 INTRODUCTION
 REQUIREMENTS
 INDIAN STANDARDS ON FORM WORK
 LOADS ON FORM WORK
 TYPES OF FORM WORK
INTRODUCTION
 Formwork (shuttering) in concrete construction is used as a mould for a structure in
which fresh concrete is poured only to harden subsequently. Types of concrete
formwork construction depends on formwork material and type of structural element.
 Classification – wooden, plywood, steel, combined wood-steel, reinforced concrete,
plain concrete.
 The construction of formwork takes time and involves expenditure upto 20 to 25% of
the cost of the structure or even more.
 Timber is the most common material used for formwork. The disadvantage with timber
formwork is that it will warp, swell and shrink. Application of water impermeable cost
to the surface of wood mitigates these defects.
 The operation of removing the formwork is known as stripping. Stripped formwork can
be reused. Reusable forms are known as panel forms and non-usable are called
stationary forms.
REQUIREMENTS
 It should be strong enough to withstand all types of dead and live loads.
 It should be rigidly constructed and efficiently propped and braced both horizontally
and vertically, so as to retain its shape.
 The joints in the formwork should be tight against leakage of cement grout.
 Construction of formwork should permit removal of various parts in desired sequences
without damage to the concrete.
 It should rest on firm base.
 The material of the formwork should be cheap, easily available and should be suitable
for reuse.
 The formwork should be set accurately to the desired line and levels should have plane
surface.
 It should be as light as possible.
 The material of the formwork should not warp or get distorted when exposed to the
elements.
ECONOMY IN FORM WORK
 The plan of the building should imply minimum number of variations in the size of
rooms, floor area etc. so as to permit reuse of the formwork repeatedly.
 Design should be perfect to use slender sections only in a most economical way.
 Minimum sawing and cutting of wooden pieces should be made to enable reuse of the
material a number of times. The quantity of surface finish depends on the quality of the
formwork.
 Fibre glass made of precast concrete and aluminium are used in cast-in-situ
construction such as slabs or members involving curved surfaces.
INDIAN STANDARDS ON FORM WORK
 General – Form work shall conform shape, lines, dimensions.
 Cleaning and treatment of forms – All rubbish, particularly chippings, shavings
and sawdust shall be removed from interior of the forms before concrete is
placed.
 Camber – Desirable to give forms an upward camber to ensure that the beams
do not have a sag.
 Tolerances – Form work shall be so constructed that the internal dimensions
are within the permissible tolerance specified by the designer.
 Stripping time
S.
No.
Description of structural member Time Period
1 Walls, columns and vertical sides of beams 1 to 2 days
2 Slabs (props left under) 3 days
3 Beam soffits (props left under) 7 days
4
Removal of props to slabs
(a) For slabs spanning upto 4.5 m 7 days
(b) For slabs spanning over 4.5 m 14 days
5
Removal of props to beams and arches
(a) Spanning upto 6 m 14 days
(b) spanning over 6 m 21 days
TYPES OF FORMWORK
Timber Formwork
 Timber for formwork should satisfy the following requirement – It should be,
 well seasoned
 light in weight
 easily workable with nails without splitting
 free from loose knots
 Timber used for shuttering for exposed concrete work should have smooth and
even surface on all faces which come in contact with concrete.
Normal sizes of members for timber formwork:
Sheeting for slabs, beam, column
side and beam bottom
25 mm to 40mm thick
Joints, ledges 50 x 70 mm to 50 x 150 mm
Posts 75 x 100mm to 100 x 100 mm
Advantages of using timber forms:
 Timber Shuttering is easy to construct for any shape, size and height.
 It is economical for Small projects.
 It can easily be made into any shape or size.
 It can be constructed using locally available timber.
 It is light weight as compared to steel or aluminum Shuttering.
