1. Certificate
2. What is Grid Sub-Station (GSS)
3. Single Line Diagram
4. Lightning Arrester
5. Bus Bar
6. Protective Relay
7. Circuit Breaker
8. Isolator
9. Current Transformer
10.Potential Transformer
11.Power Transformer
12.Wave Trap
13.Earthing
14.Capacitor Bank
15.Battery Bank
Certificate
 A grid sub-station is where transmission voltages comes to be stepped
up/stepped down by three phase transformer
What is Grid Sub-Station (GSS)
Single Line Diagram
About 132 KV Mahaveer Nagar GSS Kota
Total Capacity of GSS - 115 MVA
132 KV Incoming Feeder - Sakatpura 220 KV GSS
132 KV Outgoing Feeder - Deoli Manjhi
33KV Outgoing Feeder - 8 (Ranpur, RMIDC, Dada Bari, B.Vihar,
Talwandi, R.K. Puram, Indra Vihar, PHED)
11 KV Outgoing Feeder - 7 (M.N.1st, Balaji Nagar, M.N. 2nd, M.N. 3rd,
M.N. Ext., Medical College, Rangbari)
Lightning Arrester (LA)
 It is the first protective equipment in the
GSS.
 Lightning Arrester is a protective device
which provides protection against the
high voltage from lightning.
 A lightning Arrester has two terminal one
is the high voltage terminal and another
one is ground.
Bus Bars
 An electrical bus bar is defined as a
conductor or a group of conductor
used for collecting electric power from
the incoming feeder and distribute
them to the outgoing feeders.
 Bus Bar is made from copper (Cu) or
Aluminium (Al).
Types of Bus Bar
1. Main bus bar.
2. Auxiliary bus bar.
Protective Relay
 Protective Relay are the sensing device.
 It is sense the abnormal condition in
electrical circuit and gives the tripping
command to the circuit breaker.
Circuit Breaker
 Circuit Breaker are automatically
operated electrical switch.
 Operate at ON LOAD Condition.
 It separate faulty circuit from healthy
circuit.
Types of Circuit Breaker
1. Air Circuit Breaker
2. SF6 Circuit Breaker
3. Vacuum Circuit Breaker
4. Oil Circuit Breaker
Isolator
 Isolator is a device which is used to
break the circuit under no load
condition.
 It is used for maintenance purpose
with safety.
 It is also known as OFF - LINE
switch.
Current Transformer
 Current Transformer is an instrument
transformer which is used for
protection and metering of high value
of current.
 Secondary side of CT is connected
from relay coil.
 It is always connected in series with
system.
Potential Transformer
 Potential Transformer is an instrument
transformer which is used for
protection and measurement of high
voltage.
 PT is used to step down of voltage.
 It is connected in parallel with the
system.
Power Transformer
 Power Transformer is a static ac device which transfer power from one
electrical circuit to another electrical circuit without change in frequency.
 Working Principal – Faraday’s Law of Electromagnetic Induction.
Types of Power Transformer
1. Step Up Transformer
2. Step Down Transformer
Earthing
 The process of transferring the immediate
discharge of the electrical energy directly
to the earth by the help of the low
resistance wire is known as the earthing.
 It is used for protection against danger
electrical shocks.
Types of Earthing
1. Plate Earthing
2. Pipe Earthing
Capacitor Bank
 For compensate the reactive power,
we use capacitor bank.
Advantages
1. It reduces line current of the
system.
2. It improves voltage level of the
load.
3. It improves power factor.
Battery Bank
 It is responsible for supplying all the
relay panels which are situated in
control room.
 Relay panels works on 110V DC
supply.
 In battery room 55 batteries are
connected in series, each battery is 2V.
Thank You

Contenu connexe

Tendances

PPt on 220 kV substation
PPt on 220 kV substationPPt on 220 kV substation
PPt on 220 kV substation
Ishank Ranjan
 
Uttar pradesh power corparation ltd. training report
Uttar pradesh power corparation ltd. training reportUttar pradesh power corparation ltd. training report
Uttar pradesh power corparation ltd. training report
19saurabh89
 
400kv sub-station-final-ppt-by-mohit
400kv sub-station-final-ppt-by-mohit400kv sub-station-final-ppt-by-mohit
400kv sub-station-final-ppt-by-mohit
Mohit Awasthi
 

Tendances (20)

ppt on summer training on uppcl
ppt on summer training on uppclppt on summer training on uppcl
ppt on summer training on uppcl
 
