SlideShare une entreprise Scribd logo
1  sur  37
Télécharger pour lire hors ligne
Rapid, Collaborative Planning
                    for Global Teams
                through Project Design

                                 Bryan R. Moser
                               bryan@gpdesign.com


                        NASA Challenge 2009
                               February 24-25, 2009



    Slide 1




Global Project Design © 2009                          www.gpdesign.com
Outline                     1. The Challenge of Global Projects

                               2. Project Design:
                                  Rapid, Accurate, & Shared Plans 
                                  including Forecast of Coordination

                               3. Case Study:  
                                  Global Product Development

                               4. Conclusion




       Slide 2



Global Project Design © 2009                   NASA Challenge 2009     www.gpdesign.com
1. The Challenge of Global Projects




                        NASA Challenge 2009




    Slide 3




Global Project Design © 2009                  www.gpdesign.com
Challenges of                  Teams from different time zones, work cultures, 
Global Projects                 costs, and abilities.

                                Subsystems and services to be integrated in an 
                                overall solution, yet the “central” team does not 
                                have complete control

                                Costs and risks from coordination, 
                                communication, re‐work, and quality are 40% or 
                                greater of real effort

                                Expected Results difficult to predict with 
                                significantly greater consequences if ignored


        Slide 4



 Global Project Design © 2009                NASA Challenge 2009           www.gpdesign.com
Work In 1909:                   Ways of Working
 An Industrial                    Standard Work
     Age                          Narrow specialties
                                  Expert management
                                  Automated resources




                                           Communication, Uncertainty,
                                              & Adaptive Behavior
                                                 are Avoided
        Slide 5



 Global Project Design © 2009                 NASA Challenge 2009   www.gpdesign.com
The Missing Half of Plans is
  Century old                              Coordination
  assumptions 
    strongly 
   embedded


False precision of 
 detail becomes 
  substitute for 
  awareness & 
adaptive learning                                          The Gantt Chart Circa 1914



                                  Not included in century old methods:
                                     Complex Dependence amongst activities
                                     Communication & Meetings
                                     Decisions, Exceptions, and Re-work
                                     Travel, Time Zones, and Workdays
          Slide 6                    Reasons for Waiting related to others

   Global Project Design © 2009            NASA Challenge 2009                          www.gpdesign.com
2. Project Design:
     Rapid, Accurate, & Shared Plans
    including Forecast of Coordination


                        NASA Challenge 2009




    Slide 7




Global Project Design © 2009                  www.gpdesign.com
Planning and 
Designing Are 
Very Different
                                          Plan                                  Design
                                  Verb. To work out in
                                                                       Verb. To create the form or
                                    some detail how
                                                                       structure of something in a
                                something is to be done or
                                                                         skillful or artistic way.
                                       organized.


                                   Planning may be sufficient for routine, repeatable
                                   projects with limited uncertainty

                                   DESIGN is essential to optimize performance and
                                   manage risk in enterprise initiatives




    Slide 8


 Global Project Design © 2009                    NASA Challenge 2009                     www.gpdesign.com
Cost
                                  (M$)
Project Design:
                                 24
                                                                                       Pre-Launch
    Multiple                                                                            Forecasts
  Forecasts are                                      1. Project Model
                                                                                            Business
                                                       & Simulation
   prototype                     21
                                                                                             Result
                                                                                              Typical
“crashes” of real                     Option 1
     project                                                                               Likely Result
                                      Trade-off
                                      Trade-
                                       for time                                         with As-Is Behavior
                                 18                       Optimized
                                                            Plan
                                                       Feasible & Focused
                                 15                    for Targeted Scope            2. Design Iteration
                                                                                       & Optimization
                                         Business
                                          Target
                                         Hoped For
                                 12
                                                          Option 2                            3. Trade-Off Dialogue
                                                          Trade-off
                                                          Trade-                                on Feasible Plans
                                                           for cost




                                                     18               24                 28                32         36             38
         Slide 9
                                                                                                                 Duration (months)

  Global Project Design © 2009                                 NASA Challenge 2009                                     www.gpdesign.com
Scope:
  Locations, 
Teams (OBS), 
Product (PBS), 
     and 
Phases (WBS)




        Slide 10



 Global Project Design © 2009   NASA Challenge 2009   www.gpdesign.com
Architecture:
   Complex 
 dependence 
(concurrent & 
   mutual ) 




        Slide 11



 Global Project Design © 2009   NASA Challenge 2009   www.gpdesign.com
Real‐time 
Collaborative 
 Modeling 

 In different 
  languages
       & 
points of view




        Slide 12



 Global Project Design © 2009   NASA Challenge 2009   www.gpdesign.com
Project Design
                                                         DESIGNER
                                Visual models to capture project & complexity
                                • Top-down & linked to strategy
                                • Product, work, & teams
                                • Global roles & priorities
                                • Concurrent dependencies




  Smart Dialogue & Team Collaboration                                                   SIMULATOR
                                                                          Unique insight from predictive analytics
                                                                          • Analyzes coordination effort & costs
                                                                          • Real-world behavior & uncertainty
                                                                          • Constraints of team distribution
                                                                          • Detailed output from hi-level input




                                                     FORECAST
                                Review of realistic plans, scenarios & options
                                •Product & phase schedules
                                •Team progress, efforts, costs
                                •Concurrency, wait, & re-work
     Slide 13
                                • opportunities & risk                                                   Global Project Design ©
                                                                                                                            2009
                                                                                                             www.gpdesign.com
Simulation 
   generates 
forecasts rapidly

    Includes 
  coordination 
effort, costs and 
schedule impact




         Slide 14



  Global Project Design © 2009   NASA Challenge 2009   www.gpdesign.com
Teams examine 
Forecasts from 
    multiple 
  viewpoints:  
  WBS & PBS




         Slide 15



  Global Project Design © 2009   NASA Challenge 2009   www.gpdesign.com
Coordination is 
  real effort. 

   Impact on 
schedule clearly 
    visible.




         Slide 16



  Global Project Design © 2009   NASA Challenge 2009   www.gpdesign.com
Progress 
 Forecasts




                                                                               Drawings
                                                                               Drawings

                                                                              Documents
                                                                              Documents


                                                                                Modules
                                                                                Modules


                                                                                  Tests
                                                                                  Tests


                                                                                  Parts
                                                                                  Parts




                                                                            Progress in
                                                                             Progress in
                              Percent of Effort
                               Percent of Effort                          Real World Units,
                                                                          Real World Units,
       Slide 17        Shown with range of standard
                       Shown with range of standard                            not just
                                                                               not just
                     deviation and high/low of forecasts
                     deviation and high/low of forecasts                 Spending & Percent
                                                                         Spending & Percent

Global Project Design © 2009                       NASA Challenge 2009      www.gpdesign.com
Frequent                                Raw FTE                             Wait          Coord          Go‐Live                 Cost
                                 Model #     hrs         Forecast Effort hrs    %              %             date                    $                                     Description                       Realistic?
   Iterations                     114             4704                 6891            8%             11%      12/24/07 $                    258,692 Added meeting to first modeling approach      no

   & What If                      131
                                  138
                                                  4704
                                                  4600
                                                                       6838
                                                                       5735
                                                                                       7%
                                                                                       1%
                                                                                                      23%
                                                                                                      9%
                                                                                                               12/12/07 $                    257,368 Execute Commit not hard gateway
                                                                                                               02/19/08 $                    287,472 simple assignments no mutual deps
                                                                                                                                                                                                   no
                                                                                                                                                                                                   no

   Scenarios                      139             4600                 6450            9%             9%       02/14/08 $                    325,420 simple assignments & 1 mutual dep             somewhat
                                  143             4600               10157             35%            8%       02/23/08 $                    427,561 added 3 mutual deps                           somewhat
                                  144             4600                 9082            23%            11%      01/05/08 $                    360,000 Some blended assignments                      almost 

50 or more plans                  147
                                  148
                                                  4600
                                                  4600
                                                                       7439
                                                                       7753
                                                                                       12%
                                                                                       14%
                                                                                                      18%
                                                                                                      15%
                                                                                                               12/24/07 $                    293,500 Blended assignments & PMs as Decide
                                                                                                               12/20/07 $                    264,988 All Arcana efforts priced at 0
                                                                                                                                                                                                   almost (but cost)
                                                                                                                                                                                                   yes

 for a complex                    153             4600                 6748            8%             16%      12/11/07 $                    246,496 From 4 to 5 IT developers in SF               yes
                                  154             4600                 7067            15%            13%      12/06/07 $                    265,325 From 3 to 4 AST Developers                    yes
 project in days




         Slide 18



  Global Project Design © 2009                                                  NASA Challenge 2009                                                                                      www.gpdesign.com
Estimation of
Coordination Activity



              How can we estimate coordination?