Plywood Formwork
 Resin bonded plywood sheets are attached to timber frames to make up
panels of required sizes.
 It is possible to have smooth finish in which case on cost in surface finishing is
there.
 By use of large size panels it is possible to effect saving in the labour cost of
fixing and dismantling.
 Number of reuses are more as compared with timber shuttering. For
estimation purpose, number of reuses can be taken as 20 to 25.
Steel Formwork
 This consist of panels fabricated out of thin steel plates stiffened along the edges by
small steel angles.
 The panel units can be held together through the use of suitable clamps or bolts and
nuts.
 The panels can be fabricated in large number in any desired modular shape or size.
 Steel forms are largely used in large projects or in situation where large number reuses
of the shuttering is possible.
 This type of shuttering is considered most suitable for circular or curved structures.
Steel forms compared with timber formwork:
 Steel forms are stronger, durable and have longer life than timber formwork and their
reuses are more in number.
 Steel forms can be installed and dismantled with greater ease and speed.
 The quality of exposed concrete surface by using steel forms is good and such surfaces
need no further treatment.
 Steel formwork does not absorb moisture from concrete.
 Steel formwork does not shrink or warp.
Aluminium Form work
 Aluminium formwork is similar in many respects similar to those made of
steel.
 Aluminium forms are lighter than steel forms due to low density and this is
their primary advantage when compared to steel.
 The shuttering is economical if large numbers of repeating usage are made in
construction.
 The disadvantage is that no alteration is possible once the formwork is
constructed.
Plastic Formwork
Plastic form work is a lightweight modular, interlocking system and can be used
more than 100 times
 Advantage of Plastic Form work:-
 It is light weight shuttering hence requires less handling cost.
 It can be used for large section.
 If carefully transported and used, multiple reuses are possible making it highly
economical.
Fabric Formwork
 Fabric formwork is emerging
technology in shuttering industry for
construction of irregular shape and
complex member.
 The flexibility of this material makes it
possible to produce concrete at any
shape.
Coffor Formwork
 Coffor is a stay in place formwork
system.
 Coffor remains in place after concrete
is poured and acts as reinforcement.
 Coffor is transported to the site
prefabricated from the factory.
 This type of shuttering can be used for
any type of structure like houses,
multistory buildings etc.
Wall Form work
 Wall formwork used for concreting of
shear or RCC wall in dams, wing
walls, basement rcc walls etc.
 Wall shuttering made up of vertically
arranged upright timbers (bearers) to
which plywood sheeting boards are
nailed at the inner side.
 The upright timbers are diagonally
braced with the help of boards at both
sides.
Beam Form work
 Beam is the most important member in
RCC framed structure.
 Beam formwork has prefabricated form
work includes sheeting bottom and side
sheeting panels.
 The individual parts of form-work are
manufactured based on the beam size.
Foundation Form work
 Foundation formworks designed
according to foundation type.
 Shuttering design for foundation
depends on foundation type like
footing, combined footing, raft.
 There is a difference in the design for
individual foundations, and shuttering
for strip foundations.
Column Formwork
 Formwork arrangement for column
may differ on the basis of column
outline like rectangular, circular, and
hexagonal or any other shape.
 The sheeting of column shuttering is
constructed according to the column
dimensions.
 The panels are placed in a foot rim,
anchored in soil with the help of bolts.
REFERENCE
 https://theconstructor.org/building/formwork-shuttering/types-of-formwork-
shuttering/3767/
 https://civildigital.com/formwork-construction-types-applications-shuttering/
 Building Construction book by Dr.B.C.Punmia
THANK YOU

