SlideShare une entreprise Scribd logo
1  sur  21
Télécharger pour lire hors ligne
Chapter –6 
Critical Path Method (CPM) 
Course Code -CIE 403 
Mr. Ramesh Nayaka, (M.Tech. –IIT Madras) 
Assistant Professor 
Department of Civil Engineering 
Manipal Institute of Technology, Manipal -576104 
Karnataka, India
Content… 
•Introduction to CPM 
•Difference between CPM and PERT 
•Terms and Definitions 
•Calculation of Float 
•Critical Path
Introduction to CPM 
CPM network are usually used for repetitive type of projects, where fairly accurate estimates of time can be made for the activities of the project. 
The activities of these projects are characteristically subject to relatively small amount of variation. Hence CPM is not suitable for research and development type of projects. 
Examples from fairly diverse field where application of CPM can be made: 
Building a new bridge across river ganga, Constructing a multi-storeyed building, extension of a factory building, shifting a manufacturing unit to other site and manufacturing of a new car etc.
Difference between CPM and PERT 
CPM 
PERT 
Activity Oriented network 
Event oriented network 
The time estimatesare of a fair degree of accuracy 
Time estimates are not that accurate andthere is an uncertainty attached to it 
Follows deterministic approach 
Followsprobabilistic approach 
Cost is governingfactor 
Time is governing factor 
Project duration is so fixed such that the cost is minimum 
Assumed that cost is directly proportional to time so time is reduced maximum possible to enjoy least cost 
Critical path is thatpath which joins the critical activities 
Criticalpath is the path which joins the critical events
Terms and Definitions 
Activity Times 
Forward Passing : 
Earliest Start Time (EST) :earliest time by which an activity start 
EST = earliest event time of tail event = TEi 
Earliest Finish Time (EFT) : Earliest time by which an activity can be completed 
EFT = EST + tEij= TEi + tEij
Terms and Definitions 
Activity Times 
Backward Passing : 
Latest Finish Time (LFT) : latest time by which an activity can completed without delaying the completion of the project 
LFT = Latest Finish Time of head event = TLj 
Latest Start Time (LST) : latest time by which an activity can start without delaying the completion of the project 
LST = LFT -tEij= TLj -tEij
Terms and Definitions 
FLOATS 
Similar to slack in PERT 
Associated with activity times 
Denotes flexibility range within which the activity start and finish time may fluctuate without affecting the total duration of the project
Terms and Definitions 
TYPES OF FLOATS 
Total Float (FT) : timespan by which starting or finishing of an activity can be delayed without affecting the overall completion time of the project. 
It refers to the amount of time by which the completion of activity could be delayed beyond earliest expected completion time without affecting overall project duration time 
FT= LST –EST or LFT -EFT
Terms and Definitions 
TYPES OF FLOATS 
Free Float (FF) : duration by which an activity can be delayed without delaying any other succeeding activity. 
It refers to the amount of time by which the completion of an activity can be delayed beyond the earliest finish time without affecting the earliest start time of a subsequent succeeding activity. 
This float is concerned with the commencement of subsequent activity 
FF= FT–Sj , Sj= Slack of head event = TLj –TEj
Terms and Definitions 
TYPES OF FLOATS 
Independent Float (FID): It is excess time available if the preceding activity ends as late as possible and the succeeding activity starts as early as possible 
It is refers to that the amount of time by which the start of an activity can be delayed, without affecting earliest start time of any immediately following activities 