   Slide 19




Global Project Design © 2009                      www.gpdesign.com
Dependence an                       Team 1                               Team 2
 architectural 
measure of need
                                     Can we predict the amount of coordination effort
                                     required to effectively complete our direct work?




                                     Dependence



                                 What does my team
                                 need in the progress
                                 & results from others?



                                 DEMAND
         Slide 20                for coordination

  Global Project Design © 2009               NASA Challenge 2009                  www.gpdesign.com
A     B      C
                                                                                     E    A        C    D   B     G        F
 Dependence                         A    X            X
                                                                                 E   X

Design Structure                    B          X                                 A        X        X

 Matrix (DSM)                                                                    C   X    X        X    X
                                    C    X     X      X
                                                                                 D   X                  X

                                                                                 B        X             X   X
                                 Task Dependency in Matrix Form
                                    Goal is to sequence and partition            G   X             X        X     X

                                    Some tasks are too tightly linked            F                 X              X      X
                                        D. Steward, 1981



                                                                                 A   B    C             Level of Dependence
                                 Level of Dependence
                                     To Partition Tightly Coupled            A   A   •    •             •       Small
                                     Tasks                                   B
                                                                                 •   B                  •       Medium
                                         McCord, Eppinger, Aug 1993          C   •
                                                                                     •    C
                                                                                                        •       Large


                                                                                     A        B    C
                                 Time Duration & Probability
                                                                                 A   4        .2
                                     To Predict Total Duration
         Slide 21                    Work Transformation Matrix                  B   .4       7    .5

                                         Smith, Eppinger, Apr 1994               C   .3       .1   6

  Global Project Design © 2009                         NASA Challenge 2009                              www.gpdesign.com
Aircraft Global                                                               upstream activity
                                                                       Part6          Part1          Part16              Part5
 Development                                               s
     Project                                               p       m r             m r               m r             m r
                                                           e     I f v           I f v             I f v           I f v
                                                           c     F g w           F g w             F g w           F g w
    4 major                              Part6 IF
                                                    spec
                                 d                         fs                                      6ri             5ri                     fs
subsystems with                  o   a   Part6 mfg               co              3r                                                time-based
                                         Part6 rvw                     co                                                            (finish to start)
13 Key activities                w   c   Part1 IF          fs                                      2r              2r                      co
and Dependence                   n   t   Part1 mfg               3r              co                                                continuous flow
                                 s   i   Part1 rvw                                     co                                             (parallel)
                                 t   v   Part16 IF         fs                                                      4i
                                         Part16 mfg                                                co                              other
                                 r   i
                                         Part16 rvw                                                      co                          (information...)
                                 e   t   Part5 IF          fs
                                 a   y   Part5 mfg               4ri             1ri               5ri 5r          co
                                 m       Part5 rvw                                                                       co
                                              release                       co                co              co              co

                                                           1ri   early some results&info
                                                           2r    early most results         5r parallel half results
                                                           3r    early all results          5ri parallel half info & results
                                                           4i    early/para, some info      6ri late most info & results
                                                           4ri   early/para some results&info

         Slide 22



  Global Project Design © 2009                              NASA Challenge 2009                                                       www.gpdesign.com
Sum of Remaining          Activity_From


                                                                                          n                                                                                     to
                                                                                       sig                                                   ign                              ro
                                                                                     De                ign                 ign             es               n              sP            oto                                    ot   o              ip
                                                                                ic                   es                  es             _D               sig            nic            Pr                 ro
                                                                                                                                                                                                            to
                                                                                                                                                                                                                             Pr                   Sh
                                                                              on                   rd               lD               kg                De            tro                              P                   al
                                                                          ctr                 to                  na               &P              ell            lec              tor            ell                 n                    st
                                                                                                                                                                                                                                              &
                                       Activity_To                    Ele                  Mo                 Sig                A              Sh               E              Mo              Sh                 Sig                   Te


                                      Electronic Design         288
                                                                                                                                                                                                                                                                    Dependencies by Activity
For coordination                          Motor Design                               168
                                                                                                                                                                                                                                                                    (DSM) mapped to
 Team structure                           Signal Design         93
                                                                                                                                                                                                                                                                    Dependence across Teams
     matters                            A &Pkg_Design                                968




                                                                                              Sum of Remaining                                                   Team_From
                                           Shell Design                                                                                     288



  Architecture                                                                                                                                                                                                                                                                                                              e   rs
                                      Electronics Proto         168
                                                                                                                                                                                                                                                                                   m                                    ine
                                                                                                                                                                                                                                                                              ea
 determines if                                                                                                                                                                          es
                                                                                                                                                                                                      ign
                                                                                                                                                                                                                          up
                                                                                                                                                                                                                             pli
                                                                                                                                                                                                                                er
                                                                                                                                                                                                                                                                    sti
                                                                                                                                                                                                                                                                       cs
                                                                                                                                                                                                                                                                            _T
                                                                                                                                                                                                                                                                                          ctr
                                                                                                                                                                                                                                                                                              on
                                                                                                                                                                                                                                                                                                 ics
                                                                                                                                                                                                                                                                                                             na
                                                                                                                                                                                                                                                                                                               l   E ng
                                                                                                                                                                                                                                                                                                                                     oto
                                                                                                                                                                                                                                                                                                                                         r
                                            Motor Proto                              800
                                                                                                                                                                                      CD                                 S                                       Pla                   Ele                Sig                M
                                                                                                                                                                                    GA
  dependence                                 Shell Proto
                                                                                                                  Team_To

                                                                                                                                            320
                                                                                                                                                                                                                      T1                                      T2                  T2                   T2                 T2


stretches across                           Signal Proto
                                                                                              GAC Design
                                                                                                        288                                                288
                                                                                                                                                                           456



     teams                                  Test & Ship                                                                    288                             168             128             93                168                 380



                                                                                              T1 Supplier                                                                  968                               668                                         93                 168                 168                 128




                                                                                              T2 Plastics_Team                                                             320




                                                                                              T2 Electronics                                                                                                                                                                549




                                                                                              T2 Signal Engineers                                                                                                                                                           576




            23                                                                                T2 Motor                                                                     800




  Global Project Design © 2009                                                                                                           NASA Challenge 2009                                                                                                                                             www.gpdesign.com
Why dependence                   Coordination is interaction across the architecture 
 is not enough                   to allow downstream effective independence.  

                                 Teams that aren’t dependent have no need to 
                                 coordinate.

                                 Even if demanded, coordination is not guaranteed 
                                 to occur.

                                 Coordination requires attention, priority, & 
                                 capacity .

                                 Interaction, communication, meetings, learning, 
                                    and response consume TIME AND BUDGET.   

         Slide 24



  Global Project Design © 2009                NASA Challenge 2009           www.gpdesign.com
Coordination                       Team 1                                Team 2
Distance is the 
 Supply Side
                                    Can we predict the amount of coordination effort
                                    required to effectively complete our direct work?




                                    Dependence                           Distance



                                What does my team                 What is my team’s
                                need in the progress &            ability to coordinate
                                results from others?              with others?



