A PARTNERSHIP TO MAKE
WINSTON DRIVE
A BETTER STREET
Prop AA Funding Proposal
Winston Drive connects and serves multiple
southwest communities
 Winston Drive is the priority link from
 the Lake to Muni
Pedestrian safety on Winston Drive impacts
many neighborhoods and institutions
 Neighborhoods
 Lakeshore
 Ingleside
 Park Merced
 University Park
North and South
 Commercial Districts
 Stonestown
 Schools
 San Francisco State
University
 Lowell HS
 Lakeshore
Elementary
 Mercy HS
 Recreational Areas
 Lake Merced
 3 Golf courses
 SF Zoo
“Take MUNI to the Lake”
Winston Drive is the link from Muni to Lake
Merced recreation sites
And… arriving in late 2015: SF State
Student Recreation and Wellness Center
We will need ~5000 safe pedestrian crossings/day
This project corrects significant deficiencies in
crosswalks and sidewalk connectivity
Installs sidewalk for Lowell HS
and Lakeshore Elementary
Opens closed campus-side
crosswalk
Corrects safety and access issues with low
visibility crosswalk due to street warp
Connects Buckingham and University Park
Improves pedestrian connections into Stonestown
Widens sidewalk at bus stop
Improving this corridor
better connects our city!
Let’s make it easier to visit “SF/SW”
our southwest coastal recreation area
 Winston Drive is the priority link from
 the Lake to Muni
Ocean
Beaches
The Zoo
Funston
Headlands
3 Golf
Courses
Dining at Stonestown, SF
State, Park Merced Jogging and
walking trails
Concerts at
Stern Grove
Better sidewalks will build the pedestrian
traffic that supports Stonestown and Muni
Let’s provide those sidewalks!
Remove obstacles to pedestrians
Widen existing sidewalks
for comfort and accessibilty
Two people can’t pass –
barely room for a wheelchair
Let’s open closed crossings
Add landscape plantings in islands
for safety and attractiveness
Lift a section of road edge
to level the road for pedestrian safety
Road currently slopes steeply to the north and west within the crosswalk area,
increasing vehicle speed and reducing visibility for pedestrians.
Project lifts road
to this desired
grade
Which will correct the steeply sloping
and non-compliant midblock crosswalk
And implement traffic calming
Add median or pedestrian bulbouts to provide refuge and
shorten the unprotected crossing distance
Maintain the comfortable bike lanes
Bike lanes are 6 ft wide for safety
And provide better sidewalk
clearance at our transit stops!
Every better street makes a better city
This project showcases effective coordination between public
agencies, neighborhood associations, and commercial
properties in a project that benefits the whole city.
Project Schedule
2012/3 Design and engineering
2013 Road segment regrade,
Lowell HS sidewalk
2014 New sidewalks,
crosswalk improvements
2015/6 Roadway traffic calming

Contenu connexe

En vedette (9)

Creatig content with a purpose 2014 - Class #5 HubSpot Inbound Academy Certif...
Creatig content with a purpose 2014 - Class #5 HubSpot Inbound Academy Certif...Creatig content with a purpose 2014 - Class #5 HubSpot Inbound Academy Certif...
Creatig content with a purpose 2014 - Class #5 HubSpot Inbound Academy Certif...
 
Sk kd kelas xi mia kurikulum 2013
Sk kd kelas xi mia kurikulum 2013Sk kd kelas xi mia kurikulum 2013
Sk kd kelas xi mia kurikulum 2013
 
hyd11
hyd11hyd11
hyd11
 
Que es un sitio web
Que es un sitio webQue es un sitio web
Que es un sitio web
 
Comida mexicana
Comida mexicanaComida mexicana
Comida mexicana
 
Silabus kelas xi mia kurikulum 2013
Silabus kelas xi mia kurikulum 2013Silabus kelas xi mia kurikulum 2013
Silabus kelas xi mia kurikulum 2013
 
Samsung Galaxy Y Manual
Samsung Galaxy Y ManualSamsung Galaxy Y Manual
Samsung Galaxy Y Manual
 
El terror de sexto b
El terror de sexto bEl terror de sexto b
El terror de sexto b
 