This float concerned with prior and subsequent activities 
FID= FF–Si 
Si = slack of tail event =TLi–TEi
Terms and Definitions 
TYPES OF FLOATS 
Interfering Float (FIT) : Another name for head event slack (Sj), it is the difference between total float and free float 
FIT= FT–FF = TLj –TEj = Sj 
Note : if the total float (FT) for any activity is zero then such activity is called critical activity 
Critical Activity : an activity is said to be critical, if a delay in its start cause a further delay in the completion of the entire project
Terms and Definitions 
Critical Path : The sequence of critical activities in a network which determines the duration of a project is called critical path. 
•It is the longest path in the network from the starting event to the ending event 
•For activities lies on critical path 
EST =LST , EFT = LFT and EST –EFT = LST –LFT 
Sub critical activity : When total float (FT ) is positive 
Critical Activity :When total float (FT ) is zero 
Super critical activity : When total float (FT ) is negative
Calculating Critical Path & Float for a Network Diagram 
Find out the length of all the paths in the network diagram 
The longest path is the critical path 
Float = EF –LF = ES -LS
Terms and Definitions 
Critical Path : The sequence of critical activities in a network which determines the duration of a project is called critical path. 
•It is the longest path in the network from the starting event to the ending event 
•For activities lies on critical path 
EST =LST , EFT = LFT and EST –EFT = LST –LFT 
Sub critical activity : When total float (FT ) is positive 
Critical Activity :When total float (FT ) is zero 
Super critical activity : When total float (FT ) is negative
Terms and Definitions 
Critical Path : The sequence of critical activities in a network which determines the duration of a project is called critical path. 
•It is the longest path in the network from the starting event to the ending event 
•For activities lies on critical path 
EST =LST , EFT = LFT and EST –EFT = LST –LFT 
Sub critical activity : When total float (FT ) is positive 
Critical Activity :When total float (FT ) is zero 
Super critical activity : When total float (FT ) is negative
CPM Analysis 
F 
1 
2 
4 
3 
5 
6 
7 
8 
A 
B 
C 
D 
E 
H 
K 
J 
I 
10 
8 
12 
8 
10 
6 
5 
12 
6 
12 
8 
Aprojectconsistsof11activities,representedbythe 
networkshownbelowinfigureandalsothenormal 
durationsrequiredtoperformvariousactivitiesofthe 
projectaregiveninnetwork.Compute(a)Eventtimes 
(b)activitytimesandtotalfloat.Alsodetermine 
thecriticalpath.
a. Computation of Event times Event No. PredecessorSuccessorEventEvent12345678Earliest Expected Time (↓ )Latest occurrence Time ( ↑ ) tETETE (Max)tETLTL (Min)
b. Computation of activity times and floats 
Activity 
Duration 
Earliest (Units) 
Latest (Units) 
Total Float 
Free Float 
Independent Float 
(i -j) 
tEij 
EST 
EFT 
LST 
LFT 
FT 
FF 
FID 
1 -2 
1 -3 
2 –5 
2 –7 
3–4 
3–6 
4–5 
5 -6 
5 -7 
6 -7 
7 -8
c. Location of Critical path 
•1-3 –4 –5 –6 –7 = 52 units 
F 
1 
2 
4 
3 
5 
6 
7 
8 
A 
B 
C 
D 
E 
H 
K 
J 
I 
10 
8 
12 
8 
10 
6 
5 
12 
6 
12 
8
Problem –2 
F 
1 
2 
4 
3 
5 
6 
7 
8 
A 
B 
G 
E 
D 
I 
L 
J 
5 
4 
4 
6 
2 
6 
7 
8 
0 
6 
7 
C 
K 
3 
Networkshownbelowinfigureandalsothenormaldurationsrequiredtoperformvariousactivitiesoftheprojectaregiveninnetwork.Compute(a)Eventtimes(b) activitytimes(c)totalfloatforeachactivityandestablishthecriticalpath.Alsodeterminethefreefloatandindependentfloat.
Problem –2 
1 
2 
3 
6 
4 
5 
A 
B 
E 
D 
G 
H 
3 
5 
3 
1 
14 
4 
C 
F 
4 
Networkshownbelowinfigureandalsothenormaldurationsrequiredtoperformvariousactivitiesoftheprojectaregiveninnetwork.Compute(a)Eventtimes(b) activitytimes(c)totalfloatforeachactivityandestablishthecriticalpath.Alsodeterminethefreefloatandindependentfloat. 
6 
1 
I

