Program/Project Management
and the High-Risk Plan
February 24, 2009
Contact Information


Agency-level High-Risk Team Lead

      Rita Svarcas
      Office of Program and Institutional Integration (OPII)
      NASA Headquarters

      Rita.Svarcas@nasa.gov
      202-358-0464




                   PM Challenge 2009                   2
Agenda
• GAO High-Risk List -- Background

• NASA Status on High-Risk List

• The Seven Initiatives

• Impact on Program/Project Management

    •   Definition of Success
    •   Supporting Measures
    •   Reporting Process
    •   Management Oversight

• Next Steps

• Conclusion


                   PM Challenge 2009     3
GAO High-Risk List – Background

• U.S. Government Accountability Office (GAO)
    • Known as
       • “The investigative arm of Congress"
       • “The congressional watchdog."
    • Supports Congress in meeting its constitutional responsibilities
    • Helps improve performance and accountability of federal
      government for benefit of American people

• GAO High-Risk List
   • Since 1990, periodically Identifies federal programs and operations
     that are high risk due to
      • Their greater vulnerabilities to fraud, waste, abuse, and
        mismanagement
      • The need for broad-based transformations to address major
        economy, efficiency, or effectiveness challenges

    • Lasting solutions to high-risk problems would potentially
       • Save billions of dollars,
       • Dramatically improve service to the public
       • Strengthen confidence and trust in the performance and
         accountability of the U.S. government
       • Ensure the ability of government to deliver on its promises
                      PM Challenge 2009                           4
NASA Status on High-Risk List

• “NASA Contract Management”
    • Appeared on first GAO High-Risk List (1990)
    • Remained on list at every update (every two years
      thereafter)
       • Nature of issue evolved over time
          • Undefinitized Contractual Actions
          • IFMP
          • Cost Overruns
                                             PRO
          • Cost Estimating                      JEC
                                            M
                                           MAN    T
                                              AGE
                                                 MEN
                                                    T
• Latest GAO update released January 2009
    • Changes NASA’s risk area to “Acquisition Management”
       • A more accurate characterization given breadth of topic
       • Acknowledges NASA’s efforts and progress
          • Summarized in this briefing

                    PM Challenge 2009                      5
The Seven Initiatives
  •   Program/Project Requirements and Implementation
      Practices
      •   NPR 7120, Management Councils, BPR

  •   Agency Strategic Acquisition Approach
      •   ASP, ASM, PSM

  •   Contractor Cost Performance Monitoring
      •   Requiring, obtaining and using contractor cost data

  •   Project Management Training and Development
      •   APPEL

  •   Improving Life Cycle Cost/Schedule Management
      Processes
      •   Performance reporting, cost estimating

  •   IEMP Process Improvement
      •   Concept of Operations and Gap Analysis

  •   Procurement Processes and Policies
      •   CMM, EVM policy, Award fee policy

                     PM Challenge 2009                          6
Impact on Program/Project Management



  • Definition of Success

  • Supporting Measures

  • Reporting Process

  • Management Oversight




              PM Challenge 2009        7
Impact on Program/Project Management
DEFINITION OF SUCCESS
NASA will maintain a cost performance level for
 its portfolio of major development projects that is
 within 110% of the budget-weighted aggregate
 cost baseline.

NASA will meet the baseline schedule goals for
 its portfolio of major development projects, with
 aggregate schedule slippage falling within 110%
 of baseline.

NASA will sustain mission success by staying on-
 course to meet Level 1 requirements for 90% of
 its portfolio of major development.

               PM Challenge 2009              8
Impact on Program/Project Management:
      REPORTING PROCESS
• NASA, OMB, and GAO will track NASA performance against Definition
  of Success

• High-Risk joins several existing Agency-level reporting requirements
    • Annual Performance Plan (APP)
    • Major Program Annual Report (MPAR)
    • Integrated Budget and Performance Plan (IBPD)
    • Performance Assessment Rating Tool (PART)
    • Congressional Thresholds Reporting
       • Cost at 15% and 30% growth
       • Schedule at 6 month slip
    • OMB Program Improvement Plans
    • GAO Quick-Look Books

• NASA Headquarters has consolidated data collection and reporting
   • Integrated reporting schedule
   • Uniform data collection template
   • More consistent definitions and guidance


