SlideShare une entreprise Scribd logo
1  sur  30
Sam Padgett presenting for
       Kristen Kehrer
   KSC Integration Office
       321-867-3691
Kristen.C.Kehrer@nasa.gov
   What are the differences among EV, EVM,
    and an EVMS?
   EVM Budget vs. Funds
   Resources and current initiatives within
    NASA
   Value of work accomplished expressed in terms of
    hours or dollars
   Calculated using an EV method assigned to a
    work package, e.g.
       Level Of Effort (LOE) - value is earned based on the
        plan; appropriate for work scope with no defined
        products
       % Complete – value is earned based on quantifiable
        measure of progress
       0/100 – all value is earned upon completion; appropriate
        for tasks that start and complete within one month
       50/50 – half of the value is earned when the task is
        started and the other half when complete; appropriate
        for tasks that span two months with equal work in each
       Milestones – value is earned when milestones are
        complete
Jan     Feb     Mar     Apr              EV Method
WBS #                     WBS Description            09      09     09      09      Budget

292360.09.02.04.14.02     Hazardous Gas Detection 5,500     9,500   6,800   2,400   24,200     None
                          System
292360.09.02.04.14.02.A   Fire & Leak Detector      3,300                           3,300      0/100
                          Bracket and Stand
                          Fabrication
292360.09.02.04.14.02.B   Distribution Box Wiring   2,200   2,200                   4,400      50/50

292360.09.02.04.14.02.C   Terminal Distributor              7,300                   7,300      0/100
                          Fabrication
292360.09.02.04.14.02.D   Cable Fabrication                         6,800   2,400   9,200     % Comp
    We are at the end of Jan-09, and this is where we are
            We started the Fire & Leak Detector Bracket and Stand Fabrication
             but didn’t finish
            We started the Distribution Box Wiring but didn’t finish
            We started and finished the Terminal Distributor Fabrication
        What is my EV?
                                   Jan     Feb     Mar     Apr                  EV
WBS Description                     09      09     09      09      Jan-09 EV   Method

Hazardous Gas Detection System     5,500   9,500   6,800   2,400    9,500       None

Fire & Leak Detector Bracket and   3,300                              0        0/100
Stand Fabrication

Distribution Box Wiring            2,200   2,200                    2,200      50/50

Terminal Distributor Fabrication           7,300                    7,300      0/100

Cable Fabrication                                  6,800   2,400      0        % Comp
   Utilizing this new measure (EV) in project
    management decision making to:
       Calculate cost and schedule variances
         Schedule Variance (SV) = EV – Plan (PV, BCWS, or S)
         Cost Variance = EV – Actuals (AC, ACWP, or A)
     Identify significant cost and schedule variances and
      their drivers
     Develop corrective action plans to get back on
      track
     Forecast future cost and schedule performance
     Summarize the data to support management needs
   EVM is both performance measurement (i.e.,
    what is the program status) and performance
    management (i.e., what we can do about it)
Spend Plan vs. Actual   OR     Budget vs. Actuals

                                             900
          800
                                             800
          700
                                             700                  Project Budget
          600
Dollars




                                             600                  Actual Cost to Date
          500
                                             500
          400
                                             400
          300
                                             300
          200
                                             200
          100
                                             100
          0
                                             0
                J F M A M J J A S O N D
                          Time
Estimate At
                                                       Completion
                                                       (EAC)


 $K
2,750
                     Reporting Cut-Off Date

        Total Budgeted Cost
                                                              }   Projected
                                                                  Overrun
                                                            Budget At
2,500                                                      Completion
                                                          (BAC)
2,250             Actuals


                                    }
2,000         Plan
                                                  Projected
1,750
                                }            CV   Slippage
1,500
                                        SV
1,250
1,000
 750                                   EV

 500
 250

                                    Time (Mos.)
                                                                              9
   We are at the end of Mar-09, and this is where we are
       We finished the Fire & Leak Detector Bracket and Stand
        Fabrication
       We are still not finished with Distribution Box Wiring
       We finished the Terminal Distributor Fab.
       We fabricated 6 of 10 cables*
       The actual costs are as follows:
         Jan-09 = $9,000
         Feb-09 = $4,000
         Mar-09 = $10,000
   How am I doing and where will I end up?