Contenu connexe

Tendances (20)

Damp proofing
Damp proofingDamp proofing
Damp proofing
 
Steel Structure
Steel StructureSteel Structure
Steel Structure
 
Roof truss
Roof trussRoof truss
Roof truss
 
stretcher bond
 stretcher bond stretcher bond
stretcher bond
 
RCC Elements column, beam.
RCC Elements  column, beam.RCC Elements  column, beam.
RCC Elements column, beam.
 
Building construction materials -Tiles
Building construction materials -TilesBuilding construction materials -Tiles
Building construction materials -Tiles
 
Stone Masonry BUILDING CONSTRUCTION
Stone Masonry BUILDING CONSTRUCTIONStone Masonry BUILDING CONSTRUCTION
Stone Masonry BUILDING CONSTRUCTION
 
Chapter 7 stairs & staircases
Chapter 7 stairs & staircasesChapter 7 stairs & staircases
Chapter 7 stairs & staircases
 
2 Brick thick wall flemish bond Assignment
2 Brick thick wall flemish bond Assignment2 Brick thick wall flemish bond Assignment
2 Brick thick wall flemish bond Assignment
 
Presentation on Expansion Joint
Presentation on Expansion JointPresentation on Expansion Joint
Presentation on Expansion Joint
 
Retaining walls
Retaining wallsRetaining walls
Retaining walls
 
Brick Masonry
Brick MasonryBrick Masonry
Brick Masonry
 
Tunnel constructions
Tunnel constructionsTunnel constructions
Tunnel constructions
 
Retaining walls
Retaining walls Retaining walls
Retaining walls
 
Ferrocement ppt
Ferrocement pptFerrocement ppt
Ferrocement ppt
 
Arches
ArchesArches
Arches
 
WOOD SUBSTITUTES.pdf
WOOD SUBSTITUTES.pdfWOOD SUBSTITUTES.pdf
WOOD SUBSTITUTES.pdf
 
KUG Pertemuan 1.pptx
KUG Pertemuan 1.pptxKUG Pertemuan 1.pptx
KUG Pertemuan 1.pptx
 
Classification of Buildings as per National Building Code of India (NBC) 2016
Classification of Buildings as per National Building Code of India (NBC) 2016Classification of Buildings as per National Building Code of India (NBC) 2016
Classification of Buildings as per National Building Code of India (NBC) 2016
 
Pre-stressed concrete
Pre-stressed concrete Pre-stressed concrete
Pre-stressed concrete
 

Similaire à Formwork Types Guide for Concrete Construction

Types of Formwork & Materials.pptx
Types of Formwork & Materials.pptxTypes of Formwork & Materials.pptx
Types of Formwork & Materials.pptxMr Amol Ghogare
 
Formwork Presentation for Construction Technology
Formwork Presentation for Construction TechnologyFormwork Presentation for Construction Technology
Formwork Presentation for Construction TechnologyI'mMiss Lily
 
Formwork construction in structures
Formwork construction in structuresFormwork construction in structures
Formwork construction in structuresRithika Ravishankar
 
Formwork in civil engineering
Formwork in civil engineeringFormwork in civil engineering
Formwork in civil engineeringFazal-E- Jalal
 
Formwork For Structural Member.pptx
Formwork For Structural Member.pptxFormwork For Structural Member.pptx
Formwork For Structural Member.pptxMr Amol Ghogare
 
formwork Bco (1) final.pdf
formwork Bco (1) final.pdfformwork Bco (1) final.pdf
formwork Bco (1) final.pdfFaizanSolanki
 
Formwork seminar 2
Formwork seminar 2Formwork seminar 2
Formwork seminar 2Gali Suresh
 
types of formwork.pdf
types of formwork.pdftypes of formwork.pdf
types of formwork.pdfReigerRoyal
 
Ct formwork presentation
Ct formwork presentationCt formwork presentation
Ct formwork presentationbee_by
 
Farmwork shuttering
Farmwork shutteringFarmwork shuttering
Farmwork shutteringKishor Ade
 
All you need to know about Construction Formwork
All you need to know about Construction FormworkAll you need to know about Construction Formwork
All you need to know about Construction FormworkAnkit Singhai
 
Form-work in construction
Form-work in construction Form-work in construction
Form-work in construction purvi golecha
 
Types of modern construction formwork
Types of modern construction formwork Types of modern construction formwork
Types of modern construction formwork adarshkaushik6
 
Chapter 5 formwork
Chapter 5 formworkChapter 5 formwork
Chapter 5 formworkKHUSHBU SHAH
 

Similaire à Formwork Types Guide for Concrete Construction (20)

Types of Formwork & Materials.pptx
Types of Formwork & Materials.pptxTypes of Formwork & Materials.pptx
Types of Formwork & Materials.pptx
 
Gurme santoshkumar
Gurme santoshkumarGurme santoshkumar
Gurme santoshkumar
 
Formwork Presentation for Construction Technology
Formwork Presentation for Construction TechnologyFormwork Presentation for Construction Technology
Formwork Presentation for Construction Technology
 
Formwork construction in structures
Formwork construction in structuresFormwork construction in structures
Formwork construction in structures
 
Formwork in civil engineering
Formwork in civil engineeringFormwork in civil engineering
Formwork in civil engineering
 
Formwork For Structural Member.pptx
Formwork For Structural Member.pptxFormwork For Structural Member.pptx
Formwork For Structural Member.pptx
 
formwork Bco (1) final.pdf
formwork Bco (1) final.pdfformwork Bco (1) final.pdf
formwork Bco (1) final.pdf
 
