TECHNICAL REPORT
Project: Overhauling And Calibration Of
Control Valves
Engro Fertilizers Plant-II Shutdown, Dharki
(April 27 – May 10, 2016)
Client:
Submitted to: Mr. Asad Naeem (Instrument Engineer)
Work Order Reference: 6636 Purchase Order Reference: 5000001993
Flowtronix Head Office: 101/s, Quaid-e-Azam Industrial Estate, Kot Lakhpat, Lahore 54760 – Pakistan. UAN: 111-355-355 (111-EKL-EKL) Tel: 92-42-35215611 Fax: +92-42-35151104
E-mail: flowtronix@ddfcgroup.com
Manpower Detail
Organogram
Tools & Equipment Used Page 3
List of control valves
Daily Progress Log
Valve Record Sheets
6.1 11-XV-2011A
6.2 11-FV-2048
6.3 11-HV-2011
6.4 11-XV-2011B
6.5 11-FV-2030
6.6 11-FV-2011
6.7 11-FV-1801
6.8 11-FV-2033
6.9 11-PV-2046
Page 19
Page 20
Page 21
Overhauling and Calibrations
Of Control Valves
6
Table Of Contents
1
2
Page 12
Page 1
Page 2
Page 4
Page 5
4
5
3
Page 12
Page 13
Page 15
Page 16
Page 18
Page 17
Page 14
6.9 11-PV-2046
6.10 11-PV-2027
6.11 10-LV-1018
6.12 11-HV-3022
6.13 11-FV-2026
6.14 11-FV-2076
6.15 11-XV-2027
6.16 11-PV-7498
6.17 11-PV-2046B
6.18 11-PV-7109
6.19 PIC-611V
6.20 LIC-611A
6.21 11-FV-7010
6.22 11-PV-3015B
6.23 11-PV-2021
6.24 11-XV-2027A
6.25 11-XV-2027C
6.26 11-FV-3021B
6.27 11-FV-3026D
6.28 11-FV-3022
6.29 11-LV-5010A
6.30 11-HV-1012
6.31 10-LV-1003
6.32 11-LV-5010B
6.33 10-HV-1008
6.34 11-TV-3004
Page 20
Page 21
Page 22
Page 23
Page 24
Page 25
Page 26
Page 27
Page 28
Page 29
Page 30
Page 31
Page 32
Page 33
Page 34
Page 35
Page 36
Page 37
Page 38
Page 39
Page 40
Page 41
Page 42
Page 43
Page 45
Page 44
Page 46
Overhauling and Calibrations
Of Control Valves
Table Of Contents
6.37 11-FV-2056
6.38 10-HV-1009
6.39 11-LV-3011B
6.40 11-LV-3011A
6.41 19-FV-9001A
6.42 19-FV-9002
6.43 11-FV-2028
6.44 11-LV-2055
6.45 11-TV-5482
6.46 11-TV-5476
6.47 11-HV-1032B
Pictures (Work In Progress)
Page 53
7 Page 59
Page 48
Page 58
Page 54
Page 55
Page 56
Page 57
Page 49
Page 50
Page 51
Page 52
1. MANPOWER DETAIL:
Sr. No. Father's Name Trade Shift
1 Amer Siddiq Project Incharge Day/Night
2 Mohammad Jamil Supevervisor Day
3 Haq Nawaz Supevervisor Night
4 Sher Muhammad Instr. Fitter Night
5 Abdul Rasheed Instr. Fitter Night
6 M Yameen Instr. Fitter Day
7 M Sadiq Instr. Fitter Day
8 M Ramzan Instr. Fitter Day
9 Basheer Ahmad Instr. Fitter Day
10 M Aslam Instr. Fitter Day
11 Abdul Hameed Instr. Fitter Night
Sagheer ahmad Sajid
M Ilyas
M Tariq
Name
Ramiz Siddiq
Sajid Tanveer
Sajjad ahmad
Overhauling and Calibrations Of
Control Valves
Abdul Rehman
Saeed Ahmad
Jalal Uddin M Akbar
M Shafiq
Aamir Usman
M Khalid
11 Abdul Hameed Instr. Fitter Night
12 Ali Hassan Instr. Fitter Night
13 Riasat Ali Instr Tech Day
14 Maqbool Ahmad Instr Tech Day
15 Ghulam Akbar Instr Tech Day
16 Amman Ullah Instr Tech Day
17 Mohammad Bashir Instr Tech Night
18 Ghulam Hussain Instr Tech Night
19 Mushtaq Ahmad Instr Tech Night
20 Helper Night
21 Abdul Sattar Helper Day
22 Abdul Wahid Helper Day
23 Iftikhar Husain Helper Day
24 M Yousaf Helper Day
25 Mohammad Nazir Helper Night
26 M Alamgir Helper Day
27 Mushtaq Ahmad Helper Night
Mohammad Ali
M Umer
Mohammad Muddasar
Hafiz Adnan Hussain
Mohmmmad Mubasher
Amjad Mubeen
Anees Sattar
M Shoaib
M Zubair
M Adil
Mohammad Umair Riasat
Mohammad Abid Naeem
Abul Sattar
Irfan Ullah
Iftikhar Ahmad
M Shafiq
Aamir Usman
Page 1 of 59
2. ORGANOGRAM:
Day Shift Night Shift
Team 1 Team 2 Team 3
Ramiz Siddiq
(Project Incharge)
Mohamad Tariq
(Instr. Fitter)
Saeed Ahmad
(Instr. Fitter)
Mohammad Ilyas
(Instr. Fitter)
M Shoaib
(Helper)
Umari Riasat
(Instr. Technician)
M Adil
(Helper)
Overhauling and Calibrations Of
Control Valves
Sajid Tanveer
(Instrument Supervisor)
Abdul Sattar
(Instr. Technician)
Abid Naeem
(Instr. Technician)
Irfan Ullah
(Instr. Technician)
Abdul Rehman
(Instr. Fitter)
Jallal Uddin
(Instr. Fitter)
Anees Sattar
(Helper)
Team 1 Team 2 Team 3
Mohammad Shafiq
(Instr. Fitter)
M Shoaib
(Helper)
M Adil
(Helper)
Hafiz Adnan
(Instr. Technician)
Sajjad Ahmad
(Instrument Supervisor)
Amjad Mubeen
(Helper)
Mohamamd Ali
(Helper)
Sagheer Ahmad
(Instr. Fitter)
M Umer
(Helper)
Hafiz Iftikhar
(Instr. Technician)
M. Muddassar
(Helper)
Aamir Usman
(Instr. Fitter)
Mohammad Khalid
(Instr. Fitter)
Anees Sattar
(Helper)
M. Mubasher
(Instr. Technician)
Page 2 of 59
3. TOOLS USED:
Screw Drivers (Star Set)
Allen Key Set (Star, mm, inch)
Side Cutters
Monkey Pliers
Combination Pliers
Nose Pliers
Open End & Ring Spanner Sets
Needle File Set
Files (Round, Half Round and Flat)
Stacking Spanner Set (26-50mm)
Hammers (Rubber, Wooden, Brass & MS)
Overhauling and Calibrations Of
Control Valves
Sr. No. Tools & Equipment
1
2
3
4
5
6
7
8
9
10
11
12
A. Used For Overhauling
Hammers (Rubber, Wooden, Brass & MS)
Lifting Belts & D-Shackles
Vernier Caliper
Digital Multimeter
HART Communicator
mAmp Source
DC Source
Pressure Guage
Air Regulator
5
6
1
2
3
4
B. Used For Calibration
11
12
13
Page 3 of 59
4. LIST OF CONTROL VALVES:
Total Quantity : 47 Nos.
6
12
-
20
8
-
-
6
4
8
16
16
12
Size (inch)
8
12
-
12
4
8
11-FV-7010
LIC-611A
PIC-611V
11-PV-2046B
18
19
11-LV-5010A
11-FV-3022
11-LV-3026D
11-FV-3021B
11-XV-2027C
11-XV-2027A
10-HV-1012
10-PV-1021A
11-PV-3015B
6
3
4
5
7
8
9
10
11
13
14
15
12
16
17
11-TV-3004
10-HV-1008
11-LV-5010B
10-FV-1003
Overhauling and Calibrations Of
Control Valves
Sr. No.
1
2
Tag No.
11-HV-2071A
11-PV-7109
11-HV-1032B
46
47
-
1
4
4
4
-
11-TV-5476
45
19-PV-9001A
11-FV-2028
11-LV-2055
11-TV-5482
42
44
43
18
18
8
8
10
10
10
8
-
8
12
4
6
3
10
24
12
6
12
-
-
8
8
-
10-HV-1009
11-FV-2056
11-PV-1048
11-FV-2048
11-XV-2011A
11-LV-3011A
11-LV-3011B
19-FV-9002
11-FV-2033
10-FV-1801
11-FV-2011
11-FV-2030
11-HV-2011
11-XV-2011B
11-FV-2076
11-FV-2026
11-HV-3022
10-LV-1018
11-PV-2027
11-PV-2046A
PIC-611V
11-PV-2046B
24
25
26
22
23
11-PV-7498
11-XV-2027
18
19
20
21
27
36
37
38
39
33
34
35
40
41
28
29
30
31
32
Page 4 of 59
5. DAILY PROGRESS LOG:
Sr # Tag No. Activities Date Shift D/N
Cleaning, Oiling and Polishing
Found resetting device faulty
Found tyflon inside body
Pnumatic Relay Checked
Calibrated
Sent for Hydro testing
Cleaning, Oiling and Polishing
Found Valve ball stuck
Calibrated
Sent for Hydro testing
Cleaning, Oiling and Polishing
Air leak test of actuator was found OK
Hand jack was made smooth by servicing
Calibrated
Sent for Hydrotesting
Cleaning, Oiling and Polishing
Overhauling
3 11-HV-2011 27-4-16 Night
Day
4 27-4-16 Night
1 27-4-1611-XV-2011B
2 27-4-16 Day11-XV-2011A
11-FV-2048
Overhauling and Calibrations
Of Control Valves
Overhauling
Calibrated
Sent for Hydro testing
Cleaning, Oiling and Polishing
Overhauling Started
Cleaning, Oiling and Polishing
Removing & Cleaning Positioner
Removing & Cleaning Limit Switches
Overhauling
Found leakage in Cylinder
Cleaning, Oiling and Polishing
Overhauling
Cleaning, Oiling and Polishing
Overhauling Started
Cleaning, Oiling and Polishing
Overhauling Started
Cleaning, Oiling and Polishing
Overhauling Started
Valve body sent for machining
Cleaning, Oiling and Polishing
Overhauling
Calibrated
Sent for Hydro testing
Cleaning, Oiling and Polishing
Overhauling
Sent Actuator Stem for machining
Calibrated
Sent for Hydro testing
7 28-4-16 Day10-FV-1801
28-4-16
28-4-16
Day
Day
Night
4 27-4-16 Night
6 28-4-16 Day
5 27-4-16 Night
11-FV-2048
11-FV-2030
11-FV-2011
28-4-16
8
9
10
11-PV-2046B
11-FV-2033
10-LV-1018
Night
Night
11
12
28-4-16
28-4-16
11-PV-2027
11-FV-2030
Page 5 of 59
5. DAILY PROGRESS LOG:
Sr # Tag No. Activities Date Shift D/N
Day1 27-4-1611-XV-2011B
Overhauling and Calibrations
Of Control Valves
Cleaning, Oiling and Polishing
Removing & Cleaning of Positioner
Removing & Cleaning of Limit Switch
Overhauling
Calibration
Sent for Hydrotesting
Cleaning, Oiling and Polishing
Overhauling
Calibration
Sent for Hydrotesting
Cleaning, Oiling and Polishing
Air Leak test ok
Calibration
Valve Body returned from Machining
Calibration
Sent for Hydrotesting
Cleaning, Oiling and Polishing
15 29-4-16 Day
14 29-4-16 Day
13 29-4-16 Day11-FV-2011
11-FV-2033
11-HV-3022
29-4-16 Night16
17
10-LV-1018
29-4-16 Night
11-FV-2026
Cleaning, Oiling and Polishing
Overhauling
Calibration
Sent for Hydrotesting
Cleaning, Oiling and Polishing
Overhauling
Calibration
Sent for Hydrotesting
Cleaning, Oiling and Polishing
Air Leak test ok
Cleaning, Oiling and Polishing
Overhauling Started
Cleaning, Oiling and Polishing
Overhauling
Calibration
Sent for Hydrotesting
Cleaning, Oiling and Polishing
Overhauling
Calibration
Sent for Hydrotesting
Cleaning, Oiling and Polishing
Overhauling
Calibration
Sent for Hydrotesting
Cleaning, Oiling and Polishing
Air leak test ok
Overhauling Started
19
18
17
29-4-16 Night
20
21 30-4-16 Day
Day30-4-1622
23
29-4-16 Night
29-4-16 Night
29-4-16 Night
11-FV-2026
11-FV-2076
11-XV-2027
10-LV-2018
11-PV-7498
11-FV-1801
30-4-16 Day
24 30-4-16 Day
11-PV-2046B
11-PV-7109
Page 6 of 59
5. DAILY PROGRESS LOG:
Sr # Tag No. Activities Date Shift D/N
Day1 27-4-1611-XV-2011B
Overhauling and Calibrations
Of Control Valves
Cleaning, Oiling and Polishing
Air Leak test ok
Overhauling
Valve Seat Missing, New installed
New Lock relay installed
Calibration
Sent for Hydrotesting
Cleaning, Oiling and Polishing
Air Leak test ok
Overhauling
Calibration
Sent for Hydrotesting
Cleaning, Oiling and Polishing
Overhauling Started
Cleaning, Oiling and Polishing
Air Leak test ok
Overhauling
Night26 30-4-16
27 30-4-16 Night
25 30-4-16 NightPIC-611V
LIC-611A
11-FV-7010
28 01-5-16 Day11-PV-3015B
Overhauling
Servicing of hand wheel
Calibration
Sent for Hydrotesting
Cleaning, Oiling and Polishing
Air Leak test ok
Removing & Cleaning of Positoner
Cleaning, Oiling and Polishing
Air Leak test ok
Calibration
Sent for Hydrotesting
Cleaning, Oiling and Polishing
Air Leak test ok
Calibration
Sent for Hydrotesting
Cleaning, Oiling and Polishing
Overhauling Started
Cleaning, Oiling and Polishing
Air Leak test ok
Overhauling
Found Leakage in Pneumatic relay
Fixed Pneumatic realy
Calibration
Sent for Hydrotesting
Cleaning, Oiling and Polishing
Air Leak test ok
Overhauling Started
29 01-5-16 Day
30 01-5-16 Day
28 01-5-16 Day11-PV-3015B
11-PV-1021A
11-XV-2027A
32 01-5-16 Day
33 01-5-16 Night
31 01-5-16 Day11-XV-2027C
11-PV-7109
11-FV-7010
34 01-5-16 Night11-FV-3021B
Page 7 of 59
5. DAILY PROGRESS LOG:
Sr # Tag No. Activities Date Shift D/N
Day1 27-4-1611-XV-2011B
Overhauling and Calibrations
Of Control Valves
Cleaning, Oiling and Polishing
Air Leak test ok
Found valve not 100% opening
Positioner Dismantled
Overhauling
Sent body for machining
Hydrotest Failed @2400psi
Bench Set readjusted
Valve stem readjusted
Calibrated
Sent For Hydrotesting
Cleaning, Oiling and Polishing
Air Leak test ok
Cleaning, Oiling and Polishing
Air Leak test ok
Sent body for machining
Hydrotest Failed
02-05-16 Day
38 02-05-16 Day
39 02-05-16 Night
35 02-05-16 Day
Day02-05-1636
37
11-LV-3026D
10-FV-1801
11-FV-3022
11-LV-5010A
11-FV-7010
Hydrotest Failed
Found Valve Positioner faulty
Found Pneumatic Relay faulty
Fixed pneumatic relay and reinstalled
Calibrated
Sent For Hydrotesting
Overhauling
Air Leak test ok
Sent seat, cage and stem for machining
Calibrated
Sent For Hydrotesting
Cleaning, Oiling and Polishing
Air Leak test ok
Overhauling
Calibration Started
Cleaning, Oiling and Polishing
Air Leak test ok
Calibrated
Sent For Hydrotesting
Received Body from machining
Overhauling
44 10-FV-1003 Cleaning, Oiling and Polishing 03-05-16 Day
Cleaning, Oiling and Polishing
Air Leak test ok
Overhauling
Sent For Hydrotesting
Cleaning, Oiling and Polishing
Air Leak test ok
41 02-05-16 Night
39 02-05-16 Night
40 02-05-16 Night
42 03-05-16 Day
43 03-05-16 Day
45 03-05-16 Day
Day03-05-1646
11-LV-3026D
11-LV-5010A
11-LV-5010B
11-FV-7010
11-FV-3021B
11-FV-3022
10-HV-1012
Page 8 of 59
5. DAILY PROGRESS LOG:
Sr # Tag No. Activities Date Shift D/N
Day1 27-4-1611-XV-2011B
Overhauling and Calibrations
Of Control Valves
Calibration
Sent For Hydrotesting
Cleaning, Oiling and Polishing
Air Leak test ok
Sent seat, cage and stem for machining
49 10-HV-1008 Flange Opened 03-05-16 Night
Cleaning, Oiling and Polishing
Air Leak test ok
Sent seat, cage and stem for machining
Overhauling
Sent For Hydrotesting
Cleaning, Oiling and Polishing
Air Leak test ok
Overhauling
Calibration
Sent For Hydrotesting
Cleaning, Oiling and Polishing
11-TV-300452 04-05-16 Day
48 03-05-16 Night
47 03-05-16 Night
50 04-05-16
04-05-16 Day
Day
51
11-FV-3022
11-PV-7109
11-LV-5010B
10-PV-1021A
Cleaning, Oiling and Polishing
Air Leak test ok
Bench Set was found
Sent For Hydrotesting
Cleaning, Oiling and Polishing
Air Leak test ok
Calibration
Sent For Hydrotesting
Cleaning, Oiling and Polishing
Air Leak test ok
Calibration
Sent For Hydrotesting
Cleaning, Oiling and Polishing
Air Leak test ok
Calibration
Sent For Hydrotesting
Cleaning, Oiling and Polishing
Air Leak test ok
Seat and plug were sent for machining
All gaskets replaced
Diapharm was found torned
Diapharm replaced
Calibrated
Sent for Hydrotesting
56 05-05-16 Day
11-HV-2071A55 05-05-16 Day
11-TV-300452 04-05-16 Day
54 04-05-16 Night
Night04-05-1653 11-LV-3026D
11-HV-2011A
11-PV-1048
Page 9 of 59
5. DAILY PROGRESS LOG:
Sr # Tag No. Activities Date Shift D/N
Day1 27-4-1611-XV-2011B
Overhauling and Calibrations
Of Control Valves
Received seat, cage and stem from machining
Seat gasket replaced
Body gaskets replaced
Air leak test of actuator was found OK
Calibrated
Sent for Hydro testing
Cleaning, Oiling and Polishing
Air Leak test ok
Positioner Dismantled
Cleaning, Oiling and Polishing
Air Leak test ok
Bench Set was found
Cleaning, Oiling and Polishing
Air Leak test ok
Overhauling of body and actuator
Seat and plug were sent for machining
Cleaning, Oiling and Polishing
60 06-05-16 Day
06-05-1610-HV-100961 Day
11-PV-710957 05-05-16 Night
11-LV-3011A58 05-05-16 Night
05-05-16 Night11-LV-3011B59
19-FV-9002
Cleaning, Oiling and Polishing
Air Leak test ok
Outer diapharm of actuator was disassembled
Bench Set was found
Cleaning, Oiling and Polishing
Air Leak test ok
Plug, seat and cage were sent for machining
Cleaning, Oiling and Polishing
Air Leak test ok
Diapharm was found Ok
Overhauling of body and actuator
O-rings replaced
Seat, plug sent for machining
All gaskets replaced
Calibrated
Sent For Hydrotesting
Body gaskets replaced
Calibrated
Sent for Hydro testing
Received Plug, seat and cage from machining
All three gaskets of valve replaced
Gland packing was replaced
Calibrated
Sent for Hydro testing
Received Plug, seat and cage from machining
Gaskets were replaced
Gland packing was replaced
67 10-HV-1009 Plug and gland packing were removed 07-05-16 Day
11-LV-3011B65 06-05-16 Night
11-LV-3011A66 06-05-16 Night
19-FV-9001A63 6-5-16 Day
64 06-05-16 Night
06-05-1610-HV-100961 Day
62 06-05-16 Day
19-FV-9002
11-LV-3011B
Page 10 of 59
5. DAILY PROGRESS LOG:
Sr # Tag No. Activities Date Shift D/N
Day1 27-4-1611-XV-2011B
Overhauling and Calibrations
Of Control Valves
Received Plug, seat and cage from machining
Bench Set readjusted
Calibration
Sent for Hydro testing
Cleaning, Oiling and Polishing
Plug, seat and cage were sent for machining
Tubing was readjusted
Calibrated
Sent for Hydro testing
Cleaning, Oiling and Polishing
Air Leak test ok
Positioner was removed for cleaning
Diapharm was found ok
Calibrated
Sent For Hydrotesting
Cleaning, Oiling and Polishing
Air Leak test ok
68 11-LV-3011B 07-05-16 Day
10-LV-100772 08-05-16 Day
69 11-HV-1008 07-05-16 Day
11-LV-3011A70 07-05-16 Day
11-PV-749871 08-05-16 Day
Air Leak test ok
Calibration was tested and found ok
Scratches were found on valve stem
Removed scratches by filing and embre paper
Air Leak test ok
Sent For Hydrotesting
Actuator was reopened
Overhauling of body and actuator
Cleaning, Oiling and Polishing
Air Leak test ok
Calibration
Cleaning, Oiling and Polishing
Air Leak test ok
Calibration
Cleaning, Oiling and Polishing
Air Leak test ok
Calibration
Cleaning, Oiling and Polishing
Air Leak test ok
Calibration
Cleaning, Oiling and Polishing
Air Leak test ok
Calibration
10-LV-100772 08-05-16 Day
73 10-HV-1009 08-05-16 Day
11-TV-547677 10-05-16 Night
78 11-HV-1032B 10-05-16 Night
09-05-16 Day11-FV-202874
11-LV-205575 09-05-16 Night
11-TV-548276 10-05-16 Day
Page 11 of 59
CLIENT DATE: 27-04-2016
PROJECT DOC.NO. CV-E-001
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 11-XV-2011A SERVICE: Process Air SIZE: 12"
AREA: AMM-3 FLANGE TYPE: Flanged
PHYSICAL CHECKS:
Overhauling and Calibrations Of
Control Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
Flowtronix (Pvt) Ltd.
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:
This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
DATE
27-04-2016
EXECUTED BY
Umair Riasat
(Instrument Technician)
1. Valve ball was stuck.
2. Cleaning, oiling and polishing the vlave ball.
FAIL SAFE ACTION
Close
SUPPLIED PRESSURE
87 psi
VALVE BENCH SET
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 12 of 59
CLIENT DATE: 27-04-2016
PROJECT DOC.NO. CV-E-002
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 11-FV-2048 SERVICE: Process Air SIZE: 8-/-4-/-8"
AREA: AMM-3 FLANGE TYPE: RF Flanges
PHYSICAL CHECKS:
Overhauling and Calibrations Of
Control Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
Flowtronix (Pvt) Ltd.
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:
This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
DATE
27-04-2016
EXECUTED BY
Umair Riasat
(Instrument Technician)
1. Actuator O-rings were replaced.
