 40% of the cost of any of the other floors (except for the basement). The equivalent area of the basement = 24x15x60% = 216 m2 The equivalent area of the terrace = 24x15x40% = 144 m2 Area of rest floors = 4x (24x15) = 1440 m2 Total area of construction =1800 m2 the cost of 1 m2 of construction for the (typical) floors = 648000000 ÷ 1800 = 360000 dinars The cost of 1 m2 of basement = 360000x60% = 216000 dinars Finally, the cost of 1 m2 of the surface = 360000x40% = 144000 dinars
  • 9. Estimation, Specifications & Contracts Factors Lecture .2 8 Dr. Muthanna Adil Najm Northern Technical University Example 4: A 60x40m building consists of basement (2.8 m high), three other floors (each 3m high). The total cost of building 2250 million I. D. Calculate the cost of unit volume of the building assuming: - a- identical cost of 1m3 for all floors. b- costs of basement & ground floor are 60% and 120% of the other floors respectively. Solution: a- Vbasement = 40x60x2.8 = 6720 m3 Vothers = 40x60x3x3 = 21600 m3 __________ Total =28320 m3  Cost of 1 m3 = 2250000000 / 28320 = 79450 I. D. b- equivalent Vbas . = 40x60x208x0.6 = 4032 m3 equivalent VG. F. = 40x60x3x1.2 = 8640 m3 V others = 40x60x3x2 = 14400 m3 __________ Total = 27072 m3  cost of 1m3 of typical floor = 2250000000 / 28320 = 83112 ID cost of 1 m3 of basement = 83112x0.6 = 49867.2 I.D. cost of 1 m3 ground floor = 83112x1.2 = 99734.4 I.D.