                          PM Challenge 2009                       9
Existing Projects vs. High Risk Reporting Candidates
                                                                                                 Today

                Herschel
                  GLAST
                     NPP
                    Dawn
                     SDO                                                                                        Constellation
                   Kepler                                                                                       Space Operations
                 Phoenix                                                                                        Science
                     OCO
                Aquarius
                    Glory
                     LRO
                     MSL
Project




                    WISE
                   JWST
                   JUNO
               TDRS K/L
                     Ares
                    Orion
                   GRAIL
                   RBSP
                   LDCM     Note: SOFIA entered development in 1996.
            GPM (1st s/c)   LRD not defined but in Development until FOC in 2015
          Cx Ground Ops
                    MMS
                     EVA
          Cx Mission Ops

                        1/01      1/02    1/03      1/04     1/05       1/06    1/07    1/08     1/09    1/10      1/11    1/12    1/13
                                                                    Development Phase Duration

                                                           PM Challenge 2009                                                 10
Definition of Success and Supporting Measures: Baselines and Targets
                                            UPDATED VERSION: October 20, 2008
Outcomes (Definition of Success)
   1    NASA will maintain a cost performance level for its portfolio of major development projects that is within 110% of the budget-weighted aggregate c
   2    NASA will meet the baseline schedule goals for its portfolio of major development projects, with aggregate schedule slippage falling within 110% o
   3    NASA will sustain mission success by staying on-course to meet Level 1 requirements for 90% of its portfolio of major development projects by 20

Supporting Measures                                                                          Sep-08     Mar-09    Sep-09    Mar-10    Sep-10    Mar-11
Cost Performance Supporting Measures
Indicators of cost performance for new projects

  1.1   The LCC EAC performance for the portfolio of new major projects.          Target      110%      110%      110%      110%      110%      110%
                                                                                  Actual      100%
        The development cost EAC performance for the portfolio of new
  1.2   major projects.                                                           Target      115%      115%      115%      115%      115%      115%
                                                                                  Actual      100%

        Percentage of eligible contracts (for new development projects)
        using Earned Value Management reporting, based on associated
  1.3   deviations granted by the Headquarters Office of Procurement              Target      100%      100%      100%      100%      100%      100%
                                                                                  Actual      100%
Indicators of whether the Agency is reducing cost growth over time

  1.4   Semi-annual change in portfolio average LCC for new projects.             Target      ≤5%       ≤5%        ≤5%       ≤4%          ≤4%    ≤4%
                                                                                  Actual       0%
        Semi-annual change in portfolio average development cost for
  1.5   new projects.                                                             Target      ≤5%       ≤5%        ≤5%       ≤4%          ≤4%    ≤4%
                                                                                  Actual       0%

Schedule Performance Supporting Measures
Indicators of schedule performance for new projects
        Percentage change in development schedule EAC for new
  2.1   projects.                                                                 Target      110%      110%      110%      110%      110%      110%
                                                                                  Actual      100%
Indicators of whether the Agency is reducing schedule growth over time
        Average semi-annual growth in development schedule EAC for
  2.2   new projects.                                                             Target      ≤5%       ≤5%        ≤5%       ≤4%          ≤4%    ≤4%
                                                                                  Actual       0%

Mission Success (Level-1) Supporting Measures
Indicators of scope performance for new projects
  3.1   The portion of mission success APGs rated green.                          Target 90%        n/a     90%      n/a     90%      n/a
                                                                                  Actual  n/a       n/a              n/a              n/a
Note for purposes of comparison: the set of 13 space flight projects included in external reports through the FY 2009 budget (with SOFIA excl
restart) have had the following estimated performance as compared to confirmat
LCC: 117%;      Development Cost: 123%;        Development Schedule: 129%.

