SlideShare une entreprise Scribd logo
1  sur  33
Primavera -Basics
Aim
• To familiarize with Primavera Software, a well
known project planning and scheduling and
monitoring tool.
Basic Concepts
What is a Project ???
• A project is a set of activities and their
associated information that constitutes a plan
for creating a product or service.
• A project has a start date and finish date, WBS,
resource assignments and expenses. It can
also include risks, work documents and project-
specific codes and calendars.
Basic Terminologies
Activity:
Activities represent work to be done in order to
complete a project.
OD (Original Duration) and RD (Remaining
Duration):
The estimated time required to complete an activity is
called OD. The amount of time left to complete an
activity after it has started is known as RD (Remaining
Duration).
Predecessor:
The activity that effects start or finish dates of
other activities (successor activities).
Predecessor
Successor
Basic Terminologies
Successor:
The activity for which start or finish dates are dependent
on other activities (predecessor activities).
Predecessor
Successor
Basic Terminologies
Relationship:
Any sort of connection between two activities is
known as relationship.
Generally there are four types of relationships:
 SS (Start to Start)
 FS (Finish to Start)
 FF (Finish to Finish)
 SF (Start to Finish)
Basic Terminologies
Lag :
Lag staggers or delays the relationship of one activity
(predecessor) to another (successor).
Basic Terminologies
SS – Relationship between activities in which the start
of a successor activity depends on the start of its
predecessor.
Start-to-start
Start-to-start with lag
Predecessor
Successor
Predecessor
Successor
B
A
B
A
Lag
Basic Terminologies
FS – Relationship in which the start of successor
activity depends on the completion of its predecessor
activity.
Predecessor
Successor
Predecessor
Successor
B
A
B
A
Finish-to-start with lag
Finish-to-start
Basic Terminologies
FF – Relationship in which the finish of successor
activity depends on the finish of its predecessor activity.
Predecessor
Successor
Predecessor
Successor
B
A
B
A
Finish-to-Finish with lag
Finish-to-Finish
Lag
Basic Terminologies
SF – Relationship in which the finish of successor
activity depends on the start of its predecessor activity.
Predecessor
Successor
B
A
Start-to-Finish with lag
Start-to-Finish
Predecessor
Successor
B
A
Lag
Basic Terminologies
ES (Early Start) and EF (Early Finish) dates:
Earliest possible date by which an activity can be started /
finished.
LS (Late Start) and LF (Late Finish) dates:
Latest possible date by which an activity can be started /
finished.
Basic Terminologies
AS (Actual Start) and AF (Actual Finish) dates:
Actual Start and Actual Finish dates are the dates on which
an activity has actually started and finished.
Basic Terminologies
TF (Total Float):
Duration, measured in planning units, the activity can be delayed
without affecting the project finish date.
Negative or zero Total Float indicates that timely completion of
the activity is critical to the completion of the project. Such
activities are called Critical Activities.
FF (Free Float):
The amount of time, measured in planning units, the early start
of an activity can be delayed without delaying early start of a
successor activity. Such activities are called Non-critical
Activities.
Basic Terminologies
Constraints:
Constraints are ground realities that over-rule the logical
start and finish time of the activity.
For example: A certain piece of equipment will be received on,
say, 25th of March. That equipment’s erection activity cannot be
started before 26th of March irrespective of the fact that the
foundation will be ready by 15th of March.
So we will simply put a constraint to this activity that it cannot
start before 26th of March. Similarly concreting work cannot be
easily done in winter months in regions where temperature goes
below freezing during winter.
Basic Terminologies
Various types of constraints can be used but most
commonly used are as follows:
▫ Start No Earlier Than - This type of constraint is applied
to restrict that activity to start before a certain date
▫ Start No Later Than - This type of constraint is applied to
restrict that activity from starting beyond a certain date
▫ Finish No Earlier Than - This type of constraint is applied to restrict
that activity to finish before a certain date.
▫ Finish No Later Than - This type of constraint is applied to restrict
