SlideShare une entreprise Scribd logo
1  sur  15
Télécharger pour lire hors ligne
G.U.P PHASE II - LIQUID PIPELINES, TERMINAL & JETTIES




                             TABLE OF CONTENTS


1.0   INTRODUCTION

2.0   SUMMARY

3.0   SOIL RESISTIVITY SURVEY

4.0   DESIGN PARAMETERS

5.0   CATHODIC PROTECTION DESIGN CALCULATIONS




                                                                        Page 2 of
G.U.P PHASE II - LIQUID PIPELINES, TERMINAL & JETTIES



       1.0     INTRODUCTION

              This report defines the design calculations and requirements of Cathodic Protection System
              for one No. 17" existing gas pipeline and three new LPG product pipelines. An impressed
              current cathodic protection system will be installed to supplement the' corrosion coating in
              providing corrosion control to the pipeline. The impressed current Cathodic Protection
              system for existing gas pipeline will be upgraded to suit the new requirement for existing
              gas pipeline as well as new LPG product pipelines.

       2.0     SUMMARY

               Cathodic protection is specified for the onshore section of the subject pipeline from Dinh
               Co to Thi Vai for new LPG pipeline and from Long Hi to Phu My for existing gas pipeline-
              length and other parameters are as given in Secsion 4.0 of this document. Both galvanic
              anode and impressed current cathodic protection systems were considered during this
0             design. An impressed current cathodic protection system has been selected on a technical
              basis. The cathodic protection system has been designed in accordance with internationally
              accepted standards and compliance the codes and standards listed in section 1.2           o
              specification. A conservation design approach has been used including a 30 mA/m2 current
              density and 95% coating efficiency. For future addition a 20% spare output capacity has
              been provided ( NACE-1967). It has been determined that a single impressed current
              system required upgrading at the Phuoc Hoa LBV and at the Dinh Co Station would
              provide full cathodic protection of new LPG pipelines and existing gas pipelines.

              The soil resistivities at this location justified the installation of an effective surface anode
              groundbed. The groundbed will be located approximately 100              m from the pipeline and
              position perpendicularly to the pipeline in accordance with the --project specification
              (BS-7361 ). A rectifier will be used to energize the groundbed. They.415. VAC; three phases
              power supply to the rectifier will be provided from the�415;volt switchboard. Elec€rical
              isolation of the pipeline will be provided by the installation of insulating flange sets
c:            Insulating flange set shall be provided with Explosion-proof surge diverters to prevent
              damage due to lightning or power surges. Test stations will be provided to monitor and
              adjust the cathodic protection system . Test station also have to be provided at following
             location
             • Both side of the major river or road crosing.
             • At all insulating joint.
             • At HT overhead line crossing.
             • At all vulnerable location where interferance is possible
             These test stations will be located at maximum intervals of 1.5 km. All cable connections to
             the pipeline will be made using the brassing thermit weld process.

     3.0     SOIL RESISTIVITY SURVEY

             Soil resistivity measurements have been previously carried out by others at 65    location
             along the pipeline ROW. According to the information included in the contract documents.
             this testing was performed using the Wenner 4-pin method at depth of 0.75, 1.5, and
             metres using a .M-416 instrument made in the Soviet Union. Test equipment must have
             maximum AC & DC ground current rejection feature. Soil resistivities are critical to the
             proper design of a cathodic protection system. They are used as a guide to determine the
     P9-CPS.05-01.0                                                                               Page of I
G.U.P PHASE II - LIQUID PIPELINES, TERMINAL & JETTIES



        corrosiveness of the soil and also used to select ground locations and configurations. Soil
        resistivities are important regardless of whether and impressed current or a sacrificial anode
        cathodic protection system is utilized. It should be understood that this cathodic protection
        design has been based on the soil resistivities determined by others. Any inaccuracies in the
        reported resistivity values versus the actual resistivity values could have a significant impact on
        the effectiveness of the cathodic protection system. This can only be determined during
        commissioning of the system when the Contractor shall check the.soil resitivity inspection
        accordance with specification.

4.0     DESIGN PARAMETERS

        The following sub-sections include parameters which have been used for design of the
        proposed cathodic protection system.

4.1    GENERAL PIPELINE DETAILS

       These calculation for upgrading existing CP system for new LPG pipelines and existing gas
       pipeline will be done through two (2) cathodic protection system design.

4.1.1 Portion 1: (CP Station at Dinh Co location )

Y      Gas pipeline (Long Hai to Ba Ria)

       Length of pipeline                16.5 km             a
       Pipeline diameter                 406.4 mm      1 /17
       Pipeline number                   1
       Coating                           Coal tar enamel

•      LPG pipelines (Dinh Co to Ba Ria)

       Length of pipeline                7.5 km
       Pipeline diameter                 168 mm         C L�
       Pipeline number                   3
       Coating                           Polyethylene

4.1.2 Portion 2: (CP Station at Phuoc Hoa location )

       Gas pipeline (Ba Ria to Phu My)

      Length of pipeline                 21.5 km
      Pipeline diameter                  426 mm
      Pipeline number
      Coating                            Coal tar enamel

      LPG pipelines (Ba Ria to Thi Vai)

      Length of pipeline                 17 km
      Pipeline diameter                  168 mm
      Pipeline number                    3
                                                                                           Page 4 of I '
P9-CPS.05-01.0
Rev. D   /,(
G.U.P PHASE II - LIQUID PIPELINES, TERMINAL & JETTIES



         Coating                        Polyethylene

 4.2     CATHODIC PROTECTION DESIGN LIFE

        In accordance with the contract documents, the impressed current cathodic protection
        system will have a design life of 30 years. The cathodic protection Contractor shall
        demonstrate the design life of his proposed CP system.

 4.3    ANODE TYPE

       1 T' 'um tubular anodes with a mixed metal oxide coating will be installed. These anodes
       have proven to have superior operating characteristics over silicon iron and graphite anodes.
       Titanium / mixed metal oxide anode are also of lighter weight and capable of significantly
        higher current outputs and longer life.

 4.4    COATING EFFICIENCY

        A common method to assess the pipe coating condition is to use a factor referred to
       "percent bare". For a normal factory applied coaltar enamel coating system which would be
       inspected and repaired prior to back filling. of the pipe, a value of a approximately I to 2
       percent bare would be experienced immediately subsequent to construction. However,
       during the service life of the pipeline with expansion and contraction of the pipeline due to
       thermal effects, soil movement, water ingress through the coating etc, the condition of the
       coating will deteriorate.

       A conservative coating efficiency of 95% has been used for this cathodic protection design.
       This means that over the 30 year life, the cathodic protection system will have the capacity
       protect an average of 5% of the total surface area of the pipeline.

