SlideShare une entreprise Scribd logo
1  sur  12
Télécharger pour lire hors ligne
MAIN OBSTACELS FOR RES IN GEORIGA
2
THE CONTENT
Threats and Weaknesses
Local Component
Requirement
LCOE of Wind PP GIG Case Study
3
TREAT:
Policy Uncertainty
Lack of long-term policy in Georgia
for spurring investor confidence.
There is no differentiation between
Hydro and non-Hydro Renewables.
Currently, there is a cap for PPA
tariffs introduced under the
memorandum with IMF: 6 USDc, 8
Months.
TWO PRIMARY PROBLMS with NON-HYDRO RENEWABLES
High Initial Cost, Low Capacity Factor, Policy Uncertainty
WEAKNESS:
High Cost
By and large, RES have a high
installation cost amplified by a low
capacity factor that makes them
less competitive in countries with a
high discount rate. Although the
current WACC equals to 13.75%, it
is anticipated that for the year 2017
Georgia’s WACC will be in range
14-17%
4
• Capital Cost (Grid Connection included) – 1300 - 1700 USD/MW
• O&M - 0.6 - 1.2 USDc/kWh
• Capacity Factor – 35% - 45%
• Degradation Rate - 0.3% per annum
• Discounting Factor, WACC - 14.3%, 15.8%, 17.8% (Energy Regulators Regional Association, February
2017)
• WPP Life time- 20 years
LEVELIZED COST OF ELECTRICITY for WIND in
Georgia
INPUT PARAMETERS
Levelized Cost of Electricity =
∑
𝑪𝑪𝑪𝑪𝑪𝑪𝑪𝑪𝑪𝑪 +𝑮𝑮𝑮𝑮𝑮𝑮 𝑮𝑮 𝑪𝑪𝑪𝑪𝑪𝑪𝑪𝑪𝑪𝑪𝑪𝑪𝑪𝑪𝑪𝑪𝑪𝑪 𝑪𝑪 +𝑶𝑶&𝑴𝑴+𝑭𝑭𝑭𝑭𝑭𝑭𝑭𝑭
𝟏𝟏+𝒓𝒓 𝒕𝒕
∑
𝑬𝑬𝑬𝑬𝑬𝑬𝑬𝑬𝑬𝑬𝑬𝑬𝑬𝑬𝑬𝑬𝑬𝑬𝑬𝑬𝑬𝑬 𝑶𝑶𝑶𝑶𝑶𝑶𝑶𝑶𝑶𝑶𝑶𝑶∗ 𝟏𝟏−𝑫𝑫𝑫𝑫 𝒕𝒕
𝟏𝟏+𝒓𝒓 𝒕𝒕
5
LEVELIZED COST OF ELECTRICITY for WIND in GEORGIA
Results of Stochastic Sensitivity Analysis
WACC=14.3% WACC=15.8% WACC=17.8%
LCOE = 6.11 USDc LCOE = 6.52 USDc LCOE = 7.08 USDc
LCOE,
Stochastic Sensitivity Analysis with r=14.3%
LCOE
Density
0.050 0.055 0.060 0.065 0.070 0.075 0.080
0102030405060
Mean LCOE, 6.11 USDc
Kernel Density
LCOE,
Stochastic Sensitivity Analysis with r=15.8%
LCOE
Density
0.050 0.055 0.060 0.065 0.070 0.075 0.080 0.085
0102030405060
Mean LCOE, 6.52 USDc
Kernel Density
LCOE,
Stochastic Sensitivity Analysis with r=17.8%
LCOE
Density
0.06 0.07 0.08 0.09
01020304050
Mean LCOE, 7.08 USDc
Kernel Density
6
MICRO POWER PLANT
Net Metering
Micro Power Plant with Install
Capacity under 100 KW (Law on
Electricity and Natural Gas)
• The owner of photovoltaic panels can supply generated electricity to the system, and purchase power
from the system.
• In cases when the monthly balance (electricity produced minus electricity consumed) is negative, the
household pays for the net amount of electricity consumed.
• In the opposite case, when the monthly balance is positive, the household is paid by Utility Company.
7
GIG CASE STUDY
100 KW Roof Solar Panels
• Cost (Including roof preparation works) ≈
2.2 USDc per Watt, 100KW ≈ 220,000USD
• Simulated Production: 172.6 MWh/year
• Year 10: Inventor Outlay, 45,000USD
• O&M: 2400 USD per Annum
• Tariff: 10 USDc ≈ 24 Tetri
8
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
-200000-150000-100000-500000
0 20 40 60 80 100
-150000-100000-500000
i%
NPV
1.06
The law was adopted in April, 2016.
Only 8 micro generation PP have
been registered in GNERC so far.
GIG CASE STUDY
Results
IRR = 1.06% (!)
Payback = 21 years
NPV (i=10%), = -104671.1 (!)
9
LOCAL CONTEN REQUIREMENT: Developing Green
Economy in Georgia
Employment, Taxes, Technology Transfer
Employment Gains
By requiring enterprises to use a certain proportion of inputs from local
industries, proponents argue that employment will certainly increase
Increased Tax Base
LCR will lead to an increased tax base for governments because of a
larger local manufacturing industry. This would allow countries to have
more income, while developing a new industry
Transfer of Technology and Knowledge
Technology transfer as a result of LCR comes from learning-by-doing
and capacity building in domestic supply. Although it is not patent-
related, this knowledge of technology and how to operate it is an
important component in reaching global green industrial growth.
Local content requirements (LCR) are policy measures that
require foreign or domestic investors to source a certain
percentage of intermediate goods from local manufacturers
or producers.
10
Feed in Tariff plus LC
The Ministry of Energy and Natural Resources determined the baseline feed-in
tariff for wind energy at 7.3 USD cent/ kWh with an extra bonus for locally
manufactured component which is an extra 3.7 USD cent/ kWh:
• Bonus for Blade 0.8 USD cent/ kWh,
• Bonus for Generator/ Power Electronics 1 USD cent/ kWh,
• Bonus for Turbine tower 0.6 USD cent/ kWh,
• Bonus for all mechanical equipment in rotor and nacelle is 1.3 USD cent/
kWh.
Tender with LCR
The Ministry of Energy and Natural Resources invited interested and eligible parties
for tender on the construction of 1 GW installed capacities of Wind PPs with 65% LC
including all nececcary row materials. The tariff should be below 7 USDc, however
15 years power purchasing is guaranteed.
LCR in Turkey: Case
FiT plus LC Bonus, Tendering with LCR
11
LCR in Georgia
Spare Capacity at KAMP
GIG Spare Capacity at Kutaisi Auto
Mechanical Plant
 60 000 sq. meter
under the single roof;
 Experienced
workers;
 Not far from Black
Sea ports.
12