2. Pug and seat were sent for machining.
3. All gaskits were replaced.
4. Overhauling
5. Calibrated
6. Sent for Hydrotesting
VALVE BENCH SET FAIL SAFE ACTION
Close
SUPPLIED PRESSURE
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 13 of 59
CLIENT DATE: 27-04-2016
PROJECT DOC.NO. CV-E-003
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 11-HV-2011 SERVICE: Process Air SIZE: 8 "
AREA: AMM-3 FLANGE TYPE: RF 125 AARH
PHYSICAL CHECKS:
Flowtronix (Pvt) Ltd.
Overhauling and Calibrations Of
Control Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:
This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
1. Actuator was found stuck.
2. Air leak test of actuator was found OK
3. Hand jack was made smooth by servicing
4. Calibrated
5. Sent For Hydrotesting
DATE
27-04-2016
EXECUTED BY
Umair Riasat
(Instrument Technician)
VALVE BENCH SET FAIL SAFE ACTIONSUPPLIED PRESSURE
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 14 of 59
CLIENT DATE: 27-04-2016
PROJECT DOC.NO. CV-E-004
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 11-XV-2011B SERVICE: Process Air SIZE:
AREA: AMM-3 FLANGE TYPE:
PHYSICAL CHECKS:
Overhauling and Calibrations Of
Control Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
Flowtronix (Pvt) Ltd.
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:
This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
DATE
27-04-2016
EXECUTED BY
Umair Riasat
(Instrument Technician)
1. Tyflon Seat seal was damaged.
2. Found air leakage in resetting device.
3. Tyflon seat seal replaced.
4. Resetting device O-Rings were replaced
5. Calibrated
6. Sent for hydrotesting
VALVE BENCH SET FAIL SAFE ACTION
Open
SUPPLIED PRESSURE
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 15 of 59
CLIENT DATE: 27-04-2016
PROJECT DOC.NO. CV-E-005
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 11-FV-2030 SERVICE: Process Air SIZE: 10 "
AREA: AMM-3 FLANGE TYPE: RF Flanges
PHYSICAL CHECKS:
Overhauling and Calibrations Of
Control Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
Flowtronix (Pvt) Ltd.
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:
This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
DATE
27-04-2016
EXECUTED BY
Umair Riasat
(Instrument Technician)
1. Overhauling of actuator and body.
2. Actuator Stem was sent for machining.
3. Actuator Gasket replaced
4. Gland packing replaced.
5. Calibration
6. Sent for hydrotesting
VALVE BENCH SET FAIL SAFE ACTIONSUPPLIED PRESSURE
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 16 of 59
CLIENT DATE: 28-04-2016
PROJECT DOC.NO. CV-E-006
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 11-FV-2011 SERVICE: Process Air SIZE: 12 "
AREA: AMM-3 FLANGE TYPE: RF-125 AARH
PHYSICAL CHECKS:
Overhauling and Calibrations Of
Control Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
Flowtronix (Pvt) Ltd.
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:
This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
DATE
28-04-2016
EXECUTED BY
Umair Riasat
(Instrument Technician)
1. Found air leakage in cylinder
2. Overhauling of Actuator
3. O-rings required relacements, tyflon was wound due to inavailablity.
4. Found a embosed spot on piston
5. Removing and cleaning of positioner
6. Removing and cleaning of Actuator
7. Feedback link plate gaskets replaced
8. Calibration
9. Sent for hydrotesting
VALVE BENCH SET FAIL SAFE ACTION
Close
SUPPLIED PRESSURE
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 17 of 59
CLIENT DATE: 28-04-2016
PROJECT DOC.NO. CV-E-007
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 10-FV-1801 SERVICE: Process Air SIZE: 24 "
AREA: AMM-3 FLANGE TYPE:
PHYSICAL CHECKS:
Overhauling and Calibrations Of
Control Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
Flowtronix (Pvt) Ltd.
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:
This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
DATE
28-04-2016
EXECUTED BY
Umair Riasat
(Instrument Technician)
1. Removing and Cleaning of Positioner
2. Overhauling of Actuator
3. Plug was sent for machining
4. Gland packing replaced
5. Seals replaced
6. Found a embosed spot on piston.
7. Calibrated
8. Sent for hydrotesting
VALVE BENCH SET FAIL SAFE ACTIONSUPPLIED PRESSURE
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 18 of 59
CLIENT DATE: 28-04-2016
PROJECT DOC.NO. CV-E-008
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 11-FV-2033 SERVICE: Process Air SIZE: 6 "
AREA: AMM-3 FLANGE TYPE: RF Flanges
PHYSICAL CHECKS:
Overhauling and Calibrations Of
Control Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
Flowtronix (Pvt) Ltd.
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:
This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
DATE
28-04-2016
EXECUTED BY
Umair Riasat
(Instrument Technician)
1. Overhauling of Actuator
2. Overhauling of Body
3. Seat seals replaced
4. Gland packing replaced
5. Vapour Seals replaced
6. Actuator O-rings replaced
7. Inner and outer plug seals replaced
8. Calibrated
9. Sent for Hydrotesting
VALVE BENCH SET FAIL SAFE ACTION
Close
SUPPLIED PRESSURE
30
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 19 of 59
CLIENT DATE: 28-04-2016
PROJECT DOC.NO. CV-E-009
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 11-PV-2046A SERVICE: Process Air SIZE: 3 "
AREA: AMM-3 FLANGE TYPE: RF Flanges
PHYSICAL CHECKS:
Overhauling and Calibrations Of
Control Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
Flowtronix (Pvt) Ltd.
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:
This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
DATE
28-04-2016
EXECUTED BY
Umair Riasat
(Instrument Technician)
1. Overhauling of actuator
VALVE BENCH SET FAIL SAFE ACTION
Close
SUPPLIED PRESSURE
40
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 20 of 59
CLIENT DATE: 28-04-2016
PROJECT DOC.NO. CV-E-010
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 11-PV-2027 SERVICE: Process Air SIZE:
AREA: AMM-3 FLANGE TYPE:
PHYSICAL CHECKS:
Overhauling and Calibrations Of
Control Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
Flowtronix (Pvt) Ltd.
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:
This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
DATE
28-04-2016
EXECUTED BY
Umair Riasat
(Instrument Technician)
1. Overhauling of Actuator
2. Overhauling of Body
3. Seat, Plug and cage were sent for machining
4. Seat seals replaced
5. Gland packing replaced
6. Body and seat gasket replaced
7. Actuator O-rings replaced
VALVE BENCH SET FAIL SAFE ACTIONSUPPLIED PRESSURE
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 21 of 59
CLIENT DATE: 29-04-2016
PROJECT DOC.NO. CV-E-011
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 10-LV-1018 SERVICE: Process Air SIZE: 4 "
AREA: AMM-3 FLANGE TYPE: RF Flanges
PHYSICAL CHECKS:
Overhauling and Calibrations Of
Control Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
Flowtronix (Pvt) Ltd.
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:
This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
DATE
29-04-2016
EXECUTED BY
Umair Riasat
(Instrument Technician)
1. Found Leak test of actuator OK
2. Overhauling of Actuator
3. Overhauling of Body
4. Body was sent for machining
5. Seat seals replaced
6. Body gasket replaced
7. Actuator O-rings replaced
8. Gland packings replaced
9. Calibrated
VALVE BENCH SET FAIL SAFE ACTIONSUPPLIED PRESSURE
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 22 of 59
CLIENT DATE: 29-04-2016
PROJECT DOC.NO. CV-E-012
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 11-HV-3022 SERVICE: Process Air SIZE: 8 "
AREA: AMM-3 FLANGE TYPE: RF Flanges
PHYSICAL CHECKS:
Overhauling and Calibrations Of
Control Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
Flowtronix (Pvt) Ltd.
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:
This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
DATE
29-04-2016
EXECUTED BY
Umair Riasat
(Instrument Technician)
1. Air Leak check of actuator was found OK
2. Calibrated
3. Sent for Hydrotesting
VALVE BENCH SET FAIL SAFE ACTION
Close
SUPPLIED PRESSURE
60
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 23 of 59
CLIENT DATE: 29-04-2016
PROJECT DOC.NO. CV-E-013
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 11-FV-2026 SERVICE: Process Air SIZE: 8 "
AREA: AMM-3 FLANGE TYPE: RF Flanges
PHYSICAL CHECKS:
Overhauling and Calibrations Of
Control Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
Flowtronix (Pvt) Ltd.
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:
This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
DATE
29-04-2016
EXECUTED BY
Umair Riasat
(Instrument Technician)
1. Overhauling of Body
2. Overhauling of Actuator
3. Seat and plug were sent for machining
4. Plug seal ring (carbon) was repalced.
5. Inner and outer seals were replaced
6. Gland packing replaced
7. Calibrated
VALVE BENCH SET FAIL SAFE ACTIONSUPPLIED PRESSURE
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 24 of 59
CLIENT DATE: 29-04-2016
PROJECT DOC.NO. CV-E-014
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 11-FV-2076 SERVICE: Process Air SIZE: 4 "
AREA: AMM-3 FLANGE TYPE: RTJ Flanges
PHYSICAL CHECKS:
Overhauling and Calibrations Of
Control Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
Flowtronix (Pvt) Ltd.
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:
This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
DATE
29-04-2016
EXECUTED BY
Umair Riasat
(Instrument Technician)
1. Overhauling of body
2. Overhauling of actuator
3. Inner and outer seals replaced
4. Gland packing replaced
5. O-rings replaced
6. Calibrated
VALVE BENCH SET FAIL SAFE ACTIONSUPPLIED PRESSURE
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 25 of 59
CLIENT DATE: 29-04-2016
PROJECT DOC.NO. CV-E-015
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 11-XV-2027 SERVICE: Process Air SIZE: 4 "
AREA: AMM-3 FLANGE TYPE: RTJ Flanges
PHYSICAL CHECKS:
Overhauling and Calibrations Of
Control Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
Flowtronix (Pvt) Ltd.
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:
This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
DATE
29-04-2016
EXECUTED BY
Umair Riasat
(Instrument Technician)
1. Air leak test of actuator was found OK
2. Overhauling of actuator
3. Overhauling of body
4. Seat, Plug and Cage were machined
5. Seat seals replaced
4. Gland packing replaced
5. Body and seat gaskets replaced
6. Calibrated
VALVE BENCH SET FAIL SAFE ACTIONSUPPLIED PRESSURE
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 26 of 59
CLIENT DATE: 30-04-2016
PROJECT DOC.NO. CV-E-016
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 11-PV-7498 SERVICE: Process Air SIZE: 12 "
AREA: AMM-3 FLANGE TYPE: RF Flanges
PHYSICAL CHECKS:
Overhauling and Calibrations Of
Control Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
Flowtronix (Pvt) Ltd.
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:
This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
DATE
30-04-2016
EXECUTED BY
Abid Naeem
(Instrument Technician)
1. Diapharm was stretched and torn from nut & bolts holes at circumference.
2. Overhauling of actuator
3. Actuator seals replaced
4. Diapharm replaced
5. Calibrated
VALVE BENCH SET FAIL SAFE ACTION
Close
SUPPLIED PRESSURE
58
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 27 of 59
CLIENT DATE: 30-04-2016
PROJECT DOC.NO. CV-E-017
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 11-PV-2046B SERVICE: Process Air SIZE: 6-/-3-/-6
AREA: AMM-3 FLANGE TYPE: RF Flanges
PHYSICAL CHECKS:
Overhauling and Calibrations Of
Control Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
Flowtronix (Pvt) Ltd.
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:
This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
DATE
30-04-2016
EXECUTED BY
Abid Naeem
(Instrument Technician)
1. Overhauling of actuator
2. Plug and seat ring polished
3. Seat gaskets changed
4. Body gaskets replaced
5. Gland packing replaced.
6. O-rings of actuator replaced.
7. Calibrated
8. Sent for Hydrotesting
VALVE BENCH SET FAIL SAFE ACTIONSUPPLIED PRESSURE
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 28 of 59
CLIENT DATE: 30-04-2016
PROJECT DOC.NO. CV-E-018
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 11-PV-7109 SERVICE: Process Air SIZE: 12 "
AREA: AMM-3 FLANGE TYPE: RF Flanges
PHYSICAL CHECKS:
Overhauling and Calibrations Of
Control Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
Flowtronix (Pvt) Ltd.
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:
This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
DATE
30-04-2016
EXECUTED BY
Abid Naeem
(Instrument Technician)
1. Air leak test of actuator was found OK
2. Valve bonut was stuck with actuator yoke, heated and hammered to get them separated.
3. Overhauling of body
4. Plug, Seat and Cage were sent for machining
5. Inner and outer body gaskets were replaced
6. Both rings of valve plug were replaced
7. Calibrated
8. Sent for Hydrotesting
VALVE BENCH SET FAIL SAFE ACTION
Close
SUPPLIED PRESSURE
60
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 29 of 59
CLIENT DATE: 30-04-2016
PROJECT DOC.NO. CV-E-019
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: PIC-611V SERVICE: Process Air SIZE:
AREA: AMM-3 FLANGE TYPE:
PHYSICAL CHECKS:
Overhauling and Calibrations Of
Control Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
Flowtronix (Pvt) Ltd.
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:
This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
DATE
30-04-2016
EXECUTED BY
Abid Naeem
(Instrument Technician)
1. Valve seat was not found during disassembly
2. Lock relay was not working
3. Seat and plug were sent for machining
4. Air Leak test of Actuator was found OK
5. Overhauling of Valve body
6. Seals replaced
7. Lock relay replaced
8. Calibrated
9. Sent for Hydrotesting
VALVE BENCH SET FAIL SAFE ACTIONSUPPLIED PRESSURE
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 30 of 59
CLIENT DATE: 30-04-2016
PROJECT DOC.NO. CV-E-020
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: LIC-611A SERVICE: Process Air SIZE:
AREA: AMM-3 FLANGE TYPE:
PHYSICAL CHECKS:
Overhauling and Calibrations Of
Control Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
Flowtronix (Pvt) Ltd.
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:
This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
DATE
30-04-2016
EXECUTED BY
Abid Naeem
(Instrument Technician)
1. Air leak test of actuator was found OK
2. Overhauling of Body
3. Seals replaced
4. Gland packing replaced
5. Calibrated
6. Sent for Hydrotesting
VALVE BENCH SET FAIL SAFE ACTIONSUPPLIED PRESSURE
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 31 of 59
CLIENT DATE: 30-04-2016
PROJECT DOC.NO. CV-E-021
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 11-FV-7010 SERVICE: Process Air SIZE: 8 "
AREA: AMM-3 FLANGE TYPE: RF Flanges
PHYSICAL CHECKS:
Overhauling and Calibrations Of
Control Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
Flowtronix (Pvt) Ltd.
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:
This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
1. Air leakage found in Pneumatic relay of positioner
2. Overhauling of Body
3. Overhauling of Actuator
4. Actuator O-rings replaced
5. Body gaskets replaced
6. O-rings of pneumatic relay replaced
7. Calibrated
8. Sent for Hydrotesting
DATE
30-04-2016
EXECUTED BY
Abid Naeem
(Instrument Technician)
FAIL SAFE ACTIONSUPPLIED PRESSUREVALVE BENCH SET
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 32 of 59
CLIENT DATE: 01-05-2016
PROJECT DOC.NO. CV-E-022
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 11-PV-3015B SERVICE: Process Air SIZE: 20 "
AREA: AMM-3 FLANGE TYPE: RF-125 AARH
PHYSICAL CHECKS:
Flowtronix (Pvt) Ltd.
Overhauling and Calibrations Of
Control Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:
This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
1. Handwheel was found stucking while rotating either way.
2. Overhauling of actuator
3. Servicing, oiling and cleaning of handwheel
4. Calibrated
5. Sent for Hydrotesting
DATE
01-05-2016
EXECUTED BY
Abid Naeem
(Instrument Technician)
VALVE BENCH SET FAIL SAFE ACTIONSUPPLIED PRESSURE
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 33 of 59
CLIENT DATE: 01-05-2016
PROJECT DOC.NO. CV-E-023
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 11-PV-2021A SERVICE: Process Air SIZE:
AREA: AMM-3 FLANGE TYPE:
PHYSICAL CHECKS:
Flowtronix (Pvt) Ltd.
Overhauling and Calibrations Of
Control Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:
This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
1. Actuator air leak test was found OK.
2. Positioner dismantled and cleaned
3. Calibrated
4. Sent for Hydrotesting
DATE
01-05-2016
EXECUTED BY
Abid Naeem
(Instrument Technician)
VALVE BENCH SET FAIL SAFE ACTION
Close
SUPPLIED PRESSURE
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 34 of 59
CLIENT DATE: 01-05-2016
PROJECT DOC.NO. CV-E-024
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 11-XV-2027A SERVICE: Process Air SIZE: 12 "
AREA: AMM-3 FLANGE TYPE: Flanged
PHYSICAL CHECKS:
Flowtronix (Pvt) Ltd.
Overhauling and Calibrations Of
Control Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:
This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
1. Valve ball was not smoothly opening and closing.
2. Air leak test of actuator was found OK
