Special Report
205Chemical Weekly September 15, 2015
Abstract
T
	he discussion in this paper out-
lines modularization approach
for standard chemical plants.
Each aspect is elaborated in general
starting from conceptualization till
implementation including transporta-
tion. These aspects are applicable to
any plant (chemical or industrial) with
standard parameters.
Introduction
Modularization was developed and
adopted in the offshore structures to
facilitate large volume of fabrication
work to be carried out in shop in a con-
trolled environment. Later on, the need
was also felt for modular construction
of other structure (Onshore) and is fast
catching up in many countries, espe-
cially developed countries.
This discussion in this paper is limi-
ted to modularization approach for
standard chemical plants, especially
in developing countries like India. In
India, modularization approach is not
very popular due to availability of large
& cheap labour force; high transpor-
tation cost due to varied geographical
parameters across the country; lesser
use of water transport etc. But in com-
ing times, modularization approach
will gain wider acceptance.
Modularization of chemical plants: An overview
Stefan Lier[1] and Marcus
Grünewald, Ruhr-Universität Bochum
of Germany, compared the econo-
mics of a modular chemical plant with
those of a traditional large-scale plant
by investigating investment and ope-
ration costs, combined with revenues,
using a net present value analysis.
They concluded that: “Modular plants
consist of modules that autonomously
operate parts of the plant. These mo-
dules are technically and organization-
ally limited areas of the plant that ful-
fill defined tasks.” Starting with these
modules, companies can create capa-
city either by equaling up modules from
general structures or by numbering up
equipment. In the analysis carried out
by them, the economics of a modular
chemical plant are compared with those
of a traditional large-scale plant by in-
vestigating the net present value. The
modular plant presents a more efficient
concept for fast growing products or
products with volatile demands. This
is because the market impact during
operation is more important than the
preceding influence of the investment.
In those cases, the effects of flexibility
surpass the effects of scale.
The conventional approach is
in situ construction of facilities in-
volved in any chemical plant, using
SATISH DIWAKAR
PRASHANT YEDE
SAGAR KHATAV
TATA Consulting Engineers Ltd.
4th Floor, Tower-B, 247 Park
L B S Marg, Vikhroli
Mumbai 400 083
sndiwakar@tce.co.in
pkyede@tce.co.in
skhatav@tce.co.in
locally available construction men
& materials. When such in situ con-
struction is not feasible for any rea-
son, modularization can be adopted
to reduce the in situ work. This can be
achieved by using pre-fabricated and
pre-assembled modules at locations
away from the site. Such pre-fabri-
cated and pre-assembled modules are
then transported either by road or ship
depending upon the logistics require-
ments and erected at site.
Modules are generally a set of pre-
assembled equipments and ancillaries
such as piping, cable trays, cables, in-
sulation etc. Modules may vary in size
depending on design, installation, inter-
facing and transportation constraints.
Modularization facilitates re-us-
ability, as module can be developed,
tested, modified and reused multiple
times reducing re-development time.
Also, the modularized plant can be re-
located from one location to another by
dismantling.
Key factors influencing modulariza-
tion
Modularization can be achieved by
taking a “stick-build” design and divide
into number of modules. Modulariza-
tion is dependent on a detailed assess-
ment of the key project parameters to
determine the feasibility and the extent
of modularization.
Special Report
Chemical Weekly September 15, 2015206
The key factors[3] are generally
labour, site conditions, site access,
schedule and safety. Refer Table 1
for key factors influencing modula-
rization.
It may not be possible to go
for full modularization every time.
Sometimes part modularization may
be desirable considering the project
parameters and in some cases it may
be possible to go for full modulariza-
tion. At times it may not be advisable
to opt for modularization. However,
total modularization cannot eliminate
in situ construction activities such as
site preparation, site enabling works,
excavation, all civil works including
foundations, erection of large fabri-
cated steel vessels and final interfac-
ing of the modules themselves.
The key factor in modularization is
the module size that can be fabricated,
shipped, transported and erected at site.
The maximum size and weight will
vary from project to project, depend-
ing on the geographical features, avail-
ability of equipments for erection and
dimensional & weight limitations of the
transportation routes.
Modules shall be generally fabri-
cated at locations where labour rates
and productivity skill index are suitable
as compared to main construction site.
However, higher level of modulariza-
tion will not necessarily translate into
cost savings as these will be offset to
some extent against the cost of addi-
tional steelwork, shipping and specia-
list land transportation.
Implementation
Constructability aspects for modu-
lar projects need to be reviewed well in
advance as they impact decisions taken
during feasibility and conceptual stages
considering overall process, operation
and maintenance requirements.
Modularization decisions or chan-
ges made during later stages of project
can result in considerable rework and
may increase overall cost & time to a
great extent. A key consideration is the
overall plant layout or plot plan, which
should be designed to meet the extent
of modularization considering all the
points mentioned in Table 1. Also the
interfacing between modules, erection
sequencing, operation and maintenance
requirements shall play an important
role in making these decisions.
Modular design also facilitates par-
allel activities, i.e. several modules can
be fabricated & built in parallel and can
get assembled with higher speed. This
helps in maintaining a smaller team at
site; overall reduction in time and man-
power cost. It can reduce WIP and as-
sociated financial costs.
Modularization can be classified in
three categories.


 	First generation[2] modularization
such as pipe racks, platforms etc.;


 	Second generation[2] modulariza-
tion such as “customizing” equip-
ment and other ancillaries mounted
on structural steel skids; and


 	Third generation[2] modulariza-
tion such as “standardizing” and not
customizing of the modules mount-
ed with equipments and ancillaries.
Considering strength and profes-
sional experience of any engineering
consultant in India, it is feasible to go
for first and second generation modu-
larization as it involves primarily cus-
tomization, i.e. detail engineering
based on the available equipment and
schematic plant layout either provided
by technology supplier or by customer.
For third generation modulariza-
tion, it is necessary to have own, patent-
ed process technology or expertise of
process licensor or technology supplier
capabilities of providing technologies
Table 1
Key factors influencing modularization
Factor Influencers
Labour 

 Shortage of labour at the project site, or in the vicinity
due to any reason


 Required competencies of available labour force


 Labour and productivity rate for site and shops; the pro-
ductivity rate of skilled labour in shop is higher than field
labour by 25-40%.
Site conditions 

 Impact of climatic conditions, e.g. cyclonic conditions,
extreme cold, wind loading, rainfall, sandstorm, snow
loads etc.


