1. 21 OCTOBER 2015
This project has received funding from the European Union’s Seventh Framework Programme for
research, technological development and demonstration under grant agreement No 643330
Time and Project Management
Lowry McComb
2. ∂
Do we have a shortage of time?
“No we don’t. Time is the
medium in which we
exist. To complain about
a shortage of time is like
a fish in the sea
complaining about a
shortage of water.”
Forster 2006, 2
7. ∂
Work Priorities
Do you:
• manage multiple projects or tasks
• say ‘yes’ when you should be saying ‘no’
• find research/work taking over the rest of your
life
• miss out on opportunities
Developed by Tim Franklin, Strategic Systems Programme
Manager, University of York
8. ∂
Activity / days per month Aug Sep Oct Nov Dec Jan Feb
Working Days in month 21.0 21.0 23.0 21.0 17.0 22.0 20.0
Planned holidays 0.0 10.0 0.0
Conference / Training days 0.0 2.0 0.0
Work days balance = Total in month -
holidays and other 21.0 9.0 23.0 21.0 17.0 22.0 20.0
Business as Usual
Line Management meetings 1.0 1.0 1.0
Departmental Administration 3.0 2.0 4.0
Total for business as usual 4.0 3.0 5.0 0.0 0.0 0.0 0.0
Project days balance = Work days
balance - BAU 17.0 6.0 18.0 21.0 17.0 22.0 20.0
Project Work
Project A 2.0 3.0 5.0
Project B 5.0 1.0 1.0
Project C 5.0 2.0 2.0
Project D 0.0 0.0 2.0
Project E 0.0 0.0 0.0
Total for Project Work 12.0 6.0 10.0 0.0 0.0 0.0 0.0
Capacity / ( Overload ) 5.0 0.0 8.0 21.0 17.0 22.0 20.0
9. ∂
Activity / days per month Aug Sep Oct
Working Days in month 21.0 21.0 23.0
Planned holidays 0.0 10.0 0.0
Conference / Training days 0.0 2.0 0.0
Work days balance = Total in month -
holidays and other 21.0 9.0 23.0
Business as Usual
Line Management meetings 1.0 1.0 1.0
Departmental Administration 3.0 2.0 4.0
Total for business as usual 4.0 3.0 5.0
Project days balance = Work days
balance - BAU 17.0 6.0 18.0
Project Work
Project A 2.0 3.0 5.0
Project B 5.0 1.0 1.0
Project C 5.0 2.0 2.0
Project D 0.0 0.0 2.0
Project E 0.0 0.0 0.0
Total for Project Work 12.0 6.0 10.0
Capacity / ( Overload ) 5.0 0.0 8.0
REVIEW
10. ∂
Daily Planning
What tools and techniques do
you use for daily time
management?
How useful are they?
What are their limitations?
11. ∂
Planning Grid
1 Urgent and Important 2 Important but not Urgent
3 Urgent but not Important 4 Neither Urgent nor Important
do these first plan these carefully
and do next
try to delegate, then
turn full attention
to 2
13. ∂
How you do it
Not To-Do Lists
I am not going to:
• answer the phone before …
• work through lunch
• work later than …..
• leave my email switched on
14. ∂
‘I start out
with the
right
intentions, I
write a ‘to
do’ list but
by the end
of the day
I’ve only
crossed off
a few
things.’
What you do
15. ∂
Reactive Tasks Proactive Tasks
Those that happen
immediately
and can’t be anticipated.
e.g. responding to a
telephone call or a personal
enquiry.
Those you can plan for in
advance.
e.g. a meeting with your
supervisor or a timetabled
class.
Avoid letting non-urgent reactive
tasks take priority over the work
you have timetabled
20. ∂
Time Management - Making a Start
One thing you will stop doing
One thing you will start doing
21. ∂
Summary
• Set aside 10 minutes every morning to look at and modify your
plans
• Break overwhelming tasks down into manageable chunks
• Avoid making multiple trips to the same place every day
• Learn to say ‘no’ – your time is a precious commodity
• Face-to-face meetings take up a lot of time – can a telephone
call or e-mail suffice?