                                DEMAND                            SUPPLY
        Slide 25                for coordination                  of coordination

 Global Project Design © 2009               NASA Challenge 2009                   www.gpdesign.com
0.0: Within small teams with shared tacit knowledge, distance
 Coordination                   approaches “0”
 Distance is a 
  Measure of                    1.0: Between teams with average shared work background,
                                common native language, and co-location, distance is a
Team To Team 
                                nominal “1”
 Coordination 
    Ability                     Coordination Distance is both a macro-level and micro-level
                                measure
                                                                                                                                                                                              e   rs
                                                                                                                                                  a   m                                   ine
                                                                                                                                               Te                 nic
                                                                                                                                                                      s                 ng
                                                                                            sig
                                                                                               n                er                          s_                                        lE
                                                                                                             pli                      tic                      tro               na                  r
                                                                                       De                  up                     s                        c                                      oto
                                                                                   C                     1S                   Pla                      Ele                   Sig                2M
                                                      Team_Name                 GA                   T                     T2                       T2                    T2                  T


                                                           GAC Design     0.5                  1.1                   1.8                      1.4                  1.2                  1.3




                                                            T1 Supplier   1.1                  0.2                   1.7                      1.3                  1.1                  1.5




                                                      T2 Plastics_Team    1.9                  1.8               0.3                          1.7                   2                   1.7




                                                         T2 Electronics   1.4                  1.3               1.7                         0.1                   1.2                  1.4




                                                    T2 Signal Engineers   1.2                  1.1                   2                        1.2                   0                   1.5




           26
                                                              T2 Motor    1.3                  1.5               1.7                         1.4                   1.5                  0.2




 Global Project Design © 2009                  NASA Challenge 2009                                                                                              www.gpdesign.com
Global Factors 
which influence 
                                 Communication efficiency
                                  Some parties working in 2nd language
 Coordination 
                                  Less shared work background
   Distance
                                  Team Size & Capacity
                                  Priority of attention to interaction vs. direct work



                                 Distribution & time zones
                                  Overlap of work hours
                                  Latency/ reaction to issues
                                  Travels costs and time



                                 Exception handling behavior
                                  Local work culture & assumptions differ, distract
                                  Quality priorities, re-work capacity and attention
                                  High chance of misreading indicators
         Slide 27



  Global Project Design © 2009                 NASA Challenge 2009                       www.gpdesign.com
Team 1                                                                                                                     Team 2
Coordination = 
Dependence X 
  Distance                                       Coordination Dependency Matrix                                                                            Coordination Distance Matrix
                        Sum of Remaining      Team_From


                                                                                                                                                 ers                                                                                                                                        ers
                                                                                                               ea
                                                                                                                 m                            ine                                                                                                    am                                 ine
                                                                                                             _T              ics           ng                                                                                                      Te                ics             ng
                                                                      n                er                 cs               on            lE                                                     sig
                                                                                                                                                                                                   n                    r                        s_                on              lE
                                                                   sig             pli                 sti             ctr             na            tor                                                        pp
                                                                                                                                                                                                                  lie                         tic              ctr               na             tor
                                                                De               up                                                                                                          De                                           s
                                                            C                  1S                   Pla             Ele             Sig            Mo                                    C                    Su                       Pla                  Ele               Sig            Mo
                                Team_To                GA                  T                     T2              T2              T2             T2           Team_Name                 GA                T1                       T2                   T2                  T2             T2


                        GAC Design               456                                                                                                              GAC Design     0.5               1.1                      1.8                  1.4                 1.2              1.3




                        T1 Supplier              968                 668                    93              168            168            128                      T1 Supplier   1.1               0.2                      1.7                  1.3                 1.1              1.5




                        T2 Plastics_Team         320                                                                                                         T2 Plastics_Team    1.9               1.8                  0.3                      1.7                 2                1.7




                        T2 Electronics                                                                      549                                                 T2 Electronics   1.4               1.3                  1.7                      0.1                1.2               1.4




                        T2 Signal Engineers                                                                 576                                            T2 Signal Engineers   1.2               1.1                      2                    1.2                 0                1.5




                        T2 Motor                 800                                                                                                                 T2 Motor    1.3               1.5                  1.7                      1.4                1.5               0.2




                                                                                                                                                 Coordination
           28                                                                                                                                      Activity                                                                                            (Moser 1997)

 Global Project Design © 2009                                                                                            NASA Challenge 2009                                                                                                     www.gpdesign.com
Sum of Coordination Cost %


                                                                                                                                                                                         rs
                                                                                                                                  am                                                  ee
                                                                                                                                Te                        s                        gin                                Team to team
                                                                                      n                  r                    s_                       nic                     lE
                                                                                                                                                                                 n
                                                                                   sig               lie                   tic                      tro                      na                 r
                                                                                De                 pp                                                                                       oto
Distribution of                                                        G   AC              T   1 Su
                                                                                                               T   2P
                                                                                                                     las
                                                                                                                                         T2
                                                                                                                                               Elec
                                                                                                                                                                     T 2 Sig
                                                                                                                                                                                      T 2M                            coordination
                                                                                                                                                                                                                      activity
Coordination                             GAC Design              5%                  0%                   0%                     0%                       0%                              0%

Activity across                                                                                                                                                                                                       Changes phase
                                                                                                                                                                                                                      to phase
    Teams                                 T1 Supplier           23%
                                              Sum of Coordination Cost %
                                                                                     3%                  4%           5%
                                                                                                       Phase_From Team_From
                                                                                                                                                          4%                              4%
                                                                                                       1. Design                                                 2. Prototype                                                             3. Assembly
                                                                                                       Phase                                                     Phase                                                                    Phase



                                                                                                                                                                                                                                       ers
                                                                                                                                                                                                 am                                ine
                                    T2 Plastics_Team             13%                 0%                   0%                     n 0%                r    0%                ic   s        0% s_Te             nic
                                                                                                                                                                                                                  s             ng                                      r
                                                                                                                              sig                lie                     on                    c             o                lE                                 pli
                                                                                                                                                                                                                                                                    e
                                                                                                                         De                    pp               le   ctr                    sti          ctr               na              tor              up
                                                                                                                     C                   1S
                                                                                                                                           u
                                                                                                                                                              2E                        Pla          Ele               Sig              Mo                1S
                                                      Phase_To                     Team_To                         GA                T                    T                          T2           T2                T2               T2               T

                                                               1.
                                                                                     GAC Design              5%                 0%                   0%                    0%                   0%              0%              0%        0%
                                                    Design Phase
                                       T2 Electronics       0%                       0%                   0%                     1%                       0%                              0%



                                                                                      T1 Supplier            23%                0%                   0%                    0%                   0%              0%              0%        0%


                                  T2 Signal Engineers            0%                  0%                   0%                     15%                      0%                              0%


                                                                                   T2 Electronics            0%                 0%                   1%                    0%                   0%              0%              0%        0%




                                             T2 Motor         23%                    0%                   0%                     0%                       0%                              0%
                                                2. Prototype Phase              T2 Plastics_Team             13%                0%                   0%                    0%                   0%              0%              0%        0%




                                                                            T2 Signal Engineers              0%                 0%                   8%                    0%                   8%              0%              0%        0%




                                                                                          T2 Motor           23%                0%                   0%                    0%                   0%              0%              0%        0%




                                                                                   T2 Electronics            0%                 0%                   0%                    0%                   0%              0%              0%        0%




           29
                                                3. Assembly Phase                     T1 Supplier            0%                 1%                   0%                    4%                   5%              4%              4%               2%




 Global Project Design © 2009                                                       NASA Challenge 2009                                                                                                                    www.gpdesign.com
Coordination                    If work is complex, teams large, and dependence 
  Distance                      stretches across distant teams, coordination 
 Summary 
                                activity tends to increase 

                                Simulator handles dependence and distance 
                                interaction on a micro, transactional level.

                                Distances at a transactional level create local 
                                direct costs and increased duration

                                The architecture determines if local coordination 
                                causes systemic and propagating impacts

                               Systemically, what happens if coordination activity 
                                         is not budgeted and prioritized? 
       Slide 30



Global Project Design © 2009                 NASA Challenge 2009            www.gpdesign.com
3. Case Study:
       Product Development across 4 Global Regions


                        Retrospective Analysis




   Slide 31




Global Project Design © 2009                         www.gpdesign.com
Case Description                  New product family of complex machinery for 
                                  multiple regional markets

                                  Approximately 150,000 hrs of effort for design & 
                                  development.  5 Gateways.

Gateways                          85% of scope was visible before G2. 
                                    54% from original product family scope 
G0 – start
G1 – concept                        31% for options, not addressed until after G2.
G2 – design                         15% from scope increase at G3.
G3 – engineer
G4 – manufacture
G5 – release                                                                         Original Scope


                                                                                     Original Scope & 
                                                                                     Options

                                                                                     Original Scope, 
                                                                                     Options, & Scope 
             32                                                                      Increase



   Global Project Design © 2009                   NASA Challenge 2009                    www.gpdesign.com
Scenarios:                    A retrospective analysis:  starting condition data used to ask 
Original, Options,                “What could we have known ahead of time?”
& Scope Increase 
                                  Three Scenarios were modeled;  each simulated using 
                                  critical path (CPM) & global factors (GPD) settings.

