SlideShare une entreprise Scribd logo
1  sur  45
1
National Institute of Technology Patna
Presentation for Major Project (8CE195)
On
CONSTRUCTION OF FLYOVER IN PATNA
Presented by
Narayan Gupta(1403037)
Mahendra Kumar(1403089)
Akhilesh Rajpoot (1403016)
2
Construction of flyover
1. Connecting Mithapur flyover to Bhikhari Thakur flyover via R-Block junction (166 crores)
2. Connecting Mithapur flyover to Chiraiyatand flyover via karbigahiya (121 crores)
Client
Bihar Rajya Pul Nirman Nigam Ltd. Patna
Contractor
Rachna Construction Co. Bharuch, Gujrat
Project Detail
3
Introduction
1 2R-Block junction karbigahiya
4
What is flyover?
A bridge over another road
Allowing traffic without interruption
with its approaches on both side
Super structure
Substructure
Foundation
Girder
Pier Cap
Pier shaft
Pile cap
Pile
5
Execution of Project
Sequence of construction
1. Surveying
2. Analysis and design of the structure
3. Piling and Pile cap Construction
4. Construction of Pier shaft and Pier cap
5. Construction of Pedestal and seismic stopper
6. Launching and gluing of segments
7. Construction of road over bridge
6
SURVEYING (TOPOGRAPHICAL SURVEY)
Topography is used to locater and determine
the position of any point in both the horizontal
and vertical coordinates.
various maps are studied and then detailed is
done by Total station (TS) and layouts are
given on AutoCAD.
By using AutoCAD we can find the
coordinates(north, east) and reduce level of
any point.
Coordinates of any point is marked with the
help of Total station.
Reduce level (RL) is marked by using Auto
level.
Circular mark on ground with
nail to represent a particular
coordinate and RL
7
Auto level to mark the RL
Total Station to mark coordinate
8
Piling
Type of pile - Bored Cast in-situ concrete piles
Code of practice - (IS 2911-part 1-section 2:2010)
1- Point is located on ground to start the excavation.
2- Soil is excavated by auger at located point and
liner(length 2-3m) is inserted.
FOUNDATIONS: Foundations are the structures
which are constructed below existing ground level. It
sustains the loads coming from the sub structures and
superstructures. Bridges had to carry a big load so PILE
FOUNDATION are preferred
Auger
Liner
9
3- Flushing is done using bentonite slurry
and bentonite is also used for the
stabilization of bore hole and boring is done
upto desired depth (30m-34m).
Bentonite
Tank for mixing of bentonite and waterHydrometer
10
4- boring is done by RIG machine(MAIT) and Bucket.
Rig machine
Bucket
11
5- formation of cage
Dimension and Reinforcement Detail for pile
Cage
Cover block
12
6-Shifting of cage into borehole
13
7- Manner of concreting which shall be by use of tremie
Tremie pipe(dia 200mm)-
for flushing and concreting
TM
Concrete pouring from TM into tremie
through hopper
Insertion of tremie pipe
14
Pile cap
1-Excvation of Soil for pile cap
15
2- Chipping of extra unsound concrete of pile that is above cut off level
And PCC is done at cut off level (thickness of PCC-100mm)
16
Hexagonal Pile cap
Rectangular Pile cap
Scaffolding for reinforcement work of pile cap
17
Reinforcement For Hexagonal Pile capReinforcement of Rectangular Pile Cap
Reinforcement of Pile Cap (4 type)
18
Drawing and BBS of Pile Cap
19
Cleaning and
lubrication of formwork
Assembling of
formwork
With clear cover of
75mm
20
Location of pier shaft is marked using total station
Vertical bar of pier shaft are placed in to marked location
21
Pouring of concrete and compaction of concrete using immersion vibrator
Workability is checked by slump test before pouring and sample is collected for compressive strength
22
Shear key is made at construction joint
Unloading of formwork
Curing of pile cape
23
After 28 days of pile cap casting , the paint of epoxy coal
tar Is applied to the surface of pile cap to make the
surface impermeable
Instead of using paint, grade of concrete is increased to
M- 45
24
Pier Shaft
Drawing and detailing of pier shaft BBS of pier shaft
25
Pier Shaft
Assembly of reinforcement for first lift Cleaning and lubrication of formwork and it is applied
26
Pouring of concrete using pump and TM