3. Polishing, oiling and cleanig of valve ball was done untill required smoothness was aquired.
4. Calibrated
5. Sent for Hydrotesting
DATE
01-05-2016
EXECUTED BY
Abid Naeem
(Instrument Technician)
VALVE BENCH SET FAIL SAFE ACTION
Close
SUPPLIED PRESSURE
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 35 of 59
CLIENT DATE: 01-05-2016
PROJECT DOC.NO. CV-E-025
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 11-XV-2027C SERVICE: Process Air SIZE: 12 "
AREA: AMM-3 FLANGE TYPE: Flanged
PHYSICAL CHECKS:
Flowtronix (Pvt) Ltd.
Overhauling and Calibrations Of
Control Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:
This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
1. Valve ball was not smoothly opening and closing.
2. Air leak test of actuator was found OK
3. Polishing, oiling and cleanig of valve ball was done untill required smoothness was aquired.
4. Calibrated
5. Sent for Hydrotesting
DATE
01-05-2016
EXECUTED BY
Abid Naeem
(Instrument Technician)
VALVE BENCH SET FAIL SAFE ACTION
Close
SUPPLIED PRESSURE
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 36 of 59
CLIENT DATE: 02-05-2016
PROJECT DOC.NO. CV-E-026
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 11-FV-3021B SERVICE: Process Air SIZE: 16 "
AREA: AMM-3 FLANGE TYPE: RF Flanges
PHYSICAL CHECKS:
Flowtronix (Pvt) Ltd.
Overhauling and Calibrations Of
Control Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:
This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
1. Air leak test of Actuator was found OK
2. Overhauling of actuator
3. Overhauling of body
4. Body seals replaced
5. O-rings of actuator Replaced
6. Inner and outer body seals were replaced
7. Cage seals were replaced
8. Gland packing replaced
9. Calibration
10. Sent for Hydrotesting
DATE
02-05-2016
EXECUTED BY
Abid Naeem
(Instrument Technician)
VALVE BENCH SET FAIL SAFE ACTIONSUPPLIED PRESSURE
55
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 37 of 59
CLIENT DATE: 03-05-2016
PROJECT DOC.NO. CV-E-027
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 11-LV-3026D SERVICE: Process Air SIZE: 16-/-12-/-16"
AREA: AMM-3 FLANGE TYPE: RF Flanges
PHYSICAL CHECKS:
Flowtronix (Pvt) Ltd.
Overhauling and Calibrations Of
Control Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:
This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
1. Valve was found not opennig 100%
2. Overhauling of body
3. Positioner was readjsuted
4. Body was sent for machining
5. Calibration
6. Sent for Hydrotesting
DATE
03-05-2016
EXECUTED BY
Abid Naeem
(Instrument Technician)
VALVE BENCH SET FAIL SAFE ACTIONSUPPLIED PRESSURE
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 38 of 59
CLIENT DATE: 03-05-2016
PROJECT DOC.NO. CV-E-028
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 11-FV-3022 SERVICE: Process Air SIZE: 8 "
AREA: AMM-3 FLANGE TYPE: RF Flanges
PHYSICAL CHECKS:
Flowtronix (Pvt) Ltd.
Overhauling and Calibrations Of
Control Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:
This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
1. Air Leak test of actuator was found OK
2. Overhauling of Actuator
3. Overhauling of Body
3. Actuator O-rings replaced
4. Body gaskets replaced
5. Gland packing replaced
6. Calibration.
7. Sent for Hydrotesting
DATE
03-05-2016
EXECUTED BY
Adnan Hussain
(Instrument Technician)
VALVE BENCH SET FAIL SAFE ACTIONSUPPLIED PRESSURE
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 39 of 59
CLIENT DATE: 03-05-2016
PROJECT DOC.NO. CV-E-029
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 11-LV-5010A SERVICE: Process Air SIZE: 4 "
AREA: AMM-3 FLANGE TYPE: RTJ Flanges
PHYSICAL CHECKS:
Flowtronix (Pvt) Ltd.
Overhauling and Calibrations Of
Control Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:
This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
1. Air leak test of actuator was found OK
2. Overhauling of body
3. Inner and outer body seals replaced.
4. Body gaskets replaced
5. Plug seals replaced
6. Calibrated
7. Sent for Hydrotesting
DATE
03-05-2016
EXECUTED BY
Adnan Hussain
(Instrument Technician)
VALVE BENCH SET FAIL SAFE ACTION
Close
SUPPLIED PRESSURE
50
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 40 of 59
CLIENT DATE: 03-05-2016
PROJECT DOC.NO. CV-E-030
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 10-HV-1012 SERVICE: Process Air SIZE: 6 "
AREA: AMM-3 FLANGE TYPE: RF 125 AARH
PHYSICAL CHECKS:
Flowtronix (Pvt) Ltd.
Overhauling and Calibrations Of
Control Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:
This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
1. Air leak test of actuator was found OK
2. Calibration
3. Sent for Hydrotesting
DATE
03-05-2016
EXECUTED BY
Adnan Hussain
(Instrument Technician)
VALVE BENCH SET FAIL SAFE ACTION
Close
SUPPLIED PRESSURE
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 41 of 59
CLIENT DATE: 03-05-2016
PROJECT DOC.NO. CV-E-031
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 10-FV-1003 SERVICE: Process Air SIZE: 8 "
AREA: AMM-3 FLANGE TYPE: RTJ Flanges
PHYSICAL CHECKS:
Flowtronix (Pvt) Ltd.
Overhauling and Calibrations Of
Control Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:
This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
1. Air leak test of actuator was found OK
2. Calibration
3. Sent for Hydrotesting
DATE
03-05-2016
EXECUTED BY
Adnan Hussain
(Instrument Technician)
VALVE BENCH SET FAIL SAFE ACTION
Open
SUPPLIED PRESSURE
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 42 of 59
CLIENT DATE: 04-05-2016
PROJECT DOC.NO. CV-E-032
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 11-LV-5010B SERVICE: Process Air SIZE: 4 "
AREA: AMM-3 FLANGE TYPE: RTJ Flanges
PHYSICAL CHECKS:
Flowtronix (Pvt) Ltd.
Overhauling and Calibrations Of
Control Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:
This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
1. Air leak test of actuator was found OK
2. Overhauling of body
3. Inner and outer body seals were replaced.
4. Body gaskets replaced
5. Plug seal replaced
6. Calibration
7. Sent for Hydrotesting
DATE
04-05-2016
EXECUTED BY
Adnan Hussain
(Instrument Technician)
VALVE BENCH SET FAIL SAFE ACTION
Close
SUPPLIED PRESSURE
50
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 43 of 59
CLIENT DATE: 04-05-2016
PROJECT DOC.NO. CV-E-033
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 10-HV-1008 SERVICE: Process Air SIZE: 12 "
AREA: AMM-3 FLANGE TYPE: Lenticular
PHYSICAL CHECKS:
Flowtronix (Pvt) Ltd.
Overhauling and Calibrations Of
Control Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:
This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
1. Air leak test of actuator was found OK
2. Vlave body stud bolts were jammed with solidified urea
3. Seat, plug and cage were sent for machining.
4. Calibration
5. Sent for Hydrotesting
DATE
04-05-2016
EXECUTED BY
Adnan Hussain
(Instrument Technician)
VALVE BENCH SET FAIL SAFE ACTION
Close
SUPPLIED PRESSURE
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 44 of 59
CLIENT DATE: 04-05-2016
PROJECT DOC.NO. CV-E-034
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 11-TV-3004 SERVICE: Process Air SIZE:
AREA: AMM-3 FLANGE TYPE:
PHYSICAL CHECKS:
Flowtronix (Pvt) Ltd.
Overhauling and Calibrations Of
Control Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:
This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
1. Air leak test of actuator was found OK
2. Overhauling
3. Valve bench set was found
4. Calibration
5. Sent for Hydrotesting
DATE
04-05-2016
EXECUTED BY
Adnan Hussain
(Instrument Technician)
VALVE BENCH SET FAIL SAFE ACTION
Close
SUPPLIED PRESSURE
55
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 45 of 59
CLIENT DATE: 05-05-2016
PROJECT DOC.NO. CV-E-035
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 11-HV-2071A SERVICE: Process Air SIZE: 8 "
AREA: AMM-3 FLANGE TYPE: FLG.RF(F)
PHYSICAL CHECKS:
Flowtronix (Pvt) Ltd.
Overhauling and Calibrations Of
Control Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:
This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
1. Air leak test of actuator was found OK
2. Overhauling
3. Valve bench set was found
4. Calibration
5. Sent for Hydrotesting
DATE
05-05-2016
EXECUTED BY
Adnan Hussain
(Instrument Technician)
VALVE BENCH SET FAIL SAFE ACTIONSUPPLIED PRESSURE
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 46 of 59
CLIENT DATE: 05-05-2016
PROJECT DOC.NO. CV-E-036
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 10-PV-1048 SERVICE: Process Air SIZE: 10 "
AREA: AMM-3 FLANGE TYPE:
PHYSICAL CHECKS:
Flowtronix (Pvt) Ltd.
Overhauling and Calibrations Of
Control Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:
This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
1. Cleaning, Oiling and Polishing
2. Air Leak test of actuator was found OK
3. Seat and plug were sent for machining
4. All gaskets replaced
5. Diapharm was found torned
6. Diapharm replaced
7. Calibrated
8. Sent for Hydrotesting
DATE
05-05-2016
EXECUTED BY
Adnan Hussain
(Instrument Technician)
VALVE BENCH SET FAIL SAFE ACTIONSUPPLIED PRESSURE
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 47 of 59
CLIENT DATE: 05-05-2016
PROJECT DOC.NO. CV-E-037
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 11-FV-2056 SERVICE: Process Air SIZE: 10 "
AREA: AMM-3 FLANGE TYPE: RTJ Flanges
PHYSICAL CHECKS:
Flowtronix (Pvt) Ltd.
Overhauling and Calibrations Of
Control Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:
This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
1. Air leak of acutator was tested and found OK
2. Calibration was tested and found OK
3. Cleaning, oiling and polishing was done
4. Sent for Hydrotesting
DATE
05-05-2016
EXECUTED BY
Adnan Hussain
(Instrument Technician)
VALVE BENCH SET FAIL SAFE ACTIONSUPPLIED PRESSURE
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 48 of 59
CLIENT DATE: 05-05-2016
PROJECT DOC.NO. CV-E-038
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 10-HV-1009 SERVICE: Process Air SIZE: 8 "
AREA: AMM-3 FLANGE TYPE: Lenticular
PHYSICAL CHECKS:
Flowtronix (Pvt) Ltd.
Overhauling and Calibrations Of
Control Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:
This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
1. Actuator was found Leaked.
2. Dismantled single diapharm of actuator (outter most)
3. Body Overhauled
4. Calibrated
5. Sent for Hydrotesting
DATE
05-05-2016
EXECUTED BY
Adnan Hussain
(Instrument Technician)
VALVE BENCH SET FAIL SAFE ACTION
Close
SUPPLIED PRESSURE
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 49 of 59
CLIENT DATE: 05-05-2016
PROJECT DOC.NO. CV-E-039
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 11-LV-3011B SERVICE: Process Air SIZE: 18 "
AREA: AMM-3 FLANGE TYPE: RF Flanges
PHYSICAL CHECKS:
Flowtronix (Pvt) Ltd.
Overhauling and Calibrations Of
Control Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:
This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
1. Air leak test of actuator was found OK
2. Overhauling of body
3. Plug, seat and cage were sent for machining
4. All three gaskets replaced
5. Calibrated
6. Sent for Hydrotesting
DATE
05-05-2016
EXECUTED BY
Mohammad Mubasher
(Instrument Technician)
VALVE BENCH SET FAIL SAFE ACTION
Open
SUPPLIED PRESSURE
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 50 of 59
CLIENT DATE: 05-05-2016
PROJECT DOC.NO. CV-E-040
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 11-LV-3011A SERVICE: Process Air SIZE: 18 "
AREA: AMM-3 FLANGE TYPE: RF Flanges
PHYSICAL CHECKS:
Flowtronix (Pvt) Ltd.
Overhauling and Calibrations Of
Control Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:
This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
1. Air leak test of actuator was found OK
2. Overhauling of body
3. Valve plug, cage and seat were sent for machining
4. Cleaning, oiling and polishing were done to smoothen up the valve
5. Calibrated
6. Sent for Hydrotesting
DATE
05-05-2016
EXECUTED BY
Mohammad Mubasher
(Instrument Technician)
VALVE BENCH SET FAIL SAFE ACTION
Open
SUPPLIED PRESSURE
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 51 of 59
CLIENT DATE: 06-05-2016
PROJECT DOC.NO. CV-E-041
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 19-PV-9001A SERVICE: Process Air SIZE: 4 "
AREA: AMM-3 FLANGE TYPE: RF Flanges
PHYSICAL CHECKS:
Flowtronix (Pvt) Ltd.
Overhauling and Calibrations Of
Control Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:
This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
1. Cleaning, Oiling and Polishing
2. Air Leak test of Actuator was found OK
3. Diapharm was found Ok
4. Overhauling of body and actuator
5. O-rings replaced
6. Seat, plug sent for machining
7. All gaskets replaced
8. Calibrated
9. Sent For Hydrotesting
DATE
06-05-2016
EXECUTED BY
Mohammad Mubasher
(Instrument Technician)
VALVE BENCH SET FAIL SAFE ACTIONSUPPLIED PRESSURE
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 52 of 59
CLIENT DATE: 06-05-2016
PROJECT DOC.NO. CV-E-042
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 19-FV-9002 SERVICE: Process Air SIZE: 8 "
AREA: AMM-3 FLANGE TYPE: RF Flanges
PHYSICAL CHECKS:
Flowtronix (Pvt) Ltd.
Overhauling and Calibrations Of
Control Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:
This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
1. Air leak test of actuator was found OK
2. Overhauling of Body
3. Overhauling of Actuator
4. Seat and plug were sent for machining
5. Body gaskets replaced
6. Calibrated
9. Sent For Hydrotesting
DATE
06-05-2016
EXECUTED BY
Mohammad Mubasher
(Instrument Technician)
VALVE BENCH SET FAIL SAFE ACTION
Close
SUPPLIED PRESSURE
40
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 53 of 59
CLIENT DATE: 08-05-2016
PROJECT DOC.NO. CV-E-043
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 11-FV-2028 SERVICE: Process Air SIZE: 4 "
AREA: AMM-3 FLANGE TYPE: RF Flanges
PHYSICAL CHECKS:
Flowtronix (Pvt) Ltd.
Overhauling and Calibrations Of
Control Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:
This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
1. Cleaning, Oiling and Polishing
2. Air Leak test ok
3. Overhauling of Body
4. Overhauling of Actuator
5. Diaphram was found OK
6. O-Rings Replaced
7. Plug and seat sent for machining
8. Gland Packing Replaced
9. Calibrated
10. Sent For Hydrotesting
DATE
08-05-2016
EXECUTED BY
Mohammad Mubasher
(Instrument Technician)
VALVE BENCH SET FAIL SAFE ACTIONSUPPLIED PRESSURE
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 54 of 59
CLIENT DATE: 08-05-2016
PROJECT DOC.NO. CV-E-044
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 11-LV-2055 SERVICE: Process Air SIZE: 4-/-3-/-4
AREA: AMM-3 FLANGE TYPE: RTJ Flanges
PHYSICAL CHECKS:
Flowtronix (Pvt) Ltd.
Overhauling and Calibrations Of
Control Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:
This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
1. Cleaning, Oiling and Polishing
2. Air Leak test ok
3. Overhauling of Body
4. Overhauling of Actuator
5. Seat Replaced
6. Plug seal rings Replaced
7. Plug and Stem sent for machining
8. Gland Packing Replaced
9. Calibrated
10. Sent For Hydrotesting
DATE
08-05-2016
EXECUTED BY
Mohammad Mubasher
(Instrument Technician)
VALVE BENCH SET FAIL SAFE ACTION
Close
SUPPLIED PRESSURE
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 55 of 59
CLIENT DATE: 09-05-2016
PROJECT DOC.NO. CV-E-045
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 11-TV-5482 SERVICE: Process Air SIZE:
AREA: AMM-3 FLANGE TYPE:
PHYSICAL CHECKS:
Flowtronix (Pvt) Ltd.
Overhauling and Calibrations Of
Control Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:
This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
1. Cleaning, Oiling and Polishing
2. Air Leak test ok
3. Actuator Diapharm replaced
4. Plug seal O-rings replaced
9. Calibrated
10. Sent For Hydrotesting
DATE
09-05-2016
EXECUTED BY
Mohammad Mubasher
(Instrument Technician)
VALVE BENCH SET FAIL SAFE ACTION
Close
SUPPLIED PRESSURE
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 56 of 59
CLIENT DATE: 10-05-2016
PROJECT DOC.NO. CV-E-046
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 11-TV-5476 SERVICE: Process Air SIZE:
AREA: AMM-3 FLANGE TYPE:
PHYSICAL CHECKS:
Flowtronix (Pvt) Ltd.
Overhauling and Calibrations Of
Control Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:
This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
1. Cleaning, Oiling and Polishing
2. Air Leak test ok
3. Calibrated
4. Sent For Hydrotesting
DATE
10-05-2016
EXECUTED BY
Mohammad Mubasher
(Instrument Technician)
VALVE BENCH SET FAIL SAFE ACTIONSUPPLIED PRESSURE
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 57 of 59
CLIENT DATE: 10-05-2016
PROJECT DOC.NO. CV-E-047
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 11-HV-1032B SERVICE: Process Air SIZE: 1 "
AREA: AMM-3 FLANGE TYPE: Flanged
PHYSICAL CHECKS:
Flowtronix (Pvt) Ltd.
Overhauling and Calibrations Of
Control Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:
This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
1. Cleaning, Oiling and Polishing
2. Air Leak test ok
3. Calibrated
4. Sent For Hydrotesting
DATE
10-05-2016
EXECUTED BY
Mohammad Mubasher
(Instrument Technician)
VALVE BENCH SET FAIL SAFE ACTIONSUPPLIED PRESSURE
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 58 of 59
Overhauling and Calibrations Of
Control Valves
7. PICTURES (Work In Progress):
Page 59 of 59