Contenu connexe

Tendances

Critical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/SlacksCritical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/SlacksPrasad Thanthratey
 
PERT and CPM
PERT and CPMPERT and CPM
PERT and CPMstudent
 
Project Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTProject Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTS.Vijaya Bhaskar
 
Time cost optimisation
Time cost optimisationTime cost optimisation
Time cost optimisationCharul Sharma
 
6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource Smoothing6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource SmoothingDavidMcLachlan1
 
Network Problem CPM & PERT
Network Problem CPM &  PERTNetwork Problem CPM &  PERT
Network Problem CPM & PERTPulchowk Campus
 
Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )Akaresh Jose Kaviyil JY
 
RESOURCE LEVELLING (MS PROJECT)
RESOURCE LEVELLING (MS PROJECT)RESOURCE LEVELLING (MS PROJECT)
RESOURCE LEVELLING (MS PROJECT)Mayur Rahangdale
 
Precedence Diagramming Method PDM
Precedence Diagramming Method PDMPrecedence Diagramming Method PDM
Precedence Diagramming Method PDMShaiful Amri Mansur
 
Network Techniques for Project Management
Network Techniques for Project ManagementNetwork Techniques for Project Management
Network Techniques for Project ManagementIshan Gandhi
 

Tendances (20)

Critical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/SlacksCritical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/Slacks
 
PERT and CPM
PERT and CPMPERT and CPM
PERT and CPM
 
Pert and CPM
Pert and CPMPert and CPM
Pert and CPM
 
Project Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTProject Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERT
 
Project management techniques
Project management techniquesProject management techniques
Project management techniques
 
Time cost optimisation
Time cost optimisationTime cost optimisation
Time cost optimisation
 
P E R T
P E R TP E R T
P E R T
 
6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource Smoothing6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource Smoothing
 
crashing of project
crashing of project crashing of project
crashing of project
 
Network Techniques
Network TechniquesNetwork Techniques
Network Techniques
 
Critical Path Method(CPM)
Critical Path Method(CPM)Critical Path Method(CPM)
Critical Path Method(CPM)
 
Pert analysis
Pert analysisPert analysis
Pert analysis
 
Network Problem CPM & PERT
Network Problem CPM &  PERTNetwork Problem CPM &  PERT
Network Problem CPM & PERT
 
Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )
 
Project Management - Critical path method
Project Management - Critical path methodProject Management - Critical path method
Project Management - Critical path method
 
RESOURCE LEVELLING (MS PROJECT)
RESOURCE LEVELLING (MS PROJECT)RESOURCE LEVELLING (MS PROJECT)
RESOURCE LEVELLING (MS PROJECT)
 
Precedence Diagramming Method PDM
Precedence Diagramming Method PDMPrecedence Diagramming Method PDM
Precedence Diagramming Method PDM
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 
Pert Analysis
Pert AnalysisPert Analysis
Pert Analysis
 
Network Techniques for Project Management
Network Techniques for Project ManagementNetwork Techniques for Project Management
Network Techniques for Project Management
 

Similaire à Critical Path Method

CPM, Network Analysis A-O-A, A-O-N, Resource management
CPM, Network Analysis A-O-A, A-O-N, Resource managementCPM, Network Analysis A-O-A, A-O-N, Resource management
CPM, Network Analysis A-O-A, A-O-N, Resource managementAmit Kumbar
 
Chapter22 networktechniquesforprojectmanagement
Chapter22 networktechniquesforprojectmanagementChapter22 networktechniquesforprojectmanagement
Chapter22 networktechniquesforprojectmanagementAKSHAYA0000
 
Chapter 12(cpm pert)
Chapter 12(cpm pert)Chapter 12(cpm pert)
Chapter 12(cpm pert)Debanjan15
 
Program Evaluation and Review Technique
Program Evaluation and Review TechniqueProgram Evaluation and Review Technique
Program Evaluation and Review TechniqueRaymund Sanchez
 
CPM Schedule Float.pptx
CPM Schedule Float.pptxCPM Schedule Float.pptx
CPM Schedule Float.pptxMathew Joseph
 