 4.5   CP CURRENT DENSITY

       The National Association of Corrosion Engineers (NACE) Recommended practice
       RP-0169-92 and DNV RP B401 specifies a current density of 10-30 mA/m2 for bare steel
       structures in soil. The soils along the proposed ROW for this pipeline are very aggressive
       with high moisture content, high salinity and low soil resistivity. Therefore, this design uses
       a
       conservative 30 mAIm2 current density.

4.6    SOIL RESISTIVITY

4.6.1 Dinh Co Location

       As mentioned in previous Section 3.0, soil resistivity testing along the pipeline ROW has
       been previously carried out by others. A review of this data indicates that points R-18 and
       R-19 are located relatively near Dinh Co:

                       Depth (m)                       Soil Resistivity (ohm cm)
                       R-18
                       0.75                                   8000
                       1.50                                   4200

P9-CPS.05-01.0                 .
                                                                                         Page 5 of 14
G.U.P PHASE II - LIQUID PIPELINES, TERMINAL & JETTIES


                            3.00                                  1050
                            R-19
                            0.75                                  3600
                            1.50                                  1300
                            3.00                                  500

        The deep-well anode system will be installed for cathodic protection, The average resistivity
        value for the above two points at a   1.5m depth is 2750 ohm-cm and will be used t For
        groundbed design at Dinh Co.

 4.6.2 Phuoc Hoa Location

        Also mentioned in previous Section 3.0, soil resistivity testing along the pipeline ROW has
        been previously carried out by others. A review of this data indicates that points BH23 aid
        BH24 are located relatively near Ba Ria ( at Phuoc Hoa ) where the impressed current CP
        system will be located. The soil resistivity values reported at these locations are :

                           Depth (m)                      Soil Resistivity (ohm ern)

                           BH23
                           0.75                                  1300
                           1.50                                  1500
                           3.00                                  1000

                           BH24
                           0.75                                  1500
                           1.50                                  1500
                           3.00                                  800

       The average resistivity value for the above two points at a 1.5m depth is 1500 ohm-cnl _:d
       will be used for groundbed design at Phuoc Hoa.

4.7    CATHODIC PROTECTION CRITERIA

       NACE Recommended Practice RP-0169-92                 addresses cathodic protection criteria --Dr
       underground and submerged metallic piping systems. Applicable excerpts of this st.and=d
       relative to CP criteria for this project are as follows-

                 A negative (cathodic) potential of at least     85OmV with the cathodic protecti'Dn
                 applied. This potential is measured with respect to a saturated copper / copper ulfat.e
                 reference electrode contacting the electrolyte. Voltage drops other than those across
                 the structure to electrolyte boundary must be considered for valid interpretation of
                 this voltage measurement.

                 A negative polarized potential of at least   850 mV relative to a saturated copper   /
                 copper sulfate reference electrode.




P9-CPS.05-01.0
G.U.P PHASE II - LIQUID PIPELINES, TERMINAL & JETTIES



              A minimum of 100 mA of cathodic polarization between the structure surface and a
              stable reference electrode contacting the electrolyte. The formation or decay of
              polarization can be'measured to satisfy this criterion.

 5.0    CATHODIC PROTECTION DESIGN CALCULATIONS

 5.1    DINH CO LOCATION

 5.1.1 Pipeline Total Surface Area

        The onshore portion of Long Hai to Ba Ria gas pipeline and Dinh Co to Ba Ria LPG
        pipelines has a total surface area as follows:

                       Sa      =        (Pi) (d) (1)
                       Sa               (3.1416)-[(0.406,x 16500) + (3 x 0.168 x 7500)]
                       Sa      =        32921 (m2)

        Where:         Sa      =        Surface area (m2 )
                       Pi      =        3.1416
                       1                Length of pipeline (m)
                                        Diameter of pipeline (m)

5.1.2   CATHODIC PROTECTION CURRENT REQUIREMENT

        The cathodic protection system will have a DC output capacity as follows:

                                         (Sa) (Id) (Cb)
                       It                                 ZSF
                                             1000
                                        (32921) (30) (0.05)
                       It                                     X1.1
                                                1000

                       It     =         54.32 (A)

                       Say 55 amperes

        Where:         Sa               Total surface area (m2 )
                       Id     =         CP current density (mA/m2 )
                       Cb     =         Coating breakdown factor (%)
                       SF     =         Safety factor (1.1)


5.1.3   CATHODIC PROTECTION ANODE REQUIREMENT

        Chosen output rating of 2 Ampere for each anode, the number of anodes:

                       N      =        It/2   =           54.32/2      =    27.16
        No. of anodes based on current requirement

                                                                                          Page 7 of 14



m.1
G.U.P PHASE II - LIQUID PIPELINES, TERMINAL & JETTIES


                         N          =        30
          Another, maximum anode current output for each anodeto be determined as follows :
                         LogL= 3.3 - LogId
          Where :        L = design life in years
                         Id = Maximum anode current density (A/m2 )
          For L = 3 0 years
          The anode has a dimension of 31.75mm dia x I000mm legth with a.total area of 0.1m2
          Therefore,     Id =.66.5 A/m2
          Maximum current output of anode = 0.1m2 x 66.5 A/m2 =6.65A
          Hence 3 0 anodes will give 6.65 x3 0 = 199.5 A > Required 54.3 2 A
                                                                (0) (It)(y)
         noe wegt requ id re        ,        W          =
                                                                    Uf

                                                                0.1 (54.32) (30)
                                             W
                                                               0.6
                                       W      =         271.6 kg
         Anodes No. required based on weight requirement :
                                       N               W/Wa
                                                       271.6 / 20
                                                       13.6
         No. of anodes based on weight requirement, N = 14
         Where          Q              Anode consumption rate (kg/amp-year)
                        It     =       Cathodic Protection current ( A )
                        Y      =       Design life of the system ( years )
                        Uf     =       Anode Utilization factor ( 0.6 for a conservative design )
                        Wa     =      Weight of individual anode ( kg )
         Hence anode No. chosen is 30

         There are 20 canister anodes in existing groundbed at Dinh Co, so that 10 canister anodes
         which are the same existing anode specification will be required to add in this location.