* Assume cables are of equal complexity
   Our budget through Mar-09 for the Hazardous Gas
    Detection System was $21,800
   We spent $23,000, so we are overrunning our plan
    by $1,200
    $35,000


    $30,000                     Spending Variance = $-1,200
    $25,000


    $20,000


    $15,000                                      PV


    $10,000                                      AC

                                                 BAC
     $5,000


        $-
              Jan-09   Feb-09        Mar-09            Apr-09
$35,000

              PV
$30,000
              EV
                             Likely VAC = -$6,182
$25,000       AC


              BAC
$20,000
              EAC                              Schedule Variance
$15,000
                                               = -$3,480

                                              Cost Variance
$10,000
                                              = $-4,680

 $5,000



    $-
          Jan-09    Feb-09          Mar-09           Apr-09
   The project manager is anticipating that the most likely
    scenario is that the remaining work will be finished with
    the same efficiency as the past and is predicting to
    overrun cost by $6,182. In a best case scenario, the
    remaining work will be completed on cost, and the
    project will overrun by $4,680.
   The project manager evaluated the remaining work and
    thinks that the remaining 4 cables will be fabricated and
    the distribution box wiring will be completed in April-
    09. The Haz Gas Detection System will finish on
    schedule.*
   Using traditional cost management, the cost variance is
    significantly understated and no assessment of
    schedule can be made.
* SV goes to zero when work is completed
   An organization’s internal management systems for
    planning and control, including processes for:
       Planning all authorized work scope to completion
       Assigning authority and responsibility at the work performance
        level
       Integrating cost, schedule, and technical aspects of the work
        into a detailed baseline plan
       Measuring progress objectively (earned value) at the work
        performance level
       Accumulating and assigning actual costs
       Analyzing variances from plans
       Summarizing and reporting performance data to higher levels
        of management for action
       Forecasting achievement of milestones and completion of
        contract events
       Forecasting final contract costs and
       Maintaining a baseline in a disciplined fashion and
        incorporating revisions in a timely manner
   Every company or government agency uses some form
    of business planning and control systems for
    management purposes
   When a project is deemed critical, the customer
    requires more rigor in the supplier’s internal planning
    and control systems to ensure performance data and
    forecasts are valid, accurate, and timely.
   The EVMS guidelines have been published as an
    American National Standards Institute/Electronic
    Industries Alliance standard ANSI/EIA-748, Earned Value
    Management Systems
     The guidelines are broad enough to allow for common sense
      application
     Most of the basic principles of an EVMS are already inherent in
      good business practices and program management
   Suppliers required to produce EV data are required to
    be in compliance with, or validated against, ANSI EIA-
    748
   Define authorized work                                Record direct costs from the accounting system
   Identify the Project’s Organization Structure         Summarize direct costs into the WBS
   Integrate cost and schedule systems                   Summarize direct costs into the Organizational
                                                           structure
   Identify the organization responsible for             Record indirect costs
    overhead costs                                        Identify unit costs, equivalent unit costs or lot
   Integrate the WBS and Organizational structure         costs
    to create control accounts                            Accurate material planning and control
   Sequentially schedule the work                        Generate monthly cost and schedule variance
   Identify interim measures of progress                  data at control accounts
                                                          Explain significant variances
   Establish time-phased budgets
                                                          Identify and explain indirect cost variances
   Identify significant cost elements in the budget
                                                          Summarize data through the WBS and
   Identify discrete work packages                        Organization
   Sum work packages and planning packages to a          Implement management actions as a result of
    control account                                        EVM analysis
   Identify and control Level of Effort                  Revise Estimates based on data
   Establish overhead budgets                            Incorporate authorized changes in a timely
                                                           manner
   Identify Management Reserve and Undistributed         Reconcile budgets with prior budgets
    Budgets                                               Control retroactive changes
   Reconcile target cost goal with the sum of all        Prevent all but authorized budget changes
    internal budgets                                      Document changes
The EVMS Process Overview

      Define the Work                  Performance Measurement
                                             Baseline (PMB)


               Plan the Work

                                                               Quantify & Measure
                                                               Earned Value
                          Work the plan


                                   Collect Results

     Change
                                              Measure Work In Process
     Control

                                                          Analyze Variances

                                                                  Implement
External   Internal
                                                                  Corrective
           Changes
Changes                                                            Actions