Respuesta inmune ocular
Respuesta inmune ocularRespuesta inmune ocular
Respuesta inmune ocular
 

Similaire à Making Winston Drive Complete 091212

CE 527 - Sustainable Mobility - Group 2 - Johnson Park Final Report
CE 527 - Sustainable Mobility - Group 2 - Johnson Park Final ReportCE 527 - Sustainable Mobility - Group 2 - Johnson Park Final Report
CE 527 - Sustainable Mobility - Group 2 - Johnson Park Final Report
Doug Moody
 
Clifton Avenue Streetscape Design - Posters
Clifton Avenue Streetscape Design - PostersClifton Avenue Streetscape Design - Posters
Clifton Avenue Streetscape Design - Posters
Jake Henderson
 
Bridge Construction, Pedestrian Safety Upgrades, Tree-Plantings and Road Impr...
Bridge Construction, Pedestrian Safety Upgrades, Tree-Plantings and Road Impr...Bridge Construction, Pedestrian Safety Upgrades, Tree-Plantings and Road Impr...
Bridge Construction, Pedestrian Safety Upgrades, Tree-Plantings and Road Impr...
Maureen Kenney
 
Sindiong Project Examples
Sindiong Project ExamplesSindiong Project Examples
Sindiong Project Examples
SteveSindiong
 
Complete Streets Sussex - Eric Snyder
Complete Streets Sussex - Eric SnyderComplete Streets Sussex - Eric Snyder
Complete Streets Sussex - Eric Snyder
njbikeped
 
Remove jcfo boards
Remove jcfo boardsRemove jcfo boards
Remove jcfo boards
GardinerEast
 

Similaire à Making Winston Drive Complete 091212 (20)

Oct. 19 Complete Streets Open House Boards
Oct. 19 Complete Streets Open House BoardsOct. 19 Complete Streets Open House Boards
Oct. 19 Complete Streets Open House Boards
 
CE 527 - Sustainable Mobility - Group 2 - Johnson Park Final Report
CE 527 - Sustainable Mobility - Group 2 - Johnson Park Final ReportCE 527 - Sustainable Mobility - Group 2 - Johnson Park Final Report
CE 527 - Sustainable Mobility - Group 2 - Johnson Park Final Report
 
Clifton Avenue Streetscape Design - Posters
Clifton Avenue Streetscape Design - PostersClifton Avenue Streetscape Design - Posters
Clifton Avenue Streetscape Design - Posters
 
Hastings Way Redevelopment by Jeremy Gragert

Hastings Way Redevelopment by Jeremy Gragert
Hastings Way Redevelopment by Jeremy Gragert

Hastings Way Redevelopment by Jeremy Gragert

 
Bridge Construction, Pedestrian Safety Upgrades, Tree-Plantings and Road Impr...
Bridge Construction, Pedestrian Safety Upgrades, Tree-Plantings and Road Impr...Bridge Construction, Pedestrian Safety Upgrades, Tree-Plantings and Road Impr...
Bridge Construction, Pedestrian Safety Upgrades, Tree-Plantings and Road Impr...
 
Sindiong Project Examples
Sindiong Project ExamplesSindiong Project Examples
Sindiong Project Examples
 
Complete Streets Sussex - Eric Snyder
Complete Streets Sussex - Eric SnyderComplete Streets Sussex - Eric Snyder
Complete Streets Sussex - Eric Snyder
 
SNEAPA 2013 Thursday b5 10_30 waterbury green
SNEAPA 2013 Thursday b5 10_30 waterbury greenSNEAPA 2013 Thursday b5 10_30 waterbury green
SNEAPA 2013 Thursday b5 10_30 waterbury green
 
NACTO 2013
NACTO  2013NACTO  2013
NACTO 2013
 
City of Brea Student Site Walk audit presentation
City of Brea Student Site Walk audit presentationCity of Brea Student Site Walk audit presentation
City of Brea Student Site Walk audit presentation
 
Belchertown, MA Design & Resilience Team
Belchertown, MA Design & Resilience TeamBelchertown, MA Design & Resilience Team
Belchertown, MA Design & Resilience Team
 