• Each day schedule particular times to check your e-mail and
make phone calls
• Reward yourself
22. 21 OCTOBER 2015
This project has received funding from the European Union’s Seventh Framework Programme for
research, technological development and demonstration under grant agreement No 643330
Project Management
29. ∂
Issues to Consider
• Who are your stakeholders and how do
you manage their expectations?
• What are your objectives?
• How will you plan and manage the
process?
• How will you deal with risks?
30. ∂
Who are Your Stakeholders?
• Any individual or organisation who has an
interest in the performance or outcome of the
project
• Stakeholders usually provide resources –
they can contribute to both the success and
failure of the project
31. ∂
Stakeholder Analysis
• Identify your stakeholders
• What resources do they bring to the
project?
• What are their levels of power, influence
and interest?
i.e. how much influence do they have over
the process and the outcome?
35. ∂
Stakeholder Analysis…what next?
Tick the stakeholder analysis box and continue on a
pre-determined route
Work with stakeholders:
• What motivates them?
• What do they really want and need from the project?
• How/when will you communicate with stakeholders?
• How will you ensure they stay on side or do not
cause problems?
36. ∂
“If you do not
know where you
are going, every
road will get you
nowhere.”
Henry Kissinger
37. ∂
Aims and Objectives
Aims: What you want to achieve by the
end of a project
Objectives: the things you will do to
achieve your aims
38. ∂
Why set objectives?...
Turn dreams into targets and
deadlines
Clarify and break down what has to
be done
Make progress
Be able to assess progress
Complete
Motivation
40. ∂
Specific
Specific means that the objective is
concrete, detailed, focused and
well defined. Specific means that
it’s results and action-orientated.
http://www.thepracticeofleadership.net/2006/03/11/setting-smart-
objectives/
42. ∂
Agreed
Identify and work with stakeholders
• Disregard stakeholders
• Allow stakeholders to set your
objectives
• Negotiate and agree
43. ∂
Realistic
Objectives that are achievable, may not be realistic…..
however, realistic does not mean easy. Realistic
means that you have the resources to get it done.
http://www.thepracticeofleadership.net/2006/03/11/setting-smart-
objectives/
Realistic Challenging
45. ∂
Objective Setting
• Set positive outcomes
• Set multiple-level objectives
–in six months, in one month, in one
week
• Are they SMART?
• Review and assess progress
46. ∂
Taking Stock
Where am I now?
What have I achieved?
Tangible (Database
created / Training done)
Intangible (Interpersonal
Advancement / Feelings)
47. ∂
What do I want to have
achieved between today
and deadline?
Taking Stock
Tangible (Studies done /
papers written)
Intangible (Personal
Development / Contacts)
Your
Goals
48. ∂
W o r k B r e a k d o w n S t r u c t u r e o f T y p ic a l P r o je c t
W o r k P a c k a g e
T a s k T a s k
A c t iv it y A c t iv it y A c t iv it y
T a s k
W o r k P a c k a g e W o r k P a c k a g e
P r o je c t
NB The activities
should be small
enough chunks that
you can easily assess
your progress
49. ∂
Work Breakdown
Structure
Activity
Write conference paper
Read 3 articles
Using verbs
Product Breakdown
Structure
Product
Conference paper
Articles read
Using nouns
Focusing on the products rather than process
can increase the likelihood of completion.