      Original Scope              CPM refers to the Critical Path Method for scheduling as 
      Original Scope &            used in traditional project tools.  CPM ignores 
      Options
                                  communication, time zones, mutual dependence, re‐work, 
      Original Scope, 
      Options, & Scope            and other global factors.
      Increase


                                  GPD refers to analysis by GPD's TeamPort which 
                                  incorporates communication, complex concurrency, re‐
                                  work, time‐zones and other factors.


             33



   Global Project Design © 2009                   NASA Challenge 2009                 www.gpdesign.com
Comparison of Forecasts: Schedule Gateways
                                         Original Scope


                                         Original Scope & 
                                         Options

                                         Original Scope, 
                                         Options, & Scope 
                                         Increase




                                     Gateways

                                     G0 – start
                                     G1 – concept
                                     G2 – design
                                     G3 – engineer
                                     G4 – manufacture
                                     G5 – release

     Slide 34
                                          Global Project Design ©
                                                             2009
NASA Challenge 2009                           www.gpdesign.com
Comparison of Forecasts: Cost x 4th Gateway
                                                                                       Original Scope


                                                                                       Original Scope & 
                                                                                       Options

                                              Actual
                                                                                       Original Scope, 
                                                                                       Options, & Scope 
                                                                                       Increase
                              @ G4                     GPD


                      PM                                                          Gateways
                             @ G3

             @ G2
                                                                                  G0 – start
                                         CPM                                      G1 – concept
      @ G1
                                                                                  G2 – design
                                                                                  G3 – engineer
                                                                                  G4 – manufacture
                PM    forecasts by project team at each Gate during project.

                CPM forecasts (critical path) ignore coordination, concurrency,
                     and re-work realities.
                GPD forecasts consider coordination, concurrency, re-work,
                     time-zones and other global project realities
 35

                                                                                        Global Project Design ©
                CPM & GPD forecasts generated by TeamPort                                                  2009
                                                                                            www.gpdesign.com
Conclusion




Teams in global projects can succeed through collaborative design of
    plans, simulating progress including coordination, exposing
       assumptions, and generating situational awareness.


   Slide 36




Global Project Design © 2009                                  www.gpdesign.com
The Results of                  Project design generates a plan. And options. The plan
Project Design                  represents teams’ consensus of role, feasibility,
                                optimality, and coordination approach.

                                The plan is a social instrument; a dialogue amongst
                                teams, not just a control instrument. Teams interact
                                from their own point of view.

                                Failure is visual before starting; allows team leaders to
                                re-think how to participate. Architecture and complex
                                dependence emphasized.

                                The exercise exposes ideological assumptions and
                                prevents wishful thinking. Teams see sensitivity of total
                                project results to their own actions.

                                Situational awareness and performance emerge as
                                teams understand, commit, rehearse, and adapt
        Slide 37                ongoing with the plan.

 Global Project Design © 2009                 NASA Challenge 2009                www.gpdesign.com

Contenu connexe

Tendances

Strausser Pmi Global Congress 2009 Na Paper
Strausser Pmi Global Congress 2009 Na PaperStrausser Pmi Global Congress 2009 Na Paper
Strausser Pmi Global Congress 2009 Na Paperjciman
 
10 things to improve project management
10 things to improve project management10 things to improve project management
10 things to improve project managementStriking Group Pty Ltd
 
7 ways to improve your PMO performance
7 ways to improve your PMO performance7 ways to improve your PMO performance
7 ways to improve your PMO performancePlanningForce
 
Immutable principles of project management
Immutable principles of project managementImmutable principles of project management
Immutable principles of project managementGlen Alleman
 
Immutable principles of project management (austin pmi)(v4)(no exercise)
Immutable principles of project management (austin pmi)(v4)(no exercise)Immutable principles of project management (austin pmi)(v4)(no exercise)
Immutable principles of project management (austin pmi)(v4)(no exercise)Glen Alleman
 
2008 Fiatech Ceti Awards Smccv
2008   Fiatech Ceti Awards   Smccv2008   Fiatech Ceti Awards   Smccv
2008 Fiatech Ceti Awards Smccvsemdanat
 
0569 project management-beenish
0569 project management-beenish0569 project management-beenish
0569 project management-beenishdfhf hfghf
 
Planning a project
Planning a  projectPlanning a  project
Planning a projectcarloparlato
 
Cisco Camel Model - Avoiding Business Failure
Cisco Camel Model - Avoiding Business FailureCisco Camel Model - Avoiding Business Failure
Cisco Camel Model - Avoiding Business FailureContent Rules, Inc.
 
StrategicFit - Production Forecasting Poster
StrategicFit - Production Forecasting PosterStrategicFit - Production Forecasting Poster
StrategicFit - Production Forecasting PosterStrategicFit
 
Beyond the Scrum - I
Beyond the Scrum - IBeyond the Scrum - I
Beyond the Scrum - IAdam Monago
 
Advanced Projects(tm) Brochure Oct09
Advanced Projects(tm)   Brochure   Oct09Advanced Projects(tm)   Brochure   Oct09
Advanced Projects(tm) Brochure Oct09dbevort
 
Performance based management in a nut shell (austin pmi)(notes)
Performance based management in a nut shell (austin pmi)(notes)Performance based management in a nut shell (austin pmi)(notes)
Performance based management in a nut shell (austin pmi)(notes)Glen Alleman
 
PMI chapter meeting (v4)
PMI chapter meeting (v4)PMI chapter meeting (v4)
PMI chapter meeting (v4)Glen Alleman
 

Tendances (20)

Strausser Pmi Global Congress 2009 Na Paper
Strausser Pmi Global Congress 2009 Na PaperStrausser Pmi Global Congress 2009 Na Paper
Strausser Pmi Global Congress 2009 Na Paper
 
10 things to improve project management
10 things to improve project management10 things to improve project management
10 things to improve project management
 
Ch07
Ch07Ch07
Ch07
 
7 ways to improve your PMO performance
7 ways to improve your PMO performance7 ways to improve your PMO performance
7 ways to improve your PMO performance
 
Immutable principles of project management
Immutable principles of project managementImmutable principles of project management
Immutable principles of project management
 
Immutable principles of project management (austin pmi)(v4)(no exercise)
Immutable principles of project management (austin pmi)(v4)(no exercise)Immutable principles of project management (austin pmi)(v4)(no exercise)
Immutable principles of project management (austin pmi)(v4)(no exercise)
 
2008 Fiatech Ceti Awards Smccv
2008   Fiatech Ceti Awards   Smccv2008   Fiatech Ceti Awards   Smccv
2008 Fiatech Ceti Awards Smccv
 
0569 project management-beenish
0569 project management-beenish0569 project management-beenish
0569 project management-beenish
 
Planning a project
Planning a  projectPlanning a  project
Planning a project
 
Trn 11
Trn 11Trn 11
Trn 11
 
Cisco Camel Model - Avoiding Business Failure
Cisco Camel Model - Avoiding Business FailureCisco Camel Model - Avoiding Business Failure
Cisco Camel Model - Avoiding Business Failure
 
PRINCE2 Overview
PRINCE2 OverviewPRINCE2 Overview
PRINCE2 Overview
 
StrategicFit - Production Forecasting Poster
StrategicFit - Production Forecasting PosterStrategicFit - Production Forecasting Poster
StrategicFit - Production Forecasting Poster
 
MGT 371 Chapter 1
MGT 371 Chapter 1MGT 371 Chapter 1
MGT 371 Chapter 1
 
Beyond the Scrum - I
Beyond the Scrum - IBeyond the Scrum - I
Beyond the Scrum - I
 
Gurtu 2010
Gurtu 2010Gurtu 2010
Gurtu 2010
 
Advanced Projects(tm) Brochure Oct09
Advanced Projects(tm)   Brochure   Oct09Advanced Projects(tm)   Brochure   Oct09
Advanced Projects(tm) Brochure Oct09
 
Talent Review and Engagement
Talent Review and EngagementTalent Review and Engagement
Talent Review and Engagement
 
Performance based management in a nut shell (austin pmi)(notes)
Performance based management in a nut shell (austin pmi)(notes)Performance based management in a nut shell (austin pmi)(notes)
Performance based management in a nut shell (austin pmi)(notes)
 
PMI chapter meeting (v4)
PMI chapter meeting (v4)PMI chapter meeting (v4)
PMI chapter meeting (v4)
 

