SlideShare une entreprise Scribd logo
1  sur  7
Télécharger pour lire hors ligne
1/7
Civilverse Admin 4 October 2020
MS Project Terminology- Top 20 Terms Everyone Must
Know
civilverse.org/ms-project-terminology
Microsoft Project is one of the most used project scheduling and planning tool. The
project schedule with the Gantt Chart is helpful in visualizing the timeline of the project.
The critical path can also be visualized through the same. This article covers the top 20
MS Project terminology.
One of the important features of Microsoft Project is to create resource loaded schedules.
The resources can be defined and then can be allotted to the activities. This helps in the
planning of the resources and their required duration.
The MS Project terminology covers the task, summary task, milestone, calendar in MSP,
recurring task, task dependencies, manually and auto-scheduled tasks, baseline schedule
and baseline cost etc.
Following are 20 must-know MS Project terminology. The understanding of these terms
will help to learn the MS Project effectively.
1. Task
The activity defined in the project schedule is called ‘task’ in MS Project.
2. Summary Task
2/7
Task, Summary Task and Milestone
The summary task is the one which summarises a task or a group of tasks. The duration of
the summary task depends on its sub-tasks. The start date of the summary task is the
earliest start of its sub-tasks and finish date is the last finish date of its sub-tasks. The
summary tasks indicate a higher level of WBS than its sub-tasks.
The summary tasks are highlighted by the bold text.
3. Milestone
A milestone indicates a task of zero duration. It is used as entry milestone, exit milestone,
completion of certain activity whose process of completion is not included in the task.
For example, the handover of the site to the contractor for starting the work can be
marked as entry milestone in the schedule. The mobilisation of equipment to a
construction site can be marked as a milestone and handover to the client after
construction as exit milestone.
4. Manually Scheduled Task
The manually-scheduled task gives the steering wheel to the user. The user defines the
duration, work and the start date of the activity. The manually scheduled task is denoted
with a blue pin.
The manually scheduled task is to be used when the duration, work or the start date are
not known and to be decided later.
5. Auto-Scheduled Task
Manually Scheduled and Auto-Scheduled Tasks
3/7
The auto-scheduled task itself schedules the start date on the project start date or the
current date as per the predefined settings. It also assumes the duration of the activity as 1
day which can be changed as per the requirement. It is denoted by a blue box with a grey
right arrow.
6. Predecessor and Successor
The predecessor and successor follow their usual meaning. For example, activity ‘A’ is
followed by activity ‘B’, then ‘A’ is called the predecessor to ‘B’ and ‘B’ is called the
successor to ‘A’.
7. Calendar
The calendar in MS Project defines the working and non-working days along with working
and non-working time for each day. The calendars are of two types- task calendar that
controls the task and the resource calendar that controls the resource. The MS Project
has three pre-defined calendars-
a. Standard (Project Calendar) with 8 hours working on working days and
Saturday and Sunday as non-working days
b. Night Shift Calendar with 12 am to 8 am working with Sunday off.
c. 24 Hour Calendar with 7 days for 24 hours working every day.
The new calendar can also be created with the desired working days and time along with
keeping provision for holidays, leave etc.
8. Duration
The duration of an activity is the time to complete the activity. The duration of an activity
can be suitably be defined in days, week or month. The task calendar controls the
duration in terms of excluding the non-working days.
4/7
9. Work
The MS Project calculates the finish date, and cost etc. by the work. The work is calculated
by duration and the working time. For example, an activity has 1-day duration and
Standard Project Calendar assigned to it, the MS Project considers the activity as 8 hours
of work.
10. Unit
In MS Project unit means the unit resource. The task can be assigned to a unit. The unit
can also be assigned 50% or 80% or in any desired percentage of its actual value to a task
depending on the work requirement.
The 50% assignment of a unit to a task means that the resource works half of its total
work.
11. WBS
WBS Code Definition Dialog Box
The Work Breakdown Structure (WBS) is the breakdown of a project into manageable and
deliverable parts. For More on WBS click here.
The MS Project assigns a WBS Code to every task. The WBS Code of a task can be
modified as per the organisation.
12. Project Start Date
The MS Project allows us to mention the project start date. This function is helpful in
aligning the auto-scheduled tasks to the project start date. Further, the whole project can
be postponed just by changing the project start date.
5/7
Project Start Date & Status Date
13. Status Date
The status date is used in the schedule update and monitoring. It is the date of a project
progress update. For example, a 10-day activity was to finish on 31 January, but you
update the progress as on 28 January, then 28 January is to be set as the status date.
The status date shouldn’t be confused as today date.
14. Recurring Tasks
Recurring Task
Recurring Task Dialog Box
st
th th
6/7
The recurring task is used for the activity that is repeated during the project life. For
example, review meetings held at the end of every month is a recurring task and it can be
defined just once under recurring task with the desired recurring time.
15. Task Dependencies
The tasks are interlinked with each other through task dependencies. The task
dependencies are of four types-
1. Start to Start (SS)– Two activities start together.
2. Start to Finish (SF)– First activity starts after the second activity finishes.
3. Finish to Finish (FF)– Two activities finish together.
4. Finish to Start (FS)– First activity finishes when first starts.
16. Lead and Lag Time
The lead and lag times are used in conjugation with the task dependencies. The lead time
is positive and the lag time is negative. For example, activity ‘B’ starts 1 day after activity
‘A’ then it can be said that activity ‘B’ has 1-day lead with Start to Start.
Similarly, if activity ‘B’ finishes one day before activity ‘A’ then, ‘A’ is linked to ‘B’ with
Finish to Finish with 1-day lag.
17. Respect Link
The respect link option is used for the manually scheduled tasks. The respect link function
enables the MS Project to reschedule the task as per task dependencies when the project is
being manually scheduled.
18. Resource
Resource Sheet
The resource in MS project can be defined as work, material or cost. The manpower is a
work resource, concrete used in the project is a material resource and the mobilisation
advance given to the contractor at the project start is the cost resource.
The amount of these resources can be accrued to the resource on the start of their usage
duration, end of the usage duration or prorated (distributed throughout the duration).
19. Baseline Schedule
7/7
Baseline Schedule
The project schedule agreed between the client and the contractor is called Baseline
Schedule. All the progress, delay, planned vs actual analysis, etc. are measured with
respect to the Baseline Schedule.
20. Baseline Cost
The cost of the project that is to be incurred as per the Baseline Schedule is called Baseline
Cost. The cost variation is measured against the Baseline Cost of the project.
Read the Part-2 of this article. Click MS Project Terminology-Top 20 Terms- Part 2.
Want to move ahead with MS Project? Click here for Changing Working days and Time in
MS Project.
For more on Project Schedules click here.
Liked the MS project terminology post? Or do you have a suggestion or a doubt? Let me
know in the comment below.
Happy Engineering!