                                                      PM Challenge 2009                                                              11
Impact on Program/Project Management:
MANAGEMENT OVERSIGHT
  • Senior Leadership
     • Program Management Council
        • Baseline Performance Reviews
           • Status and progress
           • Issues and actions
     • Strategic Management Council
     • Operations Management Council
     • Internal Controls

  • Mission Directorates
       • Program level
       • Project level
       • Contract level

  • Centers


                PM Challenge 2009        12
Next Steps
• Jan 09 GAO High-Risk update urges NASA to –

   • Reduce persistent cost growth and schedule delays

   • Implement planned corrective actions

   • Deliver the kind of analysis and forward-looking information
     needed to effectively manage complex programs

   • Maintain focus on acquisition management reforms during
     transition from SSP to Cx

   • Tackle challenges despite increasingly constrained budget

   • Complete IFMP (scheduled for 2009)

   • Sustain vigorous executive leadership to foster expansion of
     business-oriented culture

   • Continue commitment to identify and take action on projects
     that are not achieving cost, schedule or performance goals
     upon which they were based when they were initiated

                    PM Challenge 2009                          13
Conclusion


    The Agency needs each of you in the
    NASA program/project community to --

       -- Take part in acquisition management
       improvement efforts

       -- Emphasize cost and schedule
       performance management…
       just as you do technical performance




             PM Challenge 2009                14

Contenu connexe

Tendances

Kremic.tibor
Kremic.tiborKremic.tibor
Kremic.tibor
NASAPMC
 
Dumbacher2012 pmchallenge
Dumbacher2012 pmchallengeDumbacher2012 pmchallenge
Dumbacher2012 pmchallenge
NASAPMC
 
Bauer.frank
Bauer.frankBauer.frank
Bauer.frank
NASAPMC
 
Grammier.richard
Grammier.richardGrammier.richard
Grammier.richard
NASAPMC
 
Lau.cheevon
Lau.cheevonLau.cheevon
Lau.cheevon
NASAPMC
 
Ortiz.james
Ortiz.jamesOrtiz.james
Ortiz.james
NASAPMC
 
Graham dave
Graham daveGraham dave
Graham dave
NASAPMC
 
Carsile.azarbain
Carsile.azarbainCarsile.azarbain
Carsile.azarbain
NASAPMC
 
Bladwin.kristen
Bladwin.kristenBladwin.kristen
Bladwin.kristen
NASAPMC
 
Bilardo.vince
Bilardo.vinceBilardo.vince
Bilardo.vince
NASAPMC
 
Newman lengyel dartpm-chal_case
Newman lengyel dartpm-chal_caseNewman lengyel dartpm-chal_case
Newman lengyel dartpm-chal_case
NASAPMC
 
Charles.leising
Charles.leisingCharles.leising
Charles.leising
NASAPMC
 
Daisy.mueller
Daisy.muellerDaisy.mueller
Daisy.mueller
NASAPMC
 
Randall.taylor
Randall.taylorRandall.taylor
Randall.taylor
NASAPMC
 
Oberhettinger
OberhettingerOberhettinger
Oberhettinger
NASAPMC
 
Thomas.coonce
Thomas.coonceThomas.coonce
Thomas.coonce
NASAPMC
 
Smalley stigberg petze
Smalley stigberg petzeSmalley stigberg petze
Smalley stigberg petze
NASAPMC
 
Mullane stanley-hamilton-wise
Mullane stanley-hamilton-wiseMullane stanley-hamilton-wise
Mullane stanley-hamilton-wise
NASAPMC
 
Ed mangopanelpm challengefinal
Ed mangopanelpm challengefinalEd mangopanelpm challengefinal
Ed mangopanelpm challengefinal
NASAPMC
 

Tendances (20)

Kremic.tibor
Kremic.tiborKremic.tibor
Kremic.tibor
 
Dumbacher2012 pmchallenge
Dumbacher2012 pmchallengeDumbacher2012 pmchallenge
Dumbacher2012 pmchallenge
 
Bauer.frank
Bauer.frankBauer.frank
Bauer.frank
 
Grammier.richard
Grammier.richardGrammier.richard
Grammier.richard
 
Lau.cheevon
Lau.cheevonLau.cheevon
Lau.cheevon
 
Ortiz.james
Ortiz.jamesOrtiz.james
Ortiz.james
 
Graham dave
Graham daveGraham dave
Graham dave
 
Carsile.azarbain
Carsile.azarbainCarsile.azarbain
Carsile.azarbain
 
Bladwin.kristen
Bladwin.kristenBladwin.kristen
Bladwin.kristen
 
Bilardo.vince
Bilardo.vinceBilardo.vince
Bilardo.vince
 
Newman lengyel dartpm-chal_case
Newman lengyel dartpm-chal_caseNewman lengyel dartpm-chal_case
Newman lengyel dartpm-chal_case
 
