SlideShare une entreprise Scribd logo
1  sur  13
Télécharger pour lire hors ligne
Standing
                                            Review Board




        PM Challenge 2009
      Independent Review in Action:
Adding Value to Orion through Independent
                 Review

  Mark Geyer, Orion Project Manager
Chet Sasaki, IPAO Orion Review Manager




                                                    1
Synopsis
                                                        Standing
                                                      Review Board


This presentation will:
• Describe how rigorous integrated
  cost/schedule/technical/risk assessments by the
  Orion Standing Review Board (SRB) are adding
  value to the Orion Project.
• It will show how, working together, the Board and
  Project are ensuring that the assessment is
  constructive, high quality, and independent.




                                                              2
Background
                                                               Standing
                                                             Review Board


• NASA’s Constellation Program (CxP) returns humans to the
  moon and provides logistical support to the International Space
  Station (ISS). In the more distant future, it will also enable
  manned missions to Mars.
• The CxP is comprised of integration elements and chartered
  Projects:
   – ARES – Constellation Launch Vehicle
   – Orion – Crew Exploration Vehicle
   – Ground Operations
   – Mission Operations
   – Extra-Vehicular Activity (EVA)
   – Altair – Lunar Lander (pre formulation)
• To help ensure that America’s next steps into space will be
  successful, NASA commissioned six CxP SRB’s, one for each of
  the Projects (except Altair) and the sixth for the Program.
                                                                     3
The Orion Project
                                                                 Standing
                                                               Review Board


• This Orion flight system is comprised of the following physical
  elements:
   – Crew Module
   – Service Module / Spacecraft Adapter
   – Launch Abort System (LAS)
• The Project is huge and complex requiring that it be well
  conceived, soundly planned, and properly executed
   – Project Management functions defined across entire
     agency
   – Unique internal/external visibility due to criticality of the
     mission and other long-term considerations (i.e. cost)
• The Project’s challenge is amplified because NASA has not
  built a new major space transportation system in over 30
  years.
                                                                       4
Initial Charge to Orion SRB
                                                        Standing
                                                      Review Board


• First CxP SRB Terms of Reference (ToR) was
  developed in February ’07 based on agreements
  between projects/CxP/ESMD, OCE, and IPAO that
  tailored NPR 7120.5D implementation.
• Challenge was to efficiently adapt the human programs
  processes to the NPR 7120.5D SRB approach:
   – Give maximum access of SRB to “in-process” project
      reviews and
   – Utilize SRB/Orion project meetings for topical
      discussions as driven by SRB interests.
• SRB selection process was handled by IPAO.
• First overview briefing to the Orion SRB was conducted
  in Feb 2007 prior to Project SRR Board.

                                                              5
Makeup of Orion SRB
                                                                                    Standing
                                                                                  Review Board

EPS                                                                  Gray Eng
Flight Operations & Human System Interface                          Consultant
Propulsion                                                          Consultant
Ground & Flight Software                                                LM
ICE                                                                    LaRC
Communications and Data Handling                                       JPL
Structures & Mechanisms                                               NESC
Mission Operations                                                  Consultant
ECLSS, Health, and Habitation                                       Consultant
Safety and Mission Assurance                                        Consultant
Avionics                                                             MEI Tech
Thermal Protection System                                             Sandia
Project Engineering Management and Launch Vehicle Integration       Lee & Assoc
Systems Engineering and Integration                                 Consultant
Ground Systems                                                      Consultant
Program and Mission Strategy, Development, Planning, and Analysis   Consultant
Schedule Risk and SE&I                                              Consultant
GNC                                                                    JPL

Aerothermal, Flt Test                                               Consultant
                                                                                          6
The SRB
                                                              Standing
                                                            Review Board

• Over the last two years, the SRB has conducted two
  comprehensive Key Decision Point (KDP) reviews, the
   • System Requirements Review (ESMD DPMC, July 2007)
   • System Definition Review / Preliminary-Non advocate
     Review (APMC, April 2008)
• Challenges for the SRB:
   – Assessments must be Constructive – looking for serious
     issues
   – Assessments must be High Quality – fact based and by
     experts
   – Assessments must be Independent – can’t grade your
     own work
• Scope of Relationship between Project and SRB: Work
  together on internal reviews as observers, formal reviews as
  participants, and project requested assessments as
  participants.
                                                                    7
The SRB Perspective
                                                               Standing
                                                             Review Board



