SlideShare une entreprise Scribd logo
1  sur  78
REPAIR &
MAINTENANCE OF
STEEL BRIDGES
VINEET GUPTA
SPB-I
BRIDGE INSPECTION
 SYSTEMATIC OBSERVATION OF
CONDITION AND BEHAVIOUR OF
VARIOUS COMPONENETS/ PARTS
OF A BRIDGE IS CALLED BRIDGE
INSPECTION
AIMS OF BRIDGE
INSPECTION
 To assess structural soundness and
fitness for use
 To identify trouble at the earliest stage
 To keep a systematic record of
condition and behaviour (data bank)
 To plan repair and rehabilitation
strategy and programme
SCHEDULE OF INSPECTION
BRIDGE INSPECTOR
 Steel girders including bearings of girders >
12.2m – once in 5 years
 Welded girder – initial inspection after 1 year of
installation, than once in 3 years
 Composite girder – 1 year and subsequently 5
years
 Overstressed girders – at least once in a year
 Early steel girder – Floor System– once in a year
: rest-once in 5 years.
 Steel work, rivet testing, weld test etc.
Schedule Of Inspection
AEN/DEN (Bridge)
 Scrutinize – register sent by BRI
 Inspect Bridges referred to him
 Bridges call for inspection
 All overstressed bridges – camber loss
 10% test check of BRIs work
Dy. CE/Bridges
 Scrutinize bridge inspection register
 Inspect Bridges referred to him or call for
inspection
BEARINGS
ROLE OF BEARINGS
 Transmission of Forces from
superstructure to substructure
 Vertical
 Horizontal
 To permit movement
 Translation
 Rotation
SHIFTING OF ROLLER
BEARING
TRANSVINGERSE SHIFT
INSPECTION OF BEARINGS
 The longitudinal alignment - straight
and central to base plates.
 The girders - symmetrically placed
 No cavity/ gap between base plate and
bed block
 Bearings are free to move in the
designed manner
INSPECTION OF BEARINGS
contd.
 Check the condition of location strip and
guide strip or shearing of rivets
 The anchor bolts - in proper position
and intact. Look for any bend or
shearing of bolt
 Uniform seating of rollers & bearing
strip check with feeler gauge
INSPECTION OF BEARINGS
contd.
INSPECTION OF BEARINGS
contd.
INSPECTION OF BEARINGS
contd.
INSPECTION OF BEARINGS
contd.
 All fittings of rocker and roller- Sound
and proper
 Free movement of bearings and
condition of grease
 check both ends of girder are in same
level.
CAMBER
 Camber in steel truss girder is provided
upward amount being equal to
deflection of girder under design load
during fabrication and erection so that
girder under full load, truss shall be in
horizontal plane (nominal shape).
 Steel plate girders of span 12.2m,
18.3m & 24.4m span (either welded
construction or rivetted construction)
are not provided with camber
PRESTRESSING
 Prestressing of open web steel girder of
track bridge is predeforming of
members during fabrication and
erection of girder to ensure girder
under full design load shall be in
nominal shape to minimise
deformation stresses.
MEASURE CAMBER
 During technical inspection, camber is
checked at every panel point of bottom
chords of both truss with the help of dumpy
level or precision level, which will facilitate
the inspection officials to understand the
structural condition.
 As far as possible camber observations are
required to be taken at the ambient
temperature mentioned in the stress sheet.
 Graph in different colour.- Dead Load Camber
INSPECTION OF STEEL
SUPERSTRUCTURE
Check the Camber
 Loss of camber/Sagging due to
 Heavy overstressing
 Loss of cross section
 Increased load/fatigue
 Overstressing of joint
 Play between holes and rivets
LOSS OF CAMBER
 IF loss of Camber observed –
 Impose SR of 30 KMPH
 Investigate in detail-loose rivets,
corrosion, distortion
 Measure stress in critical members by
Faraday Palmer Stress Recorder or
Strain Gauges
 Check for frozen bearings
INSPECTION OF STEEL
SUPERSTRUCTURE contd.
DISTORTION
Plate girder
Top flange- comp member
Web plate near bearings-stress
concentration
Top lateral bracing – excessive
vibration
INSPECTION OF STEEL
SUPERSTRUCTURE contd.
DISTORTION
Open web girder
 Top chord – insufficient restraints
 Diagonal web member – made of flat in
mid span
 Bottom chord member – if not braced
properly
 Top lateral/ portal bracing - If not braced
properly
 Frozen bearings
DISTORTION -CHECK
 Distortion can be checked visually as
well as by a piano wire stretched