Critical path lecture by EDP.pptxbdhshsjjdj
Critical path lecture by EDP.pptxbdhshsjjdjCritical path lecture by EDP.pptxbdhshsjjdj
Critical path lecture by EDP.pptxbdhshsjjdjlicpn03
 
Management science
Management scienceManagement science
Management sciencekamrul islam
 
CPM.pptx
CPM.pptxCPM.pptx
CPM.pptxLJay7
 
Critical Path Explained With 7 Q&As and a Free Excel Template
Critical Path Explained With 7 Q&As and a Free Excel TemplateCritical Path Explained With 7 Q&As and a Free Excel Template
Critical Path Explained With 7 Q&As and a Free Excel TemplateSHAZEBALIKHAN1
 
criticalpathmethod-151022164503-lva1-app6892.pdf
criticalpathmethod-151022164503-lva1-app6892.pdfcriticalpathmethod-151022164503-lva1-app6892.pdf
criticalpathmethod-151022164503-lva1-app6892.pdfSalahudin Babar
 
Critical path method (CPM).pptx
Critical path method (CPM).pptxCritical path method (CPM).pptx
Critical path method (CPM).pptxHimanshuKaklotar1
 
Critical path presentation for timely project completion
Critical path presentation for timely project completionCritical path presentation for timely project completion
Critical path presentation for timely project completionAniruddha Kulkarni
 
Pb602 operation management chapter 7
Pb602  operation management chapter 7Pb602  operation management chapter 7
Pb602 operation management chapter 7Akihisa Akimoto
 
Chap 4- CPM & PERT.pptx
Chap 4- CPM & PERT.pptxChap 4- CPM & PERT.pptx
Chap 4- CPM & PERT.pptxmohammad_bilal
 

Similaire à Critical Path Method (20)

CPM, Network Analysis A-O-A, A-O-N, Resource management
CPM, Network Analysis A-O-A, A-O-N, Resource managementCPM, Network Analysis A-O-A, A-O-N, Resource management
CPM, Network Analysis A-O-A, A-O-N, Resource management
 
Chapter22 networktechniquesforprojectmanagement
Chapter22 networktechniquesforprojectmanagementChapter22 networktechniquesforprojectmanagement
Chapter22 networktechniquesforprojectmanagement
 
Cpmpert
CpmpertCpmpert
Cpmpert
 
CPM.pptx
CPM.pptxCPM.pptx
CPM.pptx
 
Chapter 12(cpm pert)
Chapter 12(cpm pert)Chapter 12(cpm pert)
Chapter 12(cpm pert)
 
Program Evaluation and Review Technique
Program Evaluation and Review TechniqueProgram Evaluation and Review Technique
Program Evaluation and Review Technique
 
CPM Schedule Float.pptx
CPM Schedule Float.pptxCPM Schedule Float.pptx
CPM Schedule Float.pptx
 
Critical path lecture by EDP.pptxbdhshsjjdj
Critical path lecture by EDP.pptxbdhshsjjdjCritical path lecture by EDP.pptxbdhshsjjdj
Critical path lecture by EDP.pptxbdhshsjjdj
 
Management science
Management scienceManagement science
Management science
 
Networktechniques
NetworktechniquesNetworktechniques
Networktechniques
 
CPM.pptx
CPM.pptxCPM.pptx
CPM.pptx
 
Critical Path Explained With 7 Q&As and a Free Excel Template
Critical Path Explained With 7 Q&As and a Free Excel TemplateCritical Path Explained With 7 Q&As and a Free Excel Template
Critical Path Explained With 7 Q&As and a Free Excel Template
 
criticalpathmethod-151022164503-lva1-app6892.pdf
criticalpathmethod-151022164503-lva1-app6892.pdfcriticalpathmethod-151022164503-lva1-app6892.pdf
criticalpathmethod-151022164503-lva1-app6892.pdf
 
Critical path method (CPM).pptx
Critical path method (CPM).pptxCritical path method (CPM).pptx
Critical path method (CPM).pptx
 
