Procurement System in the Indian
Construction Industry: Issues and Remedies
Pavitra Sharma
CON 567- Advanced Procurement Systems - spring 2014
Dr. Dean T. Kashiwagi
Contents
Introduction-.................................................................................................................................................1
Problems Identified- .....................................................................................................................................2
The Best Value Approach (Kashiwagi, 2014)- ...............................................................................................2
Differences identified between the traditional system of procurement in India and the Best Value
Approach-......................................................................................................................................................4
Proposed Solution-........................................................................................................................................5
Conclusion-....................................................................................................................................................5
Bibliography ..................................................................................................................................................6
CON 567
Pavitra Sharma
1
Procurement System in the Indian
Construction Industry: Issues and
Remedies
Introduction-
Procurement in the Indian Construction Industry especially in the public sector is done through
the traditional contracting, that includes awards to the contractor with the lowest bid. Particularly
for public sector, at least 10 to 12 agencies are involved in the process of deciding the necessity
to procure (Jain). Huge amount of cost, paperwork and manpower is expended in the
conceptualization of the process. According to Jain, the recent estimates of the cost of initiations
are as follows (Jain)-
 Central Government: 30-40%
 State Government: 40-60%
 Public Sector Undertakings: 15-25%
 Public Ltd. companies: 5-7% of the value of goods/ (with private holding) services
procured.
 Private Ltd. Companies: 1-2%
Stated below are the principles concerning the owner as envisioned by Construction Industry
Development Council (Construction Industry Development Council; Jain)-
 Principle 1- The most competent agency should be awarded the work.
 Principle 2- The work should be executed at the most economical price.
 Principle 3- Works should progress on schedule and its quality should adhere to the
standards specified.
 Principle 4- Procurement procedure should be transparent.
 Principle 5- Owner’s representatives are competent, experienced and good managers of
work.
Stated below are the principles concerning the contractor as envisioned by Construction Industry
Development Council (Construction Industry Development Council; Jain)-
 Principle 6- Contractor possesses requisite experience in the type of work taken up.
 Principle 7- The Contractor has adequate resources for executing the work.
 Principle 8- The Contractor quotes a workable price.
 Principle 9- The Contractor has the corporate strength and resilience to overcome adverse
situations if and when they may arise.
CON 567
Pavitra Sharma
2
Problems Identified-
The reality of situation in the system of procurement is completely contradictory to principles
stated by the Construction Industry Development Council (CIDC). There is no transparency in
the system. The work is awarded to the lowest bidder. The vendors lack expertise. These are to
name a few but there lies a bigger picture.
Principle 1 and Principle 2- During the pre-bid phase, the contract is awarded to the vendor
with the lowest bid. Factors like specific past experience on similar project, performance data,
customer satisfaction and the works in hand is often ignored during the process. CIDC
emphasizes to follow pre-qualification of contractors but due the prevailing system of envelopes
and no interview during this phase, the system fails. Therefore, the owners revert back to the pre
–bid selection of the contractor with lowest bid.
Principle 3- The vendors quote unrealistic and lower bid to acquire the project which in turn
results in time and cost overruns. Therefore, the quality of the project suffers.
Principle 4- Since the lowest bidder is awarded the project during the pre-bid selection, the
credibility and expertize of the vendor is often hidden from the owner. Hence, the system
becomes opaque.
Principle 5- The owner’s team of engineers and managers lack expertise and management
skills which results in weaker quality and schedule control measures. Hence, the project suffers
in quality, time and cost overruns.
Principle 6- The contractor with the lowest bid during the pre- bid selection is awarded the
project. The expertise of the contractor, performance data like cost and time deviations, customer
satisfaction is altogether neglected.
Principle 7- In house resources are minimal in most cases. Contractors rely mostly on
temporary hiring of resources which is seldom preplanned in advance. As a result there is delay
in schedule and cost overruns. Also, the contractors lack expertise which makes it difficult to
identify and mitigate risk.
Principle 8- The field of contracting is highly unregulated in India. A contractor can bid a
certain lowest amount without the financial backing, without identifying the scope of work and
also without adequate resources.
Principle 9- When faced with adverse situations, these contractors adopt short cuts to cope up
with the work as they lack expertize, financial backing and adequate resources.
The Best Value Approach (Kashiwagi, 2014)-
The Best Value based Performance Information Procurement System (PIPS) creates an
environment that includes-
 Client does not manage, direct and control the vendor.
 The vendor is the expert.
 The client utilizes the expertise of the vendor.
CON 567
Pavitra Sharma
3
 Minimizes time and cost overruns.
 Forces accountability
 Identification and mitigation of risk.
 Minimal decision making.
 Transparency
 Minimized transactions.
 Minimizes bureaucracy.
 Protects the expert and the owner by maximizing profit and minimizing project cost.
The Best Value PIPS propose four phases-
1. Pre-qualification
2. Selection
3. Clarification
4. Execution
The Pre-Qualification Phase (Phase 0) - The goal of this phase is to increase
competitiveness, to create transparency and identify vendors according to the minimum criteria
set by the owner based on expertize, past performance and experience on similar project.
The Selection Phase (Phase 1) - This phase identifies the Best Value (BV) vendor from the
competing vendors. The BV vendor is selected based on the level of expertise and not based on
the lowest price quote or the best scope of work. The expertise criteria are project capability,
identification of risk and its mitigation plan, value added, cost and an interview. This phase also
utilizes four filters i.e. project capability, interview, prioritization and dominance check, before
moving the BV vendor into the clarification phase.
The Clarification Phase (Phase 2) - This is the most important phase of all. In this phase
the BV vendor is forced to clarify their plan and determine the scope of their proposal. They
must answer any technical questions to show their technical competence. They must provide the
following-
 Detailed project schedule.
 Identification of areas out of their control.
 Risk identification and mitigation.
 Measurement of risk performance.
 Creation of milestone schedule.
 Creation of weekly risk report (WRR) which includes a risk plan, risk mitigation plan
(RMP) and performance measurements.
The clarification phase provides an opportunity to the vendor to identify itself as a BV vendor for
the owner. If the offer is unacceptable to the owner then the next prioritized BV vendor is
brought into the clarification phase.
The Execution Phase (Phase 3) - A contract is signed after the BV vendor is identified
during the clarification phase. The BV vendor delivers its services and mitigates risk in
accordance to the WRR. The role of the client or owner here is to assure that a quality service is
provided by the BV vendor without time and cost deviations with the help of WRR.
CON 567
Pavitra Sharma
4
The purpose of these reports is to-
1. Create transparency.
2. Communicate information quickly and in a dominant fashion.
3. Assign accountability.
Differences identified between the traditional system of procurement in
India and the Best Value Approach-
Traditional System Best Value Approach
Pre-bid selection of the vendor. Four phases of selection.
Selection based on lowest bid. Selection based of expertize.
Price based industry structure. Value based environment.
No transparency. Complete transparency.
Scope of the project is determined by the
owner.
Scope of the project is determined by the BV
vendor.
Owner exercises management, direction and
control.
Owner exercises quality control and assurance
with help of WRR.
No performance measurement. Performance measurement is the key.
Vendor exercises owner’s desires. Owner utilizes the vendor’s expertize.
No risk identification beforehand and its
mitigation during the execution.
Complete risk identification and mitigation
plan before execution.
Aim is to maximize profit by maximizing
project cost.
Aim is to maximize profit with lowest possible
project cost.
A win-lose environment.
A win-win environment for the owner as well
as the BV vendor.
No accountability of the vendor. Forces accountability.
Many transactions and decision making during
the execution.
Least transactions and decision making during
the execution as everything is pre-planned.
Overall project cost increases.
Overall project cost remains within the
deviations stated by the vendor.
Owner remains accountable of the risk created
by the vendor.
Encourages transfer of risk to the expert
vendor.
Requires more project managers in the owner’s
management team for MDC.
Requires fewer project managers in the
owner’s management team.
Decreases the efficiency of the expert vendor. Maximizes the efficiency of the expert vendor.
A stressful environment. No stress environment.
CON 567
Pavitra Sharma
5
Proposed Solution-
For the vendor/contractor-
 Quoting realistic and best price during the bid.
 Provide dominant information about the past experience and related projects executed.
 Provide performance related information such as time deviations, cost deviations,
customer satisfaction.
 Identify the scope of the project.
 Identify risks that are within control as well as out of control before the execution.
 Mitigation plan of the risks identified before execution.
 Provide complete transparency to the owner before and during execution.
 Provide WRR’s during execution.
 Provide performance measurement reports during execution.
 Maximize profit by executing quality work with least time and cost deviations.
For the client/owner-
 Creation of value based environment with high competition.
 Stating clearly the level of expertise required for the project before the bidding process.
 Selection of the vendor based on the expertise.
 Recognizing that vendor is the expert.
 Accept or reject the scope of the project provided by the expert vendor.
 Provide a complete transparent and no influence environment to the vendor.
 Selection of the expert vendor with help of the four phases proposed by the PIPS
approach.
 Introduce complete transparency in the system.
 Exercise quality control and assurance based on the data provided by the expert vendor.
 Minimize transaction but exercise on-time transactions.
 No MDC and decision making.
 Provide a win-win environment.
Conclusion-
India Construction Industry is the second largest industry in the country after agriculture and
contributes to 11% of the country’s GDP. There exists immense potential for growth in the
coming years as India is one the fastest developing economies competing with the developed
counterparts. The prevailing system can be changed if the industry focuses on providing quality
work rather than maximizing profit. Experts and well educated staff should be employed by the
companies and not save money on staff salaries. Use of latest technology and performance
measurement matrices should be encouraged. Honesty and transparency should be thoroughly
exercised. Favoritism, political influence, emotion and self-interests should be discouraged. In
conclusion, the whole system should revolve around the expertise of the individual or the
company.
CON 567
Pavitra Sharma
6
Bibliography
Construction Industry Development Council. (n.d.).
Jain, R. (n.d.). System of procurement in construction works: Some flaws and their remedies.
Kashiwagi, D. T. (2014). Best Value Standard.