Formwork seminar 2
Formwork seminar 2Formwork seminar 2
Formwork seminar 2
 
Temporary Works (Form Work)
Temporary Works (Form Work)Temporary Works (Form Work)
Temporary Works (Form Work)
 
types of formwork.pdf
types of formwork.pdftypes of formwork.pdf
types of formwork.pdf
 
Types of formwork
Types of formworkTypes of formwork
Types of formwork
 
Ct formwork presentation
Ct formwork presentationCt formwork presentation
Ct formwork presentation
 
Farmwork shuttering
Farmwork shutteringFarmwork shuttering
Farmwork shuttering
 
Formwork
FormworkFormwork
Formwork
 
All you need to know about Construction Formwork
All you need to know about Construction FormworkAll you need to know about Construction Formwork
All you need to know about Construction Formwork
 
Form-work in construction
Form-work in construction Form-work in construction
Form-work in construction
 
Types of modern construction formwork
Types of modern construction formwork Types of modern construction formwork
Types of modern construction formwork
 
Formwork
FormworkFormwork
Formwork
 
Formwork 151220193813
Formwork 151220193813Formwork 151220193813
Formwork 151220193813
 
Chapter 5 formwork
Chapter 5 formworkChapter 5 formwork
Chapter 5 formwork
 

Dernier

UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGMANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGSIVASHANKAR N
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfKamal Acharya
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduitsrknatarajan
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdfKamal Acharya
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsRussian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 

Dernier (20)

UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGMANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsRussian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
 

