3. 1. SALIENT FEATURES OF THE PROJECT
1 TYPE OF CONTRACT
DESIGN, BUILT, FINANCE, OPERATE AND TRANSFER ON
ANNUITY BASIS (DBFOT)
2 COST OF THE PROJECT Rs 918.39 CRORE
3 COST OF THE PROJECT EXCLUD PRELIMINARIES Rs. 887.89 CRORE
4 APPOINTMENT DATE 10TH
AUGUST 2011
5 COMPLETION DATE 9TH
FEB 2014
6 1st
MILE STONE 180 DAYS (10% OF PROJECT COST) : 09th
Feb-12
7 2ND
MILE STONE
450 DAYS (35% OF PROJECT COST) : 09th
Nov-12
(Commencement construction of all Bridges)
8 3RD
MILE STONE
750 DAYS (70% OF PROJECT COST) : 09th
Sep-13
(Commencement construction of all Project Facility)
9
SCHEDULED FOUR LANNING DATE AS PER BASE
LINE PROGRAM
900 DAYS (100% OF PROJECT COMPLETION) : 09th
Feb-14