 Constraints on plot size and area


 Seismic zones, e.g. high seismic zones will require more
ductile structure with great amount of detailing of joints,
large member sizes for lateral load resisting members etc.
Site access 

 Available routes, infrastructure at site
Schedule 

 Constraints or requirements of the project schedule,
which necessitate the implementation of modular ap-
proach or the schedule benefit that would be achieved us-
ing modular approach.
Safety 

 Stringent safety requirements of conventional construc-
tion compared to modularization work.
Special Report
207Chemical Weekly September 15, 2015
for standardization of plant modules
depending upon various capacities and
volume. However, engineering consul-
tant may collaborate on long-term basis
with technology supplier to acquire re-
quired expertise, if he doesn’t possess
one.
First- and second-generation modu-
larization
The following inputs will be re-
quired to carry out detail engineering of
various modules to be provided. These
inputs may help during conceptualiza-
tion as well.


 	The geographical details of site loca-
tion, seismic zones, wind/cyclone/
hurricane factor, soil bearing capa-
city, groundwater table, soil resis-
tivity, prevalent wind direction and
basic wind speed, rainfall, tempera-
ture, humidity, snow loads, etc.


 	Layout of the proposed plant


 	Technological structure general ar-
rangement layouts showing tenta-
tive location of equipments.


 	P & IDs for process and utilities.


 	Customer’s design standards.


 	Hazardous area classification.


 	Data on industrial waste and waste-
water treatment etc.


 	Customer’s philosophy on sourcing
spares.


 	Details on the new electric power
distribution system, viz. system
voltage levels, loads, standby power
supply etc.


 	Master schedule for implementation
of the plant, with scheduled deli-
veries for directly sourced plant and
equipment.


 	Drawings, data sheets and founda-
tion details for the equipment being
sourced directly by customer.


 	Module sizes intended depending
upon the transportation, construc-
tability, operation and maintenance
requirements.


 	Procedures for letter of intent,
terms of payment, letter of credit,
liquidated damages, guarantees, ef-
ficiency demands, defects liability
period etc.


 	Knowledge of shipping and inland
transportation constraints such as
maximum dimension of shipping
consignment, maximum weight for
the individual module, etc.


 	Preliminary 3D model of the tech-
nology structure showing major
equipments & piping, if available.
Conceptualisation
The conceptualisation stage is con-
sidered to be very significant in any
plant design. The key elements of con-
ceptualization are Process Optimiza-
tion and Energy Optimization.
The following factors largely affect
modular design:


 	Process engineering;


 	Equipment selection;


 	Equipment layout and elevations;


 	Piping and instrumentation;


 	Size of modules;


 	Interfacing of modules at site; and


 	Availability of cranes in and around
the site.
Modularization has an influence on
equipment selection and configuration
for designing a compact plant layout.
Modular designs normally have an
optimized footprint compared to con-
ventionally erected plants. The major-
ity of the process equipments can be
modularized and located in such a way
to lower capital costs and thereby im-
proving plant efficiency. Modular de-
sign takes advantage of both horizontal
and vertical layouts to locate equipment
in a minimum space. A well-designed
module can help to minimize space re-
quirements, reduce piping and cable
lengths.
Process engineer shall be brought
on board during conceptualization
stage to extract maximum cost benefits
out of modularization. The strategic de-
cisions taken during conceptual stage
on overall equipment layout, equip-
ment configuration, piping layouts etc.
may prove critical at later date.
Engineers or designers involved
should possess multi-disciplinary capa-
bility to provide a design that envelopes
domain expertise in process, structural,
mechanical, piping, instrumentation &
electrical design, procurement etc.
Process engineering
Process engineer shall have tho-
rough knowledge of process involved,
equipment layout, type of equipments
that are required and available in mar-
ket, various process alternatives, etc.
Sometimes it is recommended to de-
sign & purchase smaller components
of equipments to facilitate modular
design, instead of designing equipment
that will not fit in the pre-defined module.
Optimizing key process stages dur-
ing the design phase leads to improve-
ments in plant operation and thereby
improve operating and maintenance
cost. Process equipment may be more
efficiently utilized by applying proprie-
tary designs, converting batch ope-
rations to continuous and reducing
residence times from hours to minutes,
depending upon the requirements.
Process dynamics and control
strategies can be optimized by care-
fully matching the operating ranges of
instrumentation and hydraulics to the
equipment.
Energy optimization
Modular systems are best suited
for energy optimization because of the
closed circuit of the process. Process loop
or circuit lengths are shorter in modules,
which increases the overall efficiency of
the plant due to elimination of the long
lengths of piping. Shorter lengths of pip-
ing helps in minimizing heat loss and
condensation in the pipelines.
Special Report
Chemical Weekly September 15, 2015208
In the current industrial scenario of
alternative fuels, a properly designed
modular system using innovative pro-
cess techniques can reduce CAPEX &
OPEX, thereby reducing utility loads
through process & energy optimization.
Civil & Structural engineering
The design of modular fabrication
shall have following Civil and Struc-
tural design requirements:
Size limitation of the module


 	Each module shall be sized, based
on the maximum transportable
length, breadth and height in con-
sultation with process collaborator
or technology supplier.


 	Planning of each module shall cater,
as far as possible, for self-contain-
ment of equipment and associated
piping works.


 	Cutting section plane for the modules.


 	The module size shall be selected as
a self-standing structure for avoid-
ing imbalance during shipment.
Analysis of the modules


 	The entire structure as a single mo-
dule will be analyzed with “PIN”
connection at module interface.
This analysis is intended to arrive at
overall structural integrity once the
plant is commissioned.


 	The plant is sub-divided in to vari-
ous modules as explained earlier.
Each module will be analysed as
independent structure during erec-
tion. The erection scheme needs to
be discussed with the contractor or
can be decided by engineering con-
sultant.


 	The modules during shipment
and transportation may have to
be arranged in a manner different
than its intended position. Such
changes require separate set of
analysis. A typical flow chart indi-
cating the different stages that
are involved in modular design is
given in Figure 1.
Structural design


 	The structural members shall be
designed to account for the forces
acting during handling, lifting and
transportation.


 	All structures shall be analyzed and
qualified for such loads other than
the normal design loads like equip-
ment load, seismic load, normal
wind load etc.


 	Additional strengthening may be
provided to resist critical forces or
to avoid any deformity during trans-
portation


 	Identifying the module sections and
lifting points.


 	Structure to be stable and safe in
assembled module as well as in the
final constructed form.