                                                                               18
Scope




           PLAN


Schedule           Budget




                            Budget vs. Funds




                                               19
What is Budget?                        What are Funds?
 Budget is created as an aid to the    Funding is process of supplying
 management process                      money to the project
 Cannot be spent                     Known by many names such as
    • A number written on a piece of   money, funding limits (obligations),
      paper (an objective)             actuals
    • A representation of work        Total costs for entire project
    • A planning vehicle                 • Experienced cost for work
    • A temporary element for              performed – actuals or ACWP
      project control                    • Expenditures & estimates of
                                           future spending for remaining
                                           project elements
 Can be planned - BCWS                 Estimate To Complete (ETC)
 Can be earned - BCWP
 BAC                                   Estimate At Complete (EAC)
                                                                           20
   Budget
       Budgeted Cost for Work Scheduled (BCWS)
         Time phased budget spread of required resources for the entire task
         Assigned (budgeted) value of the work (at any level; WP, CA, IPT, Project)
         Forms the Performance Measurement Baseline (PMB)
       Budget At Completion (BAC)
         Budgetary number representing ALL authorized work
         Cannot change without a change to scope/technical content, i.e.
          requirements change
   Funding
       Estimate To Complete (ETC)
         Funding required to complete remaining work
         When added to ACWP, it results in the EAC
       Estimate At Completion (EAC)
         Funding number representing ALL the money that will be spent
         Can (and will) change without a commensurate change to technical
          content
                                                                                       21
Project LCCE = Initial Project Budget Baseline
1. Technical Baseline     • Performance
                                                                        Initial Project
                            Objectives or
                                                                       Funding Profile
                          Parameters (e.g.,
                                                                       (PPBE process)
                           weight, thrust)
                           • Project WBS                                 (Commitment /
                              • CARDe                                      Obligation)
2. Schedule Baseline
                        • Schedule Objectives
                            (e.g., IOC, FOC)              $
                                • IMS
                                                                                                      Initial Project
                            • Critical Path
                                                                                                     Budget Baseline
                                • Risk
                                                                                                    The time phased
                                                                                                  expected costs based
3. Cost Baseline         • Cost estimating methods:
                                                                                                 on initial cost estimate
                                 • Parametric
          100
                                  • Historical
     40                   • Engineering (Bottom up)
            60                 • Considerations:
    15                                  • TRLs
                                  • Learning curves
         25
                                  • Production rates
            30                        • Risk, etc.            Year 1 Year 2   Year 3 Year 4 Year 5   Year 6 Year 7   Year 8
               30        • Resources include: work
                                                                                     TIME
                              force (Govt/Support
                          Contractor, Material, Travel,                                                                       22
                                    ODC, Etc.
MANAGEMENT RESERVE              FINANCIAL RESERVE


   Part of the PBB                Held outside the PBB
   Budget set aside for           Intended to cover
    management control              project-level overruns
    purposes (i.e., for the
    known-unknowns)                Typically held by
   Typically belongs to the        controller or exec
    project manager                 management
   Ceases to exist at end of
    program


                                                         23
      In EVM terminology, NASA Unallocated Future Expense (UFE) is considered
         a Financial Reserve (funding) and not Management Reserve (Budget)
                                                                      NASA EVM Project
 CONGRESS
                                  PROGRAM
  & OMB
                                   OFFICE
     Agency
     Baseline                       Management
   Commitment                        Baseline -
                                    PROGRAM

       UFE
                      UFE                                  AUW

                                        UFE             Management
                                                         Reserve
 AUTHORIZED                                                                      Project
                                  AUTHORIZED            Undistributed            Budget
                                                          Budget                  Base
                                                                          PMB
                                                        Distributed
                                                          Budget

Key:
       Held Back Funds/Funding Commitment Agreement

       Held Back Funds/Funding Management Agreement                             Chambers/Gibby
                                                                                    07/2010
       Not Strictly “Budget,” but should be inviolate
       Budget                                                                              24
   NASA EVMS Website at http://evm.nasa.gov/
   EVM Focal Point at each Center, Headquarters
    Mission Directorates, and Headquarters Mission
    Support Offices
   Implementation Handbooks
       Integrated Baseline Review (IBR) Toolkit
       Schedule Management Handbook
       Work Breakdown Structure (WBS) Handbook
   APPEL
     EVM Overview
     Understanding EVM
     Beyond EVM Basics: Baseline Control, Risk Considerations and
      Performance Indicators
     Advanced EVM Topics: Recognizing EVM and Scheduling Gaming, Abuse
      and Data Manipulation
     Integrating Cost and Schedule
   Online SATERN EVM Courses
       EVMS Overview
       Control Account Manager (CAM) Discussion
       IBR
       Scheduling Virtual Learning Lab
   Center-level resources
   DCMA Representative for EVMS
   Agency EVM Capability Project
       Work scope entails developing a common Agency process
        that can be used by all NASA projects
   Data Requirements Document (DRD) Guide for
    contracts and projects with EVM requirements
   EVM Working Group Quarterly Meetings
“Management 101”               “EVM 101”
• Organize              • Develop WBS
                        • Assign responsibilities
                        • Authorize work
• Plan                  • Plan, schedule, and budget work

• Coordinate            • Integrate project management
                          functions and scope, cost, and
                          schedule
• Direct                • Analyze performance data and use
                          for management decisions