• We have a strong desire to make a contribution to the
  Project/Agency by performing comprehensive reviews of the
  Project’s products and providing our inputs.
• The Project has highly qualified, conscientious, and energetic
  individuals, both managers and engineers.
• The Project has been open and candid in their dealings with us.
  They have offered us an opportunity to observe their work and
  internal reviews and have graciously and completely answered
  our questions and have taken our inputs seriously.
• The formal reviews have been responsive to our needs and
  specific requests. Their inputs are provided openly and
  discussions have been free, without defensiveness.
• The Project responded to our issues with competence and
  integrity, to the satisfaction of the Agency.
                                                                     8
Inputs from the SRB
                                                             Standing
                                                           Review Board


• Documents review (part of Project’s Internal Review process)
  – comments on details and general quality to the Project.
• Internal Reviews –Request For Actions (RFAs) and/or
  Questions & Comments to the Project.
• Formal Reviews – Formal Report and Briefing w/report out to:
   – Project/Program
   – Center Management
   – ESMD Management
   – Agency Management
• Project Requested Assessments – Written report to the
  Project.

                                                                   9
Breadth of SRB Findings
                                                          Standing
                                                        Review Board


• Program Requirements Stability
• Technical Resources Management (mass, power,
  instrumentation, etc)
• Integrated Test processes and planning (including flight
  test program)
• Budget/schedule adequacy and confidence
• System-specific architecture and design
• Operability
• Program integration issues and concerns




                                                               10
Reporting Challenges
                                                                   Standing
                                                                 Review Board


• Timing: Some perception that SRB outbriefings that
  lagged project decisions became less useful to agency
   – SDR: Project Board in August 2007, Project briefing
     to SRB in December 2007, SRB report to Project in
     February 2008, APMC/KDP-B (SDR/PNAR) in April
     2008.
   – Drivers:
      • Project: Major process changes to SDR to address criteria
        shortfalls (Mass) introduced a mass scrub that culminated in
        architecture reintegration and “rescoring” SDR internally in
        November 2008
      • SRB: Internal deliberations and processes take time.
        Particular challenge to implement Independent Cost
        Estimates during the time from project milestone completion
        to first SRB outbrief.

                                                                        11
ORION SDR
                      with Additional Review Milestones
                                                                                                                                             Standing
                                                                                                                                           Review Board


                                                                 CY2007                                   CY2008
 June      July            Aug             Sept            Oct           Nov          Dec          Jan         Feb         Mar            Apr
                                         Orion                         CPCB
SRR ESMD PMC                                                                                                                        SDR/PNAR
                                         SDR Board                 11/1POD Config
           7/16                   8/30                                                             Proj/Proj                            APMC 4/29
             SDR Kickoff                                                     SRB Reports                 ICMC
                                                                                                    ESMD DPMC
               Orion Formal SDR
               Orion Formal SDR
                                                                 SDR Document Update
                                                                 SDR Document Update

                                                                                      SRB Outbrief
                                                                                       12/4-12/7
                                                                                SRB Assessment
                                                                                SRB Assessment
                                                                                                         SRB Reporting
                                                                                                         SRB Reporting

                                 ZBV
                                             NASA Admin ZBV Status

        Mass Scrub
        Mass Scrub
                                  Risk Balancing Round 1 Buyback
                                  Risk Balancing                                                                                 Extension to allow
                                     DP Devt
                                     DP Devt
                                                         Round 2 Buyback
                                                                                                                                 for better integration
                                                                                                 Architecture/Integration
                                           Integration
                                                                          NASA Admin POD Results       Checkpoints
                                                                                                                                   CPCB   ERB CPCB
                                                   Integration
                                                                                                                                               4/22
                                                         CxP ISTIM          POD ERB

                                                                                            Orion DAC-2 (with 606c POD Config)
                                                                                            Orion DAC-2 (with 606c POD Config)




                                                                                                                                                    12
Orion Project SRB Experience
                                                                Standing
                                                              Review Board

