National Aeronautics and Space Administration




     A Practical Approach for Resource
     Loading Your Schedule
       NASA - Marshall Space Flight Center

       Office of Strategic Analysis & Communication

       Performance Analysis & Integration Office

       Project Planning & Analysis Team




       Greg Smith (Smith & Associates, LLC)



     www.nasa.gov




Used with Permission
Would Clint Eastwood carry an unloaded gun? So why
    do you have an unloaded schedule?

    •     What is resource loading?

    •     Why would I want to resource load my schedule?

    •     Why might I not want to resource load my schedule?

    •     How would I resource load my schedule if I chose to do so?                       You’ve got to ask yourself one
                                                                                             question: ‘Do I feel lucky?’




National Aeronautics and Space Administration                   A Practical Approach for Resource Loading Your Schedule     2
What is resource loading?
         Resource loading is:

              o Building a list of resources (e.g. people or skills, materials, equipment, money) and

              o Allocating those resources to tasks in a schedule

         Resources can have a rate (i.e. $ per unit) or not

              o Without a rate, one can partially assess the viability of a plan

                          Resource availability


              o With a rate, one can more fully assess the viability of a plan

                          Funding requirements


                          Cost and schedule integration




National Aeronautics and Space Administration                          A Practical Approach for Resource Loading Your Schedule   3
Why would I want to resource load my schedule?
        Integrates the budget with the work – creates a better estimate

        Creates an analysis tool for “what if” and directed changes

        Provides cash flow and funding profiles

        Identifies “what” you need, “how much” you need , and “when” you need it

        Ensures you haven’t left out something necessary

        Workforce planning & coordination

              Balance workload versus workforce

              Identify surplus & deficits

              Generate inputs for PPBE process

        Makes EVM implementation easier

        Aids in Risk Management (e.g. effectiveness of mitigation, cost and schedule impacts)


National Aeronautics and Space Administration                     A Practical Approach for Resource Loading Your Schedule   4
Why might I not want to resource load my schedule?
         Too early in Development / Formulation

         Not sure what resources are needed

         Too much effort required

         Don’t have the skills or tools                                          Don't just do
                                                                                something, stand
                                                                                    there.
         Don’t want anyone to know…

         None of the reasons “why to” apply to me




National Aeronautics and Space Administration        A Practical Approach for Resource Loading Your Schedule   5
Questions to consider before resource loading
         Will my tasks be fixed in duration? If not, what are the duration drivers?

         Will the number of resources assigned to my tasks be fixed? If not, what are the assignment
          drivers?

         Is the amount of Work fixed for each task? If not, what are the Work drivers?

         Will adding or removing resources or overtime to my task affect the duration of the task?

         What types of resources are at my disposal?

     If you intend to use costs when resource loading
         What are my resource costs?
                                                                                                             This romantic stuff is
         How will the costs for my resources be accrued?                                                  really tough. I can't wait
                                                                                                            to get back to shooting
                                                                                                                   and killing.
         Do I need to consider overhead costs? If so, then how?




                                                                Quote made during the filming of “Bridges of Madison County”



National Aeronautics and Space Administration                         A Practical Approach for Resource Loading Your Schedule           6
Never trust anyone on
                                                               an Italian movie. I know
                                                               about these things. Stay
                                                                   away from special
                                                                effects and explosives.

    Tools - Options


                                                                                              Both methods
                                                                                                 facilitate
                                                                                             assignments by
                                                                                              fractional FTE
                                                                                                 or WYE



                   Convention:                     Convention:
                1.0 = 1 equivalent              100% = 1 equivalent
                      person                         person




National Aeronautics and Space Administration                  A Practical Approach for Resource Loading Your Schedule   7
Tools - Options




National Aeronautics and Space Administration   A Practical Approach for Resource Loading Your Schedule   8
Tools - Options




           This option can also be set at the Task level




National Aeronautics and Space Administration              A Practical Approach for Resource Loading Your Schedule   9
Tools - Options