Contenu connexe

Tendances

API 622, API 624 and API 641 for Fugitive Emissions
API 622, API 624 and API 641 for Fugitive EmissionsAPI 622, API 624 and API 641 for Fugitive Emissions
API 622, API 624 and API 641 for Fugitive EmissionsPGE India - PILOT Gaskets
 
Rfi Flow Meter Product Guide
Rfi Flow Meter Product GuideRfi Flow Meter Product Guide
Rfi Flow Meter Product Guidebriansternberg
 
Brochure-C-small-file
Brochure-C-small-fileBrochure-C-small-file
Brochure-C-small-fileshadrak rufus
 
Airborne Repairs Brochure - Oil & Gas.
Airborne Repairs Brochure - Oil & Gas.Airborne Repairs Brochure - Oil & Gas.
Airborne Repairs Brochure - Oil & Gas.tyson gins
 
Siddharth Engineers, Pune, Valve & Engineering Components
Siddharth Engineers, Pune, Valve & Engineering ComponentsSiddharth Engineers, Pune, Valve & Engineering Components
Siddharth Engineers, Pune, Valve & Engineering ComponentsIndiaMART InterMESH Limited
 
AUG2012 SPICE PARK(ALL LIST) by SPICE PARK
AUG2012 SPICE PARK(ALL LIST) by SPICE PARKAUG2012 SPICE PARK(ALL LIST) by SPICE PARK
AUG2012 SPICE PARK(ALL LIST) by SPICE PARKTsuyoshi Horigome
 
engine specification
engine specification engine specification
engine specification Arul Kumar
 
52240 plumbingfixtures
52240 plumbingfixtures52240 plumbingfixtures
52240 plumbingfixturestagalamut143
 
13 lv switchboard inspection guide
13   lv switchboard inspection guide13   lv switchboard inspection guide
13 lv switchboard inspection guideSơn Trà
 
Well integrity in drilling and well operations
Well integrity in drilling and well operationsWell integrity in drilling and well operations
Well integrity in drilling and well operationsJuan Manuel Fuertes
 
( Itp ag pipe) rapid p006 a scs qac itp 3200 0007
( Itp ag pipe) rapid p006 a scs qac itp 3200 0007( Itp ag pipe) rapid p006 a scs qac itp 3200 0007
( Itp ag pipe) rapid p006 a scs qac itp 3200 0007Tonni Bruce
 
ALL SPICE Model of APR2014 in SPICE PARK
ALL SPICE Model of APR2014 in SPICE PARKALL SPICE Model of APR2014 in SPICE PARK
ALL SPICE Model of APR2014 in SPICE PARKTsuyoshi Horigome
 
Pacific Brochure Products
Pacific Brochure ProductsPacific Brochure Products
Pacific Brochure ProductsJason Salsbury
 

Tendances (19)

API 622, API 624 and API 641 for Fugitive Emissions
API 622, API 624 and API 641 for Fugitive EmissionsAPI 622, API 624 and API 641 for Fugitive Emissions
API 622, API 624 and API 641 for Fugitive Emissions
 
00 saip-07
00 saip-0700 saip-07
00 saip-07
 
Rfi Flow Meter Product Guide
Rfi Flow Meter Product GuideRfi Flow Meter Product Guide
Rfi Flow Meter Product Guide
 
Pid area 291
Pid area 291Pid area 291
Pid area 291
 
Brochure-C-small-file
Brochure-C-small-fileBrochure-C-small-file
Brochure-C-small-file
 
Airborne Repairs Brochure - Oil & Gas.
Airborne Repairs Brochure - Oil & Gas.Airborne Repairs Brochure - Oil & Gas.
Airborne Repairs Brochure - Oil & Gas.
 
Norsok d-010u4 2013.en.02
Norsok d-010u4 2013.en.02Norsok d-010u4 2013.en.02
Norsok d-010u4 2013.en.02
 
Siddharth Engineers, Pune, Valve & Engineering Components
Siddharth Engineers, Pune, Valve & Engineering ComponentsSiddharth Engineers, Pune, Valve & Engineering Components
Siddharth Engineers, Pune, Valve & Engineering Components
 
AUG2012 SPICE PARK(ALL LIST) by SPICE PARK
AUG2012 SPICE PARK(ALL LIST) by SPICE PARKAUG2012 SPICE PARK(ALL LIST) by SPICE PARK
AUG2012 SPICE PARK(ALL LIST) by SPICE PARK
 
engine specification
engine specification engine specification
engine specification
 
52240 plumbingfixtures
52240 plumbingfixtures52240 plumbingfixtures
52240 plumbingfixtures
 
13 lv switchboard inspection guide
13   lv switchboard inspection guide13   lv switchboard inspection guide
13 lv switchboard inspection guide
 
Report
ReportReport
Report
 
Ha
HaHa
Ha
 
Well integrity in drilling and well operations
Well integrity in drilling and well operationsWell integrity in drilling and well operations
Well integrity in drilling and well operations
 
1 80 fineshed
1 80 fineshed1 80 fineshed
1 80 fineshed
 
( Itp ag pipe) rapid p006 a scs qac itp 3200 0007
( Itp ag pipe) rapid p006 a scs qac itp 3200 0007( Itp ag pipe) rapid p006 a scs qac itp 3200 0007
( Itp ag pipe) rapid p006 a scs qac itp 3200 0007
 
ALL SPICE Model of APR2014 in SPICE PARK
ALL SPICE Model of APR2014 in SPICE PARKALL SPICE Model of APR2014 in SPICE PARK
ALL SPICE Model of APR2014 in SPICE PARK
 
Pacific Brochure Products
Pacific Brochure ProductsPacific Brochure Products
Pacific Brochure Products
 

En vedette

Quanto vale um apartamento de t1 ou t2 na freguesia do parque das nações vf
Quanto vale um apartamento de t1 ou t2 na freguesia do parque das nações vfQuanto vale um apartamento de t1 ou t2 na freguesia do parque das nações vf
Quanto vale um apartamento de t1 ou t2 na freguesia do parque das nações vfJoão Fonseca
 
溫哥華春櫻
溫哥華春櫻溫哥華春櫻
溫哥華春櫻hchsu
 
Election_diapo_pistolet
Election_diapo_pistoletElection_diapo_pistolet
Election_diapo_pistoletfrgerra
 
CV_Peter_Omondi_Matolo
CV_Peter_Omondi_MatoloCV_Peter_Omondi_Matolo
CV_Peter_Omondi_MatoloPeter Matolo
 
"The Next Big Thing" - Best's Review (AM Best), September 2016
"The Next Big Thing" - Best's Review (AM Best), September 2016"The Next Big Thing" - Best's Review (AM Best), September 2016
"The Next Big Thing" - Best's Review (AM Best), September 2016Gates Ouimette
 
Esercizio n°4
Esercizio n°4Esercizio n°4
Esercizio n°4sommazzi
 
國民歌后—鳳飛飛
國民歌后—鳳飛飛國民歌后—鳳飛飛
國民歌后—鳳飛飛hchsu
 
Reactful Introduction
Reactful Introduction Reactful Introduction
Reactful Introduction Reactful
 
Online Training in IBM DB2 LUW/UDB DBA in Hyderabad
Online Training in IBM DB2 LUW/UDB DBA in HyderabadOnline Training in IBM DB2 LUW/UDB DBA in Hyderabad
Online Training in IBM DB2 LUW/UDB DBA in HyderabadRavikumar Nandigam
 
Time study
Time studyTime study
Time studybogem2
 
Glee_version3
Glee_version3Glee_version3
Glee_version3frgerra
 
Communication de qualité
Communication de qualitéCommunication de qualité
Communication de qualitéveroniquehello
 

En vedette (20)

Glee
GleeGlee
Glee
 
Fiche de révision
Fiche de révisionFiche de révision
Fiche de révision
 
Evaluation presentation
Evaluation presentationEvaluation presentation
Evaluation presentation
 
Quanto vale um apartamento de t1 ou t2 na freguesia do parque das nações vf
Quanto vale um apartamento de t1 ou t2 na freguesia do parque das nações vfQuanto vale um apartamento de t1 ou t2 na freguesia do parque das nações vf
Quanto vale um apartamento de t1 ou t2 na freguesia do parque das nações vf
 
My CV
My CVMy CV
My CV
 
溫哥華春櫻
溫哥華春櫻溫哥華春櫻
溫哥華春櫻
 
Logo A
Logo ALogo A
Logo A
 
Election_diapo_pistolet
Election_diapo_pistoletElection_diapo_pistolet
Election_diapo_pistolet
 
CV_Peter_Omondi_Matolo
CV_Peter_Omondi_MatoloCV_Peter_Omondi_Matolo
CV_Peter_Omondi_Matolo
 
Imparidades
ImparidadesImparidades
Imparidades
 
"The Next Big Thing" - Best's Review (AM Best), September 2016
"The Next Big Thing" - Best's Review (AM Best), September 2016"The Next Big Thing" - Best's Review (AM Best), September 2016
"The Next Big Thing" - Best's Review (AM Best), September 2016
 
Esercizio n°4
Esercizio n°4Esercizio n°4
Esercizio n°4
 
Blogger post
Blogger postBlogger post
Blogger post
 
Act. 1 unidad 2 yannine adriana martínez valle lao
Act. 1 unidad 2 yannine adriana martínez valle laoAct. 1 unidad 2 yannine adriana martínez valle lao
Act. 1 unidad 2 yannine adriana martínez valle lao
 
國民歌后—鳳飛飛
國民歌后—鳳飛飛國民歌后—鳳飛飛
國民歌后—鳳飛飛
 
Reactful Introduction
Reactful Introduction Reactful Introduction
Reactful Introduction
 
Online Training in IBM DB2 LUW/UDB DBA in Hyderabad
Online Training in IBM DB2 LUW/UDB DBA in HyderabadOnline Training in IBM DB2 LUW/UDB DBA in Hyderabad
Online Training in IBM DB2 LUW/UDB DBA in Hyderabad
 
Time study
Time studyTime study
Time study
 
Glee_version3
Glee_version3Glee_version3
Glee_version3
 
Communication de qualité
Communication de qualitéCommunication de qualité
Communication de qualité
 

Similaire à Review 004

Mechanical resume (1)
Mechanical resume (1)Mechanical resume (1)
Mechanical resume (1)jesu lambert
 
Butterfly Valve Technique Catalogue
Butterfly Valve Technique CatalogueButterfly Valve Technique Catalogue
Butterfly Valve Technique CatalogueZhao Shannon
 
John deere 9650 self-p pelled combine
John deere 9650 self-p pelled combineJohn deere 9650 self-p pelled combine
John deere 9650 self-p pelled combinePartCatalogs Net
 
Hyundai r75 7 mini excavator service repair manual
Hyundai r75 7 mini excavator service repair manualHyundai r75 7 mini excavator service repair manual
Hyundai r75 7 mini excavator service repair manualfhsejkdkmem
 
Hyundai r75 7 mini excavator service repair manual
Hyundai r75 7 mini excavator service repair manualHyundai r75 7 mini excavator service repair manual
Hyundai r75 7 mini excavator service repair manualidkkdmmdd
 
Hyundai r75 7 mini excavator service repair manual
Hyundai r75 7 mini excavator service repair manualHyundai r75 7 mini excavator service repair manual
Hyundai r75 7 mini excavator service repair manualfhsjekkdkem
 
Hyundai r75 7 mini excavator service repair manual
Hyundai r75 7 mini excavator service repair manualHyundai r75 7 mini excavator service repair manual
Hyundai r75 7 mini excavator service repair manualsoeldksejdksem
 
Liebherr l586 2 plus2 wheel loader service repair manual
Liebherr l586 2 plus2 wheel loader service repair manualLiebherr l586 2 plus2 wheel loader service repair manual
Liebherr l586 2 plus2 wheel loader service repair manualfskkkdjskemd
 
INDUSTRIAL TRAINING REPORT BY ShRiDhAR KaDaM
INDUSTRIAL TRAINING REPORT BY ShRiDhAR KaDaMINDUSTRIAL TRAINING REPORT BY ShRiDhAR KaDaM
INDUSTRIAL TRAINING REPORT BY ShRiDhAR KaDaMshridharthecyberdude
 
Terex telelift 2506 gladiator agrilift telescopic handler service repair manual
Terex telelift 2506 gladiator agrilift telescopic handler service repair manualTerex telelift 2506 gladiator agrilift telescopic handler service repair manual
Terex telelift 2506 gladiator agrilift telescopic handler service repair manualjsemm fvdcf
 
Terex telelift 3007 gladiator agrilift telescopic handler service repair manual
Terex telelift 3007 gladiator agrilift telescopic handler service repair manualTerex telelift 3007 gladiator agrilift telescopic handler service repair manual
Terex telelift 3007 gladiator agrilift telescopic handler service repair manualfkjsekksmem
 
Terex telelift gladiator agrilift 359 telescopic handler service repair manual
Terex telelift gladiator agrilift 359 telescopic handler service repair manualTerex telelift gladiator agrilift 359 telescopic handler service repair manual
Terex telelift gladiator agrilift 359 telescopic handler service repair manualfjjskkefksme
 
TEREX TELELIFT 2506 GLADIATOR AGRILIFT TELESCOPIC HANDLER Service Repair Manual
TEREX TELELIFT 2506 GLADIATOR AGRILIFT TELESCOPIC HANDLER Service Repair ManualTEREX TELELIFT 2506 GLADIATOR AGRILIFT TELESCOPIC HANDLER Service Repair Manual
TEREX TELELIFT 2506 GLADIATOR AGRILIFT TELESCOPIC HANDLER Service Repair Manualjksebmdmn
 
TEREX TELELIFT GLADIATOR AGRILIFT 359 TELESCOPIC HANDLER Service Repair Manual
TEREX TELELIFT GLADIATOR AGRILIFT 359 TELESCOPIC HANDLER Service Repair ManualTEREX TELELIFT GLADIATOR AGRILIFT 359 TELESCOPIC HANDLER Service Repair Manual
TEREX TELELIFT GLADIATOR AGRILIFT 359 TELESCOPIC HANDLER Service Repair Manualjnfmmsd ejdkmsm
 
Terex telelift 2506 gladiator agrilift telescopic handler service repair manual
Terex telelift 2506 gladiator agrilift telescopic handler service repair manualTerex telelift 2506 gladiator agrilift telescopic handler service repair manual
Terex telelift 2506 gladiator agrilift telescopic handler service repair manualfujskekfmsme
 
Terex telelift gladiator agrilift 357 telescopic handler service repair manual
Terex telelift gladiator agrilift 357 telescopic handler service repair manualTerex telelift gladiator agrilift 357 telescopic handler service repair manual
Terex telelift gladiator agrilift 357 telescopic handler service repair manualfjskekfseik
 
Terex telelift 2506 gladiator agrilift telescopic handler service repair manual
Terex telelift 2506 gladiator agrilift telescopic handler service repair manualTerex telelift 2506 gladiator agrilift telescopic handler service repair manual
Terex telelift 2506 gladiator agrilift telescopic handler service repair manualfusekksejfkem
 

Similaire à Review 004 (18)

Mechanical resume (1)
Mechanical resume (1)Mechanical resume (1)
Mechanical resume (1)
 
Butterfly Valve Technique Catalogue
Butterfly Valve Technique CatalogueButterfly Valve Technique Catalogue
Butterfly Valve Technique Catalogue
 
John deere 9650 self-p pelled combine
John deere 9650 self-p pelled combineJohn deere 9650 self-p pelled combine
John deere 9650 self-p pelled combine
 
TPM ppt.pptx
TPM ppt.pptxTPM ppt.pptx
TPM ppt.pptx
 
Hyundai r75 7 mini excavator service repair manual
Hyundai r75 7 mini excavator service repair manualHyundai r75 7 mini excavator service repair manual
Hyundai r75 7 mini excavator service repair manual
 
Hyundai r75 7 mini excavator service repair manual
Hyundai r75 7 mini excavator service repair manualHyundai r75 7 mini excavator service repair manual
Hyundai r75 7 mini excavator service repair manual
 
Hyundai r75 7 mini excavator service repair manual
Hyundai r75 7 mini excavator service repair manualHyundai r75 7 mini excavator service repair manual
Hyundai r75 7 mini excavator service repair manual
 
Hyundai r75 7 mini excavator service repair manual
Hyundai r75 7 mini excavator service repair manualHyundai r75 7 mini excavator service repair manual
Hyundai r75 7 mini excavator service repair manual
 
Liebherr l586 2 plus2 wheel loader service repair manual
Liebherr l586 2 plus2 wheel loader service repair manualLiebherr l586 2 plus2 wheel loader service repair manual
Liebherr l586 2 plus2 wheel loader service repair manual
 
INDUSTRIAL TRAINING REPORT BY ShRiDhAR KaDaM
INDUSTRIAL TRAINING REPORT BY ShRiDhAR KaDaMINDUSTRIAL TRAINING REPORT BY ShRiDhAR KaDaM
INDUSTRIAL TRAINING REPORT BY ShRiDhAR KaDaM
 
Terex telelift 2506 gladiator agrilift telescopic handler service repair manual
Terex telelift 2506 gladiator agrilift telescopic handler service repair manualTerex telelift 2506 gladiator agrilift telescopic handler service repair manual
Terex telelift 2506 gladiator agrilift telescopic handler service repair manual
 
Terex telelift 3007 gladiator agrilift telescopic handler service repair manual
Terex telelift 3007 gladiator agrilift telescopic handler service repair manualTerex telelift 3007 gladiator agrilift telescopic handler service repair manual
Terex telelift 3007 gladiator agrilift telescopic handler service repair manual
 