PPt on 220 kV substation
PPt on 220 kV substationPPt on 220 kV substation
PPt on 220 kV substation
 
Presentation on 132/33 KVSubstation Training
Presentation on 132/33 KVSubstation Training Presentation on 132/33 KVSubstation Training
Presentation on 132/33 KVSubstation Training
 
Industrial summer training on 220 kv substation ppt
Industrial summer training on 220 kv substation pptIndustrial summer training on 220 kv substation ppt
Industrial summer training on 220 kv substation ppt
 
220 kv gss
220 kv gss220 kv gss
220 kv gss
 
Uttar pradesh power corparation ltd. training report
Uttar pradesh power corparation ltd. training reportUttar pradesh power corparation ltd. training report
Uttar pradesh power corparation ltd. training report
 
Report on industrial summer training on 220 kv substation
Report  on industrial summer training on 220 kv substationReport  on industrial summer training on 220 kv substation
Report on industrial summer training on 220 kv substation
 
132 kv
132 kv132 kv
132 kv
 
Electric substation
Electric substation Electric substation
Electric substation
 
industrial training on 132 kv substation
industrial training on 132 kv substationindustrial training on 132 kv substation
industrial training on 132 kv substation
 
PPT ON 220KV GSS
PPT ON 220KV GSSPPT ON 220KV GSS
PPT ON 220KV GSS
 
Presentation on Power transformer
Presentation on Power transformerPresentation on Power transformer
Presentation on Power transformer
 
132 33kv substation documentation
132 33kv substation documentation132 33kv substation documentation
132 33kv substation documentation
 
PPT ON 220KV GSS
PPT ON 220KV GSSPPT ON 220KV GSS
PPT ON 220KV GSS
 
400kv sub-station-final-ppt-by-mohit
400kv sub-station-final-ppt-by-mohit400kv sub-station-final-ppt-by-mohit
400kv sub-station-final-ppt-by-mohit
 
Substation Training presentation
Substation Training presentationSubstation Training presentation
Substation Training presentation
 
132 KV GSS CHAMBAL JAIPUR
132 KV GSS CHAMBAL JAIPUR132 KV GSS CHAMBAL JAIPUR
132 KV GSS CHAMBAL JAIPUR
 
Summer Training presentation on 132/33 KV sub-station Minto park, Allahabad
Summer Training presentation on 132/33 KV sub-station Minto park, AllahabadSummer Training presentation on 132/33 KV sub-station Minto park, Allahabad
Summer Training presentation on 132/33 KV sub-station Minto park, Allahabad
 
Training report on substation presentation
Training report on substation presentationTraining report on substation presentation
Training report on substation presentation
 
220 kv G.S.S (report)
220 kv G.S.S (report)220 kv G.S.S (report)
220 kv G.S.S (report)
 

Similaire à 132 kv GSS Mahaveer Nagar Kota

Manish Kumar Gangey- 19ESKEE095.pptx
Manish Kumar Gangey- 19ESKEE095.pptxManish Kumar Gangey- 19ESKEE095.pptx
Manish Kumar Gangey- 19ESKEE095.pptx
Manish Gangwal
 
Uttar pradesh power corporation limited
Uttar pradesh power corporation limitedUttar pradesh power corporation limited
Uttar pradesh power corporation limited
VSRAGHU
 
220 kv g.s.s, report
 220 kv g.s.s, report 220 kv g.s.s, report
220 kv g.s.s, report
panna rayal
 

Similaire à 132 kv GSS Mahaveer Nagar Kota (20)

Indusrtrial training ppt (1).pptx
Indusrtrial training ppt (1).pptxIndusrtrial training ppt (1).pptx
Indusrtrial training ppt (1).pptx
 
Manish Kumar Gangey- 19ESKEE095.pptx
Manish Kumar Gangey- 19ESKEE095.pptxManish Kumar Gangey- 19ESKEE095.pptx
Manish Kumar Gangey- 19ESKEE095.pptx
 
Summer Tranning priyanshu tiwari by aditya.pptx
Summer Tranning priyanshu tiwari by aditya.pptxSummer Tranning priyanshu tiwari by aditya.pptx
Summer Tranning priyanshu tiwari by aditya.pptx
 