En vedette

Les.sorge
Les.sorgeLes.sorge
Les.sorgeNASAPMC
 
Sammy.kayali
Sammy.kayaliSammy.kayali
Sammy.kayaliNASAPMC
 
Smith.donnie
Smith.donnieSmith.donnie
Smith.donnieNASAPMC
 
Sorge.les
Sorge.lesSorge.les
Sorge.lesNASAPMC
 
Bill.bastedo
Bill.bastedoBill.bastedo
Bill.bastedoNASAPMC
 
Barley2 ce hierarchica valuepmcfinal
Barley2 ce hierarchica valuepmcfinalBarley2 ce hierarchica valuepmcfinal
Barley2 ce hierarchica valuepmcfinalNASAPMC
 
Keer.beth
Keer.bethKeer.beth
Keer.bethNASAPMC
 
Bush.stewart
Bush.stewartBush.stewart
Bush.stewartNASAPMC
 
Michael.aucoin
Michael.aucoinMichael.aucoin
Michael.aucoinNASAPMC
 
Backup norm.smith
Backup norm.smithBackup norm.smith
Backup norm.smithNASAPMC
 
Patrick.guske.update
Patrick.guske.updatePatrick.guske.update
Patrick.guske.updateNASAPMC
 
C null 01-17-2011
C null 01-17-2011C null 01-17-2011
C null 01-17-2011NASAPMC
 
Michael.aucoin
Michael.aucoinMichael.aucoin
Michael.aucoinNASAPMC
 
Fleming.jon
Fleming.jonFleming.jon
Fleming.jonNASAPMC
 
Steven noneman
Steven nonemanSteven noneman
Steven nonemanNASAPMC
 
Pamela.west
Pamela.westPamela.west
Pamela.westNASAPMC
 
Brantley.wayne
Brantley.wayneBrantley.wayne
Brantley.wayneNASAPMC
 

En vedette (20)

Les.sorge
Les.sorgeLes.sorge
Les.sorge
 
Sammy.kayali
Sammy.kayaliSammy.kayali
Sammy.kayali
 
Smith.donnie
Smith.donnieSmith.donnie
Smith.donnie
 
Sorge.les
Sorge.lesSorge.les
Sorge.les
 
Bill.bastedo
Bill.bastedoBill.bastedo
Bill.bastedo
 
Barley2 ce hierarchica valuepmcfinal
Barley2 ce hierarchica valuepmcfinalBarley2 ce hierarchica valuepmcfinal
Barley2 ce hierarchica valuepmcfinal
 
Trahan
TrahanTrahan
Trahan
 
Keer.beth
Keer.bethKeer.beth
Keer.beth
 
Bush.stewart
Bush.stewartBush.stewart
Bush.stewart
 
Michael.aucoin
Michael.aucoinMichael.aucoin
Michael.aucoin
 
Hulett
HulettHulett
Hulett
 
Backup norm.smith
Backup norm.smithBackup norm.smith
Backup norm.smith
 
Patrick.guske.update
Patrick.guske.updatePatrick.guske.update
Patrick.guske.update
 
C null 01-17-2011
C null 01-17-2011C null 01-17-2011
C null 01-17-2011
 
Michael.aucoin
Michael.aucoinMichael.aucoin
Michael.aucoin
 
Heard
HeardHeard
Heard
 
Fleming.jon
Fleming.jonFleming.jon
Fleming.jon
 
Steven noneman
Steven nonemanSteven noneman
Steven noneman
 
Pamela.west
Pamela.westPamela.west
Pamela.west
 
Brantley.wayne
Brantley.wayneBrantley.wayne
Brantley.wayne
 

Similaire à Moser.bryan

Estimation Agile Projects
Estimation Agile ProjectsEstimation Agile Projects
Estimation Agile ProjectsRam Srivastava
 
Proj desresdeliv gsw
Proj desresdeliv gswProj desresdeliv gsw
Proj desresdeliv gswwoznite65
 
Proj desresdeliv gsw
Proj desresdeliv gswProj desresdeliv gsw
Proj desresdeliv gswwoznite65
 
Building an Agile framework that fits your organisation
Building an Agile framework that fits your organisationBuilding an Agile framework that fits your organisation
Building an Agile framework that fits your organisationKurt Solarte
 
The Analytical Design Planning Technique (ADePT)
The Analytical Design Planning Technique (ADePT)The Analytical Design Planning Technique (ADePT)
The Analytical Design Planning Technique (ADePT)PaulWaskett
 
Short Term Planning and Lean
Short Term Planning and LeanShort Term Planning and Lean
Short Term Planning and Leanistarkov
 
Romeo.mitchell
Romeo.mitchellRomeo.mitchell
Romeo.mitchellNASAPMC
 
Romeo.mitchell
Romeo.mitchellRomeo.mitchell
Romeo.mitchellNASAPMC
 
Eggert.joe
Eggert.joeEggert.joe
Eggert.joeNASAPMC
 
IMT Lecture:Creating Project Plans To Focus Product Development.Mm Biztel 13 ...
IMT Lecture:Creating Project Plans To Focus Product Development.Mm Biztel 13 ...IMT Lecture:Creating Project Plans To Focus Product Development.Mm Biztel 13 ...
IMT Lecture:Creating Project Plans To Focus Product Development.Mm Biztel 13 ...Djadja Sardjana
 
Scrum Day 2012 Keynote: Combining Design and Development
Scrum Day 2012 Keynote: Combining Design and DevelopmentScrum Day 2012 Keynote: Combining Design and Development
Scrum Day 2012 Keynote: Combining Design and DevelopmentTobias Schimmer
 
NG BB 07 Multi-Generation Project Planning
NG BB 07 Multi-Generation Project PlanningNG BB 07 Multi-Generation Project Planning
NG BB 07 Multi-Generation Project PlanningLeanleaders.org
 
From Waterfall to Agile - from predictive to adaptive methods
From Waterfall to Agile - from predictive to adaptive methodsFrom Waterfall to Agile - from predictive to adaptive methods
From Waterfall to Agile - from predictive to adaptive methodsBjörn Jónsson
 
New Product Introduction - Launching Success!
New Product Introduction - Launching Success! New Product Introduction - Launching Success!
New Product Introduction - Launching Success! Product Realization Group
 
Empirical Evidence Of Agile Methods
Empirical Evidence Of Agile MethodsEmpirical Evidence Of Agile Methods
Empirical Evidence Of Agile MethodsGrigori Melnik
 
Role of Project Management Through IT for "Construction and EPC World"
Role of Project Management Through IT for "Construction and EPC World"Role of Project Management Through IT for "Construction and EPC World"
Role of Project Management Through IT for "Construction and EPC World"Nishant Dean
 
Schedule Design PMI
Schedule Design PMISchedule Design PMI
Schedule Design PMIChris Carson
 

Similaire à Moser.bryan (20)

Estimation Agile Projects
Estimation Agile ProjectsEstimation Agile Projects
Estimation Agile Projects
 
Proj desresdeliv gsw
Proj desresdeliv gswProj desresdeliv gsw
Proj desresdeliv gsw
 
Proj desresdeliv gsw
Proj desresdeliv gswProj desresdeliv gsw
Proj desresdeliv gsw
 
Building an Agile framework that fits your organisation
Building an Agile framework that fits your organisationBuilding an Agile framework that fits your organisation
Building an Agile framework that fits your organisation
 
Presentation on software assessment in bangladesh basis soft_expo2012_final
Presentation on software assessment in bangladesh basis soft_expo2012_finalPresentation on software assessment in bangladesh basis soft_expo2012_final
Presentation on software assessment in bangladesh basis soft_expo2012_final
 
The Analytical Design Planning Technique (ADePT)
The Analytical Design Planning Technique (ADePT)The Analytical Design Planning Technique (ADePT)
The Analytical Design Planning Technique (ADePT)
 
Short Term Planning and Lean
Short Term Planning and LeanShort Term Planning and Lean
Short Term Planning and Lean
 
Romeo.mitchell
Romeo.mitchellRomeo.mitchell
Romeo.mitchell
 
Romeo.mitchell
Romeo.mitchellRomeo.mitchell
Romeo.mitchell
 
Eggert.joe
Eggert.joeEggert.joe
Eggert.joe
 
IMT Lecture:Creating Project Plans To Focus Product Development.Mm Biztel 13 ...
IMT Lecture:Creating Project Plans To Focus Product Development.Mm Biztel 13 ...IMT Lecture:Creating Project Plans To Focus Product Development.Mm Biztel 13 ...
IMT Lecture:Creating Project Plans To Focus Product Development.Mm Biztel 13 ...
 