50. ∂
E x a m p le o f W o r k B r e a k d o w n S t r u c t u r e o f a T y p ic a l ( ? ) P h D R e s e a r c h P r o je c t
L it . R e v ie w
O b t a in A p p e r a t u s
R e a d D e s ig n P ilo t
R e v ie w
D e s ig n E x p e r im e n t s P la n S t a t s
C o n t r o l O b s e r v e R e c o r d
R e v ie w
C a r r y o u t e x p e r im e n t s
E x p e r im e n t s A n a ly s is W r it in g
O b t a in A p p r o v a l
C o n s u lt / A p p ly fo r a p p r o v a l o r fu n d in g
P la n
E x p e r im e n t a l C h a p t e r
( P r o b a b ly 4 o r 5 o f t h e s e )
D is c u s s io n a n d C o n c lu s io n s
T h e s is
PhD Work Breakdown Structure
52. ∂
E x a m p le o f W o r k B r e a k d o w n S t r u c t u r e o f a T y p ic a l ( ? ) P h D R e s e a r c h P r o je c t
L it . R e v ie w
O b t a in A p p e r a t u s
R e a d D e s ig n P ilo t
R e v ie w
D e s ig n E x p e r im e n t s P la n S t a t s
C o n t r o l O b s e r v e R e c o r d
R e v ie w
C a r r y o u t e x p e r im e n t s
E x p e r im e n t s A n a ly s is W r it in g
O b t a in A p p r o v a l
C o n s u lt / A p p ly fo r a p p r o v a l o r fu n d in g
P la n
E x p e r im e n t a l C h a p t e r
( P r o b a b ly 4 o r 5 o f t h e s e )
D is c u s s io n a n d C o n c lu s io n s
T h e s is
What’s
missing?
PhD Work Breakdown Structure
53. ∂
Gantt Charts
•A simple graphical presentation of tasks and
times
•A bar chart with start and finish dates on a
timeline
•Easy to produce
•Easy to explain
54. ∂
Initial Literature Trawl
Design Questionnaire
Review Questionnaire
Start
Distribute
Data Inputting
Final Analyses
Hand In Date
Write Up
Basic Gantt Chart
TIME
ACTIVITY
56. ∂
Initial Literature Trawl
Design Questionnaire
Review Questionnaire
Start
Distribute
Data Inputting
Final Analyses
Hand In Date
Write Up
Basic Gantt Chart
TIME
ACTIVITY
62. ∂
Prioritise the Risks
Probability – how likely is it to happen?
Impact – how serious is it?
1 2 3
2 4 62 4 6
3 6 9
Probability
Impact
Risk (Probability x Impact)
1- 2 : Low
3 - 4 : Medium
6 - 8 : High
9 : Extreme
63. ∂
Estimating times
The most common cause of error in project
management is incorrect estimations of the length of
time the individual elements will take.
How long will each activity or task take?
• Take an educated guess – this will improve with time.
• Seek advice from others with more experience.
• Allow for contingencies by adding slack.
• Consider the risks and their probabilities
64. ∂
Estimating times
Estimating the Times of Individual Components of a
Project
TE = Estimated Time
TO = Optimistic Time
TP = Pessimistic Time
TM = Most likely time
TE = TO + 4 (TM) + TP
6
65. ∂
“Almost by definition, a student who does not complete
within the three years (or part-time equivalent) or takes
longer or does not complete at all is deficient [in their
training]”
Research Council Statement
1 year 2 years
67. ∂
If you do it, review it…
If it works:
• why did it work
• does it need fine tuning
• are there similar tools or
strategies that you could
use?
If it does not work:
•why didn’t it work
•should you revise or
scrap it?
Aims – to provide an opportunity to explore and discuss a range of time management tools and strategies
Outcomes
You will have
Had an opportunity to discuss the importance of time management in the research environment
Considered a range of tools and strategies
Reflected on your time management strategy and considered ways to develop
Preemptive
Obsession with beating deadlines
Seldom team-players
Prone to ‘burn out’
People Pleaser
Can’t say ‘No’
To much happening/ work overtime
Harbour resentment
Perfectionist
Can’t let go
Insufficient time/ run late
Worry/ fear of failure
Procrastination
The most common type of time abuser
Insufficient time / run late
Fear of failure
Ask yourself
What are your priorities?