                                                 ‘Soft’
                                                 Option




            This option can also be set at the Task level



National Aeronautics and Space Administration               A Practical Approach for Resource Loading Your Schedule   10
Tools - Options




National Aeronautics and Space Administration   A Practical Approach for Resource Loading Your Schedule   11
Tools - Options




                                                          Tools – Change Working Time




National Aeronautics and Space Administration   A Practical Approach for Resource Loading Your Schedule   12
Resource Loading Method Examples
         Resources can be created and defined by

              Person                            ID      Resource Name            T                                              They say marriages are
                                                    1    Joe Blow                 W                                              made in Heaven. But so
                                                    2    I. M. Cross              W                                              is thunder and lightning.
                                                    3    U. R. Knott              W
                                                    4    Jane Doe                 W
                                                    5    Lois Lane                W
                                                    6    Clark Kent               W



              Skill                            ID      Resource Name         T
                                                1       Structural Engineer   W
                                                2       System Engineer       W
                                                3       Mechanical Engineer   W
                                                4       Electrical Engineer   W
                                                5       Project Manager       W
                                                6       Admin Assis tant      W


                                                                         ID           Resource         Resource Description            T
              Group, Team, or Organization                                           Name
                                                                         1            ER00       PROPULSION SYSTEMS DEPARTMENT W
                                                                         2            ER01            Propulsion Sy stems Department W
                                                                         3            ER02       PROPULSION SYSTEMS DEPARTMENT W
                                                                         4            ER21       PROPULSION SYSTEMS DEPARTMENT W
                                                                         5            ER23       PROPULSION SYSTEMS DEPARTMENT W
                                                                          6           ER24       PROPULSION SYSTEMS DEPARTMENT W
                                                                          7           ER30       PROPULSION SYSTEMS DEPARTMENT W
                                                                          8           ER31       PROPULSION SYSTEMS DEPARTMENT W
                                                                          9           ER32       PROPULSION SYSTEMS DEPARTMENT W
                                                                         10           ER33       PROPULSION SYSTEMS DEPARTMENT W
                                                                         11           ER34       PROPULSION SYSTEMS DEPARTMENT W
                                                                         12           ER41       PROPULSION SYSTEMS DEPARTMENT W
                                                                         13           ER42       PROPULSION SYSTEMS DEPARTMENT W
                                                                         14           ER43       PROPULSION SYSTEMS DEPARTMENT W
                                                                         15           ER51       PROPULSION SYSTEMS DEPARTMENT W
                                                                         16           ER52       PROPULSION SYSTEMS DEPARTMENT W


National Aeronautics and Space Administration                                                     A Practical Approach for Resource Loading Your Schedule    13
Defining Resources




                      Common fields used to describe, identify, sort, group, organize, or codify




National Aeronautics and Space Administration                       A Practical Approach for Resource Loading Your Schedule   14
Defining Resources


                                                   Resources types can be defined as



                                                      Work – people and equipment



                                                      Material – consumable supplies and bulk material



                                                      Cost – dollars (or other currency)




These resource types determine how resource calculations are performed depending upon the
                       Task Type and ‘Effort Driven’ options selected



National Aeronautics and Space Administration                             A Practical Approach for Resource Loading Your Schedule   15
Defining Resources
                                                                               Aids in
                                                                              balancing
                                                                              work load




                                                   Max Units - the maximum units of a resource that is available
                                                    at any given time during the project

                                                   Std Rate – the cost per unit displayed for standard time

                                                   Ovt Rate – the cost per unit displayed for overtime
                        Aids in
                      determining
                         costs                     Cost/Use – the cost for each resource assignment instance

                                                       Once only for each Material Type resource assignment

                                                       Per Unit for Work Type resources




National Aeronautics and Space Administration                               A Practical Approach for Resource Loading Your Schedule   16
Defining Resources

                                                   Costs are accrued

                                                        At the start of a resource assignment

                                                        At the end of a resource assignment

                                                        Evenly across the duration of the resource assignment




                                                   Choose Base Calendar from the drop down box

                                                   Calendars are defined under Tools – Change Working Time

                                                   Applies to the resource assignment




National Aeronautics and Space Administration                                    A Practical Approach for Resource Loading Your Schedule   17
Resource Loading Method Examples
         Resources can be allocated to different types of schedule tasks