Remove jcfo boards
Remove jcfo boardsRemove jcfo boards
Remove jcfo boards
 
Great streets
Great streetsGreat streets
Great streets
 
Urban Design: Streets
Urban Design: StreetsUrban Design: Streets
Urban Design: Streets
 
C1 Planning with Kids
C1 Planning with KidsC1 Planning with Kids
C1 Planning with Kids
 
De witt final_report_180213
De witt final_report_180213De witt final_report_180213
De witt final_report_180213
 
Champ can trail action plan ppt
Champ can trail action plan pptChamp can trail action plan ppt
Champ can trail action plan ppt
 
WS 2D Goldilocks & Streets: What's Just Right for You
WS 2D   Goldilocks & Streets: What's Just Right for YouWS 2D   Goldilocks & Streets: What's Just Right for You
WS 2D Goldilocks & Streets: What's Just Right for You
 
130423 pubmtgppt2
130423 pubmtgppt2130423 pubmtgppt2
130423 pubmtgppt2
 
Simran deo- architectural conservation- neighbourhood design and planning
Simran deo- architectural conservation- neighbourhood design and planningSimran deo- architectural conservation- neighbourhood design and planning
Simran deo- architectural conservation- neighbourhood design and planning
 

Making Winston Drive Complete 091212

  • 1. A PARTNERSHIP TO MAKE WINSTON DRIVE A BETTER STREET Prop AA Funding Proposal
  • 2. Winston Drive connects and serves multiple southwest communities  Winston Drive is the priority link from  the Lake to Muni
  • 3. Pedestrian safety on Winston Drive impacts many neighborhoods and institutions  Neighborhoods  Lakeshore  Ingleside  Park Merced  University Park North and South  Commercial Districts  Stonestown  Schools  San Francisco State University  Lowell HS  Lakeshore Elementary  Mercy HS  Recreational Areas  Lake Merced  3 Golf courses  SF Zoo
  • 4. “Take MUNI to the Lake” Winston Drive is the link from Muni to Lake Merced recreation sites
  • 5. And… arriving in late 2015: SF State Student Recreation and Wellness Center We will need ~5000 safe pedestrian crossings/day
  • 6. This project corrects significant deficiencies in crosswalks and sidewalk connectivity Installs sidewalk for Lowell HS and Lakeshore Elementary Opens closed campus-side crosswalk Corrects safety and access issues with low visibility crosswalk due to street warp Connects Buckingham and University Park Improves pedestrian connections into Stonestown Widens sidewalk at bus stop
  • 7. Improving this corridor better connects our city!
  • 8. Let’s make it easier to visit “SF/SW” our southwest coastal recreation area  Winston Drive is the priority link from  the Lake to Muni Ocean Beaches The Zoo Funston Headlands 3 Golf Courses Dining at Stonestown, SF State, Park Merced Jogging and walking trails Concerts at Stern Grove
  • 9. Better sidewalks will build the pedestrian traffic that supports Stonestown and Muni
  • 10. Let’s provide those sidewalks!
  • 11. Remove obstacles to pedestrians
  • 12. Widen existing sidewalks for comfort and accessibilty Two people can’t pass – barely room for a wheelchair
  • 13. Let’s open closed crossings
  • 14. Add landscape plantings in islands for safety and attractiveness
  • 15. Lift a section of road edge to level the road for pedestrian safety Road currently slopes steeply to the north and west within the crosswalk area, increasing vehicle speed and reducing visibility for pedestrians. Project lifts road to this desired grade
  • 16. Which will correct the steeply sloping and non-compliant midblock crosswalk
  • 17. And implement traffic calming Add median or pedestrian bulbouts to provide refuge and shorten the unprotected crossing distance
  • 18. Maintain the comfortable bike lanes Bike lanes are 6 ft wide for safety
  • 19. And provide better sidewalk clearance at our transit stops!
  • 20. Every better street makes a better city This project showcases effective coordination between public agencies, neighborhood associations, and commercial properties in a project that benefits the whole city.
  • 21. Project Schedule 2012/3 Design and engineering 2013 Road segment regrade, Lowell HS sidewalk 2014 New sidewalks, crosswalk improvements 2015/6 Roadway traffic calming