• Excellent technical insights from board members
   – SRB member observations and “stories” extremely
     helpful in steering the project
• Independent validation of management processes
   – All SRB concerns previously identified in project risk
     management process or otherwise highlighted routinely
   – SRB discussions have the effect of elevating priorities or
     improving the emphasis on issue resolution
       • Examples: failure tolerance, LOC/LOM, mass management
• Agency confidence
   – Objectivity and credibility of SRB reporting and project
     responses yield increased confidence by agency
     executives (A, AA(s), OCE, OSMA, ESMD, centers) in
     ability of project to execute
   – Should derive similar long-term benefits from the external
     stakeholders (i.e. OMB, CBO, GAO, OIG, NAC, ASAP,
     NAS, etc)
                                                                     13

Contenu connexe

Tendances

Matt.gonzales
Matt.gonzalesMatt.gonzales
Matt.gonzales
NASAPMC
 
Thomas.coonce
Thomas.coonceThomas.coonce
Thomas.coonce
NASAPMC
 
Carmichael.kevin
Carmichael.kevinCarmichael.kevin
Carmichael.kevin
NASAPMC
 
Daniel.dvorak
Daniel.dvorakDaniel.dvorak
Daniel.dvorak
NASAPMC
 
Costello kenneth
Costello kennethCostello kenneth
Costello kenneth
NASAPMC
 
Chen.tim
Chen.timChen.tim
Chen.tim
NASAPMC
 
Esker.linda
Esker.lindaEsker.linda
Esker.linda
NASAPMC
 
Thomas.mc vittie
Thomas.mc vittieThomas.mc vittie
Thomas.mc vittie
NASAPMC
 
Hazen michael
Hazen michaelHazen michael
Hazen michael
NASAPMC
 
Corcoran webster
Corcoran websterCorcoran webster
Corcoran webster
NASAPMC
 
Bladwin.kristen
Bladwin.kristenBladwin.kristen
Bladwin.kristen
NASAPMC
 
Kremic.tibor
Kremic.tiborKremic.tibor
Kremic.tibor
NASAPMC
 
Woods.edwards.pm challenge bpr presentation 2012 v1
Woods.edwards.pm challenge bpr presentation 2012 v1Woods.edwards.pm challenge bpr presentation 2012 v1
Woods.edwards.pm challenge bpr presentation 2012 v1
NASAPMC
 
Armstrong
ArmstrongArmstrong
Armstrong
NASAPMC
 
Bilardo.vince
Bilardo.vinceBilardo.vince
Bilardo.vince
NASAPMC
 
David.oberhettinger
David.oberhettingerDavid.oberhettinger
David.oberhettinger
NASAPMC
 
Barth simpkins
Barth simpkinsBarth simpkins
Barth simpkins
NASAPMC
 
Backup darren elliott
Backup darren elliottBackup darren elliott
Backup darren elliott
NASAPMC
 
Majerowicz
MajerowiczMajerowicz
Majerowicz
NASAPMC
 
Harvey elliott
Harvey elliottHarvey elliott
Harvey elliott
NASAPMC
 

Tendances (20)

Matt.gonzales
Matt.gonzalesMatt.gonzales
Matt.gonzales
 
Thomas.coonce
Thomas.coonceThomas.coonce
Thomas.coonce
 
Carmichael.kevin
Carmichael.kevinCarmichael.kevin
Carmichael.kevin
 
Daniel.dvorak
Daniel.dvorakDaniel.dvorak
Daniel.dvorak
 
Costello kenneth
Costello kennethCostello kenneth
Costello kenneth
 
Chen.tim
Chen.timChen.tim
Chen.tim
 
Esker.linda
Esker.lindaEsker.linda
Esker.linda
 
Thomas.mc vittie
Thomas.mc vittieThomas.mc vittie
Thomas.mc vittie
 
Hazen michael
Hazen michaelHazen michael
Hazen michael
 
Corcoran webster
Corcoran websterCorcoran webster
Corcoran webster
 
Bladwin.kristen
Bladwin.kristenBladwin.kristen
Bladwin.kristen
 
Kremic.tibor
Kremic.tiborKremic.tibor
Kremic.tibor
 
Woods.edwards.pm challenge bpr presentation 2012 v1
Woods.edwards.pm challenge bpr presentation 2012 v1Woods.edwards.pm challenge bpr presentation 2012 v1
Woods.edwards.pm challenge bpr presentation 2012 v1
 
Armstrong
ArmstrongArmstrong
Armstrong
 
Bilardo.vince
Bilardo.vinceBilardo.vince
Bilardo.vince
 
David.oberhettinger
David.oberhettingerDavid.oberhettinger
David.oberhettinger
 
Barth simpkins
Barth simpkinsBarth simpkins
Barth simpkins
 
Backup darren elliott
Backup darren elliottBackup darren elliott
Backup darren elliott
 