33/11 KV SUB-STATION, VIBHUTI KHAND, GOMTI NAGAR, LUCKNOW
33/11 KV SUB-STATION, VIBHUTI KHAND, GOMTI  NAGAR, LUCKNOW33/11 KV SUB-STATION, VIBHUTI KHAND, GOMTI  NAGAR, LUCKNOW
33/11 KV SUB-STATION, VIBHUTI KHAND, GOMTI NAGAR, LUCKNOW
 
Gss ppt by kanhaiya
Gss ppt  by kanhaiyaGss ppt  by kanhaiya
Gss ppt by kanhaiya
 
Harvindar 132 KV GSS from ARYA college (fb.com/hrrock)
Harvindar 132 KV GSS from ARYA college (fb.com/hrrock)Harvindar 132 KV GSS from ARYA college (fb.com/hrrock)
Harvindar 132 KV GSS from ARYA college (fb.com/hrrock)
 
UPPCL,33/11KV H.A.L SUBSTATION,INDIRANAGAR(LUCKNOW)
UPPCL,33/11KV H.A.L SUBSTATION,INDIRANAGAR(LUCKNOW)UPPCL,33/11KV H.A.L SUBSTATION,INDIRANAGAR(LUCKNOW)
UPPCL,33/11KV H.A.L SUBSTATION,INDIRANAGAR(LUCKNOW)
 
Uttar pradesh power corporation limited
Uttar pradesh power corporation limitedUttar pradesh power corporation limited
Uttar pradesh power corporation limited
 
Srijan tripathi(220kv gss) ppt
Srijan tripathi(220kv gss) pptSrijan tripathi(220kv gss) ppt
Srijan tripathi(220kv gss) ppt
 
400 KV GSS HEERAPURA, JAIPUR
400 KV GSS HEERAPURA, JAIPUR400 KV GSS HEERAPURA, JAIPUR
400 KV GSS HEERAPURA, JAIPUR
 
220 kv g.s.s, report
 220 kv g.s.s, report 220 kv g.s.s, report
220 kv g.s.s, report
 
PPT ON SUMMER TRAINING FROM UPPCL 132/33 KV SUB STATION
PPT ON SUMMER TRAINING FROM UPPCL 132/33 KV SUB STATIONPPT ON SUMMER TRAINING FROM UPPCL 132/33 KV SUB STATION
PPT ON SUMMER TRAINING FROM UPPCL 132/33 KV SUB STATION
 
Electrostatic Precipitator
Electrostatic Precipitator Electrostatic Precipitator
Electrostatic Precipitator
 
Ppt of 132kv gss sitapura jaipur
Ppt of 132kv gss sitapura jaipurPpt of 132kv gss sitapura jaipur
Ppt of 132kv gss sitapura jaipur
 
Summer_Tranning_satihs[1].pptx
Summer_Tranning_satihs[1].pptxSummer_Tranning_satihs[1].pptx
Summer_Tranning_satihs[1].pptx
 
132 KV Substation Gajraula.pptx
132 KV Substation Gajraula.pptx132 KV Substation Gajraula.pptx
132 KV Substation Gajraula.pptx
 
Anurag Attri.pptx
Anurag Attri.pptxAnurag Attri.pptx
Anurag Attri.pptx
 
Industrial summer training
Industrial summer trainingIndustrial summer training
Industrial summer training
 
lecture1424354515.pdf
lecture1424354515.pdflecture1424354515.pdf
lecture1424354515.pdf
 
sub subsation seminar ppt.pptx
sub subsation seminar ppt.pptxsub subsation seminar ppt.pptx
sub subsation seminar ppt.pptx
 

Dernier

DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakes
MayuraD1
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
jaanualu31
 
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
HenryBriggs2
 
+97470301568>> buy weed in qatar,buy thc oil qatar,buy weed and vape oil in d...
+97470301568>> buy weed in qatar,buy thc oil qatar,buy weed and vape oil in d...+97470301568>> buy weed in qatar,buy thc oil qatar,buy weed and vape oil in d...
+97470301568>> buy weed in qatar,buy thc oil qatar,buy weed and vape oil in d...
Health
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Kandungan 087776558899
 

Dernier (20)

DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakes
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxA CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
 
Minimum and Maximum Modes of microprocessor 8086
Minimum and Maximum Modes of microprocessor 8086Minimum and Maximum Modes of microprocessor 8086
Minimum and Maximum Modes of microprocessor 8086
 
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
 
kiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal loadkiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal load
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.ppt
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.
 