Contenu connexe

Tendances

Rhone Resch | Industry Perspective on a National Performance Based Incentive
Rhone Resch | Industry Perspective on a National Performance Based IncentiveRhone Resch | Industry Perspective on a National Performance Based Incentive
Rhone Resch | Industry Perspective on a National Performance Based IncentiveGW Solar Institute
 
Us solar market outlook and growth trajectory 2025
Us solar market outlook and growth trajectory 2025Us solar market outlook and growth trajectory 2025
Us solar market outlook and growth trajectory 2025Ashish Verma
 
Playing Well with Others - Market for Storage Hybrids
Playing Well with Others - Market for Storage HybridsPlaying Well with Others - Market for Storage Hybrids
Playing Well with Others - Market for Storage HybridsJill Kirkpatrick
 
Power of sun and solar energy (india power)
Power of sun and solar energy (india power)Power of sun and solar energy (india power)
Power of sun and solar energy (india power)Mahesh Chandra Manav
 
2012 Reenergize the Americas 1A: Richard Gruber
2012 Reenergize the Americas 1A: Richard Gruber2012 Reenergize the Americas 1A: Richard Gruber
2012 Reenergize the Americas 1A: Richard GruberReenergize
 
Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019
Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019
Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019Gensol Engineering Limited
 
Colin Smith and Dan Finn-Foley
Colin Smith and Dan Finn-FoleyColin Smith and Dan Finn-Foley
Colin Smith and Dan Finn-FoleyNicole Green
 
Hotel engineers association sydney june 2013
Hotel engineers association sydney june 2013Hotel engineers association sydney june 2013
Hotel engineers association sydney june 2013Knowledge Global
 
Keynote Interview: Texas as a U.S. Flagship for Energy Transition
Keynote Interview: Texas as a U.S. Flagship for Energy TransitionKeynote Interview: Texas as a U.S. Flagship for Energy Transition
Keynote Interview: Texas as a U.S. Flagship for Energy TransitionNicole Green
 
How a successful Feed-in Tariff system will stimulate the growth of the PV in...
How a successful Feed-in Tariff system will stimulate the growth of the PV in...How a successful Feed-in Tariff system will stimulate the growth of the PV in...
How a successful Feed-in Tariff system will stimulate the growth of the PV in...Smithers Apex
 
Micro Generation And Selling Your Power
Micro Generation And Selling Your PowerMicro Generation And Selling Your Power
Micro Generation And Selling Your PowerStephen Rowley
 
Decarbonising UK Energy
Decarbonising UK EnergyDecarbonising UK Energy
Decarbonising UK Energyliammacuaid
 
TECH START UP TURNED UTILITY – EMPOWERING CUSTOMERS WITH DATA TO TAKE CONTROL...
TECH START UP TURNED UTILITY – EMPOWERING CUSTOMERS WITH DATA TO TAKE CONTROL...TECH START UP TURNED UTILITY – EMPOWERING CUSTOMERS WITH DATA TO TAKE CONTROL...
TECH START UP TURNED UTILITY – EMPOWERING CUSTOMERS WITH DATA TO TAKE CONTROL...Big Data Week
 
The Wholesale Electric Market in ERCOT
The Wholesale Electric Market in ERCOT The Wholesale Electric Market in ERCOT
The Wholesale Electric Market in ERCOT aectnet
 
NATS Connect Live | Pub/Sub on the Power Grid
NATS Connect Live | Pub/Sub on the Power GridNATS Connect Live | Pub/Sub on the Power Grid
NATS Connect Live | Pub/Sub on the Power GridNATS
 
Гідроелектростанції в Україні
Гідроелектростанції в УкраїніГідроелектростанції в Україні
Гідроелектростанції в УкраїніUAReforms
 

Tendances (20)

Rhone Resch | Industry Perspective on a National Performance Based Incentive
Rhone Resch | Industry Perspective on a National Performance Based IncentiveRhone Resch | Industry Perspective on a National Performance Based Incentive
Rhone Resch | Industry Perspective on a National Performance Based Incentive
 
Feed In Tariffs
Feed In TariffsFeed In Tariffs
Feed In Tariffs
 
Us solar market outlook and growth trajectory 2025
Us solar market outlook and growth trajectory 2025Us solar market outlook and growth trajectory 2025
Us solar market outlook and growth trajectory 2025
 
Playing Well with Others - Market for Storage Hybrids
Playing Well with Others - Market for Storage HybridsPlaying Well with Others - Market for Storage Hybrids
Playing Well with Others - Market for Storage Hybrids
 
Power of sun and solar energy (india power)
Power of sun and solar energy (india power)Power of sun and solar energy (india power)
Power of sun and solar energy (india power)
 
2012 Reenergize the Americas 1A: Richard Gruber
2012 Reenergize the Americas 1A: Richard Gruber2012 Reenergize the Americas 1A: Richard Gruber
2012 Reenergize the Americas 1A: Richard Gruber
 
Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019
Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019
Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019
 
Colin Smith and Dan Finn-Foley
Colin Smith and Dan Finn-FoleyColin Smith and Dan Finn-Foley
Colin Smith and Dan Finn-Foley
 
Resch - Solar Vision Forum
Resch - Solar Vision ForumResch - Solar Vision Forum
Resch - Solar Vision Forum
 
Hotel engineers association sydney june 2013
Hotel engineers association sydney june 2013Hotel engineers association sydney june 2013
Hotel engineers association sydney june 2013
 
Keynote Interview: Texas as a U.S. Flagship for Energy Transition
Keynote Interview: Texas as a U.S. Flagship for Energy TransitionKeynote Interview: Texas as a U.S. Flagship for Energy Transition
Keynote Interview: Texas as a U.S. Flagship for Energy Transition
 
How a successful Feed-in Tariff system will stimulate the growth of the PV in...
How a successful Feed-in Tariff system will stimulate the growth of the PV in...How a successful Feed-in Tariff system will stimulate the growth of the PV in...
How a successful Feed-in Tariff system will stimulate the growth of the PV in...
 