Majerowicz
MajerowiczMajerowicz
Majerowicz
 
Harvey elliott
Harvey elliottHarvey elliott
Harvey elliott
 

En vedette

Brockhurst.lane
Brockhurst.laneBrockhurst.lane
Brockhurst.lane
NASAPMC
 
Backup norm.smith
Backup norm.smithBackup norm.smith
Backup norm.smith
NASAPMC
 
John.olson
John.olsonJohn.olson
John.olson
NASAPMC
 
John.emond
John.emondJohn.emond
John.emond
NASAPMC
 
K.pagel.beene
K.pagel.beeneK.pagel.beene
K.pagel.beene
NASAPMC
 
C null 01-17-2011
C null 01-17-2011C null 01-17-2011
C null 01-17-2011
NASAPMC
 
Patrick.guske.update
Patrick.guske.updatePatrick.guske.update
Patrick.guske.update
NASAPMC
 
Kirsch.mike
Kirsch.mikeKirsch.mike
Kirsch.mike
NASAPMC
 
Debbie.dusterwald
Debbie.dusterwaldDebbie.dusterwald
Debbie.dusterwald
NASAPMC
 
Harrison.g.poole.k
Harrison.g.poole.kHarrison.g.poole.k
Harrison.g.poole.k
NASAPMC
 
Inter pech bounds
Inter pech boundsInter pech bounds
Inter pech bounds
NASAPMC
 
Neiberding
NeiberdingNeiberding
Neiberding
NASAPMC
 
Serrato.be be
Serrato.be beSerrato.be be
Serrato.be be
NASAPMC
 
Coonce.tom
Coonce.tomCoonce.tom
Coonce.tom
NASAPMC
 
Dillon.r.tinsley.c.rogers.e
Dillon.r.tinsley.c.rogers.eDillon.r.tinsley.c.rogers.e
Dillon.r.tinsley.c.rogers.e
NASAPMC
 
B ackroyd
B ackroydB ackroyd
B ackroyd
NASAPMC
 
Patrick.guske.update
Patrick.guske.updatePatrick.guske.update
Patrick.guske.update
NASAPMC
 
Rippe.carpio
Rippe.carpioRippe.carpio
Rippe.carpio
NASAPMC
 

En vedette (20)

Brockhurst.lane
Brockhurst.laneBrockhurst.lane
Brockhurst.lane
 
Backup norm.smith
Backup norm.smithBackup norm.smith
Backup norm.smith
 
Hulett
HulettHulett
Hulett
 
John.olson
John.olsonJohn.olson
John.olson
 
John.emond
John.emondJohn.emond
John.emond
 
K.pagel.beene
K.pagel.beeneK.pagel.beene
K.pagel.beene
 
C null 01-17-2011
C null 01-17-2011C null 01-17-2011
C null 01-17-2011
 
Patrick.guske.update
Patrick.guske.updatePatrick.guske.update
Patrick.guske.update
 
Kirsch.mike
Kirsch.mikeKirsch.mike
Kirsch.mike
 
Debbie.dusterwald
Debbie.dusterwaldDebbie.dusterwald
Debbie.dusterwald
 
Harrison.g.poole.k
Harrison.g.poole.kHarrison.g.poole.k
Harrison.g.poole.k
 
Inter pech bounds
Inter pech boundsInter pech bounds
Inter pech bounds
 
Neiberding
NeiberdingNeiberding
Neiberding
 
Serrato.be be
Serrato.be beSerrato.be be
Serrato.be be
 
Coonce.tom
Coonce.tomCoonce.tom
Coonce.tom
 
Dillon.r.tinsley.c.rogers.e
Dillon.r.tinsley.c.rogers.eDillon.r.tinsley.c.rogers.e
Dillon.r.tinsley.c.rogers.e
 
Heard
HeardHeard
Heard
 
B ackroyd
B ackroydB ackroyd
B ackroyd
 
Patrick.guske.update
Patrick.guske.updatePatrick.guske.update
Patrick.guske.update
 
Rippe.carpio
Rippe.carpioRippe.carpio
Rippe.carpio
 

Similaire à Geyer.m.sasaki.c (20)