Contenu connexe

Tendances

Professional Practice 1 Assignment
Professional Practice 1 AssignmentProfessional Practice 1 Assignment
Professional Practice 1 AssignmentMelvin Lim
 
Construction Law Final Report
Construction Law Final ReportConstruction Law Final Report
Construction Law Final ReportArissa Loh
 
The architect as contract administrator a legal perspective - presentation ...
The architect as contract administrator   a legal perspective - presentation ...The architect as contract administrator   a legal perspective - presentation ...
The architect as contract administrator a legal perspective - presentation ...Zainab Zainordin
 
Certificates and payments
Certificates and paymentsCertificates and payments
Certificates and paymentsHafizul Mukhlis
 
Procurement Methods and their Application.
Procurement Methods and their Application.Procurement Methods and their Application.
Procurement Methods and their Application.Lilian Nwachukwu
 
Guide for Construction Contract Administrators
Guide for Construction Contract AdministratorsGuide for Construction Contract Administrators
Guide for Construction Contract AdministratorsSarah Fox
 
FIDIC Presentation-2016.pdf
FIDIC Presentation-2016.pdfFIDIC Presentation-2016.pdf
FIDIC Presentation-2016.pdfPachyCarmona1
 
Professional Practice 1 Tutorial 7
Professional Practice 1 Tutorial 7Professional Practice 1 Tutorial 7
Professional Practice 1 Tutorial 7ashleyyeap
 
Project management
Project managementProject management
Project managementBenjamin Tan
 
Training fidic moustafa ismail 2017 _ lec 4
Training fidic moustafa ismail  2017 _  lec 4Training fidic moustafa ismail  2017 _  lec 4
Training fidic moustafa ismail 2017 _ lec 4Moustafa Ismail Abu Dief
 
Contract Administration Presentation
Contract Administration PresentationContract Administration Presentation
Contract Administration PresentationYanet Ormeno
 
Construction Claims Explained
Construction Claims ExplainedConstruction Claims Explained
Construction Claims Explainedclaimsconsultancy
 
Cp 2 selection of contractor - pq and post q
Cp 2 selection of contractor - pq and post qCp 2 selection of contractor - pq and post q
Cp 2 selection of contractor - pq and post qumes manandhar
 
fidic-flow-chart.pptx
fidic-flow-chart.pptxfidic-flow-chart.pptx
fidic-flow-chart.pptxssuserb337ce1
 
Sectional completion and partial possession by employer PP2 Coursework 1
Sectional completion and partial possession by employer PP2 Coursework 1Sectional completion and partial possession by employer PP2 Coursework 1
Sectional completion and partial possession by employer PP2 Coursework 1Arissa Loh
 
A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 Pang Khai Shuen
 
Presentation - Construction Contract Dispute Resolution
Presentation - Construction Contract Dispute ResolutionPresentation - Construction Contract Dispute Resolution
Presentation - Construction Contract Dispute ResolutionJustin DeMerchant
 

Tendances (20)

Professional Practice 1 Assignment
Professional Practice 1 AssignmentProfessional Practice 1 Assignment
Professional Practice 1 Assignment
 
Construction Law Final Report
Construction Law Final ReportConstruction Law Final Report
Construction Law Final Report
 
The architect as contract administrator a legal perspective - presentation ...
The architect as contract administrator   a legal perspective - presentation ...The architect as contract administrator   a legal perspective - presentation ...
The architect as contract administrator a legal perspective - presentation ...
 