between panel points over the
members
 Sometimes web member i.e. diagonal,
vertical and end rakers in through
girder bridges are hit by moving loads
due to shifting of load in wagons,
particularly ODC. Hence, these
members should be checked at 1.2
meters above rail level for any damage.
RIVETS
 3 groups:
 stitch rivets are driven to form a member.
These rivets are driven in workshop and
mostly do not become loose in service life
of girder upto 80 to 100 years
 rivets at joints connecting members. These
rivets transfer the load from member to
joint. Tend to become loose after 40 to 50
years.
 rivets connecting top and bottom lateral
bracings including sway and portal
bracings tend to become loose on account
of vibrations.
TESTING FOR LOOSE
RIVETS
 Testing of rivets by rivet hammer chips
off the paint film, making rivet head
steel exposed to environment leading to
corrosion of rivet heads
 During technical inspection rivets should
be tested at the critical locations
 Inspect Rivets for loose rivets
 rivet testing once in 5 years
LOOSE RIVET–CRITICAL LOCATION
PLATE/COMPOSITE GIRDER
 Web plate to flange angle at end of
girders
 Bearing stiffener
 Splice rivets of flanges
 Bracing and cross frame connection
LOOSE RIVET –CRITICAL LOCATION
OPEN WEB GIRDERS
 Rail bearer – cross girder connections
 Cross girder – panel point gussets
 Panel point main gussets
 Top/bottom lateral bracings
CORROSION
Inspect for corrosion/loss of section
Critical locations
 Under wooden sleepers
 Formation of water pocket due to
construction
 Places where dust accumulate
 In vicinity of drainage system
 Area directly affected by diesel loco fumes
CORROSION- PAINTING
 The inspecting officials should clearly
indicate the following during inspection:
 i) Major portion of steel work require
only cover coat painting and at some
locations patch painting.
 ii) Steel girder requires complete
painting.
 iii) Only patch painting.
 iv) Paint in good condition, hence no
painting is required.
FATIGUE
 Fatigue Cracks
 Fatigue is the tendency of metal to fail
at lower stress level when subjected to
cyclic loading
 Fatigue is becoming important because
of growing volume of traffic at greater
speeds and higher axle loads.
LOCATION-FATIGUE CRACK
 Critical locations of cracking;
 i) Ends of diagonal members near middle of
the span due to reversal of stresses.
 ii) Sharp edges at cut notch in stringer
flanges at connections with cross girders.
 iii) Top flange plates or flange angles of plate
girders or rail bearers especially below the
sleepers.
LOCATION-FATIGUE CRACK
 iv) Roots of channel and angles on
account of rolling defects.
 v) Corrosion pits at any location in
tension member. Joints where heavy
shear is transmitted.
 To arrest the crack propagation, a hole
should be drilled at the end of the crack
in plate and cover material is provided
with rivets.
CANTI LEVER BRACKET CORROSION LOSS
TILTED ROCKER BEARING
TILTED MULTIPLE ROCKER BEARING
GIRDER BOTTOM FLANGE CORROSION LOSS
TOP CHORD CORROSION AT JOINT
BRACING MEMBER CORROSION LOSS
BOTTOM TRUSS CHORD CORROSION
BOTTOM CHORD CORROSION AT JOINT
CORROSION OF PIN & CRACKING OF HANGER
PLATE
GIRDER BOTTOM FLANGE VEHICLE IMPACT
DAMAGE
Maintenance of Steel superstructures
 Inspection and recording
 Cleaning and greasing of bearings
 Protective painting system for steel
structures
 Replacement of loose rivets or repair to
weld joint
 Strengthening of steel superstructure
 Replacement of corroded rivets
Painting
 Steel girders are prone for corrosion
 Where humidity > 60%
 In coastal areas
 Bridge across creek
 Bridge surrounded by chemical industry.
 Type of traffic
 Public nuisance
Painting
Surface preperation
 Use emery paper , wire brush, scrappers
 With power tools
 Blast cleaning – sand or grit
 Flame cleaning – oxy-acetylene flame
(not to be done on plates with
thickness<10mm)
 Luke warm water – 2% detergent
Painting
No severe corrosion
 Priming coat
 Heavy coat of ready mixed paint red lead
priming to IS 102 or
 One coat of Zink cromate priming to IS 104
followed by red oxide zink crome priming to IS
2074 or
 Two coat of Zink cromate red oxide primer to
IRS P31
 Finishing coat
 Two cover coats of red oxide paint to IS 123
