Constellation Program
  Planning & Control

   Project Management Challenge


             Charlie Stegemoeller
Director, Constellation Program Planning and Control

                Wayne Thomas
     Chief, Constellation Contracts Integration
Constellation Program Planning and
                     Control

Objective:
• Share the perspectives and lessons from standing up the
  Constellation Program within today’s Agency policies

Topics:
• Overview of the Constellation Program
   – Organizational Relationships
   – Lessons Learned
• Program Contracts Integration
• Implementation of 7120.5D

                                                            2
Overview of Constellation Program

Timeline of Program:
• Vision for Space Exploration – Issued January 2004
• Precursors for Orion and Ares Projects initiated (kickoff of RFPs) –
   Spring of 2004
• Exploration Systems Architecture Study – conducted
   Spring/Summer 2005
• Constellation Program Manager named October 2005
• First Cx Control Board – January 2006
• Cx Formulation Authorization Document - August 2006
• Contracts for Orion and Ares systems start – Summer 2006
• Cx Program Systems Requirements Review – Fall 2006
• Cx Program Systems Definition Review – March 2008
• Project PDRs underway
• Program PAR planned for Summer 2009
                                                                         3
Building on Proven Technologies
120
                                                             Launch Vehicle Comparisons                                                            Crew
                                                                                                                 Lunar
                                                                                                                 Lander
                                                                                                                                                   Lander
                                                                                                                 Earth Departure
         Overall Vehicle Height in Meters




90                                                                                                               Stage (EDS) (1 J-2X)
                                                                                                                 253 tons LOx/LH2
                                                                                                                                                   S-IVB
                                                                               Upper Stage                                                         (1 J-2 engine)
                                                                               (1 J-2X)                                                            110 t Lox/LH2
                                                                               127 tons LOx/LH2
60                                                                                                                                                 S-II
                                                                                                                                                   (5 J-2 engines)
                                                                                                                                                   450 t LOx/LH2
                                                                                                                 Core Stage
                                                                                                                 (6 RS-68B engines)
                                                                                                                 1590 tons LOx/LH2
                                                                               5 - segment
                                                                               shuttle derived                                                     S-IC
30
                                                                               solid rocket                                                        (5 F-1)
                                                                               booster                           5.5 segment                       1770 t LOx/RP
                                                                                                                 2 RSRBs




                                            Space Shuttle              Ares I                          Ares V                            Saturn V
             Height: 56m                                             Height: 98m                      Height: 109m                    Height: 111m
     Gross Liftoff Mass: 2040 tons                            Gross Liftoff Mass: 910 tons       Gross Liftoff Mass: 3310t     Gross Liftoff Mass: 2950 tons
                                                                                                   55 tons cargo to moon                45 tons to moon
                                            25 tons to LEO          22 tons to LEO                66 tons to moon in dual-              119 tons to LEO
                                                                                                  launch mode with Ares 1
                                                                                                      150 tons to LEO                                           4
NASA’s Exploration Roadmap
05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25…
        Initial Capability                                          Lunar Capability

       Lunar Robotic Missions                                         Lunar Outpost Buildup

R&T Development on ISS for Risk Reduction

  Commercial Orbital Transportation for ISS

Space Shuttle Operations


Ares and Orion Development

Operations Capability Development
(EVA Systems, Ground Ops, Mission Ops)

                           Ares & Orion Production and Operations

        Altair Lunar Lander Development

           Ares V & Earth Departure Stage

     Lunar Surface Systems Development
                                                                                              5
Systems of the Constellation Program
        Initial Capability                    Lunar Capability
                                Orion

   Ares I




                                                                Altair

                       EVA
                                                          EVA




                                         Ares V


Ground Operations   Mission Operations
                                                        Lunar Surface

                                                                         6
Agency/Constellation Organization
Level 1                                                NASA



     Exploration Systems            Space Operations                Science Mission              Aeronautics Research
     Mission Directorate            Mission Directorate               Directorate                 Mission Directorate


     Constellation Program



Level 2
                                                      Program
                                                      Manager




                                                                          Safety,
            Program              Operations,          Systems
                                                                        Reliability &           Information
           Planning &             Testing &         Engineering
                                                                          Quality                 Systems
             Control             Integration        & Integration
                                                                        Assurance

Level 3

                                   Extravehicular      Ground          Mission                           Lunar Surface
  Ares Project   Orion Project       Activities       Operations      Operations        Altair Project     Systems
                                      Project          Project         Project                              Project
                                                                                                                         7
Program Management Relationships
                                            NASA Administrator
                                                 Deputy

                                               NASA Associate
                                              Administrator (AA)                    Program
                                                                                  Commitment
                                                                                Agreement (PCA)

Space Operations Mission               Exploration Systems Mission
  Directorate Associate                   Directorate Associate                                   Center Directors
Administrator (SOMD AA)                 Administrator (ESMD AA)
                 Formulation
                Authorization                              Level 1 Program
               Document (FAD)                              Requirements &               Constellation Systems
                                                              Funding                      Division NASA
                  Program                                                                  Headquarters
                 Planning &
                 Reporting
                                             Constellation Program                                Project insight and
                                                   Manager                                         information flow


                                     Project                      Level 2 Project
                                Plans & Reporting             Requirements & Funding

        Coordinates                         Constellation Project
        Supports                                Managers                                                                8
CONSTELLATION’S WORKFORCE - CENTERS




                                                       9
As of 11/11/08
CONSTELLATION’S WORKFORCE -
                        CONTRACTORS




                                               10
As of 11/11/08
CxP Integration Roadmap – Path Forward
                                        Fiscal Year 2008                                            Fiscal Year 2009                                               Fiscal Year 2010                                          Fiscal Year 2011                                  Fiscal Year 2012
                                             Q1           Q2           Q3                   Q4            Q1                      Q2           Q3            Q4          Q1          Q2            Q3                Q4          Q1            Q2         Q3         Q4           Q1         Q2
                                                                                                                                                            ARES I-X                                 VM-2             AA-1                                        AA-3
                   Flight Tests
PA                & Simulations                                                                                                         PA-1    VM-1
RP
OP
GR                                          QPMR         QPMR                         QPMR                QPMR                   QPMR          QPMR         QPMR         QPMR      QPMR           QPMR               QPMR       QPMR           QPMR      QPMR        QPMR         QPMR       QPMR
                         ESMD
RO
AV                                                                   TRR                    TRR        TRR      TRR
MA                       Program
                                                                   4/17-18                 8/6-7     10/28-29 12/9-10r
 L                                             SRR/PPAR                                            SDR/PAR                                                             PDR              PDR
                                                                                                                                                                                   Synchronization                                    CDR                                         SIR
    Initial Capability




