SlideShare une entreprise Scribd logo
1  sur  2
Project Experience
Bunnythorpe Seismic Upgrades - Crane Building
Client: TranspowerNewZealand
PositionHeld: Project Manager
Opus are engaged to complete seismic evaluations and subsequent upgrades of a number of Transpower's buildings
throughout the country. It was identified that the Crane Building at the Bunnythorpe Substation needed some remedial
works to ensure the protection of the buildings around it. A structural solution was designed to force the building to collapse
in such a manner that it will not be a risk to other surrounding buildings. This is a unique methodology that has created a
number of complex construction issues to be resolved, with a relatively tight timeframe. Furthermore, on all Transpower
sites Health and Safety is top priority which has created some project delays whilst trying to ensure the continued safety of
contractors working on site.
Bunnythorpe Warehouse Fire and Racking Upgrade
Client: Transpower
PositionHeld: Project Manager
In line with Transpower's seismic assessments, it was identified that the storage racks in Transpower's Bunnythorpe
Warehouse required seismic strengthening. This in turn triggered a required fire services upgrade. The warehouse stores
surplus equipment for Transpower stations throughout the country, all of which are delicate and expensive to replace.
Additionally, the warehouse was fully operational for the duration of the project, thus there had to be significant
programmingcoordinationwithall concernedpartiesto ensure adequate protection ofTranspowerstock andstaff.
T ranspower Various: RoofReplace
Client: Transpower
PositionHeld: AssistantProjectManager
This project involved replacing the roofs on three substations throughout the Lower North Island. This project had a very
tight timeframe and a number of complexities to be managed. Working on the exterior of a live electrical site has a number
of Health and Safety risks which are currently being managed. In order to replace the roofon one ofthe sites, a power outage
was required, this took significant planning with the contractor and client to ensure smooth transitions and no loss ofservice
to the enduser.
Ernst and Young Office Fit Out
Client: Ernst and Young
PositionHeld: LocalProjectManager
Opus were engaged to act as the local project manager for this office fit out in Wellington. The project was run concurrently
with a large, multi million dollar seismic upgrade of the basebuilding and had to be delicately programmed around their
requirements. The seismic upgrades meant that the programme was incredibly tight and inflexible, whilst the client required
a high quality finish. There were a number of affected stakeholders and as such it was vitally important to ensure that
communication between allstakeholders was effectivelymanaged.
Opus - New Research and Education Facility
Client: Opus International
PositionHeld: GraduateProjectManager
Project Value: $3M
This was a 3200m2 fit out of an existing facility on the Petone foreshore, which was to be completed within a tight timeframe
and within a very tight budget. The new facility is a flagship for research and education and encompasses an extensive
laboratory fit-out, training centre and open plan offices. I was supporting the Project Manager with management of design
and basebuildconsultants andstakeholderliaison.
T e Papa LevelFour Gallery Conversion
Client: MuseumofNewZealandTe PapaTongarewa
PositionHeld: GraduateProjectManager
I was supporting the lead Project Manager in documentation and construction management of a fit-out for Te Papa. This
project had complex stakeholder requirements and engineering services to ensure that art works displayed meet lender
requirements. Theproject timelinewascrucial forpublic openingin July 2013.
Housing New Zealand Condition Surveys
Client: Housing New Zealand
PositionHeld: Condition Assessor
This contract was for the Condition Assessment of a number of Housing New Zealand owned houses nationally. I was
involved in the Wellington region team of 20 auditors, who collectively had to complete surveys of 4000 houses. The nature
of the houses that were being inspected required strong communication skills to ensure that tenants were comfortable with
the survey being completed, and fully understoodits implications.
Ministry ofEducation Earthquake Remediations
Client: Ministry ofEducation
PositionHeld: GraduateProjectManager
Opus were engaged by the Ministry of Education to undertake seismic assessments of various schools in the Christchurch
region. In this project, I was assisting the Project Manager with progress tracking and co-ordination ofthe numerous reports
being compiled,ensuringkey deadlinesweremet.