Ortiz.james
Ortiz.jamesOrtiz.james
Ortiz.james
 
Keer.beth
Keer.bethKeer.beth
Keer.beth
 
Keer.beth
Keer.bethKeer.beth
Keer.beth
 
C armstrong tbyers
C armstrong tbyersC armstrong tbyers
C armstrong tbyers
 
Charles.armstrong
Charles.armstrongCharles.armstrong
Charles.armstrong
 
Amer.tahani
Amer.tahaniAmer.tahani
Amer.tahani
 
oakland county parks cost recovery
oakland county parks cost recoveryoakland county parks cost recovery
oakland county parks cost recovery
 
Mukai
MukaiMukai
Mukai
 
Ingoldsby.k.lee.y
Ingoldsby.k.lee.yIngoldsby.k.lee.y
Ingoldsby.k.lee.y
 
Daniel.dvorak
Daniel.dvorakDaniel.dvorak
Daniel.dvorak
 
Amer bill steve
Amer bill steveAmer bill steve
Amer bill steve
 
Amer bill steve
Amer bill steveAmer bill steve
Amer bill steve
 
Hihn.jarius
Hihn.jariusHihn.jarius
Hihn.jarius
 
Vonnie simonsen
Vonnie simonsenVonnie simonsen
Vonnie simonsen
 
Doug.sander
Doug.sanderDoug.sander
Doug.sander
 
Owners Project Requirements Overview Presentation
Owners Project Requirements   Overview PresentationOwners Project Requirements   Overview Presentation
Owners Project Requirements Overview Presentation
 
Saltzman.john
Saltzman.johnSaltzman.john
Saltzman.john
 
Saltzman.john
Saltzman.johnSaltzman.john
Saltzman.john
 
Lean Six Sigma Green Belt Services Certification Brochure
Lean Six Sigma Green Belt Services Certification BrochureLean Six Sigma Green Belt Services Certification Brochure
Lean Six Sigma Green Belt Services Certification Brochure
 
Calloway amer v2
Calloway amer v2Calloway amer v2
Calloway amer v2
 

Plus de NASAPMC

Bejmuk bo
Bejmuk boBejmuk bo
Bejmuk bo
NASAPMC
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski john
NASAPMC
 
Yew manson
Yew mansonYew manson
Yew manson
NASAPMC
 
Wood frank
Wood frankWood frank
Wood frank
NASAPMC
 
Wood frank
Wood frankWood frank
Wood frank
NASAPMC
 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)
NASAPMC
 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joe
NASAPMC
 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuart
NASAPMC
 
Stock gahm
Stock gahmStock gahm
Stock gahm
NASAPMC
 
Snow lee
Snow leeSnow lee
Snow lee
NASAPMC
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandra
NASAPMC
 
Seftas krage
Seftas krageSeftas krage
Seftas krage
NASAPMC
 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marco
NASAPMC
 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mike
NASAPMC
 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karlene
NASAPMC
 
Rackley mike
Rackley mikeRackley mike
Rackley mike
NASAPMC
 
Paradis william
Paradis williamParadis william
Paradis william
NASAPMC
 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeff
NASAPMC
 
O'keefe william
O'keefe williamO'keefe william
O'keefe william
NASAPMC
 
Muller ralf
Muller ralfMuller ralf
Muller ralf
NASAPMC
 

Plus de NASAPMC (20)

Bejmuk bo
Bejmuk boBejmuk bo
Bejmuk bo
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski john
 
Yew manson
Yew mansonYew manson
Yew manson
 
Wood frank
Wood frankWood frank
Wood frank
 
Wood frank
Wood frankWood frank
Wood frank
 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)
 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joe
 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuart
 
Stock gahm
Stock gahmStock gahm
Stock gahm
 
Snow lee
Snow leeSnow lee
Snow lee
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandra
 
Seftas krage
Seftas krageSeftas krage
Seftas krage
 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marco
 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mike
 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karlene
 
Rackley mike
Rackley mikeRackley mike
Rackley mike
 
Paradis william
Paradis williamParadis william
Paradis william
 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeff
 
O'keefe william
O'keefe williamO'keefe william
O'keefe william
 
Muller ralf
Muller ralfMuller ralf
Muller ralf
 

Dernier

Artificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsArtificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and Myths
Joaquim Jorge
 
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Safe Software
 
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
?#DUbAI#??##{{(☎️+971_581248768%)**%*]'#abortion pills for sale in dubai@
 

Dernier (20)

presentation ICT roal in 21st century education
presentation ICT roal in 21st century educationpresentation ICT roal in 21st century education
presentation ICT roal in 21st century education
 
Polkadot JAM Slides - Token2049 - By Dr. Gavin Wood
Polkadot JAM Slides - Token2049 - By Dr. Gavin WoodPolkadot JAM Slides - Token2049 - By Dr. Gavin Wood
Polkadot JAM Slides - Token2049 - By Dr. Gavin Wood
 
2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...
 
