SlideShare une entreprise Scribd logo
1  sur  23
Télécharger pour lire hors ligne
NTPC Tamilnadu Energy Company Ltd
Velammal
Engineering
College
Report on Training
underwent at Vallur
Thermal Power Project
29-06-2015 to 12-07-2015
Er.R.S.RAJPRASAD
ACKOWLEDGEMENT
I express my sincere thanks to NTPC TamilNadu Energy
Company Ltd for offering me this opportunity to be trained at
Vallur Thermal Power station, Chennai.
I express my profound sense of gratitude to
Shri.Rajendran, Deputy Manager(Electrical Maintainance),
NTPC for his valuable guidance during the course of the
training programme.
I take this opportunity to thank all the Engineers ,
Supervisors and other workers on site for their support during
the course of this training programme.
ABSTRACT
This report inculcates the quantum of knowledge
grasped as a part of the training programme that was offered
at the Vallur Thermal Power Project.
Based on the experience imbibed by virtue of understanding
the nuances of Practical applications, the observations carried
out are briefed out in this report.
The Entire course of training can be
sectionalized into following…
- Testing of Switchgear Relays
- Battery Capacitance Test
- Testing of Transformers
- Stability Test for H.T motor Relays
- Study of the Plant profile
TESTING OF SWITCHGEAR RELAYS
Switchgear devices are situated at the key points of electrical
energy transmission and distribution systems.
Their reliability has a decisive influence on the availability,
safety and economic efficiency of electricity supply systems.
Only regular, on-site tests can ensure that switchgear devices
function perfectly throughout their operational life.
The CMC 256plus is the first choice for applications requiring
very high accuracy. This unit is not only an excellent test set
for protection devices of all kinds but also a universal
calibrator.
Its high precision allows the calibration of a wide range of
measuring devices.
Its unique accuracy and flexibility make the CMC 256plus
ideal for protection and measurement equipment
manufacturers for research and development, production and
type testing.
The Various tests carried out on the Swithgear relay using
CMC 256 Plus are as follows :
- Overcurrent Protection Test
- Differential Protection Test
- Earth Fault Protection Test
OVERCURRENT PROTECTION TEST:
To evaluate the feasibility for overcurrent
protection offered by the Relay, the pick up value for the
relay is set and corresponding current above the pick up
value is injected into the C.T input of the relay.
If the Relay triggers the trip signal
depending on the time setting (instantaneous or definite
time), then the relay is said to reliable in its operation.
DIFFERENTIAL PROTECTION TEST:
In Differential protection test, the currents
corresponding to the inputs from the two C.T’s are injected
into the relay and is checked .If the relay reacts to the
differential current and executes the corresponding logic
depending upon the magnitude of the differential current,
then the relay is considered to be fit for differential
protection.
EARTH FAULT PROTECTION TEST:
A low level arcing ground fault can destroy
switchgear in seconds, before the main service overcurrent
protection will operate. A 480/277 volt solidly grounded
system has sufficient voltage to maintain an arc between one
phase and a ground but not enough current to cause a large
main breaker or fuse to clear the fault quickly. The resulting
arc is similar to an electric weld, consuming large amounts of
metal in the seconds it takes the breaker or fuse to operate. A
properly installed and operating ground fault protection
system will detect and clear the fault in milliseconds, fast
enough to limit damage to acceptable levels.
Using CMC 256 plus, an earth fault is simulated
and checked if the relay reacts effectively to it, within the
ensured response time.
These are the major tests associated
with the testing of Switchgear relays.
BATTERY CAPACITANCE TEST
The Battery capacitance test is an important test,
that has to be carried out regularily , so as to ensure the
healthiness of the battery banks and assure reliable support
in case of crisis.
The Various steps involved in the Battery
charging test are as follows :
 Initially check the charging unit if it is in proper
condition to charge the battery unit after it is
discharged. For this, boost the battery from the charger
unit and check.
 Now, isolate the load side from the DCDB (DC
distribution board) .
 Connect a resistive load bank to the rectifier output
terminals of the charging unit, after proper isolation of
the previous load terminals.
 Now, close the load isolator switch in the DCDB and add
the load from the resistive load bank.
 After discharging the entire battery bank, check for the
electrolyte parameters, clean if needed and carry out
other maintenance work if required.
 Now remove the Resistive load and start boost charging
the battery bank from the charger unit.
Thus the battery capacitance test is carried out to
ensure the healthiness and reliability of the battery bank so
that it is assured to be available whenever it is needed.
TESTING OF TRANSFORMERS
For confirming the specifications and performances
of an Electrical power transformer, it has to go through