Charles.leising
Charles.leisingCharles.leising
Charles.leising
 
Daisy.mueller
Daisy.muellerDaisy.mueller
Daisy.mueller
 
Randall.taylor
Randall.taylorRandall.taylor
Randall.taylor
 
Oberhettinger
OberhettingerOberhettinger
Oberhettinger
 
Thomas.coonce
Thomas.coonceThomas.coonce
Thomas.coonce
 
Smalley stigberg petze
Smalley stigberg petzeSmalley stigberg petze
Smalley stigberg petze
 
Mullane stanley-hamilton-wise
Mullane stanley-hamilton-wiseMullane stanley-hamilton-wise
Mullane stanley-hamilton-wise
 
Ed mangopanelpm challengefinal
Ed mangopanelpm challengefinalEd mangopanelpm challengefinal
Ed mangopanelpm challengefinal
 
Symons
SymonsSymons
Symons
 

En vedette

Dawn.schaible
Dawn.schaibleDawn.schaible
Dawn.schaible
NASAPMC
 
Johnny busby
Johnny busbyJohnny busby
Johnny busby
NASAPMC
 
Backup jim cassidy
Backup jim cassidyBackup jim cassidy
Backup jim cassidy
NASAPMC
 
Black.j.smith.g
Black.j.smith.gBlack.j.smith.g
Black.j.smith.g
NASAPMC
 
Hoffman,ed ipmc update for pm challenge 02 22 2012
Hoffman,ed ipmc update for pm challenge 02 22 2012Hoffman,ed ipmc update for pm challenge 02 22 2012
Hoffman,ed ipmc update for pm challenge 02 22 2012
NASAPMC
 
Inter approach to_spaceprogmgmt
Inter approach to_spaceprogmgmtInter approach to_spaceprogmgmt
Inter approach to_spaceprogmgmt
NASAPMC
 
Anderson.joel
Anderson.joelAnderson.joel
Anderson.joel
NASAPMC
 
Pollitt.julie
Pollitt.juliePollitt.julie
Pollitt.julie
NASAPMC
 
Sally.godfrey
Sally.godfrey Sally.godfrey
Sally.godfrey
NASAPMC
 
Jeff.robinson
Jeff.robinsonJeff.robinson
Jeff.robinson
NASAPMC
 
Ipao great houseetc-programmatic analysis ll
Ipao great houseetc-programmatic analysis llIpao great houseetc-programmatic analysis ll
Ipao great houseetc-programmatic analysis ll
NASAPMC
 
Ortiz.james
Ortiz.jamesOrtiz.james
Ortiz.james
NASAPMC
 
Kothari.d.mitchell.r
Kothari.d.mitchell.rKothari.d.mitchell.r
Kothari.d.mitchell.r
NASAPMC
 
Kline.robinson
Kline.robinsonKline.robinson
Kline.robinson
NASAPMC
 
Krahula john
Krahula johnKrahula john
Krahula john
NASAPMC
 
Vipavetz.kevin
Vipavetz.kevinVipavetz.kevin
Vipavetz.kevin
NASAPMC
 
Goldstein.barry
Goldstein.barryGoldstein.barry
Goldstein.barry
NASAPMC
 
Gonzales.matthew
Gonzales.matthewGonzales.matthew
Gonzales.matthew
NASAPMC
 

En vedette (20)

Dawn.schaible
Dawn.schaibleDawn.schaible
Dawn.schaible
 
Johnny busby
Johnny busbyJohnny busby
Johnny busby
 
Backup jim cassidy
Backup jim cassidyBackup jim cassidy
Backup jim cassidy
 
Black.j.smith.g
Black.j.smith.gBlack.j.smith.g
Black.j.smith.g
 
Tiffany
TiffanyTiffany
Tiffany
 
Hoffman,ed ipmc update for pm challenge 02 22 2012
Hoffman,ed ipmc update for pm challenge 02 22 2012Hoffman,ed ipmc update for pm challenge 02 22 2012
Hoffman,ed ipmc update for pm challenge 02 22 2012
 