that activity to finish beyond a certain date.
▫ Start On - To impose a compulsory start date to that activity.
▫ Finish On - To impose a compulsory finish to that activity.
Basic Terminologies
Critical Activity:
An activity that has potential of delaying a project is called a critical
activity. Such activities possess total float equal to zero or even less.
Critical Path:
Chain of critical activities that has potential of delaying a
project is called Critical Path.
Critical Path Method (CPM):
A network analysis technique used to predict project duration, by
analyzing which sequence of activities (which path) has the least
amount of scheduling flexibility (the least amount of float).
Basic Terminologies
Critical Path
Predecessor
Successor
Predecessor
A
C
ES = 1 EF = 10
OD = 10
FS Lag = 0 ES=15 OD=6 EF=20
FS Lag=0
ES=1 OD=14 EF=14
B
Activity B and C are on critical path because :
1. These are forming the longest chain (14 days + 6 days = 20 days)
2. Any delay in any of the activity on critical path will cause a delay of the whole project
Basic Terminologies
Scheduling:
The process of calculating start and end dates of the activities.
This process is carried out in two passes i.e. Forward Pass &
Backward Pass.
Forward Pass:
The process of calculating start and finish dates of each activity
starting from the project start date.
This process generates early start and early finish
dates for each activity.
Basic Terminologies
Backward Pass:
The process of calculating finish and start dates of each activity
starting from the project finish date.
This process generates Late Start and Late Finish
dates for each activity.
Data Date:
The point in time that separates actual (Historical) data
from future (Scheduled) data.
Basic Terminologies
Man-Hours:
It is yardstick for measurement of effort. For example, 4
Man-Hour will mean any of the following:
▫ 1 man working for 4 hours
▫ 2 men working for 2 hours
▫ 4 men working for 1 hour
Standard Man-Hours:
Estimated effort per unit required to perform a job in terms
of man-hours.
Basic Terminologies
Budgeted Cost:
Total estimated cost approved for execution of a project.
Cost at Completion:
The expected total cost at completion of an activity or a
project.
Cost at completion is estimated periodically during course
of project execution.
Basic Terminologies
Program Evaluation and Review Technique (PERT):
An event oriented network analysis technique used to estimate
project duration when there is a higher degree of uncertainty with
the individual activity duration estimates. PERT applies the Critical
Path Method (CPM) to a weighted average duration estimates.
Gantt Chart:
A graphic display of schedule-related information listing project
elements on left side of the chart, dates across the top and activity
durations are shown as date-placed horizontal bars. It is also known
as Bar Chart.
Basic Terminologies
PERT
GANTT
Resource:
▫ Anything that is required to perform an activity is called a
resource
▫ Resources can be Manpower, Equipment and Materials
Basic Terminologies
Resource Allocation & Leveling
Resources required may include:
• Manpower
• Tools & Plants
• Direct materials
• Consumables
• Special jigs & fixtures
• Resource requirement should be a smooth curve i.e. ;
gradual increase till it reaches its peak, maintains peak for
required period and then gradually decrease till project is
completed.
• Resource Leveling is done in P3.
Resource Allocation & Leveling
Work Breakdown Structure
• Breaking down a long and complex project into work
packages of smaller duration and complexity.
• A properly planned WBS delivers the following benefits:
▫ The project can be planned systematically
▫ Resources can be effectively scheduled
▫ Work teams can be assigned responsibilities
▫ Costs and budget elements can be compared
Work Breakdown Structure
1. Project
1.1 Construction
1.1.1 Discipline
1.1.1.1 Zone/Area
1.1.1.1.1 Cost Center/Activity
Organization Breakdown Structure
• Represents a project organization structure that matches
with WBS.
• Facilitates better control through mini projects within large
and complicated projects.
• Defines responsibility for each level of WBS.
Organization Breakdown Structure
PROJECT/SITE MANAGER
AREA I/C
Engr. Civil
Engr. Piping
(
Engr. Equip.
AREA I/C #1
Engr. Civil
(area #1)
Engr. Piping
Engr. Equip.
Engr. Piping
Engr. Equip.
AREA I/C #2
Engr. Civil
Const. Mngr.
- Civil
Const. Mngr.
- Mech.
Const. Mngr.
- Elec.