 	All site joints to be designed as bolt-
ed joints and all shop joints shall be
welded joints.Fig. 1: Typical flow chart of modular design
Yes
Yes
Yes
Yes
No
No
No
No
Permanent
Permanent
Permanent
Permanent
Reinforce
structure
Reinforce
structure
Reinforce
structure
Reinforce
structure
Incorporate in
combined model
End
Start
Integrated in place
structural analysis
Individual module in
place analysis
Lifting analysis
Up righting analysis
Transportation analysis
Temporary bracing
Temporary bracing
Temporary bracing
Temporary bracing
Acceptable
result
Acceptable
result
Acceptable
result
Acceptable
result
Special Report
209Chemical Weekly September 15, 2015


 	Permanent or temporary reinforce-
ment techniques shall be adopted
for members likely to be over-
stressed during lifting and trans-
portation. Connections shall be de-
signed for maximum capacity of the
member and checked for stresses
arising during lifting and transpor-
tation analysis.
Material of construction


 	Rolled steel members, Wide/paral-
lel flange sections and plates from
approved Indian or foreign suppli-
ers shall be used as structural mem-
bers.


 	Special corrosion protection allow-
ance or paints to be used to take care
of transport and handling.
Additional loading during handling


 	Tensile and compressive stresses
arising from lifting & transportation
analysis of the modules.


 	Rolling, pitching, “heave & yaw”
effects of the ship on modules.


 	Adequate packing or temporary
supports (wooden/steel bracings/
lacings, shock absorbing materials,
etc.) need to provided for the equip-
ments and other ancillaries mounted
on modules during transportation.


 	Generally for lifting and transpor-
tation analysis, API RP-2A & GL
Noble Denton guidelines may be
followed.
Checks required prior to shipment


 	Completeness of the end connec-
tions, checking/testing of weld con-
nections & materials.


 	Completion of painting and touch
up painting before release of the
modules for shipment.


 	Additional temporary bracing
members to cater to stresses aris-
ing from transportation as well as
“Set Down” and “Load out Beam”
analysis.


 	Completion of the tag numbers to
all the modules, spare connecting
members and match marking.


 	Demonstrate rigidity of the mo-
dule by lifting it to a small height
duly slung to the lifting hook.


 	Prior to shipment, check mark-
ing of centre of gravity (COG) on
modules for lifting operations.


 	Weight control report shall be pre-
pared before despatch of modules to
site.
Civil and structural works required
at site


 	Foundations.


 	Installation of the modules as per
the erection sequencing procedure.


 	Grouting.


 	Interconnection of the modules with
prefabricated structural members
either by bolting or welding.


 	Installation of the prefabricated ope-
rating platforms after erection of
stand-alone equipment.


 	Installation of prefabricated pipe
supports, minor equipment struc-
tures outside of the module.


 	Touch up painting.


 	Encasement and/or fire-proof con-
creting.
Mechanical design
Mechanical designs shall follow
the relevant standards, codes of prac-
tices such as ASTM, ASME, TEMA,
API, IBR and BIS etc. Flexibility shall
be one of the key components of me-
chanical design. Bolted joints shall be
preferred over welded joints. Interfac-
ing for the pipes between two modules
shall be with spool pipe.
Sizing of equipment, pipelines for
process & utility and selection & loca-
tion of valves & instruments shall be
a part of detailed engineering as per
the Project/Plant Design Manual, P &
IDs, Data Sheets and relevant codes
and standards. Equipment layout shall
feature adequate space for O & M,
aesthetics and ergonomics, headroom
clearances and adherence to the local/
international safety norms such as
OSHA.
Preferably all the equipment, com-
ponents, instruments, valves, pipes,
gaskets, fasteners, special tools, con-
sumable and capital spares etc., should
be sourced from indigenous reputed and
ISO certified manufacturers/sources.
Provision for easy and fast mounting
of imported items, if any, with minimal
deployment of men & machinery shall
feature in the module.
Process pumps that are to be posi-
tioned on the modules shall be aligned
with suction and delivery pipes con-
nected. Pumps that are to be installed
outside the modules shall be shipped
separately with the pump and its drive
aligned but short of dowel pins. This
arrangement shall also be applicable to
other rotary equipment.
Access, i.e. walkway/inter-connect-
ing platforms, to the tall towers such
as reactors, stacks, refiners, distillers,
Special Report
Chemical Weekly September 15, 2015210
strippers etc., shall be featured from re-
lated modules.
On the fabricated module, posi-
tioning of the equipment shall be com-
pleted first. Placement of pipelines
shall be after alignment of majority of
the equipment. Prior to erection of the
fabricated pipes onto the modules, the
inside surfaces shall undergo thorough
mechanical cleaning using a combina-
tion of sponge balls and compressed air
or other acceptable practices. Where
flange joints are involved, such joints
should be at the interface of the mo-
dules or with flanged pipe spool.
Welded pipe joints requiring stress
relieving shall be completed to the
maximum extent on the modules. Metal
ring type flanged joints may be used for
high pressure lines at the point of sepa-
rating out from the module to eliminate
onsite weld joints with stress relieving.
Pipe isometrics running outside the
modules shall be fabricated in single
or multiple loops and housed in corre-
sponding modules for shipment.
Each module shall be identified with
a distinct number. Pipeline designation
number and tag number for equipment,
valves, instruments etc. shall be pre-
fixed with the module identification
number. Tags, punch marks or perma-
nent inscriptions shall be used for iden-
tification. Match marks are preferred
for pipe loops for onsite assembly.
Equipment, pipes and valves requir-
ing thermal insulation shall be wrapped
in the approved insulation material with
aluminium sheet cladding. Configured
spare insulation shall be supplied loose
for onsite fixing at interface of the mo-
dules. Fireproofing, also, shall be pro-
vided where applicable.
Instrumentation design
All the control room mounted
equipment such as DCS/PLC/SCADA
system packages shall be sourced
either locally or abroad as these re-
quire vendor’s assistance for en-
abling, commissioning and fine tun-
ing as per process requirements. As
part of the module, the following
shall be housed:


 	Field instruments, control valves,
junction boxes and power supply
distribution boards.


 	Cabling between the field instru-
ments, junction boxes and power
distribution boards, which are con-
tained within the module.


 	Cable trays and conduits for the ca-
bling within the module.


 	All impulse tubing, fittings supports
required for transmitters.