Workability is checked before pouring and cubes are casted
for compressive strength
Vertical pipe is used to prevent the
segregation of concrete
27
Reinforcement is done for second lift
Formwork is placed using hydra and pouring is done
28
Pier Shaft Curing of pier shaft is done using jute bag (sprinkle method)
29
Pier Cap and Portal beam of rotary is under construction….
30
Test
1- sample of concrete is collected at the time of pouring.
workability is checked by slump test.
for compressive strength of concrete, cube are casted and sent to lab for testing
Slump cone
31
Pile load test
Routine test
As per 2911 (part 4):1985
It is carried out on a working
pile with a view to check
whether pile is capable of
taking the working load
assigned to it.
The number of tests may
generally be one-half percent
of the total number of piles
required.
In this test compression load
is applied to the pile top by
means of a hydraulic jack
against rolled steel joist and
suitable load frame capable of
providing reaction and the
settlement is recorded by dial
gauges.
Dial gauge
Hydraulic jack
Kentledge
Maximum allowable settlement is 12 mm
32
Pile Integrity test
Non destructive pile integrity test (PIT)
using low strain integrity test
As per IS 14893:2001
This test is performed for confirming the
integrity of pile upto full depth
33
Supervision
-Helmet, jacket and shoes
for all employs and worker
-Barricading, Instruction
board, light, reflector, safety
cone, flag
-safety belt is used if any
worker is at height more
than 2m from ground
Safety
34
Supervision
Quality control
• Quality of Concrete--- workability and strength
compaction of concrete using immersion vibrator (IS 3558:1983)
curing
• Steel --- reinforcement as per drawing and BBS, dia and length of bar, spacing of bar,
lap length, binding of bar, development length, coupler, clear cover.
• Other material --- lubricant, bentonite, coal tar epoxy, paint etc.
35
Concrete material
Pile M 35
PCC M 15
Pile cape M 40
Pier shaft M 50
Clear cover to the reinforcement shall be
a) Pile cape - 75mm
b) Pile - 75mm
c) Pier - 50/75mm
Minimum lap length
Pile = 54d
Pile cape = 51d( for bottom and side face reinforcement)
=78d (for top face reinforcement )
Pier = 44d
d- Diameter of smaller bar being lapped
Steel
TMT bar (Fe 500D)
36
Cutting and bending of steel at yard
Threading for rebar splicing mechanical coupler
Reinforcement Yard
37
Batching plant
for production
of concrete
Batching Plant
38
Testing machines at lab
39
Fabrication of formwork and staging
Fabrication unit
40
Machine and Tools
Trailer concrete pump
Backhoe loader
Transit mixture
Water tanker Crawler crane
41
Machine and Tools
Rig machine
Hydraulic crane
Immersion
needle
vibrator
Concrete
breaker
42
Machine and Tools
Tremie pipe Funnel
Bucket Auger
Liner
43
Conclusion
Flyover makes transportation very easy. It becomes very difficult task when there
is a project inside the city. R-block and Karbigahiya are the busiest route of
Patna. In construction of flyover, construction of foundation requires large area
that interrupt the already running traffic.
Some point what we learned at site.
• To analyze the drawing of project and to prepare the BBS from drawing.
• Calculation of required concrete, steel and other material
• Surveying for accuracy of position of different part
• Various site test to ensure the quality of construction
• Safety check for efficient work
• Management of running traffic with the help of local police
• Handling of existing structure like sewer, underground cables and statue.
• Maintenance of data for completed structure
44
References
1. IS 456:2000
2. IS 2911 (Part 1/Sec 2):2010
3. IS 2911 (part 4):1985
4. IS 14893:2001
5. IS 3558:1983
Code of practice for plain and reinforced concrete
Design and construction of pile foundations-code of practice (bored cast in-
situ concrete piles)
Codes of practice for design and construction of pile foundations – load
test on piles
Non-destructive integrity testing of piles (NDT)-guidelines
Code of practice for use of immersion vibrators for consolidating concrete
45
THANK YOU