                                             APMC                                                                                                                                       6/10                                                                             APMC
                                                                            SDR                                                                 APMC u/r                                                             APMC                                     CDR
                         Projects           10/11/07                   Synchronization                                                                                                                                                                   Synchronization




                                                                                                                                                    KDP 1




                                                                                                                                                                                                             KDP 2
                                                                          6/16-17
                           • Orion                      IC Formulation Phase                                                                                                                       IC Implementation Phase
                           • Ares
                           • Ground Ops




                                                                                                                                                                                   KDP C




                                                                                                                                                                                                                                       KDP D
                                                                                   KDP B


                           • Mission Ops                                                                                           Project PDRs/NARs                                                                                                                     SIR
                           • EVA Systems

                                             Project SDRs/PNARs                                                                                                                                     Project CDRs/PRRs
                                                               Ares    Orion               MO GO                                EVA
                                                                                                                                 u/r
                           Design &
                           Analysis           IDAC 3                     IDAC-4A & B                                              IDAC 5                          IDAC 6                                             IDAC 7
E
X
                                                                                                                                                                                                              HLR                                                     Lunar
E                        Program                                                            LCCR
                                                                                                                                                                                                                                                                    Checkpoint
                                                                                           6/18-20                                                                                                          SRR 6/10
    Lunar Capability




C                                                                                                                 LC Formulation Phase
                          Human Lunar
U                         Return
T                         • Ares V                                           MCR                               APMC
                                                                                                       KDP A




                                                                                                                                                                                                                                               Lunar Projects SRR
                                               Pre-Project                  6/18-20
I                         • Altair
                                               Formulation                                                                                                         Project Formulation
                                                                                                                                                                                                                                                       u/r

O                         Core Lunar
N                         Infrastructure
                          • Lunar Surface                                                                                                                                                          LSS Review
                            Systems                                                                                                    Pre-Project Formulation
R                                           OMB
                                            Passback
                                                               2009 President
                                                               Budget Submit
                           2009 PBS
E                                                              to Congress
                                                                                                       OMB                             2010 President
S                          2010 PBS         PMR ’08/PPBE ‘10                                       Passback                            Budget Submit
                                                                                                                                       to Congress
O                                                                                                                                                                     OMB                  2011 President
                           2011 PBS                                                                        PMR ’09/PPBE ‘11                                       Passback                 Budget Submit
U                                                                                                                                                                                          to Congress                        OMB                2012 President
                                                                                                                You are here.




R                          2012 PBS                                                                                                                                    PMR ’10/PPBE ‘12
                                                                                                                                                                                                                          Passback               Budget Submit
                                                                                                                                                                                                                                                 to Congress                   OMB
C                          2013 PBS                                                                                                                                                                                                                                        Passback
                                                                                                                                                                                                                                                                                               2013 President
                                                                                                                                                                                                                                                                                               Budget Submit
                                                                                                                                                                                                                              PMR ’11/PPBE ‘13
E                                                                                                                                                                                                                                                                                              to Congress
                           2014 PBS
S                                                                                                                                                                                                                                                                               PMR ’12/PPBE ‘14
                                                                                                                                                                                                                                                                                                        11
Ares Test Flight                             Quarterly Program Management Review            PSRR / PPAR – Program System Requirements Review / Preliminary Program Approval Review LSCR – Lunar Surface Concept Review                                               Constellation Program Planning &Control
                                                                                            PSDR / PAR – Program System Definition Review / Program Approval Review                HLR / SRR – Human Lunar Return / System Readiness Review
Pad Abort (PA)/Ascent Abort (AA)             Top Risk Review
                                                                                            PDR / NAR – Preliminary Design Review / Non-advocate Review
                                                                                                                                                                                                                                                                                              Draft Version 33
Virtual Mission                              Agency Program Management Council              CDR / PRR - Critical Design Review / Production Readiness Review                                                                                                                     Updated: December 15, 2008
Stakeholders
White House
   •OSTP                Congress
    •OMB                 •Members                       Administrator   OCE
     •OIG                 • Staffers
                            •GAO
                                                    PAO                       PA&E


                                                   Office
                                                              NASA HQ
                                                    of
                                 Mission           Procure-                   S&MA
                                                    ment
                               Directorates
                                  •Programs                   OLA       OGC
         JSC &
                                   •Shuttle
   KSC   WSTF    ARC
                                     •ISS

GSFC               GRC                         External
   NASA Centers                                 Review
                                              Committees        Private Industry
LaRC              Dryden

  SSC    MSFC     JPL
          &
         MAF                                                                         12
PP&C Lessons Learned
• Start-up is hard
• Concurrent initiation AND accomplishment of work takes time
  and talent
   – Best practice – develop a plan and enact the plan
• Staffing is always key
• Develop requirements first – then review for accuracy
• Don’t underestimate the time it takes to coordinate among
  stakeholders
• Don’t underestimate the number of stakeholders
• Solicit feedback from external parties and greybeards
• Policy enactment is more complicated than policy
  development
• Open communication is a force multiplier
                                                                13
Program Contracts
   Integration

Project Management Challenge

           Wayne Thomas
    Chief, Contracts Integration Office
Acquisition Management Challenge


• Programs supported by multiple NASA Centers have an
  integration challenge to maintain a strategic program
  focus in contracts
• Contracts are typically awarded and managed at the
  project level by center procurement offices supporting
  the individual projects
• Need to ensure that Program and Agency objectives are
  supported by the Program’s contracts
• Need to ensure that contracts operate together in an
  efficient and cohesive fashion to successfully execute
  the Program