              Hammock




              Summary




              Detailed




National Aeronautics and Space Administration                     A Practical Approach for Resource Loading Your Schedule   18
Assigning Resources


                                                Step 2. Select Resource Button




 Step 1. Select Task




                                                                      Step 3. Select Resource




                             Repeat Steps 3 through 5 for each resource to be assigned




National Aeronautics and Space Administration                                                   A Practical Approach for Resource Loading Your Schedule   19
Simplified Resource Loading Calculation Matrix

                                                       Task Type                    Effort Driven?          Resource Type                                          Results

                                                                      Fixed Work
                Action              Fixed Duration      Fixed Units       (1)      Yes          No   Work     Material       Cost          Work            Units              Duration      Cost


           Assign Resource                 X                 X            X        X             X    X                                  Calculated        Enter             Unchanged    Calculated

                   or                      X                 X            X        X             X               X                          N/A            Enter             Unchanged    Calculated

          Remove Resource                  X                 X            X        X             X                             X            N/A             N/A              Unchanged      Enter




           Change Units (2)                X                                       X             X    X                                  Calculated        Enter             Unchanged    Calculated

                                                             X                     X             X    X                                 Unchanged          Enter             Calculated   Unchanged

                                                                          X        X                  X                                  Unchanged         Enter             Calculated   Unchanged

                                           X                 X            X        X             X               X                          N/A            Enter             Unchanged    Calculated




           Change Work (3)                 X                                       X             X    X                                    Enter         Calculated          Unchanged    Calculated

                                                             X            X        X             X    X                                    Enter        Unchanged            Calculated   Calculated




         Change Duration (3)               X                              X        X                  X                                  Unchanged       Calculated            Enter      Unchanged
                                           X                                                     X    X                                  Calculated     Unchanged              Enter      Calculated
                                                             X                     X             X    X                                  Calculated     Unchanged              Enter      Calculated




      (1) If selected, Effort Driven 'Yes' selection is mandatory
      (2) Action has no impact on Cost Type Resources
      (3) Action has no impact on Material or Cost Type Resources



National Aeronautics and Space Administration                                                                            A Practical Approach for Resource Loading Your Schedule                       20
Now what? After all that, what do I get for my efforts?
        Grouped by Resource,                    User selects what data items
     showing each task assignment                        to see here                                                      This film cost $31
                                                                                                                       million. With that kind
                                                                                                                       of money I could have
                                                                                                                            invaded some
                                                                                                                               country.




                                                                                    Red font indicates over
                                                                                    allocation of resources




                                                                                   In this example, we see
                                                                                  the most people working
                                                                                    at any one time (Peak
                                                                                  Units), the percentage of
                                                                                    time the total available
                                                                                  resource is assigned (%
                                                                                       Alloc), and the total
                                                                                    hours to be worked by
                                                                                      that resource (Work)
National Aeronautics and Space Administration                                  A Practical Approach for Resource Loading Your Schedule           21
Over Allocated
                                                   Amount

                  Max Units from
                  Resource Sheet




                                                        Available for other work
                                                                                                 Peak number of
                                                                                                  this resource
                                                                                                 assigned during
                                                                                                   this period




National Aeronautics and Space Administration    A Practical Approach for Resource Loading Your Schedule           22
What do I do with this information?

        Determine if I have enough of the right type of resources available to do the work as scheduled

        Justify a schedule shift to accommodate resource availability

        Support decisions to acquire additional resources

        Balance workload

        Coordinate activities within a project and between multiple projects

        Provide data to support annual budget process (i.e. PPBE)

        Negotiate the addition of “unfunded mandates”

        Analyze changes to schedule and resource requirements

        And…




National Aeronautics and Space Administration                     A Practical Approach for Resource Loading Your Schedule   23
In Summary…

        Resource loading isn’t for everyone

        If you decide resource loading is for you, decide if you want resource management capability
         only or both resource and cost management capability

        Ask questions to understand your resources, tasks, and desired data outputs (i.e. prepare)

        Set up your software options and load your resource data

        Make assignments and analyze data – adjust as necessary

        You are now prepared to answer ‘what if’ questions regarding changes in funding, schedule, or
         resource requirements
                                                                                                Go ahead, make my day.
        DEFEND YOUR POSITION!