Contenu connexe

Tendances

Road, Culvert & Bridge Training
Road, Culvert & Bridge TrainingRoad, Culvert & Bridge Training
Road, Culvert & Bridge TrainingAbhishek Bharti
 
Internship report on rcc road
Internship report on rcc roadInternship report on rcc road
Internship report on rcc roaddeepak athwal
 
Training report - RCC Bridge
Training report - RCC BridgeTraining report - RCC Bridge
Training report - RCC BridgePRASUNMANI
 
REPORT ON SUMMER TRAINING AT PWD(FLEXIBLE PAVEMENTS CONSTRUCTION)
REPORT ON SUMMER TRAINING AT PWD(FLEXIBLE PAVEMENTS CONSTRUCTION)REPORT ON SUMMER TRAINING AT PWD(FLEXIBLE PAVEMENTS CONSTRUCTION)
REPORT ON SUMMER TRAINING AT PWD(FLEXIBLE PAVEMENTS CONSTRUCTION)Ratnesh Kushwaha
 
INDUSTRIAL TRAINING PRESENTATION FOR CIVIL ENGINEERING
INDUSTRIAL TRAINING PRESENTATION FOR CIVIL ENGINEERING INDUSTRIAL TRAINING PRESENTATION FOR CIVIL ENGINEERING
INDUSTRIAL TRAINING PRESENTATION FOR CIVIL ENGINEERING Ram1239
 
HIGH FLOOD LEVEL BRIDGE CONSTRUCTION
HIGH FLOOD LEVEL BRIDGE CONSTRUCTIONHIGH FLOOD LEVEL BRIDGE CONSTRUCTION
HIGH FLOOD LEVEL BRIDGE CONSTRUCTIONTEJPRAKASH KUMAWAT
 
Construction of flexible pavement
Construction of flexible pavementConstruction of flexible pavement
Construction of flexible pavementUTU Dehradun
 
A project report on flyover internship bihar rajya pul nirman nigam limited p...
A project report on flyover internship bihar rajya pul nirman nigam limited p...A project report on flyover internship bihar rajya pul nirman nigam limited p...
A project report on flyover internship bihar rajya pul nirman nigam limited p...Prashant Shaurabh
 
TRAINING REPORT ON COSTRUCTION OF FLYOVER FROM MITHAPUR TO CHIRIYATAND (BIHAR)
TRAINING REPORT ON  COSTRUCTION OF FLYOVER FROM  MITHAPUR TO CHIRIYATAND (BIHAR)TRAINING REPORT ON  COSTRUCTION OF FLYOVER FROM  MITHAPUR TO CHIRIYATAND (BIHAR)
TRAINING REPORT ON COSTRUCTION OF FLYOVER FROM MITHAPUR TO CHIRIYATAND (BIHAR)vishal prakash
 
flyover internship 2
flyover internship 2flyover internship 2
flyover internship 2Ravi Mehta
 
Flexible pavement presentation
Flexible pavement presentationFlexible pavement presentation
Flexible pavement presentationPawan Kumar
 
Hyderabad metro rail L&T | Construction sequence and procedure
Hyderabad metro rail L&T | Construction sequence and procedureHyderabad metro rail L&T | Construction sequence and procedure
Hyderabad metro rail L&T | Construction sequence and procedureAravind Samala
 
Rigid pavement
Rigid pavementRigid pavement
Rigid pavementpjainrahul
 
construction of flexible pavement
construction of flexible pavementconstruction of flexible pavement
construction of flexible pavementRafi Khan
 