                                                           15
Major Constellation Prime Contracts
                                              FY08         FY09     FY10   FY11     FY12   FY13      FY14        FY15      FY16
                                                         Ares I-X                          Ares I-Y Or-1   Or-2 Or-3 Or-4 Or-5 Or-6 Or-7   Or-8

Cx Milestones
                                                                                                           IOC       FOC       PMR 08
                                                                                                                               Rev 1
                                                                     Ground Operations
               SPOC JOFOC for Cx Tasks

       GO ‘EGLS’ Cx Processing contract



                                                                     Mission Operations
  Facilities Development and Ops (FDOC)

            Mission Support Ops (MSOC)

  Integrated Mission Ops Contract (IMOC)

         NBL/SVMF Ops Contract (NSOC)


                                                                           Orion
                Sched A DDT&E for Orion

                    *Sched B Production
                * Sched C Sustaining Eng      *Options

                                                                           EVA
            DDT&E/Prod for 1 flt, Conf 1
                               st

   Option 2 Config 1 Prod and Sustaining
   Option 1 DDT&E/Prod for 1st flt, Conf. 2

                                                                           Ares 1
                      First Stage DDT&E

   First Stage Production/Sustaining Eng           Plan in Development
                             J-2X DDT&E

        J2-X Production/Sustaining Eng.            Plan in Development
                 Upper Stage Production
                                                                                                                                            16
 US Instrument Unit Avionics Production
Program Level Contract Integration


• CxP maintains a Program-level interface for
  acquisitions across NASA with a dedicated
  contracts integration function
• Staff function within PP&C office
  – Provides single point for acquisition related matters at
    the Program level
  – Program level acquisition interface with Level 3
    projects and with HQ Mission Directorates and Office
    of Procurement


                                                               17
Contracts Integration office

• Contracts Integration
   – Primary role is interface with CxP contracting offices at the
     various centers
   – Facilitate Program-level understanding of and consistency in
     strategic contract features and processes
   – Facilitate Program-level approvals
   – Integrate relevant Program procurement information
   – Support Agency-level acquisition planning for the Program
• Does not perform Contracting Office functions:
   – Execute or manage contracts
   – Focus is on programmatic issues not on procurement processes
     and regs


                                                                     18
Agency Strategic Acquisition Planning

• Program acquisition strategy must consider the broader
  agency impacts of the planned acquisitions
• Outcomes of a good strategy
   –   Cost effective execution of projects and programs
   –   Facilitate workforce transitions
   –   Maintain key NASA in-house capabilities
   –   Support NASA procurement tenets
   –   Help support Agency goal of ten healthy centers
• Agency-level reviews ensure broader aspects are
  considered
   – ESMD/SOMD Joint Integration Control Board (JICB) acquisition
     reviews
   – Acquisition Strategy Meeting (ASM) - 7120.5D milestone

                                                                    19
Lessons Learned

• Understand the difference between the contracts integration
  role and the procurement office role – they should be
  complimentary
• Key to success is communication –
   – Resist creating new Level 2 reporting or approval of requirements
   – Use existing communication forums and data sources to the
     maximum extent
• There are many stakeholders and they can have different
  interests and priorities for acquisition strategies
   – Expect acquisition strategy to evolve and mature to meet the broad
     range of project, program, and agency needs
   – Pre-briefs are useful to frame issues and develop the acquisition
     strategy

                                                                          20
Implementing
           7120.5D

  Project Management Challenge

             Charlie Stegemoeller
Director, Constellation Program Planning and Control
Constellation PP&C Organization
                                                 Director
                                            Deputy Director
                                           Associate Director
                                         Asst. for Security Mgmt.         ZB111




                                                          Schedules, Cost
 Management               Contracts Integration           Estimating, and             Resources
Systems Office                                          Assessments (SCEA)         Management Office
                    ZB2                           ZB                       ZB/LW                                ZB/LZ


                            Exploration Systems           Assessment Team          CxP Level II / Projects Level III
    Configuration                                          Assessment Team
                            Procurement Office
    Management
                                                         Cost Estimating Team              Level 2 Integration
                                                                                             and Analysis
 Information Systems        Ground Operations
                            Project Procurement                                          Program Integration
                                                            IMS/EVM Team                  Program Integration
                                                             IMS/EVM Team                      Project
                                                                                                Project
                                Ares Project              Analysis Integration              Other Projects
                             Procurement Office            Analysis Integration        Lunar Lander-Surf. Sys. etc


                                                                                             Orion Project
                                                                                              Orion Project

PP&C Office is responsible for tracking the
implementation of NPD 7120.5 – policies,
processes, tools, and records
                                                                                                                 22
Program Life Cycle




                     23
                      23
NPR 7120.5D Lessons Learned
•   Thoroughly study the NPR 7120.5D requirements and associated
    documentation
•   Your customers are the Convening Authorities –
     – Know what they want
•   Document your internal and independent review processes,
     – Identify implementation of requirements
•   Do not hold the SRB Site Review before you have a validated,
    integrated technical, cost and schedule baseline
•   Proactively set the agenda for the SRB Site Review
     – Set the stage, boundaries, objectives
•   Although NPR 7120.5D requirements can be “document centric,” the
    SRB is not all that interested in your documents
•   Find a way to minimize the overhead of providing data to the SRB
•   Understand the capabilities and limitations of the confidence level
    tools you are using

                                                                          24
Standard Engagement Approach

              Nominal Timeline                                         Road to KDP                                     KDP
Project Internal Review cycle       Project & SRB        Site Review            Findings and               APMC
(2-4 months)                        Prep for KDP         (5-10 days)            Response                   (1/2 day)
                                    (30-120 days)                               (<30 days)

• SRB (& others) participate as     • Respond to IR      • Project presents     • Quick report on major    • Site Review + 30
  observers during review             actions              summary of T, C,       findings to Project,       days
• Project includes T, C, S, R       • Respond to RFAs      S, R of Project        Center, etc. Site        • Final statement of
  entry/exit criteria as part of    • Complete actions     (presents Deltas       review <24 hours)          findings and
  Internal Board Event                for KDP              since IR)            • Briefings to Project –     recommendations
• At conclusion of IR, map path     • A: reconcile all   • Respond to RFAs        Program – ESMD             on KDP
  to KDP                              related            • Identify Open Work   • Prep for APMC
• SRB submits RFAs post-              cost/schedule      • TA’s + Centers       • Include Center’s POC
  conclusion of board and states      products with        report as part of      as needed
  opinion of Project readiness to     SRB team             site review          • Develop
  proceed to KDP                                         • SRB reports            recommendations for
• A: Projects develop                                      findings of            APMC
  cost/schedule products as                                cost/schedule        • Conduct DPMC
  required                                                 reconciliation
• Project submits Quick Look
  report up the chain at                 IR = Internal Review
  conclusion of Board &                  A: Action to Develop Process/Timeline R+R for ICE; Conf Level Products
  recommendation to proceed.