Certificates and payments
Certificates and paymentsCertificates and payments
Certificates and payments
 
Procurement Methods and their Application.
Procurement Methods and their Application.Procurement Methods and their Application.
Procurement Methods and their Application.
 
Guide for Construction Contract Administrators
Guide for Construction Contract AdministratorsGuide for Construction Contract Administrators
Guide for Construction Contract Administrators
 
FIDIC Presentation-2016.pdf
FIDIC Presentation-2016.pdfFIDIC Presentation-2016.pdf
FIDIC Presentation-2016.pdf
 
Professional Practice 1 Tutorial 7
Professional Practice 1 Tutorial 7Professional Practice 1 Tutorial 7
Professional Practice 1 Tutorial 7
 
Project management
Project managementProject management
Project management
 
Training fidic moustafa ismail 2017 _ lec 4
Training fidic moustafa ismail  2017 _  lec 4Training fidic moustafa ismail  2017 _  lec 4
Training fidic moustafa ismail 2017 _ lec 4
 
Contract Administration Presentation
Contract Administration PresentationContract Administration Presentation
Contract Administration Presentation
 
Construction Claims Explained
Construction Claims ExplainedConstruction Claims Explained
Construction Claims Explained
 
Cp 2 selection of contractor - pq and post q
Cp 2 selection of contractor - pq and post qCp 2 selection of contractor - pq and post q
Cp 2 selection of contractor - pq and post q
 
Contract management general
Contract management generalContract management general
Contract management general
 
fidic-flow-chart.pptx
fidic-flow-chart.pptxfidic-flow-chart.pptx
fidic-flow-chart.pptx
 
Contract management
Contract managementContract management
Contract management
 
Sectional completion and partial possession by employer PP2 Coursework 1
Sectional completion and partial possession by employer PP2 Coursework 1Sectional completion and partial possession by employer PP2 Coursework 1
Sectional completion and partial possession by employer PP2 Coursework 1
 
A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1
 
Presentation - Construction Contract Dispute Resolution
Presentation - Construction Contract Dispute ResolutionPresentation - Construction Contract Dispute Resolution
Presentation - Construction Contract Dispute Resolution
 
Bid Evaluation
Bid EvaluationBid Evaluation
Bid Evaluation
 

En vedette

Lecture 1 introduction to construction procurement process.
Lecture 1   introduction to construction procurement process.Lecture 1   introduction to construction procurement process.
Lecture 1 introduction to construction procurement process.Aszahari Aie
 
Guide to Construction Procurement Strategies
Guide to Construction Procurement StrategiesGuide to Construction Procurement Strategies
Guide to Construction Procurement StrategiesSarah Fox
 
Public Sector Construction Procurement Changes - Government Trial Projects
Public Sector Construction Procurement Changes - Government Trial ProjectsPublic Sector Construction Procurement Changes - Government Trial Projects
Public Sector Construction Procurement Changes - Government Trial ProjectsRob Garvey
 
Importance of Sustainable Procurement Practices
Importance of Sustainable Procurement PracticesImportance of Sustainable Procurement Practices
Importance of Sustainable Procurement PracticesBrickworkSourcing
 
Engineering Procurement & Construction Making India Brick by Brick
Engineering Procurement & Construction Making India Brick by BrickEngineering Procurement & Construction Making India Brick by Brick
Engineering Procurement & Construction Making India Brick by Brickelithomas202
 
Toronto Pearson Airport - Procurement Strategy Study
Toronto Pearson Airport - Procurement Strategy StudyToronto Pearson Airport - Procurement Strategy Study
Toronto Pearson Airport - Procurement Strategy StudyAhmed Mahmoud
 
Engineering, Procurement and Construction Contracts for Infrastructure Projec...
Engineering, Procurement and Construction Contracts for Infrastructure Projec...Engineering, Procurement and Construction Contracts for Infrastructure Projec...
Engineering, Procurement and Construction Contracts for Infrastructure Projec...John Buchovecky
 
Procurement Strategy by Derek Hendrikz
Procurement Strategy by Derek HendrikzProcurement Strategy by Derek Hendrikz
Procurement Strategy by Derek HendrikzDerek Hendrikz
 
Golden Book of e-Procurement Good Practices
Golden Book of e-Procurement Good PracticesGolden Book of e-Procurement Good Practices
Golden Book of e-Procurement Good PracticesNicolas Loozen
 
3 other methods of procurement
3 other methods of procurement3 other methods of procurement
3 other methods of procurementJoy Irman
 
Procurement Cost Saving Strategy " Procurement dari cost centre menjadi profit...
Procurement Cost Saving Strategy " Procurement dari cost centre menjadi profit...Procurement Cost Saving Strategy " Procurement dari cost centre menjadi profit...
Procurement Cost Saving Strategy " Procurement dari cost centre menjadi profit...Indonesian Procurement Society
 
Trends in public and private sector in india
Trends in public and private sector in indiaTrends in public and private sector in india
Trends in public and private sector in indiaAshutosh Gupta
 
Anatomy of a construction procurement a complex process in a changing market
Anatomy of a construction procurement a  complex process in a changing marketAnatomy of a construction procurement a  complex process in a changing market
Anatomy of a construction procurement a complex process in a changing marketLAZOVOY
 
Construction activities and Process
Construction activities and ProcessConstruction activities and Process
Construction activities and ProcessIbrahim Adhnan
 
What is Procurement
What is ProcurementWhat is Procurement
What is ProcurementFahad Ali
 

En vedette (20)

Lecture 1 introduction to construction procurement process.
Lecture 1   introduction to construction procurement process.Lecture 1   introduction to construction procurement process.
Lecture 1 introduction to construction procurement process.
 