Project report file on construction of flexible pavement by Harshit Prakash Garg
Project report file on construction of flexible pavement by Harshit Prakash GargProject report file on construction of flexible pavement by Harshit Prakash Garg
Project report file on construction of flexible pavement by Harshit Prakash Gargharshit315
 
bridge report
bridge reportbridge report
bridge reportabc def
 

Tendances (20)

Road, Culvert & Bridge Training
Road, Culvert & Bridge TrainingRoad, Culvert & Bridge Training
Road, Culvert & Bridge Training
 
Internship report on rcc road
Internship report on rcc roadInternship report on rcc road
Internship report on rcc road
 
FINAL REPORT
FINAL REPORTFINAL REPORT
FINAL REPORT
 
Training report - RCC Bridge
Training report - RCC BridgeTraining report - RCC Bridge
Training report - RCC Bridge
 
REPORT ON SUMMER TRAINING AT PWD(FLEXIBLE PAVEMENTS CONSTRUCTION)
REPORT ON SUMMER TRAINING AT PWD(FLEXIBLE PAVEMENTS CONSTRUCTION)REPORT ON SUMMER TRAINING AT PWD(FLEXIBLE PAVEMENTS CONSTRUCTION)
REPORT ON SUMMER TRAINING AT PWD(FLEXIBLE PAVEMENTS CONSTRUCTION)
 
INDUSTRIAL TRAINING PRESENTATION FOR CIVIL ENGINEERING
INDUSTRIAL TRAINING PRESENTATION FOR CIVIL ENGINEERING INDUSTRIAL TRAINING PRESENTATION FOR CIVIL ENGINEERING
INDUSTRIAL TRAINING PRESENTATION FOR CIVIL ENGINEERING
 
HIGH FLOOD LEVEL BRIDGE CONSTRUCTION
HIGH FLOOD LEVEL BRIDGE CONSTRUCTIONHIGH FLOOD LEVEL BRIDGE CONSTRUCTION
HIGH FLOOD LEVEL BRIDGE CONSTRUCTION
 
Concrete mix design
Concrete mix designConcrete mix design
Concrete mix design
 
Construction of flexible pavement
Construction of flexible pavementConstruction of flexible pavement
Construction of flexible pavement
 
A project report on flyover internship bihar rajya pul nirman nigam limited p...
A project report on flyover internship bihar rajya pul nirman nigam limited p...A project report on flyover internship bihar rajya pul nirman nigam limited p...
A project report on flyover internship bihar rajya pul nirman nigam limited p...
 
TRAINING REPORT ON COSTRUCTION OF FLYOVER FROM MITHAPUR TO CHIRIYATAND (BIHAR)
TRAINING REPORT ON  COSTRUCTION OF FLYOVER FROM  MITHAPUR TO CHIRIYATAND (BIHAR)TRAINING REPORT ON  COSTRUCTION OF FLYOVER FROM  MITHAPUR TO CHIRIYATAND (BIHAR)
TRAINING REPORT ON COSTRUCTION OF FLYOVER FROM MITHAPUR TO CHIRIYATAND (BIHAR)
 
flyover internship 2
flyover internship 2flyover internship 2
flyover internship 2
 
Flexible pavement presentation
Flexible pavement presentationFlexible pavement presentation
Flexible pavement presentation
 
Hyderabad metro rail L&T | Construction sequence and procedure
Hyderabad metro rail L&T | Construction sequence and procedureHyderabad metro rail L&T | Construction sequence and procedure
Hyderabad metro rail L&T | Construction sequence and procedure
 
Rigid pavement
Rigid pavementRigid pavement
Rigid pavement
 
construction of flexible pavement
construction of flexible pavementconstruction of flexible pavement
construction of flexible pavement
 
Project report file on construction of flexible pavement by Harshit Prakash Garg
Project report file on construction of flexible pavement by Harshit Prakash GargProject report file on construction of flexible pavement by Harshit Prakash Garg
Project report file on construction of flexible pavement by Harshit Prakash Garg
 
Bridge report
Bridge reportBridge report
Bridge report
 
bridge report
bridge reportbridge report
bridge report
 
Training report ON BRIDGE
Training report ON BRIDGETraining report ON BRIDGE
Training report ON BRIDGE
 