Micro Generation And Selling Your Power
Micro Generation And Selling Your PowerMicro Generation And Selling Your Power
Micro Generation And Selling Your Power
 
Suttonbridge1
Suttonbridge1Suttonbridge1
Suttonbridge1
 
Decarbonising UK Energy
Decarbonising UK EnergyDecarbonising UK Energy
Decarbonising UK Energy
 
TECH START UP TURNED UTILITY – EMPOWERING CUSTOMERS WITH DATA TO TAKE CONTROL...
TECH START UP TURNED UTILITY – EMPOWERING CUSTOMERS WITH DATA TO TAKE CONTROL...TECH START UP TURNED UTILITY – EMPOWERING CUSTOMERS WITH DATA TO TAKE CONTROL...
TECH START UP TURNED UTILITY – EMPOWERING CUSTOMERS WITH DATA TO TAKE CONTROL...
 
The Wholesale Electric Market in ERCOT
The Wholesale Electric Market in ERCOT The Wholesale Electric Market in ERCOT
The Wholesale Electric Market in ERCOT
 
NATS Connect Live | Pub/Sub on the Power Grid
NATS Connect Live | Pub/Sub on the Power GridNATS Connect Live | Pub/Sub on the Power Grid
NATS Connect Live | Pub/Sub on the Power Grid
 
Counting the Capacity that Didn't Hatch
Counting the Capacity that Didn't HatchCounting the Capacity that Didn't Hatch
Counting the Capacity that Didn't Hatch
 
Гідроелектростанції в Україні
Гідроелектростанції в УкраїніГідроелектростанції в Україні
Гідроелектростанції в Україні
 

Similaire à Main obstacles and LCOE of wind power in Georgia

public serviceenterprise group LehmanConference
public serviceenterprise group LehmanConferencepublic serviceenterprise group LehmanConference
public serviceenterprise group LehmanConferencefinance20
 
public serviceenterprise group LehmanConference
public serviceenterprise group LehmanConferencepublic serviceenterprise group LehmanConference
public serviceenterprise group LehmanConferencefinance20
 
Island states - Renewable Energy Policy Pioneers
Island states - Renewable Energy Policy PioneersIsland states - Renewable Energy Policy Pioneers
Island states - Renewable Energy Policy PioneersLeonardo ENERGY
 
WindFarmFeasibility (1).ppt
WindFarmFeasibility (1).pptWindFarmFeasibility (1).ppt
WindFarmFeasibility (1).pptssuserfdb06f
 
Mylene Capongol, Department of Energy - Philippine Experience in Furthering R...
Mylene Capongol, Department of Energy - Philippine Experience in Furthering R...Mylene Capongol, Department of Energy - Philippine Experience in Furthering R...
Mylene Capongol, Department of Energy - Philippine Experience in Furthering R...OECD Environment
 
Massachusetts policies for combined heat & power
Massachusetts policies for combined heat & powerMassachusetts policies for combined heat & power
Massachusetts policies for combined heat & powerTNenergy
 
Separating Myth From Fact on Solar
Separating Myth From Fact on SolarSeparating Myth From Fact on Solar
Separating Myth From Fact on SolarPatti Gettinger
 
Economy and energy security for pakistan
Economy and energy security for pakistanEconomy and energy security for pakistan
Economy and energy security for pakistanFaizan Shabbir
 
Energy comsats 12_oct13_2
Energy comsats 12_oct13_2Energy comsats 12_oct13_2
Energy comsats 12_oct13_2Faizan Shabbir
 
Renewable Energy Act of 2008 - Seven Years After
Renewable Energy Act of 2008 - Seven Years AfterRenewable Energy Act of 2008 - Seven Years After
Renewable Energy Act of 2008 - Seven Years AfterFernando Penarroyo
 
New jersey's clean energy program opportunities for chp
New jersey's clean energy program   opportunities for chpNew jersey's clean energy program   opportunities for chp
New jersey's clean energy program opportunities for chpTNenergy
 
Peter Meier Feed-in-tariff for Vietnam and Srilanka
Peter Meier Feed-in-tariff for Vietnam and SrilankaPeter Meier Feed-in-tariff for Vietnam and Srilanka
Peter Meier Feed-in-tariff for Vietnam and SrilankaTuong Do
 
Hug Teeth
Hug TeethHug Teeth
Hug Teethroaudet
 

Similaire à Main obstacles and LCOE of wind power in Georgia (20)

Small Power Generation Plant
Small Power Generation PlantSmall Power Generation Plant
Small Power Generation Plant
 
Agham Feed-in Tariff system Briefer
Agham Feed-in Tariff system BrieferAgham Feed-in Tariff system Briefer
Agham Feed-in Tariff system Briefer
 
public serviceenterprise group LehmanConference
public serviceenterprise group LehmanConferencepublic serviceenterprise group LehmanConference
public serviceenterprise group LehmanConference
 
public serviceenterprise group LehmanConference
public serviceenterprise group LehmanConferencepublic serviceenterprise group LehmanConference
public serviceenterprise group LehmanConference
 
Island states - Renewable Energy Policy Pioneers
Island states - Renewable Energy Policy PioneersIsland states - Renewable Energy Policy Pioneers
Island states - Renewable Energy Policy Pioneers
 
WindFarmFeasibility (1).ppt
WindFarmFeasibility (1).pptWindFarmFeasibility (1).ppt
WindFarmFeasibility (1).ppt
 
Mylene Capongol, Department of Energy - Philippine Experience in Furthering R...
Mylene Capongol, Department of Energy - Philippine Experience in Furthering R...Mylene Capongol, Department of Energy - Philippine Experience in Furthering R...
Mylene Capongol, Department of Energy - Philippine Experience in Furthering R...
 