Guide to Construction Procurement Strategies
Guide to Construction Procurement StrategiesGuide to Construction Procurement Strategies
Guide to Construction Procurement Strategies
 
Public Sector Construction Procurement Changes - Government Trial Projects
Public Sector Construction Procurement Changes - Government Trial ProjectsPublic Sector Construction Procurement Changes - Government Trial Projects
Public Sector Construction Procurement Changes - Government Trial Projects
 
Ppp
PppPpp
Ppp
 
Procurement process snippet
Procurement process snippetProcurement process snippet
Procurement process snippet
 
Importance of Sustainable Procurement Practices
Importance of Sustainable Procurement PracticesImportance of Sustainable Procurement Practices
Importance of Sustainable Procurement Practices
 
Engineering Procurement & Construction Making India Brick by Brick
Engineering Procurement & Construction Making India Brick by BrickEngineering Procurement & Construction Making India Brick by Brick
Engineering Procurement & Construction Making India Brick by Brick
 
Toronto Pearson Airport - Procurement Strategy Study
Toronto Pearson Airport - Procurement Strategy StudyToronto Pearson Airport - Procurement Strategy Study
Toronto Pearson Airport - Procurement Strategy Study
 
Engineering, Procurement and Construction Contracts for Infrastructure Projec...
Engineering, Procurement and Construction Contracts for Infrastructure Projec...Engineering, Procurement and Construction Contracts for Infrastructure Projec...
Engineering, Procurement and Construction Contracts for Infrastructure Projec...
 
5 Central Public Procurement Functions Identification, Combination, Separatio...
5 Central Public Procurement Functions Identification, Combination, Separatio...5 Central Public Procurement Functions Identification, Combination, Separatio...
5 Central Public Procurement Functions Identification, Combination, Separatio...
 
Procurement Strategy by Derek Hendrikz
Procurement Strategy by Derek HendrikzProcurement Strategy by Derek Hendrikz
Procurement Strategy by Derek Hendrikz
 
Golden Book of e-Procurement Good Practices
Golden Book of e-Procurement Good PracticesGolden Book of e-Procurement Good Practices
Golden Book of e-Procurement Good Practices
 
3 other methods of procurement
3 other methods of procurement3 other methods of procurement
3 other methods of procurement
 
Procurement Cost Saving Strategy " Procurement dari cost centre menjadi profit...
Procurement Cost Saving Strategy " Procurement dari cost centre menjadi profit...Procurement Cost Saving Strategy " Procurement dari cost centre menjadi profit...
Procurement Cost Saving Strategy " Procurement dari cost centre menjadi profit...
 
Trends in public and private sector in india
Trends in public and private sector in indiaTrends in public and private sector in india
Trends in public and private sector in india
 
e-Procurement in Indian Government
e-Procurement in Indian Governmente-Procurement in Indian Government
e-Procurement in Indian Government
 
Anatomy of a construction procurement a complex process in a changing market
Anatomy of a construction procurement a  complex process in a changing marketAnatomy of a construction procurement a  complex process in a changing market
Anatomy of a construction procurement a complex process in a changing market
 
Construction activities and Process
Construction activities and ProcessConstruction activities and Process
Construction activities and Process
 
What is Procurement
What is ProcurementWhat is Procurement
What is Procurement
 
E Procurement
E ProcurementE Procurement
E Procurement
 

Similaire à Procurement system in the Indian construction industry issues and remedies

Mb0049 project management
Mb0049   project managementMb0049   project management
Mb0049 project managementsmumbahelp
 
Mindavation - Requirements Enoughness - when is enough enough?
Mindavation - Requirements Enoughness - when is enough enough?Mindavation - Requirements Enoughness - when is enough enough?
Mindavation - Requirements Enoughness - when is enough enough?Haydn Thomas
 
Auditing projects in the early stages.pdf
Auditing projects in the early stages.pdfAuditing projects in the early stages.pdf
Auditing projects in the early stages.pdfAddisu15
 
INDEPEDENT OUTSOURCING ASSURANCE
INDEPEDENT OUTSOURCING ASSURANCEINDEPEDENT OUTSOURCING ASSURANCE
INDEPEDENT OUTSOURCING ASSURANCEArul Nambi
 
2 asca 2- purcasing [compatibility mode]
2 asca 2- purcasing [compatibility mode]2 asca 2- purcasing [compatibility mode]
2 asca 2- purcasing [compatibility mode]Firly Zulkifli
 
Procurement management-plan template
Procurement management-plan templateProcurement management-plan template
Procurement management-plan templateVivek Srivastava
 
Lecture-10-10052021-030135pm-29092022-070414pm.pptx
Lecture-10-10052021-030135pm-29092022-070414pm.pptxLecture-10-10052021-030135pm-29092022-070414pm.pptx
Lecture-10-10052021-030135pm-29092022-070414pm.pptxMuhammadAftab89
 
Gopinathramachandran 131008015755-phpapp02
Gopinathramachandran 131008015755-phpapp02Gopinathramachandran 131008015755-phpapp02
Gopinathramachandran 131008015755-phpapp02PMI_IREP_TP
 
Gopinath ramachandran
Gopinath ramachandranGopinath ramachandran
Gopinath ramachandranPMI2011
 
requirement gathering
requirement gatheringrequirement gathering
requirement gatheringSaeedMat
 
Operation and Production Management
Operation and Production ManagementOperation and Production Management
Operation and Production ManagementSeetal Daas
 
OM2_Lecture 11vvvhhbbjjbjdjjeebjrhvhuuhh
OM2_Lecture 11vvvhhbbjjbjdjjeebjrhvhuuhhOM2_Lecture 11vvvhhbbjjbjdjjeebjrhvhuuhh
OM2_Lecture 11vvvhhbbjjbjdjjeebjrhvhuuhhrammanoharjharupnaga
 
VENDOR PROCESS DEVELOPMENT
VENDOR PROCESS DEVELOPMENTVENDOR PROCESS DEVELOPMENT
VENDOR PROCESS DEVELOPMENTSWAPAN KUMAR ROY
 

Similaire à Procurement system in the Indian construction industry issues and remedies (20)

Mb0049 project management
Mb0049   project managementMb0049   project management
Mb0049 project management
 
Mindavation - Requirements Enoughness - when is enough enough?
Mindavation - Requirements Enoughness - when is enough enough?Mindavation - Requirements Enoughness - when is enough enough?
Mindavation - Requirements Enoughness - when is enough enough?
 