Painting
Severe corrosion
 Priming coat
 Two coats of red lead priming to IS 102
 Finishing
 Two coats of aluminium paint to IS 2339
 Above also recommended for open web girders in
all cases due to better and longer life.
 All floor and top bracing system in electrified
areas with epoxy painting
Paint life
 Paint red lead - 4 months
 Paint red oxide – 1 year
 Aluminium
 When paste & oil not mixed – 1 year
 When mixed – 4 months
 Red lead dry paint – No time limit
Time lag between paints
 Surface prep and Primer – 24 hours
 Primer coat and first finishing coat – 7
days
 First fininshing coat and 2nd fininshing
coat –7 days
Epoxy painting
Should be done for
 Flooring system ( cross girder and rail bearer) in
open web girders
 Top flange plate of plate girder and underslung
girder
 Top bracing system in open web girders in
electrified areas
 Steel girders subjected to salt spray
Epoxy painting
 Remove oil/grease using petrolium hydrocarbon
solvent ( IS 1745)
 Prepare the surface by sand blasting
 Primer coat – Epoxy zinc phosphate primer
to 60 micron min. ( RDSO M&C/PCN-102/ 86)
 Intermediate coat – One coat of micaceous iron
oxide to 100 micron . ( RDSO M&C/PCN-103/ 86)
 Finishing coat - two coats of polyurethane
aluminium to 40 micron. ( RDSO M&C/PCN-110/
88)
Metallising
Should be done for
 Flooring system ( cross girder and rail bearer) in
open web girders
 Top flange plate of plate girder and underslung
girder
 Top bracing system in open web girders in
electrified areas
 Steel girders subjected to salt spray
Metallising
 Zinc chrome primer to IS 104
 Two coat of aluminium paint to IS2339
 Min thickness of metal coating 115 micron
 Surface preparation crucial
 Final cleaning by chilled iron grit G24.
 Final surface roughness as per IS 5909.
 Aluminium to be sprayed as per BS1475
Renewal of loose rivets
 Slight slackness does not cause loss of
strength
 Renewal should be done only when in groups
 All hand loose rivets which have lost 50% of
head
 All hammer loose rivets where corrosion has
set in bet head and plate
 In end stiffeners where hammer loose rivets
> 30%
Renewal of loose rivets
 Use only pneumatic rivetting
 Not > 10% rivets should be cut at a joint at a
time
 Preferably drill a rivet out than use a rivet
buster
 Rivet to be heated to white hot
 Rivet to be driven and snap removed within
20 sec. After leaving fire
 Length
 Snap head – L= G +1.5 D +1 mm for every 4mm of grip
 Counter sunk – L= G + 0.5 D +1 mm for every 4mm of grip
Strengthening
CRACKED GIRDER REPAIR
Vertical
Member
Diagonal
Member
Flooring
Detail at 'A'
Member broken at node No.1
due to excess corrosion
NEW
GUSSET
PLATE
2 3 4 5 6 7 8
HORIZONTAL LEG OF ANGLE MISSING
DUE TO ACUTE CORROSSION
3' 4' 5' 6' 7'
OHE OHE
VIEW A-A
ADDITIONAL
COVER PLATE
CORRODED BOTTOM
FLANGE ANGLE WITH
MISSING LEG BOTTOM SPLICE PLATE
INTACT BOTTOM FLANGE
ANGLE
NEW ANGLES WELDED
TO PROVIDE BOTTOM
FLANGE AREA
CORRODED BOTTOM
FLANGE ANGLE WITH
MISSING LEG BOTTOM SPLICE PLATE
INTACT BOTTOM FLANGE
ANGLE
NEW ANGLES WELDED
TO PROVIDE BOTTOM
FLANGE AREA
CORRODED BOTTOM
FLANGE ANGLE WITH
MISSING LEG BOTTOM SPLICE PLATE
INTACT BOTTOM FLANGE
ANGLE
NEW ANGLES WELDED
TO PROVIDE BOTTOM
FLANGE AREA
BOTTOM SPLICE PLATE
INTACT BOTTOM FLANGE
ANGLE
NEW ANGLES WELDED
TO PROVIDE BOTTOM
FLANGE AREA
INTACT BOTTOM FLANGE
ANGLE
NEW ANGLES WELDED
TO PROVIDE BOTTOM
FLANGE AREA
NEW ANGLES WELDED
TO PROVIDE BOTTOM
FLANGE AREA
Maintenance &amp; repair of steel bridges
Maintenance &amp; repair of steel bridges
Maintenance &amp; repair of steel bridges
Maintenance &amp; repair of steel bridges
Maintenance &amp; repair of steel bridges
Maintenance &amp; repair of steel bridges
Maintenance &amp; repair of steel bridges
Maintenance &amp; repair of steel bridges
Maintenance &amp; repair of steel bridges
Maintenance &amp; repair of steel bridges
Maintenance &amp; repair of steel bridges
Maintenance &amp; repair of steel bridges
Maintenance &amp; repair of steel bridges
Maintenance &amp; repair of steel bridges
Maintenance &amp; repair of steel bridges
Maintenance &amp; repair of steel bridges
Maintenance &amp; repair of steel bridges
Maintenance &amp; repair of steel bridges