numbers of testing procedures. Some tests are done at
manufacturer premises before delivering the transformer. In
addition to that some transformer tests are also carried out at
the consumer site before commissioning and also periodically
in regular & emergency basis throughout its service life.
During the course , UNIT II was shut down and all the
associated auxiliaries were taken for annual maintainance.
So, the tests carried out on the Generator Transformers (G.T)
are listed below.
The various tests carried out on site on the
single phase Generation Transformers are as follows :
Insulation Resistance Test
Magnetizing Current Test
Short Circuit Test
Turns Ratio Test
Winding Resistance Test
Tan-delta Test
Test 1 : INSULATION RESISTANCE TEST:
Basically, the Insulation Resistance test is
carried out to verify the insulation levels of the windings of
the transformer as insulation is the most important factor
that determines the substantial quality of operation of an
electrical component.
Testing Apparatus: HV Digital Megger
 The applied voltage from the megger is 5KV
 The resultant IR value obtained will be in GΩ and is
measured at 60 seconds.
 The test point terminals between which the IR value is
measured are
- HV to Ground
- LV to Ground
- HV to LV
Test 2 : MAGNETIZING CURRENT TEST:
The Magnetizing current test is carried out , so as to
measure the approximate magnetizing currents flowing
through the winding.
NOTE: As it is practically impossible to determine the exact
magnetizing currents flowing in HV winding, a low voltage
is injected and checked.
z
t
 Apart from the winding to be tested, the other terminal
is kept open .
 On the winding to be tested, inject voltage on the
terminals and measure the current flowing through the
winding using clamp meter
 The injected voltage is 242.7 V
Transformer
SUPPLY
MEASURING NODE
Test 3 : SHORT CIRCUIT TEST:
The Short circuit Test is another important test to be
carried out in a transformer, to assess the magnitude of
current flowing in the HV side due to any short circuit faults
in the LV side.
z
t
 Initially the LV side is shorted using shorting cable
 Now, voltage of 246.8 (approx) is injected on the HV
terminals
 The corresponding current flowing through the HV and
LV windings are measured
 The value measured in LV side would be in mA, while the
value measured in HV side would be in A .
Transformer
LV
HV
SUPPLY
Test 4 : TURNS RATIO TEST:
The turns ratio test is carried out to analyze the
actual ratio of turns within the transformer windings and
the percentage of error associated with it.
Testing Apparatus: MEGGER TTR320
 Connect the cables “CABLE H” and “CABLE X”
 Ground the Kit
 Connect H1 and H2 to the HV side
 Connect X1 and X2 to the LV side
HV LV
H1
H2
X1
X2
Diagram selected in kit for test:
Voltage Rating:
HIGH LOW
230.900
21.000
TAPS 7
On entering the data, the following parameters will
automatically be calculated by the kit :
 Actual Ratio
 % Error
 Excitation Current
 Phasor Deviation
K (Turns ratio)=V2/V1= N2/N1=I1/I2
1:1 1:2 2:1 2:2
Test 5 : WINDING RESISTANCE TEST:
The winding Resistance Test is carried out to calculate and
analyze the resistance offered by the winding to the flow of
current.
Testing Apparatus: MEGGER TTR320
 The C+ and C- wires are connected at the terminals of
the winding to be tested
 The V+ and V- wires are connected on the path of C+
and C- respectively as shown in figure.
C+
C-
V+
V-
 The Injected DC current is 10A
The observations made on the HV and LV windings are
as follows :
HV winding : R=165 mΩ
LV winding : R=880 mΩ
Test 6 : TAN-DELTA TEST:
The Tan-delta test is one of the most important
tests carried out in a transformer. The Tan-delta test is
mainly carried out to determine the capacitance and
dissipation factor of the transformer.
Dissipation factor = IR/IC
Testing Apparatus: OMICRON CPC 100 and CP TD1
 After all the connections are made, the kit is switched
ON.
 There are two modes of testing: - UST mode and GST
mode
 UST- Ungrounded Specimen Test
GST- Grounded Specimen Test
 In UST mode, tests are run between HV-Tandelta point
and HV-LV
 In GST mode, tests are run between HV-Ground and
Tandelta point-Ground
 Guard is used whenever accuracy in results are required
 The Injected Voltages are as follows:
-For higher capacitance : 2kV,5kV and 10kV
-For lower capacitance : 300V and 500V
Thus , depending on the dissipation factor, the ageing of
the transformer is determined.
STABILITY TEST FOR HT MOTOR RELAY
The Stability test for HT motor Relay is
mainly done to assure the reliability of the Motor protection
Relay towards Internal Faults.
In this test, an internal fault is simulated by
manually charging the winding terminals with a variac
connected to an external source.
Now, it is observed whether the relay
picks up the fault immediately and trips .
Thus, the stability test ensures that the
relay acts in a feasible manner for any kind of internal faults.
STUDY OF PLANT PROFILE
Vallur Thermal Power Station is a
power plant located in Athipattu village, Vallur in Thiruvallur
district, North Chennai, India. The power plant is operated by
NTPC Tamil Nadu Energy Company Limited, a joint venture
between NTPC Limited and TANGEDCO and has three units
with 500 MW each.
In January 2014, the units in the power plant achieved a