Critical path presentation for timely project completion
Critical path presentation for timely project completionCritical path presentation for timely project completion
Critical path presentation for timely project completion
 
Project Management.pptx
Project Management.pptxProject Management.pptx
Project Management.pptx
 
Pb602 operation management chapter 7
Pb602  operation management chapter 7Pb602  operation management chapter 7
Pb602 operation management chapter 7
 
Cpm and pert
Cpm and pertCpm and pert
Cpm and pert
 
Cpm n pert
Cpm n pertCpm n pert
Cpm n pert
 
Chap 4- CPM & PERT.pptx
Chap 4- CPM & PERT.pptxChap 4- CPM & PERT.pptx
Chap 4- CPM & PERT.pptx
 

Dernier

College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGMANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGSIVASHANKAR N
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsRussian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdfKamal Acharya
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdfankushspencer015
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...ranjana rawat
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 

Dernier (20)

College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGMANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsRussian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 

Critical Path Method

  • 1. Chapter –6 Critical Path Method (CPM) Course Code -CIE 403 Mr. Ramesh Nayaka, (M.Tech. –IIT Madras) Assistant Professor Department of Civil Engineering Manipal Institute of Technology, Manipal -576104 Karnataka, India
  • 2. Content… •Introduction to CPM •Difference between CPM and PERT •Terms and Definitions •Calculation of Float •Critical Path
  • 3. Introduction to CPM CPM network are usually used for repetitive type of projects, where fairly accurate estimates of time can be made for the activities of the project. The activities of these projects are characteristically subject to relatively small amount of variation. Hence CPM is not suitable for research and development type of projects. Examples from fairly diverse field where application of CPM can be made: Building a new bridge across river ganga, Constructing a multi-storeyed building, extension of a factory building, shifting a manufacturing unit to other site and manufacturing of a new car etc.
  • 4. Difference between CPM and PERT CPM PERT Activity Oriented network Event oriented network The time estimatesare of a fair degree of accuracy Time estimates are not that accurate andthere is an uncertainty attached to it Follows deterministic approach Followsprobabilistic approach Cost is governingfactor Time is governing factor Project duration is so fixed such that the cost is minimum Assumed that cost is directly proportional to time so time is reduced maximum possible to enjoy least cost Critical path is thatpath which joins the critical activities Criticalpath is the path which joins the critical events
  • 5. Terms and Definitions Activity Times Forward Passing : Earliest Start Time (EST) :earliest time by which an activity start EST = earliest event time of tail event = TEi Earliest Finish Time (EFT) : Earliest time by which an activity can be completed EFT = EST + tEij= TEi + tEij
  • 6. Terms and Definitions Activity Times Backward Passing : Latest Finish Time (LFT) : latest time by which an activity can completed without delaying the completion of the project LFT = Latest Finish Time of head event = TLj Latest Start Time (LST) : latest time by which an activity can start without delaying the completion of the project LST = LFT -tEij= TLj -tEij
  • 7. Terms and Definitions FLOATS Similar to slack in PERT Associated with activity times Denotes flexibility range within which the activity start and finish time may fluctuate without affecting the total duration of the project
  • 8. Terms and Definitions TYPES OF FLOATS Total Float (FT) : timespan by which starting or finishing of an activity can be delayed without affecting the overall completion time of the project. It refers to the amount of time by which the completion of activity could be delayed beyond earliest expected completion time without affecting overall project duration time FT= LST –EST or LFT -EFT