                                                                                                                             25
Standard Review Board
                    Engagement Timeline
      SRB observer role
                                                    “One pager” by Project, includes plan to KDP
   S/S Reviews
                      Internal
                      Project PDR

                                          RFAs               Findings
               SRB assessment
               of entry criteria to        SRB Site             “One pager” + 1 day (joint activity)
               Project/Program             Review                • Quick status
                                                                 • Only big issues, not concerns/observations
                                       Integrated
                                                                 • Initial ICE
                                                    SRB
                                                    PDR/NAR                                KDP
                              1–6
                              months                5 – 10 days               30 days
                                                    •Technical
                                                    •Cost
       “Pre-work”                                   •Schedule
                                                    •Risk       Briefings: P/p, CMC, DPMC, APMC
Model Development Joint
with IPAO/Project
ICA/ICE/ISA reconciliations                         Independent Life Cycle Review (ILCR)

                                                                                                                26
Driving Conditions for Constellation
• Program stood-up after Ares and Orion projects
• Agency re-alignment of policies and assignments
   – Concurrent with Program start-up
   – Ten healthy centers
   – 7120.5 Rev D issuance
• Performance measurement tools actively in design and
  development
   – EVMS
   – Confidence levels
   – Standing review boards
• Shuttle Program definition of retirement evolving
   – Resultant transfer of fixed costs


Fortunately . . . . . political support remained strong
                                                          27
PP&C Lessons Learned - Recap
• Start-up is hard
• Concurrent initiation AND accomplishment of work takes time
  and talent
   – Best practice – develop a plan and enact the plan
• Develop requirements first – then review for accuracy
• Staffing is always key
• Don’t underestimate the time it takes to coordinate among
  stakeholders
• Don’t underestimate the number of stakeholders
• Open communication is a force multiplier
• Policy enactment is more complicated than policy
  development
• Solicit feedback from external parties and greybeards         28
Questions?



         Constellation main page:
http://www.nasa.gov/mission_pages/const
         ellation/main/index.html
Exploration Systems Mission Directorate:
http://www.nasa.gov/directorates/esmd/ho
               me/index.html
Back up



          30
Project Roles

                    Host                                                Project Requirements
     Project                                 Project Systems
                   Center                                                  Documentation
                            • Ascent Module                           • CxP 70000 Constellation
Altair              JSC     • Descent Module                           Architecture Requirements
                            • Airlock                                  Document (CARD)

                            •   First Stage Element                   • CxP 70057 Ares Projects
                            •   Upper Stage Element                     Plan
Ares I             MSFC     •   Upper Stage Engine                    • CxP 72034 Ares SRD
                            •   Orion/Ares vehicle integration

                            •   Earth Departure Stage                 • CxP 70000 Constellation
                            •   Loiter Skirt                           Architecture Requirements
Ares V             MSFC     •   Interstage                             Document (CARD)
                            •   Solid Rocket Boosters
                            •   Core Stage

                            • Suit Systems (Configurations 1 and 2)   • CxP 72179 EVA Systems
Extravehicular              • Vehicle Interface Systems                 Project Plan
Activities (EVA)    JSC     • Tool and Equipment Systems              • CxP 72002 EVA Systems
Systems                                                                 SRD


                                                                                                  31
Project Roles continued
                   Host                                                 Project Requirements
    Project                            Project Systems
                  Center                                                   Documentation
                           Spacecraft Processing Element (SPE)         CxP 72120 Ground
                           Solid Rocket Processing Element (SRPE)      Operations Project (GOP)
                           Vertical Integration Element (VIE)          Project Plan
                           Mobil Launch Element (MLE)                  CxP 72006 GOP SRD
Ground                     Launch Pad Element (LPE)
                   KSC     Spacecraft Recover and Retrieval Element
Operations (GO)
                           (SRRE)
                           Command, Control & Communications
                           Element (CCCE)
                           Operations Support Element (OSE)

                           Elements (includes habitable volumes)       CxP 70000 Constellation
Lunar Surface
                   JSC     Surface Mobility Systems                    Architecture Requirements
Systems
                           In-situ Resource Development Systems        Document (CARD)
                           Mission Control Center System (MCCS)        CxP 72165 Mission
Mission                    Mission Operations Reconfiguration System   Operations (MO) Project
                   JSC
Operations (MO)            (MORS)                                      Plan
                           Constellation Training Element              CxP 72136 MO SRD
Orion –                    Launch Abort System (LAS)                   CxP 72008 CEV Project
(Crew                      Crew Module (CM)                            Plan
                   JSC
Exploration                Service Module (SM)                         CxP 72000 CEV SRD
Vehicle (CEV))             Spacecraft Adapter (SA)                                                32
Flow of Agency and ESMD
      Requirements
      U.S. Space Exploration Policy
         (NP-2004-01-334-HQ)


     NASA Authorization Act of 2005
            (P.L.109-155)


 Exploration Needs, Goals, and Objectives
       (ESMD-ENGO-01.08 Rev. A)

  Exploration Architecture Requirements
            Document (EARD)
      (ESMD-EARD-08.07 Rev. A)

       Constellation Program Plan
             (CxP 70003)

 Constellation Architecture Requirements
            Document (CARD)
                                            33
               (CxP 70000)
Program Authorization