Contenu connexe

Tendances (19)

GMcnicol CV
GMcnicol CVGMcnicol CV
GMcnicol CV
 
Michael Dismore Resume 24-04-14
Michael Dismore Resume 24-04-14Michael Dismore Resume 24-04-14
Michael Dismore Resume 24-04-14
 
KENRICK RAMOS 2017
KENRICK RAMOS 2017KENRICK RAMOS 2017
KENRICK RAMOS 2017
 
Tony Woodfine 2016 resume
Tony Woodfine 2016 resumeTony Woodfine 2016 resume
Tony Woodfine 2016 resume
 
Krishna kumar cv
Krishna kumar cvKrishna kumar cv
Krishna kumar cv
 
Projects Annex
Projects AnnexProjects Annex
Projects Annex
 
GNA Surveyors Ltd - Company Presentation 2014
GNA Surveyors Ltd - Company Presentation 2014GNA Surveyors Ltd - Company Presentation 2014
GNA Surveyors Ltd - Company Presentation 2014
 
Current Public Resume
Current Public ResumeCurrent Public Resume
Current Public Resume
 
Ashraf Suleiman.
Ashraf Suleiman.Ashraf Suleiman.
Ashraf Suleiman.
 
Key experience Feb 2016
Key experience Feb 2016Key experience Feb 2016
Key experience Feb 2016
 
CV~PW~02-02-16 Opus
CV~PW~02-02-16 OpusCV~PW~02-02-16 Opus
CV~PW~02-02-16 Opus
 
Resume 26-07-15
Resume 26-07-15Resume 26-07-15
Resume 26-07-15
 
Lng markets a canadian contactors perspective john j. jeffers
Lng markets a canadian contactors perspective   john j. jeffersLng markets a canadian contactors perspective   john j. jeffers
Lng markets a canadian contactors perspective john j. jeffers
 
larry_dosher opengr resume
larry_dosher opengr resumelarry_dosher opengr resume
larry_dosher opengr resume
 
Kiran 8 years
Kiran 8 yearsKiran 8 years
Kiran 8 years
 
CV.PM
CV.PMCV.PM
CV.PM
 
LATEST SHORT CV 2015
LATEST SHORT CV 2015LATEST SHORT CV 2015
LATEST SHORT CV 2015
 
GLOBAL Engineers & Constructors -KENTZ
GLOBAL Engineers & Constructors -KENTZGLOBAL Engineers & Constructors -KENTZ
GLOBAL Engineers & Constructors -KENTZ
 
Mep contractors in abu dhabi
Mep contractors in abu dhabiMep contractors in abu dhabi
Mep contractors in abu dhabi
 

Similaire à Project Experience Rachel Byrne

cv_de jong_Andrew July 2015
cv_de jong_Andrew July 2015cv_de jong_Andrew July 2015
cv_de jong_Andrew July 2015Andrew De Jong
 
Chalcroft Special Projects
Chalcroft Special ProjectsChalcroft Special Projects
Chalcroft Special ProjectsChalcroft Ltd
 
CV 160105 Paul Magee
CV 160105 Paul MageeCV 160105 Paul Magee
CV 160105 Paul MageePaul Magee
 
RRozek Project List 9 20 15
RRozek Project List 9 20 15RRozek Project List 9 20 15
RRozek Project List 9 20 15Roman Rozek
 
Peter Dally Aquenta CV
Peter Dally Aquenta CVPeter Dally Aquenta CV
Peter Dally Aquenta CVPeter Dally
 
Chalcroft construction for the warehouse and logistics industries
Chalcroft construction for the warehouse and logistics industriesChalcroft construction for the warehouse and logistics industries
Chalcroft construction for the warehouse and logistics industriesChalcroft Ltd
 
Intertek - Industry Services
Intertek - Industry ServicesIntertek - Industry Services
Intertek - Industry Servicesogonzalez1997
 