Contenu connexe

Tendances

15.2.2 bored pile wall - method statement
15.2.2   bored pile wall - method statement15.2.2   bored pile wall - method statement
15.2.2 bored pile wall - method statement
NECB
 
Connections in steel structures
Connections in steel structuresConnections in steel structures
Connections in steel structures
Rizwan Khurram
 

Tendances (20)

Bolted connections
Bolted connectionsBolted connections
Bolted connections
 
Railway Planning - Unit 1
Railway Planning - Unit 1Railway Planning - Unit 1
Railway Planning - Unit 1
 
Composite materials for bridge construction
Composite materials for bridge constructionComposite materials for bridge construction
Composite materials for bridge construction
 
design philosophy in structure design in civil engineering
design philosophy in structure design in civil engineeringdesign philosophy in structure design in civil engineering
design philosophy in structure design in civil engineering
 
Railway track:An Introduction
Railway track:An IntroductionRailway track:An Introduction
Railway track:An Introduction
 
Post tensioning
Post tensioningPost tensioning
Post tensioning
 
Bridge foundation
Bridge foundationBridge foundation
Bridge foundation
 
Bridge introduction
Bridge introductionBridge introduction
Bridge introduction
 
Bridge loading and bridge design fundamentals
Bridge loading and bridge design fundamentalsBridge loading and bridge design fundamentals
Bridge loading and bridge design fundamentals
 
Bridges in Hilly areas seminar
Bridges in Hilly areas seminarBridges in Hilly areas seminar
Bridges in Hilly areas seminar
 
Training report ON BRIDGE
Training report ON BRIDGETraining report ON BRIDGE
Training report ON BRIDGE
 
15.2.2 bored pile wall - method statement
15.2.2   bored pile wall - method statement15.2.2   bored pile wall - method statement
15.2.2 bored pile wall - method statement
 
Bridge
BridgeBridge
Bridge
 
Composite deck bridge systems
Composite deck bridge systemsComposite deck bridge systems
Composite deck bridge systems
 
Construction methods of Bridges and its types
Construction methods of Bridges and its typesConstruction methods of Bridges and its types
Construction methods of Bridges and its types
 
Structural Design of Bridges
Structural Design of BridgesStructural Design of Bridges
Structural Design of Bridges
 
Inspection,Repair and Strengthening of PSC Bridge.
Inspection,Repair and Strengthening of PSC  Bridge.Inspection,Repair and Strengthening of PSC  Bridge.
Inspection,Repair and Strengthening of PSC Bridge.
 