• ESMD Formulation Authorization Document (FAD), July
  31, 2006
   – Authorized formulation of Orion, Ares I, Ground Operations,
     Mission Operations and Extravehicular Activity Projects
• ESMD Lunar Capability FAD, August 25, 2008
   – Authorized formulation of Ares V and Altair Projects
• CxP Program Plan approved by ESMD AA, October 17,
  2008
• Program Commitment Agreement to be authorized at
  completion of CxP Program Approval Review (key
  decision point 1)


                                                                   34

Contenu connexe

Plus de NASAPMC

Bejmuk bo
Bejmuk boBejmuk bo
Bejmuk boNASAPMC
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski johnNASAPMC
 
Yew manson
Yew mansonYew manson
Yew mansonNASAPMC
 
Wood frank
Wood frankWood frank
Wood frankNASAPMC
 
Wood frank
Wood frankWood frank
Wood frankNASAPMC
 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)NASAPMC
 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joeNASAPMC
 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuartNASAPMC
 
Stock gahm
Stock gahmStock gahm
Stock gahmNASAPMC
 
Snow lee
Snow leeSnow lee
Snow leeNASAPMC
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandraNASAPMC
 
Seftas krage
Seftas krageSeftas krage
Seftas krageNASAPMC
 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marcoNASAPMC
 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mikeNASAPMC
 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karleneNASAPMC
 
Rackley mike
Rackley mikeRackley mike
Rackley mikeNASAPMC
 
Paradis william
Paradis williamParadis william
Paradis williamNASAPMC
 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeffNASAPMC
 
O'keefe william
O'keefe williamO'keefe william
O'keefe williamNASAPMC
 
Muller ralf
Muller ralfMuller ralf
Muller ralfNASAPMC
 

Plus de NASAPMC (20)

Bejmuk bo
Bejmuk boBejmuk bo
Bejmuk bo
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski john
 
Yew manson
Yew mansonYew manson
Yew manson
 
Wood frank
Wood frankWood frank
Wood frank
 
Wood frank
Wood frankWood frank
Wood frank
 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)
 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joe
 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuart
 
Stock gahm
Stock gahmStock gahm
Stock gahm
 
Snow lee
Snow leeSnow lee
Snow lee
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandra
 
Seftas krage
Seftas krageSeftas krage
Seftas krage
 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marco
 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mike
 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karlene
 
Rackley mike
Rackley mikeRackley mike
Rackley mike
 
Paradis william
Paradis williamParadis william
Paradis william
 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeff
 
O'keefe william
O'keefe williamO'keefe william
O'keefe william
 
Muller ralf
Muller ralfMuller ralf
Muller ralf
 

Dernier

GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationMichael W. Hawkins
 
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...Patryk Bandurski
 
Azure Monitor & Application Insight to monitor Infrastructure & Application
Azure Monitor & Application Insight to monitor Infrastructure & ApplicationAzure Monitor & Application Insight to monitor Infrastructure & Application
Azure Monitor & Application Insight to monitor Infrastructure & ApplicationAndikSusilo4
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationSafe Software
 
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 3652toLead Limited
 
How to Remove Document Management Hurdles with X-Docs?
How to Remove Document Management Hurdles with X-Docs?How to Remove Document Management Hurdles with X-Docs?
How to Remove Document Management Hurdles with X-Docs?XfilesPro
 
Benefits Of Flutter Compared To Other Frameworks
Benefits Of Flutter Compared To Other FrameworksBenefits Of Flutter Compared To Other Frameworks
Benefits Of Flutter Compared To Other FrameworksSoftradix Technologies
 
SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024Scott Keck-Warren
 
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersEnhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersThousandEyes
 
Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Allon Mureinik
 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreternaman860154
 
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...shyamraj55
 
Install Stable Diffusion in windows machine
Install Stable Diffusion in windows machineInstall Stable Diffusion in windows machine
Install Stable Diffusion in windows machinePadma Pradeep
 
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking MenDelhi Call girls
 
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationBeyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationSafe Software
 
Breaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountBreaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountPuma Security, LLC
 
Key Features Of Token Development (1).pptx
Key  Features Of Token  Development (1).pptxKey  Features Of Token  Development (1).pptx
Key Features Of Token Development (1).pptxLBM Solutions
 
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...Neo4j
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)Gabriella Davis
 
08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking MenDelhi Call girls
 

Dernier (20)

GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day Presentation
 
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
 
Azure Monitor & Application Insight to monitor Infrastructure & Application
Azure Monitor & Application Insight to monitor Infrastructure & ApplicationAzure Monitor & Application Insight to monitor Infrastructure & Application
Azure Monitor & Application Insight to monitor Infrastructure & Application
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
 
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
 
How to Remove Document Management Hurdles with X-Docs?
How to Remove Document Management Hurdles with X-Docs?How to Remove Document Management Hurdles with X-Docs?
How to Remove Document Management Hurdles with X-Docs?
 
Benefits Of Flutter Compared To Other Frameworks
Benefits Of Flutter Compared To Other FrameworksBenefits Of Flutter Compared To Other Frameworks
Benefits Of Flutter Compared To Other Frameworks
 
SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024
 
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersEnhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
 
Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)
 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreter
 
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
 
Install Stable Diffusion in windows machine
Install Stable Diffusion in windows machineInstall Stable Diffusion in windows machine
Install Stable Diffusion in windows machine
 
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
 
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationBeyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
 
Breaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountBreaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path Mount
 
Key Features Of Token Development (1).pptx
Key  Features Of Token  Development (1).pptxKey  Features Of Token  Development (1).pptx
Key Features Of Token Development (1).pptx
 
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)
 