5.1.4 GROUNDBED RESISTANCE

         Installation of 30 canister anodes on 5 metre spacing in 2750 ohm-cm soil results in an
         estimated groundbed resistance of 0.5844 ohm as follows:

                Rn      =          RI   + R2            ( NACE - 1967, page 95 )

                Where              Rl               Anode to backfill resistance
                                   R2               Backfill to soil resistance

                                        Pb              BLcr - 1+ 2La
                R1                                [In                 In(0.656N)])     { NACE - 1967 )
                                   N.yLcrx6.28          do        S

                                                              .- I + (2)(100)
                R1' =                    50        Fn (8)(100)                ln(0.656)(30)]
                                   (30)(100)(6.28)      3175            500

                Ri                 0.0152 (ohm)

Rev. D
                               -
G.U.P PHASE II - LIQUID PIPELINES, TERMINAL & JETTIES




 Where:             Pb             Backfill resistivity (ohm-cm)
                    La     =       Length of anode- excluding backfill (cm)
                    da     =       Diameter of anode- excluding backfill (cm)
                    S      =       Spacing of anodes (cm)
                    N              Number of anodes..


                                         Ps            8Lc -1 + 2Lc
                    R2                           [In                     In(0.656N)J)               (NACE - 196J )
                                    NxLcx6.28          do          S

                                          2750              (8) (150)          (2) (150)
                    R2                                                  -1 +               in(0.656)(30)J
                                    (30)(150)(6.28) [in       76                 500

                    R2     =       0.5692 (ohm)


 Where:             Ps             Soil resistivity (ohm-cm)
                    Lc             Length of anode- including backfill (cm)
                    dc             Diameter of anode- including backfill (cm)
                    S.             Spacing of anodes (cm)
                                   Number of anodes.

Hence               Rn    =        0.0152 + 0.5692
                                   0.5844 (ohm)


5.1.5 TRANSFORMER RECTIFIER DC OUTPUT VOLTAGE

          It is estimated that the transformer rectifier will require a 45             volt output to achieve :Lie
          desired 54.32 ampere DC current output as follows:

                                           It.(Rn+Rc) + Bemf
                          E                54.32x(0.5844 + 0.2) + 2
                          E                44.6 volts

                          Say     45 volts

          Where :         E               Rectifier DC output voltage (volts)
                          It      =       Rectifier output current (amp)
                          Rn      =       Total groundbed resistance (ohm)
                          Rc              Total cable resistance (0.2 ohm)
                          Bemf =         Dropped voltage between pipeline and ground (-2.0 volts)
          Note : Pipe to earth resistance (Rpe) has not been considered since the coating resistari :e is so
          high.( >1010 ohm-mz ) that all current will pass through 5% bare areas through r±e pipeline
          coating.




Rev. D
G.U.P PHASE II - LIQUID PIPELINES, TERMINAL & JETTIES


 5.1.6 TRANSFORMER RECTIFIER AC INPUT

           Actual DC power output required       :       Pd = 44.6 x 55.32
                                                               2422.672 (W)
           DC power requirement including 20% overvoltage provision (20% spare Capacity )
                          = 1.2x44.6x54.32=2907.2         (W)
           Now, considering overall system P.F (power factor) = 0.8
           and Transformer Rectifier Unit efficiency (E.F) = 0.85 (85% )
           For 3 phases, 415V, 50Hz supply input to Transformer Rectifier Unit :
           Input current

                                                 2907.2
                             Ip
                                            Jx415x0.8x0.85

                             Ip     =      5.95 A

          Hence, AC power input ( including 20% spare capacity) is :
                                       43 x 415 x 5.95 x 0.8
                                           3420.23 Watt

 5.1.7    CHANGE IN EARTH POTENTIAL DUE TO FORCED DRAINAGE

          When CP current is injected into ground through anode bed, the current flow results          in a
          potential gradient in the earth.                                            _...

          The change in earth potential near the pipelines

                                           (Ps)(It)
                          V        =
                                            27r(r)


                                           (2750)(54.32)
                         V
                                             27zx10000

                                          2.38 Volts
          Where :        Ps               Soil resistivity ( ohm-cm )
                         It               Cathodic Protection current ( Ampere )
                         r                Distance between pipeline and anode bed (cm )

5.2      PHUOC HOA LOCATION

5.2.1 Pipeline Total Surface Area

         The onshore portion of Ba Ria to Phu My gas pipeline and Ba Ria to Thi Vai LPG pipelines
         has a total surface area as follows:

                         Sa        _      (Pi) (d) (1)
                         Sa               (3.1416) [(0.426 x 21.500)+ (3 x 0.168 x 17000)]
                         Sa        =      55691 (m2 )

P9-CPS.05-01.0                                                                               Page 10 of 14
G.U.P PHASE I1- LIQUID PIPELINES, TERMINAL & JETTIES




             Where:             Sa                    Surface area (m2 )
                                Pi                    3.1416
                                I                     Length of pipeline (m)
                                                      Diameter of pipeline (m)

   5.2.2     CATHODIC PROTECTION CURRENT REQUIREMENT

             The cathodic protection system will have a DC output capacity as follows:




                      ( Sa ) * Id * Cb
              It =                     xSF
                            1000
                     ( 55691 ) * 30 * 0 . 05
              It =                           x1 . 1
                            1000

                                                  It = 91.89 A
                               Say 92 amperes

            Where:             Sa                Total surface area (m2 )
                               Id       =        CP current density (mA/m2 )
                               Cb       =        Coating breakdown factor (%)
                               SF       =        Safety factor (1.1)

 5.2.3 CATHODIC PROTECTION ANODE REQUIREMENT

           Chosen output rating of 2 Ampere for each anode, the number of anodes:

                          N       =       It/2                     92/2    =         45.95
           No. of anodes based on current requirement

                           N      =        50
           Another, maximum anode current output for each anodeto be determined as follows :
                          LogL=3.3 -Log Id
           Where :        L = design life in years
                          Id = Maximum anode current density ( A/m2 )
           For L = 30 years
           The anode has a dimension of 31.75mm dia x 1000mm legth with a total area of 0.1m2
           Therefore,    Id = 66.5 A/m2
           Maximum current output of anode = 0.1 m2 x 66.5 A/m2 = 6.65A
           Hence 50 anodes will give 6.65 x 50 = 332.5 A > Required 92 A
                                                                   (Q)(It)(Y)
           Anode weight required,               W          =           Uf

                                                                   (0.1) (92) (30)
                                                W
                                                                       0.6
                                                          =       460 kg

Rev. D                                                                                       Page I 1-of 14-
G.U.P PHASE II - LIQUID PIPELINES, TERMINAL & JETTIES

                Anodes No. required based on weight requirement :
                                             N       =      W / Wa
                                                                          460 / 20
                                                                          23
                No. of anodes based on weight requirement, N = 23
                Where          Q      =       Anode consumption rate (kg/amp-year )
                               It     =       Cathodic Protection current (A )
                               Y      =       Design life of the system ( years )
                               Uf     =       Anode Utilization factor ( 0.6 for a conservative design
                                     Wa      =         Weight of individual anode ( kg )

               Hence anode No. chosen is 30

               There are 20 canister anodes in existing groundbed at Phuoc Hoa, so that 30 canister
               anodes which are the same existing anode specification will be required to add in this
               location.