Bridge Rule
Bridge RuleBridge Rule
Bridge Rule
 
Bridge engineering
Bridge engineeringBridge engineering
Bridge engineering
 
Connections in steel structures
Connections in steel structuresConnections in steel structures
Connections in steel structures
 

Similaire à Maintenance &amp; repair of steel bridges

Presentation on Expansion Joint
Presentation on Expansion JointPresentation on Expansion Joint
Presentation on Expansion Joint
Rais Uddin
 
Final Presentation
Final PresentationFinal Presentation
Final Presentation
Monique F M
 
PDL’s Construction Development (Technical) Training Session-I_Structural.pptx
PDL’s Construction Development (Technical) Training Session-I_Structural.pptxPDL’s Construction Development (Technical) Training Session-I_Structural.pptx
PDL’s Construction Development (Technical) Training Session-I_Structural.pptx
ChristopherThomas578171
 

Similaire à Maintenance &amp; repair of steel bridges (20)

Presentation on steel, fabrication & erection Munger Ganga Bridge
Presentation on steel, fabrication & erection  Munger Ganga BridgePresentation on steel, fabrication & erection  Munger Ganga Bridge
Presentation on steel, fabrication & erection Munger Ganga Bridge
 
Presentation on Expansion Joint
Presentation on Expansion JointPresentation on Expansion Joint
Presentation on Expansion Joint
 
Expansion joints in bridge
Expansion joints in bridgeExpansion joints in bridge
Expansion joints in bridge
 
TANK 13042023.pptx
TANK 13042023.pptxTANK 13042023.pptx
TANK 13042023.pptx
 
RCC-.pdf
RCC-.pdfRCC-.pdf
RCC-.pdf
 
Formwork
FormworkFormwork
Formwork
 
Final Presentation
Final PresentationFinal Presentation
Final Presentation
 
Composite construction by Er. SURESH RAO
Composite construction by Er. SURESH RAOComposite construction by Er. SURESH RAO
Composite construction by Er. SURESH RAO
 
PDL’s Construction Development (Technical) Training Session-I_Structural.pptx
PDL’s Construction Development (Technical) Training Session-I_Structural.pptxPDL’s Construction Development (Technical) Training Session-I_Structural.pptx
PDL’s Construction Development (Technical) Training Session-I_Structural.pptx
 
Farmwork shuttering
Farmwork shutteringFarmwork shuttering
Farmwork shuttering
 
Speedy construction
Speedy constructionSpeedy construction
Speedy construction
 
Pole type structures
Pole type structuresPole type structures
Pole type structures
 
Presentation on Piping Familiarization.ppt
Presentation on Piping Familiarization.pptPresentation on Piping Familiarization.ppt
Presentation on Piping Familiarization.ppt
 
report of open web girder (railway)
report of open web girder (railway)report of open web girder (railway)
report of open web girder (railway)
 
Types of pavement construction procedure
Types of pavement construction procedureTypes of pavement construction procedure
Types of pavement construction procedure
 
Experimental Investigation on Steel Concrete Composite Floor Slab
Experimental Investigation on Steel Concrete Composite Floor SlabExperimental Investigation on Steel Concrete Composite Floor Slab
Experimental Investigation on Steel Concrete Composite Floor Slab
 
Piping ppt1
Piping ppt1Piping ppt1
Piping ppt1
 
walkson-presentation-r1.pdf
walkson-presentation-r1.pdfwalkson-presentation-r1.pdf
walkson-presentation-r1.pdf
 
3rd unit
3rd unit3rd unit
3rd unit
 
8.ppt
8.ppt8.ppt
8.ppt
 

Dernier

DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakes
MayuraD1
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
ssuser89054b
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdf
Kamal Acharya
 
Verification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptxVerification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptx
chumtiyababu
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
AldoGarca30
 

Dernier (20)

DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakes
 
kiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal loadkiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal load
 
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equation
 
PE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiesPE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and properties
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna Municipality
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptx
 
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxA CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdf
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdf
 
Verification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptxVerification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptx
 
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
 
Moment Distribution Method For Btech Civil
Moment Distribution Method For Btech CivilMoment Distribution Method For Btech Civil
Moment Distribution Method For Btech Civil
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdf
 