Intertek - Industry Services 2013
Intertek - Industry Services 2013Intertek - Industry Services 2013
Intertek - Industry Services 2013ogonzalez1997
 
Resume November 2016
Resume November 2016Resume November 2016
Resume November 2016John Brennan
 
KBE Laboratories 2011
KBE Laboratories 2011 KBE Laboratories 2011
KBE Laboratories 2011 charkins
 
New brochure 240311
New brochure 240311New brochure 240311
New brochure 240311weydon23
 
GW Amec Foster Wheeler
GW Amec Foster WheelerGW Amec Foster Wheeler
GW Amec Foster WheelerGareth White
 
Tim Read CV January 2016
Tim Read CV January 2016Tim Read CV January 2016
Tim Read CV January 2016Tim Read
 
Tim Read CV January 2016
Tim Read CV January 2016Tim Read CV January 2016
Tim Read CV January 2016Tim Read
 
Zinfra Group Australia: Corporate Brochure
Zinfra Group Australia: Corporate BrochureZinfra Group Australia: Corporate Brochure
Zinfra Group Australia: Corporate BrochureZinfra Group
 
20160704 Carline_Andrew
20160704 Carline_Andrew20160704 Carline_Andrew
20160704 Carline_AndrewAndrew Carline
 

Similaire à Project Experience Rachel Byrne (20)

cv_de jong_Andrew July 2015
cv_de jong_Andrew July 2015cv_de jong_Andrew July 2015
cv_de jong_Andrew July 2015
 
Chalcroft Special Projects
Chalcroft Special ProjectsChalcroft Special Projects
Chalcroft Special Projects
 
CV 160105 Paul Magee
CV 160105 Paul MageeCV 160105 Paul Magee
CV 160105 Paul Magee
 
RRozek Project List 9 20 15
RRozek Project List 9 20 15RRozek Project List 9 20 15
RRozek Project List 9 20 15
 
Peter Dally Aquenta CV
Peter Dally Aquenta CVPeter Dally Aquenta CV
Peter Dally Aquenta CV
 
Chalcroft construction for the warehouse and logistics industries
Chalcroft construction for the warehouse and logistics industriesChalcroft construction for the warehouse and logistics industries
Chalcroft construction for the warehouse and logistics industries
 
Intertek - Industry Services
Intertek - Industry ServicesIntertek - Industry Services
Intertek - Industry Services
 
Ashley cv most recent2016 7
Ashley cv most recent2016 7Ashley cv most recent2016 7
Ashley cv most recent2016 7
 
Ashley cv most recent2016 7
Ashley cv most recent2016 7Ashley cv most recent2016 7
Ashley cv most recent2016 7
 
DaveGriffithsCV
DaveGriffithsCVDaveGriffithsCV
DaveGriffithsCV
 
Intertek - Industry Services 2013
Intertek - Industry Services 2013Intertek - Industry Services 2013
Intertek - Industry Services 2013
 
Resume November 2016
Resume November 2016Resume November 2016
Resume November 2016
 
KBE Laboratories 2011
KBE Laboratories 2011 KBE Laboratories 2011
KBE Laboratories 2011
 
Gazette Issue 1 2016
Gazette Issue 1 2016Gazette Issue 1 2016
Gazette Issue 1 2016
 
New brochure 240311
New brochure 240311New brochure 240311
New brochure 240311
 
GW Amec Foster Wheeler
GW Amec Foster WheelerGW Amec Foster Wheeler
GW Amec Foster Wheeler
 
Tim Read CV January 2016
Tim Read CV January 2016Tim Read CV January 2016
Tim Read CV January 2016
 
Tim Read CV January 2016
Tim Read CV January 2016Tim Read CV January 2016
Tim Read CV January 2016
 
Zinfra Group Australia: Corporate Brochure
Zinfra Group Australia: Corporate BrochureZinfra Group Australia: Corporate Brochure
Zinfra Group Australia: Corporate Brochure
 