      5.2.4    OROUNDDED RESISTANCE

              Installation of 50 canister anodes on 5 metre spacing in        1500 ohm-cm soil results in an
              estimated groundbed resistance of 0.19 ohm as follows:
                      Rn =            R1 + R2
                      Where           R1      =       Anode to backfill resistance
                                      R2              Backfill to soil resistance
  R1=

           Pb              8 La     2 La               
      N × La × 6 . 28    Ln da − 1 + S (ln 0 . 656 N ) 
                                                       

R1=
              50              8 * 100     2 * 100                    
                            Ln         −1+         (ln 0 . 656 * 50 ) 
        50 × 100 × 6 . 28 
                              3 . 175       500                      

                                             R1 = 0.0094 Ohm

  Where:                Pb                 Backfill resistivity (ohm-cm)
                                           Length of anode- excluding backfill (cm)
                        La       =
                                           Diameter of anode- excluding backfill (cm)
                        da       =
                                           Spacing of anodes (cm)
                        S        =
                                           Number of anodes.
                        N        =
R2=

        Pb                    8 Lc    2 Lc               
   N × Lc × 6 . 28         Ln dc − 1 + S (ln 0 . 656 N ) 
                                                         
                                     R2 =

               50                   8 * 150      2 * 150                 
         50 × 150 × 6 . 28       Ln 3 . 175 − 1 + 500 (ln 0 . 656 * 50 ) 
                                                                         


                                     R2= 0.196 (ohm)

 Where:.             Ps     =        Soil resistivity (ohm-cm)
                     Lc     =        Length of anode- including backfill (cm)
                     dc              Diameter of anode- including backfill (cm)
                     S               Spacing of anodes (cm)
                                     Number of anodes.

Hence                Rn              0.0094 + 0.196
                                     0.2054 (ohm)

5.2.5 TRANSFORMER RECTIFIER DC OUTPUT VOLTAGE

         It is estimated that the transformer rectifier will require a 42 volt output to achieve
the desired 92mpere DC current output as follows:

                                            It.(Rn+Rc) + Bemf
                           E                92 x (0.2054 + 0.2) + 2
                           E                39.29 volts

                           Say      42 volts

           Where.:         E                Rectifier DC output voltage (volts)
                           it       =       Rectifier output current_ (amp)
                           Rn       _       Total groundbed resistance (ohm)
                           Rc       =       Total cable resistance (0.2 ohm)
                           Bemf     =       Dropped voltage between pipeline and ground (-2.0
volts)

        Note : Pipe to earth resistance (Rpe ) has not been considered since the coating
resistance
        is so high ( >1010 ohm-nag ) that all current will pass through 5% bare areas
through the
        pipeline coating.




5.2.6 TRANSFORMER RECTIFIER AC INPUT

          Actual DC power output required        :     Pdc = 39.29 x 92
                                                              3614.68 ( W)
DC power requirement including 20% overvoltage provision (20% spare Capacity)
                  = 1.2x39.29x92=4337.6      (W)
Now, considering overall system P.F ( power factor) = 0.8
and Transformer Rectifier Unit efficiency (E.F) = 0.85 ( 85% )
For 3 phases, 415V, 50Hz supply input to Transformer
Rectifier Unit : Input current

IP=
       4337 . 6
  3 x 415 x 0 . 8 x 0 . 85

               Ip       =8.875 A


Hence, AC power input ( including 20% spare capacity) is :
         -                     _

      3 x 415 x 8 . 875 x 0 . 8 = 5013 W
:
                        G.U.P PHASE II - LIQUID PIPELINES, TERMINAL & JETTIES



5.2.7   CHANGE IN EARTH POTENTIAL DUE TO FORCED DRAINAGE

        When CP current is injected into ground through anode bed, the current flow results in a
        potential gradient in the earth.

        The change in earth potential near the pipelines

                                           (Ps)(It)
                                            2 r(r)

                                           (1500)(92)
                        V       =
                                            2πxl0000

                                           = 2.2 Volts

        Where :         Ps      =          Soil resistivity ( ohm-cm )
                        It      =          Cathodic Protection current ( Ampere )
                        r       =          Distance between pipeline and anode bed ( cm )




                                                                                            Page 14 of 14

Contenu connexe

Similaire à Thiet ke duong_ong_tren_bo

Thiết kế đường ống trên bờ
Thiết kế đường ống trên bờThiết kế đường ống trên bờ
Thiết kế đường ống trên bờVcoi Vit
 
20392769 design-calculation-cathodic-protection-impressed-cureent-system
20392769 design-calculation-cathodic-protection-impressed-cureent-system20392769 design-calculation-cathodic-protection-impressed-cureent-system
20392769 design-calculation-cathodic-protection-impressed-cureent-systemAdeoye Okunoye
 
20392769 design-calculation-cathodic-protection-impressed-cureent-system
20392769 design-calculation-cathodic-protection-impressed-cureent-system20392769 design-calculation-cathodic-protection-impressed-cureent-system
20392769 design-calculation-cathodic-protection-impressed-cureent-systemAdeoye Okunoye
 
Cathodic Protection For Oil Wells
Cathodic Protection For Oil WellsCathodic Protection For Oil Wells
Cathodic Protection For Oil WellsAbinash Padhy
 
AME POWER PLANT REFERENCES
AME POWER PLANT REFERENCESAME POWER PLANT REFERENCES
AME POWER PLANT REFERENCESCarlo Avanzini
 
Corrosion control
Corrosion controlCorrosion control
Corrosion controlDuy Vu
 
Cathodic Protection for Above Ground Storage Tanks (AGSTs)
Cathodic Protection for Above Ground Storage Tanks (AGSTs) Cathodic Protection for Above Ground Storage Tanks (AGSTs)
Cathodic Protection for Above Ground Storage Tanks (AGSTs) Audubon Engineering Company
 
Corrosion Control Project
Corrosion Control ProjectCorrosion Control Project
Corrosion Control ProjectDil Nawaz
 
An Example for Borehole Seismology in Marmara Sea
An Example for Borehole Seismology in Marmara SeaAn Example for Borehole Seismology in Marmara Sea
An Example for Borehole Seismology in Marmara SeaAli Osman Öncel
 
City gas distribution- Complete Overview
City gas distribution- Complete OverviewCity gas distribution- Complete Overview
City gas distribution- Complete OverviewUjjwal Rao
 
Shyam cable catalogue
Shyam cable catalogueShyam cable catalogue
Shyam cable catalogueuibsamit87
 