Contenu connexe

Tendances

Primavera P6 manual
Primavera P6 manual Primavera P6 manual
Primavera P6 manual Abbas Tahir
 
Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™Charlie Jackson
 
Introduction to Primavera Reflections
Introduction to Primavera ReflectionsIntroduction to Primavera Reflections
Introduction to Primavera Reflectionsp6academy
 
Scheduling by using microsoft project 2013
Scheduling by using microsoft project 2013Scheduling by using microsoft project 2013
Scheduling by using microsoft project 2013Chetanraj M
 
Project planning and Scheduling
Project planning and SchedulingProject planning and Scheduling
Project planning and Schedulingsaurabmi2
 
Introduction to MS project
Introduction to MS projectIntroduction to MS project
Introduction to MS projectSamir Paralikar
 
MS Project Presentation
MS Project PresentationMS Project Presentation
MS Project PresentationKhem Singh
 
Project planning and scheduling
Project planning and schedulingProject planning and scheduling
Project planning and schedulingadeel hamid
 
Pdf primavera tutorial
Pdf primavera tutorialPdf primavera tutorial
Pdf primavera tutorialKetut Swandana
 
construction project planing
 construction project planing construction project planing
construction project planingSANJEEV Wazir
 
Primavera p6 18.8 planning and scheduling guide r3
Primavera p6 18.8 planning and  scheduling guide r3Primavera p6 18.8 planning and  scheduling guide r3
Primavera p6 18.8 planning and scheduling guide r3Matiwos Tsegaye
 
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERSPLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERSHafiz JUNAID
 
Ms Project Workshop
Ms Project WorkshopMs Project Workshop
Ms Project WorkshopEder Alves
 

Tendances (20)

Primavera P6 manual
Primavera P6 manual Primavera P6 manual
Primavera P6 manual
 
Ms project lectures
Ms project lecturesMs project lectures
Ms project lectures
 
Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™
 
Introduction to Primavera Reflections
Introduction to Primavera ReflectionsIntroduction to Primavera Reflections
Introduction to Primavera Reflections
 
Scheduling by using microsoft project 2013
Scheduling by using microsoft project 2013Scheduling by using microsoft project 2013
Scheduling by using microsoft project 2013
 
Primavera p6 advanced project planning
Primavera p6 advanced project planningPrimavera p6 advanced project planning
Primavera p6 advanced project planning
 
Project planning and Scheduling
Project planning and SchedulingProject planning and Scheduling
Project planning and Scheduling
 
Introduction to MS project
Introduction to MS projectIntroduction to MS project
Introduction to MS project
 
MS Project Presentation
MS Project PresentationMS Project Presentation
MS Project Presentation
 
Project planning and scheduling
Project planning and schedulingProject planning and scheduling
Project planning and scheduling
 
Primavera P6
Primavera P6Primavera P6
Primavera P6
 
Pdf primavera tutorial
Pdf primavera tutorialPdf primavera tutorial
Pdf primavera tutorial
 
PM using P6
PM using P6PM using P6
PM using P6
 
Schedule Updates
Schedule UpdatesSchedule Updates
Schedule Updates
 
Primavera software
Primavera softwarePrimavera software
Primavera software
 
construction project planing
 construction project planing construction project planing
construction project planing
 
Primavera p6 18.8 planning and scheduling guide r3
Primavera p6 18.8 planning and  scheduling guide r3Primavera p6 18.8 planning and  scheduling guide r3
Primavera p6 18.8 planning and scheduling guide r3
 
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERSPLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
 
Project Scheduling
Project SchedulingProject Scheduling
Project Scheduling
 
Ms Project Workshop
Ms Project WorkshopMs Project Workshop
Ms Project Workshop
 

Similaire à Primavera presentation

Chapter 12(cpm pert)
Chapter 12(cpm pert)Chapter 12(cpm pert)
Chapter 12(cpm pert)Debanjan15
 
Fundamentals of scheduling
Fundamentals of schedulingFundamentals of scheduling
Fundamentals of schedulingjmd2011
 
CPM, Network Analysis A-O-A, A-O-N, Resource management
CPM, Network Analysis A-O-A, A-O-N, Resource managementCPM, Network Analysis A-O-A, A-O-N, Resource management
CPM, Network Analysis A-O-A, A-O-N, Resource managementAmit Kumbar
 