Formwork Types Guide for Concrete Construction

  • 1. FORMWORK AND ITS TYPES NAME : PRADUMN BALAJI SURYAKAR GUIDED BY: DR. S. S. KORANNE CLASS: S.E. CIVIL ROLL NO.: BE17F01F049
  • 2. CONTENTS  INTRODUCTION  REQUIREMENTS  INDIAN STANDARDS ON FORM WORK  LOADS ON FORM WORK  TYPES OF FORM WORK
  • 3. INTRODUCTION  Formwork (shuttering) in concrete construction is used as a mould for a structure in which fresh concrete is poured only to harden subsequently. Types of concrete formwork construction depends on formwork material and type of structural element.  Classification – wooden, plywood, steel, combined wood-steel, reinforced concrete, plain concrete.  The construction of formwork takes time and involves expenditure upto 20 to 25% of the cost of the structure or even more.
  • 4.  Timber is the most common material used for formwork. The disadvantage with timber formwork is that it will warp, swell and shrink. Application of water impermeable cost to the surface of wood mitigates these defects.  The operation of removing the formwork is known as stripping. Stripped formwork can be reused. Reusable forms are known as panel forms and non-usable are called stationary forms.
  • 5. REQUIREMENTS  It should be strong enough to withstand all types of dead and live loads.  It should be rigidly constructed and efficiently propped and braced both horizontally and vertically, so as to retain its shape.  The joints in the formwork should be tight against leakage of cement grout.  Construction of formwork should permit removal of various parts in desired sequences without damage to the concrete.  It should rest on firm base.
  • 6.  The material of the formwork should be cheap, easily available and should be suitable for reuse.  The formwork should be set accurately to the desired line and levels should have plane surface.  It should be as light as possible.  The material of the formwork should not warp or get distorted when exposed to the elements.
  • 7. ECONOMY IN FORM WORK  The plan of the building should imply minimum number of variations in the size of rooms, floor area etc. so as to permit reuse of the formwork repeatedly.  Design should be perfect to use slender sections only in a most economical way.  Minimum sawing and cutting of wooden pieces should be made to enable reuse of the material a number of times. The quantity of surface finish depends on the quality of the formwork.  Fibre glass made of precast concrete and aluminium are used in cast-in-situ construction such as slabs or members involving curved surfaces.
  • 8. INDIAN STANDARDS ON FORM WORK  General – Form work shall conform shape, lines, dimensions.  Cleaning and treatment of forms – All rubbish, particularly chippings, shavings and sawdust shall be removed from interior of the forms before concrete is placed.  Camber – Desirable to give forms an upward camber to ensure that the beams do not have a sag.  Tolerances – Form work shall be so constructed that the internal dimensions are within the permissible tolerance specified by the designer.
  • 9.  Stripping time S. No. Description of structural member Time Period 1 Walls, columns and vertical sides of beams 1 to 2 days 2 Slabs (props left under) 3 days 3 Beam soffits (props left under) 7 days 4 Removal of props to slabs (a) For slabs spanning upto 4.5 m 7 days (b) For slabs spanning over 4.5 m 14 days 5 Removal of props to beams and arches (a) Spanning upto 6 m 14 days (b) spanning over 6 m 21 days
  • 11. Timber Formwork  Timber for formwork should satisfy the following requirement – It should be,  well seasoned  light in weight  easily workable with nails without splitting  free from loose knots  Timber used for shuttering for exposed concrete work should have smooth and even surface on all faces which come in contact with concrete.
  • 12.
  • 13. Normal sizes of members for timber formwork: Sheeting for slabs, beam, column side and beam bottom 25 mm to 40mm thick Joints, ledges 50 x 70 mm to 50 x 150 mm Posts 75 x 100mm to 100 x 100 mm
  • 14. Advantages of using timber forms:  Timber Shuttering is easy to construct for any shape, size and height.  It is economical for Small projects.  It can easily be made into any shape or size.  It can be constructed using locally available timber.  It is light weight as compared to steel or aluminum Shuttering.
  • 15. Plywood Formwork  Resin bonded plywood sheets are attached to timber frames to make up panels of required sizes.  It is possible to have smooth finish in which case on cost in surface finishing is there.  By use of large size panels it is possible to effect saving in the labour cost of fixing and dismantling.  Number of reuses are more as compared with timber shuttering. For estimation purpose, number of reuses can be taken as 20 to 25.
  • 16.
  • 17. Steel Formwork  This consist of panels fabricated out of thin steel plates stiffened along the edges by small steel angles.  The panel units can be held together through the use of suitable clamps or bolts and nuts.  The panels can be fabricated in large number in any desired modular shape or size.  Steel forms are largely used in large projects or in situation where large number reuses of the shuttering is possible.  This type of shuttering is considered most suitable for circular or curved structures.
  • 18.
  • 19. Steel forms compared with timber formwork:  Steel forms are stronger, durable and have longer life than timber formwork and their reuses are more in number.  Steel forms can be installed and dismantled with greater ease and speed.  The quality of exposed concrete surface by using steel forms is good and such surfaces need no further treatment.  Steel formwork does not absorb moisture from concrete.  Steel formwork does not shrink or warp.
  • 20. Aluminium Form work  Aluminium formwork is similar in many respects similar to those made of steel.  Aluminium forms are lighter than steel forms due to low density and this is their primary advantage when compared to steel.  The shuttering is economical if large numbers of repeating usage are made in construction.  The disadvantage is that no alteration is possible once the formwork is constructed.
  • 21.
  • 22. Plastic Formwork Plastic form work is a lightweight modular, interlocking system and can be used more than 100 times  Advantage of Plastic Form work:-  It is light weight shuttering hence requires less handling cost.  It can be used for large section.  If carefully transported and used, multiple reuses are possible making it highly economical.
  • 23.
  • 24. Fabric Formwork  Fabric formwork is emerging technology in shuttering industry for construction of irregular shape and complex member.  The flexibility of this material makes it possible to produce concrete at any shape. Coffor Formwork  Coffor is a stay in place formwork system.  Coffor remains in place after concrete is poured and acts as reinforcement.  Coffor is transported to the site prefabricated from the factory.  This type of shuttering can be used for any type of structure like houses, multistory buildings etc.
  • 25. Wall Form work  Wall formwork used for concreting of shear or RCC wall in dams, wing walls, basement rcc walls etc.  Wall shuttering made up of vertically arranged upright timbers (bearers) to which plywood sheeting boards are nailed at the inner side.  The upright timbers are diagonally braced with the help of boards at both sides. Beam Form work  Beam is the most important member in RCC framed structure.  Beam formwork has prefabricated form work includes sheeting bottom and side sheeting panels.  The individual parts of form-work are manufactured based on the beam size.
  • 26. Foundation Form work  Foundation formworks designed according to foundation type.  Shuttering design for foundation depends on foundation type like footing, combined footing, raft.  There is a difference in the design for individual foundations, and shuttering for strip foundations. Column Formwork  Formwork arrangement for column may differ on the basis of column outline like rectangular, circular, and hexagonal or any other shape.  The sheeting of column shuttering is constructed according to the column dimensions.  The panels are placed in a foot rim, anchored in soil with the help of bolts.