Auditing projects in the early stages.pdf
Auditing projects in the early stages.pdfAuditing projects in the early stages.pdf
Auditing projects in the early stages.pdf
 
Procurement evaluation-vivich
Procurement evaluation-vivichProcurement evaluation-vivich
Procurement evaluation-vivich
 
CHAPTER-ONE.pptx
CHAPTER-ONE.pptxCHAPTER-ONE.pptx
CHAPTER-ONE.pptx
 
Week 8
Week 8Week 8
Week 8
 
HOQ and SERVQUAL
HOQ and SERVQUALHOQ and SERVQUAL
HOQ and SERVQUAL
 
INDEPEDENT OUTSOURCING ASSURANCE
INDEPEDENT OUTSOURCING ASSURANCEINDEPEDENT OUTSOURCING ASSURANCE
INDEPEDENT OUTSOURCING ASSURANCE
 
2 asca 2- purcasing [compatibility mode]
2 asca 2- purcasing [compatibility mode]2 asca 2- purcasing [compatibility mode]
2 asca 2- purcasing [compatibility mode]
 
Procurement management-plan template
Procurement management-plan templateProcurement management-plan template
Procurement management-plan template
 
6. mba 206 project management assignment 2nd semester
6. mba 206 project management assignment 2nd semester6. mba 206 project management assignment 2nd semester
6. mba 206 project management assignment 2nd semester
 
Lecture-10-10052021-030135pm-29092022-070414pm.pptx
Lecture-10-10052021-030135pm-29092022-070414pm.pptxLecture-10-10052021-030135pm-29092022-070414pm.pptx
Lecture-10-10052021-030135pm-29092022-070414pm.pptx
 
Gopinathramachandran 131008015755-phpapp02
Gopinathramachandran 131008015755-phpapp02Gopinathramachandran 131008015755-phpapp02
Gopinathramachandran 131008015755-phpapp02
 
Gopinath ramachandran
Gopinath ramachandranGopinath ramachandran
Gopinath ramachandran
 
requirement gathering
requirement gatheringrequirement gathering
requirement gathering
 
Operation and Production Management
Operation and Production ManagementOperation and Production Management
Operation and Production Management
 
OM2_Lecture 11vvvhhbbjjbjdjjeebjrhvhuuhh
OM2_Lecture 11vvvhhbbjjbjdjjeebjrhvhuuhhOM2_Lecture 11vvvhhbbjjbjdjjeebjrhvhuuhh
OM2_Lecture 11vvvhhbbjjbjdjjeebjrhvhuuhh
 
Project/ Business life cycle methodology
Project/ Business life cycle methodologyProject/ Business life cycle methodology
Project/ Business life cycle methodology
 
Project Procurement Management
Project Procurement ManagementProject Procurement Management
Project Procurement Management
 
VENDOR PROCESS DEVELOPMENT
VENDOR PROCESS DEVELOPMENTVENDOR PROCESS DEVELOPMENT
VENDOR PROCESS DEVELOPMENT
 

Dernier

Purva Soukhyam in Guduvancheri Chennai.pdf
Purva Soukhyam in Guduvancheri Chennai.pdfPurva Soukhyam in Guduvancheri Chennai.pdf
Purva Soukhyam in Guduvancheri Chennai.pdfpritika141199
 
9990771857 Call Girls in Dwarka Sector 7 Delhi (Call Girls) Delhi
9990771857 Call Girls in Dwarka Sector 7 Delhi (Call Girls) Delhi9990771857 Call Girls in Dwarka Sector 7 Delhi (Call Girls) Delhi
9990771857 Call Girls in Dwarka Sector 7 Delhi (Call Girls) Delhidelhimodel235
 
Kolte Patil Kharadi Pune E Brochure.pdf
Kolte Patil Kharadi Pune E  Brochure.pdfKolte Patil Kharadi Pune E  Brochure.pdf
Kolte Patil Kharadi Pune E Brochure.pdfabbu831446
 
Low Rate ↬Call Girls in Trilokpuri Delhi ↫8447779280}Escorts Service In Delhi
Low Rate ↬Call Girls in Trilokpuri Delhi ↫8447779280}Escorts Service In DelhiLow Rate ↬Call Girls in Trilokpuri Delhi ↫8447779280}Escorts Service In Delhi
Low Rate ↬Call Girls in Trilokpuri Delhi ↫8447779280}Escorts Service In Delhiasmaqueen5
 
9990771857 Call Girls in Dwarka Sector 1 Delhi (Call Girls) Delhi
9990771857 Call Girls in Dwarka Sector 1 Delhi (Call Girls) Delhi9990771857 Call Girls in Dwarka Sector 1 Delhi (Call Girls) Delhi
9990771857 Call Girls in Dwarka Sector 1 Delhi (Call Girls) Delhidelhimodel235
 
Call Girls In Mayur Vihar Delhi ☆↫8447779280 ❤Escorts Service In Delhi
Call Girls In Mayur Vihar Delhi ☆↫8447779280 ❤Escorts Service In DelhiCall Girls In Mayur Vihar Delhi ☆↫8447779280 ❤Escorts Service In Delhi
Call Girls In Mayur Vihar Delhi ☆↫8447779280 ❤Escorts Service In Delhiasmaqueen5
 
Kohinoor Hinjewadi Phase 2 Pune E-Brochure.pdf
Kohinoor Hinjewadi Phase 2 Pune  E-Brochure.pdfKohinoor Hinjewadi Phase 2 Pune  E-Brochure.pdf
Kohinoor Hinjewadi Phase 2 Pune E-Brochure.pdfManishSaxena95
 
Mahindra Happinest Tathawade Pune Brochure.pdf
Mahindra Happinest Tathawade Pune Brochure.pdfMahindra Happinest Tathawade Pune Brochure.pdf
Mahindra Happinest Tathawade Pune Brochure.pdfBabyrudram
 
Maha Mauka Squarefeet Brochure |Maha Mauka Squarefeet PDF Brochure|
Maha Mauka Squarefeet Brochure |Maha Mauka Squarefeet PDF Brochure|Maha Mauka Squarefeet Brochure |Maha Mauka Squarefeet PDF Brochure|
Maha Mauka Squarefeet Brochure |Maha Mauka Squarefeet PDF Brochure|AkshayJoshi575980
 
Call Girls In Vasant Vihar Delhi 💯Call Us 🔝8264348440🔝
Call Girls In Vasant Vihar Delhi 💯Call Us 🔝8264348440🔝Call Girls In Vasant Vihar Delhi 💯Call Us 🔝8264348440🔝
Call Girls In Vasant Vihar Delhi 💯Call Us 🔝8264348440🔝soniya singh
 
call girls in ganesh nagar Delhi 8264348440 ✅ call girls ❤️
call girls in ganesh nagar Delhi 8264348440 ✅ call girls ❤️call girls in ganesh nagar Delhi 8264348440 ✅ call girls ❤️
call girls in ganesh nagar Delhi 8264348440 ✅ call girls ❤️soniya singh
 
TENANT SCREENING REPORT SERVICES​ How Tenant Screening Reports Work
TENANT SCREENING REPORT SERVICES​ How Tenant Screening Reports WorkTENANT SCREENING REPORT SERVICES​ How Tenant Screening Reports Work
TENANT SCREENING REPORT SERVICES​ How Tenant Screening Reports WorkTurbo Tenant
 