Standards_Technical Seminar for Cathodic Protection to GOGC Design.pdf
Standards_Technical Seminar for Cathodic Protection to GOGC Design.pdfStandards_Technical Seminar for Cathodic Protection to GOGC Design.pdf
Standards_Technical Seminar for Cathodic Protection to GOGC Design.pdfSergeRINAUDO1
 
PPEJ.090.2010 rev2
PPEJ.090.2010 rev2PPEJ.090.2010 rev2
PPEJ.090.2010 rev2Rahmat Riski
 

Similaire à Thiet ke duong_ong_tren_bo (20)

Thiết kế đường ống trên bờ
Thiết kế đường ống trên bờThiết kế đường ống trên bờ
Thiết kế đường ống trên bờ
 
20392769 design-calculation-cathodic-protection-impressed-cureent-system
20392769 design-calculation-cathodic-protection-impressed-cureent-system20392769 design-calculation-cathodic-protection-impressed-cureent-system
20392769 design-calculation-cathodic-protection-impressed-cureent-system
 
20392769 design-calculation-cathodic-protection-impressed-cureent-system
20392769 design-calculation-cathodic-protection-impressed-cureent-system20392769 design-calculation-cathodic-protection-impressed-cureent-system
20392769 design-calculation-cathodic-protection-impressed-cureent-system
 
Cp1
Cp1Cp1
Cp1
 
MC _ CP Rev.0.pdf
MC _ CP Rev.0.pdfMC _ CP Rev.0.pdf
MC _ CP Rev.0.pdf
 
SLIDES
SLIDESSLIDES
SLIDES
 
01_WP-CPL_0608_LR
01_WP-CPL_0608_LR01_WP-CPL_0608_LR
01_WP-CPL_0608_LR
 
KNPC Volume 3B.pdf
KNPC Volume 3B.pdfKNPC Volume 3B.pdf
KNPC Volume 3B.pdf
 
Cathodic Protection For Oil Wells
Cathodic Protection For Oil WellsCathodic Protection For Oil Wells
Cathodic Protection For Oil Wells
 
AME POWER PLANT REFERENCES
AME POWER PLANT REFERENCESAME POWER PLANT REFERENCES
AME POWER PLANT REFERENCES
 
Corrosion control
Corrosion controlCorrosion control
Corrosion control
 
Cathodic Protection for Above Ground Storage Tanks (AGSTs)
Cathodic Protection for Above Ground Storage Tanks (AGSTs) Cathodic Protection for Above Ground Storage Tanks (AGSTs)
Cathodic Protection for Above Ground Storage Tanks (AGSTs)
 
Boiler Operation and Maintenance Experiences
Boiler Operation and Maintenance ExperiencesBoiler Operation and Maintenance Experiences
Boiler Operation and Maintenance Experiences
 
Annual Report-2015-Hybrid-2
Annual Report-2015-Hybrid-2Annual Report-2015-Hybrid-2
Annual Report-2015-Hybrid-2
 
Corrosion Control Project
Corrosion Control ProjectCorrosion Control Project
Corrosion Control Project
 
An Example for Borehole Seismology in Marmara Sea
An Example for Borehole Seismology in Marmara SeaAn Example for Borehole Seismology in Marmara Sea
An Example for Borehole Seismology in Marmara Sea
 
City gas distribution- Complete Overview
City gas distribution- Complete OverviewCity gas distribution- Complete Overview
City gas distribution- Complete Overview
 
Shyam cable catalogue
Shyam cable catalogueShyam cable catalogue
Shyam cable catalogue
 
Standards_Technical Seminar for Cathodic Protection to GOGC Design.pdf
Standards_Technical Seminar for Cathodic Protection to GOGC Design.pdfStandards_Technical Seminar for Cathodic Protection to GOGC Design.pdf
Standards_Technical Seminar for Cathodic Protection to GOGC Design.pdf
 
PPEJ.090.2010 rev2
PPEJ.090.2010 rev2PPEJ.090.2010 rev2
PPEJ.090.2010 rev2
 

Dernier

Best Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in IndiaBest Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in IndiaShree Krishna Exports
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Dave Litwiller
 
Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...Roland Driesen
 
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetCreating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetDenis Gagné
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Servicediscovermytutordmt
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst SummitHolger Mueller
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableDipal Arora
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Centuryrwgiffor
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxWorkforce Group
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...anilsa9823
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMANIlamathiKannappan
 
Grateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfGrateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfPaul Menig
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Roland Driesen
 
Call Girls In Holiday Inn Express Gurugram➥99902@11544 ( Best price)100% Genu...
Call Girls In Holiday Inn Express Gurugram➥99902@11544 ( Best price)100% Genu...Call Girls In Holiday Inn Express Gurugram➥99902@11544 ( Best price)100% Genu...
Call Girls In Holiday Inn Express Gurugram➥99902@11544 ( Best price)100% Genu...lizamodels9
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.Aaiza Hassan
 
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876dlhescort
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Serviceritikaroy0888
 
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyThe Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyEthan lee
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...Paul Menig
 

Dernier (20)

Best Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in IndiaBest Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in India
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
 
Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...
 
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetCreating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Service
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst Summit
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Century
 
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabiunwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptx
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMAN
 
Grateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfGrateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdf
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...
 
Call Girls In Holiday Inn Express Gurugram➥99902@11544 ( Best price)100% Genu...
Call Girls In Holiday Inn Express Gurugram➥99902@11544 ( Best price)100% Genu...Call Girls In Holiday Inn Express Gurugram➥99902@11544 ( Best price)100% Genu...
Call Girls In Holiday Inn Express Gurugram➥99902@11544 ( Best price)100% Genu...
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.
 
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Service
 
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyThe Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...
 