 	Local control panel, pneumatic
control panels and hydraulic power
pack required for equipment con-
tained within the modules.
The multi-core cables and cable
trays from junction boxes to DCS/PLC
system in the control room shall be
laid at site. Analyzer shelter along with
analyzer panels & sample conditioning
panels installed in it shall be transport-
ed as one module. The sampling lines
and cabling for same shall be carried
out at site.
Instrumentation and control system
design and documentation shall be car-
ried out by using internationally proven
software such as “INTOOLS”.
I&C system design shall follow the
relevant code, standards and practices
such as NFPA, UL/CSA, IEC, EN and
ISA.
Electrical design
Electrical design shall comply with
the relevant codes, standards and prac-
tices such as NFPA, ANSI/IEEE, UL/
CSA, IEC and EN.
Modules shall house the local power
distribution board, control consoles,
fire alarm panel etc. Cable carrier sys-
tem consisting of cable trays, tray sup-
ports shall be included along with the
pipe rack. The module shall include
poles, towers, & other supports for
mounting of lighting fixtures complete
with wiring. However, the fixtures will
be fitted on site. The protection enclo-
sure within the modules shall be speci-
fied and provided as per hazardous area
classification for that module.
For cables emanating & terminating
within the module, cable pulling and
Special Report
211Chemical Weekly September 15, 2015
termination will be executed as a part of
the module. Cable pulling for the cables
joining one module to another will be
carried out on site.
The main earth strip will be in-
stalled on the cable tray and individual
equipment earth leads will be welded to
this main earth strip. All connections to
earth pits/earth electrodes will have to
be done at site.
The lightening protection for build-
ing/structure/vessels, if required, shall
be done at site.
Safety aspects
Safety standards and codes as ap-
plicable to the industry and as required
by the concerned local authorities shall
be adhered to while designing the plant,
equipment, layouts and utility services.
The agency(s) appointed for fabrica-
tion of the modules shall be required to
submit their safety plans for approval,
prior to commencement of work. The
vendor shall indemnify the purchaser
against charges/penalties on the vendor
for violation of safety norms resulting
in damages to the equipment, machi-
nery, handling apparatus/equipment
etc., and/or against injury, accident or
death of labour deployed on this job.
Safety norms for electrical equip-
ment shall be in conformity with the
rules and regulations stipulated by the
competent authorities of the country in
which the plant is being installed and
operated.
Special design considerations
The plant shall be modeled in 3D
environment. The model shall initially
show the following:


 	Structural steel supporting frame-
work for individual module.


 	Lifting points and guying points for
the modules.


 	Structural steel columns, beams,
stairways, walkways/leeways, floor
gratings, hand railing, toe plates,
monorails etc.


 	Plant and equipment.


 	Pipelines, valves, and specialties.


 	Cable trays.


 	Monorails.


 	Identify large/over-sized equipment
such as columns/reactors/vessels
etc., which needs to be transported
or shipped and erected separately at
the plant site.


 	Emphasis shall be to spread the
plant and equipment installed on
the modules to ensure adequate lee
ways, head room clearances, clear
passage for movement of person-
nel and materials handled by the
monorails, access for external crane
hook, adequate space around the
equipments for maintenance etc.


 	Layout and spacing of the cable car-
riers should facilitate safe and easy
cable pulls. Light fittings shall be
easily accessible for replacement of
lamps. Layout of the lights shall be
spread to provide desired illumina-
tion lumens.
Conclusion
Modular design and construction is
most suited to almost all plants having
standard parameters with less degree
of variability. It has brought significant
change in the nature of engineering ser-
vices that are being offered today espe-
cially. In India, it may gain acceptance
and momentum little slower as com-
pared to the developed countries, due to
availability of large labour. To remain
competitive in the international market
in the future, it is necessary for engineer-
ing consultants in India to provide engi-
neering services (in India and abroad)
for “Third Generation” modular design
by either joint venture or
long term association with
technology suppliers (in-
ternational and domestic).
References
1.	 S. Lier. “Net Present
Value Analysis of Modu-
lar Chemical Production
Plants”, Chemical Engi-
neering & Technology,
05/2011.
2.	 “IQPC Modular Con-
struction and Fabrication
2013” Conference.
3.	 “Chemical Plant Design
and Construction,” Rich-
ard Brookfield and Jere-
mey Cooke.

Contenu connexe

Tendances (11)

IRJET- An Investigation of Maintenance Management of Construction Equipment f...
IRJET- An Investigation of Maintenance Management of Construction Equipment f...IRJET- An Investigation of Maintenance Management of Construction Equipment f...
IRJET- An Investigation of Maintenance Management of Construction Equipment f...
 
Esteban Raganit_2016
Esteban Raganit_2016Esteban Raganit_2016
Esteban Raganit_2016
 
Design, Modelling & Analytical Analysis of Rotary Fixture for CNC with an App...
Design, Modelling & Analytical Analysis of Rotary Fixture for CNC with an App...Design, Modelling & Analytical Analysis of Rotary Fixture for CNC with an App...
Design, Modelling & Analytical Analysis of Rotary Fixture for CNC with an App...
 
A_suresha_rao_Jan_2015
A_suresha_rao_Jan_2015A_suresha_rao_Jan_2015
A_suresha_rao_Jan_2015
 
Twaddle_resume_160523
Twaddle_resume_160523Twaddle_resume_160523
Twaddle_resume_160523
 
Nick amott
Nick amottNick amott
Nick amott
 
Salman Resume 2016
Salman Resume  2016Salman Resume  2016
Salman Resume 2016
 
F113243
F113243F113243
F113243
 
Mal_CV
Mal_CVMal_CV
Mal_CV
 
Updated CV (LEONARDO M VILLAMIL JR) 19-1-16
Updated CV  (LEONARDO M  VILLAMIL JR) 19-1-16Updated CV  (LEONARDO M  VILLAMIL JR) 19-1-16
Updated CV (LEONARDO M VILLAMIL JR) 19-1-16
 
IRJET- A Study and Analysis of Construction Equipment Management used in ...
IRJET-  	  A Study and Analysis of Construction Equipment Management used in ...IRJET-  	  A Study and Analysis of Construction Equipment Management used in ...
IRJET- A Study and Analysis of Construction Equipment Management used in ...
 

En vedette (14)

Actividad ludica
Actividad ludicaActividad ludica
Actividad ludica
 
Obtener y dar confianza.
Obtener y dar confianza.Obtener y dar confianza.
Obtener y dar confianza.
 