Critical Path MethodIntroductionOnce you have the network diag.docx
Critical Path MethodIntroductionOnce you have the network diag.docxCritical Path MethodIntroductionOnce you have the network diag.docx
Critical Path MethodIntroductionOnce you have the network diag.docxannettsparrow
 
Baseline schedule review and analysis
Baseline schedule review and analysisBaseline schedule review and analysis
Baseline schedule review and analysisADITYA GHUMARE
 
Chap 4- CPM & PERT.pptx
Chap 4- CPM & PERT.pptxChap 4- CPM & PERT.pptx
Chap 4- CPM & PERT.pptxmohammad_bilal
 
Traditional Management System.ppt
Traditional Management System.pptTraditional Management System.ppt
Traditional Management System.pptUtkarshDwivedi74
 
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...Zulfiquer Ahmed Amin
 
Construction scheduling & Cost control
Construction scheduling & Cost controlConstruction scheduling & Cost control
Construction scheduling & Cost controlGuhan M
 
PROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptxPROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptxTecnicoItca
 
Critical path method & pert
Critical path method & pertCritical path method & pert
Critical path method & pertBhim Upadhyaya
 
project management -04.ppt
project management -04.pptproject management -04.ppt
project management -04.pptMdHelalHossain6
 
Time --updated 60b084af4f5af-
Time --updated 60b084af4f5af-Time --updated 60b084af4f5af-
Time --updated 60b084af4f5af-seminiMaya
 
Project schedule- What, How, Tools & Techniques
Project schedule- What, How, Tools & TechniquesProject schedule- What, How, Tools & Techniques
Project schedule- What, How, Tools & TechniquesSHAZEBALIKHAN1
 

Similaire à Primavera presentation (20)

Chapter 12(cpm pert)
Chapter 12(cpm pert)Chapter 12(cpm pert)
Chapter 12(cpm pert)
 
Fundamentals of scheduling
Fundamentals of schedulingFundamentals of scheduling
Fundamentals of scheduling
 
CPM, Network Analysis A-O-A, A-O-N, Resource management
CPM, Network Analysis A-O-A, A-O-N, Resource managementCPM, Network Analysis A-O-A, A-O-N, Resource management
CPM, Network Analysis A-O-A, A-O-N, Resource management
 
Critical Path MethodIntroductionOnce you have the network diag.docx
Critical Path MethodIntroductionOnce you have the network diag.docxCritical Path MethodIntroductionOnce you have the network diag.docx
Critical Path MethodIntroductionOnce you have the network diag.docx
 
Baseline schedule review and analysis
Baseline schedule review and analysisBaseline schedule review and analysis
Baseline schedule review and analysis
 
pm--basic.pptx
pm--basic.pptxpm--basic.pptx
pm--basic.pptx
 
Chap 4- CPM & PERT.pptx
Chap 4- CPM & PERT.pptxChap 4- CPM & PERT.pptx
Chap 4- CPM & PERT.pptx
 
Traditional Management System.ppt
Traditional Management System.pptTraditional Management System.ppt
Traditional Management System.ppt
 
Project Planning Scheduling
Project Planning SchedulingProject Planning Scheduling
Project Planning Scheduling
 
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
 
Construction scheduling & Cost control
Construction scheduling & Cost controlConstruction scheduling & Cost control
Construction scheduling & Cost control
 
PROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptxPROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptx
 
Unit IV-Project Management
Unit IV-Project ManagementUnit IV-Project Management
Unit IV-Project Management
 
Critical path method & pert
Critical path method & pertCritical path method & pert
Critical path method & pert
 
Project management techniques
Project management techniquesProject management techniques
Project management techniques
 
project management -04.ppt
project management -04.pptproject management -04.ppt
project management -04.ppt
 
Time --updated 60b084af4f5af-
Time --updated 60b084af4f5af-Time --updated 60b084af4f5af-
Time --updated 60b084af4f5af-
 
Network Analysis- CPM ppt..pptx
Network Analysis- CPM  ppt..pptxNetwork Analysis- CPM  ppt..pptx
Network Analysis- CPM ppt..pptx
 