Thiet ke duong_ong_tren_bo

  • 1. G.U.P PHASE II - LIQUID PIPELINES, TERMINAL & JETTIES TABLE OF CONTENTS 1.0 INTRODUCTION 2.0 SUMMARY 3.0 SOIL RESISTIVITY SURVEY 4.0 DESIGN PARAMETERS 5.0 CATHODIC PROTECTION DESIGN CALCULATIONS Page 2 of
  • 2. G.U.P PHASE II - LIQUID PIPELINES, TERMINAL & JETTIES 1.0 INTRODUCTION This report defines the design calculations and requirements of Cathodic Protection System for one No. 17" existing gas pipeline and three new LPG product pipelines. An impressed current cathodic protection system will be installed to supplement the' corrosion coating in providing corrosion control to the pipeline. The impressed current Cathodic Protection system for existing gas pipeline will be upgraded to suit the new requirement for existing gas pipeline as well as new LPG product pipelines. 2.0 SUMMARY Cathodic protection is specified for the onshore section of the subject pipeline from Dinh Co to Thi Vai for new LPG pipeline and from Long Hi to Phu My for existing gas pipeline- length and other parameters are as given in Secsion 4.0 of this document. Both galvanic anode and impressed current cathodic protection systems were considered during this 0 design. An impressed current cathodic protection system has been selected on a technical basis. The cathodic protection system has been designed in accordance with internationally accepted standards and compliance the codes and standards listed in section 1.2 o specification. A conservation design approach has been used including a 30 mA/m2 current density and 95% coating efficiency. For future addition a 20% spare output capacity has been provided ( NACE-1967). It has been determined that a single impressed current system required upgrading at the Phuoc Hoa LBV and at the Dinh Co Station would provide full cathodic protection of new LPG pipelines and existing gas pipelines. The soil resistivities at this location justified the installation of an effective surface anode groundbed. The groundbed will be located approximately 100 m from the pipeline and position perpendicularly to the pipeline in accordance with the --project specification (BS-7361 ). A rectifier will be used to energize the groundbed. They.415. VAC; three phases power supply to the rectifier will be provided from the�415;volt switchboard. Elec€rical isolation of the pipeline will be provided by the installation of insulating flange sets c: Insulating flange set shall be provided with Explosion-proof surge diverters to prevent damage due to lightning or power surges. Test stations will be provided to monitor and adjust the cathodic protection system . Test station also have to be provided at following location • Both side of the major river or road crosing. • At all insulating joint. • At HT overhead line crossing. • At all vulnerable location where interferance is possible These test stations will be located at maximum intervals of 1.5 km. All cable connections to the pipeline will be made using the brassing thermit weld process. 3.0 SOIL RESISTIVITY SURVEY Soil resistivity measurements have been previously carried out by others at 65 location along the pipeline ROW. According to the information included in the contract documents. this testing was performed using the Wenner 4-pin method at depth of 0.75, 1.5, and metres using a .M-416 instrument made in the Soviet Union. Test equipment must have maximum AC & DC ground current rejection feature. Soil resistivities are critical to the proper design of a cathodic protection system. They are used as a guide to determine the P9-CPS.05-01.0 Page of I
  • 3. G.U.P PHASE II - LIQUID PIPELINES, TERMINAL & JETTIES corrosiveness of the soil and also used to select ground locations and configurations. Soil resistivities are important regardless of whether and impressed current or a sacrificial anode cathodic protection system is utilized. It should be understood that this cathodic protection design has been based on the soil resistivities determined by others. Any inaccuracies in the reported resistivity values versus the actual resistivity values could have a significant impact on the effectiveness of the cathodic protection system. This can only be determined during commissioning of the system when the Contractor shall check the.soil resitivity inspection accordance with specification. 4.0 DESIGN PARAMETERS The following sub-sections include parameters which have been used for design of the proposed cathodic protection system. 4.1 GENERAL PIPELINE DETAILS These calculation for upgrading existing CP system for new LPG pipelines and existing gas pipeline will be done through two (2) cathodic protection system design. 4.1.1 Portion 1: (CP Station at Dinh Co location ) Y Gas pipeline (Long Hai to Ba Ria) Length of pipeline 16.5 km a Pipeline diameter 406.4 mm 1 /17 Pipeline number 1 Coating Coal tar enamel • LPG pipelines (Dinh Co to Ba Ria) Length of pipeline 7.5 km Pipeline diameter 168 mm C L� Pipeline number 3 Coating Polyethylene 4.1.2 Portion 2: (CP Station at Phuoc Hoa location ) Gas pipeline (Ba Ria to Phu My) Length of pipeline 21.5 km Pipeline diameter 426 mm Pipeline number Coating Coal tar enamel LPG pipelines (Ba Ria to Thi Vai) Length of pipeline 17 km Pipeline diameter 168 mm Pipeline number 3 Page 4 of I ' P9-CPS.05-01.0
  • 4. Rev. D /,(
  • 5. G.U.P PHASE II - LIQUID PIPELINES, TERMINAL & JETTIES Coating Polyethylene 4.2 CATHODIC PROTECTION DESIGN LIFE In accordance with the contract documents, the impressed current cathodic protection system will have a design life of 30 years. The cathodic protection Contractor shall demonstrate the design life of his proposed CP system. 4.3 ANODE TYPE 1 T' 'um tubular anodes with a mixed metal oxide coating will be installed. These anodes have proven to have superior operating characteristics over silicon iron and graphite anodes. Titanium / mixed metal oxide anode are also of lighter weight and capable of significantly higher current outputs and longer life. 4.4 COATING EFFICIENCY A common method to assess the pipe coating condition is to use a factor referred to "percent bare". For a normal factory applied coaltar enamel coating system which would be inspected and repaired prior to back filling. of the pipe, a value of a approximately I to 2 percent bare would be experienced immediately subsequent to construction. However, during the service life of the pipeline with expansion and contraction of the pipeline due to thermal effects, soil movement, water ingress through the coating etc, the condition of the coating will deteriorate. A conservative coating efficiency of 95% has been used for this cathodic protection design. This means that over the 30 year life, the cathodic protection system will have the capacity protect an average of 5% of the total surface area of the pipeline. 