Inter approach to_spaceprogmgmt
Inter approach to_spaceprogmgmtInter approach to_spaceprogmgmt
Inter approach to_spaceprogmgmt
 
Anderson.joel
Anderson.joelAnderson.joel
Anderson.joel
 
Pollitt.julie
Pollitt.juliePollitt.julie
Pollitt.julie
 
Sally.godfrey
Sally.godfrey Sally.godfrey
Sally.godfrey
 
Jeff.robinson
Jeff.robinsonJeff.robinson
Jeff.robinson
 
Sparrow
SparrowSparrow
Sparrow
 
Ipao great houseetc-programmatic analysis ll
Ipao great houseetc-programmatic analysis llIpao great houseetc-programmatic analysis ll
Ipao great houseetc-programmatic analysis ll
 
Ortiz.james
Ortiz.jamesOrtiz.james
Ortiz.james
 
Kothari.d.mitchell.r
Kothari.d.mitchell.rKothari.d.mitchell.r
Kothari.d.mitchell.r
 
Kline.robinson
Kline.robinsonKline.robinson
Kline.robinson
 
Krahula john
Krahula johnKrahula john
Krahula john
 
Vipavetz.kevin
Vipavetz.kevinVipavetz.kevin
Vipavetz.kevin
 
Goldstein.barry
Goldstein.barryGoldstein.barry
Goldstein.barry
 
Gonzales.matthew
Gonzales.matthewGonzales.matthew
Gonzales.matthew
 

Similaire à Svarcas.rita

Mary.zimmerman
Mary.zimmermanMary.zimmerman
Mary.zimmerman
NASAPMC
 
Hoyt diana
Hoyt dianaHoyt diana
Hoyt diana
NASAPMC
 
Coonce.tom
Coonce.tomCoonce.tom
Coonce.tom
NASAPMC
 
Dwayne Davis resume June 2016
Dwayne Davis resume June 2016Dwayne Davis resume June 2016
Dwayne Davis resume June 2016
Dwayne Davis
 
David.graham
David.grahamDavid.graham
David.graham
NASAPMC
 
RCH Experience PM
RCH Experience PMRCH Experience PM
RCH Experience PM
Randy Horst
 
K gallagher tosborne
K gallagher tosborneK gallagher tosborne
K gallagher tosborne
NASAPMC
 
Vanessa.jeff
Vanessa.jeffVanessa.jeff
Vanessa.jeff
NASAPMC
 

Similaire à Svarcas.rita (20)

Mary.zimmerman
Mary.zimmermanMary.zimmerman
Mary.zimmerman
 
The impact of Risk on the Five Immutable Principles of Project Success by "Ri...
The impact of Risk on the Five Immutable Principles of Project Success by "Ri...The impact of Risk on the Five Immutable Principles of Project Success by "Ri...
The impact of Risk on the Five Immutable Principles of Project Success by "Ri...
 
Philippines - stregthening institutional capacity
Philippines - stregthening institutional capacityPhilippines - stregthening institutional capacity
Philippines - stregthening institutional capacity
 
Hoyt diana
Hoyt dianaHoyt diana
Hoyt diana
 
Risk Management Processes from Jerry Klanac
Risk Management Processes from Jerry KlanacRisk Management Processes from Jerry Klanac
Risk Management Processes from Jerry Klanac
 
ASCLME project management indicators
ASCLME project management indicatorsASCLME project management indicators
ASCLME project management indicators
 
ASCLME project management indicators
ASCLME project management indicatorsASCLME project management indicators
ASCLME project management indicators
 
Experience with the Design of Logical Frameworks and the Evaluation of Delive...
Experience with the Design of Logical Frameworks and the Evaluation of Delive...Experience with the Design of Logical Frameworks and the Evaluation of Delive...
Experience with the Design of Logical Frameworks and the Evaluation of Delive...
 