Old School New Tools
Old School New ToolsOld School New Tools
Old School New Tools
 
Kelompok tik 2 (sma)
Kelompok  tik 2 (sma)Kelompok  tik 2 (sma)
Kelompok tik 2 (sma)
 
MCB Katalog otvorenih treninga Proleće 2016
MCB Katalog otvorenih treninga Proleće 2016MCB Katalog otvorenih treninga Proleće 2016
MCB Katalog otvorenih treninga Proleće 2016
 
конференція сша
конференція сшаконференція сша
конференція сша
 
Resume
ResumeResume
Resume
 
CM-04
CM-04CM-04
CM-04
 
The-Bolt-Winter-Spring-2015
The-Bolt-Winter-Spring-2015The-Bolt-Winter-Spring-2015
The-Bolt-Winter-Spring-2015
 
Creating a Digital Classroom
Creating a Digital ClassroomCreating a Digital Classroom
Creating a Digital Classroom
 
ICV_IGC_Valuepaper_SRB_BW
ICV_IGC_Valuepaper_SRB_BWICV_IGC_Valuepaper_SRB_BW
ICV_IGC_Valuepaper_SRB_BW
 
gobierno de toledo
gobierno de toledogobierno de toledo
gobierno de toledo
 
творча група
творча групатворча група
творча група
 
CM-02
CM-02CM-02
CM-02
 

Similaire à TCE Paper on Modular Engineering

2. Brief of the Invention
2. Brief of the Invention2. Brief of the Invention
2. Brief of the Invention
Abdulqadr Momo
 
Claims Management Challenges in the Modularized Construction Environment
Claims Management Challenges in the Modularized Construction EnvironmentClaims Management Challenges in the Modularized Construction Environment
Claims Management Challenges in the Modularized Construction Environment
Charles Fournier
 
Fabulous Pre-fabApplying Modular Construction to Multifamily.docx
Fabulous Pre-fabApplying Modular Construction to Multifamily.docxFabulous Pre-fabApplying Modular Construction to Multifamily.docx
Fabulous Pre-fabApplying Modular Construction to Multifamily.docx
lmelaine
 
Fabulous Pre-fabApplying Modular Construction to Multifamily.docx
Fabulous Pre-fabApplying Modular Construction to Multifamily.docxFabulous Pre-fabApplying Modular Construction to Multifamily.docx
Fabulous Pre-fabApplying Modular Construction to Multifamily.docx
mecklenburgstrelitzh
 

Similaire à TCE Paper on Modular Engineering (20)

2. Brief of the Invention
2. Brief of the Invention2. Brief of the Invention
2. Brief of the Invention
 
Opportunities and Challenges of Modular Coordination: A Review
Opportunities and Challenges of Modular Coordination: A ReviewOpportunities and Challenges of Modular Coordination: A Review
Opportunities and Challenges of Modular Coordination: A Review
 
PRESENT APPLICATION OFRESOURCE MANAGEMENT IN PREFABRICATED AND IN-SITU CONSTR...
PRESENT APPLICATION OFRESOURCE MANAGEMENT IN PREFABRICATED AND IN-SITU CONSTR...PRESENT APPLICATION OFRESOURCE MANAGEMENT IN PREFABRICATED AND IN-SITU CONSTR...
PRESENT APPLICATION OFRESOURCE MANAGEMENT IN PREFABRICATED AND IN-SITU CONSTR...
 
modular construction
modular construction modular construction
modular construction
 
Unit 6 A Construction Equipments for civil engineering.pdf
Unit 6 A Construction Equipments for civil engineering.pdfUnit 6 A Construction Equipments for civil engineering.pdf
Unit 6 A Construction Equipments for civil engineering.pdf
 
Cost and Quality Management in Buildings
Cost and Quality Management in BuildingsCost and Quality Management in Buildings
Cost and Quality Management in Buildings
 
Construction Equipment used in construction projects
Construction Equipment used in construction projectsConstruction Equipment used in construction projects
Construction Equipment used in construction projects
 
Modular Construction In India : Opportunities and challenges pdf notes
Modular Construction  In India : Opportunities and challenges pdf notesModular Construction  In India : Opportunities and challenges pdf notes
Modular Construction In India : Opportunities and challenges pdf notes
 
innovation.pptx
innovation.pptxinnovation.pptx
innovation.pptx
 
Seminar on modular building
Seminar on modular buildingSeminar on modular building
Seminar on modular building
 
CL 380_Unit-1 (1).pptx
CL 380_Unit-1 (1).pptxCL 380_Unit-1 (1).pptx
CL 380_Unit-1 (1).pptx
 
Claims Management Challenges in the Modularized Construction Environment
Claims Management Challenges in the Modularized Construction EnvironmentClaims Management Challenges in the Modularized Construction Environment
Claims Management Challenges in the Modularized Construction Environment
 
Seminar on Robotics in Construction
Seminar on Robotics in ConstructionSeminar on Robotics in Construction
Seminar on Robotics in Construction
 
INDUSTRIALISED BUILDING SYSTEMS & MODULAR COORDINATION
INDUSTRIALISED BUILDING SYSTEMS & MODULAR COORDINATIONINDUSTRIALISED BUILDING SYSTEMS & MODULAR COORDINATION
INDUSTRIALISED BUILDING SYSTEMS & MODULAR COORDINATION
 
Selection Criteria of Equipment in Construction Project
Selection Criteria of Equipment in Construction ProjectSelection Criteria of Equipment in Construction Project
Selection Criteria of Equipment in Construction Project
 
Birhanu
BirhanuBirhanu
Birhanu
 
Fabulous Pre-fabApplying Modular Construction to Multifamily.docx
Fabulous Pre-fabApplying Modular Construction to Multifamily.docxFabulous Pre-fabApplying Modular Construction to Multifamily.docx
Fabulous Pre-fabApplying Modular Construction to Multifamily.docx
 
Fabulous Pre-fabApplying Modular Construction to Multifamily.docx
Fabulous Pre-fabApplying Modular Construction to Multifamily.docxFabulous Pre-fabApplying Modular Construction to Multifamily.docx
Fabulous Pre-fabApplying Modular Construction to Multifamily.docx
 
Off-site and on -site modern method of construction
Off-site and on -site modern method of constructionOff-site and on -site modern method of construction
Off-site and on -site modern method of construction
 