Top 10 Most Downloaded Games on Play Store in 2024
Top 10 Most Downloaded Games on Play Store in 2024Top 10 Most Downloaded Games on Play Store in 2024
Top 10 Most Downloaded Games on Play Store in 2024
 
AWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of TerraformAWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of Terraform
 
Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...
 
Top 5 Benefits OF Using Muvi Live Paywall For Live Streams
Top 5 Benefits OF Using Muvi Live Paywall For Live StreamsTop 5 Benefits OF Using Muvi Live Paywall For Live Streams
Top 5 Benefits OF Using Muvi Live Paywall For Live Streams
 
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, AdobeApidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
 
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...
 
A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?
 
Strategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherStrategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a Fresher
 
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
 
Artificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsArtificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and Myths
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024
 
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost SavingRepurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
 
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
 
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
 
Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)
 
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
 

Geyer.m.sasaki.c

  • 1. Standing Review Board PM Challenge 2009 Independent Review in Action: Adding Value to Orion through Independent Review Mark Geyer, Orion Project Manager Chet Sasaki, IPAO Orion Review Manager 1
  • 2. Synopsis Standing Review Board This presentation will: • Describe how rigorous integrated cost/schedule/technical/risk assessments by the Orion Standing Review Board (SRB) are adding value to the Orion Project. • It will show how, working together, the Board and Project are ensuring that the assessment is constructive, high quality, and independent. 2
  • 3. Background Standing Review Board • NASA’s Constellation Program (CxP) returns humans to the moon and provides logistical support to the International Space Station (ISS). In the more distant future, it will also enable manned missions to Mars. • The CxP is comprised of integration elements and chartered Projects: – ARES – Constellation Launch Vehicle – Orion – Crew Exploration Vehicle – Ground Operations – Mission Operations – Extra-Vehicular Activity (EVA) – Altair – Lunar Lander (pre formulation) • To help ensure that America’s next steps into space will be successful, NASA commissioned six CxP SRB’s, one for each of the Projects (except Altair) and the sixth for the Program. 3
  • 4. The Orion Project Standing Review Board • This Orion flight system is comprised of the following physical elements: – Crew Module – Service Module / Spacecraft Adapter – Launch Abort System (LAS) • The Project is huge and complex requiring that it be well conceived, soundly planned, and properly executed – Project Management functions defined across entire agency – Unique internal/external visibility due to criticality of the mission and other long-term considerations (i.e. cost) • The Project’s challenge is amplified because NASA has not built a new major space transportation system in over 30 years. 4
  • 5. Initial Charge to Orion SRB Standing Review Board • First CxP SRB Terms of Reference (ToR) was developed in February ’07 based on agreements between projects/CxP/ESMD, OCE, and IPAO that tailored NPR 7120.5D implementation. • Challenge was to efficiently adapt the human programs processes to the NPR 7120.5D SRB approach: – Give maximum access of SRB to “in-process” project reviews and – Utilize SRB/Orion project meetings for topical discussions as driven by SRB interests. • SRB selection process was handled by IPAO. • First overview briefing to the Orion SRB was conducted in Feb 2007 prior to Project SRR Board. 5
  • 6. Makeup of Orion SRB Standing Review Board EPS Gray Eng Flight Operations & Human System Interface Consultant Propulsion Consultant Ground & Flight Software LM ICE LaRC Communications and Data Handling JPL Structures & Mechanisms NESC Mission Operations Consultant ECLSS, Health, and Habitation Consultant Safety and Mission Assurance Consultant Avionics MEI Tech Thermal Protection System Sandia Project Engineering Management and Launch Vehicle Integration Lee & Assoc Systems Engineering and Integration Consultant Ground Systems Consultant Program and Mission Strategy, Development, Planning, and Analysis Consultant Schedule Risk and SE&I Consultant GNC JPL Aerothermal, Flt Test Consultant 6