Nce603 mod unit2
Nce603 mod unit2Nce603 mod unit2
Nce603 mod unit2
 
Project schedule- What, How, Tools & Techniques
Project schedule- What, How, Tools & TechniquesProject schedule- What, How, Tools & Techniques
Project schedule- What, How, Tools & Techniques
 

Primavera presentation

  • 2. Aim • To familiarize with Primavera Software, a well known project planning and scheduling and monitoring tool.
  • 3. Basic Concepts What is a Project ??? • A project is a set of activities and their associated information that constitutes a plan for creating a product or service. • A project has a start date and finish date, WBS, resource assignments and expenses. It can also include risks, work documents and project- specific codes and calendars.
  • 4. Basic Terminologies Activity: Activities represent work to be done in order to complete a project. OD (Original Duration) and RD (Remaining Duration): The estimated time required to complete an activity is called OD. The amount of time left to complete an activity after it has started is known as RD (Remaining Duration).
  • 5. Predecessor: The activity that effects start or finish dates of other activities (successor activities). Predecessor Successor Basic Terminologies
  • 6. Successor: The activity for which start or finish dates are dependent on other activities (predecessor activities). Predecessor Successor Basic Terminologies
  • 7. Relationship: Any sort of connection between two activities is known as relationship. Generally there are four types of relationships:  SS (Start to Start)  FS (Finish to Start)  FF (Finish to Finish)  SF (Start to Finish) Basic Terminologies
  • 8. Lag : Lag staggers or delays the relationship of one activity (predecessor) to another (successor). Basic Terminologies
  • 9. SS – Relationship between activities in which the start of a successor activity depends on the start of its predecessor. Start-to-start Start-to-start with lag Predecessor Successor Predecessor Successor B A B A Lag Basic Terminologies
  • 10. FS – Relationship in which the start of successor activity depends on the completion of its predecessor activity. Predecessor Successor Predecessor Successor B A B A Finish-to-start with lag Finish-to-start Basic Terminologies
  • 11. FF – Relationship in which the finish of successor activity depends on the finish of its predecessor activity. Predecessor Successor Predecessor Successor B A B A Finish-to-Finish with lag Finish-to-Finish Lag Basic Terminologies
  • 12. SF – Relationship in which the finish of successor activity depends on the start of its predecessor activity. Predecessor Successor B A Start-to-Finish with lag Start-to-Finish Predecessor Successor B A Lag Basic Terminologies
  • 13. ES (Early Start) and EF (Early Finish) dates: Earliest possible date by which an activity can be started / finished. LS (Late Start) and LF (Late Finish) dates: Latest possible date by which an activity can be started / finished. Basic Terminologies
  • 14. AS (Actual Start) and AF (Actual Finish) dates: Actual Start and Actual Finish dates are the dates on which an activity has actually started and finished. Basic Terminologies
  • 15. TF (Total Float): Duration, measured in planning units, the activity can be delayed without affecting the project finish date. Negative or zero Total Float indicates that timely completion of the activity is critical to the completion of the project. Such activities are called Critical Activities. FF (Free Float): The amount of time, measured in planning units, the early start of an activity can be delayed without delaying early start of a successor activity. Such activities are called Non-critical Activities. Basic Terminologies
  • 16. Constraints: Constraints are ground realities that over-rule the logical start and finish time of the activity. For example: A certain piece of equipment will be received on, say, 25th of March. That equipment’s erection activity cannot be started before 26th of March irrespective of the fact that the foundation will be ready by 15th of March. So we will simply put a constraint to this activity that it cannot start before 26th of March. Similarly concreting work cannot be easily done in winter months in regions where temperature goes below freezing during winter. Basic Terminologies
  • 17. Various types of constraints can be used but most commonly used are as follows: ▫ Start No Earlier Than - This type of constraint is applied to restrict that activity to start before a certain date ▫ Start No Later Than - This type of constraint is applied to restrict that activity from starting beyond a certain date ▫ Finish No Earlier Than - This type of constraint is applied to restrict that activity to finish before a certain date. ▫ Finish No Later Than - This type of constraint is applied to restrict that activity to finish beyond a certain date. ▫ Start On - To impose a compulsory start date to that activity. ▫ Finish On - To impose a compulsory finish to that activity. Basic Terminologies