• Control               • Maintain validity of integrated cost,
                          schedule, and technical performance
                          data
                                                             29
EVM Myth                      EVM Fact
• Government Requirement    •   Standard Business Practice
                                Management Tool
• Burdensome process        • Tailorable process based on project
                              size, complexity, & risk
• “Bean Counter” exercise   •   “Owned” by entire Management
                                Team
• Costly to implement       • Can be costly NOT to implement
                                 – (Overruns, Project Cancellations)

• Too Much Data             • Data can be summarized for reporting



                                                                 30

Contenu connexe

Similaire à Padgett.sam

Earned value management in action - A Webinar by Vivek Prakash, pmwares
Earned value management in action - A Webinar by Vivek Prakash, pmwares Earned value management in action - A Webinar by Vivek Prakash, pmwares
Earned value management in action - A Webinar by Vivek Prakash, pmwares
Vivek Prakash
 
Kim.yunjin
Kim.yunjinKim.yunjin
Kim.yunjin
NASAPMC
 
Homework chapter 7
Homework chapter 7Homework chapter 7
Homework chapter 7
Miles Nowak
 
Supporting Spreadsheet How to replace your datacenter with Amazon Web Services
Supporting Spreadsheet How to replace your datacenter with Amazon Web ServicesSupporting Spreadsheet How to replace your datacenter with Amazon Web Services
Supporting Spreadsheet How to replace your datacenter with Amazon Web Services
Smartscale Systems
 
NJFuture Redevelopment Forum 13 Infrastructure Strickland
NJFuture Redevelopment Forum 13 Infrastructure StricklandNJFuture Redevelopment Forum 13 Infrastructure Strickland
NJFuture Redevelopment Forum 13 Infrastructure Strickland
New Jersey Future
 
Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docx
sagarlesley
 
The simple problem of schedule performance indices
The simple problem of schedule performance indicesThe simple problem of schedule performance indices
The simple problem of schedule performance indices
Glen Alleman
 

Similaire à Padgett.sam (20)

Project Performance Measurement Earned Value A Starter
Project Performance Measurement   Earned Value   A StarterProject Performance Measurement   Earned Value   A Starter
Project Performance Measurement Earned Value A Starter
 
Earned value management in action - A Webinar by Vivek Prakash, pmwares
Earned value management in action - A Webinar by Vivek Prakash, pmwares Earned value management in action - A Webinar by Vivek Prakash, pmwares
Earned value management in action - A Webinar by Vivek Prakash, pmwares
 
Kim.yunjin
Kim.yunjinKim.yunjin
Kim.yunjin
 
Earnvalue analysis in Software engineering
Earnvalue analysis in Software engineeringEarnvalue analysis in Software engineering
Earnvalue analysis in Software engineering
 
Homework chapter 7
Homework chapter 7Homework chapter 7
Homework chapter 7
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 
Cost Controlling And Forecasting of Project.pdf
Cost Controlling And Forecasting of Project.pdfCost Controlling And Forecasting of Project.pdf
Cost Controlling And Forecasting of Project.pdf
 
Linking Budgets And Resources With Project Timelines
Linking Budgets And Resources With Project TimelinesLinking Budgets And Resources With Project Timelines
Linking Budgets And Resources With Project Timelines
 
Day 5:The Lebanese Energy Audit Experience: From Canada, India, Tunisia, Jord...
Day 5:The Lebanese Energy Audit Experience: From Canada, India, Tunisia, Jord...Day 5:The Lebanese Energy Audit Experience: From Canada, India, Tunisia, Jord...
Day 5:The Lebanese Energy Audit Experience: From Canada, India, Tunisia, Jord...
 
Earned Value Management Project Analysis
Earned Value Management Project Analysis Earned Value Management Project Analysis
Earned Value Management Project Analysis
 
Culture Check on using Earned Value in Organization
Culture Check on using Earned Value in OrganizationCulture Check on using Earned Value in Organization
Culture Check on using Earned Value in Organization
 
Supporting Spreadsheet How to replace your datacenter with Amazon Web Services
Supporting Spreadsheet How to replace your datacenter with Amazon Web ServicesSupporting Spreadsheet How to replace your datacenter with Amazon Web Services
Supporting Spreadsheet How to replace your datacenter with Amazon Web Services
 
S-Curve Presentation- 20130529
S-Curve Presentation- 20130529S-Curve Presentation- 20130529
S-Curve Presentation- 20130529
 
Earned value analysis
Earned value analysisEarned value analysis
Earned value analysis
 
NJFuture Redevelopment Forum 13 Infrastructure Strickland
NJFuture Redevelopment Forum 13 Infrastructure StricklandNJFuture Redevelopment Forum 13 Infrastructure Strickland
NJFuture Redevelopment Forum 13 Infrastructure Strickland
 