PLANT LAYOUT
PLANT LAYOUTPLANT LAYOUT
PLANT LAYOUT
 

TCE Paper on Modular Engineering

  • 1. Special Report 205Chemical Weekly September 15, 2015 Abstract T he discussion in this paper out- lines modularization approach for standard chemical plants. Each aspect is elaborated in general starting from conceptualization till implementation including transporta- tion. These aspects are applicable to any plant (chemical or industrial) with standard parameters. Introduction Modularization was developed and adopted in the offshore structures to facilitate large volume of fabrication work to be carried out in shop in a con- trolled environment. Later on, the need was also felt for modular construction of other structure (Onshore) and is fast catching up in many countries, espe- cially developed countries. This discussion in this paper is limi- ted to modularization approach for standard chemical plants, especially in developing countries like India. In India, modularization approach is not very popular due to availability of large & cheap labour force; high transpor- tation cost due to varied geographical parameters across the country; lesser use of water transport etc. But in com- ing times, modularization approach will gain wider acceptance. Modularization of chemical plants: An overview Stefan Lier[1] and Marcus Grünewald, Ruhr-Universität Bochum of Germany, compared the econo- mics of a modular chemical plant with those of a traditional large-scale plant by investigating investment and ope- ration costs, combined with revenues, using a net present value analysis. They concluded that: “Modular plants consist of modules that autonomously operate parts of the plant. These mo- dules are technically and organization- ally limited areas of the plant that ful- fill defined tasks.” Starting with these modules, companies can create capa- city either by equaling up modules from general structures or by numbering up equipment. In the analysis carried out by them, the economics of a modular chemical plant are compared with those of a traditional large-scale plant by in- vestigating the net present value. The modular plant presents a more efficient concept for fast growing products or products with volatile demands. This is because the market impact during operation is more important than the preceding influence of the investment. In those cases, the effects of flexibility surpass the effects of scale. The conventional approach is in situ construction of facilities in- volved in any chemical plant, using SATISH DIWAKAR PRASHANT YEDE SAGAR KHATAV TATA Consulting Engineers Ltd. 4th Floor, Tower-B, 247 Park L B S Marg, Vikhroli Mumbai 400 083 sndiwakar@tce.co.in pkyede@tce.co.in skhatav@tce.co.in locally available construction men & materials. When such in situ con- struction is not feasible for any rea- son, modularization can be adopted to reduce the in situ work. This can be achieved by using pre-fabricated and pre-assembled modules at locations away from the site. Such pre-fabri- cated and pre-assembled modules are then transported either by road or ship depending upon the logistics require- ments and erected at site. Modules are generally a set of pre- assembled equipments and ancillaries such as piping, cable trays, cables, in- sulation etc. Modules may vary in size depending on design, installation, inter- facing and transportation constraints. Modularization facilitates re-us- ability, as module can be developed, tested, modified and reused multiple times reducing re-development time. Also, the modularized plant can be re- located from one location to another by dismantling. Key factors influencing modulariza- tion Modularization can be achieved by taking a “stick-build” design and divide into number of modules. Modulariza- tion is dependent on a detailed assess- ment of the key project parameters to determine the feasibility and the extent of modularization.
  • 2. Special Report Chemical Weekly September 15, 2015206 The key factors[3] are generally labour, site conditions, site access, schedule and safety. Refer Table 1 for key factors influencing modula- rization. It may not be possible to go for full modularization every time. Sometimes part modularization may be desirable considering the project parameters and in some cases it may be possible to go for full modulariza- tion. At times it may not be advisable to opt for modularization. However, total modularization cannot eliminate in situ construction activities such as site preparation, site enabling works, excavation, all civil works including foundations, erection of large fabri- cated steel vessels and final interfac- ing of the modules themselves. The key factor in modularization is the module size that can be fabricated, shipped, transported and erected at site. The maximum size and weight will vary from project to project, depend- ing on the geographical features, avail- ability of equipments for erection and dimensional & weight limitations of the transportation routes. Modules shall be generally fabri- cated at locations where labour rates and productivity skill index are suitable as compared to main construction site. However, higher level of modulariza- tion will not necessarily translate into cost savings as these will be offset to some extent against the cost of addi- tional steelwork, shipping and specia- list land transportation. Implementation Constructability aspects for modu- lar projects need to be reviewed well in advance as they impact decisions taken during feasibility and conceptual stages considering overall process, operation and maintenance requirements. Modularization decisions or chan- ges made during later stages of project can result in considerable rework and may increase overall cost & time to a great extent. A key consideration is the overall plant layout or plot plan, which should be designed to meet the extent of modularization considering all the points mentioned in Table 1. Also the interfacing between modules, erection sequencing, operation and maintenance requirements shall play an important role in making these decisions. Modular design also facilitates par- allel activities, i.e. several modules can be fabricated & built in parallel and can get assembled with higher speed. This helps in maintaining a smaller team at site; overall reduction in time and man- power cost. It can reduce WIP and as- sociated financial costs. Modularization can be classified in three categories. First generation[2] modularization such as pipe racks, platforms etc.; Second generation[2] modulariza- tion such as “customizing” equip- ment and other ancillaries mounted on structural steel skids; and Third generation[2] modulariza- tion such as “standardizing” and not customizing of the modules mount- ed with equipments and ancillaries. Considering strength and profes- sional experience of any engineering consultant in India, it is feasible to go for first and second generation modu- larization as it involves primarily cus- tomization, i.e. detail engineering based on the available equipment and schematic plant layout either provided by technology supplier or by customer. For third generation modulariza- tion, it is necessary to have own, patent- ed process technology or expertise of process licensor or technology supplier capabilities of providing technologies Table 1 Key factors influencing modularization Factor Influencers Labour Shortage of labour at the project site, or in the vicinity due to any reason Required competencies of available labour force Labour and productivity rate for site and shops; the pro- ductivity rate of skilled labour in shop is higher than field labour by 25-40%. Site conditions Impact of climatic conditions, e.g. cyclonic conditions, extreme cold, wind loading, rainfall, sandstorm, snow loads etc. Constraints on plot size and area Seismic zones, e.g. high seismic zones will require more ductile structure with great amount of detailing of joints, large member sizes for lateral load resisting members etc. Site access Available routes, infrastructure at site Schedule Constraints or requirements of the project schedule, which necessitate the implementation of modular ap- proach or the schedule benefit that would be achieved us- ing modular approach. Safety Stringent safety requirements of conventional construc- tion compared to modularization work.