Similaire à Major Project ppt

Larsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship PresentationLarsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship PresentationShuBham RaNa
 
DMRC (METRO TRAINING REPORT)
DMRC (METRO TRAINING REPORT)DMRC (METRO TRAINING REPORT)
DMRC (METRO TRAINING REPORT)Sukhdarshan Singh
 
Mahakali Bridge Project Presentation (2077 chaitra 11)
Mahakali Bridge Project Presentation (2077 chaitra 11)Mahakali Bridge Project Presentation (2077 chaitra 11)
Mahakali Bridge Project Presentation (2077 chaitra 11)Rabindra Shrestha
 
Industrial Training Report1
Industrial Training Report1Industrial Training Report1
Industrial Training Report1Er Naveen Kumar
 
presentation on shotcrete technology
presentation on shotcrete technologypresentation on shotcrete technology
presentation on shotcrete technologyAbhishek Paul
 
Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Rajesh Prasad
 
signature bridge short presentation
signature bridge short presentationsignature bridge short presentation
signature bridge short presentationPravin Gaurav
 
tunnelling scope, construction techniques and necessity
tunnelling scope, construction techniques and necessitytunnelling scope, construction techniques and necessity
tunnelling scope, construction techniques and necessityShashank Gaurav
 
Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...
Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...
Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...IJERA Editor
 
Dda training presentation
Dda training presentationDda training presentation
Dda training presentationAKASHGARG131
 

Similaire à Major Project ppt (20)

Saurabhk601
Saurabhk601Saurabhk601
Saurabhk601
 
Metroppt
MetropptMetroppt
Metroppt
 
Intership in DMRC
Intership in DMRCIntership in DMRC
Intership in DMRC
 
Summer training report
Summer training reportSummer training report
Summer training report
 
Larsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship PresentationLarsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
 
DMRC (METRO TRAINING REPORT)
DMRC (METRO TRAINING REPORT)DMRC (METRO TRAINING REPORT)
DMRC (METRO TRAINING REPORT)
 
presentation
presentationpresentation
presentation
 
Railway over bridge
Railway over bridgeRailway over bridge
Railway over bridge
 
Shotcrete technology
Shotcrete technologyShotcrete technology
Shotcrete technology
 
Mahakali Bridge Project Presentation (2077 chaitra 11)
Mahakali Bridge Project Presentation (2077 chaitra 11)Mahakali Bridge Project Presentation (2077 chaitra 11)
Mahakali Bridge Project Presentation (2077 chaitra 11)
 
Industrial Training Report1
Industrial Training Report1Industrial Training Report1
Industrial Training Report1
 
Delhi metro presention
Delhi   metro presentionDelhi   metro presention
Delhi metro presention
 
presentation on shotcrete technology
presentation on shotcrete technologypresentation on shotcrete technology
presentation on shotcrete technology
 
Box culverts
Box culvertsBox culverts
Box culverts
 
Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...
 
signature bridge short presentation
signature bridge short presentationsignature bridge short presentation
signature bridge short presentation
 
tunnelling scope, construction techniques and necessity
tunnelling scope, construction techniques and necessitytunnelling scope, construction techniques and necessity
tunnelling scope, construction techniques and necessity
 
Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...
Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...
Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...
 
Pavements PPT
 Pavements PPT  Pavements PPT
Pavements PPT
 
Dda training presentation
Dda training presentationDda training presentation
Dda training presentation
 

Dernier

CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...Call Girls in Nagpur High Profile
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGMANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGSIVASHANKAR N
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 

Dernier (20)

DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGMANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 