  • 18. Critical Activity: An activity that has potential of delaying a project is called a critical activity. Such activities possess total float equal to zero or even less. Critical Path: Chain of critical activities that has potential of delaying a project is called Critical Path. Critical Path Method (CPM): A network analysis technique used to predict project duration, by analyzing which sequence of activities (which path) has the least amount of scheduling flexibility (the least amount of float). Basic Terminologies
  • 19. Critical Path Predecessor Successor Predecessor A C ES = 1 EF = 10 OD = 10 FS Lag = 0 ES=15 OD=6 EF=20 FS Lag=0 ES=1 OD=14 EF=14 B Activity B and C are on critical path because : 1. These are forming the longest chain (14 days + 6 days = 20 days) 2. Any delay in any of the activity on critical path will cause a delay of the whole project Basic Terminologies
  • 20. Scheduling: The process of calculating start and end dates of the activities. This process is carried out in two passes i.e. Forward Pass & Backward Pass. Forward Pass: The process of calculating start and finish dates of each activity starting from the project start date. This process generates early start and early finish dates for each activity. Basic Terminologies
  • 21. Backward Pass: The process of calculating finish and start dates of each activity starting from the project finish date. This process generates Late Start and Late Finish dates for each activity. Data Date: The point in time that separates actual (Historical) data from future (Scheduled) data. Basic Terminologies
  • 22. Man-Hours: It is yardstick for measurement of effort. For example, 4 Man-Hour will mean any of the following: ▫ 1 man working for 4 hours ▫ 2 men working for 2 hours ▫ 4 men working for 1 hour Standard Man-Hours: Estimated effort per unit required to perform a job in terms of man-hours. Basic Terminologies
  • 23. Budgeted Cost: Total estimated cost approved for execution of a project. Cost at Completion: The expected total cost at completion of an activity or a project. Cost at completion is estimated periodically during course of project execution. Basic Terminologies
  • 24. Program Evaluation and Review Technique (PERT): An event oriented network analysis technique used to estimate project duration when there is a higher degree of uncertainty with the individual activity duration estimates. PERT applies the Critical Path Method (CPM) to a weighted average duration estimates. Gantt Chart: A graphic display of schedule-related information listing project elements on left side of the chart, dates across the top and activity durations are shown as date-placed horizontal bars. It is also known as Bar Chart. Basic Terminologies
  • 25. PERT
  • 26. GANTT
  • 27. Resource: ▫ Anything that is required to perform an activity is called a resource ▫ Resources can be Manpower, Equipment and Materials Basic Terminologies
  • 28. Resource Allocation & Leveling Resources required may include: • Manpower • Tools & Plants • Direct materials • Consumables • Special jigs & fixtures
  • 29. • Resource requirement should be a smooth curve i.e. ; gradual increase till it reaches its peak, maintains peak for required period and then gradually decrease till project is completed. • Resource Leveling is done in P3. Resource Allocation & Leveling
  • 30. Work Breakdown Structure • Breaking down a long and complex project into work packages of smaller duration and complexity. • A properly planned WBS delivers the following benefits: ▫ The project can be planned systematically ▫ Resources can be effectively scheduled ▫ Work teams can be assigned responsibilities ▫ Costs and budget elements can be compared
  • 31. Work Breakdown Structure 1. Project 1.1 Construction 1.1.1 Discipline 1.1.1.1 Zone/Area 1.1.1.1.1 Cost Center/Activity
  • 32. Organization Breakdown Structure • Represents a project organization structure that matches with WBS. • Facilitates better control through mini projects within large and complicated projects. • Defines responsibility for each level of WBS.
  • 33. Organization Breakdown Structure PROJECT/SITE MANAGER AREA I/C Engr. Civil Engr. Piping ( Engr. Equip. AREA I/C #1 Engr. Civil (area #1) Engr. Piping Engr. Equip. Engr. Piping Engr. Equip. AREA I/C #2 Engr. Civil Const. Mngr. - Civil Const. Mngr. - Mech. Const. Mngr. - Elec.