National Aeronautics and Space Administration                    A Practical Approach for Resource Loading Your Schedule   24
National Aeronautics and Space Administration   Your Title Here   25

Contenu connexe

Plus de NASAPMC

Yew manson
Yew mansonYew manson
Yew mansonNASAPMC
 
Wood frank
Wood frankWood frank
Wood frankNASAPMC
 
Wood frank
Wood frankWood frank
Wood frankNASAPMC
 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)NASAPMC
 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joeNASAPMC
 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuartNASAPMC
 
Stock gahm
Stock gahmStock gahm
Stock gahmNASAPMC
 
Snow lee
Snow leeSnow lee
Snow leeNASAPMC
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandraNASAPMC
 
Seftas krage
Seftas krageSeftas krage
Seftas krageNASAPMC
 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marcoNASAPMC
 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mikeNASAPMC
 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karleneNASAPMC
 
Rackley mike
Rackley mikeRackley mike
Rackley mikeNASAPMC
 
Paradis william
Paradis williamParadis william
Paradis williamNASAPMC
 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeffNASAPMC
 
O'keefe william
O'keefe williamO'keefe william
O'keefe williamNASAPMC
 
Muller ralf
Muller ralfMuller ralf
Muller ralfNASAPMC
 
Mulenburg jerry
Mulenburg jerryMulenburg jerry
Mulenburg jerryNASAPMC
 
Mitskevich amanda
Mitskevich amandaMitskevich amanda
Mitskevich amandaNASAPMC
 

Plus de NASAPMC (20)

Yew manson
Yew mansonYew manson
Yew manson
 
Wood frank
Wood frankWood frank
Wood frank
 
Wood frank
Wood frankWood frank
Wood frank
 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)
 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joe
 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuart
 
Stock gahm
Stock gahmStock gahm
Stock gahm
 
Snow lee
Snow leeSnow lee
Snow lee
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandra
 
Seftas krage
Seftas krageSeftas krage
Seftas krage
 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marco
 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mike
 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karlene
 
Rackley mike
Rackley mikeRackley mike
Rackley mike
 
Paradis william
Paradis williamParadis william
Paradis william
 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeff
 
O'keefe william
O'keefe williamO'keefe william
O'keefe william
 
Muller ralf
Muller ralfMuller ralf
Muller ralf
 
Mulenburg jerry
Mulenburg jerryMulenburg jerry
Mulenburg jerry
 
Mitskevich amanda
Mitskevich amandaMitskevich amanda
Mitskevich amanda
 

Dernier

Real Time Object Detection Using Open CV
Real Time Object Detection Using Open CVReal Time Object Detection Using Open CV
Real Time Object Detection Using Open CVKhem
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsEnterprise Knowledge
 
Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024The Digital Insurer
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024Rafal Los
 
How to convert PDF to text with Nanonets
How to convert PDF to text with NanonetsHow to convert PDF to text with Nanonets
How to convert PDF to text with Nanonetsnaman860154
 
🐬 The future of MySQL is Postgres 🐘
🐬  The future of MySQL is Postgres   🐘🐬  The future of MySQL is Postgres   🐘
🐬 The future of MySQL is Postgres 🐘RTylerCroy
 
Artificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsArtificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsJoaquim Jorge
 
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Drew Madelung
 
Automating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps ScriptAutomating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps Scriptwesley chun
 
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Miguel Araújo
 
Understanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdfUnderstanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdfUK Journal
 
Breaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountBreaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountPuma Security, LLC
 
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking MenDelhi Call girls
 
CNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of ServiceCNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of Servicegiselly40
 
Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)wesley chun
 
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfThe Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfEnterprise Knowledge
 
Advantages of Hiring UIUX Design Service Providers for Your Business
Advantages of Hiring UIUX Design Service Providers for Your BusinessAdvantages of Hiring UIUX Design Service Providers for Your Business
Advantages of Hiring UIUX Design Service Providers for Your BusinessPixlogix Infotech
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024The Digital Insurer
 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreternaman860154
 
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Igalia
 

Dernier (20)

Real Time Object Detection Using Open CV
Real Time Object Detection Using Open CVReal Time Object Detection Using Open CV
Real Time Object Detection Using Open CV
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI Solutions
 
Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024
 
How to convert PDF to text with Nanonets
How to convert PDF to text with NanonetsHow to convert PDF to text with Nanonets
How to convert PDF to text with Nanonets
 
🐬 The future of MySQL is Postgres 🐘
🐬  The future of MySQL is Postgres   🐘🐬  The future of MySQL is Postgres   🐘
🐬 The future of MySQL is Postgres 🐘
 
Artificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsArtificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and Myths
 
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
 
Automating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps ScriptAutomating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps Script
 
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
 
Understanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdfUnderstanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdf
 
Breaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountBreaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path Mount
 
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
 
CNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of ServiceCNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of Service
 
Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)
 
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfThe Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
 
Advantages of Hiring UIUX Design Service Providers for Your Business
Advantages of Hiring UIUX Design Service Providers for Your BusinessAdvantages of Hiring UIUX Design Service Providers for Your Business
Advantages of Hiring UIUX Design Service Providers for Your Business
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024
 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreter
 