Terex telelift gladiator agrilift 359 telescopic handler service repair manual
Terex telelift gladiator agrilift 359 telescopic handler service repair manualTerex telelift gladiator agrilift 359 telescopic handler service repair manual
Terex telelift gladiator agrilift 359 telescopic handler service repair manual
 
TEREX TELELIFT 2506 GLADIATOR AGRILIFT TELESCOPIC HANDLER Service Repair Manual
TEREX TELELIFT 2506 GLADIATOR AGRILIFT TELESCOPIC HANDLER Service Repair ManualTEREX TELELIFT 2506 GLADIATOR AGRILIFT TELESCOPIC HANDLER Service Repair Manual
TEREX TELELIFT 2506 GLADIATOR AGRILIFT TELESCOPIC HANDLER Service Repair Manual
 
TEREX TELELIFT GLADIATOR AGRILIFT 359 TELESCOPIC HANDLER Service Repair Manual
TEREX TELELIFT GLADIATOR AGRILIFT 359 TELESCOPIC HANDLER Service Repair ManualTEREX TELELIFT GLADIATOR AGRILIFT 359 TELESCOPIC HANDLER Service Repair Manual
TEREX TELELIFT GLADIATOR AGRILIFT 359 TELESCOPIC HANDLER Service Repair Manual
 
Terex telelift 2506 gladiator agrilift telescopic handler service repair manual
Terex telelift 2506 gladiator agrilift telescopic handler service repair manualTerex telelift 2506 gladiator agrilift telescopic handler service repair manual
Terex telelift 2506 gladiator agrilift telescopic handler service repair manual
 
Terex telelift gladiator agrilift 357 telescopic handler service repair manual
Terex telelift gladiator agrilift 357 telescopic handler service repair manualTerex telelift gladiator agrilift 357 telescopic handler service repair manual
Terex telelift gladiator agrilift 357 telescopic handler service repair manual
 
Terex telelift 2506 gladiator agrilift telescopic handler service repair manual
Terex telelift 2506 gladiator agrilift telescopic handler service repair manualTerex telelift 2506 gladiator agrilift telescopic handler service repair manual
Terex telelift 2506 gladiator agrilift telescopic handler service repair manual
 