record generation of 24.09 million units of electricity.[1] The
project adds nearly 24 million units a day to the grid. Tamil
Nadu is the major beneficiary of power generated from this
facility (about 750 MW), while some of it is supplied
to Andhra Pradesh, Karnataka, Kerala, and Puducherry.
The plant will consume 4.62 mt of coal a year. Coal for the
plant will be brought from Orissa through ship to Ennore
Port, from where it will be transported by closed belt
conveyor system.
The boiler systems at the plant consists of single- or two-pass
type, with front/rear/side mill layout, which can have
single/bi-drum arrangement with natural or controlled
circulation. There is constant or sliding pressure operation,
and hot or cold primary air systems. Steam turbine operates at
a speeds of 3,000 rpm. The main steam is at 130–250 bar at
500–540 °C. Steam reheat is at 30–70 and 500–600 °C. The
back pressure is between 20 and 300 mbar.
The plant has six induced draft cooling towers (IDCTs), which
have a capacity of 30,000 m3/h with nine cells of 21 × 14
m each.The IDCTs use seawater, which is drawn from the
intake channel of North Chennai Thermal Power Station, and
fresh water requirement is met from a desalination plant. The
plant has adopted closed cycle re-circulating type cooling
water system for its operations.
The coal conveyor system in the plant includes a 4.4-km-long
pipe conveyor with a capacity of 4,000 tonnes/hour, which is
the world's largest pipe conveyor.
The plant requires 13,400 tonnes of coal per day, and 53
percent of the need is met from domestic coalfields and the
remainder through coal imports.
Following is the unit wise capacity of the 1500 MW plant.
Stage Unit Number Installed Capacity (MW)
Stage I 1 500
Stage I 2 500
Stage I 3 500
GAS INSULATED SWITCHYARD :
A Gas Insulated Switchgear substation (GIS substation) uses
Sulfur hexafluoride gas (SF6 Gas) whose dielectric strength is
higher than air, to provide the phase to ground insulation for
the switchgear of an electrical substation. This works where
by the conductors and contacts are insulated by pressurized
SF6 gas meaning clearances required are smaller than that of
AIS substations. The main advantage of the GIS substation is
that this phase to phase spacing can be reduced significantly
resulting in a substation with comparable load capability to
an AIS substation but with a much smaller compound
footprint. This is particularly advantageous in an urban
environment where land size is at a premium. It also results in
a smaller visual impact on a landscape as it can result in a
significantly smaller footprint than its AIS counterpart.
The GIS switch gear shall be of modular design offering high
degree of flexibility. Each module shall be complete with SF6
gas circuit breaker, Disconnectors, Maintenance Grounding
switches, fast Earthing switches, voltage transformers,
Current transformers, bus & elbow sections, cable end
enclosures, L.A., local control cubicle and all necessary
components required for safe & reliable operation and
maintenance. All the three phases of the busbars and
associated equipments like breakers, disconnectors,
instrument transformers & earthing switches etc., are to be
encapsulated in a single gas filled metallic enclosure for 66 &
132 kV voltage class and phase wise separate metallic
enclosures for 400 kV class. The bus bars shall be sub-divided
into compartments including the associated bus bar
disconnector. Bus bars are partitioned at each bay with an
objective to isolate Busbar compartment for the purpose of
extension and at the same time avoid damage to adjacent
bays in the event of fault.
In the past, there was also a concern that only the original
manufacturer of an installation would be willing to accept the
risk of offering an expansion to that installation. The concern
was the integrity of the seals at the point where the original
installation and the expansion came together. As a result, a
purchaser who committed to a GIS installation was
perpetually tied to the supplier of that installation for any
future expansion needs, and this put the purchaser at the
mercy of that supplier in future expansions. In recent years,
manufacturers have overcome the technical issues of assuring
the reliability of the seals between dissimilar equipment, so
this problem is less significant today.
Thus, the Vallur Thermal Power Project boasts for its
effectively designed Gas insulated switchgear, thereby
proving to be space efficient in design and pioneering in the
art of keeping pace with the growing electrical technology
and trends.
CONCLUSION:
In review, this internship has been an excellent and
rewarding experience. I have been able to meet and network
with so many people , which I would carry ahead in the years
to come.
My experience at Vallur Thermal Power Project has been
invaluable. I thoroughly enjoyed my position and learned a
great deal about all the various aspects of a major Generating
utility.
During the course of training, the insight into professional
practices helped me acquire Practical skills and link theory to
practice in the real Power System workspace.
This training was beneficial for me and I’m thankful that I got
experience to learn many things.