9990771857 Call Girls Dwarka Sector 9 Delhi (Call Girls ) Delhi
9990771857 Call Girls Dwarka Sector 9 Delhi (Call Girls ) Delhi9990771857 Call Girls Dwarka Sector 9 Delhi (Call Girls ) Delhi
9990771857 Call Girls Dwarka Sector 9 Delhi (Call Girls ) Delhidelhimodel235
 
Magarpatta Nova Elegance Mundhwa Pune E-Brochure.pdf
Magarpatta Nova Elegance Mundhwa Pune  E-Brochure.pdfMagarpatta Nova Elegance Mundhwa Pune  E-Brochure.pdf
Magarpatta Nova Elegance Mundhwa Pune E-Brochure.pdfManishSaxena95
 
9990771857 Call Girls in Dwarka Sector 3 Delhi (Call Girls) Delhi
9990771857 Call Girls in Dwarka Sector 3 Delhi (Call Girls) Delhi9990771857 Call Girls in Dwarka Sector 3 Delhi (Call Girls) Delhi
9990771857 Call Girls in Dwarka Sector 3 Delhi (Call Girls) Delhidelhimodel235
 
Greater Vancouver Realtors Statistics Package April 2024
Greater Vancouver Realtors Statistics Package April 2024Greater Vancouver Realtors Statistics Package April 2024
Greater Vancouver Realtors Statistics Package April 2024VickyAulakh1
 
Best Deal Virtual Space in Satya The Hive Tata Zudio 750 Sqft 1.89 Cr All inc...
Best Deal Virtual Space in Satya The Hive Tata Zudio 750 Sqft 1.89 Cr All inc...Best Deal Virtual Space in Satya The Hive Tata Zudio 750 Sqft 1.89 Cr All inc...
Best Deal Virtual Space in Satya The Hive Tata Zudio 750 Sqft 1.89 Cr All inc...ApartmentWala1
 
Call Girls in shastri nagar Delhi 8264348440 ✅ call girls ❤️
Call Girls in shastri nagar Delhi 8264348440 ✅ call girls ❤️Call Girls in shastri nagar Delhi 8264348440 ✅ call girls ❤️
Call Girls in shastri nagar Delhi 8264348440 ✅ call girls ❤️soniya singh
 
Shapoorji Pallonji Joyville Vista Pune | Spend Your Family Time Together
Shapoorji Pallonji Joyville Vista Pune | Spend Your Family Time TogetherShapoorji Pallonji Joyville Vista Pune | Spend Your Family Time Together
Shapoorji Pallonji Joyville Vista Pune | Spend Your Family Time Togetheraidasheikh47
 
Properties for Sale in Istanbul with Schools and Parks | Antalya Development
Properties for Sale in Istanbul with Schools and Parks | Antalya DevelopmentProperties for Sale in Istanbul with Schools and Parks | Antalya Development
Properties for Sale in Istanbul with Schools and Parks | Antalya DevelopmentAntalya Development
 

Dernier (20)

Purva Soukhyam in Guduvancheri Chennai.pdf
Purva Soukhyam in Guduvancheri Chennai.pdfPurva Soukhyam in Guduvancheri Chennai.pdf
Purva Soukhyam in Guduvancheri Chennai.pdf
 
9990771857 Call Girls in Dwarka Sector 7 Delhi (Call Girls) Delhi
9990771857 Call Girls in Dwarka Sector 7 Delhi (Call Girls) Delhi9990771857 Call Girls in Dwarka Sector 7 Delhi (Call Girls) Delhi
9990771857 Call Girls in Dwarka Sector 7 Delhi (Call Girls) Delhi
 
Kolte Patil Kharadi Pune E Brochure.pdf
Kolte Patil Kharadi Pune E  Brochure.pdfKolte Patil Kharadi Pune E  Brochure.pdf
Kolte Patil Kharadi Pune E Brochure.pdf
 
Low Rate ↬Call Girls in Trilokpuri Delhi ↫8447779280}Escorts Service In Delhi
Low Rate ↬Call Girls in Trilokpuri Delhi ↫8447779280}Escorts Service In DelhiLow Rate ↬Call Girls in Trilokpuri Delhi ↫8447779280}Escorts Service In Delhi
Low Rate ↬Call Girls in Trilokpuri Delhi ↫8447779280}Escorts Service In Delhi
 
9990771857 Call Girls in Dwarka Sector 1 Delhi (Call Girls) Delhi
9990771857 Call Girls in Dwarka Sector 1 Delhi (Call Girls) Delhi9990771857 Call Girls in Dwarka Sector 1 Delhi (Call Girls) Delhi
9990771857 Call Girls in Dwarka Sector 1 Delhi (Call Girls) Delhi
 
Call Girls In Mayur Vihar Delhi ☆↫8447779280 ❤Escorts Service In Delhi
Call Girls In Mayur Vihar Delhi ☆↫8447779280 ❤Escorts Service In DelhiCall Girls In Mayur Vihar Delhi ☆↫8447779280 ❤Escorts Service In Delhi
Call Girls In Mayur Vihar Delhi ☆↫8447779280 ❤Escorts Service In Delhi
 
Kohinoor Hinjewadi Phase 2 Pune E-Brochure.pdf
Kohinoor Hinjewadi Phase 2 Pune  E-Brochure.pdfKohinoor Hinjewadi Phase 2 Pune  E-Brochure.pdf
Kohinoor Hinjewadi Phase 2 Pune E-Brochure.pdf
 
Mahindra Happinest Tathawade Pune Brochure.pdf
Mahindra Happinest Tathawade Pune Brochure.pdfMahindra Happinest Tathawade Pune Brochure.pdf
Mahindra Happinest Tathawade Pune Brochure.pdf
 
Maha Mauka Squarefeet Brochure |Maha Mauka Squarefeet PDF Brochure|
Maha Mauka Squarefeet Brochure |Maha Mauka Squarefeet PDF Brochure|Maha Mauka Squarefeet Brochure |Maha Mauka Squarefeet PDF Brochure|
Maha Mauka Squarefeet Brochure |Maha Mauka Squarefeet PDF Brochure|
 
Call Girls In Vasant Vihar Delhi 💯Call Us 🔝8264348440🔝
Call Girls In Vasant Vihar Delhi 💯Call Us 🔝8264348440🔝Call Girls In Vasant Vihar Delhi 💯Call Us 🔝8264348440🔝
Call Girls In Vasant Vihar Delhi 💯Call Us 🔝8264348440🔝
 
call girls in ganesh nagar Delhi 8264348440 ✅ call girls ❤️
call girls in ganesh nagar Delhi 8264348440 ✅ call girls ❤️call girls in ganesh nagar Delhi 8264348440 ✅ call girls ❤️
call girls in ganesh nagar Delhi 8264348440 ✅ call girls ❤️
 