Review 004

  • 1. TECHNICAL REPORT Project: Overhauling And Calibration Of Control Valves Engro Fertilizers Plant-II Shutdown, Dharki (April 27 – May 10, 2016) Client: Submitted to: Mr. Asad Naeem (Instrument Engineer) Work Order Reference: 6636 Purchase Order Reference: 5000001993 Flowtronix Head Office: 101/s, Quaid-e-Azam Industrial Estate, Kot Lakhpat, Lahore 54760 – Pakistan. UAN: 111-355-355 (111-EKL-EKL) Tel: 92-42-35215611 Fax: +92-42-35151104 E-mail: flowtronix@ddfcgroup.com
  • 2. Manpower Detail Organogram Tools & Equipment Used Page 3 List of control valves Daily Progress Log Valve Record Sheets 6.1 11-XV-2011A 6.2 11-FV-2048 6.3 11-HV-2011 6.4 11-XV-2011B 6.5 11-FV-2030 6.6 11-FV-2011 6.7 11-FV-1801 6.8 11-FV-2033 6.9 11-PV-2046 Page 19 Page 20 Page 21 Overhauling and Calibrations Of Control Valves 6 Table Of Contents 1 2 Page 12 Page 1 Page 2 Page 4 Page 5 4 5 3 Page 12 Page 13 Page 15 Page 16 Page 18 Page 17 Page 14 6.9 11-PV-2046 6.10 11-PV-2027 6.11 10-LV-1018 6.12 11-HV-3022 6.13 11-FV-2026 6.14 11-FV-2076 6.15 11-XV-2027 6.16 11-PV-7498 6.17 11-PV-2046B 6.18 11-PV-7109 6.19 PIC-611V 6.20 LIC-611A 6.21 11-FV-7010 6.22 11-PV-3015B 6.23 11-PV-2021 6.24 11-XV-2027A 6.25 11-XV-2027C 6.26 11-FV-3021B 6.27 11-FV-3026D 6.28 11-FV-3022 6.29 11-LV-5010A 6.30 11-HV-1012 6.31 10-LV-1003 6.32 11-LV-5010B 6.33 10-HV-1008 6.34 11-TV-3004 Page 20 Page 21 Page 22 Page 23 Page 24 Page 25 Page 26 Page 27 Page 28 Page 29 Page 30 Page 31 Page 32 Page 33 Page 34 Page 35 Page 36 Page 37 Page 38 Page 39 Page 40 Page 41 Page 42 Page 43 Page 45 Page 44 Page 46
  • 3. Overhauling and Calibrations Of Control Valves Table Of Contents 6.37 11-FV-2056 6.38 10-HV-1009 6.39 11-LV-3011B 6.40 11-LV-3011A 6.41 19-FV-9001A 6.42 19-FV-9002 6.43 11-FV-2028 6.44 11-LV-2055 6.45 11-TV-5482 6.46 11-TV-5476 6.47 11-HV-1032B Pictures (Work In Progress) Page 53 7 Page 59 Page 48 Page 58 Page 54 Page 55 Page 56 Page 57 Page 49 Page 50 Page 51 Page 52
  • 4. 1. MANPOWER DETAIL: Sr. No. Father's Name Trade Shift 1 Amer Siddiq Project Incharge Day/Night 2 Mohammad Jamil Supevervisor Day 3 Haq Nawaz Supevervisor Night 4 Sher Muhammad Instr. Fitter Night 5 Abdul Rasheed Instr. Fitter Night 6 M Yameen Instr. Fitter Day 7 M Sadiq Instr. Fitter Day 8 M Ramzan Instr. Fitter Day 9 Basheer Ahmad Instr. Fitter Day 10 M Aslam Instr. Fitter Day 11 Abdul Hameed Instr. Fitter Night Sagheer ahmad Sajid M Ilyas M Tariq Name Ramiz Siddiq Sajid Tanveer Sajjad ahmad Overhauling and Calibrations Of Control Valves Abdul Rehman Saeed Ahmad Jalal Uddin M Akbar M Shafiq Aamir Usman M Khalid 11 Abdul Hameed Instr. Fitter Night 12 Ali Hassan Instr. Fitter Night 13 Riasat Ali Instr Tech Day 14 Maqbool Ahmad Instr Tech Day 15 Ghulam Akbar Instr Tech Day 16 Amman Ullah Instr Tech Day 17 Mohammad Bashir Instr Tech Night 18 Ghulam Hussain Instr Tech Night 19 Mushtaq Ahmad Instr Tech Night 20 Helper Night 21 Abdul Sattar Helper Day 22 Abdul Wahid Helper Day 23 Iftikhar Husain Helper Day 24 M Yousaf Helper Day 25 Mohammad Nazir Helper Night 26 M Alamgir Helper Day 27 Mushtaq Ahmad Helper Night Mohammad Ali M Umer Mohammad Muddasar Hafiz Adnan Hussain Mohmmmad Mubasher Amjad Mubeen Anees Sattar M Shoaib M Zubair M Adil Mohammad Umair Riasat Mohammad Abid Naeem Abul Sattar Irfan Ullah Iftikhar Ahmad M Shafiq Aamir Usman Page 1 of 59
  • 5. 2. ORGANOGRAM: Day Shift Night Shift Team 1 Team 2 Team 3 Ramiz Siddiq (Project Incharge) Mohamad Tariq (Instr. Fitter) Saeed Ahmad (Instr. Fitter) Mohammad Ilyas (Instr. Fitter) M Shoaib (Helper) Umari Riasat (Instr. Technician) M Adil (Helper) Overhauling and Calibrations Of Control Valves Sajid Tanveer (Instrument Supervisor) Abdul Sattar (Instr. Technician) Abid Naeem (Instr. Technician) Irfan Ullah (Instr. Technician) Abdul Rehman (Instr. Fitter) Jallal Uddin (Instr. Fitter) Anees Sattar (Helper) Team 1 Team 2 Team 3 Mohammad Shafiq (Instr. Fitter) M Shoaib (Helper) M Adil (Helper) Hafiz Adnan (Instr. Technician) Sajjad Ahmad (Instrument Supervisor) Amjad Mubeen (Helper) Mohamamd Ali (Helper) Sagheer Ahmad (Instr. Fitter) M Umer (Helper) Hafiz Iftikhar (Instr. Technician) M. Muddassar (Helper) Aamir Usman (Instr. Fitter) Mohammad Khalid (Instr. Fitter) Anees Sattar (Helper) M. Mubasher (Instr. Technician) Page 2 of 59
  • 6. 3. TOOLS USED: Screw Drivers (Star Set) Allen Key Set (Star, mm, inch) Side Cutters Monkey Pliers Combination Pliers Nose Pliers Open End & Ring Spanner Sets Needle File Set Files (Round, Half Round and Flat) Stacking Spanner Set (26-50mm) Hammers (Rubber, Wooden, Brass & MS) Overhauling and Calibrations Of Control Valves Sr. No. Tools & Equipment 1 2 3 4 5 6 7 8 9 10 11 12 A. Used For Overhauling Hammers (Rubber, Wooden, Brass & MS) Lifting Belts & D-Shackles Vernier Caliper Digital Multimeter HART Communicator mAmp Source DC Source Pressure Guage Air Regulator 5 6 1 2 3 4 B. Used For Calibration 11 12 13 Page 3 of 59
  • 7. 4. LIST OF CONTROL VALVES: Total Quantity : 47 Nos. 6 12 - 20 8 - - 6 4 8 16 16 12 Size (inch) 8 12 - 12 4 8 11-FV-7010 LIC-611A PIC-611V 11-PV-2046B 18 19 11-LV-5010A 11-FV-3022 11-LV-3026D 11-FV-3021B 11-XV-2027C 11-XV-2027A 10-HV-1012 10-PV-1021A 11-PV-3015B 6 3 4 5 7 8 9 10 11 13 14 15 12 16 17 11-TV-3004 10-HV-1008 11-LV-5010B 10-FV-1003 Overhauling and Calibrations Of Control Valves Sr. No. 1 2 Tag No. 11-HV-2071A 11-PV-7109 11-HV-1032B 46 47 - 1 4 4 4 - 11-TV-5476 45 19-PV-9001A 11-FV-2028 11-LV-2055 11-TV-5482 42 44 43 18 18 8 8 10 10 10 8 - 8 12 4 6 3 10 24 12 6 12 - - 8 8 - 10-HV-1009 11-FV-2056 11-PV-1048 11-FV-2048 11-XV-2011A 11-LV-3011A 11-LV-3011B 19-FV-9002 11-FV-2033 10-FV-1801 11-FV-2011 11-FV-2030 11-HV-2011 11-XV-2011B 11-FV-2076 11-FV-2026 11-HV-3022 10-LV-1018 11-PV-2027 11-PV-2046A PIC-611V 11-PV-2046B 24 25 26 22 23 11-PV-7498 11-XV-2027 18 19 20 21 27 36 37 38 39 33 34 35 40 41 28 29 30 31 32 Page 4 of 59
  • 8. 5. DAILY PROGRESS LOG: Sr # Tag No. Activities Date Shift D/N Cleaning, Oiling and Polishing Found resetting device faulty Found tyflon inside body Pnumatic Relay Checked Calibrated Sent for Hydro testing Cleaning, Oiling and Polishing Found Valve ball stuck Calibrated Sent for Hydro testing Cleaning, Oiling and Polishing Air leak test of actuator was found OK Hand jack was made smooth by servicing Calibrated Sent for Hydrotesting Cleaning, Oiling and Polishing Overhauling 3 11-HV-2011 27-4-16 Night Day 4 27-4-16 Night 1 27-4-1611-XV-2011B 2 27-4-16 Day11-XV-2011A 11-FV-2048 Overhauling and Calibrations Of Control Valves Overhauling Calibrated Sent for Hydro testing Cleaning, Oiling and Polishing Overhauling Started Cleaning, Oiling and Polishing Removing & Cleaning Positioner Removing & Cleaning Limit Switches Overhauling Found leakage in Cylinder Cleaning, Oiling and Polishing Overhauling Cleaning, Oiling and Polishing Overhauling Started Cleaning, Oiling and Polishing Overhauling Started Cleaning, Oiling and Polishing Overhauling Started Valve body sent for machining Cleaning, Oiling and Polishing Overhauling Calibrated Sent for Hydro testing Cleaning, Oiling and Polishing Overhauling Sent Actuator Stem for machining Calibrated Sent for Hydro testing 7 28-4-16 Day10-FV-1801 28-4-16 28-4-16 Day Day Night 4 27-4-16 Night 6 28-4-16 Day 5 27-4-16 Night 11-FV-2048 11-FV-2030 11-FV-2011 28-4-16 8 9 10 11-PV-2046B 11-FV-2033 10-LV-1018 Night Night 11 12 28-4-16 28-4-16 11-PV-2027 11-FV-2030 Page 5 of 59
  • 9. 5. DAILY PROGRESS LOG: Sr # Tag No. Activities Date Shift D/N Day1 27-4-1611-XV-2011B Overhauling and Calibrations Of Control Valves Cleaning, Oiling and Polishing Removing & Cleaning of Positioner Removing & Cleaning of Limit Switch Overhauling Calibration Sent for Hydrotesting Cleaning, Oiling and Polishing Overhauling Calibration Sent for Hydrotesting Cleaning, Oiling and Polishing Air Leak test ok Calibration Valve Body returned from Machining Calibration Sent for Hydrotesting Cleaning, Oiling and Polishing 15 29-4-16 Day 14 29-4-16 Day 13 29-4-16 Day11-FV-2011 11-FV-2033 11-HV-3022 29-4-16 Night16 17 10-LV-1018 29-4-16 Night 11-FV-2026 Cleaning, Oiling and Polishing Overhauling Calibration Sent for Hydrotesting Cleaning, Oiling and Polishing Overhauling Calibration Sent for Hydrotesting Cleaning, Oiling and Polishing Air Leak test ok Cleaning, Oiling and Polishing Overhauling Started Cleaning, Oiling and Polishing Overhauling Calibration Sent for Hydrotesting Cleaning, Oiling and Polishing Overhauling Calibration Sent for Hydrotesting Cleaning, Oiling and Polishing Overhauling Calibration Sent for Hydrotesting Cleaning, Oiling and Polishing Air leak test ok Overhauling Started 19 18 17 29-4-16 Night 20 21 30-4-16 Day Day30-4-1622 23 29-4-16 Night 29-4-16 Night 29-4-16 Night 11-FV-2026 11-FV-2076 11-XV-2027 10-LV-2018 11-PV-7498 11-FV-1801 30-4-16 Day 24 30-4-16 Day 11-PV-2046B 11-PV-7109 Page 6 of 59
  • 10. 5. DAILY PROGRESS LOG: Sr # Tag No. Activities Date Shift D/N Day1 27-4-1611-XV-2011B Overhauling and Calibrations Of Control Valves Cleaning, Oiling and Polishing Air Leak test ok Overhauling Valve Seat Missing, New installed New Lock relay installed Calibration Sent for Hydrotesting Cleaning, Oiling and Polishing Air Leak test ok Overhauling Calibration Sent for Hydrotesting Cleaning, Oiling and Polishing Overhauling Started Cleaning, Oiling and Polishing Air Leak test ok Overhauling Night26 30-4-16 27 30-4-16 Night 25 30-4-16 NightPIC-611V LIC-611A 11-FV-7010 28 01-5-16 Day11-PV-3015B Overhauling Servicing of hand wheel Calibration Sent for Hydrotesting Cleaning, Oiling and Polishing Air Leak test ok Removing & Cleaning of Positoner Cleaning, Oiling and Polishing Air Leak test ok Calibration Sent for Hydrotesting Cleaning, Oiling and Polishing Air Leak test ok Calibration Sent for Hydrotesting Cleaning, Oiling and Polishing Overhauling Started Cleaning, Oiling and Polishing Air Leak test ok Overhauling Found Leakage in Pneumatic relay Fixed Pneumatic realy Calibration Sent for Hydrotesting Cleaning, Oiling and Polishing Air Leak test ok Overhauling Started 29 01-5-16 Day 30 01-5-16 Day 28 01-5-16 Day11-PV-3015B 11-PV-1021A 11-XV-2027A 32 01-5-16 Day 33 01-5-16 Night 31 01-5-16 Day11-XV-2027C 11-PV-7109 11-FV-7010 34 01-5-16 Night11-FV-3021B Page 7 of 59
  • 11. 5. DAILY PROGRESS LOG: Sr # Tag No. Activities Date Shift D/N Day1 27-4-1611-XV-2011B Overhauling and Calibrations Of Control Valves Cleaning, Oiling and Polishing Air Leak test ok Found valve not 100% opening Positioner Dismantled Overhauling Sent body for machining Hydrotest Failed @2400psi Bench Set readjusted Valve stem readjusted Calibrated Sent For Hydrotesting Cleaning, Oiling and Polishing Air Leak test ok Cleaning, Oiling and Polishing Air Leak test ok Sent body for machining Hydrotest Failed 02-05-16 Day 38 02-05-16 Day 39 02-05-16 Night 35 02-05-16 Day Day02-05-1636 37 11-LV-3026D 10-FV-1801 11-FV-3022 11-LV-5010A 11-FV-7010 Hydrotest Failed Found Valve Positioner faulty Found Pneumatic Relay faulty Fixed pneumatic relay and reinstalled Calibrated Sent For Hydrotesting Overhauling Air Leak test ok Sent seat, cage and stem for machining Calibrated Sent For Hydrotesting Cleaning, Oiling and Polishing Air Leak test ok Overhauling Calibration Started Cleaning, Oiling and Polishing Air Leak test ok Calibrated Sent For Hydrotesting Received Body from machining Overhauling 44 10-FV-1003 Cleaning, Oiling and Polishing 03-05-16 Day Cleaning, Oiling and Polishing Air Leak test ok Overhauling Sent For Hydrotesting Cleaning, Oiling and Polishing Air Leak test ok 41 02-05-16 Night 39 02-05-16 Night 40 02-05-16 Night 42 03-05-16 Day 43 03-05-16 Day 45 03-05-16 Day Day03-05-1646 11-LV-3026D 11-LV-5010A 11-LV-5010B 11-FV-7010 11-FV-3021B 11-FV-3022 10-HV-1012 Page 8 of 59
  • 12. 5. DAILY PROGRESS LOG: Sr # Tag No. Activities Date Shift D/N Day1 27-4-1611-XV-2011B Overhauling and Calibrations Of Control Valves Calibration Sent For Hydrotesting Cleaning, Oiling and Polishing Air Leak test ok Sent seat, cage and stem for machining 49 10-HV-1008 Flange Opened 03-05-16 Night Cleaning, Oiling and Polishing Air Leak test ok Sent seat, cage and stem for machining Overhauling Sent For Hydrotesting Cleaning, Oiling and Polishing Air Leak test ok Overhauling Calibration Sent For Hydrotesting Cleaning, Oiling and Polishing 11-TV-300452 04-05-16 Day 48 03-05-16 Night 47 03-05-16 Night 50 04-05-16 04-05-16 Day Day 51 11-FV-3022 11-PV-7109 11-LV-5010B 10-PV-1021A Cleaning, Oiling and Polishing Air Leak test ok Bench Set was found Sent For Hydrotesting Cleaning, Oiling and Polishing Air Leak test ok Calibration Sent For Hydrotesting Cleaning, Oiling and Polishing Air Leak test ok Calibration Sent For Hydrotesting Cleaning, Oiling and Polishing Air Leak test ok Calibration Sent For Hydrotesting Cleaning, Oiling and Polishing Air Leak test ok Seat and plug were sent for machining All gaskets replaced Diapharm was found torned Diapharm replaced Calibrated Sent for Hydrotesting 56 05-05-16 Day 11-HV-2071A55 05-05-16 Day 11-TV-300452 04-05-16 Day 54 04-05-16 Night Night04-05-1653 11-LV-3026D 11-HV-2011A 11-PV-1048 Page 9 of 59
  • 13. 5. DAILY PROGRESS LOG: Sr # Tag No. Activities Date Shift D/N Day1 27-4-1611-XV-2011B Overhauling and Calibrations Of Control Valves Received seat, cage and stem from machining Seat gasket replaced Body gaskets replaced Air leak test of actuator was found OK Calibrated Sent for Hydro testing Cleaning, Oiling and Polishing Air Leak test ok Positioner Dismantled Cleaning, Oiling and Polishing Air Leak test ok Bench Set was found Cleaning, Oiling and Polishing Air Leak test ok Overhauling of body and actuator Seat and plug were sent for machining Cleaning, Oiling and Polishing 60 06-05-16 Day 06-05-1610-HV-100961 Day 11-PV-710957 05-05-16 Night 11-LV-3011A58 05-05-16 Night 05-05-16 Night11-LV-3011B59 19-FV-9002 Cleaning, Oiling and Polishing Air Leak test ok Outer diapharm of actuator was disassembled Bench Set was found Cleaning, Oiling and Polishing Air Leak test ok Plug, seat and cage were sent for machining Cleaning, Oiling and Polishing Air Leak test ok Diapharm was found Ok Overhauling of body and actuator O-rings replaced Seat, plug sent for machining All gaskets replaced Calibrated Sent For Hydrotesting Body gaskets replaced Calibrated Sent for Hydro testing Received Plug, seat and cage from machining All three gaskets of valve replaced Gland packing was replaced Calibrated Sent for Hydro testing Received Plug, seat and cage from machining Gaskets were replaced Gland packing was replaced 67 10-HV-1009 Plug and gland packing were removed 07-05-16 Day 11-LV-3011B65 06-05-16 Night 11-LV-3011A66 06-05-16 Night 19-FV-9001A63 6-5-16 Day 64 06-05-16 Night 06-05-1610-HV-100961 Day 62 06-05-16 Day 19-FV-9002 11-LV-3011B Page 10 of 59
  • 14. 5. DAILY PROGRESS LOG: Sr # Tag No. Activities Date Shift D/N Day1 27-4-1611-XV-2011B Overhauling and Calibrations Of Control Valves Received Plug, seat and cage from machining Bench Set readjusted Calibration Sent for Hydro testing Cleaning, Oiling and Polishing Plug, seat and cage were sent for machining Tubing was readjusted Calibrated Sent for Hydro testing Cleaning, Oiling and Polishing Air Leak test ok Positioner was removed for cleaning Diapharm was found ok Calibrated Sent For Hydrotesting Cleaning, Oiling and Polishing Air Leak test ok 68 11-LV-3011B 07-05-16 Day 10-LV-100772 08-05-16 Day 69 11-HV-1008 07-05-16 Day 11-LV-3011A70 07-05-16 Day 11-PV-749871 08-05-16 Day Air Leak test ok Calibration was tested and found ok Scratches were found on valve stem Removed scratches by filing and embre paper Air Leak test ok Sent For Hydrotesting Actuator was reopened Overhauling of body and actuator Cleaning, Oiling and Polishing Air Leak test ok Calibration Cleaning, Oiling and Polishing Air Leak test ok Calibration Cleaning, Oiling and Polishing Air Leak test ok Calibration Cleaning, Oiling and Polishing Air Leak test ok Calibration Cleaning, Oiling and Polishing Air Leak test ok Calibration 10-LV-100772 08-05-16 Day 73 10-HV-1009 08-05-16 Day 11-TV-547677 10-05-16 Night 78 11-HV-1032B 10-05-16 Night 09-05-16 Day11-FV-202874 11-LV-205575 09-05-16 Night 11-TV-548276 10-05-16 Day Page 11 of 59
  • 15. CLIENT DATE: 27-04-2016 PROJECT DOC.NO. CV-E-001 CONTRACTOR JOB NO. F-689 VALVE INFORMATON: TAG NO: 11-XV-2011A SERVICE: Process Air SIZE: 12" AREA: AMM-3 FLANGE TYPE: Flanged PHYSICAL CHECKS: Overhauling and Calibrations Of Control Valves (Valve Record Sheet) Engro Fertilizers Limited Plant-II Shutdown 2016 Flowtronix (Pvt) Ltd. AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT TEST RESULTS: CONDITIONS (As Found) & CORRECTIVE MAINTENANCE: REMARKS: This valve has been overhauled, Calibrated and Cleared for area installation. Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh DATE 27-04-2016 EXECUTED BY Umair Riasat (Instrument Technician) 1. Valve ball was stuck. 2. Cleaning, oiling and polishing the vlave ball. FAIL SAFE ACTION Close SUPPLIED PRESSURE 87 psi VALVE BENCH SET AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT Page 12 of 59
  • 16. CLIENT DATE: 27-04-2016 PROJECT DOC.NO. CV-E-002 CONTRACTOR JOB NO. F-689 VALVE INFORMATON: TAG NO: 11-FV-2048 SERVICE: Process Air SIZE: 8-/-4-/-8" AREA: AMM-3 FLANGE TYPE: RF Flanges PHYSICAL CHECKS: Overhauling and Calibrations Of Control Valves (Valve Record Sheet) Engro Fertilizers Limited Plant-II Shutdown 2016 Flowtronix (Pvt) Ltd. AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT TEST RESULTS: CONDITIONS (As Found) & CORRECTIVE MAINTENANCE: REMARKS: This valve has been overhauled, Calibrated and Cleared for area installation. Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh DATE 27-04-2016 EXECUTED BY Umair Riasat (Instrument Technician) 1. Actuator O-rings were replaced. 2. Pug and seat were sent for machining. 3. All gaskits were replaced. 4. Overhauling 5. Calibrated 6. Sent for Hydrotesting VALVE BENCH SET FAIL SAFE ACTION Close SUPPLIED PRESSURE AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT Page 13 of 59
  • 17. CLIENT DATE: 27-04-2016 PROJECT DOC.NO. CV-E-003 CONTRACTOR JOB NO. F-689 VALVE INFORMATON: TAG NO: 11-HV-2011 SERVICE: Process Air SIZE: 8 " AREA: AMM-3 FLANGE TYPE: RF 125 AARH PHYSICAL CHECKS: Flowtronix (Pvt) Ltd. Overhauling and Calibrations Of Control Valves (Valve Record Sheet) Engro Fertilizers Limited Plant-II Shutdown 2016 AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT TEST RESULTS: CONDITIONS (As Found) & CORRECTIVE MAINTENANCE: REMARKS: This valve has been overhauled, Calibrated and Cleared for area installation. Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh 1. Actuator was found stuck. 2. Air leak test of actuator was found OK 3. Hand jack was made smooth by servicing 4. Calibrated 5. Sent For Hydrotesting DATE 27-04-2016 EXECUTED BY Umair Riasat (Instrument Technician) VALVE BENCH SET FAIL SAFE ACTIONSUPPLIED PRESSURE AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT Page 14 of 59
  • 18. CLIENT DATE: 27-04-2016 PROJECT DOC.NO. CV-E-004 CONTRACTOR JOB NO. F-689 VALVE INFORMATON: TAG NO: 11-XV-2011B SERVICE: Process Air SIZE: AREA: AMM-3 FLANGE TYPE: PHYSICAL CHECKS: Overhauling and Calibrations Of Control Valves (Valve Record Sheet) Engro Fertilizers Limited Plant-II Shutdown 2016 Flowtronix (Pvt) Ltd. AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT TEST RESULTS: CONDITIONS (As Found) & CORRECTIVE MAINTENANCE: REMARKS: This valve has been overhauled, Calibrated and Cleared for area installation. Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh DATE 27-04-2016 EXECUTED BY Umair Riasat (Instrument Technician) 1. Tyflon Seat seal was damaged. 2. Found air leakage in resetting device. 3. Tyflon seat seal replaced. 4. Resetting device O-Rings were replaced 5. Calibrated 6. Sent for hydrotesting VALVE BENCH SET FAIL SAFE ACTION Open SUPPLIED PRESSURE AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT Page 15 of 59
  • 19. CLIENT DATE: 27-04-2016 PROJECT DOC.NO. CV-E-005 CONTRACTOR JOB NO. F-689 VALVE INFORMATON: TAG NO: 11-FV-2030 SERVICE: Process Air SIZE: 10 " AREA: AMM-3 FLANGE TYPE: RF Flanges PHYSICAL CHECKS: Overhauling and Calibrations Of Control Valves (Valve Record Sheet) Engro Fertilizers Limited Plant-II Shutdown 2016 Flowtronix (Pvt) Ltd. AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT TEST RESULTS: CONDITIONS (As Found) & CORRECTIVE MAINTENANCE: REMARKS: This valve has been overhauled, Calibrated and Cleared for area installation. Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh DATE 27-04-2016 EXECUTED BY Umair Riasat (Instrument Technician) 1. Overhauling of actuator and body. 2. Actuator Stem was sent for machining. 3. Actuator Gasket replaced 4. Gland packing replaced. 5. Calibration 6. Sent for hydrotesting VALVE BENCH SET FAIL SAFE ACTIONSUPPLIED PRESSURE AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT Page 16 of 59