Contenu connexe

Tendances

Power transformer maintenance
Power transformer maintenancePower transformer maintenance
Power transformer maintenanceLucian Lazar
 
sivachandran resume
sivachandran resumesivachandran resume
sivachandran resumesiva karnan
 
Remediation of Old Substations for Arc Flash hazard
Remediation of Old Substations for Arc Flash hazardRemediation of Old Substations for Arc Flash hazard
Remediation of Old Substations for Arc Flash hazardIJAPEJOURNAL
 
Quasi-resonant Flyback Converter Simulations with Saber - APEC 2016
Quasi-resonant Flyback Converter Simulations with Saber - APEC 2016Quasi-resonant Flyback Converter Simulations with Saber - APEC 2016
Quasi-resonant Flyback Converter Simulations with Saber - APEC 2016Alan Courtay
 
ELECHTRICAL COMMISSIONING TECHNICIAN 2201622
ELECHTRICAL   COMMISSIONING  TECHNICIAN   2201622ELECHTRICAL   COMMISSIONING  TECHNICIAN   2201622
ELECHTRICAL COMMISSIONING TECHNICIAN 2201622MOHAMMAD KHALID MUSTAFA
 
TRANSFORMER TEST acceptance criteria
TRANSFORMER TEST acceptance criteriaTRANSFORMER TEST acceptance criteria
TRANSFORMER TEST acceptance criteriaRajuGupta88
 
Ashok Resume-2015
Ashok Resume-2015Ashok Resume-2015
Ashok Resume-2015ashok kumar
 
Relay Setting Calculation For REF615/ REJ601
Relay Setting Calculation For REF615/ REJ601Relay Setting Calculation For REF615/ REJ601
Relay Setting Calculation For REF615/ REJ601SARAVANAN A
 
Project Presentation :Analysis and characterization of different high density...
Project Presentation :Analysis and characterization of different high density...Project Presentation :Analysis and characterization of different high density...
Project Presentation :Analysis and characterization of different high density...Aalay Kapadia
 
Vipin Resume
Vipin ResumeVipin Resume
Vipin ResumeVipin Das
 
TRANSFORMER SAMPLE REPORT DGA PHYSICAL CONDITION
TRANSFORMER SAMPLE REPORT DGA PHYSICAL CONDITION TRANSFORMER SAMPLE REPORT DGA PHYSICAL CONDITION
TRANSFORMER SAMPLE REPORT DGA PHYSICAL CONDITION RajuGupta88
 
IRJET- Auto Earth System for HV Test Set Up for Transformer in Applicatio...
IRJET-  	  Auto Earth System for HV Test Set Up for Transformer in Applicatio...IRJET-  	  Auto Earth System for HV Test Set Up for Transformer in Applicatio...
IRJET- Auto Earth System for HV Test Set Up for Transformer in Applicatio...IRJET Journal
 
IRJET- Design of Single Phase High Frequency Inverter for Wireless Charging A...
IRJET- Design of Single Phase High Frequency Inverter for Wireless Charging A...IRJET- Design of Single Phase High Frequency Inverter for Wireless Charging A...
IRJET- Design of Single Phase High Frequency Inverter for Wireless Charging A...IRJET Journal
 

Tendances (20)

Power transformer maintenance
Power transformer maintenancePower transformer maintenance
Power transformer maintenance
 
sivachandran resume
sivachandran resumesivachandran resume
sivachandran resume
 
cv of pjnehru
cv of pjnehrucv of pjnehru
cv of pjnehru
 
Remediation of Old Substations for Arc Flash hazard
Remediation of Old Substations for Arc Flash hazardRemediation of Old Substations for Arc Flash hazard
Remediation of Old Substations for Arc Flash hazard
 
QA/QC ENGINEER
QA/QC ENGINEERQA/QC ENGINEER
QA/QC ENGINEER
 
Quasi-resonant Flyback Converter Simulations with Saber - APEC 2016
Quasi-resonant Flyback Converter Simulations with Saber - APEC 2016Quasi-resonant Flyback Converter Simulations with Saber - APEC 2016
Quasi-resonant Flyback Converter Simulations with Saber - APEC 2016
 
New cv jithesh
New cv jitheshNew cv jithesh
New cv jithesh
 
CM_APW_2015
CM_APW_2015CM_APW_2015
CM_APW_2015
 
Satham Mohamed.A-CV..
Satham Mohamed.A-CV..Satham Mohamed.A-CV..
Satham Mohamed.A-CV..
 
ELECHTRICAL COMMISSIONING TECHNICIAN 2201622
ELECHTRICAL   COMMISSIONING  TECHNICIAN   2201622ELECHTRICAL   COMMISSIONING  TECHNICIAN   2201622
ELECHTRICAL COMMISSIONING TECHNICIAN 2201622
 
TRANSFORMER TEST acceptance criteria
TRANSFORMER TEST acceptance criteriaTRANSFORMER TEST acceptance criteria
TRANSFORMER TEST acceptance criteria
 
Ashok Resume-2015
Ashok Resume-2015Ashok Resume-2015
Ashok Resume-2015
 
Relay Setting Calculation For REF615/ REJ601
Relay Setting Calculation For REF615/ REJ601Relay Setting Calculation For REF615/ REJ601
Relay Setting Calculation For REF615/ REJ601
 
Project Presentation :Analysis and characterization of different high density...
Project Presentation :Analysis and characterization of different high density...Project Presentation :Analysis and characterization of different high density...
Project Presentation :Analysis and characterization of different high density...
 
loai_Resume
loai_Resumeloai_Resume
loai_Resume
 
Vipin Resume
Vipin ResumeVipin Resume
Vipin Resume
 
Transformers
TransformersTransformers
Transformers
 
TRANSFORMER SAMPLE REPORT DGA PHYSICAL CONDITION
TRANSFORMER SAMPLE REPORT DGA PHYSICAL CONDITION TRANSFORMER SAMPLE REPORT DGA PHYSICAL CONDITION
TRANSFORMER SAMPLE REPORT DGA PHYSICAL CONDITION
 
IRJET- Auto Earth System for HV Test Set Up for Transformer in Applicatio...
IRJET-  	  Auto Earth System for HV Test Set Up for Transformer in Applicatio...IRJET-  	  Auto Earth System for HV Test Set Up for Transformer in Applicatio...
IRJET- Auto Earth System for HV Test Set Up for Transformer in Applicatio...
 