William masson 2016-cv_a
William masson 2016-cv_aWilliam masson 2016-cv_a
William masson 2016-cv_a
 
Cda Esm Comparative Decision Analysis Economic Safety Margin
Cda Esm Comparative Decision Analysis   Economic Safety MarginCda Esm Comparative Decision Analysis   Economic Safety Margin
Cda Esm Comparative Decision Analysis Economic Safety Margin
 
Coonce.tom
Coonce.tomCoonce.tom
Coonce.tom
 
EP Project Charter OpenWells2.3
EP Project Charter OpenWells2.3EP Project Charter OpenWells2.3
EP Project Charter OpenWells2.3
 
PD - Contract and Risk Conference - Integrated Schedule Cost Risk Analysis fo...
PD - Contract and Risk Conference - Integrated Schedule Cost Risk Analysis fo...PD - Contract and Risk Conference - Integrated Schedule Cost Risk Analysis fo...
PD - Contract and Risk Conference - Integrated Schedule Cost Risk Analysis fo...
 
CCS Projects Integration Workshop - London 3Nov11 - ROAD - CCS project integr...
CCS Projects Integration Workshop - London 3Nov11 - ROAD - CCS project integr...CCS Projects Integration Workshop - London 3Nov11 - ROAD - CCS project integr...
CCS Projects Integration Workshop - London 3Nov11 - ROAD - CCS project integr...
 
Scope creep - cylfe campain
Scope creep - cylfe campainScope creep - cylfe campain
Scope creep - cylfe campain
 
Dwayne Davis resume June 2016
Dwayne Davis resume June 2016Dwayne Davis resume June 2016
Dwayne Davis resume June 2016
 
David.graham
David.grahamDavid.graham
David.graham
 
RCH Experience PM
RCH Experience PMRCH Experience PM
RCH Experience PM
 
K gallagher tosborne
K gallagher tosborneK gallagher tosborne
K gallagher tosborne
 
Vanessa.jeff
Vanessa.jeffVanessa.jeff
Vanessa.jeff
 

Plus de NASAPMC

Bejmuk bo
Bejmuk boBejmuk bo
Bejmuk bo
NASAPMC
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski john
NASAPMC
 
Yew manson
Yew mansonYew manson
Yew manson
NASAPMC
 
Wood frank
Wood frankWood frank
Wood frank
NASAPMC
 
Wood frank
Wood frankWood frank
Wood frank
NASAPMC
 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)
NASAPMC
 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joe
NASAPMC
 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuart
NASAPMC
 
Stock gahm
Stock gahmStock gahm
Stock gahm
NASAPMC
 
Snow lee
Snow leeSnow lee
Snow lee
NASAPMC
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandra
NASAPMC
 
Seftas krage
Seftas krageSeftas krage
Seftas krage
NASAPMC
 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marco
NASAPMC
 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mike
NASAPMC
 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karlene
NASAPMC
 
Rackley mike
Rackley mikeRackley mike
Rackley mike
NASAPMC
 
Paradis william
Paradis williamParadis william
Paradis william
NASAPMC
 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeff
NASAPMC
 
O'keefe william
O'keefe williamO'keefe william
O'keefe william
NASAPMC
 
Muller ralf
Muller ralfMuller ralf
Muller ralf
NASAPMC
 

Plus de NASAPMC (20)

Bejmuk bo
Bejmuk boBejmuk bo
Bejmuk bo
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski john
 
Yew manson
Yew mansonYew manson
Yew manson
 
Wood frank
Wood frankWood frank
Wood frank
 
Wood frank
Wood frankWood frank
Wood frank
 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)
 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joe
 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuart
 
Stock gahm
Stock gahmStock gahm
Stock gahm
 
Snow lee
Snow leeSnow lee
Snow lee
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandra
 
Seftas krage
Seftas krageSeftas krage
Seftas krage
 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marco
 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mike
 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karlene
 
Rackley mike
Rackley mikeRackley mike
Rackley mike
 
Paradis william
Paradis williamParadis william
Paradis william
 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeff
 
O'keefe william
O'keefe williamO'keefe william
O'keefe william
 
Muller ralf
Muller ralfMuller ralf
Muller ralf
 

Dernier

EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
Earley Information Science
 
Histor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slideHistor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slide
vu2urc
 

Dernier (20)

Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
 
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
 
Data Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonData Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt Robison
 
A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024
 
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 
Automating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps ScriptAutomating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps Script
 
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024
 
Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)
 
Boost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfBoost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdf
 
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
 
Breaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountBreaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path Mount
 
Understanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdfUnderstanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdf
 
Exploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone ProcessorsExploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone Processors
 
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
 
Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024
 
Histor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slideHistor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slide
 
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfThe Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
 
Real Time Object Detection Using Open CV
Real Time Object Detection Using Open CVReal Time Object Detection Using Open CV
Real Time Object Detection Using Open CV
 

Svarcas.rita

  • 1. Program/Project Management and the High-Risk Plan February 24, 2009
  • 2. Contact Information Agency-level High-Risk Team Lead Rita Svarcas Office of Program and Institutional Integration (OPII) NASA Headquarters Rita.Svarcas@nasa.gov 202-358-0464 PM Challenge 2009 2
  • 3. Agenda • GAO High-Risk List -- Background • NASA Status on High-Risk List • The Seven Initiatives • Impact on Program/Project Management • Definition of Success • Supporting Measures • Reporting Process • Management Oversight • Next Steps • Conclusion PM Challenge 2009 3
  • 4. GAO High-Risk List – Background • U.S. Government Accountability Office (GAO) • Known as • “The investigative arm of Congress" • “The congressional watchdog." • Supports Congress in meeting its constitutional responsibilities • Helps improve performance and accountability of federal government for benefit of American people • GAO High-Risk List • Since 1990, periodically Identifies federal programs and operations that are high risk due to • Their greater vulnerabilities to fraud, waste, abuse, and mismanagement • The need for broad-based transformations to address major economy, efficiency, or effectiveness challenges • Lasting solutions to high-risk problems would potentially • Save billions of dollars, • Dramatically improve service to the public • Strengthen confidence and trust in the performance and accountability of the U.S. government • Ensure the ability of government to deliver on its promises PM Challenge 2009 4
  • 5. NASA Status on High-Risk List • “NASA Contract Management” • Appeared on first GAO High-Risk List (1990) • Remained on list at every update (every two years thereafter) • Nature of issue evolved over time • Undefinitized Contractual Actions • IFMP • Cost Overruns PRO • Cost Estimating JEC M MAN T AGE MEN T • Latest GAO update released January 2009 • Changes NASA’s risk area to “Acquisition Management” • A more accurate characterization given breadth of topic • Acknowledges NASA’s efforts and progress • Summarized in this briefing PM Challenge 2009 5
  • 6. The Seven Initiatives • Program/Project Requirements and Implementation Practices • NPR 7120, Management Councils, BPR • Agency Strategic Acquisition Approach • ASP, ASM, PSM • Contractor Cost Performance Monitoring • Requiring, obtaining and using contractor cost data • Project Management Training and Development • APPEL • Improving Life Cycle Cost/Schedule Management Processes • Performance reporting, cost estimating • IEMP Process Improvement • Concept of Operations and Gap Analysis • Procurement Processes and Policies • CMM, EVM policy, Award fee policy PM Challenge 2009 6
  • 7. Impact on Program/Project Management • Definition of Success • Supporting Measures • Reporting Process • Management Oversight PM Challenge 2009 7
  • 8. Impact on Program/Project Management DEFINITION OF SUCCESS NASA will maintain a cost performance level for its portfolio of major development projects that is within 110% of the budget-weighted aggregate cost baseline. NASA will meet the baseline schedule goals for its portfolio of major development projects, with aggregate schedule slippage falling within 110% of baseline. NASA will sustain mission success by staying on- course to meet Level 1 requirements for 90% of its portfolio of major development. PM Challenge 2009 8
  • 9. Impact on Program/Project Management: REPORTING PROCESS • NASA, OMB, and GAO will track NASA performance against Definition of Success • High-Risk joins several existing Agency-level reporting requirements • Annual Performance Plan (APP) • Major Program Annual Report (MPAR) • Integrated Budget and Performance Plan (IBPD) • Performance Assessment Rating Tool (PART) • Congressional Thresholds Reporting • Cost at 15% and 30% growth • Schedule at 6 month slip • OMB Program Improvement Plans • GAO Quick-Look Books • NASA Headquarters has consolidated data collection and reporting • Integrated reporting schedule • Uniform data collection template • More consistent definitions and guidance PM Challenge 2009 9