Earned Value Reporting
Earned Value ReportingEarned Value Reporting
Earned Value Reporting
 
BPP vetted contracts for feb. 2012
BPP vetted contracts for feb. 2012BPP vetted contracts for feb. 2012
BPP vetted contracts for feb. 2012
 
Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docx
 
The simple problem of schedule performance indices
The simple problem of schedule performance indicesThe simple problem of schedule performance indices
The simple problem of schedule performance indices
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 

Plus de NASAPMC

Bejmuk bo
Bejmuk boBejmuk bo
Bejmuk bo
NASAPMC
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski john
NASAPMC
 
Yew manson
Yew mansonYew manson
Yew manson
NASAPMC
 
Wood frank
Wood frankWood frank
Wood frank
NASAPMC
 
Wood frank
Wood frankWood frank
Wood frank
NASAPMC
 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)
NASAPMC
 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joe
NASAPMC
 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuart
NASAPMC
 
Stock gahm
Stock gahmStock gahm
Stock gahm
NASAPMC
 
Snow lee
Snow leeSnow lee
Snow lee
NASAPMC
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandra
NASAPMC
 
Seftas krage
Seftas krageSeftas krage
Seftas krage
NASAPMC
 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marco
NASAPMC
 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mike
NASAPMC
 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karlene
NASAPMC
 
Rackley mike
Rackley mikeRackley mike
Rackley mike
NASAPMC
 
Paradis william
Paradis williamParadis william
Paradis william
NASAPMC
 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeff
NASAPMC
 
O'keefe william
O'keefe williamO'keefe william
O'keefe william
NASAPMC
 
Muller ralf
Muller ralfMuller ralf
Muller ralf
NASAPMC
 

Plus de NASAPMC (20)

Bejmuk bo
Bejmuk boBejmuk bo
Bejmuk bo
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski john
 
Yew manson
Yew mansonYew manson
Yew manson
 
Wood frank
Wood frankWood frank
Wood frank
 
Wood frank
Wood frankWood frank
Wood frank
 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)
 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joe
 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuart
 
Stock gahm
Stock gahmStock gahm
Stock gahm
 
Snow lee
Snow leeSnow lee
Snow lee
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandra
 
Seftas krage
Seftas krageSeftas krage
Seftas krage
 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marco
 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mike
 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karlene
 
Rackley mike
Rackley mikeRackley mike
Rackley mike
 
Paradis william
Paradis williamParadis william
Paradis william
 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeff
 
O'keefe william
O'keefe williamO'keefe william
O'keefe william
 
Muller ralf
Muller ralfMuller ralf
Muller ralf
 

Dernier

Why Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire businessWhy Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire business
panagenda
 
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Safe Software
 

Dernier (20)

Why Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire businessWhy Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire business
 
Navi Mumbai Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Navi Mumbai Call Girls 🥰 8617370543 Service Offer VIP Hot ModelNavi Mumbai Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Navi Mumbai Call Girls 🥰 8617370543 Service Offer VIP Hot Model
 
Corporate and higher education May webinar.pptx
Corporate and higher education May webinar.pptxCorporate and higher education May webinar.pptx
Corporate and higher education May webinar.pptx
 
Manulife - Insurer Transformation Award 2024
Manulife - Insurer Transformation Award 2024Manulife - Insurer Transformation Award 2024
Manulife - Insurer Transformation Award 2024
 
Polkadot JAM Slides - Token2049 - By Dr. Gavin Wood
Polkadot JAM Slides - Token2049 - By Dr. Gavin WoodPolkadot JAM Slides - Token2049 - By Dr. Gavin Wood
Polkadot JAM Slides - Token2049 - By Dr. Gavin Wood
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024
 
presentation ICT roal in 21st century education
presentation ICT roal in 21st century educationpresentation ICT roal in 21st century education
presentation ICT roal in 21st century education
 
Apidays Singapore 2024 - Modernizing Securities Finance by Madhu Subbu
Apidays Singapore 2024 - Modernizing Securities Finance by Madhu SubbuApidays Singapore 2024 - Modernizing Securities Finance by Madhu Subbu
Apidays Singapore 2024 - Modernizing Securities Finance by Madhu Subbu
 
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, AdobeApidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
 
MS Copilot expands with MS Graph connectors
MS Copilot expands with MS Graph connectorsMS Copilot expands with MS Graph connectors
MS Copilot expands with MS Graph connectors
 
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
 
A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?
 
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
 
Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...
Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...
Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
 
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot TakeoffStrategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
 
A Beginners Guide to Building a RAG App Using Open Source Milvus
A Beginners Guide to Building a RAG App Using Open Source MilvusA Beginners Guide to Building a RAG App Using Open Source Milvus
A Beginners Guide to Building a RAG App Using Open Source Milvus
 
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
 
2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...
 