4.5 CP CURRENT DENSITY The National Association of Corrosion Engineers (NACE) Recommended practice RP-0169-92 and DNV RP B401 specifies a current density of 10-30 mA/m2 for bare steel structures in soil. The soils along the proposed ROW for this pipeline are very aggressive with high moisture content, high salinity and low soil resistivity. Therefore, this design uses a conservative 30 mAIm2 current density. 4.6 SOIL RESISTIVITY 4.6.1 Dinh Co Location As mentioned in previous Section 3.0, soil resistivity testing along the pipeline ROW has been previously carried out by others. A review of this data indicates that points R-18 and R-19 are located relatively near Dinh Co: Depth (m) Soil Resistivity (ohm cm) R-18 0.75 8000 1.50 4200 P9-CPS.05-01.0 . Page 5 of 14
  • 6. G.U.P PHASE II - LIQUID PIPELINES, TERMINAL & JETTIES 3.00 1050 R-19 0.75 3600 1.50 1300 3.00 500 The deep-well anode system will be installed for cathodic protection, The average resistivity value for the above two points at a 1.5m depth is 2750 ohm-cm and will be used t For groundbed design at Dinh Co. 4.6.2 Phuoc Hoa Location Also mentioned in previous Section 3.0, soil resistivity testing along the pipeline ROW has been previously carried out by others. A review of this data indicates that points BH23 aid BH24 are located relatively near Ba Ria ( at Phuoc Hoa ) where the impressed current CP system will be located. The soil resistivity values reported at these locations are : Depth (m) Soil Resistivity (ohm ern) BH23 0.75 1300 1.50 1500 3.00 1000 BH24 0.75 1500 1.50 1500 3.00 800 The average resistivity value for the above two points at a 1.5m depth is 1500 ohm-cnl _:d will be used for groundbed design at Phuoc Hoa. 4.7 CATHODIC PROTECTION CRITERIA NACE Recommended Practice RP-0169-92 addresses cathodic protection criteria --Dr underground and submerged metallic piping systems. Applicable excerpts of this st.and=d relative to CP criteria for this project are as follows- A negative (cathodic) potential of at least 85OmV with the cathodic protecti'Dn applied. This potential is measured with respect to a saturated copper / copper ulfat.e reference electrode contacting the electrolyte. Voltage drops other than those across the structure to electrolyte boundary must be considered for valid interpretation of this voltage measurement. A negative polarized potential of at least 850 mV relative to a saturated copper / copper sulfate reference electrode. P9-CPS.05-01.0
  • 7. G.U.P PHASE II - LIQUID PIPELINES, TERMINAL & JETTIES A minimum of 100 mA of cathodic polarization between the structure surface and a stable reference electrode contacting the electrolyte. The formation or decay of polarization can be'measured to satisfy this criterion. 5.0 CATHODIC PROTECTION DESIGN CALCULATIONS 5.1 DINH CO LOCATION 5.1.1 Pipeline Total Surface Area The onshore portion of Long Hai to Ba Ria gas pipeline and Dinh Co to Ba Ria LPG pipelines has a total surface area as follows: Sa = (Pi) (d) (1) Sa (3.1416)-[(0.406,x 16500) + (3 x 0.168 x 7500)] Sa = 32921 (m2) Where: Sa = Surface area (m2 ) Pi = 3.1416 1 Length of pipeline (m) Diameter of pipeline (m) 5.1.2 CATHODIC PROTECTION CURRENT REQUIREMENT The cathodic protection system will have a DC output capacity as follows: (Sa) (Id) (Cb) It ZSF 1000 (32921) (30) (0.05) It X1.1 1000 It = 54.32 (A) Say 55 amperes Where: Sa Total surface area (m2 ) Id = CP current density (mA/m2 ) Cb = Coating breakdown factor (%) SF = Safety factor (1.1) 5.1.3 CATHODIC PROTECTION ANODE REQUIREMENT Chosen output rating of 2 Ampere for each anode, the number of anodes: N = It/2 = 54.32/2 = 27.16 No. of anodes based on current requirement Page 7 of 14 m.1
  • 8. G.U.P PHASE II - LIQUID PIPELINES, TERMINAL & JETTIES N = 30 Another, maximum anode current output for each anodeto be determined as follows : LogL= 3.3 - LogId Where : L = design life in years Id = Maximum anode current density (A/m2 ) For L = 3 0 years The anode has a dimension of 31.75mm dia x I000mm legth with a.total area of 0.1m2 Therefore, Id =.66.5 A/m2 Maximum current output of anode = 0.1m2 x 66.5 A/m2 =6.65A Hence 3 0 anodes will give 6.65 x3 0 = 199.5 A > Required 54.3 2 A (0) (It)(y) noe wegt requ id re , W = Uf 0.1 (54.32) (30) W 0.6 W = 271.6 kg Anodes No. required based on weight requirement : N W/Wa 271.6 / 20 13.6 No. of anodes based on weight requirement, N = 14 Where Q Anode consumption rate (kg/amp-year) It = Cathodic Protection current ( A ) Y = Design life of the system ( years ) Uf = Anode Utilization factor ( 0.6 for a conservative design ) Wa = Weight of individual anode ( kg ) Hence anode No. chosen is 30 There are 20 canister anodes in existing groundbed at Dinh Co, so that 10 canister anodes which are the same existing anode specification will be required to add in this location. 5.1.4 GROUNDBED RESISTANCE Installation of 30 canister anodes on 5 metre spacing in 2750 ohm-cm soil results in an estimated groundbed resistance of 0.5844 ohm as follows: Rn = RI + R2 ( NACE - 1967, page 95 ) Where Rl Anode to backfill resistance R2 Backfill to soil resistance Pb BLcr - 1+ 2La R1 [In In(0.656N)]) { NACE - 1967 ) N.yLcrx6.28 do S .- I + (2)(100) R1' = 50 Fn (8)(100) ln(0.656)(30)] (30)(100)(6.28) 3175 500 Ri 0.0152 (ohm) Rev. D -
  • 9. G.U.P PHASE II - LIQUID PIPELINES, TERMINAL & JETTIES Where: Pb Backfill resistivity (ohm-cm) La = Length of anode- excluding backfill (cm) da = Diameter of anode- excluding backfill (cm) S = Spacing of anodes (cm) N Number of anodes.. Ps 8Lc -1 + 2Lc R2 [In In(0.656N)J) (NACE - 196J ) NxLcx6.28 do S 2750 (8) (150) (2) (150) R2 -1 + in(0.656)(30)J (30)(150)(6.28) [in 76 500 R2 = 0.5692 (ohm) Where: Ps Soil resistivity (ohm-cm) Lc Length of anode- including backfill (cm) dc Diameter of anode- including backfill (cm) S. Spacing of anodes (cm) Number of anodes. Hence Rn = 0.0152 + 0.5692 0.5844 (ohm) 5.1.5 TRANSFORMER RECTIFIER DC OUTPUT VOLTAGE It is estimated that the transformer rectifier will require a 45 volt output to achieve :Lie desired 54.32 ampere DC current output as follows: It.(Rn+Rc) + Bemf E 54.32x(0.5844 + 0.2) + 2 E 44.6 volts Say 45 volts Where : E Rectifier DC output voltage (volts) It = Rectifier output current (amp) Rn = Total groundbed resistance (ohm) Rc Total cable resistance (0.2 ohm) Bemf = Dropped voltage between pipeline and ground (-2.0 volts) Note : Pipe to earth resistance (Rpe) has not been considered since the coating resistari :e is so high.( >1010 ohm-mz ) that all current will pass through 5% bare areas through r±e pipeline coating. Rev. D