Final project jrrm
Final project jrrm Final project jrrm
Final project jrrm
 
Two difficulties
Two difficultiesTwo difficulties
Two difficulties
 
Energy Use and Pricing for Carlsbad Seawater Desalination
Energy Use and Pricing for Carlsbad Seawater DesalinationEnergy Use and Pricing for Carlsbad Seawater Desalination
Energy Use and Pricing for Carlsbad Seawater Desalination
 
Massachusetts policies for combined heat & power
Massachusetts policies for combined heat & powerMassachusetts policies for combined heat & power
Massachusetts policies for combined heat & power
 
RENEWABLE POLICY
RENEWABLE POLICYRENEWABLE POLICY
RENEWABLE POLICY
 
42918
4291842918
42918
 
Separating Myth From Fact on Solar
Separating Myth From Fact on SolarSeparating Myth From Fact on Solar
Separating Myth From Fact on Solar
 
Economy and energy security for pakistan
Economy and energy security for pakistanEconomy and energy security for pakistan
Economy and energy security for pakistan
 
Energy comsats 12_oct13_2
Energy comsats 12_oct13_2Energy comsats 12_oct13_2
Energy comsats 12_oct13_2
 
Renewable Energy Act of 2008 - Seven Years After
Renewable Energy Act of 2008 - Seven Years AfterRenewable Energy Act of 2008 - Seven Years After
Renewable Energy Act of 2008 - Seven Years After
 
New jersey's clean energy program opportunities for chp
New jersey's clean energy program   opportunities for chpNew jersey's clean energy program   opportunities for chp
New jersey's clean energy program opportunities for chp
 
Peter Meier Feed-in-tariff for Vietnam and Srilanka
Peter Meier Feed-in-tariff for Vietnam and SrilankaPeter Meier Feed-in-tariff for Vietnam and Srilanka
Peter Meier Feed-in-tariff for Vietnam and Srilanka
 
Hug Teeth
Hug TeethHug Teeth
Hug Teeth
 

Plus de OECD Environment

GREEN Action Task Force - Full Presentations.pdf
GREEN Action Task Force - Full Presentations.pdfGREEN Action Task Force - Full Presentations.pdf
GREEN Action Task Force - Full Presentations.pdfOECD Environment
 
Case Study: Peptides-based Plant Protection Product (harpin proteins*) by Ros...
Case Study: Peptides-based Plant Protection Product (harpin proteins*) by Ros...Case Study: Peptides-based Plant Protection Product (harpin proteins*) by Ros...
Case Study: Peptides-based Plant Protection Product (harpin proteins*) by Ros...OECD Environment
 
CLE Contribution on the Assessment of Innovative Biochemicals in the EU Statu...
CLE Contribution on the Assessment of Innovative Biochemicals in the EU Statu...CLE Contribution on the Assessment of Innovative Biochemicals in the EU Statu...
CLE Contribution on the Assessment of Innovative Biochemicals in the EU Statu...OECD Environment
 
Additional Considerations for Pesticide Formulations Containing Microbial Pes...
Additional Considerations for Pesticide Formulations Containing Microbial Pes...Additional Considerations for Pesticide Formulations Containing Microbial Pes...
Additional Considerations for Pesticide Formulations Containing Microbial Pes...OECD Environment
 
Role of genome sequencing (WGS) in microbial biopesticides safety assessment ...
Role of genome sequencing (WGS) in microbial biopesticides safety assessment ...Role of genome sequencing (WGS) in microbial biopesticides safety assessment ...
Role of genome sequencing (WGS) in microbial biopesticides safety assessment ...OECD Environment
 
Considerations for Problem Formulation for Human Health Safety Assessments of...
Considerations for Problem Formulation for Human Health Safety Assessments of...Considerations for Problem Formulation for Human Health Safety Assessments of...
Considerations for Problem Formulation for Human Health Safety Assessments of...OECD Environment
 
How to Identify and Quantify Mixtures What is Essential to Know for Risk Asse...
How to Identify and Quantify Mixtures What is Essential to Know for Risk Asse...How to Identify and Quantify Mixtures What is Essential to Know for Risk Asse...
How to Identify and Quantify Mixtures What is Essential to Know for Risk Asse...OECD Environment
 
APVMA outcome-focussed approach to data requirements to support registration ...
APVMA outcome-focussed approach to data requirements to support registration ...APVMA outcome-focussed approach to data requirements to support registration ...
APVMA outcome-focussed approach to data requirements to support registration ...OECD Environment
 
The U.S. Perspective on Problem Formulation for Biopesticides: Shannon BORGES
The U.S. Perspective on Problem Formulation for Biopesticides: Shannon BORGESThe U.S. Perspective on Problem Formulation for Biopesticides: Shannon BORGES
The U.S. Perspective on Problem Formulation for Biopesticides: Shannon BORGESOECD Environment
 
Problem formulation for environmental risk assessment – Finnish case study: ...
Problem formulation for environmental risk assessment – Finnish case study:  ...Problem formulation for environmental risk assessment – Finnish case study:  ...
Problem formulation for environmental risk assessment – Finnish case study: ...OECD Environment
 
Problem formulation for environmental risk assessment in the context of EC Re...
Problem formulation for environmental risk assessment in the context of EC Re...Problem formulation for environmental risk assessment in the context of EC Re...
Problem formulation for environmental risk assessment in the context of EC Re...OECD Environment
 
Canadian Perspective on Problem Formulation for Biopesticides: Emma Babij
Canadian Perspective on Problem Formulation for Biopesticides: Emma BabijCanadian Perspective on Problem Formulation for Biopesticides: Emma Babij
Canadian Perspective on Problem Formulation for Biopesticides: Emma BabijOECD Environment
 