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
 

James.smith

  • 1. National Aeronautics and Space Administration A Practical Approach for Resource Loading Your Schedule NASA - Marshall Space Flight Center Office of Strategic Analysis & Communication Performance Analysis & Integration Office Project Planning & Analysis Team Greg Smith (Smith & Associates, LLC) www.nasa.gov Used with Permission
  • 2. Would Clint Eastwood carry an unloaded gun? So why do you have an unloaded schedule? • What is resource loading? • Why would I want to resource load my schedule? • Why might I not want to resource load my schedule? • How would I resource load my schedule if I chose to do so? You’ve got to ask yourself one question: ‘Do I feel lucky?’ National Aeronautics and Space Administration A Practical Approach for Resource Loading Your Schedule 2
  • 3. What is resource loading?  Resource loading is: o Building a list of resources (e.g. people or skills, materials, equipment, money) and o Allocating those resources to tasks in a schedule  Resources can have a rate (i.e. $ per unit) or not o Without a rate, one can partially assess the viability of a plan  Resource availability o With a rate, one can more fully assess the viability of a plan  Funding requirements  Cost and schedule integration National Aeronautics and Space Administration A Practical Approach for Resource Loading Your Schedule 3
  • 4. Why would I want to resource load my schedule?  Integrates the budget with the work – creates a better estimate  Creates an analysis tool for “what if” and directed changes  Provides cash flow and funding profiles  Identifies “what” you need, “how much” you need , and “when” you need it  Ensures you haven’t left out something necessary  Workforce planning & coordination  Balance workload versus workforce  Identify surplus & deficits  Generate inputs for PPBE process  Makes EVM implementation easier  Aids in Risk Management (e.g. effectiveness of mitigation, cost and schedule impacts) National Aeronautics and Space Administration A Practical Approach for Resource Loading Your Schedule 4
  • 5. Why might I not want to resource load my schedule?  Too early in Development / Formulation  Not sure what resources are needed  Too much effort required  Don’t have the skills or tools Don't just do something, stand there.  Don’t want anyone to know…  None of the reasons “why to” apply to me National Aeronautics and Space Administration A Practical Approach for Resource Loading Your Schedule 5
  • 6. Questions to consider before resource loading  Will my tasks be fixed in duration? If not, what are the duration drivers?  Will the number of resources assigned to my tasks be fixed? If not, what are the assignment drivers?  Is the amount of Work fixed for each task? If not, what are the Work drivers?  Will adding or removing resources or overtime to my task affect the duration of the task?  What types of resources are at my disposal? If you intend to use costs when resource loading  What are my resource costs? This romantic stuff is  How will the costs for my resources be accrued? really tough. I can't wait to get back to shooting and killing.  Do I need to consider overhead costs? If so, then how? Quote made during the filming of “Bridges of Madison County” National Aeronautics and Space Administration A Practical Approach for Resource Loading Your Schedule 6
  • 7. Never trust anyone on an Italian movie. I know about these things. Stay away from special effects and explosives. Tools - Options Both methods facilitate assignments by fractional FTE or WYE Convention: Convention: 1.0 = 1 equivalent 100% = 1 equivalent person person National Aeronautics and Space Administration A Practical Approach for Resource Loading Your Schedule 7
  • 8. Tools - Options National Aeronautics and Space Administration A Practical Approach for Resource Loading Your Schedule 8
  • 9. Tools - Options This option can also be set at the Task level National Aeronautics and Space Administration A Practical Approach for Resource Loading Your Schedule 9
  • 10. Tools - Options ‘Soft’ Option This option can also be set at the Task level National Aeronautics and Space Administration A Practical Approach for Resource Loading Your Schedule 10
  • 11. Tools - Options National Aeronautics and Space Administration A Practical Approach for Resource Loading Your Schedule 11
  • 12. Tools - Options Tools – Change Working Time National Aeronautics and Space Administration A Practical Approach for Resource Loading Your Schedule 12
  • 13. Resource Loading Method Examples  Resources can be created and defined by Person ID Resource Name T They say marriages are 1 Joe Blow W made in Heaven. But so 2 I. M. Cross W is thunder and lightning. 3 U. R. Knott W 4 Jane Doe W 5 Lois Lane W 6 Clark Kent W Skill ID Resource Name T 1 Structural Engineer W 2 System Engineer W 3 Mechanical Engineer W 4 Electrical Engineer W 5 Project Manager W 6 Admin Assis tant W ID Resource Resource Description T Group, Team, or Organization Name 1 ER00 PROPULSION SYSTEMS DEPARTMENT W 2 ER01 Propulsion Sy stems Department W 3 ER02 PROPULSION SYSTEMS DEPARTMENT W 4 ER21 PROPULSION SYSTEMS DEPARTMENT W 5 ER23 PROPULSION SYSTEMS DEPARTMENT W 6 ER24 PROPULSION SYSTEMS DEPARTMENT W 7 ER30 PROPULSION SYSTEMS DEPARTMENT W 8 ER31 PROPULSION SYSTEMS DEPARTMENT W 9 ER32 PROPULSION SYSTEMS DEPARTMENT W 10 ER33 PROPULSION SYSTEMS DEPARTMENT W 11 ER34 PROPULSION SYSTEMS DEPARTMENT W 12 ER41 PROPULSION SYSTEMS DEPARTMENT W 13 ER42 PROPULSION SYSTEMS DEPARTMENT W 14 ER43 PROPULSION SYSTEMS DEPARTMENT W 15 ER51 PROPULSION SYSTEMS DEPARTMENT W 16 ER52 PROPULSION SYSTEMS DEPARTMENT W National Aeronautics and Space Administration A Practical Approach for Resource Loading Your Schedule 13