Padgett.sam

  • 1. Sam Padgett presenting for Kristen Kehrer KSC Integration Office 321-867-3691 Kristen.C.Kehrer@nasa.gov
  • 2. What are the differences among EV, EVM, and an EVMS?  EVM Budget vs. Funds  Resources and current initiatives within NASA
  • 3. Value of work accomplished expressed in terms of hours or dollars  Calculated using an EV method assigned to a work package, e.g.  Level Of Effort (LOE) - value is earned based on the plan; appropriate for work scope with no defined products  % Complete – value is earned based on quantifiable measure of progress  0/100 – all value is earned upon completion; appropriate for tasks that start and complete within one month  50/50 – half of the value is earned when the task is started and the other half when complete; appropriate for tasks that span two months with equal work in each  Milestones – value is earned when milestones are complete
  • 4. Jan Feb Mar Apr EV Method WBS # WBS Description 09 09 09 09 Budget 292360.09.02.04.14.02 Hazardous Gas Detection 5,500 9,500 6,800 2,400 24,200 None System 292360.09.02.04.14.02.A Fire & Leak Detector 3,300 3,300 0/100 Bracket and Stand Fabrication 292360.09.02.04.14.02.B Distribution Box Wiring 2,200 2,200 4,400 50/50 292360.09.02.04.14.02.C Terminal Distributor 7,300 7,300 0/100 Fabrication 292360.09.02.04.14.02.D Cable Fabrication 6,800 2,400 9,200 % Comp
  • 5. We are at the end of Jan-09, and this is where we are  We started the Fire & Leak Detector Bracket and Stand Fabrication but didn’t finish  We started the Distribution Box Wiring but didn’t finish  We started and finished the Terminal Distributor Fabrication  What is my EV? Jan Feb Mar Apr EV WBS Description 09 09 09 09 Jan-09 EV Method Hazardous Gas Detection System 5,500 9,500 6,800 2,400 9,500 None Fire & Leak Detector Bracket and 3,300 0 0/100 Stand Fabrication Distribution Box Wiring 2,200 2,200 2,200 50/50 Terminal Distributor Fabrication 7,300 7,300 0/100 Cable Fabrication 6,800 2,400 0 % Comp
  • 6.
  • 7. Utilizing this new measure (EV) in project management decision making to:  Calculate cost and schedule variances  Schedule Variance (SV) = EV – Plan (PV, BCWS, or S)  Cost Variance = EV – Actuals (AC, ACWP, or A)  Identify significant cost and schedule variances and their drivers  Develop corrective action plans to get back on track  Forecast future cost and schedule performance  Summarize the data to support management needs  EVM is both performance measurement (i.e., what is the program status) and performance management (i.e., what we can do about it)
  • 8. Spend Plan vs. Actual OR Budget vs. Actuals 900 800 800 700 700 Project Budget 600 Dollars 600 Actual Cost to Date 500 500 400 400 300 300 200 200 100 100 0 0 J F M A M J J A S O N D Time
  • 9. Estimate At Completion (EAC) $K 2,750 Reporting Cut-Off Date Total Budgeted Cost } Projected Overrun Budget At 2,500 Completion (BAC) 2,250 Actuals } 2,000 Plan Projected 1,750 } CV Slippage 1,500 SV 1,250 1,000 750 EV 500 250 Time (Mos.) 9
  • 10. We are at the end of Mar-09, and this is where we are  We finished the Fire & Leak Detector Bracket and Stand Fabrication  We are still not finished with Distribution Box Wiring  We finished the Terminal Distributor Fab.  We fabricated 6 of 10 cables*  The actual costs are as follows:  Jan-09 = $9,000  Feb-09 = $4,000  Mar-09 = $10,000  How am I doing and where will I end up? * Assume cables are of equal complexity
  • 11. Our budget through Mar-09 for the Hazardous Gas Detection System was $21,800  We spent $23,000, so we are overrunning our plan by $1,200 $35,000 $30,000 Spending Variance = $-1,200 $25,000 $20,000 $15,000 PV $10,000 AC BAC $5,000 $- Jan-09 Feb-09 Mar-09 Apr-09
  • 12. $35,000 PV $30,000 EV Likely VAC = -$6,182 $25,000 AC BAC $20,000 EAC Schedule Variance $15,000 = -$3,480 Cost Variance $10,000 = $-4,680 $5,000 $- Jan-09 Feb-09 Mar-09 Apr-09
  • 13. The project manager is anticipating that the most likely scenario is that the remaining work will be finished with the same efficiency as the past and is predicting to overrun cost by $6,182. In a best case scenario, the remaining work will be completed on cost, and the project will overrun by $4,680.  The project manager evaluated the remaining work and thinks that the remaining 4 cables will be fabricated and the distribution box wiring will be completed in April- 09. The Haz Gas Detection System will finish on schedule.*  Using traditional cost management, the cost variance is significantly understated and no assessment of schedule can be made. * SV goes to zero when work is completed
  • 14.
  • 15. An organization’s internal management systems for planning and control, including processes for:  Planning all authorized work scope to completion  Assigning authority and responsibility at the work performance level  Integrating cost, schedule, and technical aspects of the work into a detailed baseline plan  Measuring progress objectively (earned value) at the work performance level  Accumulating and assigning actual costs  Analyzing variances from plans  Summarizing and reporting performance data to higher levels of management for action  Forecasting achievement of milestones and completion of contract events  Forecasting final contract costs and  Maintaining a baseline in a disciplined fashion and incorporating revisions in a timely manner
  • 16. Every company or government agency uses some form of business planning and control systems for management purposes  When a project is deemed critical, the customer requires more rigor in the supplier’s internal planning and control systems to ensure performance data and forecasts are valid, accurate, and timely.  The EVMS guidelines have been published as an American National Standards Institute/Electronic Industries Alliance standard ANSI/EIA-748, Earned Value Management Systems  The guidelines are broad enough to allow for common sense application  Most of the basic principles of an EVMS are already inherent in good business practices and program management  Suppliers required to produce EV data are required to be in compliance with, or validated against, ANSI EIA- 748