Problem Formulation as an Ecological Testing and Assessment Tool for Microbia...
Problem Formulation as an Ecological Testing and Assessment Tool for Microbia...Problem Formulation as an Ecological Testing and Assessment Tool for Microbia...
Problem Formulation as an Ecological Testing and Assessment Tool for Microbia...OECD Environment
 
History, principles and use for biopesticide risk assessment: Boet Glandorf a...
History, principles and use for biopesticide risk assessment: Boet Glandorf a...History, principles and use for biopesticide risk assessment: Boet Glandorf a...
History, principles and use for biopesticide risk assessment: Boet Glandorf a...OECD Environment
 
CCXG global forum, April 2025, Key takeaways
CCXG global forum, April 2025, Key takeawaysCCXG global forum, April 2025, Key takeaways
CCXG global forum, April 2025, Key takeawaysOECD Environment
 
CCXG global forum, April 2024, Mentimeter results
CCXG global forum, April 2024, Mentimeter resultsCCXG global forum, April 2024, Mentimeter results
CCXG global forum, April 2024, Mentimeter resultsOECD Environment
 
CCXG global forum, April 2024, Chiara Falduto
CCXG global forum, April 2024, Chiara FaldutoCCXG global forum, April 2024, Chiara Falduto
CCXG global forum, April 2024, Chiara FaldutoOECD Environment
 
CCXG global forum, April 2024, Siddharth Singh
CCXG global forum, April 2024, Siddharth SinghCCXG global forum, April 2024, Siddharth Singh
CCXG global forum, April 2024, Siddharth SinghOECD Environment
 
CCXG global forum, April 2024, Geraldine Ang
CCXG global forum, April 2024, Geraldine AngCCXG global forum, April 2024, Geraldine Ang
CCXG global forum, April 2024, Geraldine AngOECD Environment
 
CCXG global forum, April 2024, Raphaël Jachnik
CCXG global forum, April 2024, Raphaël JachnikCCXG global forum, April 2024, Raphaël Jachnik
CCXG global forum, April 2024, Raphaël JachnikOECD Environment
 

Plus de OECD Environment (20)

GREEN Action Task Force - Full Presentations.pdf
GREEN Action Task Force - Full Presentations.pdfGREEN Action Task Force - Full Presentations.pdf
GREEN Action Task Force - Full Presentations.pdf
 
Case Study: Peptides-based Plant Protection Product (harpin proteins*) by Ros...
Case Study: Peptides-based Plant Protection Product (harpin proteins*) by Ros...Case Study: Peptides-based Plant Protection Product (harpin proteins*) by Ros...
Case Study: Peptides-based Plant Protection Product (harpin proteins*) by Ros...
 
CLE Contribution on the Assessment of Innovative Biochemicals in the EU Statu...
CLE Contribution on the Assessment of Innovative Biochemicals in the EU Statu...CLE Contribution on the Assessment of Innovative Biochemicals in the EU Statu...
CLE Contribution on the Assessment of Innovative Biochemicals in the EU Statu...
 
Additional Considerations for Pesticide Formulations Containing Microbial Pes...
Additional Considerations for Pesticide Formulations Containing Microbial Pes...Additional Considerations for Pesticide Formulations Containing Microbial Pes...
Additional Considerations for Pesticide Formulations Containing Microbial Pes...
 
Role of genome sequencing (WGS) in microbial biopesticides safety assessment ...
Role of genome sequencing (WGS) in microbial biopesticides safety assessment ...Role of genome sequencing (WGS) in microbial biopesticides safety assessment ...
Role of genome sequencing (WGS) in microbial biopesticides safety assessment ...
 
Considerations for Problem Formulation for Human Health Safety Assessments of...
Considerations for Problem Formulation for Human Health Safety Assessments of...Considerations for Problem Formulation for Human Health Safety Assessments of...
Considerations for Problem Formulation for Human Health Safety Assessments of...
 
How to Identify and Quantify Mixtures What is Essential to Know for Risk Asse...
How to Identify and Quantify Mixtures What is Essential to Know for Risk Asse...How to Identify and Quantify Mixtures What is Essential to Know for Risk Asse...
How to Identify and Quantify Mixtures What is Essential to Know for Risk Asse...
 
APVMA outcome-focussed approach to data requirements to support registration ...
APVMA outcome-focussed approach to data requirements to support registration ...APVMA outcome-focussed approach to data requirements to support registration ...
APVMA outcome-focussed approach to data requirements to support registration ...
 
The U.S. Perspective on Problem Formulation for Biopesticides: Shannon BORGES
The U.S. Perspective on Problem Formulation for Biopesticides: Shannon BORGESThe U.S. Perspective on Problem Formulation for Biopesticides: Shannon BORGES
The U.S. Perspective on Problem Formulation for Biopesticides: Shannon BORGES
 
Problem formulation for environmental risk assessment – Finnish case study: ...
Problem formulation for environmental risk assessment – Finnish case study:  ...Problem formulation for environmental risk assessment – Finnish case study:  ...
Problem formulation for environmental risk assessment – Finnish case study: ...
 
Problem formulation for environmental risk assessment in the context of EC Re...
Problem formulation for environmental risk assessment in the context of EC Re...Problem formulation for environmental risk assessment in the context of EC Re...
Problem formulation for environmental risk assessment in the context of EC Re...
 
Canadian Perspective on Problem Formulation for Biopesticides: Emma Babij
Canadian Perspective on Problem Formulation for Biopesticides: Emma BabijCanadian Perspective on Problem Formulation for Biopesticides: Emma Babij
Canadian Perspective on Problem Formulation for Biopesticides: Emma Babij
 
Problem Formulation as an Ecological Testing and Assessment Tool for Microbia...
Problem Formulation as an Ecological Testing and Assessment Tool for Microbia...Problem Formulation as an Ecological Testing and Assessment Tool for Microbia...
Problem Formulation as an Ecological Testing and Assessment Tool for Microbia...
 
History, principles and use for biopesticide risk assessment: Boet Glandorf a...
History, principles and use for biopesticide risk assessment: Boet Glandorf a...History, principles and use for biopesticide risk assessment: Boet Glandorf a...
History, principles and use for biopesticide risk assessment: Boet Glandorf a...
 