Maintenance &amp; repair of steel bridges

  • 1. REPAIR & MAINTENANCE OF STEEL BRIDGES VINEET GUPTA SPB-I
  • 2. BRIDGE INSPECTION  SYSTEMATIC OBSERVATION OF CONDITION AND BEHAVIOUR OF VARIOUS COMPONENETS/ PARTS OF A BRIDGE IS CALLED BRIDGE INSPECTION
  • 3. AIMS OF BRIDGE INSPECTION  To assess structural soundness and fitness for use  To identify trouble at the earliest stage  To keep a systematic record of condition and behaviour (data bank)  To plan repair and rehabilitation strategy and programme
  • 4. SCHEDULE OF INSPECTION BRIDGE INSPECTOR  Steel girders including bearings of girders > 12.2m – once in 5 years  Welded girder – initial inspection after 1 year of installation, than once in 3 years  Composite girder – 1 year and subsequently 5 years  Overstressed girders – at least once in a year  Early steel girder – Floor System– once in a year : rest-once in 5 years.  Steel work, rivet testing, weld test etc.
  • 5. Schedule Of Inspection AEN/DEN (Bridge)  Scrutinize – register sent by BRI  Inspect Bridges referred to him  Bridges call for inspection  All overstressed bridges – camber loss  10% test check of BRIs work Dy. CE/Bridges  Scrutinize bridge inspection register  Inspect Bridges referred to him or call for inspection
  • 6. BEARINGS ROLE OF BEARINGS  Transmission of Forces from superstructure to substructure  Vertical  Horizontal  To permit movement  Translation  Rotation
  • 9. INSPECTION OF BEARINGS  The longitudinal alignment - straight and central to base plates.  The girders - symmetrically placed  No cavity/ gap between base plate and bed block  Bearings are free to move in the designed manner
  • 10. INSPECTION OF BEARINGS contd.  Check the condition of location strip and guide strip or shearing of rivets  The anchor bolts - in proper position and intact. Look for any bend or shearing of bolt  Uniform seating of rollers & bearing strip check with feeler gauge
  • 14. INSPECTION OF BEARINGS contd.  All fittings of rocker and roller- Sound and proper  Free movement of bearings and condition of grease  check both ends of girder are in same level.
  • 15. CAMBER  Camber in steel truss girder is provided upward amount being equal to deflection of girder under design load during fabrication and erection so that girder under full load, truss shall be in horizontal plane (nominal shape).  Steel plate girders of span 12.2m, 18.3m & 24.4m span (either welded construction or rivetted construction) are not provided with camber
  • 16. PRESTRESSING  Prestressing of open web steel girder of track bridge is predeforming of members during fabrication and erection of girder to ensure girder under full design load shall be in nominal shape to minimise deformation stresses.
  • 17. MEASURE CAMBER  During technical inspection, camber is checked at every panel point of bottom chords of both truss with the help of dumpy level or precision level, which will facilitate the inspection officials to understand the structural condition.  As far as possible camber observations are required to be taken at the ambient temperature mentioned in the stress sheet.  Graph in different colour.- Dead Load Camber
  • 18. INSPECTION OF STEEL SUPERSTRUCTURE Check the Camber  Loss of camber/Sagging due to  Heavy overstressing  Loss of cross section  Increased load/fatigue  Overstressing of joint  Play between holes and rivets
  • 19. LOSS OF CAMBER  IF loss of Camber observed –  Impose SR of 30 KMPH  Investigate in detail-loose rivets, corrosion, distortion  Measure stress in critical members by Faraday Palmer Stress Recorder or Strain Gauges  Check for frozen bearings
  • 20. INSPECTION OF STEEL SUPERSTRUCTURE contd. DISTORTION Plate girder Top flange- comp member Web plate near bearings-stress concentration Top lateral bracing – excessive vibration
  • 21. INSPECTION OF STEEL SUPERSTRUCTURE contd. DISTORTION Open web girder  Top chord – insufficient restraints  Diagonal web member – made of flat in mid span  Bottom chord member – if not braced properly  Top lateral/ portal bracing - If not braced properly  Frozen bearings