  • 3. Special Report 207Chemical Weekly September 15, 2015 for standardization of plant modules depending upon various capacities and volume. However, engineering consul- tant may collaborate on long-term basis with technology supplier to acquire re- quired expertise, if he doesn’t possess one. First- and second-generation modu- larization The following inputs will be re- quired to carry out detail engineering of various modules to be provided. These inputs may help during conceptualiza- tion as well. The geographical details of site loca- tion, seismic zones, wind/cyclone/ hurricane factor, soil bearing capa- city, groundwater table, soil resis- tivity, prevalent wind direction and basic wind speed, rainfall, tempera- ture, humidity, snow loads, etc. Layout of the proposed plant Technological structure general ar- rangement layouts showing tenta- tive location of equipments. P & IDs for process and utilities. Customer’s design standards. Hazardous area classification. Data on industrial waste and waste- water treatment etc. Customer’s philosophy on sourcing spares. Details on the new electric power distribution system, viz. system voltage levels, loads, standby power supply etc. Master schedule for implementation of the plant, with scheduled deli- veries for directly sourced plant and equipment. Drawings, data sheets and founda- tion details for the equipment being sourced directly by customer. Module sizes intended depending upon the transportation, construc- tability, operation and maintenance requirements. Procedures for letter of intent, terms of payment, letter of credit, liquidated damages, guarantees, ef- ficiency demands, defects liability period etc. Knowledge of shipping and inland transportation constraints such as maximum dimension of shipping consignment, maximum weight for the individual module, etc. Preliminary 3D model of the tech- nology structure showing major equipments & piping, if available. Conceptualisation The conceptualisation stage is con- sidered to be very significant in any plant design. The key elements of con- ceptualization are Process Optimiza- tion and Energy Optimization. The following factors largely affect modular design: Process engineering; Equipment selection; Equipment layout and elevations; Piping and instrumentation; Size of modules; Interfacing of modules at site; and Availability of cranes in and around the site. Modularization has an influence on equipment selection and configuration for designing a compact plant layout. Modular designs normally have an optimized footprint compared to con- ventionally erected plants. The major- ity of the process equipments can be modularized and located in such a way to lower capital costs and thereby im- proving plant efficiency. Modular de- sign takes advantage of both horizontal and vertical layouts to locate equipment in a minimum space. A well-designed module can help to minimize space re- quirements, reduce piping and cable lengths. Process engineer shall be brought on board during conceptualization stage to extract maximum cost benefits out of modularization. The strategic de- cisions taken during conceptual stage on overall equipment layout, equip- ment configuration, piping layouts etc. may prove critical at later date. Engineers or designers involved should possess multi-disciplinary capa- bility to provide a design that envelopes domain expertise in process, structural, mechanical, piping, instrumentation & electrical design, procurement etc. Process engineering Process engineer shall have tho- rough knowledge of process involved, equipment layout, type of equipments that are required and available in mar- ket, various process alternatives, etc. Sometimes it is recommended to de- sign & purchase smaller components of equipments to facilitate modular design, instead of designing equipment that will not fit in the pre-defined module. Optimizing key process stages dur- ing the design phase leads to improve- ments in plant operation and thereby improve operating and maintenance cost. Process equipment may be more efficiently utilized by applying proprie- tary designs, converting batch ope- rations to continuous and reducing residence times from hours to minutes, depending upon the requirements. Process dynamics and control strategies can be optimized by care- fully matching the operating ranges of instrumentation and hydraulics to the equipment. Energy optimization Modular systems are best suited for energy optimization because of the closed circuit of the process. Process loop or circuit lengths are shorter in modules, which increases the overall efficiency of the plant due to elimination of the long lengths of piping. Shorter lengths of pip- ing helps in minimizing heat loss and condensation in the pipelines.
  • 4. Special Report Chemical Weekly September 15, 2015208 In the current industrial scenario of alternative fuels, a properly designed modular system using innovative pro- cess techniques can reduce CAPEX & OPEX, thereby reducing utility loads through process & energy optimization. Civil & Structural engineering The design of modular fabrication shall have following Civil and Struc- tural design requirements: Size limitation of the module Each module shall be sized, based on the maximum transportable length, breadth and height in con- sultation with process collaborator or technology supplier. Planning of each module shall cater, as far as possible, for self-contain- ment of equipment and associated piping works. Cutting section plane for the modules. The module size shall be selected as a self-standing structure for avoid- ing imbalance during shipment. Analysis of the modules The entire structure as a single mo- dule will be analyzed with “PIN” connection at module interface. This analysis is intended to arrive at overall structural integrity once the plant is commissioned. The plant is sub-divided in to vari- ous modules as explained earlier. Each module will be analysed as independent structure during erec- tion. The erection scheme needs to be discussed with the contractor or can be decided by engineering con- sultant. The modules during shipment and transportation may have to be arranged in a manner different than its intended position. Such changes require separate set of analysis. A typical flow chart indi- cating the different stages that are involved in modular design is given in Figure 1. Structural design The structural members shall be designed to account for the forces acting during handling, lifting and transportation. All structures shall be analyzed and qualified for such loads other than the normal design loads like equip- ment load, seismic load, normal wind load etc. Additional strengthening may be provided to resist critical forces or to avoid any deformity during trans- portation Identifying the module sections and lifting points. Structure to be stable and safe in assembled module as well as in the final constructed form. All site joints to be designed as bolt- ed joints and all shop joints shall be welded joints.Fig. 1: Typical flow chart of modular design Yes Yes Yes Yes No No No No Permanent Permanent Permanent Permanent Reinforce structure Reinforce structure Reinforce structure Reinforce structure Incorporate in combined model End Start Integrated in place structural analysis Individual module in place analysis Lifting analysis Up righting analysis Transportation analysis Temporary bracing Temporary bracing Temporary bracing Temporary bracing Acceptable result Acceptable result Acceptable result Acceptable result
  • 5. Special Report 209Chemical Weekly September 15, 2015 Permanent or temporary reinforce- ment techniques shall be adopted for members likely to be over- stressed during lifting and trans- portation. Connections shall be de- signed for maximum capacity of the member and checked for stresses arising during lifting and transpor- tation analysis. Material of construction Rolled steel members, Wide/paral- lel flange sections and plates from approved Indian or foreign suppli- ers shall be used as structural mem- bers. Special corrosion protection allow- ance or paints to be used to take care of transport and handling. Additional loading during handling Tensile and compressive stresses arising from lifting & transportation analysis of the modules. Rolling, pitching, “heave & yaw” effects of the ship on modules. Adequate packing or temporary supports (wooden/steel bracings/ lacings, shock absorbing materials, etc.) need to provided for the equip- ments and other ancillaries mounted on modules during transportation. Generally for lifting and transpor- tation analysis, API RP-2A & GL Noble Denton guidelines may be followed. Checks required prior to shipment Completeness of the end connec- tions, checking/testing of weld con- nections & materials. Completion of painting and touch up painting before release of the modules for shipment. Additional temporary bracing members to cater to stresses aris- ing from transportation as well as “Set Down” and “Load out Beam” analysis. Completion of the tag numbers to all the modules, spare connecting members and match marking. Demonstrate rigidity of the mo- dule by lifting it to a small height duly slung to the lifting hook. Prior to shipment, check mark- ing of centre of gravity (COG) on modules for lifting operations. Weight control report shall be pre- pared before despatch of modules to site. Civil and structural works required at site Foundations. Installation of the modules as per the erection sequencing procedure. Grouting. Interconnection of the modules with prefabricated structural members either by bolting or welding. Installation