  • 14. Defining Resources Common fields used to describe, identify, sort, group, organize, or codify National Aeronautics and Space Administration A Practical Approach for Resource Loading Your Schedule 14
  • 15. Defining Resources  Resources types can be defined as Work – people and equipment Material – consumable supplies and bulk material Cost – dollars (or other currency) These resource types determine how resource calculations are performed depending upon the Task Type and ‘Effort Driven’ options selected National Aeronautics and Space Administration A Practical Approach for Resource Loading Your Schedule 15
  • 16. Defining Resources Aids in balancing work load  Max Units - the maximum units of a resource that is available at any given time during the project  Std Rate – the cost per unit displayed for standard time  Ovt Rate – the cost per unit displayed for overtime Aids in determining costs  Cost/Use – the cost for each resource assignment instance  Once only for each Material Type resource assignment  Per Unit for Work Type resources National Aeronautics and Space Administration A Practical Approach for Resource Loading Your Schedule 16
  • 17. Defining Resources  Costs are accrued  At the start of a resource assignment  At the end of a resource assignment  Evenly across the duration of the resource assignment  Choose Base Calendar from the drop down box  Calendars are defined under Tools – Change Working Time  Applies to the resource assignment National Aeronautics and Space Administration A Practical Approach for Resource Loading Your Schedule 17
  • 18. Resource Loading Method Examples  Resources can be allocated to different types of schedule tasks Hammock Summary Detailed National Aeronautics and Space Administration A Practical Approach for Resource Loading Your Schedule 18
  • 19. Assigning Resources Step 2. Select Resource Button Step 1. Select Task Step 3. Select Resource Repeat Steps 3 through 5 for each resource to be assigned National Aeronautics and Space Administration A Practical Approach for Resource Loading Your Schedule 19
  • 20. Simplified Resource Loading Calculation Matrix Task Type Effort Driven? Resource Type Results Fixed Work Action Fixed Duration Fixed Units (1) Yes No Work Material Cost Work Units Duration Cost Assign Resource X X X X X X Calculated Enter Unchanged Calculated or X X X X X X N/A Enter Unchanged Calculated Remove Resource X X X X X X N/A N/A Unchanged Enter Change Units (2) X X X X Calculated Enter Unchanged Calculated X X X X Unchanged Enter Calculated Unchanged X X X Unchanged Enter Calculated Unchanged X X X X X X N/A Enter Unchanged Calculated Change Work (3) X X X X Enter Calculated Unchanged Calculated X X X X X Enter Unchanged Calculated Calculated Change Duration (3) X X X X Unchanged Calculated Enter Unchanged X X X Calculated Unchanged Enter Calculated X X X X Calculated Unchanged Enter Calculated (1) If selected, Effort Driven 'Yes' selection is mandatory (2) Action has no impact on Cost Type Resources (3) Action has no impact on Material or Cost Type Resources National Aeronautics and Space Administration A Practical Approach for Resource Loading Your Schedule 20
  • 21. Now what? After all that, what do I get for my efforts? Grouped by Resource, User selects what data items showing each task assignment to see here This film cost $31 million. With that kind of money I could have invaded some country. Red font indicates over allocation of resources In this example, we see the most people working at any one time (Peak Units), the percentage of time the total available resource is assigned (% Alloc), and the total hours to be worked by that resource (Work) National Aeronautics and Space Administration A Practical Approach for Resource Loading Your Schedule 21
  • 22. Over Allocated Amount Max Units from Resource Sheet Available for other work Peak number of this resource assigned during this period National Aeronautics and Space Administration A Practical Approach for Resource Loading Your Schedule 22
  • 23. What do I do with this information?  Determine if I have enough of the right type of resources available to do the work as scheduled  Justify a schedule shift to accommodate resource availability  Support decisions to acquire additional resources  Balance workload  Coordinate activities within a project and between multiple projects  Provide data to support annual budget process (i.e. PPBE)  Negotiate the addition of “unfunded mandates”  Analyze changes to schedule and resource requirements  And… National Aeronautics and Space Administration A Practical Approach for Resource Loading Your Schedule 23
  • 24. In Summary…  Resource loading isn’t for everyone  If you decide resource loading is for you, decide if you want resource management capability only or both resource and cost management capability  Ask questions to understand your resources, tasks, and desired data outputs (i.e. prepare)  Set up your software options and load your resource data  Make assignments and analyze data – adjust as necessary  You are now prepared to answer ‘what if’ questions regarding changes in funding, schedule, or resource requirements Go ahead, make my day.  DEFEND YOUR POSITION! National Aeronautics and Space Administration A Practical Approach for Resource Loading Your Schedule 24
  • 25. National Aeronautics and Space Administration Your Title Here 25