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech students
 
Air Compressor reciprocating single stage
Air Compressor reciprocating single stageAir Compressor reciprocating single stage
Air Compressor reciprocating single stage
 
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
 
+97470301568>> buy weed in qatar,buy thc oil qatar,buy weed and vape oil in d...
+97470301568>> buy weed in qatar,buy thc oil qatar,buy weed and vape oil in d...+97470301568>> buy weed in qatar,buy thc oil qatar,buy weed and vape oil in d...
+97470301568>> buy weed in qatar,buy thc oil qatar,buy weed and vape oil in d...
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdf
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
 

132 kv GSS Mahaveer Nagar Kota

  • 1. Submitted To:- MR. Ashok Kumar Sharma (Associate professor) Presented By :- Pramod Nagar Roll No. – 17/770 Batch – EE-6 7th Sem. (EE)
  • 2. CONTENT 1. Certificate 2. What is Grid Sub-Station (GSS) 3. Single Line Diagram 4. Lightning Arrester 5. Bus Bar 6. Protective Relay 7. Circuit Breaker 8. Isolator 9. Current Transformer 10.Potential Transformer 11.Power Transformer 12.Wave Trap 13.Earthing 14.Capacitor Bank 15.Battery Bank
  • 4.  A grid sub-station is where transmission voltages comes to be stepped up/stepped down by three phase transformer What is Grid Sub-Station (GSS)
  • 6. About 132 KV Mahaveer Nagar GSS Kota Total Capacity of GSS - 115 MVA 132 KV Incoming Feeder - Sakatpura 220 KV GSS 132 KV Outgoing Feeder - Deoli Manjhi 33KV Outgoing Feeder - 8 (Ranpur, RMIDC, Dada Bari, B.Vihar, Talwandi, R.K. Puram, Indra Vihar, PHED) 11 KV Outgoing Feeder - 7 (M.N.1st, Balaji Nagar, M.N. 2nd, M.N. 3rd, M.N. Ext., Medical College, Rangbari)
  • 7. Lightning Arrester (LA)  It is the first protective equipment in the GSS.  Lightning Arrester is a protective device which provides protection against the high voltage from lightning.  A lightning Arrester has two terminal one is the high voltage terminal and another one is ground.
  • 8. Bus Bars  An electrical bus bar is defined as a conductor or a group of conductor used for collecting electric power from the incoming feeder and distribute them to the outgoing feeders.  Bus Bar is made from copper (Cu) or Aluminium (Al). Types of Bus Bar 1. Main bus bar. 2. Auxiliary bus bar.
  • 9. Protective Relay  Protective Relay are the sensing device.  It is sense the abnormal condition in electrical circuit and gives the tripping command to the circuit breaker.
  • 10. Circuit Breaker  Circuit Breaker are automatically operated electrical switch.  Operate at ON LOAD Condition.  It separate faulty circuit from healthy circuit. Types of Circuit Breaker 1. Air Circuit Breaker 2. SF6 Circuit Breaker 3. Vacuum Circuit Breaker 4. Oil Circuit Breaker
  • 11. Isolator  Isolator is a device which is used to break the circuit under no load condition.  It is used for maintenance purpose with safety.  It is also known as OFF - LINE switch.
  • 12. Current Transformer  Current Transformer is an instrument transformer which is used for protection and metering of high value of current.  Secondary side of CT is connected from relay coil.  It is always connected in series with system.
  • 13. Potential Transformer  Potential Transformer is an instrument transformer which is used for protection and measurement of high voltage.  PT is used to step down of voltage.  It is connected in parallel with the system.
  • 14. Power Transformer  Power Transformer is a static ac device which transfer power from one electrical circuit to another electrical circuit without change in frequency.  Working Principal – Faraday’s Law of Electromagnetic Induction. Types of Power Transformer 1. Step Up Transformer 2. Step Down Transformer
  • 15. Earthing  The process of transferring the immediate discharge of the electrical energy directly to the earth by the help of the low resistance wire is known as the earthing.  It is used for protection against danger electrical shocks. Types of Earthing 1. Plate Earthing 2. Pipe Earthing
  • 16. Capacitor Bank  For compensate the reactive power, we use capacitor bank. Advantages 1. It reduces line current of the system. 2. It improves voltage level of the load. 3. It improves power factor.
  • 17. Battery Bank  It is responsible for supplying all the relay panels which are situated in control room.  Relay panels works on 110V DC supply.  In battery room 55 batteries are connected in series, each battery is 2V.