  • 20. CLIENT DATE: 28-04-2016 PROJECT DOC.NO. CV-E-006 CONTRACTOR JOB NO. F-689 VALVE INFORMATON: TAG NO: 11-FV-2011 SERVICE: Process Air SIZE: 12 " AREA: AMM-3 FLANGE TYPE: RF-125 AARH PHYSICAL CHECKS: Overhauling and Calibrations Of Control Valves (Valve Record Sheet) Engro Fertilizers Limited Plant-II Shutdown 2016 Flowtronix (Pvt) Ltd. AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT TEST RESULTS: CONDITIONS (As Found) & CORRECTIVE MAINTENANCE: REMARKS: This valve has been overhauled, Calibrated and Cleared for area installation. Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh DATE 28-04-2016 EXECUTED BY Umair Riasat (Instrument Technician) 1. Found air leakage in cylinder 2. Overhauling of Actuator 3. O-rings required relacements, tyflon was wound due to inavailablity. 4. Found a embosed spot on piston 5. Removing and cleaning of positioner 6. Removing and cleaning of Actuator 7. Feedback link plate gaskets replaced 8. Calibration 9. Sent for hydrotesting VALVE BENCH SET FAIL SAFE ACTION Close SUPPLIED PRESSURE AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT Page 17 of 59
  • 21. CLIENT DATE: 28-04-2016 PROJECT DOC.NO. CV-E-007 CONTRACTOR JOB NO. F-689 VALVE INFORMATON: TAG NO: 10-FV-1801 SERVICE: Process Air SIZE: 24 " AREA: AMM-3 FLANGE TYPE: PHYSICAL CHECKS: Overhauling and Calibrations Of Control Valves (Valve Record Sheet) Engro Fertilizers Limited Plant-II Shutdown 2016 Flowtronix (Pvt) Ltd. AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT TEST RESULTS: CONDITIONS (As Found) & CORRECTIVE MAINTENANCE: REMARKS: This valve has been overhauled, Calibrated and Cleared for area installation. Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh DATE 28-04-2016 EXECUTED BY Umair Riasat (Instrument Technician) 1. Removing and Cleaning of Positioner 2. Overhauling of Actuator 3. Plug was sent for machining 4. Gland packing replaced 5. Seals replaced 6. Found a embosed spot on piston. 7. Calibrated 8. Sent for hydrotesting VALVE BENCH SET FAIL SAFE ACTIONSUPPLIED PRESSURE AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT Page 18 of 59
  • 22. CLIENT DATE: 28-04-2016 PROJECT DOC.NO. CV-E-008 CONTRACTOR JOB NO. F-689 VALVE INFORMATON: TAG NO: 11-FV-2033 SERVICE: Process Air SIZE: 6 " AREA: AMM-3 FLANGE TYPE: RF Flanges PHYSICAL CHECKS: Overhauling and Calibrations Of Control Valves (Valve Record Sheet) Engro Fertilizers Limited Plant-II Shutdown 2016 Flowtronix (Pvt) Ltd. AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT TEST RESULTS: CONDITIONS (As Found) & CORRECTIVE MAINTENANCE: REMARKS: This valve has been overhauled, Calibrated and Cleared for area installation. Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh DATE 28-04-2016 EXECUTED BY Umair Riasat (Instrument Technician) 1. Overhauling of Actuator 2. Overhauling of Body 3. Seat seals replaced 4. Gland packing replaced 5. Vapour Seals replaced 6. Actuator O-rings replaced 7. Inner and outer plug seals replaced 8. Calibrated 9. Sent for Hydrotesting VALVE BENCH SET FAIL SAFE ACTION Close SUPPLIED PRESSURE 30 AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT Page 19 of 59
  • 23. CLIENT DATE: 28-04-2016 PROJECT DOC.NO. CV-E-009 CONTRACTOR JOB NO. F-689 VALVE INFORMATON: TAG NO: 11-PV-2046A SERVICE: Process Air SIZE: 3 " AREA: AMM-3 FLANGE TYPE: RF Flanges PHYSICAL CHECKS: Overhauling and Calibrations Of Control Valves (Valve Record Sheet) Engro Fertilizers Limited Plant-II Shutdown 2016 Flowtronix (Pvt) Ltd. AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT TEST RESULTS: CONDITIONS (As Found) & CORRECTIVE MAINTENANCE: REMARKS: This valve has been overhauled, Calibrated and Cleared for area installation. Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh DATE 28-04-2016 EXECUTED BY Umair Riasat (Instrument Technician) 1. Overhauling of actuator VALVE BENCH SET FAIL SAFE ACTION Close SUPPLIED PRESSURE 40 AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT Page 20 of 59
  • 24. CLIENT DATE: 28-04-2016 PROJECT DOC.NO. CV-E-010 CONTRACTOR JOB NO. F-689 VALVE INFORMATON: TAG NO: 11-PV-2027 SERVICE: Process Air SIZE: AREA: AMM-3 FLANGE TYPE: PHYSICAL CHECKS: Overhauling and Calibrations Of Control Valves (Valve Record Sheet) Engro Fertilizers Limited Plant-II Shutdown 2016 Flowtronix (Pvt) Ltd. AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT TEST RESULTS: CONDITIONS (As Found) & CORRECTIVE MAINTENANCE: REMARKS: This valve has been overhauled, Calibrated and Cleared for area installation. Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh DATE 28-04-2016 EXECUTED BY Umair Riasat (Instrument Technician) 1. Overhauling of Actuator 2. Overhauling of Body 3. Seat, Plug and cage were sent for machining 4. Seat seals replaced 5. Gland packing replaced 6. Body and seat gasket replaced 7. Actuator O-rings replaced VALVE BENCH SET FAIL SAFE ACTIONSUPPLIED PRESSURE AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT Page 21 of 59
  • 25. CLIENT DATE: 29-04-2016 PROJECT DOC.NO. CV-E-011 CONTRACTOR JOB NO. F-689 VALVE INFORMATON: TAG NO: 10-LV-1018 SERVICE: Process Air SIZE: 4 " AREA: AMM-3 FLANGE TYPE: RF Flanges PHYSICAL CHECKS: Overhauling and Calibrations Of Control Valves (Valve Record Sheet) Engro Fertilizers Limited Plant-II Shutdown 2016 Flowtronix (Pvt) Ltd. AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT TEST RESULTS: CONDITIONS (As Found) & CORRECTIVE MAINTENANCE: REMARKS: This valve has been overhauled, Calibrated and Cleared for area installation. Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh DATE 29-04-2016 EXECUTED BY Umair Riasat (Instrument Technician) 1. Found Leak test of actuator OK 2. Overhauling of Actuator 3. Overhauling of Body 4. Body was sent for machining 5. Seat seals replaced 6. Body gasket replaced 7. Actuator O-rings replaced 8. Gland packings replaced 9. Calibrated VALVE BENCH SET FAIL SAFE ACTIONSUPPLIED PRESSURE AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT Page 22 of 59
  • 26. CLIENT DATE: 29-04-2016 PROJECT DOC.NO. CV-E-012 CONTRACTOR JOB NO. F-689 VALVE INFORMATON: TAG NO: 11-HV-3022 SERVICE: Process Air SIZE: 8 " AREA: AMM-3 FLANGE TYPE: RF Flanges PHYSICAL CHECKS: Overhauling and Calibrations Of Control Valves (Valve Record Sheet) Engro Fertilizers Limited Plant-II Shutdown 2016 Flowtronix (Pvt) Ltd. AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT TEST RESULTS: CONDITIONS (As Found) & CORRECTIVE MAINTENANCE: REMARKS: This valve has been overhauled, Calibrated and Cleared for area installation. Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh DATE 29-04-2016 EXECUTED BY Umair Riasat (Instrument Technician) 1. Air Leak check of actuator was found OK 2. Calibrated 3. Sent for Hydrotesting VALVE BENCH SET FAIL SAFE ACTION Close SUPPLIED PRESSURE 60 AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT Page 23 of 59
  • 27. CLIENT DATE: 29-04-2016 PROJECT DOC.NO. CV-E-013 CONTRACTOR JOB NO. F-689 VALVE INFORMATON: TAG NO: 11-FV-2026 SERVICE: Process Air SIZE: 8 " AREA: AMM-3 FLANGE TYPE: RF Flanges PHYSICAL CHECKS: Overhauling and Calibrations Of Control Valves (Valve Record Sheet) Engro Fertilizers Limited Plant-II Shutdown 2016 Flowtronix (Pvt) Ltd. AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT TEST RESULTS: CONDITIONS (As Found) & CORRECTIVE MAINTENANCE: REMARKS: This valve has been overhauled, Calibrated and Cleared for area installation. Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh DATE 29-04-2016 EXECUTED BY Umair Riasat (Instrument Technician) 1. Overhauling of Body 2. Overhauling of Actuator 3. Seat and plug were sent for machining 4. Plug seal ring (carbon) was repalced. 5. Inner and outer seals were replaced 6. Gland packing replaced 7. Calibrated VALVE BENCH SET FAIL SAFE ACTIONSUPPLIED PRESSURE AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT Page 24 of 59
  • 28. CLIENT DATE: 29-04-2016 PROJECT DOC.NO. CV-E-014 CONTRACTOR JOB NO. F-689 VALVE INFORMATON: TAG NO: 11-FV-2076 SERVICE: Process Air SIZE: 4 " AREA: AMM-3 FLANGE TYPE: RTJ Flanges PHYSICAL CHECKS: Overhauling and Calibrations Of Control Valves (Valve Record Sheet) Engro Fertilizers Limited Plant-II Shutdown 2016 Flowtronix (Pvt) Ltd. AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT TEST RESULTS: CONDITIONS (As Found) & CORRECTIVE MAINTENANCE: REMARKS: This valve has been overhauled, Calibrated and Cleared for area installation. Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh DATE 29-04-2016 EXECUTED BY Umair Riasat (Instrument Technician) 1. Overhauling of body 2. Overhauling of actuator 3. Inner and outer seals replaced 4. Gland packing replaced 5. O-rings replaced 6. Calibrated VALVE BENCH SET FAIL SAFE ACTIONSUPPLIED PRESSURE AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT Page 25 of 59
  • 29. CLIENT DATE: 29-04-2016 PROJECT DOC.NO. CV-E-015 CONTRACTOR JOB NO. F-689 VALVE INFORMATON: TAG NO: 11-XV-2027 SERVICE: Process Air SIZE: 4 " AREA: AMM-3 FLANGE TYPE: RTJ Flanges PHYSICAL CHECKS: Overhauling and Calibrations Of Control Valves (Valve Record Sheet) Engro Fertilizers Limited Plant-II Shutdown 2016 Flowtronix (Pvt) Ltd. AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT TEST RESULTS: CONDITIONS (As Found) & CORRECTIVE MAINTENANCE: REMARKS: This valve has been overhauled, Calibrated and Cleared for area installation. Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh DATE 29-04-2016 EXECUTED BY Umair Riasat (Instrument Technician) 1. Air leak test of actuator was found OK 2. Overhauling of actuator 3. Overhauling of body 4. Seat, Plug and Cage were machined 5. Seat seals replaced 4. Gland packing replaced 5. Body and seat gaskets replaced 6. Calibrated VALVE BENCH SET FAIL SAFE ACTIONSUPPLIED PRESSURE AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT Page 26 of 59
  • 30. CLIENT DATE: 30-04-2016 PROJECT DOC.NO. CV-E-016 CONTRACTOR JOB NO. F-689 VALVE INFORMATON: TAG NO: 11-PV-7498 SERVICE: Process Air SIZE: 12 " AREA: AMM-3 FLANGE TYPE: RF Flanges PHYSICAL CHECKS: Overhauling and Calibrations Of Control Valves (Valve Record Sheet) Engro Fertilizers Limited Plant-II Shutdown 2016 Flowtronix (Pvt) Ltd. AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT TEST RESULTS: CONDITIONS (As Found) & CORRECTIVE MAINTENANCE: REMARKS: This valve has been overhauled, Calibrated and Cleared for area installation. Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh DATE 30-04-2016 EXECUTED BY Abid Naeem (Instrument Technician) 1. Diapharm was stretched and torn from nut & bolts holes at circumference. 2. Overhauling of actuator 3. Actuator seals replaced 4. Diapharm replaced 5. Calibrated VALVE BENCH SET FAIL SAFE ACTION Close SUPPLIED PRESSURE 58 AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT Page 27 of 59
  • 31. CLIENT DATE: 30-04-2016 PROJECT DOC.NO. CV-E-017 CONTRACTOR JOB NO. F-689 VALVE INFORMATON: TAG NO: 11-PV-2046B SERVICE: Process Air SIZE: 6-/-3-/-6 AREA: AMM-3 FLANGE TYPE: RF Flanges PHYSICAL CHECKS: Overhauling and Calibrations Of Control Valves (Valve Record Sheet) Engro Fertilizers Limited Plant-II Shutdown 2016 Flowtronix (Pvt) Ltd. AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT TEST RESULTS: CONDITIONS (As Found) & CORRECTIVE MAINTENANCE: REMARKS: This valve has been overhauled, Calibrated and Cleared for area installation. Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh DATE 30-04-2016 EXECUTED BY Abid Naeem (Instrument Technician) 1. Overhauling of actuator 2. Plug and seat ring polished 3. Seat gaskets changed 4. Body gaskets replaced 5. Gland packing replaced. 6. O-rings of actuator replaced. 7. Calibrated 8. Sent for Hydrotesting VALVE BENCH SET FAIL SAFE ACTIONSUPPLIED PRESSURE AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT Page 28 of 59
  • 32. CLIENT DATE: 30-04-2016 PROJECT DOC.NO. CV-E-018 CONTRACTOR JOB NO. F-689 VALVE INFORMATON: TAG NO: 11-PV-7109 SERVICE: Process Air SIZE: 12 " AREA: AMM-3 FLANGE TYPE: RF Flanges PHYSICAL CHECKS: Overhauling and Calibrations Of Control Valves (Valve Record Sheet) Engro Fertilizers Limited Plant-II Shutdown 2016 Flowtronix (Pvt) Ltd. AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT TEST RESULTS: CONDITIONS (As Found) & CORRECTIVE MAINTENANCE: REMARKS: This valve has been overhauled, Calibrated and Cleared for area installation. Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh DATE 30-04-2016 EXECUTED BY Abid Naeem (Instrument Technician) 1. Air leak test of actuator was found OK 2. Valve bonut was stuck with actuator yoke, heated and hammered to get them separated. 3. Overhauling of body 4. Plug, Seat and Cage were sent for machining 5. Inner and outer body gaskets were replaced 6. Both rings of valve plug were replaced 7. Calibrated 8. Sent for Hydrotesting VALVE BENCH SET FAIL SAFE ACTION Close SUPPLIED PRESSURE 60 AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT Page 29 of 59
  • 33. CLIENT DATE: 30-04-2016 PROJECT DOC.NO. CV-E-019 CONTRACTOR JOB NO. F-689 VALVE INFORMATON: TAG NO: PIC-611V SERVICE: Process Air SIZE: AREA: AMM-3 FLANGE TYPE: PHYSICAL CHECKS: Overhauling and Calibrations Of Control Valves (Valve Record Sheet) Engro Fertilizers Limited Plant-II Shutdown 2016 Flowtronix (Pvt) Ltd. AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT TEST RESULTS: CONDITIONS (As Found) & CORRECTIVE MAINTENANCE: REMARKS: This valve has been overhauled, Calibrated and Cleared for area installation. Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh DATE 30-04-2016 EXECUTED BY Abid Naeem (Instrument Technician) 1. Valve seat was not found during disassembly 2. Lock relay was not working 3. Seat and plug were sent for machining 4. Air Leak test of Actuator was found OK 5. Overhauling of Valve body 6. Seals replaced 7. Lock relay replaced 8. Calibrated 9. Sent for Hydrotesting VALVE BENCH SET FAIL SAFE ACTIONSUPPLIED PRESSURE AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT Page 30 of 59
  • 34. CLIENT DATE: 30-04-2016 PROJECT DOC.NO. CV-E-020 CONTRACTOR JOB NO. F-689 VALVE INFORMATON: TAG NO: LIC-611A SERVICE: Process Air SIZE: AREA: AMM-3 FLANGE TYPE: PHYSICAL CHECKS: Overhauling and Calibrations Of Control Valves (Valve Record Sheet) Engro Fertilizers Limited Plant-II Shutdown 2016 Flowtronix (Pvt) Ltd. AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT TEST RESULTS: CONDITIONS (As Found) & CORRECTIVE MAINTENANCE: REMARKS: This valve has been overhauled, Calibrated and Cleared for area installation. Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh DATE 30-04-2016 EXECUTED BY Abid Naeem (Instrument Technician) 1. Air leak test of actuator was found OK 2. Overhauling of Body 3. Seals replaced 4. Gland packing replaced 5. Calibrated 6. Sent for Hydrotesting VALVE BENCH SET FAIL SAFE ACTIONSUPPLIED PRESSURE AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT Page 31 of 59
  • 35. CLIENT DATE: 30-04-2016 PROJECT DOC.NO. CV-E-021 CONTRACTOR JOB NO. F-689 VALVE INFORMATON: TAG NO: 11-FV-7010 SERVICE: Process Air SIZE: 8 " AREA: AMM-3 FLANGE TYPE: RF Flanges PHYSICAL CHECKS: Overhauling and Calibrations Of Control Valves (Valve Record Sheet) Engro Fertilizers Limited Plant-II Shutdown 2016 Flowtronix (Pvt) Ltd. AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT TEST RESULTS: CONDITIONS (As Found) & CORRECTIVE MAINTENANCE: REMARKS: This valve has been overhauled, Calibrated and Cleared for area installation. Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh 1. Air leakage found in Pneumatic relay of positioner 2. Overhauling of Body 3. Overhauling of Actuator 4. Actuator O-rings replaced 5. Body gaskets replaced 6. O-rings of pneumatic relay replaced 7. Calibrated 8. Sent for Hydrotesting DATE 30-04-2016 EXECUTED BY Abid Naeem (Instrument Technician) FAIL SAFE ACTIONSUPPLIED PRESSUREVALVE BENCH SET AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT Page 32 of 59
  • 36. CLIENT DATE: 01-05-2016 PROJECT DOC.NO. CV-E-022 CONTRACTOR JOB NO. F-689 VALVE INFORMATON: TAG NO: 11-PV-3015B SERVICE: Process Air SIZE: 20 " AREA: AMM-3 FLANGE TYPE: RF-125 AARH PHYSICAL CHECKS: Flowtronix (Pvt) Ltd. Overhauling and Calibrations Of Control Valves (Valve Record Sheet) Engro Fertilizers Limited Plant-II Shutdown 2016 AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT TEST RESULTS: CONDITIONS (As Found) & CORRECTIVE MAINTENANCE: REMARKS: This valve has been overhauled, Calibrated and Cleared for area installation. Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh 1. Handwheel was found stucking while rotating either way. 2. Overhauling of actuator 3. Servicing, oiling and cleaning of handwheel 4. Calibrated 5. Sent for Hydrotesting DATE 01-05-2016 EXECUTED BY Abid Naeem (Instrument Technician) VALVE BENCH SET FAIL SAFE ACTIONSUPPLIED PRESSURE AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT Page 33 of 59
  • 37. CLIENT DATE: 01-05-2016 PROJECT DOC.NO. CV-E-023 CONTRACTOR JOB NO. F-689 VALVE INFORMATON: TAG NO: 11-PV-2021A SERVICE: Process Air SIZE: AREA: AMM-3 FLANGE TYPE: PHYSICAL CHECKS: Flowtronix (Pvt) Ltd. Overhauling and Calibrations Of Control Valves (Valve Record Sheet) Engro Fertilizers Limited Plant-II Shutdown 2016 AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT TEST RESULTS: CONDITIONS (As Found) & CORRECTIVE MAINTENANCE: REMARKS: This valve has been overhauled, Calibrated and Cleared for area installation. Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh 1. Actuator air leak test was found OK. 2. Positioner dismantled and cleaned 3. Calibrated 4. Sent for Hydrotesting DATE 01-05-2016 EXECUTED BY Abid Naeem (Instrument Technician) VALVE BENCH SET FAIL SAFE ACTION Close SUPPLIED PRESSURE AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT Page 34 of 59
  • 38. CLIENT DATE: 01-05-2016 PROJECT DOC.NO. CV-E-024 CONTRACTOR JOB NO. F-689 VALVE INFORMATON: TAG NO: 11-XV-2027A SERVICE: Process Air SIZE: 12 " AREA: AMM-3 FLANGE TYPE: Flanged PHYSICAL CHECKS: Flowtronix (Pvt) Ltd. Overhauling and Calibrations Of Control Valves (Valve Record Sheet) Engro Fertilizers Limited Plant-II Shutdown 2016 AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT TEST RESULTS: CONDITIONS (As Found) & CORRECTIVE MAINTENANCE: REMARKS: This valve has been overhauled, Calibrated and Cleared for area installation. Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh 1. Valve ball was not smoothly opening and closing. 2. Air leak test of actuator was found OK 3. Polishing, oiling and cleanig of valve ball was done untill required smoothness was aquired. 4. Calibrated 5. Sent for Hydrotesting DATE 01-05-2016 EXECUTED BY Abid Naeem (Instrument Technician) VALVE BENCH SET FAIL SAFE ACTION Close SUPPLIED PRESSURE AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT Page 35 of 59
  • 39. CLIENT DATE: 01-05-2016 PROJECT DOC.NO. CV-E-025 CONTRACTOR JOB NO. F-689 VALVE INFORMATON: TAG NO: 11-XV-2027C SERVICE: Process Air SIZE: 12 " AREA: AMM-3 FLANGE TYPE: Flanged PHYSICAL CHECKS: Flowtronix (Pvt) Ltd. Overhauling and Calibrations Of Control Valves (Valve Record Sheet) Engro Fertilizers Limited Plant-II Shutdown 2016 AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT TEST RESULTS: CONDITIONS (As Found) & CORRECTIVE MAINTENANCE: REMARKS: This valve has been overhauled, Calibrated and Cleared for area installation. Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh 1. Valve ball was not smoothly opening and closing. 2. Air leak test of actuator was found OK 3. Polishing, oiling and cleanig of valve ball was done untill required smoothness was aquired. 4. Calibrated 5. Sent for Hydrotesting DATE 01-05-2016 EXECUTED BY Abid Naeem (Instrument Technician) VALVE BENCH SET FAIL SAFE ACTION Close SUPPLIED PRESSURE AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT Page 36 of 59
  • 40. CLIENT DATE: 02-05-2016 PROJECT DOC.NO. CV-E-026 CONTRACTOR JOB NO. F-689 VALVE INFORMATON: TAG NO: 11-FV-3021B SERVICE: Process Air SIZE: 16 " AREA: AMM-3 FLANGE TYPE: RF Flanges PHYSICAL CHECKS: Flowtronix (Pvt) Ltd. Overhauling and Calibrations Of Control Valves (Valve Record Sheet) Engro Fertilizers Limited Plant-II Shutdown 2016 AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT TEST RESULTS: CONDITIONS (As Found) & CORRECTIVE MAINTENANCE: REMARKS: This valve has been overhauled, Calibrated and Cleared for area installation. Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh 1. Air leak test of Actuator was found OK 2. Overhauling of actuator 3. Overhauling of body 4. Body seals replaced 5. O-rings of actuator Replaced 6. Inner and outer body seals were replaced 7. Cage seals were replaced 8. Gland packing replaced 9. Calibration 10. Sent for Hydrotesting DATE 02-05-2016 EXECUTED BY Abid Naeem (Instrument Technician) VALVE BENCH SET FAIL SAFE ACTIONSUPPLIED PRESSURE 55 AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT Page 37 of 59