CCXG global forum, April 2025, Key takeaways
CCXG global forum, April 2025, Key takeawaysCCXG global forum, April 2025, Key takeaways
CCXG global forum, April 2025, Key takeaways
 
CCXG global forum, April 2024, Mentimeter results
CCXG global forum, April 2024, Mentimeter resultsCCXG global forum, April 2024, Mentimeter results
CCXG global forum, April 2024, Mentimeter results
 
CCXG global forum, April 2024, Chiara Falduto
CCXG global forum, April 2024, Chiara FaldutoCCXG global forum, April 2024, Chiara Falduto
CCXG global forum, April 2024, Chiara Falduto
 
CCXG global forum, April 2024, Siddharth Singh
CCXG global forum, April 2024, Siddharth SinghCCXG global forum, April 2024, Siddharth Singh
CCXG global forum, April 2024, Siddharth Singh
 
CCXG global forum, April 2024, Geraldine Ang
CCXG global forum, April 2024, Geraldine AngCCXG global forum, April 2024, Geraldine Ang
CCXG global forum, April 2024, Geraldine Ang
 
CCXG global forum, April 2024, Raphaël Jachnik
CCXG global forum, April 2024, Raphaël JachnikCCXG global forum, April 2024, Raphaël Jachnik
CCXG global forum, April 2024, Raphaël Jachnik
 

Dernier

The Most Attractive Pune Call Girls Shirwal 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Shirwal 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Shirwal 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Shirwal 8250192130 Will You Miss This Cha...ranjana rawat
 
(ANAYA) Call Girls Hadapsar ( 7001035870 ) HI-Fi Pune Escorts Service
(ANAYA) Call Girls Hadapsar ( 7001035870 ) HI-Fi Pune Escorts Service(ANAYA) Call Girls Hadapsar ( 7001035870 ) HI-Fi Pune Escorts Service
(ANAYA) Call Girls Hadapsar ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
(PARI) Viman Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...
(PARI) Viman Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...(PARI) Viman Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...
(PARI) Viman Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...ranjana rawat
 
VIP Call Girls Saharanpur Aaradhya 8250192130 Independent Escort Service Saha...
VIP Call Girls Saharanpur Aaradhya 8250192130 Independent Escort Service Saha...VIP Call Girls Saharanpur Aaradhya 8250192130 Independent Escort Service Saha...
VIP Call Girls Saharanpur Aaradhya 8250192130 Independent Escort Service Saha...Suhani Kapoor
 
(DIYA) Call Girls Sinhagad Road ( 7001035870 ) HI-Fi Pune Escorts Service
(DIYA) Call Girls Sinhagad Road ( 7001035870 ) HI-Fi Pune Escorts Service(DIYA) Call Girls Sinhagad Road ( 7001035870 ) HI-Fi Pune Escorts Service
(DIYA) Call Girls Sinhagad Road ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
VIP Kolkata Call Girl Kalighat 👉 8250192130 Available With Room
VIP Kolkata Call Girl Kalighat 👉 8250192130  Available With RoomVIP Kolkata Call Girl Kalighat 👉 8250192130  Available With Room
VIP Kolkata Call Girl Kalighat 👉 8250192130 Available With Roomdivyansh0kumar0
 
VIP Call Girls Service Chaitanyapuri Hyderabad Call +91-8250192130
VIP Call Girls Service Chaitanyapuri Hyderabad Call +91-8250192130VIP Call Girls Service Chaitanyapuri Hyderabad Call +91-8250192130
VIP Call Girls Service Chaitanyapuri Hyderabad Call +91-8250192130Suhani Kapoor
 
(NANDITA) Hadapsar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...
(NANDITA) Hadapsar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...(NANDITA) Hadapsar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...
(NANDITA) Hadapsar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...ranjana rawat
 
DENR EPR Law Compliance Updates April 2024
DENR EPR Law Compliance Updates April 2024DENR EPR Law Compliance Updates April 2024
DENR EPR Law Compliance Updates April 2024itadmin50
 
VVIP Pune Call Girls Koregaon Park (7001035870) Pune Escorts Nearby with Comp...
VVIP Pune Call Girls Koregaon Park (7001035870) Pune Escorts Nearby with Comp...VVIP Pune Call Girls Koregaon Park (7001035870) Pune Escorts Nearby with Comp...
VVIP Pune Call Girls Koregaon Park (7001035870) Pune Escorts Nearby with Comp...Call Girls in Nagpur High Profile
 
Call Girls In Faridabad(Ballabgarh) Book ☎ 8168257667, @4999
Call Girls In Faridabad(Ballabgarh) Book ☎ 8168257667, @4999Call Girls In Faridabad(Ballabgarh) Book ☎ 8168257667, @4999
Call Girls In Faridabad(Ballabgarh) Book ☎ 8168257667, @4999Tina Ji
 
Mumbai Call Girls, 💞 Prity 9892124323, Navi Mumbai Call girls
Mumbai Call Girls, 💞  Prity 9892124323, Navi Mumbai Call girlsMumbai Call Girls, 💞  Prity 9892124323, Navi Mumbai Call girls
Mumbai Call Girls, 💞 Prity 9892124323, Navi Mumbai Call girlsPooja Nehwal
 
Sustainable Clothing Strategies and Challenges
Sustainable Clothing Strategies and ChallengesSustainable Clothing Strategies and Challenges
Sustainable Clothing Strategies and ChallengesDr. Salem Baidas
 
Horizon Net Zero Dawn – keynote slides by Ben Abraham
Horizon Net Zero Dawn – keynote slides by Ben AbrahamHorizon Net Zero Dawn – keynote slides by Ben Abraham
Horizon Net Zero Dawn – keynote slides by Ben Abrahamssuserbb03ff
 
Call Girls South Delhi Delhi reach out to us at ☎ 9711199012
Call Girls South Delhi Delhi reach out to us at ☎ 9711199012Call Girls South Delhi Delhi reach out to us at ☎ 9711199012
Call Girls South Delhi Delhi reach out to us at ☎ 9711199012sapnasaifi408
 

Dernier (20)

The Most Attractive Pune Call Girls Shirwal 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Shirwal 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Shirwal 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Shirwal 8250192130 Will You Miss This Cha...
 