IRJET- Design of Single Phase High Frequency Inverter for Wireless Charging A...
IRJET- Design of Single Phase High Frequency Inverter for Wireless Charging A...IRJET- Design of Single Phase High Frequency Inverter for Wireless Charging A...
IRJET- Design of Single Phase High Frequency Inverter for Wireless Charging A...
 

Similaire à REPORT -VALLUR THERMAL POWER PLANT

INSTALLATION OF 500MVA TRANSFORMER AT PGCIL
INSTALLATION OF 500MVA TRANSFORMER AT PGCIL INSTALLATION OF 500MVA TRANSFORMER AT PGCIL
INSTALLATION OF 500MVA TRANSFORMER AT PGCIL Rahul Akinapelli
 
Chapter 5 mukesh gurjar
Chapter 5 mukesh gurjarChapter 5 mukesh gurjar
Chapter 5 mukesh gurjarMukesh gurjar
 
Testing,maintenance&protection
Testing,maintenance&protectionTesting,maintenance&protection
Testing,maintenance&protectionRakesh Joshi
 
220kv grid wapda town lahore
220kv grid wapda town lahore220kv grid wapda town lahore
220kv grid wapda town lahoresammy9916
 
TESTING,MAINTENANCE&PROTECTION.ppt
TESTING,MAINTENANCE&PROTECTION.pptTESTING,MAINTENANCE&PROTECTION.ppt
TESTING,MAINTENANCE&PROTECTION.pptChristinaBoyd12
 
93518813-TESTING-MAINTENANCE-PROTECTION-OF-DISTRIBUTION-TRANSFORMERS.ppt
93518813-TESTING-MAINTENANCE-PROTECTION-OF-DISTRIBUTION-TRANSFORMERS.ppt93518813-TESTING-MAINTENANCE-PROTECTION-OF-DISTRIBUTION-TRANSFORMERS.ppt
93518813-TESTING-MAINTENANCE-PROTECTION-OF-DISTRIBUTION-TRANSFORMERS.pptsantubanga333
 
TESTING,MAINTENANCE&PROTECTION.ppt
TESTING,MAINTENANCE&PROTECTION.pptTESTING,MAINTENANCE&PROTECTION.ppt
TESTING,MAINTENANCE&PROTECTION.pptssuser1f60f6
 
Power transformer testing and commissioning guidelines r
Power transformer testing and commissioning guidelines rPower transformer testing and commissioning guidelines r
Power transformer testing and commissioning guidelines rAshish Patel
 
Isolator and bushing
Isolator and bushingIsolator and bushing
Isolator and bushingNovia Putri
 
Presentation OutDoorSwithGear(AIS) .pptx
Presentation OutDoorSwithGear(AIS) .pptxPresentation OutDoorSwithGear(AIS) .pptx
Presentation OutDoorSwithGear(AIS) .pptxRAJKIRANR3
 
AC Circuit Breakers Routine Tests according to IEC 62271-100
AC Circuit Breakers Routine Tests according to IEC 62271-100AC Circuit Breakers Routine Tests according to IEC 62271-100
AC Circuit Breakers Routine Tests according to IEC 62271-100Ali Sepehri
 
Distribution Transformer testing, West Bengal, India
Distribution Transformer testing,  West Bengal, IndiaDistribution Transformer testing,  West Bengal, India
Distribution Transformer testing, West Bengal, IndiaRajuMondal18
 

Similaire à REPORT -VALLUR THERMAL POWER PLANT (20)

INSTALLATION OF 500MVA TRANSFORMER AT PGCIL
INSTALLATION OF 500MVA TRANSFORMER AT PGCIL INSTALLATION OF 500MVA TRANSFORMER AT PGCIL
INSTALLATION OF 500MVA TRANSFORMER AT PGCIL
 
EIT_Presentation
EIT_PresentationEIT_Presentation
EIT_Presentation
 
Relay testing procedure
Relay testing procedure Relay testing procedure
Relay testing procedure
 
Fusing Metering Voltages for High Capacity Circuits
Fusing Metering Voltages for High Capacity CircuitsFusing Metering Voltages for High Capacity Circuits
Fusing Metering Voltages for High Capacity Circuits
 
Chapter 5 mukesh gurjar
Chapter 5 mukesh gurjarChapter 5 mukesh gurjar
Chapter 5 mukesh gurjar
 
Testing,maintenance&protection
Testing,maintenance&protectionTesting,maintenance&protection
Testing,maintenance&protection
 
220kv grid wapda town lahore
220kv grid wapda town lahore220kv grid wapda town lahore
220kv grid wapda town lahore
 
Unit 1-2-b
Unit 1-2-bUnit 1-2-b
Unit 1-2-b
 
Testing of transformer
Testing of transformerTesting of transformer
Testing of transformer
 
TESTING,MAINTENANCE&PROTECTION.ppt
TESTING,MAINTENANCE&PROTECTION.pptTESTING,MAINTENANCE&PROTECTION.ppt
TESTING,MAINTENANCE&PROTECTION.ppt
 