20160704 Carline_Andrew
20160704 Carline_Andrew20160704 Carline_Andrew
20160704 Carline_Andrew
 

Project Experience Rachel Byrne

  • 1. Project Experience Bunnythorpe Seismic Upgrades - Crane Building Client: TranspowerNewZealand PositionHeld: Project Manager Opus are engaged to complete seismic evaluations and subsequent upgrades of a number of Transpower's buildings throughout the country. It was identified that the Crane Building at the Bunnythorpe Substation needed some remedial works to ensure the protection of the buildings around it. A structural solution was designed to force the building to collapse in such a manner that it will not be a risk to other surrounding buildings. This is a unique methodology that has created a number of complex construction issues to be resolved, with a relatively tight timeframe. Furthermore, on all Transpower sites Health and Safety is top priority which has created some project delays whilst trying to ensure the continued safety of contractors working on site. Bunnythorpe Warehouse Fire and Racking Upgrade Client: Transpower PositionHeld: Project Manager In line with Transpower's seismic assessments, it was identified that the storage racks in Transpower's Bunnythorpe Warehouse required seismic strengthening. This in turn triggered a required fire services upgrade. The warehouse stores surplus equipment for Transpower stations throughout the country, all of which are delicate and expensive to replace. Additionally, the warehouse was fully operational for the duration of the project, thus there had to be significant programmingcoordinationwithall concernedpartiesto ensure adequate protection ofTranspowerstock andstaff. T ranspower Various: RoofReplace Client: Transpower PositionHeld: AssistantProjectManager This project involved replacing the roofs on three substations throughout the Lower North Island. This project had a very tight timeframe and a number of complexities to be managed. Working on the exterior of a live electrical site has a number of Health and Safety risks which are currently being managed. In order to replace the roofon one ofthe sites, a power outage was required, this took significant planning with the contractor and client to ensure smooth transitions and no loss ofservice to the enduser. Ernst and Young Office Fit Out Client: Ernst and Young PositionHeld: LocalProjectManager Opus were engaged to act as the local project manager for this office fit out in Wellington. The project was run concurrently with a large, multi million dollar seismic upgrade of the basebuilding and had to be delicately programmed around their requirements. The seismic upgrades meant that the programme was incredibly tight and inflexible, whilst the client required a high quality finish. There were a number of affected stakeholders and as such it was vitally important to ensure that communication between allstakeholders was effectivelymanaged. Opus - New Research and Education Facility Client: Opus International PositionHeld: GraduateProjectManager Project Value: $3M This was a 3200m2 fit out of an existing facility on the Petone foreshore, which was to be completed within a tight timeframe and within a very tight budget. The new facility is a flagship for research and education and encompasses an extensive laboratory fit-out, training centre and open plan offices. I was supporting the Project Manager with management of design and basebuildconsultants andstakeholderliaison. T e Papa LevelFour Gallery Conversion Client: MuseumofNewZealandTe PapaTongarewa PositionHeld: GraduateProjectManager I was supporting the lead Project Manager in documentation and construction management of a fit-out for Te Papa. This project had complex stakeholder requirements and engineering services to ensure that art works displayed meet lender requirements. Theproject timelinewascrucial forpublic openingin July 2013.
  • 2. Housing New Zealand Condition Surveys Client: Housing New Zealand PositionHeld: Condition Assessor This contract was for the Condition Assessment of a number of Housing New Zealand owned houses nationally. I was involved in the Wellington region team of 20 auditors, who collectively had to complete surveys of 4000 houses. The nature of the houses that were being inspected required strong communication skills to ensure that tenants were comfortable with the survey being completed, and fully understoodits implications. Ministry ofEducation Earthquake Remediations Client: Ministry ofEducation PositionHeld: GraduateProjectManager Opus were engaged by the Ministry of Education to undertake seismic assessments of various schools in the Christchurch region. In this project, I was assisting the Project Manager with progress tracking and co-ordination ofthe numerous reports being compiled,ensuringkey deadlinesweremet.