2. Fiber Design Efficiencies cost savings
1. Drive teams dispatched to drive up
and down streets in a target area to
determine Aerial vs. Underground
construction
2. Drive teams sketch proposed routes
and send to CAD to create prelim
field drawings, usually takes weeks to
convert field notes to actual drawings
for the field
3. After prelim route drawings created
in CAD drive teams re dispatched to
collect pole data & construction
details for CDs
4. Field data collected sent in to
complete pole applications, ROW
permits and to the CAD Dept. to
create a set of actual Construction
Drawings
1. Aerial vs. Underground assessment
completed via raster images
embedded in GIS mapping takes days
vs. weeks or months
2. Route drawings are created in
mapping as part of the assessment
process. A few clicks and you print
scaled field drawings for survey
teams.
3. The scaled GIS drawings go to the
field so teams can collect pole data &
verify underground constructability.
4. Field data can be collected and input
electronically to create CDs. Mapping
utilities can auto complete pole
applications, determine
municipalities to contacted for
permits.
Traditional Method Our Approach
3. Aerial & Underground Fiber Build Cost Synopsis
Some communications providers have excess fiber strands. Fiber count in cables ranges from 6 to
24 near residences and individual businesses to more than 1,000 on backbone routes. The cost of
a 6-count fiber cable is $2,000 per mile, while an 864-count cable is $50,000 per mile, implying a
marginal cost of approximately $50 per fiber per mile. Actual costs for fiber purchase or lease, of
course, reflect market costs and depend on the total availability of fiber over the route–and are
thus, typically, considerably higher; however, fiber lease or purchase may be a serious
consideration over routes where construction is difficult or costly and considerable fiber has
already been installed (e.g., river crossings, tunnels).
Aerial Versus Underground Typical construction is a mixture of aerial and underground
techniques. Aerial construction can be completed for $20,000 per mile. Aerial construction may
be more expensive when poles are crowded or when the utility pole owner charges high rates for
access. Worst-case costs can be $100,000 per mile (which usually would lead a network owner to
build underground or over another route). Underground construction also has a wide cost range.
In areas where restoration is not important and long continuous runs are possible (e.g., rural
areas, in dirt, on the side of interstate roads), “plowing” the fiber into the ground is an
inexpensive option— approximately $40,000 per mile. In more built-up areas, directional boring
is necessary, because it is less destructive to the right-of-way and requires less restoration. Boring
is more expensive, approximately $60,000 to $100,000 per mile. Boring also limits the amount of
cable and conduit that can be built. (Two 2-inch conduit is a typical limit, corresponding to four
medium-sized fiber optic cables.)
4. Drawings created in GIS mapping software. Right of Way, Geography and Demographic
Spatial data is imported and analyzed to make the business case. Please note the
elaborate geocompression analytical tools in the drop down window
A few clicks and we print scaled field drawings for teams to drive.
5. Aerial vs. Underground route assessments are completed using embedding
Raster images translucently in the background of our GIS mapping software.
Screen shot below shows a mile high view of a given target area. GIS designs eliminates the need for field teams driving every
road in the area to see if poles exist on streets for aerial route planning. Red dots are poles for aerial placement, blue dots are
vault placements for underground routes (purple lines).
6. Screenshot below is zoomed into the center of previous mile high Raster imagery view. Designing
in a virtual world significantly reduces overall engineering time and cost.
How we use imagery to find existing poles for aerial cable routing.
7. Screenshot below is zoomed into an underground portion to show level of detail
available to accurately design UG paths and structure placement.
Using Raster images embedded translucently in ESRI GIS allows the drafter is able to see actual field conditions as they plan routes and
placement of PON cabinets and underground structures. Traditionally this was done in CAD. All the drafter saw was black and white ROW &
pavement lines. All too often these structures were drawn in middle of sidewalks or other places they couldn’t be installed. The ole “looks
good on paper” was not an efficient method of network drawing creation .
8. Below depicts how we use Google Earth or Bing street view feature to conduct a
virtual survey of planned routes. In doing so we assess the extent of aerial make ready
and identify UG constructability issues.
Note this street is very light make ready (only one cable attached) and has existing UG fiber. You can see the fiber optic
cable marker post.
9. Electronic pole data collection for aerial attachments.
The attachments can be captured via (DMT) Digital Measuring Technology. We can import
electronic pole data to GIS using ESRI conversion tools.
Below is example of the Ocalc system
Osmose developed for the RBOC ‘s.
Below is GE’s answer to the
Osmose product offering
10. GIS data exported to auto populate pole sheets and attachment applications reducing
field survey costs.
The data can be collected manually (shown below) or electronically . If collected manually we
insert spreadsheet data to mapping via layer attributes.
11. GIS mapping utilities also determine municipalities, agencies and pole owners to be
contacted for cable attachments, ROW, zoning and permitting.
Below is a sample Verizon Pole Application
Below is a typical neighborhood
demographic shown in spatial data