  • 10. G.U.P PHASE II - LIQUID PIPELINES, TERMINAL & JETTIES 5.1.6 TRANSFORMER RECTIFIER AC INPUT Actual DC power output required : Pd = 44.6 x 55.32 2422.672 (W) DC power requirement including 20% overvoltage provision (20% spare Capacity ) = 1.2x44.6x54.32=2907.2 (W) Now, considering overall system P.F (power factor) = 0.8 and Transformer Rectifier Unit efficiency (E.F) = 0.85 (85% ) For 3 phases, 415V, 50Hz supply input to Transformer Rectifier Unit : Input current 2907.2 Ip Jx415x0.8x0.85 Ip = 5.95 A Hence, AC power input ( including 20% spare capacity) is : 43 x 415 x 5.95 x 0.8 3420.23 Watt 5.1.7 CHANGE IN EARTH POTENTIAL DUE TO FORCED DRAINAGE When CP current is injected into ground through anode bed, the current flow results in a potential gradient in the earth. _... The change in earth potential near the pipelines (Ps)(It) V = 27r(r) (2750)(54.32) V 27zx10000 2.38 Volts Where : Ps Soil resistivity ( ohm-cm ) It Cathodic Protection current ( Ampere ) r Distance between pipeline and anode bed (cm ) 5.2 PHUOC HOA LOCATION 5.2.1 Pipeline Total Surface Area The onshore portion of Ba Ria to Phu My gas pipeline and Ba Ria to Thi Vai LPG pipelines has a total surface area as follows: Sa _ (Pi) (d) (1) Sa (3.1416) [(0.426 x 21.500)+ (3 x 0.168 x 17000)] Sa = 55691 (m2 ) P9-CPS.05-01.0 Page 10 of 14
  • 11. G.U.P PHASE I1- LIQUID PIPELINES, TERMINAL & JETTIES Where: Sa Surface area (m2 ) Pi 3.1416 I Length of pipeline (m) Diameter of pipeline (m) 5.2.2 CATHODIC PROTECTION CURRENT REQUIREMENT The cathodic protection system will have a DC output capacity as follows: ( Sa ) * Id * Cb It = xSF 1000 ( 55691 ) * 30 * 0 . 05 It = x1 . 1 1000 It = 91.89 A Say 92 amperes Where: Sa Total surface area (m2 ) Id = CP current density (mA/m2 ) Cb = Coating breakdown factor (%) SF = Safety factor (1.1) 5.2.3 CATHODIC PROTECTION ANODE REQUIREMENT Chosen output rating of 2 Ampere for each anode, the number of anodes: N = It/2 92/2 = 45.95 No. of anodes based on current requirement N = 50 Another, maximum anode current output for each anodeto be determined as follows : LogL=3.3 -Log Id Where : L = design life in years Id = Maximum anode current density ( A/m2 ) For L = 30 years The anode has a dimension of 31.75mm dia x 1000mm legth with a total area of 0.1m2 Therefore, Id = 66.5 A/m2 Maximum current output of anode = 0.1 m2 x 66.5 A/m2 = 6.65A Hence 50 anodes will give 6.65 x 50 = 332.5 A > Required 92 A (Q)(It)(Y) Anode weight required, W = Uf (0.1) (92) (30) W 0.6 = 460 kg Rev. D Page I 1-of 14-
  • 12. G.U.P PHASE II - LIQUID PIPELINES, TERMINAL & JETTIES Anodes No. required based on weight requirement : N = W / Wa 460 / 20 23 No. of anodes based on weight requirement, N = 23 Where Q = Anode consumption rate (kg/amp-year ) It = Cathodic Protection current (A ) Y = Design life of the system ( years ) Uf = Anode Utilization factor ( 0.6 for a conservative design Wa = Weight of individual anode ( kg ) Hence anode No. chosen is 30 There are 20 canister anodes in existing groundbed at Phuoc Hoa, so that 30 canister anodes which are the same existing anode specification will be required to add in this location. 5.2.4 OROUNDDED RESISTANCE Installation of 50 canister anodes on 5 metre spacing in 1500 ohm-cm soil results in an estimated groundbed resistance of 0.19 ohm as follows: Rn = R1 + R2 Where R1 = Anode to backfill resistance R2 Backfill to soil resistance R1= Pb  8 La 2 La  N × La × 6 . 28  Ln da − 1 + S (ln 0 . 656 N )    R1= 50  8 * 100 2 * 100  Ln −1+ (ln 0 . 656 * 50 )  50 × 100 × 6 . 28   3 . 175 500  R1 = 0.0094 Ohm Where: Pb Backfill resistivity (ohm-cm) Length of anode- excluding backfill (cm) La = Diameter of anode- excluding backfill (cm) da = Spacing of anodes (cm) S = Number of anodes. N =
  • 13. R2= Pb  8 Lc 2 Lc  N × Lc × 6 . 28  Ln dc − 1 + S (ln 0 . 656 N )    R2 = 50  8 * 150 2 * 150  50 × 150 × 6 . 28  Ln 3 . 175 − 1 + 500 (ln 0 . 656 * 50 )    R2= 0.196 (ohm) Where:. Ps = Soil resistivity (ohm-cm) Lc = Length of anode- including backfill (cm) dc Diameter of anode- including backfill (cm) S Spacing of anodes (cm) Number of anodes. Hence Rn 0.0094 + 0.196 0.2054 (ohm) 5.2.5 TRANSFORMER RECTIFIER DC OUTPUT VOLTAGE It is estimated that the transformer rectifier will require a 42 volt output to achieve the desired 92mpere DC current output as follows: It.(Rn+Rc) + Bemf E 92 x (0.2054 + 0.2) + 2 E 39.29 volts Say 42 volts Where.: E Rectifier DC output voltage (volts) it = Rectifier output current_ (amp) Rn _ Total groundbed resistance (ohm) Rc = Total cable resistance (0.2 ohm) Bemf = Dropped voltage between pipeline and ground (-2.0 volts) Note : Pipe to earth resistance (Rpe ) has not been considered since the coating resistance is so high ( >1010 ohm-nag ) that all current will pass through 5% bare areas through the pipeline coating. 5.2.6 TRANSFORMER RECTIFIER AC INPUT Actual DC power output required : Pdc = 39.29 x 92 3614.68 ( W)
  • 14. DC power requirement including 20% overvoltage provision (20% spare Capacity) = 1.2x39.29x92=4337.6 (W) Now, considering overall system P.F ( power factor) = 0.8 and Transformer Rectifier Unit efficiency (E.F) = 0.85 ( 85% ) For 3 phases, 415V, 50Hz supply input to Transformer Rectifier Unit : Input current IP= 4337 . 6 3 x 415 x 0 . 8 x 0 . 85 Ip =8.875 A Hence, AC power input ( including 20% spare capacity) is : - _ 3 x 415 x 8 . 875 x 0 . 8 = 5013 W
  • 15. : G.U.P PHASE II - LIQUID PIPELINES, TERMINAL & JETTIES 5.2.7 CHANGE IN EARTH POTENTIAL DUE TO FORCED DRAINAGE When CP current is injected into ground through anode bed, the current flow results in a potential gradient in the earth. The change in earth potential near the pipelines (Ps)(It) 2 r(r) (1500)(92) V = 2πxl0000 = 2.2 Volts Where : Ps = Soil resistivity ( ohm-cm ) It = Cathodic Protection current ( Ampere ) r = Distance between pipeline and anode bed ( cm ) Page 14 of 14