  • 17. Define authorized work  Record direct costs from the accounting system  Identify the Project’s Organization Structure  Summarize direct costs into the WBS  Integrate cost and schedule systems  Summarize direct costs into the Organizational structure  Identify the organization responsible for  Record indirect costs overhead costs  Identify unit costs, equivalent unit costs or lot  Integrate the WBS and Organizational structure costs to create control accounts  Accurate material planning and control  Sequentially schedule the work  Generate monthly cost and schedule variance  Identify interim measures of progress data at control accounts  Explain significant variances  Establish time-phased budgets  Identify and explain indirect cost variances  Identify significant cost elements in the budget  Summarize data through the WBS and  Identify discrete work packages Organization  Sum work packages and planning packages to a  Implement management actions as a result of control account EVM analysis  Identify and control Level of Effort  Revise Estimates based on data  Establish overhead budgets  Incorporate authorized changes in a timely manner  Identify Management Reserve and Undistributed  Reconcile budgets with prior budgets Budgets  Control retroactive changes  Reconcile target cost goal with the sum of all  Prevent all but authorized budget changes internal budgets  Document changes
  • 18. The EVMS Process Overview Define the Work Performance Measurement Baseline (PMB) Plan the Work Quantify & Measure Earned Value Work the plan Collect Results Change Measure Work In Process Control Analyze Variances Implement External Internal Corrective Changes Changes Actions 18
  • 19. Scope PLAN Schedule Budget Budget vs. Funds 19
  • 20. What is Budget? What are Funds?  Budget is created as an aid to the  Funding is process of supplying management process money to the project  Cannot be spent  Known by many names such as • A number written on a piece of money, funding limits (obligations), paper (an objective) actuals • A representation of work  Total costs for entire project • A planning vehicle • Experienced cost for work • A temporary element for performed – actuals or ACWP project control • Expenditures & estimates of future spending for remaining project elements  Can be planned - BCWS  Estimate To Complete (ETC)  Can be earned - BCWP  BAC  Estimate At Complete (EAC) 20
  • 21. Budget  Budgeted Cost for Work Scheduled (BCWS)  Time phased budget spread of required resources for the entire task  Assigned (budgeted) value of the work (at any level; WP, CA, IPT, Project)  Forms the Performance Measurement Baseline (PMB)  Budget At Completion (BAC)  Budgetary number representing ALL authorized work  Cannot change without a change to scope/technical content, i.e. requirements change  Funding  Estimate To Complete (ETC)  Funding required to complete remaining work  When added to ACWP, it results in the EAC  Estimate At Completion (EAC)  Funding number representing ALL the money that will be spent  Can (and will) change without a commensurate change to technical content 21
  • 22. Project LCCE = Initial Project Budget Baseline 1. Technical Baseline • Performance Initial Project Objectives or Funding Profile Parameters (e.g., (PPBE process) weight, thrust) • Project WBS (Commitment / • CARDe Obligation) 2. Schedule Baseline • Schedule Objectives (e.g., IOC, FOC) $ • IMS Initial Project • Critical Path Budget Baseline • Risk The time phased expected costs based 3. Cost Baseline • Cost estimating methods: on initial cost estimate • Parametric 100 • Historical 40 • Engineering (Bottom up) 60 • Considerations: 15 • TRLs • Learning curves 25 • Production rates 30 • Risk, etc. Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 30 • Resources include: work TIME force (Govt/Support Contractor, Material, Travel, 22 ODC, Etc.
  • 23. MANAGEMENT RESERVE FINANCIAL RESERVE  Part of the PBB  Held outside the PBB  Budget set aside for  Intended to cover management control project-level overruns purposes (i.e., for the known-unknowns)  Typically held by  Typically belongs to the controller or exec project manager management  Ceases to exist at end of program 23
  • 24. In EVM terminology, NASA Unallocated Future Expense (UFE) is considered a Financial Reserve (funding) and not Management Reserve (Budget) NASA EVM Project CONGRESS PROGRAM & OMB OFFICE Agency Baseline Management Commitment Baseline - PROGRAM UFE UFE AUW UFE Management Reserve AUTHORIZED Project AUTHORIZED Undistributed Budget Budget Base PMB Distributed Budget Key: Held Back Funds/Funding Commitment Agreement Held Back Funds/Funding Management Agreement Chambers/Gibby 07/2010 Not Strictly “Budget,” but should be inviolate Budget 24
  • 25. NASA EVMS Website at http://evm.nasa.gov/  EVM Focal Point at each Center, Headquarters Mission Directorates, and Headquarters Mission Support Offices  Implementation Handbooks  Integrated Baseline Review (IBR) Toolkit  Schedule Management Handbook  Work Breakdown Structure (WBS) Handbook
  • 26. APPEL  EVM Overview  Understanding EVM  Beyond EVM Basics: Baseline Control, Risk Considerations and Performance Indicators  Advanced EVM Topics: Recognizing EVM and Scheduling Gaming, Abuse and Data Manipulation  Integrating Cost and Schedule  Online SATERN EVM Courses  EVMS Overview  Control Account Manager (CAM) Discussion  IBR  Scheduling Virtual Learning Lab  Center-level resources  DCMA Representative for EVMS
  • 27. Agency EVM Capability Project  Work scope entails developing a common Agency process that can be used by all NASA projects  Data Requirements Document (DRD) Guide for contracts and projects with EVM requirements  EVM Working Group Quarterly Meetings
  • 28.
  • 29. “Management 101” “EVM 101” • Organize • Develop WBS • Assign responsibilities • Authorize work • Plan • Plan, schedule, and budget work • Coordinate • Integrate project management functions and scope, cost, and schedule • Direct • Analyze performance data and use for management decisions • Control • Maintain validity of integrated cost, schedule, and technical performance data 29
  • 30. EVM Myth EVM Fact • Government Requirement • Standard Business Practice Management Tool • Burdensome process • Tailorable process based on project size, complexity, & risk • “Bean Counter” exercise • “Owned” by entire Management Team • Costly to implement • Can be costly NOT to implement – (Overruns, Project Cancellations) • Too Much Data • Data can be summarized for reporting 30