of the prefabricated ope- rating platforms after erection of stand-alone equipment. Installation of prefabricated pipe supports, minor equipment struc- tures outside of the module. Touch up painting. Encasement and/or fire-proof con- creting. Mechanical design Mechanical designs shall follow the relevant standards, codes of prac- tices such as ASTM, ASME, TEMA, API, IBR and BIS etc. Flexibility shall be one of the key components of me- chanical design. Bolted joints shall be preferred over welded joints. Interfac- ing for the pipes between two modules shall be with spool pipe. Sizing of equipment, pipelines for process & utility and selection & loca- tion of valves & instruments shall be a part of detailed engineering as per the Project/Plant Design Manual, P & IDs, Data Sheets and relevant codes and standards. Equipment layout shall feature adequate space for O & M, aesthetics and ergonomics, headroom clearances and adherence to the local/ international safety norms such as OSHA. Preferably all the equipment, com- ponents, instruments, valves, pipes, gaskets, fasteners, special tools, con- sumable and capital spares etc., should be sourced from indigenous reputed and ISO certified manufacturers/sources. Provision for easy and fast mounting of imported items, if any, with minimal deployment of men & machinery shall feature in the module. Process pumps that are to be posi- tioned on the modules shall be aligned with suction and delivery pipes con- nected. Pumps that are to be installed outside the modules shall be shipped separately with the pump and its drive aligned but short of dowel pins. This arrangement shall also be applicable to other rotary equipment. Access, i.e. walkway/inter-connect- ing platforms, to the tall towers such as reactors, stacks, refiners, distillers,
  • 6. Special Report Chemical Weekly September 15, 2015210 strippers etc., shall be featured from re- lated modules. On the fabricated module, posi- tioning of the equipment shall be com- pleted first. Placement of pipelines shall be after alignment of majority of the equipment. Prior to erection of the fabricated pipes onto the modules, the inside surfaces shall undergo thorough mechanical cleaning using a combina- tion of sponge balls and compressed air or other acceptable practices. Where flange joints are involved, such joints should be at the interface of the mo- dules or with flanged pipe spool. Welded pipe joints requiring stress relieving shall be completed to the maximum extent on the modules. Metal ring type flanged joints may be used for high pressure lines at the point of sepa- rating out from the module to eliminate onsite weld joints with stress relieving. Pipe isometrics running outside the modules shall be fabricated in single or multiple loops and housed in corre- sponding modules for shipment. Each module shall be identified with a distinct number. Pipeline designation number and tag number for equipment, valves, instruments etc. shall be pre- fixed with the module identification number. Tags, punch marks or perma- nent inscriptions shall be used for iden- tification. Match marks are preferred for pipe loops for onsite assembly. Equipment, pipes and valves requir- ing thermal insulation shall be wrapped in the approved insulation material with aluminium sheet cladding. Configured spare insulation shall be supplied loose for onsite fixing at interface of the mo- dules. Fireproofing, also, shall be pro- vided where applicable. Instrumentation design All the control room mounted equipment such as DCS/PLC/SCADA system packages shall be sourced either locally or abroad as these re- quire vendor’s assistance for en- abling, commissioning and fine tun- ing as per process requirements. As part of the module, the following shall be housed: Field instruments, control valves, junction boxes and power supply distribution boards. Cabling between the field instru- ments, junction boxes and power distribution boards, which are con- tained within the module. Cable trays and conduits for the ca- bling within the module. All impulse tubing, fittings supports required for transmitters. Local control panel, pneumatic control panels and hydraulic power pack required for equipment con- tained within the modules. The multi-core cables and cable trays from junction boxes to DCS/PLC system in the control room shall be laid at site. Analyzer shelter along with analyzer panels & sample conditioning panels installed in it shall be transport- ed as one module. The sampling lines and cabling for same shall be carried out at site. Instrumentation and control system design and documentation shall be car- ried out by using internationally proven software such as “INTOOLS”. I&C system design shall follow the relevant code, standards and practices such as NFPA, UL/CSA, IEC, EN and ISA. Electrical design Electrical design shall comply with the relevant codes, standards and prac- tices such as NFPA, ANSI/IEEE, UL/ CSA, IEC and EN. Modules shall house the local power distribution board, control consoles, fire alarm panel etc. Cable carrier sys- tem consisting of cable trays, tray sup- ports shall be included along with the pipe rack. The module shall include poles, towers, & other supports for mounting of lighting fixtures complete with wiring. However, the fixtures will be fitted on site. The protection enclo- sure within the modules shall be speci- fied and provided as per hazardous area classification for that module. For cables emanating & terminating within the module, cable pulling and
  • 7. Special Report 211Chemical Weekly September 15, 2015 termination will be executed as a part of the module. Cable pulling for the cables joining one module to another will be carried out on site. The main earth strip will be in- stalled on the cable tray and individual equipment earth leads will be welded to this main earth strip. All connections to earth pits/earth electrodes will have to be done at site. The lightening protection for build- ing/structure/vessels, if required, shall be done at site. Safety aspects Safety standards and codes as ap- plicable to the industry and as required by the concerned local authorities shall be adhered to while designing the plant, equipment, layouts and utility services. The agency(s) appointed for fabrica- tion of the modules shall be required to submit their safety plans for approval, prior to commencement of work. The vendor shall indemnify the purchaser against charges/penalties on the vendor for violation of safety norms resulting in damages to the equipment, machi- nery, handling apparatus/equipment etc., and/or against injury, accident or death of labour deployed on this job. Safety norms for electrical equip- ment shall be in conformity with the rules and regulations stipulated by the competent authorities of the country in which the plant is being installed and operated. Special design considerations The plant shall be modeled in 3D environment. The model shall initially show the following: Structural steel supporting frame- work for individual module. Lifting points and guying points for the modules. Structural steel columns, beams, stairways, walkways/leeways, floor gratings, hand railing, toe plates, monorails etc. Plant and equipment. Pipelines, valves, and specialties. Cable trays. Monorails. Identify large/over-sized equipment such as columns/reactors/vessels etc., which needs to be transported or shipped and erected separately at the plant site. Emphasis shall be to spread the plant and equipment installed on the modules to ensure adequate lee ways, head room clearances, clear passage for movement of person- nel and materials handled by the monorails, access for external crane hook, adequate space around the equipments for maintenance etc. Layout and spacing of the cable car- riers should facilitate safe and easy cable pulls. Light fittings shall be easily accessible for replacement of lamps. Layout of the lights shall be spread to provide desired illumina- tion lumens. Conclusion Modular design and construction is most suited to almost all plants having standard parameters with less degree of variability. It has brought significant change in the nature of engineering ser- vices that are being offered today espe- cially. In India, it may gain acceptance and momentum little slower as com- pared to the developed countries, due to availability of large labour. To remain competitive in the international market in the future, it is necessary for engineer- ing consultants in India to provide engi- neering services (in India and abroad) for “Third Generation” modular design by either joint venture or long term association with technology suppliers (in- ternational and domestic). References 1. S. Lier. “Net Present Value Analysis of Modu- lar Chemical Production Plants”, Chemical Engi- neering & Technology, 05/2011. 2. “IQPC Modular Con- struction and Fabrication 2013” Conference. 3. “Chemical Plant Design and Construction,” Rich- ard Brookfield and Jere- mey Cooke.