  • 41. CLIENT DATE: 03-05-2016 PROJECT DOC.NO. CV-E-027 CONTRACTOR JOB NO. F-689 VALVE INFORMATON: TAG NO: 11-LV-3026D SERVICE: Process Air SIZE: 16-/-12-/-16" AREA: AMM-3 FLANGE TYPE: RF Flanges PHYSICAL CHECKS: Flowtronix (Pvt) Ltd. Overhauling and Calibrations Of Control Valves (Valve Record Sheet) Engro Fertilizers Limited Plant-II Shutdown 2016 AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT TEST RESULTS: CONDITIONS (As Found) & CORRECTIVE MAINTENANCE: REMARKS: This valve has been overhauled, Calibrated and Cleared for area installation. Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh 1. Valve was found not opennig 100% 2. Overhauling of body 3. Positioner was readjsuted 4. Body was sent for machining 5. Calibration 6. Sent for Hydrotesting DATE 03-05-2016 EXECUTED BY Abid Naeem (Instrument Technician) VALVE BENCH SET FAIL SAFE ACTIONSUPPLIED PRESSURE AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT Page 38 of 59
  • 42. CLIENT DATE: 03-05-2016 PROJECT DOC.NO. CV-E-028 CONTRACTOR JOB NO. F-689 VALVE INFORMATON: TAG NO: 11-FV-3022 SERVICE: Process Air SIZE: 8 " AREA: AMM-3 FLANGE TYPE: RF Flanges PHYSICAL CHECKS: Flowtronix (Pvt) Ltd. Overhauling and Calibrations Of Control Valves (Valve Record Sheet) Engro Fertilizers Limited Plant-II Shutdown 2016 AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT TEST RESULTS: CONDITIONS (As Found) & CORRECTIVE MAINTENANCE: REMARKS: This valve has been overhauled, Calibrated and Cleared for area installation. Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh 1. Air Leak test of actuator was found OK 2. Overhauling of Actuator 3. Overhauling of Body 3. Actuator O-rings replaced 4. Body gaskets replaced 5. Gland packing replaced 6. Calibration. 7. Sent for Hydrotesting DATE 03-05-2016 EXECUTED BY Adnan Hussain (Instrument Technician) VALVE BENCH SET FAIL SAFE ACTIONSUPPLIED PRESSURE AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT Page 39 of 59
  • 43. CLIENT DATE: 03-05-2016 PROJECT DOC.NO. CV-E-029 CONTRACTOR JOB NO. F-689 VALVE INFORMATON: TAG NO: 11-LV-5010A SERVICE: Process Air SIZE: 4 " AREA: AMM-3 FLANGE TYPE: RTJ Flanges PHYSICAL CHECKS: Flowtronix (Pvt) Ltd. Overhauling and Calibrations Of Control Valves (Valve Record Sheet) Engro Fertilizers Limited Plant-II Shutdown 2016 AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT TEST RESULTS: CONDITIONS (As Found) & CORRECTIVE MAINTENANCE: REMARKS: This valve has been overhauled, Calibrated and Cleared for area installation. Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh 1. Air leak test of actuator was found OK 2. Overhauling of body 3. Inner and outer body seals replaced. 4. Body gaskets replaced 5. Plug seals replaced 6. Calibrated 7. Sent for Hydrotesting DATE 03-05-2016 EXECUTED BY Adnan Hussain (Instrument Technician) VALVE BENCH SET FAIL SAFE ACTION Close SUPPLIED PRESSURE 50 AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT Page 40 of 59
  • 44. CLIENT DATE: 03-05-2016 PROJECT DOC.NO. CV-E-030 CONTRACTOR JOB NO. F-689 VALVE INFORMATON: TAG NO: 10-HV-1012 SERVICE: Process Air SIZE: 6 " AREA: AMM-3 FLANGE TYPE: RF 125 AARH PHYSICAL CHECKS: Flowtronix (Pvt) Ltd. Overhauling and Calibrations Of Control Valves (Valve Record Sheet) Engro Fertilizers Limited Plant-II Shutdown 2016 AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT TEST RESULTS: CONDITIONS (As Found) & CORRECTIVE MAINTENANCE: REMARKS: This valve has been overhauled, Calibrated and Cleared for area installation. Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh 1. Air leak test of actuator was found OK 2. Calibration 3. Sent for Hydrotesting DATE 03-05-2016 EXECUTED BY Adnan Hussain (Instrument Technician) VALVE BENCH SET FAIL SAFE ACTION Close SUPPLIED PRESSURE AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT Page 41 of 59
  • 45. CLIENT DATE: 03-05-2016 PROJECT DOC.NO. CV-E-031 CONTRACTOR JOB NO. F-689 VALVE INFORMATON: TAG NO: 10-FV-1003 SERVICE: Process Air SIZE: 8 " AREA: AMM-3 FLANGE TYPE: RTJ Flanges PHYSICAL CHECKS: Flowtronix (Pvt) Ltd. Overhauling and Calibrations Of Control Valves (Valve Record Sheet) Engro Fertilizers Limited Plant-II Shutdown 2016 AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT TEST RESULTS: CONDITIONS (As Found) & CORRECTIVE MAINTENANCE: REMARKS: This valve has been overhauled, Calibrated and Cleared for area installation. Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh 1. Air leak test of actuator was found OK 2. Calibration 3. Sent for Hydrotesting DATE 03-05-2016 EXECUTED BY Adnan Hussain (Instrument Technician) VALVE BENCH SET FAIL SAFE ACTION Open SUPPLIED PRESSURE AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT Page 42 of 59
  • 46. CLIENT DATE: 04-05-2016 PROJECT DOC.NO. CV-E-032 CONTRACTOR JOB NO. F-689 VALVE INFORMATON: TAG NO: 11-LV-5010B SERVICE: Process Air SIZE: 4 " AREA: AMM-3 FLANGE TYPE: RTJ Flanges PHYSICAL CHECKS: Flowtronix (Pvt) Ltd. Overhauling and Calibrations Of Control Valves (Valve Record Sheet) Engro Fertilizers Limited Plant-II Shutdown 2016 AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT TEST RESULTS: CONDITIONS (As Found) & CORRECTIVE MAINTENANCE: REMARKS: This valve has been overhauled, Calibrated and Cleared for area installation. Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh 1. Air leak test of actuator was found OK 2. Overhauling of body 3. Inner and outer body seals were replaced. 4. Body gaskets replaced 5. Plug seal replaced 6. Calibration 7. Sent for Hydrotesting DATE 04-05-2016 EXECUTED BY Adnan Hussain (Instrument Technician) VALVE BENCH SET FAIL SAFE ACTION Close SUPPLIED PRESSURE 50 AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT Page 43 of 59
  • 47. CLIENT DATE: 04-05-2016 PROJECT DOC.NO. CV-E-033 CONTRACTOR JOB NO. F-689 VALVE INFORMATON: TAG NO: 10-HV-1008 SERVICE: Process Air SIZE: 12 " AREA: AMM-3 FLANGE TYPE: Lenticular PHYSICAL CHECKS: Flowtronix (Pvt) Ltd. Overhauling and Calibrations Of Control Valves (Valve Record Sheet) Engro Fertilizers Limited Plant-II Shutdown 2016 AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT TEST RESULTS: CONDITIONS (As Found) & CORRECTIVE MAINTENANCE: REMARKS: This valve has been overhauled, Calibrated and Cleared for area installation. Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh 1. Air leak test of actuator was found OK 2. Vlave body stud bolts were jammed with solidified urea 3. Seat, plug and cage were sent for machining. 4. Calibration 5. Sent for Hydrotesting DATE 04-05-2016 EXECUTED BY Adnan Hussain (Instrument Technician) VALVE BENCH SET FAIL SAFE ACTION Close SUPPLIED PRESSURE AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT Page 44 of 59
  • 48. CLIENT DATE: 04-05-2016 PROJECT DOC.NO. CV-E-034 CONTRACTOR JOB NO. F-689 VALVE INFORMATON: TAG NO: 11-TV-3004 SERVICE: Process Air SIZE: AREA: AMM-3 FLANGE TYPE: PHYSICAL CHECKS: Flowtronix (Pvt) Ltd. Overhauling and Calibrations Of Control Valves (Valve Record Sheet) Engro Fertilizers Limited Plant-II Shutdown 2016 AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT TEST RESULTS: CONDITIONS (As Found) & CORRECTIVE MAINTENANCE: REMARKS: This valve has been overhauled, Calibrated and Cleared for area installation. Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh 1. Air leak test of actuator was found OK 2. Overhauling 3. Valve bench set was found 4. Calibration 5. Sent for Hydrotesting DATE 04-05-2016 EXECUTED BY Adnan Hussain (Instrument Technician) VALVE BENCH SET FAIL SAFE ACTION Close SUPPLIED PRESSURE 55 AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT Page 45 of 59
  • 49. CLIENT DATE: 05-05-2016 PROJECT DOC.NO. CV-E-035 CONTRACTOR JOB NO. F-689 VALVE INFORMATON: TAG NO: 11-HV-2071A SERVICE: Process Air SIZE: 8 " AREA: AMM-3 FLANGE TYPE: FLG.RF(F) PHYSICAL CHECKS: Flowtronix (Pvt) Ltd. Overhauling and Calibrations Of Control Valves (Valve Record Sheet) Engro Fertilizers Limited Plant-II Shutdown 2016 AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT TEST RESULTS: CONDITIONS (As Found) & CORRECTIVE MAINTENANCE: REMARKS: This valve has been overhauled, Calibrated and Cleared for area installation. Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh 1. Air leak test of actuator was found OK 2. Overhauling 3. Valve bench set was found 4. Calibration 5. Sent for Hydrotesting DATE 05-05-2016 EXECUTED BY Adnan Hussain (Instrument Technician) VALVE BENCH SET FAIL SAFE ACTIONSUPPLIED PRESSURE AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT Page 46 of 59
  • 50. CLIENT DATE: 05-05-2016 PROJECT DOC.NO. CV-E-036 CONTRACTOR JOB NO. F-689 VALVE INFORMATON: TAG NO: 10-PV-1048 SERVICE: Process Air SIZE: 10 " AREA: AMM-3 FLANGE TYPE: PHYSICAL CHECKS: Flowtronix (Pvt) Ltd. Overhauling and Calibrations Of Control Valves (Valve Record Sheet) Engro Fertilizers Limited Plant-II Shutdown 2016 AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT TEST RESULTS: CONDITIONS (As Found) & CORRECTIVE MAINTENANCE: REMARKS: This valve has been overhauled, Calibrated and Cleared for area installation. Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh 1. Cleaning, Oiling and Polishing 2. Air Leak test of actuator was found OK 3. Seat and plug were sent for machining 4. All gaskets replaced 5. Diapharm was found torned 6. Diapharm replaced 7. Calibrated 8. Sent for Hydrotesting DATE 05-05-2016 EXECUTED BY Adnan Hussain (Instrument Technician) VALVE BENCH SET FAIL SAFE ACTIONSUPPLIED PRESSURE AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT Page 47 of 59
  • 51. CLIENT DATE: 05-05-2016 PROJECT DOC.NO. CV-E-037 CONTRACTOR JOB NO. F-689 VALVE INFORMATON: TAG NO: 11-FV-2056 SERVICE: Process Air SIZE: 10 " AREA: AMM-3 FLANGE TYPE: RTJ Flanges PHYSICAL CHECKS: Flowtronix (Pvt) Ltd. Overhauling and Calibrations Of Control Valves (Valve Record Sheet) Engro Fertilizers Limited Plant-II Shutdown 2016 AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT TEST RESULTS: CONDITIONS (As Found) & CORRECTIVE MAINTENANCE: REMARKS: This valve has been overhauled, Calibrated and Cleared for area installation. Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh 1. Air leak of acutator was tested and found OK 2. Calibration was tested and found OK 3. Cleaning, oiling and polishing was done 4. Sent for Hydrotesting DATE 05-05-2016 EXECUTED BY Adnan Hussain (Instrument Technician) VALVE BENCH SET FAIL SAFE ACTIONSUPPLIED PRESSURE AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT Page 48 of 59
  • 52. CLIENT DATE: 05-05-2016 PROJECT DOC.NO. CV-E-038 CONTRACTOR JOB NO. F-689 VALVE INFORMATON: TAG NO: 10-HV-1009 SERVICE: Process Air SIZE: 8 " AREA: AMM-3 FLANGE TYPE: Lenticular PHYSICAL CHECKS: Flowtronix (Pvt) Ltd. Overhauling and Calibrations Of Control Valves (Valve Record Sheet) Engro Fertilizers Limited Plant-II Shutdown 2016 AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT TEST RESULTS: CONDITIONS (As Found) & CORRECTIVE MAINTENANCE: REMARKS: This valve has been overhauled, Calibrated and Cleared for area installation. Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh 1. Actuator was found Leaked. 2. Dismantled single diapharm of actuator (outter most) 3. Body Overhauled 4. Calibrated 5. Sent for Hydrotesting DATE 05-05-2016 EXECUTED BY Adnan Hussain (Instrument Technician) VALVE BENCH SET FAIL SAFE ACTION Close SUPPLIED PRESSURE AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT Page 49 of 59
  • 53. CLIENT DATE: 05-05-2016 PROJECT DOC.NO. CV-E-039 CONTRACTOR JOB NO. F-689 VALVE INFORMATON: TAG NO: 11-LV-3011B SERVICE: Process Air SIZE: 18 " AREA: AMM-3 FLANGE TYPE: RF Flanges PHYSICAL CHECKS: Flowtronix (Pvt) Ltd. Overhauling and Calibrations Of Control Valves (Valve Record Sheet) Engro Fertilizers Limited Plant-II Shutdown 2016 AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT TEST RESULTS: CONDITIONS (As Found) & CORRECTIVE MAINTENANCE: REMARKS: This valve has been overhauled, Calibrated and Cleared for area installation. Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh 1. Air leak test of actuator was found OK 2. Overhauling of body 3. Plug, seat and cage were sent for machining 4. All three gaskets replaced 5. Calibrated 6. Sent for Hydrotesting DATE 05-05-2016 EXECUTED BY Mohammad Mubasher (Instrument Technician) VALVE BENCH SET FAIL SAFE ACTION Open SUPPLIED PRESSURE AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT Page 50 of 59
  • 54. CLIENT DATE: 05-05-2016 PROJECT DOC.NO. CV-E-040 CONTRACTOR JOB NO. F-689 VALVE INFORMATON: TAG NO: 11-LV-3011A SERVICE: Process Air SIZE: 18 " AREA: AMM-3 FLANGE TYPE: RF Flanges PHYSICAL CHECKS: Flowtronix (Pvt) Ltd. Overhauling and Calibrations Of Control Valves (Valve Record Sheet) Engro Fertilizers Limited Plant-II Shutdown 2016 AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT TEST RESULTS: CONDITIONS (As Found) & CORRECTIVE MAINTENANCE: REMARKS: This valve has been overhauled, Calibrated and Cleared for area installation. Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh 1. Air leak test of actuator was found OK 2. Overhauling of body 3. Valve plug, cage and seat were sent for machining 4. Cleaning, oiling and polishing were done to smoothen up the valve 5. Calibrated 6. Sent for Hydrotesting DATE 05-05-2016 EXECUTED BY Mohammad Mubasher (Instrument Technician) VALVE BENCH SET FAIL SAFE ACTION Open SUPPLIED PRESSURE AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT Page 51 of 59
  • 55. CLIENT DATE: 06-05-2016 PROJECT DOC.NO. CV-E-041 CONTRACTOR JOB NO. F-689 VALVE INFORMATON: TAG NO: 19-PV-9001A SERVICE: Process Air SIZE: 4 " AREA: AMM-3 FLANGE TYPE: RF Flanges PHYSICAL CHECKS: Flowtronix (Pvt) Ltd. Overhauling and Calibrations Of Control Valves (Valve Record Sheet) Engro Fertilizers Limited Plant-II Shutdown 2016 AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT TEST RESULTS: CONDITIONS (As Found) & CORRECTIVE MAINTENANCE: REMARKS: This valve has been overhauled, Calibrated and Cleared for area installation. Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh 1. Cleaning, Oiling and Polishing 2. Air Leak test of Actuator was found OK 3. Diapharm was found Ok 4. Overhauling of body and actuator 5. O-rings replaced 6. Seat, plug sent for machining 7. All gaskets replaced 8. Calibrated 9. Sent For Hydrotesting DATE 06-05-2016 EXECUTED BY Mohammad Mubasher (Instrument Technician) VALVE BENCH SET FAIL SAFE ACTIONSUPPLIED PRESSURE AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT Page 52 of 59
  • 56. CLIENT DATE: 06-05-2016 PROJECT DOC.NO. CV-E-042 CONTRACTOR JOB NO. F-689 VALVE INFORMATON: TAG NO: 19-FV-9002 SERVICE: Process Air SIZE: 8 " AREA: AMM-3 FLANGE TYPE: RF Flanges PHYSICAL CHECKS: Flowtronix (Pvt) Ltd. Overhauling and Calibrations Of Control Valves (Valve Record Sheet) Engro Fertilizers Limited Plant-II Shutdown 2016 AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT TEST RESULTS: CONDITIONS (As Found) & CORRECTIVE MAINTENANCE: REMARKS: This valve has been overhauled, Calibrated and Cleared for area installation. Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh 1. Air leak test of actuator was found OK 2. Overhauling of Body 3. Overhauling of Actuator 4. Seat and plug were sent for machining 5. Body gaskets replaced 6. Calibrated 9. Sent For Hydrotesting DATE 06-05-2016 EXECUTED BY Mohammad Mubasher (Instrument Technician) VALVE BENCH SET FAIL SAFE ACTION Close SUPPLIED PRESSURE 40 AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT Page 53 of 59
  • 57. CLIENT DATE: 08-05-2016 PROJECT DOC.NO. CV-E-043 CONTRACTOR JOB NO. F-689 VALVE INFORMATON: TAG NO: 11-FV-2028 SERVICE: Process Air SIZE: 4 " AREA: AMM-3 FLANGE TYPE: RF Flanges PHYSICAL CHECKS: Flowtronix (Pvt) Ltd. Overhauling and Calibrations Of Control Valves (Valve Record Sheet) Engro Fertilizers Limited Plant-II Shutdown 2016 AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT TEST RESULTS: CONDITIONS (As Found) & CORRECTIVE MAINTENANCE: REMARKS: This valve has been overhauled, Calibrated and Cleared for area installation. Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh 1. Cleaning, Oiling and Polishing 2. Air Leak test ok 3. Overhauling of Body 4. Overhauling of Actuator 5. Diaphram was found OK 6. O-Rings Replaced 7. Plug and seat sent for machining 8. Gland Packing Replaced 9. Calibrated 10. Sent For Hydrotesting DATE 08-05-2016 EXECUTED BY Mohammad Mubasher (Instrument Technician) VALVE BENCH SET FAIL SAFE ACTIONSUPPLIED PRESSURE AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT Page 54 of 59
  • 58. CLIENT DATE: 08-05-2016 PROJECT DOC.NO. CV-E-044 CONTRACTOR JOB NO. F-689 VALVE INFORMATON: TAG NO: 11-LV-2055 SERVICE: Process Air SIZE: 4-/-3-/-4 AREA: AMM-3 FLANGE TYPE: RTJ Flanges PHYSICAL CHECKS: Flowtronix (Pvt) Ltd. Overhauling and Calibrations Of Control Valves (Valve Record Sheet) Engro Fertilizers Limited Plant-II Shutdown 2016 AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT TEST RESULTS: CONDITIONS (As Found) & CORRECTIVE MAINTENANCE: REMARKS: This valve has been overhauled, Calibrated and Cleared for area installation. Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh 1. Cleaning, Oiling and Polishing 2. Air Leak test ok 3. Overhauling of Body 4. Overhauling of Actuator 5. Seat Replaced 6. Plug seal rings Replaced 7. Plug and Stem sent for machining 8. Gland Packing Replaced 9. Calibrated 10. Sent For Hydrotesting DATE 08-05-2016 EXECUTED BY Mohammad Mubasher (Instrument Technician) VALVE BENCH SET FAIL SAFE ACTION Close SUPPLIED PRESSURE AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT Page 55 of 59
  • 59. CLIENT DATE: 09-05-2016 PROJECT DOC.NO. CV-E-045 CONTRACTOR JOB NO. F-689 VALVE INFORMATON: TAG NO: 11-TV-5482 SERVICE: Process Air SIZE: AREA: AMM-3 FLANGE TYPE: PHYSICAL CHECKS: Flowtronix (Pvt) Ltd. Overhauling and Calibrations Of Control Valves (Valve Record Sheet) Engro Fertilizers Limited Plant-II Shutdown 2016 AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT TEST RESULTS: CONDITIONS (As Found) & CORRECTIVE MAINTENANCE: REMARKS: This valve has been overhauled, Calibrated and Cleared for area installation. Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh 1. Cleaning, Oiling and Polishing 2. Air Leak test ok 3. Actuator Diapharm replaced 4. Plug seal O-rings replaced 9. Calibrated 10. Sent For Hydrotesting DATE 09-05-2016 EXECUTED BY Mohammad Mubasher (Instrument Technician) VALVE BENCH SET FAIL SAFE ACTION Close SUPPLIED PRESSURE AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT Page 56 of 59
  • 60. CLIENT DATE: 10-05-2016 PROJECT DOC.NO. CV-E-046 CONTRACTOR JOB NO. F-689 VALVE INFORMATON: TAG NO: 11-TV-5476 SERVICE: Process Air SIZE: AREA: AMM-3 FLANGE TYPE: PHYSICAL CHECKS: Flowtronix (Pvt) Ltd. Overhauling and Calibrations Of Control Valves (Valve Record Sheet) Engro Fertilizers Limited Plant-II Shutdown 2016 AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT TEST RESULTS: CONDITIONS (As Found) & CORRECTIVE MAINTENANCE: REMARKS: This valve has been overhauled, Calibrated and Cleared for area installation. Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh 1. Cleaning, Oiling and Polishing 2. Air Leak test ok 3. Calibrated 4. Sent For Hydrotesting DATE 10-05-2016 EXECUTED BY Mohammad Mubasher (Instrument Technician) VALVE BENCH SET FAIL SAFE ACTIONSUPPLIED PRESSURE AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT Page 57 of 59
  • 61. CLIENT DATE: 10-05-2016 PROJECT DOC.NO. CV-E-047 CONTRACTOR JOB NO. F-689 VALVE INFORMATON: TAG NO: 11-HV-1032B SERVICE: Process Air SIZE: 1 " AREA: AMM-3 FLANGE TYPE: Flanged PHYSICAL CHECKS: Flowtronix (Pvt) Ltd. Overhauling and Calibrations Of Control Valves (Valve Record Sheet) Engro Fertilizers Limited Plant-II Shutdown 2016 AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT TEST RESULTS: CONDITIONS (As Found) & CORRECTIVE MAINTENANCE: REMARKS: This valve has been overhauled, Calibrated and Cleared for area installation. Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh 1. Cleaning, Oiling and Polishing 2. Air Leak test ok 3. Calibrated 4. Sent For Hydrotesting DATE 10-05-2016 EXECUTED BY Mohammad Mubasher (Instrument Technician) VALVE BENCH SET FAIL SAFE ACTIONSUPPLIED PRESSURE AIR FAILURE CORRECT PNEU./ELECT.CONN.CORRECT PLUG+SEAT MATERIAL CORRECT PLUG+SEAT SIZE CORRECT POSITIONER CORRECT BODY ARROW IN DIRECTION OF FLOW PROCESS CONN.CORRECT Page 58 of 59
  • 62. Overhauling and Calibrations Of Control Valves 7. PICTURES (Work In Progress): Page 59 of 59