  • 10. Existing Projects vs. High Risk Reporting Candidates Today Herschel GLAST NPP Dawn SDO Constellation Kepler Space Operations Phoenix Science OCO Aquarius Glory LRO MSL Project WISE JWST JUNO TDRS K/L Ares Orion GRAIL RBSP LDCM Note: SOFIA entered development in 1996. GPM (1st s/c) LRD not defined but in Development until FOC in 2015 Cx Ground Ops MMS EVA Cx Mission Ops 1/01 1/02 1/03 1/04 1/05 1/06 1/07 1/08 1/09 1/10 1/11 1/12 1/13 Development Phase Duration PM Challenge 2009 10
  • 11. Definition of Success and Supporting Measures: Baselines and Targets UPDATED VERSION: October 20, 2008 Outcomes (Definition of Success) 1 NASA will maintain a cost performance level for its portfolio of major development projects that is within 110% of the budget-weighted aggregate c 2 NASA will meet the baseline schedule goals for its portfolio of major development projects, with aggregate schedule slippage falling within 110% o 3 NASA will sustain mission success by staying on-course to meet Level 1 requirements for 90% of its portfolio of major development projects by 20 Supporting Measures Sep-08 Mar-09 Sep-09 Mar-10 Sep-10 Mar-11 Cost Performance Supporting Measures Indicators of cost performance for new projects 1.1 The LCC EAC performance for the portfolio of new major projects. Target 110% 110% 110% 110% 110% 110% Actual 100% The development cost EAC performance for the portfolio of new 1.2 major projects. Target 115% 115% 115% 115% 115% 115% Actual 100% Percentage of eligible contracts (for new development projects) using Earned Value Management reporting, based on associated 1.3 deviations granted by the Headquarters Office of Procurement Target 100% 100% 100% 100% 100% 100% Actual 100% Indicators of whether the Agency is reducing cost growth over time 1.4 Semi-annual change in portfolio average LCC for new projects. Target ≤5% ≤5% ≤5% ≤4% ≤4% ≤4% Actual 0% Semi-annual change in portfolio average development cost for 1.5 new projects. Target ≤5% ≤5% ≤5% ≤4% ≤4% ≤4% Actual 0% Schedule Performance Supporting Measures Indicators of schedule performance for new projects Percentage change in development schedule EAC for new 2.1 projects. Target 110% 110% 110% 110% 110% 110% Actual 100% Indicators of whether the Agency is reducing schedule growth over time Average semi-annual growth in development schedule EAC for 2.2 new projects. Target ≤5% ≤5% ≤5% ≤4% ≤4% ≤4% Actual 0% Mission Success (Level-1) Supporting Measures Indicators of scope performance for new projects 3.1 The portion of mission success APGs rated green. Target 90% n/a 90% n/a 90% n/a Actual n/a n/a n/a n/a Note for purposes of comparison: the set of 13 space flight projects included in external reports through the FY 2009 budget (with SOFIA excl restart) have had the following estimated performance as compared to confirmat LCC: 117%; Development Cost: 123%; Development Schedule: 129%. PM Challenge 2009 11
  • 12. Impact on Program/Project Management: MANAGEMENT OVERSIGHT • Senior Leadership • Program Management Council • Baseline Performance Reviews • Status and progress • Issues and actions • Strategic Management Council • Operations Management Council • Internal Controls • Mission Directorates • Program level • Project level • Contract level • Centers PM Challenge 2009 12
  • 13. Next Steps • Jan 09 GAO High-Risk update urges NASA to – • Reduce persistent cost growth and schedule delays • Implement planned corrective actions • Deliver the kind of analysis and forward-looking information needed to effectively manage complex programs • Maintain focus on acquisition management reforms during transition from SSP to Cx • Tackle challenges despite increasingly constrained budget • Complete IFMP (scheduled for 2009) • Sustain vigorous executive leadership to foster expansion of business-oriented culture • Continue commitment to identify and take action on projects that are not achieving cost, schedule or performance goals upon which they were based when they were initiated PM Challenge 2009 13
  • 14. Conclusion The Agency needs each of you in the NASA program/project community to -- -- Take part in acquisition management improvement efforts -- Emphasize cost and schedule performance management… just as you do technical performance PM Challenge 2009 14