08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men
 

Cx p plan-panel

  • 1. Constellation Program Planning & Control Project Management Challenge Charlie Stegemoeller Director, Constellation Program Planning and Control Wayne Thomas Chief, Constellation Contracts Integration
  • 2. Constellation Program Planning and Control Objective: • Share the perspectives and lessons from standing up the Constellation Program within today’s Agency policies Topics: • Overview of the Constellation Program – Organizational Relationships – Lessons Learned • Program Contracts Integration • Implementation of 7120.5D 2
  • 3. Overview of Constellation Program Timeline of Program: • Vision for Space Exploration – Issued January 2004 • Precursors for Orion and Ares Projects initiated (kickoff of RFPs) – Spring of 2004 • Exploration Systems Architecture Study – conducted Spring/Summer 2005 • Constellation Program Manager named October 2005 • First Cx Control Board – January 2006 • Cx Formulation Authorization Document - August 2006 • Contracts for Orion and Ares systems start – Summer 2006 • Cx Program Systems Requirements Review – Fall 2006 • Cx Program Systems Definition Review – March 2008 • Project PDRs underway • Program PAR planned for Summer 2009 3
  • 4. Building on Proven Technologies 120 Launch Vehicle Comparisons Crew Lunar Lander Lander Earth Departure Overall Vehicle Height in Meters 90 Stage (EDS) (1 J-2X) 253 tons LOx/LH2 S-IVB Upper Stage (1 J-2 engine) (1 J-2X) 110 t Lox/LH2 127 tons LOx/LH2 60 S-II (5 J-2 engines) 450 t LOx/LH2 Core Stage (6 RS-68B engines) 1590 tons LOx/LH2 5 - segment shuttle derived S-IC 30 solid rocket (5 F-1) booster 5.5 segment 1770 t LOx/RP 2 RSRBs Space Shuttle Ares I Ares V Saturn V Height: 56m Height: 98m Height: 109m Height: 111m Gross Liftoff Mass: 2040 tons Gross Liftoff Mass: 910 tons Gross Liftoff Mass: 3310t Gross Liftoff Mass: 2950 tons 55 tons cargo to moon 45 tons to moon 25 tons to LEO 22 tons to LEO 66 tons to moon in dual- 119 tons to LEO launch mode with Ares 1 150 tons to LEO 4
  • 5. NASA’s Exploration Roadmap 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25… Initial Capability Lunar Capability Lunar Robotic Missions Lunar Outpost Buildup R&T Development on ISS for Risk Reduction Commercial Orbital Transportation for ISS Space Shuttle Operations Ares and Orion Development Operations Capability Development (EVA Systems, Ground Ops, Mission Ops) Ares & Orion Production and Operations Altair Lunar Lander Development Ares V & Earth Departure Stage Lunar Surface Systems Development 5
  • 6. Systems of the Constellation Program Initial Capability Lunar Capability Orion Ares I Altair EVA EVA Ares V Ground Operations Mission Operations Lunar Surface 6
  • 7. Agency/Constellation Organization Level 1 NASA Exploration Systems Space Operations Science Mission Aeronautics Research Mission Directorate Mission Directorate Directorate Mission Directorate Constellation Program Level 2 Program Manager Safety, Program Operations, Systems Reliability & Information Planning & Testing & Engineering Quality Systems Control Integration & Integration Assurance Level 3 Extravehicular Ground Mission Lunar Surface Ares Project Orion Project Activities Operations Operations Altair Project Systems Project Project Project Project 7
  • 8. Program Management Relationships NASA Administrator Deputy NASA Associate Administrator (AA) Program Commitment Agreement (PCA) Space Operations Mission Exploration Systems Mission Directorate Associate Directorate Associate Center Directors Administrator (SOMD AA) Administrator (ESMD AA) Formulation Authorization Level 1 Program Document (FAD) Requirements & Constellation Systems Funding Division NASA Program Headquarters Planning & Reporting Constellation Program Project insight and Manager information flow Project Level 2 Project Plans & Reporting Requirements & Funding Coordinates Constellation Project Supports Managers 8
  • 9. CONSTELLATION’S WORKFORCE - CENTERS 9 As of 11/11/08
  • 10. CONSTELLATION’S WORKFORCE - CONTRACTORS 10 As of 11/11/08
  • 11. CxP Integration Roadmap – Path Forward Fiscal Year 2008 Fiscal Year 2009 Fiscal Year 2010 Fiscal Year 2011 Fiscal Year 2012 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 ARES I-X VM-2 AA-1 AA-3 Flight Tests PA & Simulations PA-1 VM-1 RP OP GR QPMR QPMR QPMR QPMR QPMR QPMR QPMR QPMR QPMR QPMR QPMR QPMR QPMR QPMR QPMR QPMR QPMR ESMD RO AV TRR TRR TRR TRR MA Program 4/17-18 8/6-7 10/28-29 12/9-10r L SRR/PPAR SDR/PAR PDR PDR Synchronization CDR SIR Initial Capability APMC 6/10 APMC SDR APMC u/r APMC CDR Projects 10/11/07 Synchronization Synchronization KDP 1 KDP 2 6/16-17 • Orion IC Formulation Phase IC Implementation Phase • Ares • Ground Ops KDP C KDP D KDP B • Mission Ops Project PDRs/NARs SIR • EVA Systems Project SDRs/PNARs Project CDRs/PRRs Ares Orion MO GO EVA u/r Design & Analysis IDAC 3 IDAC-4A & B IDAC 5 IDAC 6 IDAC 7 E X HLR Lunar E Program LCCR Checkpoint 6/18-20 SRR 6/10 Lunar Capability C LC Formulation Phase Human Lunar U Return T • Ares V MCR APMC KDP A Lunar Projects SRR Pre-Project 6/18-20 I • Altair Formulation Project Formulation u/r O Core Lunar N Infrastructure • Lunar Surface LSS Review Systems Pre-Project Formulation R OMB Passback 2009 President Budget Submit 2009 PBS E to Congress OMB 2010 President S 2010 PBS PMR ’08/PPBE ‘10 Passback Budget Submit to Congress O OMB 2011 President 2011 PBS PMR ’09/PPBE ‘11 Passback Budget Submit U to Congress OMB 2012 President You are here. R 2012 PBS PMR ’10/PPBE ‘12 Passback Budget Submit to Congress OMB C 2013 PBS Passback 2013 President Budget Submit PMR ’11/PPBE ‘13 E to Congress 2014 PBS S PMR ’12/PPBE ‘14 11 Ares Test Flight Quarterly Program Management Review PSRR / PPAR – Program System Requirements Review / Preliminary Program Approval Review LSCR – Lunar Surface Concept Review Constellation Program Planning &Control PSDR / PAR – Program System Definition Review / Program Approval Review HLR / SRR – Human Lunar Return / System Readiness Review Pad Abort (PA)/Ascent Abort (AA) Top Risk Review PDR / NAR – Preliminary Design Review / Non-advocate Review Draft Version 33 Virtual Mission Agency Program Management Council CDR / PRR - Critical Design Review / Production Readiness Review Updated: December 15, 2008