Major Project ppt

  • 1. 1 National Institute of Technology Patna Presentation for Major Project (8CE195) On CONSTRUCTION OF FLYOVER IN PATNA Presented by Narayan Gupta(1403037) Mahendra Kumar(1403089) Akhilesh Rajpoot (1403016)
  • 2. 2 Construction of flyover 1. Connecting Mithapur flyover to Bhikhari Thakur flyover via R-Block junction (166 crores) 2. Connecting Mithapur flyover to Chiraiyatand flyover via karbigahiya (121 crores) Client Bihar Rajya Pul Nirman Nigam Ltd. Patna Contractor Rachna Construction Co. Bharuch, Gujrat Project Detail
  • 4. 4 What is flyover? A bridge over another road Allowing traffic without interruption with its approaches on both side Super structure Substructure Foundation Girder Pier Cap Pier shaft Pile cap Pile
  • 5. 5 Execution of Project Sequence of construction 1. Surveying 2. Analysis and design of the structure 3. Piling and Pile cap Construction 4. Construction of Pier shaft and Pier cap 5. Construction of Pedestal and seismic stopper 6. Launching and gluing of segments 7. Construction of road over bridge
  • 6. 6 SURVEYING (TOPOGRAPHICAL SURVEY) Topography is used to locater and determine the position of any point in both the horizontal and vertical coordinates. various maps are studied and then detailed is done by Total station (TS) and layouts are given on AutoCAD. By using AutoCAD we can find the coordinates(north, east) and reduce level of any point. Coordinates of any point is marked with the help of Total station. Reduce level (RL) is marked by using Auto level. Circular mark on ground with nail to represent a particular coordinate and RL
  • 7. 7 Auto level to mark the RL Total Station to mark coordinate
  • 8. 8 Piling Type of pile - Bored Cast in-situ concrete piles Code of practice - (IS 2911-part 1-section 2:2010) 1- Point is located on ground to start the excavation. 2- Soil is excavated by auger at located point and liner(length 2-3m) is inserted. FOUNDATIONS: Foundations are the structures which are constructed below existing ground level. It sustains the loads coming from the sub structures and superstructures. Bridges had to carry a big load so PILE FOUNDATION are preferred Auger Liner
  • 9. 9 3- Flushing is done using bentonite slurry and bentonite is also used for the stabilization of bore hole and boring is done upto desired depth (30m-34m). Bentonite Tank for mixing of bentonite and waterHydrometer
  • 10. 10 4- boring is done by RIG machine(MAIT) and Bucket. Rig machine Bucket
  • 11. 11 5- formation of cage Dimension and Reinforcement Detail for pile Cage Cover block
  • 12. 12 6-Shifting of cage into borehole
  • 13. 13 7- Manner of concreting which shall be by use of tremie Tremie pipe(dia 200mm)- for flushing and concreting TM Concrete pouring from TM into tremie through hopper Insertion of tremie pipe
  • 14. 14 Pile cap 1-Excvation of Soil for pile cap
  • 15. 15 2- Chipping of extra unsound concrete of pile that is above cut off level And PCC is done at cut off level (thickness of PCC-100mm)
  • 16. 16 Hexagonal Pile cap Rectangular Pile cap Scaffolding for reinforcement work of pile cap
  • 17. 17 Reinforcement For Hexagonal Pile capReinforcement of Rectangular Pile Cap Reinforcement of Pile Cap (4 type)
  • 18. 18 Drawing and BBS of Pile Cap
  • 19. 19 Cleaning and lubrication of formwork Assembling of formwork With clear cover of 75mm
  • 20. 20 Location of pier shaft is marked using total station Vertical bar of pier shaft are placed in to marked location
  • 21. 21 Pouring of concrete and compaction of concrete using immersion vibrator Workability is checked by slump test before pouring and sample is collected for compressive strength
  • 22. 22 Shear key is made at construction joint Unloading of formwork Curing of pile cape
  • 23. 23 After 28 days of pile cap casting , the paint of epoxy coal tar Is applied to the surface of pile cap to make the surface impermeable Instead of using paint, grade of concrete is increased to M- 45
  • 24. 24 Pier Shaft Drawing and detailing of pier shaft BBS of pier shaft
  • 25. 25 Pier Shaft Assembly of reinforcement for first lift Cleaning and lubrication of formwork and it is applied
