1 ScottishPower Renewables: Introduction
2 ScottishPower Renewables: Offshore
3 East Anglia ONE Offshore Windfarm: Overview
4 Key Dates
5 Indicative Contracting Strategy
6 Major Packages
7 Supply Chain Plan Overview
8 Future opportunities/challenges
3. 3
ScottishPower Renewables: a world leader in wind power
> 950 turbines
> 1,600 MW in
operation
Double Queen’s Award
winners
Best practice
environmental approach
> 600 MW in
construction
4. 4
Offshore: A growing global portfolio
Four projects in three key markets
Saint Brieuc
500 MW
Planning application 2015
70% JV with Eole RES
West of Duddon Sands
389 MW
Operational October 2014
50% JV with DONG
East Anglia ONE
714 MW
Consented June 2014
CfD awarded February 2015
Wikinger
350 MW
Construction begins 2015
100% SPR
5. 5
• UK Round 3 Zone, total Zone
capacity 7.2 GW
• Consent awarded for first project in
June 2014
• CfD contract award in February
2015 - up to 714 MW
• East coast of England – 45 km
southeast of Lowestoft
• Area of 300 km2
• Water depths range between 30 and
55 m
• Jacket foundations
East Anglia ONE Offshore Windfarm Overview
East Anglia ONE
Offshore Windfarm
6. 6
Key Dates
Activity Timing
Procurement of Main Contracts All major packages ongoing
Final Investment Decision February 2016
CfD Milestone Commitment March 2016
Onshore Construction Window January 2017 – January 2019
Offshore Construction Period August 2018 – June 2020
First Power March 2019
Fully Operational June 2020
7. East Anglia ONE Indicative Contracting Strategy
Supply
Installation
O&M
Detail
Engineering
Fabrication
O&M
Fabrication
Installation
Fabrication
Installation
Number of
contracts
TBC
Number of
contracts
TBC
Number of
contracts TBC
Ports and Logistics – (1) Construction, Monitoring and Management Port
(2) WTG Pre Assembly Port
(3) O&M Base Port
(4) Foundations Marshalling
WTG
Founda-
tions
Array
Cables
Export
Cable
Offshore
Substation
Onshore
Cable
Onshore
Substation
OFTO
Installation
8. Major Packages
Package Status
1. Wind Turbine Supply & Installation Preferred bidder stage
2. Foundation Design Contract awarded
3. Foundation & Pile Supply ITT issued
Bids received & under review
4. Foundation Installation ITT issued
Bids received & under review
5. Array Cables Supply & Installation ITT issued
Bids received & under review
6. On/Offshore Transmission package Major ITT’s issued
Bids due from Nov ‘15 onwards
7. Wind Turbine Operations and
Maintenance
Preferred bidder stage
8. Ports Shortlist of ports identified and
negotiations ongoing.
9. Competition
• Committed to open and competitive procurement processes
• 50% UK content target
• Supplier Supply Chain Plans
Innovation
• Test site prospect 3-5 positions
• Employer and supplier innovation investment targets
Skills
• Employment projection – 1,500-3,000 FTEs
• Skills Implementation Plan 2016
• Collaborative approach to skills delivery with chosen suppliers
Supply Chain Plan Overview
10. Future Opportunities
EA THREE Project
• Approximately 305 km2
• 1,200 MW (possibly 2 x 600MW)
• Landfall at Bawdsey
• Uses cable conduits laid by EA ONE
• Connects to Bramford
• 1 x substation required
• November 2015 application to Planning
Inspectorate
• Q4 2016: Decision by Secretary of State