  • 12. Stakeholders White House •OSTP Congress •OMB •Members Administrator OCE •OIG • Staffers •GAO PAO PA&E Office NASA HQ of Mission Procure- S&MA ment Directorates •Programs OLA OGC JSC & •Shuttle KSC WSTF ARC •ISS GSFC GRC External NASA Centers Review Committees Private Industry LaRC Dryden SSC MSFC JPL & MAF 12
  • 13. PP&C Lessons Learned • Start-up is hard • Concurrent initiation AND accomplishment of work takes time and talent – Best practice – develop a plan and enact the plan • Staffing is always key • Develop requirements first – then review for accuracy • Don’t underestimate the time it takes to coordinate among stakeholders • Don’t underestimate the number of stakeholders • Solicit feedback from external parties and greybeards • Policy enactment is more complicated than policy development • Open communication is a force multiplier 13
  • 14. Program Contracts Integration Project Management Challenge Wayne Thomas Chief, Contracts Integration Office
  • 15. Acquisition Management Challenge • Programs supported by multiple NASA Centers have an integration challenge to maintain a strategic program focus in contracts • Contracts are typically awarded and managed at the project level by center procurement offices supporting the individual projects • Need to ensure that Program and Agency objectives are supported by the Program’s contracts • Need to ensure that contracts operate together in an efficient and cohesive fashion to successfully execute the Program 15
  • 16. Major Constellation Prime Contracts FY08 FY09 FY10 FY11 FY12 FY13 FY14 FY15 FY16 Ares I-X Ares I-Y Or-1 Or-2 Or-3 Or-4 Or-5 Or-6 Or-7 Or-8 Cx Milestones IOC FOC PMR 08 Rev 1 Ground Operations SPOC JOFOC for Cx Tasks GO ‘EGLS’ Cx Processing contract Mission Operations Facilities Development and Ops (FDOC) Mission Support Ops (MSOC) Integrated Mission Ops Contract (IMOC) NBL/SVMF Ops Contract (NSOC) Orion Sched A DDT&E for Orion *Sched B Production * Sched C Sustaining Eng *Options EVA DDT&E/Prod for 1 flt, Conf 1 st Option 2 Config 1 Prod and Sustaining Option 1 DDT&E/Prod for 1st flt, Conf. 2 Ares 1 First Stage DDT&E First Stage Production/Sustaining Eng Plan in Development J-2X DDT&E J2-X Production/Sustaining Eng. Plan in Development Upper Stage Production 16 US Instrument Unit Avionics Production
  • 17. Program Level Contract Integration • CxP maintains a Program-level interface for acquisitions across NASA with a dedicated contracts integration function • Staff function within PP&C office – Provides single point for acquisition related matters at the Program level – Program level acquisition interface with Level 3 projects and with HQ Mission Directorates and Office of Procurement 17
  • 18. Contracts Integration office • Contracts Integration – Primary role is interface with CxP contracting offices at the various centers – Facilitate Program-level understanding of and consistency in strategic contract features and processes – Facilitate Program-level approvals – Integrate relevant Program procurement information – Support Agency-level acquisition planning for the Program • Does not perform Contracting Office functions: – Execute or manage contracts – Focus is on programmatic issues not on procurement processes and regs 18
  • 19. Agency Strategic Acquisition Planning • Program acquisition strategy must consider the broader agency impacts of the planned acquisitions • Outcomes of a good strategy – Cost effective execution of projects and programs – Facilitate workforce transitions – Maintain key NASA in-house capabilities – Support NASA procurement tenets – Help support Agency goal of ten healthy centers • Agency-level reviews ensure broader aspects are considered – ESMD/SOMD Joint Integration Control Board (JICB) acquisition reviews – Acquisition Strategy Meeting (ASM) - 7120.5D milestone 19
  • 20. Lessons Learned • Understand the difference between the contracts integration role and the procurement office role – they should be complimentary • Key to success is communication – – Resist creating new Level 2 reporting or approval of requirements – Use existing communication forums and data sources to the maximum extent • There are many stakeholders and they can have different interests and priorities for acquisition strategies – Expect acquisition strategy to evolve and mature to meet the broad range of project, program, and agency needs – Pre-briefs are useful to frame issues and develop the acquisition strategy 20
  • 21. Implementing 7120.5D Project Management Challenge Charlie Stegemoeller Director, Constellation Program Planning and Control
  • 22. Constellation PP&C Organization Director Deputy Director Associate Director Asst. for Security Mgmt. ZB111 Schedules, Cost Management Contracts Integration Estimating, and Resources Systems Office Assessments (SCEA) Management Office ZB2 ZB ZB/LW ZB/LZ Exploration Systems Assessment Team CxP Level II / Projects Level III Configuration Assessment Team Procurement Office Management Cost Estimating Team Level 2 Integration and Analysis Information Systems Ground Operations Project Procurement Program Integration IMS/EVM Team Program Integration IMS/EVM Team Project Project Ares Project Analysis Integration Other Projects Procurement Office Analysis Integration Lunar Lander-Surf. Sys. etc Orion Project Orion Project PP&C Office is responsible for tracking the implementation of NPD 7120.5 – policies, processes, tools, and records 22
  • 24. NPR 7120.5D Lessons Learned • Thoroughly study the NPR 7120.5D requirements and associated documentation • Your customers are the Convening Authorities – – Know what they want • Document your internal and independent review processes, – Identify implementation of requirements • Do not hold the SRB Site Review before you have a validated, integrated technical, cost and schedule baseline • Proactively set the agenda for the SRB Site Review – Set the stage, boundaries, objectives • Although NPR 7120.5D requirements can be “document centric,” the SRB is not all that interested in your documents • Find a way to minimize the overhead of providing data to the SRB • Understand the capabilities and limitations of the confidence level tools you are using 24