93518813-TESTING-MAINTENANCE-PROTECTION-OF-DISTRIBUTION-TRANSFORMERS.ppt
93518813-TESTING-MAINTENANCE-PROTECTION-OF-DISTRIBUTION-TRANSFORMERS.ppt93518813-TESTING-MAINTENANCE-PROTECTION-OF-DISTRIBUTION-TRANSFORMERS.ppt
93518813-TESTING-MAINTENANCE-PROTECTION-OF-DISTRIBUTION-TRANSFORMERS.ppt
 
TESTING,MAINTENANCE&PROTECTION.ppt
TESTING,MAINTENANCE&PROTECTION.pptTESTING,MAINTENANCE&PROTECTION.ppt
TESTING,MAINTENANCE&PROTECTION.ppt
 
tcee-161003100321.pptx
tcee-161003100321.pptxtcee-161003100321.pptx
tcee-161003100321.pptx
 
Power transformer testing and commissioning guidelines r
Power transformer testing and commissioning guidelines rPower transformer testing and commissioning guidelines r
Power transformer testing and commissioning guidelines r
 
Isolator and bushing
Isolator and bushingIsolator and bushing
Isolator and bushing
 
Presentation OutDoorSwithGear(AIS) .pptx
Presentation OutDoorSwithGear(AIS) .pptxPresentation OutDoorSwithGear(AIS) .pptx
Presentation OutDoorSwithGear(AIS) .pptx
 
AC Circuit Breakers Routine Tests according to IEC 62271-100
AC Circuit Breakers Routine Tests according to IEC 62271-100AC Circuit Breakers Routine Tests according to IEC 62271-100
AC Circuit Breakers Routine Tests according to IEC 62271-100
 
Testing of cb
Testing of cbTesting of cb
Testing of cb
 
Transformer
TransformerTransformer
Transformer
 
Distribution Transformer testing, West Bengal, India
Distribution Transformer testing,  West Bengal, IndiaDistribution Transformer testing,  West Bengal, India
Distribution Transformer testing, West Bengal, India
 