  • 7. The SRB Standing Review Board • Over the last two years, the SRB has conducted two comprehensive Key Decision Point (KDP) reviews, the • System Requirements Review (ESMD DPMC, July 2007) • System Definition Review / Preliminary-Non advocate Review (APMC, April 2008) • Challenges for the SRB: – Assessments must be Constructive – looking for serious issues – Assessments must be High Quality – fact based and by experts – Assessments must be Independent – can’t grade your own work • Scope of Relationship between Project and SRB: Work together on internal reviews as observers, formal reviews as participants, and project requested assessments as participants. 7
  • 8. The SRB Perspective Standing Review Board • We have a strong desire to make a contribution to the Project/Agency by performing comprehensive reviews of the Project’s products and providing our inputs. • The Project has highly qualified, conscientious, and energetic individuals, both managers and engineers. • The Project has been open and candid in their dealings with us. They have offered us an opportunity to observe their work and internal reviews and have graciously and completely answered our questions and have taken our inputs seriously. • The formal reviews have been responsive to our needs and specific requests. Their inputs are provided openly and discussions have been free, without defensiveness. • The Project responded to our issues with competence and integrity, to the satisfaction of the Agency. 8
  • 9. Inputs from the SRB Standing Review Board • Documents review (part of Project’s Internal Review process) – comments on details and general quality to the Project. • Internal Reviews –Request For Actions (RFAs) and/or Questions & Comments to the Project. • Formal Reviews – Formal Report and Briefing w/report out to: – Project/Program – Center Management – ESMD Management – Agency Management • Project Requested Assessments – Written report to the Project. 9
  • 10. Breadth of SRB Findings Standing Review Board • Program Requirements Stability • Technical Resources Management (mass, power, instrumentation, etc) • Integrated Test processes and planning (including flight test program) • Budget/schedule adequacy and confidence • System-specific architecture and design • Operability • Program integration issues and concerns 10
  • 11. Reporting Challenges Standing Review Board • Timing: Some perception that SRB outbriefings that lagged project decisions became less useful to agency – SDR: Project Board in August 2007, Project briefing to SRB in December 2007, SRB report to Project in February 2008, APMC/KDP-B (SDR/PNAR) in April 2008. – Drivers: • Project: Major process changes to SDR to address criteria shortfalls (Mass) introduced a mass scrub that culminated in architecture reintegration and “rescoring” SDR internally in November 2008 • SRB: Internal deliberations and processes take time. Particular challenge to implement Independent Cost Estimates during the time from project milestone completion to first SRB outbrief. 11
  • 12. ORION SDR with Additional Review Milestones Standing Review Board CY2007 CY2008 June July Aug Sept Oct Nov Dec Jan Feb Mar Apr Orion CPCB SRR ESMD PMC SDR/PNAR SDR Board 11/1POD Config 7/16 8/30 Proj/Proj APMC 4/29 SDR Kickoff SRB Reports ICMC ESMD DPMC Orion Formal SDR Orion Formal SDR SDR Document Update SDR Document Update SRB Outbrief 12/4-12/7 SRB Assessment SRB Assessment SRB Reporting SRB Reporting ZBV NASA Admin ZBV Status Mass Scrub Mass Scrub Risk Balancing Round 1 Buyback Risk Balancing Extension to allow DP Devt DP Devt Round 2 Buyback for better integration Architecture/Integration Integration NASA Admin POD Results Checkpoints CPCB ERB CPCB Integration 4/22 CxP ISTIM POD ERB Orion DAC-2 (with 606c POD Config) Orion DAC-2 (with 606c POD Config) 12
  • 13. Orion Project SRB Experience Standing Review Board • Excellent technical insights from board members – SRB member observations and “stories” extremely helpful in steering the project • Independent validation of management processes – All SRB concerns previously identified in project risk management process or otherwise highlighted routinely – SRB discussions have the effect of elevating priorities or improving the emphasis on issue resolution • Examples: failure tolerance, LOC/LOM, mass management • Agency confidence – Objectivity and credibility of SRB reporting and project responses yield increased confidence by agency executives (A, AA(s), OCE, OSMA, ESMD, centers) in ability of project to execute – Should derive similar long-term benefits from the external stakeholders (i.e. OMB, CBO, GAO, OIG, NAC, ASAP, NAS, etc) 13