Scrum Day 2012 Keynote: Combining Design and Development
Scrum Day 2012 Keynote: Combining Design and DevelopmentScrum Day 2012 Keynote: Combining Design and Development
Scrum Day 2012 Keynote: Combining Design and Development
 
NG BB 07 Multi-Generation Project Planning
NG BB 07 Multi-Generation Project PlanningNG BB 07 Multi-Generation Project Planning
NG BB 07 Multi-Generation Project Planning
 
Ch3 proj.mgt
Ch3 proj.mgtCh3 proj.mgt
Ch3 proj.mgt
 
From Waterfall to Agile - from predictive to adaptive methods
From Waterfall to Agile - from predictive to adaptive methodsFrom Waterfall to Agile - from predictive to adaptive methods
From Waterfall to Agile - from predictive to adaptive methods
 
New Product Introduction - Launching Success!
New Product Introduction - Launching Success! New Product Introduction - Launching Success!
New Product Introduction - Launching Success!
 
Empirical Evidence Of Agile Methods
Empirical Evidence Of Agile MethodsEmpirical Evidence Of Agile Methods
Empirical Evidence Of Agile Methods
 
Role of Project Management Through IT for "Construction and EPC World"
Role of Project Management Through IT for "Construction and EPC World"Role of Project Management Through IT for "Construction and EPC World"
Role of Project Management Through IT for "Construction and EPC World"
 
Schedule Design PMI
Schedule Design PMISchedule Design PMI
Schedule Design PMI
 
IIIT Guest Talk 0512
IIIT Guest Talk 0512IIIT Guest Talk 0512
IIIT Guest Talk 0512
 

Plus de NASAPMC

Bejmuk bo
Bejmuk boBejmuk bo
Bejmuk boNASAPMC
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski johnNASAPMC
 
Yew manson
Yew mansonYew manson
Yew mansonNASAPMC
 
Wood frank
Wood frankWood frank
Wood frankNASAPMC
 
Wood frank
Wood frankWood frank
Wood frankNASAPMC
 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)NASAPMC
 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joeNASAPMC
 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuartNASAPMC
 
Stock gahm
Stock gahmStock gahm
Stock gahmNASAPMC
 
Snow lee
Snow leeSnow lee
Snow leeNASAPMC
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandraNASAPMC
 
Seftas krage
Seftas krageSeftas krage
Seftas krageNASAPMC
 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marcoNASAPMC
 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mikeNASAPMC
 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karleneNASAPMC
 
Rackley mike
Rackley mikeRackley mike
Rackley mikeNASAPMC
 
Paradis william
Paradis williamParadis william
Paradis williamNASAPMC
 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeffNASAPMC
 
O'keefe william
O'keefe williamO'keefe william
O'keefe williamNASAPMC
 
Muller ralf
Muller ralfMuller ralf
Muller ralfNASAPMC
 

Plus de NASAPMC (20)

Bejmuk bo
Bejmuk boBejmuk bo
Bejmuk bo
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski john
 
Yew manson
Yew mansonYew manson
Yew manson
 
Wood frank
Wood frankWood frank
Wood frank
 
Wood frank
Wood frankWood frank
Wood frank
 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)
 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joe
 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuart
 
Stock gahm
Stock gahmStock gahm
Stock gahm
 
Snow lee
Snow leeSnow lee
Snow lee
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandra
 
Seftas krage
Seftas krageSeftas krage
Seftas krage
 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marco
 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mike
 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karlene
 
Rackley mike
Rackley mikeRackley mike
Rackley mike
 
Paradis william
Paradis williamParadis william
Paradis william
 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeff
 
O'keefe william
O'keefe williamO'keefe william
O'keefe william
 
Muller ralf
Muller ralfMuller ralf
Muller ralf
 

Dernier

How to convert PDF to text with Nanonets
How to convert PDF to text with NanonetsHow to convert PDF to text with Nanonets
How to convert PDF to text with Nanonetsnaman860154
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationMichael W. Hawkins
 
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking MenDelhi Call girls
 
Google AI Hackathon: LLM based Evaluator for RAG
Google AI Hackathon: LLM based Evaluator for RAGGoogle AI Hackathon: LLM based Evaluator for RAG
Google AI Hackathon: LLM based Evaluator for RAGSujit Pal
 
Breaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountBreaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountPuma Security, LLC
 
Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsMaria Levchenko
 
Slack Application Development 101 Slides
Slack Application Development 101 SlidesSlack Application Development 101 Slides
Slack Application Development 101 Slidespraypatel2
 
08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking MenDelhi Call girls
 
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...HostedbyConfluent
 
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure serviceWhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure servicePooja Nehwal
 
Data Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonData Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonAnna Loughnan Colquhoun
 
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...shyamraj55
 
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 3652toLead Limited
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024Rafal Los
 
Histor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slideHistor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slidevu2urc
 
Boost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityBoost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityPrincipled Technologies
 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreternaman860154
 
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...Neo4j
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking MenDelhi Call girls
 
A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024Results
 

Dernier (20)

How to convert PDF to text with Nanonets
How to convert PDF to text with NanonetsHow to convert PDF to text with Nanonets
How to convert PDF to text with Nanonets
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day Presentation
 
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
 
Google AI Hackathon: LLM based Evaluator for RAG
Google AI Hackathon: LLM based Evaluator for RAGGoogle AI Hackathon: LLM based Evaluator for RAG
Google AI Hackathon: LLM based Evaluator for RAG
 
Breaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountBreaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path Mount
 
Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed texts
 
Slack Application Development 101 Slides
Slack Application Development 101 SlidesSlack Application Development 101 Slides
Slack Application Development 101 Slides
 
08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men
 
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
 
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure serviceWhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
 
Data Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonData Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt Robison
 
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
 
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024
 
Histor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slideHistor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slide
 
Boost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityBoost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivity
 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreter
 