Notes de l'éditeur

  1. Work Package (WP). Detailed jobs, or material items, identified by the supplier for accomplishing work required. A work package has the following characteristics:(a) It represents units of work at levels where work is performed.(b) It is clearly distinguished from all other work packages.(c) It is assigned to a single organizational element.(d) It has scheduled start and completion dates and, as applicable, interim milestones, which are representative of physical accomplishment.(e) It has a budget or assigned value expressed in terms of dollars, man-hours, or other measurable units.(f) Its duration is limited to a relatively short span of time or it is subdivided by discrete value milestones to facilitate the objective measurement of work performed or it is level-of-effort. (g) It is integrated with detailed engineering, manufacturing, or other schedules.
  2. Hazardous Gas Detection System – None, because this is a control accountFire & Leak Detector Bracket and Stand Fabrication – 0/100 since this task is Planned to start and complete in one monthDistribution Box Wiring –50/50 Terminal Distributor Fabrication – 0/100 because this task is planned to start and complete in one monthCable Fabrication - % Complete based on number of cables fabricated
  3. Schedule Variance: I planned to get this much done (PV) but I really got this much done (EV)Cost Variance: For the work that I completed, I planned for it to cost this much (EV) but it really cost this much (AC).Lots of other indicators that can be calculated using EV:Cost Performance Index (CPI) = EV/ACSchedule Performance Index (SPI) = EV/PV
  4. Every company or government agency uses some form of business planning and control systems for management purposesIt works with other company systems to meet all of an organization’s day-to-day management needs
  5. Discuss the difference between the two based on the chart above.
  6. Discuss how the chart shows the funding needs and how the three components on the left give you that baseline.