What are the things that are most important to you?
Diaries – see handout
To-do lists – see handout
The Deming Cycle
By Paul Arveson
W. Edwards Deming in the 1950's proposed that business processes should be analyzed and measured to identify sources of variations that cause products to deviate from customer requirements. He recommended that business processes be placed in a continuous feedback loop so that managers can identify and change the parts of the process that need improvements. As a teacher, Deming created a (rather oversimplified) diagram to illustrate this continuous process, commonly known as the PDCA cycle for Plan, Do, Check, Act*:
PLAN: Design or revise business process components to improve results
DO: Implement the plan and measure its performance
CHECK: Assess the measurements and report the results to decision makers
ACT: Decide on changes needed to improve the process
See handout
Deadlines
If you say ‘I’ll try’ and subsequently miss the deadline – what people will remember is not that you tried but that you missed the deadline.
Deadlines should be realistic and specific
Stakeholders – people who trade resources (time / money / values) with the project. Managing the stakeholders is key – this can revolve around making sure you keep them informed to making sure that a balance of the outcomes of all the stakeholders is reached by the end of the project.
Having identified the stakeholders I can then identify who are the advocates and supporters and who are the blockers and critics. These can be colour coded, red, green or orange for neutral.
Having Identified the stakeholders and their feelings about the project, I then need to consider their levels of power and interest. The power/interest grid is a clear way of plotting this and causes the user to focus on exactly how they interact with the various stakeholders.
Identifying and monitoring stakeholders is an ongoing rather than a one off activity. Stakeholders, their agendas and the impact they can have on a project can change. Running a project with scant regard for the stakeholders can result in at best, dissatisfaction and at best, failure of the project.
By developing a good understanding of your stakeholders you will gain an understanding of how they are likely to respond to the developing project. It also helps in identifying what motivates your stakeholders and what you can do to win them around.
As I mentioned in the project management session, the way to eat an elephant is bit by bit and setting objectives is all about identifying and breaking down what needs to be done. That isn’t to say it is about focussing on the minutae. Once you identify the components and integrate them into a plan, then you are able to assess and monitor the whole.
Success is a motivator – moving onto the next aim with a success under your belt and a system/approach that you know works.
UKGRAD - Notes
Objectives are useful as without them it is difficult to both focus on the tasks which need done (the process of setting an objective should help clarify what needs done in order to complete the task) and also to assess progress. For PhD students the process of setting objectives should also help you step back from the small details within which you work on a daily basis and look at the wider picture. Well set objectives which are challenging but not too challenging can be an excellent method of motivation as when the objective is met the individual should have a sense of achievement.
After this ask them to think about objectives they can set for themselves, using either the grad handout prompts or the businessballs planning grid. Give them time to review and discuss them with each other.
Checklists
Review
Schedule analysis
Look at similar projects – talk to other project managers
Brainstorming
Do something different to terminate the risk
Work with risk to reduce impact or probability
If cost is greater than impact or probability?
Plan B
Pass to third party
This is a very commonly used grid which allows you to prioritise the risks which the project is under.
Ask the questions
– how probable
- how bad
This will allow you to plot the risks on the grid and come up with a priority list.
The Deming Cycle
By Paul Arveson
W. Edwards Deming in the 1950's proposed that business processes should be analyzed and measured to identify sources of variations that cause products to deviate from customer requirements. He recommended that business processes be placed in a continuous feedback loop so that managers can identify and change the parts of the process that need improvements. As a teacher, Deming created a (rather oversimplified) diagram to illustrate this continuous process, commonly known as the PDCA cycle for Plan, Do, Check, Act*:
PLAN: Design or revise business process components to improve results
DO: Implement the plan and measure its performance
CHECK: Assess the measurements and report the results to decision makers
ACT: Decide on changes needed to improve the process