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
 
A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024
 

Moser.bryan

  • 1. Rapid, Collaborative Planning for Global Teams through Project Design Bryan R. Moser bryan@gpdesign.com NASA Challenge 2009 February 24-25, 2009 Slide 1 Global Project Design © 2009 www.gpdesign.com
  • 2. Outline 1. The Challenge of Global Projects 2. Project Design: Rapid, Accurate, & Shared Plans  including Forecast of Coordination 3. Case Study:   Global Product Development 4. Conclusion Slide 2 Global Project Design © 2009 NASA Challenge 2009 www.gpdesign.com
  • 3. 1. The Challenge of Global Projects NASA Challenge 2009 Slide 3 Global Project Design © 2009 www.gpdesign.com
  • 4. Challenges of  Teams from different time zones, work cultures,  Global Projects costs, and abilities. Subsystems and services to be integrated in an  overall solution, yet the “central” team does not  have complete control Costs and risks from coordination,  communication, re‐work, and quality are 40% or  greater of real effort Expected Results difficult to predict with  significantly greater consequences if ignored Slide 4 Global Project Design © 2009 NASA Challenge 2009 www.gpdesign.com
  • 5. Work In 1909: Ways of Working An Industrial  Standard Work Age Narrow specialties Expert management Automated resources Communication, Uncertainty, & Adaptive Behavior are Avoided Slide 5 Global Project Design © 2009 NASA Challenge 2009 www.gpdesign.com
  • 6. The Missing Half of Plans is Century old  Coordination assumptions  strongly  embedded False precision of  detail becomes  substitute for  awareness &  adaptive learning The Gantt Chart Circa 1914 Not included in century old methods: Complex Dependence amongst activities Communication & Meetings Decisions, Exceptions, and Re-work Travel, Time Zones, and Workdays Slide 6 Reasons for Waiting related to others Global Project Design © 2009 NASA Challenge 2009 www.gpdesign.com
  • 7. 2. Project Design: Rapid, Accurate, & Shared Plans including Forecast of Coordination NASA Challenge 2009 Slide 7 Global Project Design © 2009 www.gpdesign.com
  • 8. Planning and  Designing Are  Very Different Plan Design Verb. To work out in Verb. To create the form or some detail how structure of something in a something is to be done or skillful or artistic way. organized. Planning may be sufficient for routine, repeatable projects with limited uncertainty DESIGN is essential to optimize performance and manage risk in enterprise initiatives Slide 8 Global Project Design © 2009 NASA Challenge 2009 www.gpdesign.com
  • 9. Cost (M$) Project Design: 24 Pre-Launch Multiple  Forecasts Forecasts are  1. Project Model Business & Simulation prototype  21 Result Typical “crashes” of real  Option 1 project Likely Result Trade-off Trade- for time with As-Is Behavior 18 Optimized Plan Feasible & Focused 15 for Targeted Scope 2. Design Iteration & Optimization Business Target Hoped For 12 Option 2 3. Trade-Off Dialogue Trade-off Trade- on Feasible Plans for cost 18 24 28 32 36 38 Slide 9 Duration (months) Global Project Design © 2009 NASA Challenge 2009 www.gpdesign.com
  • 10. Scope: Locations,  Teams (OBS),  Product (PBS),  and  Phases (WBS) Slide 10 Global Project Design © 2009 NASA Challenge 2009 www.gpdesign.com
  • 11. Architecture: Complex  dependence  (concurrent &  mutual )  Slide 11 Global Project Design © 2009 NASA Challenge 2009 www.gpdesign.com
  • 12. Real‐time  Collaborative  Modeling  In different  languages &  points of view Slide 12 Global Project Design © 2009 NASA Challenge 2009 www.gpdesign.com
  • 13. Project Design DESIGNER Visual models to capture project & complexity • Top-down & linked to strategy • Product, work, & teams • Global roles & priorities • Concurrent dependencies Smart Dialogue & Team Collaboration SIMULATOR Unique insight from predictive analytics • Analyzes coordination effort & costs • Real-world behavior & uncertainty • Constraints of team distribution • Detailed output from hi-level input FORECAST Review of realistic plans, scenarios & options •Product & phase schedules •Team progress, efforts, costs •Concurrency, wait, & re-work Slide 13 • opportunities & risk Global Project Design © 2009 www.gpdesign.com
  • 14. Simulation  generates  forecasts rapidly Includes  coordination  effort, costs and  schedule impact Slide 14 Global Project Design © 2009 NASA Challenge 2009 www.gpdesign.com
  • 15. Teams examine  Forecasts from  multiple  viewpoints:   WBS & PBS Slide 15 Global Project Design © 2009 NASA Challenge 2009 www.gpdesign.com
  • 16. Coordination is  real effort.  Impact on  schedule clearly  visible. Slide 16 Global Project Design © 2009 NASA Challenge 2009 www.gpdesign.com
  • 17. Progress  Forecasts Drawings Drawings Documents Documents Modules Modules Tests Tests Parts Parts Progress in Progress in Percent of Effort Percent of Effort Real World Units, Real World Units, Slide 17 Shown with range of standard Shown with range of standard not just not just deviation and high/low of forecasts deviation and high/low of forecasts Spending & Percent Spending & Percent Global Project Design © 2009 NASA Challenge 2009 www.gpdesign.com
  • 18. Frequent  Raw FTE  Wait  Coord  Go‐Live  Cost Model # hrs Forecast Effort hrs % % date $  Description Realistic? Iterations 114 4704 6891 8% 11% 12/24/07 $                    258,692 Added meeting to first modeling approach no & What If  131 138 4704 4600 6838 5735 7% 1% 23% 9% 12/12/07 $                    257,368 Execute Commit not hard gateway 02/19/08 $                    287,472 simple assignments no mutual deps no no Scenarios 139 4600 6450 9% 9% 02/14/08 $                    325,420 simple assignments & 1 mutual dep somewhat 143 4600 10157 35% 8% 02/23/08 $                    427,561 added 3 mutual deps somewhat 144 4600 9082 23% 11% 01/05/08 $                    360,000 Some blended assignments almost  50 or more plans  147 148 4600 4600 7439 7753 12% 14% 18% 15% 12/24/07 $                    293,500 Blended assignments & PMs as Decide 12/20/07 $                    264,988 All Arcana efforts priced at 0 almost (but cost) yes for a complex  153 4600 6748 8% 16% 12/11/07 $                    246,496 From 4 to 5 IT developers in SF yes 154 4600 7067 15% 13% 12/06/07 $                    265,325 From 3 to 4 AST Developers yes project in days Slide 18 Global Project Design © 2009 NASA Challenge 2009 www.gpdesign.com
  • 19. Estimation of Coordination Activity How can we estimate coordination? Slide 19 Global Project Design © 2009 www.gpdesign.com
  • 20. Dependence an  Team 1 Team 2 architectural  measure of need Can we predict the amount of coordination effort required to effectively complete our direct work? Dependence What does my team need in the progress & results from others? DEMAND Slide 20 for coordination Global Project Design © 2009 NASA Challenge 2009 www.gpdesign.com
  • 21. A B C E A C D B G F Dependence A X X E X Design Structure  B X A X X Matrix (DSM) C X X X X C X X X D X X B X X X Task Dependency in Matrix Form Goal is to sequence and partition G X X X X Some tasks are too tightly linked F X X X D. Steward, 1981 A B C Level of Dependence Level of Dependence To Partition Tightly Coupled A A • • • Small Tasks B • B • Medium McCord, Eppinger, Aug 1993 C • • C • Large A B C Time Duration & Probability A 4 .2 To Predict Total Duration Slide 21 Work Transformation Matrix B .4 7 .5 Smith, Eppinger, Apr 1994 C .3 .1 6 Global Project Design © 2009 NASA Challenge 2009 www.gpdesign.com
  • 22. Aircraft Global  upstream activity Part6 Part1 Part16 Part5 Development  s Project p m r m r m r m r e I f v I f v I f v I f v c F g w F g w F g w F g w 4 major  Part6 IF spec d fs 6ri 5ri fs subsystems with  o a Part6 mfg co 3r time-based Part6 rvw co (finish to start) 13 Key activities  w c Part1 IF fs 2r 2r co and Dependence n t Part1 mfg 3r co continuous flow s i Part1 rvw co (parallel) t v Part16 IF fs 4i Part16 mfg co other r i Part16 rvw co (information...) e t Part5 IF fs a y Part5 mfg 4ri 1ri 5ri 5r co m Part5 rvw co release co co co co 1ri early some results&info 2r early most results 5r parallel half results 3r early all results 5ri parallel half info & results 4i early/para, some info 6ri late most info & results 4ri early/para some results&info Slide 22 Global Project Design © 2009 NASA Challenge 2009 www.gpdesign.com