REPORT -VALLUR THERMAL POWER PLANT

  • 1. NTPC Tamilnadu Energy Company Ltd Velammal Engineering College Report on Training underwent at Vallur Thermal Power Project 29-06-2015 to 12-07-2015 Er.R.S.RAJPRASAD
  • 2. ACKOWLEDGEMENT I express my sincere thanks to NTPC TamilNadu Energy Company Ltd for offering me this opportunity to be trained at Vallur Thermal Power station, Chennai. I express my profound sense of gratitude to Shri.Rajendran, Deputy Manager(Electrical Maintainance), NTPC for his valuable guidance during the course of the training programme. I take this opportunity to thank all the Engineers , Supervisors and other workers on site for their support during the course of this training programme.
  • 3. ABSTRACT This report inculcates the quantum of knowledge grasped as a part of the training programme that was offered at the Vallur Thermal Power Project. Based on the experience imbibed by virtue of understanding the nuances of Practical applications, the observations carried out are briefed out in this report. The Entire course of training can be sectionalized into following… - Testing of Switchgear Relays - Battery Capacitance Test - Testing of Transformers - Stability Test for H.T motor Relays - Study of the Plant profile
  • 4. TESTING OF SWITCHGEAR RELAYS Switchgear devices are situated at the key points of electrical energy transmission and distribution systems. Their reliability has a decisive influence on the availability, safety and economic efficiency of electricity supply systems. Only regular, on-site tests can ensure that switchgear devices function perfectly throughout their operational life. The CMC 256plus is the first choice for applications requiring very high accuracy. This unit is not only an excellent test set for protection devices of all kinds but also a universal calibrator. Its high precision allows the calibration of a wide range of measuring devices. Its unique accuracy and flexibility make the CMC 256plus ideal for protection and measurement equipment manufacturers for research and development, production and type testing.
  • 5. The Various tests carried out on the Swithgear relay using CMC 256 Plus are as follows : - Overcurrent Protection Test - Differential Protection Test - Earth Fault Protection Test OVERCURRENT PROTECTION TEST: To evaluate the feasibility for overcurrent protection offered by the Relay, the pick up value for the relay is set and corresponding current above the pick up value is injected into the C.T input of the relay. If the Relay triggers the trip signal depending on the time setting (instantaneous or definite time), then the relay is said to reliable in its operation. DIFFERENTIAL PROTECTION TEST: In Differential protection test, the currents corresponding to the inputs from the two C.T’s are injected into the relay and is checked .If the relay reacts to the differential current and executes the corresponding logic depending upon the magnitude of the differential current,
  • 6. then the relay is considered to be fit for differential protection. EARTH FAULT PROTECTION TEST: A low level arcing ground fault can destroy switchgear in seconds, before the main service overcurrent protection will operate. A 480/277 volt solidly grounded system has sufficient voltage to maintain an arc between one phase and a ground but not enough current to cause a large main breaker or fuse to clear the fault quickly. The resulting arc is similar to an electric weld, consuming large amounts of metal in the seconds it takes the breaker or fuse to operate. A properly installed and operating ground fault protection system will detect and clear the fault in milliseconds, fast enough to limit damage to acceptable levels. Using CMC 256 plus, an earth fault is simulated and checked if the relay reacts effectively to it, within the ensured response time. These are the major tests associated with the testing of Switchgear relays.
  • 7. BATTERY CAPACITANCE TEST The Battery capacitance test is an important test, that has to be carried out regularily , so as to ensure the healthiness of the battery banks and assure reliable support in case of crisis. The Various steps involved in the Battery charging test are as follows :  Initially check the charging unit if it is in proper condition to charge the battery unit after it is discharged. For this, boost the battery from the charger unit and check.  Now, isolate the load side from the DCDB (DC distribution board) .  Connect a resistive load bank to the rectifier output terminals of the charging unit, after proper isolation of the previous load terminals.
  • 8.  Now, close the load isolator switch in the DCDB and add the load from the resistive load bank.  After discharging the entire battery bank, check for the electrolyte parameters, clean if needed and carry out other maintenance work if required.  Now remove the Resistive load and start boost charging the battery bank from the charger unit. Thus the battery capacitance test is carried out to ensure the healthiness and reliability of the battery bank so that it is assured to be available whenever it is needed.
  • 9. TESTING OF TRANSFORMERS For confirming the specifications and performances of an Electrical power transformer, it has to go through numbers of testing procedures. Some tests are done at manufacturer premises before delivering the transformer. In addition to that some transformer tests are also carried out at the consumer site before commissioning and also periodically in regular & emergency basis throughout its service life. During the course , UNIT II was shut down and all the associated auxiliaries were taken for annual maintainance. So, the tests carried out on the Generator Transformers (G.T) are listed below. The various tests carried out on site on the single phase Generation Transformers are as follows : Insulation Resistance Test Magnetizing Current Test Short Circuit Test Turns Ratio Test Winding Resistance Test Tan-delta Test
  • 10. Test 1 : INSULATION RESISTANCE TEST: Basically, the Insulation Resistance test is carried out to verify the insulation levels of the windings of the transformer as insulation is the most important factor that determines the substantial quality of operation of an electrical component. Testing Apparatus: HV Digital Megger  The applied voltage from the megger is 5KV  The resultant IR value obtained will be in GΩ and is measured at 60 seconds.  The test point terminals between which the IR value is measured are - HV to Ground - LV to Ground - HV to LV
  • 11. Test 2 : MAGNETIZING CURRENT TEST: The Magnetizing current test is carried out , so as to measure the approximate magnetizing currents flowing through the winding. NOTE: As it is practically impossible to determine the exact magnetizing currents flowing in HV winding, a low voltage is injected and checked. z t  Apart from the winding to be tested, the other terminal is kept open .  On the winding to be tested, inject voltage on the terminals and measure the current flowing through the winding using clamp meter  The injected voltage is 242.7 V Transformer SUPPLY MEASURING NODE
  • 12. Test 3 : SHORT CIRCUIT TEST: The Short circuit Test is another important test to be carried out in a transformer, to assess the magnitude of current flowing in the HV side due to any short circuit faults in the LV side. z t  Initially the LV side is shorted using shorting cable  Now, voltage of 246.8 (approx) is injected on the HV terminals  The corresponding current flowing through the HV and LV windings are measured  The value measured in LV side would be in mA, while the value measured in HV side would be in A . Transformer LV HV SUPPLY
  • 13. Test 4 : TURNS RATIO TEST: The turns ratio test is carried out to analyze the actual ratio of turns within the transformer windings and the percentage of error associated with it. Testing Apparatus: MEGGER TTR320  Connect the cables “CABLE H” and “CABLE X”  Ground the Kit  Connect H1 and H2 to the HV side  Connect X1 and X2 to the LV side HV LV H1 H2 X1 X2