  • 9. Terms and Definitions TYPES OF FLOATS Free Float (FF) : duration by which an activity can be delayed without delaying any other succeeding activity. It refers to the amount of time by which the completion of an activity can be delayed beyond the earliest finish time without affecting the earliest start time of a subsequent succeeding activity. This float is concerned with the commencement of subsequent activity FF= FT–Sj , Sj= Slack of head event = TLj –TEj
  • 10. Terms and Definitions TYPES OF FLOATS Independent Float (FID): It is excess time available if the preceding activity ends as late as possible and the succeeding activity starts as early as possible It is refers to that the amount of time by which the start of an activity can be delayed, without affecting earliest start time of any immediately following activities This float concerned with prior and subsequent activities FID= FF–Si Si = slack of tail event =TLi–TEi
  • 11. Terms and Definitions TYPES OF FLOATS Interfering Float (FIT) : Another name for head event slack (Sj), it is the difference between total float and free float FIT= FT–FF = TLj –TEj = Sj Note : if the total float (FT) for any activity is zero then such activity is called critical activity Critical Activity : an activity is said to be critical, if a delay in its start cause a further delay in the completion of the entire project
  • 12. Terms and Definitions Critical Path : The sequence of critical activities in a network which determines the duration of a project is called critical path. •It is the longest path in the network from the starting event to the ending event •For activities lies on critical path EST =LST , EFT = LFT and EST –EFT = LST –LFT Sub critical activity : When total float (FT ) is positive Critical Activity :When total float (FT ) is zero Super critical activity : When total float (FT ) is negative
  • 13. Calculating Critical Path & Float for a Network Diagram Find out the length of all the paths in the network diagram The longest path is the critical path Float = EF –LF = ES -LS
  • 14. Terms and Definitions Critical Path : The sequence of critical activities in a network which determines the duration of a project is called critical path. •It is the longest path in the network from the starting event to the ending event •For activities lies on critical path EST =LST , EFT = LFT and EST –EFT = LST –LFT Sub critical activity : When total float (FT ) is positive Critical Activity :When total float (FT ) is zero Super critical activity : When total float (FT ) is negative
  • 15. Terms and Definitions Critical Path : The sequence of critical activities in a network which determines the duration of a project is called critical path. •It is the longest path in the network from the starting event to the ending event •For activities lies on critical path EST =LST , EFT = LFT and EST –EFT = LST –LFT Sub critical activity : When total float (FT ) is positive Critical Activity :When total float (FT ) is zero Super critical activity : When total float (FT ) is negative
  • 16. CPM Analysis F 1 2 4 3 5 6 7 8 A B C D E H K J I 10 8 12 8 10 6 5 12 6 12 8 Aprojectconsistsof11activities,representedbythe networkshownbelowinfigureandalsothenormal durationsrequiredtoperformvariousactivitiesofthe projectaregiveninnetwork.Compute(a)Eventtimes (b)activitytimesandtotalfloat.Alsodetermine thecriticalpath.
  • 17. a. Computation of Event times Event No. PredecessorSuccessorEventEvent12345678Earliest Expected Time (↓ )Latest occurrence Time ( ↑ ) tETETE (Max)tETLTL (Min)
  • 18. b. Computation of activity times and floats Activity Duration Earliest (Units) Latest (Units) Total Float Free Float Independent Float (i -j) tEij EST EFT LST LFT FT FF FID 1 -2 1 -3 2 –5 2 –7 3–4 3–6 4–5 5 -6 5 -7 6 -7 7 -8
  • 19. c. Location of Critical path •1-3 –4 –5 –6 –7 = 52 units F 1 2 4 3 5 6 7 8 A B C D E H K J I 10 8 12 8 10 6 5 12 6 12 8
  • 20. Problem –2 F 1 2 4 3 5 6 7 8 A B G E D I L J 5 4 4 6 2 6 7 8 0 6 7 C K 3 Networkshownbelowinfigureandalsothenormaldurationsrequiredtoperformvariousactivitiesoftheprojectaregiveninnetwork.Compute(a)Eventtimes(b) activitytimes(c)totalfloatforeachactivityandestablishthecriticalpath.Alsodeterminethefreefloatandindependentfloat.
  • 21. Problem –2 1 2 3 6 4 5 A B E D G H 3 5 3 1 14 4 C F 4 Networkshownbelowinfigureandalsothenormaldurationsrequiredtoperformvariousactivitiesoftheprojectaregiveninnetwork.Compute(a)Eventtimes(b) activitytimes(c)totalfloatforeachactivityandestablishthecriticalpath.Alsodeterminethefreefloatandindependentfloat. 6 1 I