  • 23. Sum of Remaining Activity_From n to sig ign ro De ign ign es n sP oto ot o ip ic es es _D sig nic Pr ro to Pr Sh on rd lD kg De tro P al ctr to na &P ell lec tor ell n st & Activity_To Ele Mo Sig A Sh E Mo Sh Sig Te Electronic Design 288 Dependencies by Activity For coordination  Motor Design 168 (DSM) mapped to Team structure  Signal Design 93 Dependence across Teams matters A &Pkg_Design 968 Sum of Remaining Team_From Shell Design 288 Architecture  e rs Electronics Proto 168 m ine ea determines if  es ign up pli er sti cs _T ctr on ics na l E ng oto r Motor Proto 800 CD S Pla Ele Sig M GA dependence  Shell Proto Team_To 320 T1 T2 T2 T2 T2 stretches across  Signal Proto GAC Design 288 288 456 teams Test & Ship 288 168 128 93 168 380 T1 Supplier 968 668 93 168 168 128 T2 Plastics_Team 320 T2 Electronics 549 T2 Signal Engineers 576 23 T2 Motor 800 Global Project Design © 2009 NASA Challenge 2009 www.gpdesign.com
  • 24. Why dependence  Coordination is interaction across the architecture  is not enough to allow downstream effective independence.   Teams that aren’t dependent have no need to  coordinate. Even if demanded, coordination is not guaranteed  to occur. Coordination requires attention, priority, &  capacity . Interaction, communication, meetings, learning,  and response consume TIME AND BUDGET.    Slide 24 Global Project Design © 2009 NASA Challenge 2009 www.gpdesign.com
  • 25. Coordination  Team 1 Team 2 Distance is the  Supply Side Can we predict the amount of coordination effort required to effectively complete our direct work? Dependence Distance What does my team What is my team’s need in the progress & ability to coordinate results from others? with others? DEMAND SUPPLY Slide 25 for coordination of coordination Global Project Design © 2009 NASA Challenge 2009 www.gpdesign.com
  • 26. 0.0: Within small teams with shared tacit knowledge, distance Coordination  approaches “0” Distance is a  Measure of  1.0: Between teams with average shared work background, common native language, and co-location, distance is a Team To Team  nominal “1” Coordination  Ability  Coordination Distance is both a macro-level and micro-level measure e rs a m ine Te nic s ng sig n er s_ lE pli tic tro na r De up s c oto C 1S Pla Ele Sig 2M Team_Name GA T T2 T2 T2 T GAC Design 0.5 1.1 1.8 1.4 1.2 1.3 T1 Supplier 1.1 0.2 1.7 1.3 1.1 1.5 T2 Plastics_Team 1.9 1.8 0.3 1.7 2 1.7 T2 Electronics 1.4 1.3 1.7 0.1 1.2 1.4 T2 Signal Engineers 1.2 1.1 2 1.2 0 1.5 26 T2 Motor 1.3 1.5 1.7 1.4 1.5 0.2 Global Project Design © 2009 NASA Challenge 2009 www.gpdesign.com
  • 27. Global Factors  which influence  Communication efficiency Some parties working in 2nd language Coordination  Less shared work background Distance Team Size & Capacity Priority of attention to interaction vs. direct work Distribution & time zones Overlap of work hours Latency/ reaction to issues Travels costs and time Exception handling behavior Local work culture & assumptions differ, distract Quality priorities, re-work capacity and attention High chance of misreading indicators Slide 27 Global Project Design © 2009 NASA Challenge 2009 www.gpdesign.com
  • 28. Team 1 Team 2 Coordination =  Dependence X  Distance Coordination Dependency Matrix Coordination Distance Matrix Sum of Remaining Team_From ers ers ea m ine am ine _T ics ng Te ics ng n er cs on lE sig n r s_ on lE sig pli sti ctr na tor pp lie tic ctr na tor De up De s C 1S Pla Ele Sig Mo C Su Pla Ele Sig Mo Team_To GA T T2 T2 T2 T2 Team_Name GA T1 T2 T2 T2 T2 GAC Design 456 GAC Design 0.5 1.1 1.8 1.4 1.2 1.3 T1 Supplier 968 668 93 168 168 128 T1 Supplier 1.1 0.2 1.7 1.3 1.1 1.5 T2 Plastics_Team 320 T2 Plastics_Team 1.9 1.8 0.3 1.7 2 1.7 T2 Electronics 549 T2 Electronics 1.4 1.3 1.7 0.1 1.2 1.4 T2 Signal Engineers 576 T2 Signal Engineers 1.2 1.1 2 1.2 0 1.5 T2 Motor 800 T2 Motor 1.3 1.5 1.7 1.4 1.5 0.2 Coordination 28 Activity (Moser 1997) Global Project Design © 2009 NASA Challenge 2009 www.gpdesign.com
  • 29. Sum of Coordination Cost % rs am ee Te s gin Team to team n r s_ nic lE n sig lie tic tro na r De pp oto Distribution of  G AC T 1 Su T 2P las T2 Elec T 2 Sig T 2M coordination activity Coordination  GAC Design 5% 0% 0% 0% 0% 0% Activity across  Changes phase to phase Teams T1 Supplier 23% Sum of Coordination Cost % 3% 4% 5% Phase_From Team_From 4% 4% 1. Design 2. Prototype 3. Assembly Phase Phase Phase ers am ine T2 Plastics_Team 13% 0% 0% n 0% r 0% ic s 0% s_Te nic s ng r sig lie on c o lE pli e De pp le ctr sti ctr na tor up C 1S u 2E Pla Ele Sig Mo 1S Phase_To Team_To GA T T T2 T2 T2 T2 T 1. GAC Design 5% 0% 0% 0% 0% 0% 0% 0% Design Phase T2 Electronics 0% 0% 0% 1% 0% 0% T1 Supplier 23% 0% 0% 0% 0% 0% 0% 0% T2 Signal Engineers 0% 0% 0% 15% 0% 0% T2 Electronics 0% 0% 1% 0% 0% 0% 0% 0% T2 Motor 23% 0% 0% 0% 0% 0% 2. Prototype Phase T2 Plastics_Team 13% 0% 0% 0% 0% 0% 0% 0% T2 Signal Engineers 0% 0% 8% 0% 8% 0% 0% 0% T2 Motor 23% 0% 0% 0% 0% 0% 0% 0% T2 Electronics 0% 0% 0% 0% 0% 0% 0% 0% 29 3. Assembly Phase T1 Supplier 0% 1% 0% 4% 5% 4% 4% 2% Global Project Design © 2009 NASA Challenge 2009 www.gpdesign.com
  • 30. Coordination  If work is complex, teams large, and dependence  Distance stretches across distant teams, coordination  Summary  activity tends to increase  Simulator handles dependence and distance  interaction on a micro, transactional level. Distances at a transactional level create local  direct costs and increased duration The architecture determines if local coordination  causes systemic and propagating impacts Systemically, what happens if coordination activity  is not budgeted and prioritized?  Slide 30 Global Project Design © 2009 NASA Challenge 2009 www.gpdesign.com
  • 31. 3. Case Study: Product Development across 4 Global Regions Retrospective Analysis Slide 31 Global Project Design © 2009 www.gpdesign.com
  • 32. Case Description New product family of complex machinery for  multiple regional markets Approximately 150,000 hrs of effort for design &  development.  5 Gateways. Gateways 85% of scope was visible before G2.  54% from original product family scope  G0 – start G1 – concept 31% for options, not addressed until after G2. G2 – design 15% from scope increase at G3. G3 – engineer G4 – manufacture G5 – release Original Scope Original Scope &  Options Original Scope,  Options, & Scope  32 Increase Global Project Design © 2009 NASA Challenge 2009 www.gpdesign.com
  • 33. Scenarios:  A retrospective analysis:  starting condition data used to ask  Original, Options,  “What could we have known ahead of time?” & Scope Increase  Three Scenarios were modeled;  each simulated using  critical path (CPM) & global factors (GPD) settings. Original Scope CPM refers to the Critical Path Method for scheduling as  Original Scope &  used in traditional project tools.  CPM ignores  Options communication, time zones, mutual dependence, re‐work,  Original Scope,  Options, & Scope  and other global factors. Increase GPD refers to analysis by GPD's TeamPort which  incorporates communication, complex concurrency, re‐ work, time‐zones and other factors. 33 Global Project Design © 2009 NASA Challenge 2009 www.gpdesign.com
  • 34. Comparison of Forecasts: Schedule Gateways Original Scope Original Scope &  Options Original Scope,  Options, & Scope  Increase Gateways G0 – start G1 – concept G2 – design G3 – engineer G4 – manufacture G5 – release Slide 34 Global Project Design © 2009 NASA Challenge 2009 www.gpdesign.com
  • 35. Comparison of Forecasts: Cost x 4th Gateway Original Scope Original Scope &  Options Actual Original Scope,  Options, & Scope  Increase @ G4 GPD PM Gateways @ G3 @ G2 G0 – start CPM G1 – concept @ G1 G2 – design G3 – engineer G4 – manufacture PM forecasts by project team at each Gate during project. CPM forecasts (critical path) ignore coordination, concurrency, and re-work realities. GPD forecasts consider coordination, concurrency, re-work, time-zones and other global project realities 35 Global Project Design © CPM & GPD forecasts generated by TeamPort 2009 www.gpdesign.com
  • 36. Conclusion Teams in global projects can succeed through collaborative design of plans, simulating progress including coordination, exposing assumptions, and generating situational awareness. Slide 36 Global Project Design © 2009 www.gpdesign.com
  • 37. The Results of  Project design generates a plan. And options. The plan Project Design represents teams’ consensus of role, feasibility, optimality, and coordination approach. The plan is a social instrument; a dialogue amongst teams, not just a control instrument. Teams interact from their own point of view. Failure is visual before starting; allows team leaders to re-think how to participate. Architecture and complex dependence emphasized. The exercise exposes ideological assumptions and prevents wishful thinking. Teams see sensitivity of total project results to their own actions. Situational awareness and performance emerge as teams understand, commit, rehearse, and adapt Slide 37 ongoing with the plan. Global Project Design © 2009 NASA Challenge 2009 www.gpdesign.com