(ANAYA) Call Girls Hadapsar ( 7001035870 ) HI-Fi Pune Escorts Service
(ANAYA) Call Girls Hadapsar ( 7001035870 ) HI-Fi Pune Escorts Service(ANAYA) Call Girls Hadapsar ( 7001035870 ) HI-Fi Pune Escorts Service
(ANAYA) Call Girls Hadapsar ( 7001035870 ) HI-Fi Pune Escorts Service
 
E Waste Management
E Waste ManagementE Waste Management
E Waste Management
 
(PARI) Viman Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...
(PARI) Viman Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...(PARI) Viman Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...
(PARI) Viman Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...
 
young Whatsapp Call Girls in Delhi Cantt🔝 9953056974 🔝 escort service
young Whatsapp Call Girls in Delhi Cantt🔝 9953056974 🔝 escort serviceyoung Whatsapp Call Girls in Delhi Cantt🔝 9953056974 🔝 escort service
young Whatsapp Call Girls in Delhi Cantt🔝 9953056974 🔝 escort service
 
VIP Call Girls Saharanpur Aaradhya 8250192130 Independent Escort Service Saha...
VIP Call Girls Saharanpur Aaradhya 8250192130 Independent Escort Service Saha...VIP Call Girls Saharanpur Aaradhya 8250192130 Independent Escort Service Saha...
VIP Call Girls Saharanpur Aaradhya 8250192130 Independent Escort Service Saha...
 
Green Marketing
Green MarketingGreen Marketing
Green Marketing
 
(DIYA) Call Girls Sinhagad Road ( 7001035870 ) HI-Fi Pune Escorts Service
(DIYA) Call Girls Sinhagad Road ( 7001035870 ) HI-Fi Pune Escorts Service(DIYA) Call Girls Sinhagad Road ( 7001035870 ) HI-Fi Pune Escorts Service
(DIYA) Call Girls Sinhagad Road ( 7001035870 ) HI-Fi Pune Escorts Service
 
VIP Kolkata Call Girl Kalighat 👉 8250192130 Available With Room
VIP Kolkata Call Girl Kalighat 👉 8250192130  Available With RoomVIP Kolkata Call Girl Kalighat 👉 8250192130  Available With Room
VIP Kolkata Call Girl Kalighat 👉 8250192130 Available With Room
 
VIP Call Girls Service Chaitanyapuri Hyderabad Call +91-8250192130
VIP Call Girls Service Chaitanyapuri Hyderabad Call +91-8250192130VIP Call Girls Service Chaitanyapuri Hyderabad Call +91-8250192130
VIP Call Girls Service Chaitanyapuri Hyderabad Call +91-8250192130
 
(NANDITA) Hadapsar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...
(NANDITA) Hadapsar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...(NANDITA) Hadapsar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...
(NANDITA) Hadapsar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...
 
DENR EPR Law Compliance Updates April 2024
DENR EPR Law Compliance Updates April 2024DENR EPR Law Compliance Updates April 2024
DENR EPR Law Compliance Updates April 2024
 
VVIP Pune Call Girls Koregaon Park (7001035870) Pune Escorts Nearby with Comp...
VVIP Pune Call Girls Koregaon Park (7001035870) Pune Escorts Nearby with Comp...VVIP Pune Call Girls Koregaon Park (7001035870) Pune Escorts Nearby with Comp...
VVIP Pune Call Girls Koregaon Park (7001035870) Pune Escorts Nearby with Comp...
 
Call Girls In Faridabad(Ballabgarh) Book ☎ 8168257667, @4999
Call Girls In Faridabad(Ballabgarh) Book ☎ 8168257667, @4999Call Girls In Faridabad(Ballabgarh) Book ☎ 8168257667, @4999
Call Girls In Faridabad(Ballabgarh) Book ☎ 8168257667, @4999
 
Gandhi Nagar (Delhi) 9953330565 Escorts, Call Girls Services
Gandhi Nagar (Delhi) 9953330565 Escorts, Call Girls ServicesGandhi Nagar (Delhi) 9953330565 Escorts, Call Girls Services
Gandhi Nagar (Delhi) 9953330565 Escorts, Call Girls Services
 
Mumbai Call Girls, 💞 Prity 9892124323, Navi Mumbai Call girls
Mumbai Call Girls, 💞  Prity 9892124323, Navi Mumbai Call girlsMumbai Call Girls, 💞  Prity 9892124323, Navi Mumbai Call girls
Mumbai Call Girls, 💞 Prity 9892124323, Navi Mumbai Call girls
 
Sustainable Clothing Strategies and Challenges
Sustainable Clothing Strategies and ChallengesSustainable Clothing Strategies and Challenges
Sustainable Clothing Strategies and Challenges
 
Horizon Net Zero Dawn – keynote slides by Ben Abraham
Horizon Net Zero Dawn – keynote slides by Ben AbrahamHorizon Net Zero Dawn – keynote slides by Ben Abraham
Horizon Net Zero Dawn – keynote slides by Ben Abraham
 
Call Girls South Delhi Delhi reach out to us at ☎ 9711199012
Call Girls South Delhi Delhi reach out to us at ☎ 9711199012Call Girls South Delhi Delhi reach out to us at ☎ 9711199012
Call Girls South Delhi Delhi reach out to us at ☎ 9711199012
 
Sustainable Packaging
Sustainable PackagingSustainable Packaging
Sustainable Packaging
 