  • 26. 26 Pouring of concrete using pump and TM Workability is checked before pouring and cubes are casted for compressive strength Vertical pipe is used to prevent the segregation of concrete
  • 27. 27 Reinforcement is done for second lift Formwork is placed using hydra and pouring is done
  • 28. 28 Pier Shaft Curing of pier shaft is done using jute bag (sprinkle method)
  • 29. 29 Pier Cap and Portal beam of rotary is under construction….
  • 30. 30 Test 1- sample of concrete is collected at the time of pouring. workability is checked by slump test. for compressive strength of concrete, cube are casted and sent to lab for testing Slump cone
  • 31. 31 Pile load test Routine test As per 2911 (part 4):1985 It is carried out on a working pile with a view to check whether pile is capable of taking the working load assigned to it. The number of tests may generally be one-half percent of the total number of piles required. In this test compression load is applied to the pile top by means of a hydraulic jack against rolled steel joist and suitable load frame capable of providing reaction and the settlement is recorded by dial gauges. Dial gauge Hydraulic jack Kentledge Maximum allowable settlement is 12 mm
  • 32. 32 Pile Integrity test Non destructive pile integrity test (PIT) using low strain integrity test As per IS 14893:2001 This test is performed for confirming the integrity of pile upto full depth
  • 33. 33 Supervision -Helmet, jacket and shoes for all employs and worker -Barricading, Instruction board, light, reflector, safety cone, flag -safety belt is used if any worker is at height more than 2m from ground Safety
  • 34. 34 Supervision Quality control • Quality of Concrete--- workability and strength compaction of concrete using immersion vibrator (IS 3558:1983) curing • Steel --- reinforcement as per drawing and BBS, dia and length of bar, spacing of bar, lap length, binding of bar, development length, coupler, clear cover. • Other material --- lubricant, bentonite, coal tar epoxy, paint etc.
  • 35. 35 Concrete material Pile M 35 PCC M 15 Pile cape M 40 Pier shaft M 50 Clear cover to the reinforcement shall be a) Pile cape - 75mm b) Pile - 75mm c) Pier - 50/75mm Minimum lap length Pile = 54d Pile cape = 51d( for bottom and side face reinforcement) =78d (for top face reinforcement ) Pier = 44d d- Diameter of smaller bar being lapped Steel TMT bar (Fe 500D)
  • 36. 36 Cutting and bending of steel at yard Threading for rebar splicing mechanical coupler Reinforcement Yard
  • 37. 37 Batching plant for production of concrete Batching Plant
  • 39. 39 Fabrication of formwork and staging Fabrication unit
  • 40. 40 Machine and Tools Trailer concrete pump Backhoe loader Transit mixture Water tanker Crawler crane
  • 41. 41 Machine and Tools Rig machine Hydraulic crane Immersion needle vibrator Concrete breaker
  • 42. 42 Machine and Tools Tremie pipe Funnel Bucket Auger Liner
  • 43. 43 Conclusion Flyover makes transportation very easy. It becomes very difficult task when there is a project inside the city. R-block and Karbigahiya are the busiest route of Patna. In construction of flyover, construction of foundation requires large area that interrupt the already running traffic. Some point what we learned at site. • To analyze the drawing of project and to prepare the BBS from drawing. • Calculation of required concrete, steel and other material • Surveying for accuracy of position of different part • Various site test to ensure the quality of construction • Safety check for efficient work • Management of running traffic with the help of local police • Handling of existing structure like sewer, underground cables and statue. • Maintenance of data for completed structure
  • 44. 44 References 1. IS 456:2000 2. IS 2911 (Part 1/Sec 2):2010 3. IS 2911 (part 4):1985 4. IS 14893:2001 5. IS 3558:1983 Code of practice for plain and reinforced concrete Design and construction of pile foundations-code of practice (bored cast in- situ concrete piles) Codes of practice for design and construction of pile foundations – load test on piles Non-destructive integrity testing of piles (NDT)-guidelines Code of practice for use of immersion vibrators for consolidating concrete