  • 22. DISTORTION -CHECK  Distortion can be checked visually as well as by a piano wire stretched between panel points over the members  Sometimes web member i.e. diagonal, vertical and end rakers in through girder bridges are hit by moving loads due to shifting of load in wagons, particularly ODC. Hence, these members should be checked at 1.2 meters above rail level for any damage.
  • 23. RIVETS  3 groups:  stitch rivets are driven to form a member. These rivets are driven in workshop and mostly do not become loose in service life of girder upto 80 to 100 years  rivets at joints connecting members. These rivets transfer the load from member to joint. Tend to become loose after 40 to 50 years.  rivets connecting top and bottom lateral bracings including sway and portal bracings tend to become loose on account of vibrations.
  • 24. TESTING FOR LOOSE RIVETS  Testing of rivets by rivet hammer chips off the paint film, making rivet head steel exposed to environment leading to corrosion of rivet heads  During technical inspection rivets should be tested at the critical locations  Inspect Rivets for loose rivets  rivet testing once in 5 years
  • 25. LOOSE RIVET–CRITICAL LOCATION PLATE/COMPOSITE GIRDER  Web plate to flange angle at end of girders  Bearing stiffener  Splice rivets of flanges  Bracing and cross frame connection
  • 26. LOOSE RIVET –CRITICAL LOCATION OPEN WEB GIRDERS  Rail bearer – cross girder connections  Cross girder – panel point gussets  Panel point main gussets  Top/bottom lateral bracings
  • 27. CORROSION Inspect for corrosion/loss of section Critical locations  Under wooden sleepers  Formation of water pocket due to construction  Places where dust accumulate  In vicinity of drainage system  Area directly affected by diesel loco fumes
  • 28. CORROSION- PAINTING  The inspecting officials should clearly indicate the following during inspection:  i) Major portion of steel work require only cover coat painting and at some locations patch painting.  ii) Steel girder requires complete painting.  iii) Only patch painting.  iv) Paint in good condition, hence no painting is required.
  • 29. FATIGUE  Fatigue Cracks  Fatigue is the tendency of metal to fail at lower stress level when subjected to cyclic loading  Fatigue is becoming important because of growing volume of traffic at greater speeds and higher axle loads.
  • 30. LOCATION-FATIGUE CRACK  Critical locations of cracking;  i) Ends of diagonal members near middle of the span due to reversal of stresses.  ii) Sharp edges at cut notch in stringer flanges at connections with cross girders.  iii) Top flange plates or flange angles of plate girders or rail bearers especially below the sleepers.
  • 31. LOCATION-FATIGUE CRACK  iv) Roots of channel and angles on account of rolling defects.  v) Corrosion pits at any location in tension member. Joints where heavy shear is transmitted.  To arrest the crack propagation, a hole should be drilled at the end of the crack in plate and cover material is provided with rivets.
  • 32. CANTI LEVER BRACKET CORROSION LOSS
  • 35. GIRDER BOTTOM FLANGE CORROSION LOSS
  • 38. BOTTOM TRUSS CHORD CORROSION
  • 40. CORROSION OF PIN & CRACKING OF HANGER PLATE
  • 41. GIRDER BOTTOM FLANGE VEHICLE IMPACT DAMAGE
  • 42. Maintenance of Steel superstructures  Inspection and recording  Cleaning and greasing of bearings  Protective painting system for steel structures  Replacement of loose rivets or repair to weld joint  Strengthening of steel superstructure  Replacement of corroded rivets
  • 43. Painting  Steel girders are prone for corrosion  Where humidity > 60%  In coastal areas  Bridge across creek  Bridge surrounded by chemical industry.  Type of traffic  Public nuisance