Main obstacles and LCOE of wind power in Georgia

  • 1. MAIN OBSTACELS FOR RES IN GEORIGA
  • 2. 2 THE CONTENT Threats and Weaknesses Local Component Requirement LCOE of Wind PP GIG Case Study
  • 3. 3 TREAT: Policy Uncertainty Lack of long-term policy in Georgia for spurring investor confidence. There is no differentiation between Hydro and non-Hydro Renewables. Currently, there is a cap for PPA tariffs introduced under the memorandum with IMF: 6 USDc, 8 Months. TWO PRIMARY PROBLMS with NON-HYDRO RENEWABLES High Initial Cost, Low Capacity Factor, Policy Uncertainty WEAKNESS: High Cost By and large, RES have a high installation cost amplified by a low capacity factor that makes them less competitive in countries with a high discount rate. Although the current WACC equals to 13.75%, it is anticipated that for the year 2017 Georgia’s WACC will be in range 14-17%
  • 4. 4 • Capital Cost (Grid Connection included) – 1300 - 1700 USD/MW • O&M - 0.6 - 1.2 USDc/kWh • Capacity Factor – 35% - 45% • Degradation Rate - 0.3% per annum • Discounting Factor, WACC - 14.3%, 15.8%, 17.8% (Energy Regulators Regional Association, February 2017) • WPP Life time- 20 years LEVELIZED COST OF ELECTRICITY for WIND in Georgia INPUT PARAMETERS Levelized Cost of Electricity = ∑ 𝑪𝑪𝑪𝑪𝑪𝑪𝑪𝑪𝑪𝑪 +𝑮𝑮𝑮𝑮𝑮𝑮 𝑮𝑮 𝑪𝑪𝑪𝑪𝑪𝑪𝑪𝑪𝑪𝑪𝑪𝑪𝑪𝑪𝑪𝑪𝑪𝑪 𝑪𝑪 +𝑶𝑶&𝑴𝑴+𝑭𝑭𝑭𝑭𝑭𝑭𝑭𝑭 𝟏𝟏+𝒓𝒓 𝒕𝒕 ∑ 𝑬𝑬𝑬𝑬𝑬𝑬𝑬𝑬𝑬𝑬𝑬𝑬𝑬𝑬𝑬𝑬𝑬𝑬𝑬𝑬𝑬𝑬 𝑶𝑶𝑶𝑶𝑶𝑶𝑶𝑶𝑶𝑶𝑶𝑶∗ 𝟏𝟏−𝑫𝑫𝑫𝑫 𝒕𝒕 𝟏𝟏+𝒓𝒓 𝒕𝒕
  • 5. 5 LEVELIZED COST OF ELECTRICITY for WIND in GEORGIA Results of Stochastic Sensitivity Analysis WACC=14.3% WACC=15.8% WACC=17.8% LCOE = 6.11 USDc LCOE = 6.52 USDc LCOE = 7.08 USDc LCOE, Stochastic Sensitivity Analysis with r=14.3% LCOE Density 0.050 0.055 0.060 0.065 0.070 0.075 0.080 0102030405060 Mean LCOE, 6.11 USDc Kernel Density LCOE, Stochastic Sensitivity Analysis with r=15.8% LCOE Density 0.050 0.055 0.060 0.065 0.070 0.075 0.080 0.085 0102030405060 Mean LCOE, 6.52 USDc Kernel Density LCOE, Stochastic Sensitivity Analysis with r=17.8% LCOE Density 0.06 0.07 0.08 0.09 01020304050 Mean LCOE, 7.08 USDc Kernel Density
  • 6. 6 MICRO POWER PLANT Net Metering Micro Power Plant with Install Capacity under 100 KW (Law on Electricity and Natural Gas) • The owner of photovoltaic panels can supply generated electricity to the system, and purchase power from the system. • In cases when the monthly balance (electricity produced minus electricity consumed) is negative, the household pays for the net amount of electricity consumed. • In the opposite case, when the monthly balance is positive, the household is paid by Utility Company.
  • 7. 7 GIG CASE STUDY 100 KW Roof Solar Panels • Cost (Including roof preparation works) ≈ 2.2 USDc per Watt, 100KW ≈ 220,000USD • Simulated Production: 172.6 MWh/year • Year 10: Inventor Outlay, 45,000USD • O&M: 2400 USD per Annum • Tariff: 10 USDc ≈ 24 Tetri
  • 8. 8 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 -200000-150000-100000-500000 0 20 40 60 80 100 -150000-100000-500000 i% NPV 1.06 The law was adopted in April, 2016. Only 8 micro generation PP have been registered in GNERC so far. GIG CASE STUDY Results IRR = 1.06% (!) Payback = 21 years NPV (i=10%), = -104671.1 (!)
  • 9. 9 LOCAL CONTEN REQUIREMENT: Developing Green Economy in Georgia Employment, Taxes, Technology Transfer Employment Gains By requiring enterprises to use a certain proportion of inputs from local industries, proponents argue that employment will certainly increase Increased Tax Base LCR will lead to an increased tax base for governments because of a larger local manufacturing industry. This would allow countries to have more income, while developing a new industry Transfer of Technology and Knowledge Technology transfer as a result of LCR comes from learning-by-doing and capacity building in domestic supply. Although it is not patent- related, this knowledge of technology and how to operate it is an important component in reaching global green industrial growth. Local content requirements (LCR) are policy measures that require foreign or domestic investors to source a certain percentage of intermediate goods from local manufacturers or producers.
  • 10. 10 Feed in Tariff plus LC The Ministry of Energy and Natural Resources determined the baseline feed-in tariff for wind energy at 7.3 USD cent/ kWh with an extra bonus for locally manufactured component which is an extra 3.7 USD cent/ kWh: • Bonus for Blade 0.8 USD cent/ kWh, • Bonus for Generator/ Power Electronics 1 USD cent/ kWh, • Bonus for Turbine tower 0.6 USD cent/ kWh, • Bonus for all mechanical equipment in rotor and nacelle is 1.3 USD cent/ kWh. Tender with LCR The Ministry of Energy and Natural Resources invited interested and eligible parties for tender on the construction of 1 GW installed capacities of Wind PPs with 65% LC including all nececcary row materials. The tariff should be below 7 USDc, however 15 years power purchasing is guaranteed. LCR in Turkey: Case FiT plus LC Bonus, Tendering with LCR
  • 11. 11 LCR in Georgia Spare Capacity at KAMP GIG Spare Capacity at Kutaisi Auto Mechanical Plant  60 000 sq. meter under the single roof;  Experienced workers;  Not far from Black Sea ports.
  • 12. 12