  • 25. Standard Engagement Approach Nominal Timeline Road to KDP KDP Project Internal Review cycle Project & SRB Site Review Findings and APMC (2-4 months) Prep for KDP (5-10 days) Response (1/2 day) (30-120 days) (<30 days) • SRB (& others) participate as • Respond to IR • Project presents • Quick report on major • Site Review + 30 observers during review actions summary of T, C, findings to Project, days • Project includes T, C, S, R • Respond to RFAs S, R of Project Center, etc. Site • Final statement of entry/exit criteria as part of • Complete actions (presents Deltas review <24 hours) findings and Internal Board Event for KDP since IR) • Briefings to Project – recommendations • At conclusion of IR, map path • A: reconcile all • Respond to RFAs Program – ESMD on KDP to KDP related • Identify Open Work • Prep for APMC • SRB submits RFAs post- cost/schedule • TA’s + Centers • Include Center’s POC conclusion of board and states products with report as part of as needed opinion of Project readiness to SRB team site review • Develop proceed to KDP • SRB reports recommendations for • A: Projects develop findings of APMC cost/schedule products as cost/schedule • Conduct DPMC required reconciliation • Project submits Quick Look report up the chain at IR = Internal Review conclusion of Board & A: Action to Develop Process/Timeline R+R for ICE; Conf Level Products recommendation to proceed. 25
  • 26. Standard Review Board Engagement Timeline SRB observer role “One pager” by Project, includes plan to KDP S/S Reviews Internal Project PDR RFAs Findings SRB assessment of entry criteria to SRB Site “One pager” + 1 day (joint activity) Project/Program Review • Quick status • Only big issues, not concerns/observations Integrated • Initial ICE SRB PDR/NAR KDP 1–6 months 5 – 10 days 30 days •Technical •Cost “Pre-work” •Schedule •Risk Briefings: P/p, CMC, DPMC, APMC Model Development Joint with IPAO/Project ICA/ICE/ISA reconciliations Independent Life Cycle Review (ILCR) 26
  • 27. Driving Conditions for Constellation • Program stood-up after Ares and Orion projects • Agency re-alignment of policies and assignments – Concurrent with Program start-up – Ten healthy centers – 7120.5 Rev D issuance • Performance measurement tools actively in design and development – EVMS – Confidence levels – Standing review boards • Shuttle Program definition of retirement evolving – Resultant transfer of fixed costs Fortunately . . . . . political support remained strong 27
  • 28. PP&C Lessons Learned - Recap • Start-up is hard • Concurrent initiation AND accomplishment of work takes time and talent – Best practice – develop a plan and enact the plan • Develop requirements first – then review for accuracy • Staffing is always key • Don’t underestimate the time it takes to coordinate among stakeholders • Don’t underestimate the number of stakeholders • Open communication is a force multiplier • Policy enactment is more complicated than policy development • Solicit feedback from external parties and greybeards 28
  • 29. Questions? Constellation main page: http://www.nasa.gov/mission_pages/const ellation/main/index.html Exploration Systems Mission Directorate: http://www.nasa.gov/directorates/esmd/ho me/index.html
  • 30. Back up 30
  • 31. Project Roles Host Project Requirements Project Project Systems Center Documentation • Ascent Module • CxP 70000 Constellation Altair JSC • Descent Module Architecture Requirements • Airlock Document (CARD) • First Stage Element • CxP 70057 Ares Projects • Upper Stage Element Plan Ares I MSFC • Upper Stage Engine • CxP 72034 Ares SRD • Orion/Ares vehicle integration • Earth Departure Stage • CxP 70000 Constellation • Loiter Skirt Architecture Requirements Ares V MSFC • Interstage Document (CARD) • Solid Rocket Boosters • Core Stage • Suit Systems (Configurations 1 and 2) • CxP 72179 EVA Systems Extravehicular • Vehicle Interface Systems Project Plan Activities (EVA) JSC • Tool and Equipment Systems • CxP 72002 EVA Systems Systems SRD 31
  • 32. Project Roles continued Host Project Requirements Project Project Systems Center Documentation Spacecraft Processing Element (SPE) CxP 72120 Ground Solid Rocket Processing Element (SRPE) Operations Project (GOP) Vertical Integration Element (VIE) Project Plan Mobil Launch Element (MLE) CxP 72006 GOP SRD Ground Launch Pad Element (LPE) KSC Spacecraft Recover and Retrieval Element Operations (GO) (SRRE) Command, Control & Communications Element (CCCE) Operations Support Element (OSE) Elements (includes habitable volumes) CxP 70000 Constellation Lunar Surface JSC Surface Mobility Systems Architecture Requirements Systems In-situ Resource Development Systems Document (CARD) Mission Control Center System (MCCS) CxP 72165 Mission Mission Mission Operations Reconfiguration System Operations (MO) Project JSC Operations (MO) (MORS) Plan Constellation Training Element CxP 72136 MO SRD Orion – Launch Abort System (LAS) CxP 72008 CEV Project (Crew Crew Module (CM) Plan JSC Exploration Service Module (SM) CxP 72000 CEV SRD Vehicle (CEV)) Spacecraft Adapter (SA) 32
  • 33. Flow of Agency and ESMD Requirements U.S. Space Exploration Policy (NP-2004-01-334-HQ) NASA Authorization Act of 2005 (P.L.109-155) Exploration Needs, Goals, and Objectives (ESMD-ENGO-01.08 Rev. A) Exploration Architecture Requirements Document (EARD) (ESMD-EARD-08.07 Rev. A) Constellation Program Plan (CxP 70003) Constellation Architecture Requirements Document (CARD) 33 (CxP 70000)
  • 34. Program Authorization • ESMD Formulation Authorization Document (FAD), July 31, 2006 – Authorized formulation of Orion, Ares I, Ground Operations, Mission Operations and Extravehicular Activity Projects • ESMD Lunar Capability FAD, August 25, 2008 – Authorized formulation of Ares V and Altair Projects • CxP Program Plan approved by ESMD AA, October 17, 2008 • Program Commitment Agreement to be authorized at completion of CxP Program Approval Review (key decision point 1) 34