  • 44. Painting Surface preperation  Use emery paper , wire brush, scrappers  With power tools  Blast cleaning – sand or grit  Flame cleaning – oxy-acetylene flame (not to be done on plates with thickness<10mm)  Luke warm water – 2% detergent
  • 45. Painting No severe corrosion  Priming coat  Heavy coat of ready mixed paint red lead priming to IS 102 or  One coat of Zink cromate priming to IS 104 followed by red oxide zink crome priming to IS 2074 or  Two coat of Zink cromate red oxide primer to IRS P31  Finishing coat  Two cover coats of red oxide paint to IS 123
  • 46. Painting Severe corrosion  Priming coat  Two coats of red lead priming to IS 102  Finishing  Two coats of aluminium paint to IS 2339  Above also recommended for open web girders in all cases due to better and longer life.  All floor and top bracing system in electrified areas with epoxy painting
  • 47. Paint life  Paint red lead - 4 months  Paint red oxide – 1 year  Aluminium  When paste & oil not mixed – 1 year  When mixed – 4 months  Red lead dry paint – No time limit
  • 48. Time lag between paints  Surface prep and Primer – 24 hours  Primer coat and first finishing coat – 7 days  First fininshing coat and 2nd fininshing coat –7 days
  • 49. Epoxy painting Should be done for  Flooring system ( cross girder and rail bearer) in open web girders  Top flange plate of plate girder and underslung girder  Top bracing system in open web girders in electrified areas  Steel girders subjected to salt spray
  • 50. Epoxy painting  Remove oil/grease using petrolium hydrocarbon solvent ( IS 1745)  Prepare the surface by sand blasting  Primer coat – Epoxy zinc phosphate primer to 60 micron min. ( RDSO M&C/PCN-102/ 86)  Intermediate coat – One coat of micaceous iron oxide to 100 micron . ( RDSO M&C/PCN-103/ 86)  Finishing coat - two coats of polyurethane aluminium to 40 micron. ( RDSO M&C/PCN-110/ 88)
  • 51. Metallising Should be done for  Flooring system ( cross girder and rail bearer) in open web girders  Top flange plate of plate girder and underslung girder  Top bracing system in open web girders in electrified areas  Steel girders subjected to salt spray
  • 52. Metallising  Zinc chrome primer to IS 104  Two coat of aluminium paint to IS2339  Min thickness of metal coating 115 micron  Surface preparation crucial  Final cleaning by chilled iron grit G24.  Final surface roughness as per IS 5909.  Aluminium to be sprayed as per BS1475
  • 53. Renewal of loose rivets  Slight slackness does not cause loss of strength  Renewal should be done only when in groups  All hand loose rivets which have lost 50% of head  All hammer loose rivets where corrosion has set in bet head and plate  In end stiffeners where hammer loose rivets > 30%
  • 54. Renewal of loose rivets  Use only pneumatic rivetting  Not > 10% rivets should be cut at a joint at a time  Preferably drill a rivet out than use a rivet buster  Rivet to be heated to white hot  Rivet to be driven and snap removed within 20 sec. After leaving fire  Length  Snap head – L= G +1.5 D +1 mm for every 4mm of grip  Counter sunk – L= G + 0.5 D +1 mm for every 4mm of grip
  • 57.
  • 58. Vertical Member Diagonal Member Flooring Detail at 'A' Member broken at node No.1 due to excess corrosion NEW GUSSET PLATE
  • 59. 2 3 4 5 6 7 8 HORIZONTAL LEG OF ANGLE MISSING DUE TO ACUTE CORROSSION 3' 4' 5' 6' 7' OHE OHE VIEW A-A ADDITIONAL COVER PLATE
  • 60. CORRODED BOTTOM FLANGE ANGLE WITH MISSING LEG BOTTOM SPLICE PLATE INTACT BOTTOM FLANGE ANGLE NEW ANGLES WELDED TO PROVIDE BOTTOM FLANGE AREA CORRODED BOTTOM FLANGE ANGLE WITH MISSING LEG BOTTOM SPLICE PLATE INTACT BOTTOM FLANGE ANGLE NEW ANGLES WELDED TO PROVIDE BOTTOM FLANGE AREA CORRODED BOTTOM FLANGE ANGLE WITH MISSING LEG BOTTOM SPLICE PLATE INTACT BOTTOM FLANGE ANGLE NEW ANGLES WELDED TO PROVIDE BOTTOM FLANGE AREA BOTTOM SPLICE PLATE INTACT BOTTOM FLANGE ANGLE NEW ANGLES WELDED TO PROVIDE BOTTOM FLANGE AREA INTACT BOTTOM FLANGE ANGLE NEW ANGLES WELDED TO PROVIDE BOTTOM FLANGE AREA NEW ANGLES WELDED TO PROVIDE BOTTOM FLANGE AREA