  • 14. Diagram selected in kit for test: Voltage Rating: HIGH LOW 230.900 21.000 TAPS 7 On entering the data, the following parameters will automatically be calculated by the kit :  Actual Ratio  % Error  Excitation Current  Phasor Deviation K (Turns ratio)=V2/V1= N2/N1=I1/I2 1:1 1:2 2:1 2:2
  • 15. Test 5 : WINDING RESISTANCE TEST: The winding Resistance Test is carried out to calculate and analyze the resistance offered by the winding to the flow of current. Testing Apparatus: MEGGER TTR320  The C+ and C- wires are connected at the terminals of the winding to be tested  The V+ and V- wires are connected on the path of C+ and C- respectively as shown in figure. C+ C- V+ V-
  • 16.  The Injected DC current is 10A The observations made on the HV and LV windings are as follows : HV winding : R=165 mΩ LV winding : R=880 mΩ Test 6 : TAN-DELTA TEST: The Tan-delta test is one of the most important tests carried out in a transformer. The Tan-delta test is mainly carried out to determine the capacitance and dissipation factor of the transformer. Dissipation factor = IR/IC Testing Apparatus: OMICRON CPC 100 and CP TD1  After all the connections are made, the kit is switched ON.  There are two modes of testing: - UST mode and GST mode  UST- Ungrounded Specimen Test GST- Grounded Specimen Test  In UST mode, tests are run between HV-Tandelta point and HV-LV
  • 17.  In GST mode, tests are run between HV-Ground and Tandelta point-Ground  Guard is used whenever accuracy in results are required  The Injected Voltages are as follows: -For higher capacitance : 2kV,5kV and 10kV -For lower capacitance : 300V and 500V Thus , depending on the dissipation factor, the ageing of the transformer is determined.
  • 18. STABILITY TEST FOR HT MOTOR RELAY The Stability test for HT motor Relay is mainly done to assure the reliability of the Motor protection Relay towards Internal Faults. In this test, an internal fault is simulated by manually charging the winding terminals with a variac connected to an external source. Now, it is observed whether the relay picks up the fault immediately and trips . Thus, the stability test ensures that the relay acts in a feasible manner for any kind of internal faults.
  • 19. STUDY OF PLANT PROFILE Vallur Thermal Power Station is a power plant located in Athipattu village, Vallur in Thiruvallur district, North Chennai, India. The power plant is operated by NTPC Tamil Nadu Energy Company Limited, a joint venture between NTPC Limited and TANGEDCO and has three units with 500 MW each. In January 2014, the units in the power plant achieved a record generation of 24.09 million units of electricity.[1] The project adds nearly 24 million units a day to the grid. Tamil Nadu is the major beneficiary of power generated from this facility (about 750 MW), while some of it is supplied to Andhra Pradesh, Karnataka, Kerala, and Puducherry. The plant will consume 4.62 mt of coal a year. Coal for the plant will be brought from Orissa through ship to Ennore Port, from where it will be transported by closed belt conveyor system. The boiler systems at the plant consists of single- or two-pass type, with front/rear/side mill layout, which can have single/bi-drum arrangement with natural or controlled circulation. There is constant or sliding pressure operation, and hot or cold primary air systems. Steam turbine operates at a speeds of 3,000 rpm. The main steam is at 130–250 bar at 500–540 °C. Steam reheat is at 30–70 and 500–600 °C. The back pressure is between 20 and 300 mbar. The plant has six induced draft cooling towers (IDCTs), which have a capacity of 30,000 m3/h with nine cells of 21 × 14 m each.The IDCTs use seawater, which is drawn from the intake channel of North Chennai Thermal Power Station, and fresh water requirement is met from a desalination plant. The plant has adopted closed cycle re-circulating type cooling water system for its operations.
  • 20. The coal conveyor system in the plant includes a 4.4-km-long pipe conveyor with a capacity of 4,000 tonnes/hour, which is the world's largest pipe conveyor. The plant requires 13,400 tonnes of coal per day, and 53 percent of the need is met from domestic coalfields and the remainder through coal imports. Following is the unit wise capacity of the 1500 MW plant. Stage Unit Number Installed Capacity (MW) Stage I 1 500 Stage I 2 500 Stage I 3 500 GAS INSULATED SWITCHYARD : A Gas Insulated Switchgear substation (GIS substation) uses Sulfur hexafluoride gas (SF6 Gas) whose dielectric strength is higher than air, to provide the phase to ground insulation for the switchgear of an electrical substation. This works where by the conductors and contacts are insulated by pressurized SF6 gas meaning clearances required are smaller than that of AIS substations. The main advantage of the GIS substation is that this phase to phase spacing can be reduced significantly resulting in a substation with comparable load capability to an AIS substation but with a much smaller compound
  • 21. footprint. This is particularly advantageous in an urban environment where land size is at a premium. It also results in a smaller visual impact on a landscape as it can result in a significantly smaller footprint than its AIS counterpart. The GIS switch gear shall be of modular design offering high degree of flexibility. Each module shall be complete with SF6 gas circuit breaker, Disconnectors, Maintenance Grounding switches, fast Earthing switches, voltage transformers, Current transformers, bus & elbow sections, cable end enclosures, L.A., local control cubicle and all necessary components required for safe & reliable operation and maintenance. All the three phases of the busbars and associated equipments like breakers, disconnectors, instrument transformers & earthing switches etc., are to be encapsulated in a single gas filled metallic enclosure for 66 & 132 kV voltage class and phase wise separate metallic enclosures for 400 kV class. The bus bars shall be sub-divided into compartments including the associated bus bar disconnector. Bus bars are partitioned at each bay with an objective to isolate Busbar compartment for the purpose of extension and at the same time avoid damage to adjacent bays in the event of fault. In the past, there was also a concern that only the original manufacturer of an installation would be willing to accept the risk of offering an expansion to that installation. The concern was the integrity of the seals at the point where the original installation and the expansion came together. As a result, a purchaser who committed to a GIS installation was
  • 22. perpetually tied to the supplier of that installation for any future expansion needs, and this put the purchaser at the mercy of that supplier in future expansions. In recent years, manufacturers have overcome the technical issues of assuring the reliability of the seals between dissimilar equipment, so this problem is less significant today. Thus, the Vallur Thermal Power Project boasts for its effectively designed Gas insulated switchgear, thereby proving to be space efficient in design and pioneering in the art of keeping pace with the growing electrical technology and trends.
  • 23. CONCLUSION: In review, this internship has been an excellent and rewarding experience. I have been able to meet and network with so many people , which I would carry ahead in the years to come. My experience at Vallur Thermal Power Project has been invaluable. I thoroughly enjoyed my position and learned a great deal about all the various aspects of a major Generating utility. During the course of training, the insight into professional practices helped me acquire Practical skills and link theory to practice in the real Power System workspace. This training was beneficial for me and I’m thankful that I got experience to learn many things.