TENANT SCREENING REPORT SERVICES​ How Tenant Screening Reports Work
TENANT SCREENING REPORT SERVICES​ How Tenant Screening Reports WorkTENANT SCREENING REPORT SERVICES​ How Tenant Screening Reports Work
TENANT SCREENING REPORT SERVICES​ How Tenant Screening Reports Work
 
9990771857 Call Girls Dwarka Sector 9 Delhi (Call Girls ) Delhi
9990771857 Call Girls Dwarka Sector 9 Delhi (Call Girls ) Delhi9990771857 Call Girls Dwarka Sector 9 Delhi (Call Girls ) Delhi
9990771857 Call Girls Dwarka Sector 9 Delhi (Call Girls ) Delhi
 
Magarpatta Nova Elegance Mundhwa Pune E-Brochure.pdf
Magarpatta Nova Elegance Mundhwa Pune  E-Brochure.pdfMagarpatta Nova Elegance Mundhwa Pune  E-Brochure.pdf
Magarpatta Nova Elegance Mundhwa Pune E-Brochure.pdf
 
9990771857 Call Girls in Dwarka Sector 3 Delhi (Call Girls) Delhi
9990771857 Call Girls in Dwarka Sector 3 Delhi (Call Girls) Delhi9990771857 Call Girls in Dwarka Sector 3 Delhi (Call Girls) Delhi
9990771857 Call Girls in Dwarka Sector 3 Delhi (Call Girls) Delhi
 
Greater Vancouver Realtors Statistics Package April 2024
Greater Vancouver Realtors Statistics Package April 2024Greater Vancouver Realtors Statistics Package April 2024
Greater Vancouver Realtors Statistics Package April 2024
 
Best Deal Virtual Space in Satya The Hive Tata Zudio 750 Sqft 1.89 Cr All inc...
Best Deal Virtual Space in Satya The Hive Tata Zudio 750 Sqft 1.89 Cr All inc...Best Deal Virtual Space in Satya The Hive Tata Zudio 750 Sqft 1.89 Cr All inc...
Best Deal Virtual Space in Satya The Hive Tata Zudio 750 Sqft 1.89 Cr All inc...
 
Call Girls in shastri nagar Delhi 8264348440 ✅ call girls ❤️
Call Girls in shastri nagar Delhi 8264348440 ✅ call girls ❤️Call Girls in shastri nagar Delhi 8264348440 ✅ call girls ❤️
Call Girls in shastri nagar Delhi 8264348440 ✅ call girls ❤️
 
Shapoorji Pallonji Joyville Vista Pune | Spend Your Family Time Together
Shapoorji Pallonji Joyville Vista Pune | Spend Your Family Time TogetherShapoorji Pallonji Joyville Vista Pune | Spend Your Family Time Together
Shapoorji Pallonji Joyville Vista Pune | Spend Your Family Time Together
 
Properties for Sale in Istanbul with Schools and Parks | Antalya Development
Properties for Sale in Istanbul with Schools and Parks | Antalya DevelopmentProperties for Sale in Istanbul with Schools and Parks | Antalya Development
Properties for Sale in Istanbul with Schools and Parks | Antalya Development
 

Procurement system in the Indian construction industry issues and remedies

  • 1. Procurement System in the Indian Construction Industry: Issues and Remedies Pavitra Sharma CON 567- Advanced Procurement Systems - spring 2014 Dr. Dean T. Kashiwagi
  • 2. Contents Introduction-.................................................................................................................................................1 Problems Identified- .....................................................................................................................................2 The Best Value Approach (Kashiwagi, 2014)- ...............................................................................................2 Differences identified between the traditional system of procurement in India and the Best Value Approach-......................................................................................................................................................4 Proposed Solution-........................................................................................................................................5 Conclusion-....................................................................................................................................................5 Bibliography ..................................................................................................................................................6
  • 3. CON 567 Pavitra Sharma 1 Procurement System in the Indian Construction Industry: Issues and Remedies Introduction- Procurement in the Indian Construction Industry especially in the public sector is done through the traditional contracting, that includes awards to the contractor with the lowest bid. Particularly for public sector, at least 10 to 12 agencies are involved in the process of deciding the necessity to procure (Jain). Huge amount of cost, paperwork and manpower is expended in the conceptualization of the process. According to Jain, the recent estimates of the cost of initiations are as follows (Jain)-  Central Government: 30-40%  State Government: 40-60%  Public Sector Undertakings: 15-25%  Public Ltd. companies: 5-7% of the value of goods/ (with private holding) services procured.  Private Ltd. Companies: 1-2% Stated below are the principles concerning the owner as envisioned by Construction Industry Development Council (Construction Industry Development Council; Jain)-  Principle 1- The most competent agency should be awarded the work.  Principle 2- The work should be executed at the most economical price.  Principle 3- Works should progress on schedule and its quality should adhere to the standards specified.  Principle 4- Procurement procedure should be transparent.  Principle 5- Owner’s representatives are competent, experienced and good managers of work. Stated below are the principles concerning the contractor as envisioned by Construction Industry Development Council (Construction Industry Development Council; Jain)-  Principle 6- Contractor possesses requisite experience in the type of work taken up.  Principle 7- The Contractor has adequate resources for executing the work.  Principle 8- The Contractor quotes a workable price.  Principle 9- The Contractor has the corporate strength and resilience to overcome adverse situations if and when they may arise.
  • 4. CON 567 Pavitra Sharma 2 Problems Identified- The reality of situation in the system of procurement is completely contradictory to principles stated by the Construction Industry Development Council (CIDC). There is no transparency in the system. The work is awarded to the lowest bidder. The vendors lack expertise. These are to name a few but there lies a bigger picture. Principle 1 and Principle 2- During the pre-bid phase, the contract is awarded to the vendor with the lowest bid. Factors like specific past experience on similar project, performance data, customer satisfaction and the works in hand is often ignored during the process. CIDC emphasizes to follow pre-qualification of contractors but due the prevailing system of envelopes and no interview during this phase, the system fails. Therefore, the owners revert back to the pre –bid selection of the contractor with lowest bid. Principle 3- The vendors quote unrealistic and lower bid to acquire the project which in turn results in time and cost overruns. Therefore, the quality of the project suffers. Principle 4- Since the lowest bidder is awarded the project during the pre-bid selection, the credibility and expertize of the vendor is often hidden from the owner. Hence, the system becomes opaque. Principle 5- The owner’s team of engineers and managers lack expertise and management skills which results in weaker quality and schedule control measures. Hence, the project suffers in quality, time and cost overruns. Principle 6- The contractor with the lowest bid during the pre- bid selection is awarded the project. The expertise of the contractor, performance data like cost and time deviations, customer satisfaction is altogether neglected. Principle 7- In house resources are minimal in most cases. Contractors rely mostly on temporary hiring of resources which is seldom preplanned in advance. As a result there is delay in schedule and cost overruns. Also, the contractors lack expertise which makes it difficult to identify and mitigate risk. Principle 8- The field of contracting is highly unregulated in India. A contractor can bid a certain lowest amount without the financial backing, without identifying the scope of work and also without adequate resources. Principle 9- When faced with adverse situations, these contractors adopt short cuts to cope up with the work as they lack expertize, financial backing and adequate resources. The Best Value Approach (Kashiwagi, 2014)- The Best Value based Performance Information Procurement System (PIPS) creates an environment that includes-  Client does not manage, direct and control the vendor.  The vendor is the expert.  The client utilizes the expertise of the vendor.
  • 5. CON 567 Pavitra Sharma 3  Minimizes time and cost overruns.  Forces accountability  Identification and mitigation of risk.  Minimal decision making.  Transparency  Minimized transactions.  Minimizes bureaucracy.  Protects the expert and the owner by maximizing profit and minimizing project cost. The Best Value PIPS propose four phases- 1. Pre-qualification 2. Selection 3. Clarification 4. Execution The Pre-Qualification Phase (Phase 0) - The goal of this phase is to increase competitiveness, to create transparency and identify vendors according to the minimum criteria set by the owner based on expertize, past performance and experience on similar project. The Selection Phase (Phase 1) - This phase identifies the Best Value (BV) vendor from the competing vendors. The BV vendor is selected based on the level of expertise and not based on the lowest price quote or the best scope of work. The expertise criteria are project capability, identification of risk and its mitigation plan, value added, cost and an interview. This phase also utilizes four filters i.e. project capability, interview, prioritization and dominance check, before moving the BV vendor into the clarification phase. The Clarification Phase (Phase 2) - This is the most important phase of all. In this phase the BV vendor is forced to clarify their plan and determine the scope of their proposal. They must answer any technical questions to show their technical competence. They must provide the following-  Detailed project schedule.  Identification of areas out of their control.  Risk identification and mitigation.  Measurement of risk performance.  Creation of milestone schedule.  Creation of weekly risk report (WRR) which includes a risk plan, risk mitigation plan (RMP) and performance measurements. The clarification phase provides an opportunity to the vendor to identify itself as a BV vendor for the owner. If the offer is unacceptable to the owner then the next prioritized BV vendor is brought into the clarification phase. The Execution Phase (Phase 3) - A contract is signed after the BV vendor is identified during the clarification phase. The BV vendor delivers its services and mitigates risk in accordance to the WRR. The role of the client or owner here is to assure that a quality service is provided by the BV vendor without time and cost deviations with the help of WRR.
  • 6. CON 567 Pavitra Sharma 4 The purpose of these reports is to- 1. Create transparency. 2. Communicate information quickly and in a dominant fashion. 3. Assign accountability. Differences identified between the traditional system of procurement in India and the Best Value Approach- Traditional System Best Value Approach Pre-bid selection of the vendor. Four phases of selection. Selection based on lowest bid. Selection based of expertize. Price based industry structure. Value based environment. No transparency. Complete transparency. Scope of the project is determined by the owner. Scope of the project is determined by the BV vendor. Owner exercises management, direction and control. Owner exercises quality control and assurance with help of WRR. No performance measurement. Performance measurement is the key. Vendor exercises owner’s desires. Owner utilizes the vendor’s expertize. No risk identification beforehand and its mitigation during the execution. Complete risk identification and mitigation plan before execution. Aim is to maximize profit by maximizing project cost. Aim is to maximize profit with lowest possible project cost. A win-lose environment. A win-win environment for the owner as well as the BV vendor. No accountability of the vendor. Forces accountability. Many transactions and decision making during the execution. Least transactions and decision making during the execution as everything is pre-planned. Overall project cost increases. Overall project cost remains within the deviations stated by the vendor. Owner remains accountable of the risk created by the vendor. Encourages transfer of risk to the expert vendor. Requires more project managers in the owner’s management team for MDC. Requires fewer project managers in the owner’s management team. Decreases the efficiency of the expert vendor. Maximizes the efficiency of the expert vendor. A stressful environment. No stress environment.
  • 7. CON 567 Pavitra Sharma 5 Proposed Solution- For the vendor/contractor-  Quoting realistic and best price during the bid.  Provide dominant information about the past experience and related projects executed.  Provide performance related information such as time deviations, cost deviations, customer satisfaction.  Identify the scope of the project.  Identify risks that are within control as well as out of control before the execution.  Mitigation plan of the risks identified before execution.  Provide complete transparency to the owner before and during execution.  Provide WRR’s during execution.  Provide performance measurement reports during execution.  Maximize profit by executing quality work with least time and cost deviations. For the client/owner-  Creation of value based environment with high competition.  Stating clearly the level of expertise required for the project before the bidding process.  Selection of the vendor based on the expertise.  Recognizing that vendor is the expert.  Accept or reject the scope of the project provided by the expert vendor.  Provide a complete transparent and no influence environment to the vendor.  Selection of the expert vendor with help of the four phases proposed by the PIPS approach.  Introduce complete transparency in the system.  Exercise quality control and assurance based on the data provided by the expert vendor.  Minimize transaction but exercise on-time transactions.  No MDC and decision making.  Provide a win-win environment. Conclusion- India Construction Industry is the second largest industry in the country after agriculture and contributes to 11% of the country’s GDP. There exists immense potential for growth in the coming years as India is one the fastest developing economies competing with the developed counterparts. The prevailing system can be changed if the industry focuses on providing quality work rather than maximizing profit. Experts and well educated staff should be employed by the companies and not save money on staff salaries. Use of latest technology and performance measurement matrices should be encouraged. Honesty and transparency should be thoroughly exercised. Favoritism, political influence, emotion and self-interests should be discouraged. In conclusion, the whole system should revolve around the expertise of the individual or the company.
  • 8. CON 567 Pavitra Sharma 6 Bibliography Construction Industry Development Council. (n.d.). Jain, R. (n.d.). System of procurement in construction works: Some flaws and their remedies. Kashiwagi, D. T. (2014). Best Value Standard.