Contenu connexe

Tendances

44259126 ms-project-presentation
44259126 ms-project-presentation44259126 ms-project-presentation
44259126 ms-project-presentation
Farrukh Raja
 

Tendances (20)

Primavera - Tutorial
Primavera - TutorialPrimavera - Tutorial
Primavera - Tutorial
 
Primavera P6 manual
Primavera P6 manual Primavera P6 manual
Primavera P6 manual
 
Primavera Training P6
Primavera Training P6Primavera Training P6
Primavera Training P6
 
Avoiding unrealistic schedules
Avoiding unrealistic schedulesAvoiding unrealistic schedules
Avoiding unrealistic schedules
 
tcc primavera
tcc primaveratcc primavera
tcc primavera
 
Primavera p6 advanced project planning
Primavera p6 advanced project planningPrimavera p6 advanced project planning
Primavera p6 advanced project planning
 
44259126 ms-project-presentation
44259126 ms-project-presentation44259126 ms-project-presentation
44259126 ms-project-presentation
 
Primavera p6 18.8 planning and scheduling guide r3
Primavera p6 18.8 planning and  scheduling guide r3Primavera p6 18.8 planning and  scheduling guide r3
Primavera p6 18.8 planning and scheduling guide r3
 
Loading cost in primavera schedule using resources and expenses r01
Loading cost in primavera schedule using resources and expenses r01Loading cost in primavera schedule using resources and expenses r01
Loading cost in primavera schedule using resources and expenses r01
 
Primavera Project Management
Primavera Project ManagementPrimavera Project Management
Primavera Project Management
 
Scheduling by using microsoft project 2013
Scheduling by using microsoft project 2013Scheduling by using microsoft project 2013
Scheduling by using microsoft project 2013
 
Project Management using MS Project 2010
Project Management using MS Project 2010Project Management using MS Project 2010
Project Management using MS Project 2010
 
Introduction To Primavera (P6)
Introduction To Primavera (P6)Introduction To Primavera (P6)
Introduction To Primavera (P6)
 
Essentials of EOT Claims
Essentials of EOT ClaimsEssentials of EOT Claims
Essentials of EOT Claims
 
ppt for primevera
ppt for primeverappt for primevera
ppt for primevera
 
PRIMAVERA P6 manual.pptx
PRIMAVERA P6 manual.pptxPRIMAVERA P6 manual.pptx
PRIMAVERA P6 manual.pptx
 
Project management in construction
Project management in constructionProject management in construction
Project management in construction
 
5 Popular Types of Construction Contracts
5 Popular Types of Construction Contracts5 Popular Types of Construction Contracts
5 Popular Types of Construction Contracts
 
Resource allocation and smoothing
Resource allocation and smoothingResource allocation and smoothing
Resource allocation and smoothing
 
Construction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedConstruction Delay Analysis, Simplified
Construction Delay Analysis, Simplified
 

Similaire à MS Project Terminology -Top 20 terms everyone must know

MGT 3302, Introduction to Project Management 1 Cou.docx
MGT 3302, Introduction to Project Management 1 Cou.docxMGT 3302, Introduction to Project Management 1 Cou.docx
MGT 3302, Introduction to Project Management 1 Cou.docx
adkinspaige22
 
Wbs & Project Scheduling
Wbs & Project SchedulingWbs & Project Scheduling
Wbs & Project Scheduling
sslovepk
 
MBA 6941, Managing Project Teams 1 Course Learning Outco.docx
MBA 6941, Managing Project Teams 1 Course Learning Outco.docxMBA 6941, Managing Project Teams 1 Course Learning Outco.docx
MBA 6941, Managing Project Teams 1 Course Learning Outco.docx
alfredacavx97
 
Project control tools by Samuel obino mokaya
Project control tools by Samuel obino mokayaProject control tools by Samuel obino mokaya
Project control tools by Samuel obino mokaya
Discover JKUAT
 
Critical Path MethodIntroductionOnce you have the network diag.docx
Critical Path MethodIntroductionOnce you have the network diag.docxCritical Path MethodIntroductionOnce you have the network diag.docx
Critical Path MethodIntroductionOnce you have the network diag.docx
annettsparrow
 
Summer Internship Report by waqar ahmed javed
Summer Internship Report by waqar ahmed javedSummer Internship Report by waqar ahmed javed
Summer Internship Report by waqar ahmed javed
Waqar Ahmed
 

Similaire à MS Project Terminology -Top 20 terms everyone must know (20)

Project 2007 full handout
Project 2007 full handoutProject 2007 full handout
Project 2007 full handout
 
MGT 3302, Introduction to Project Management 1 Cou.docx
MGT 3302, Introduction to Project Management 1 Cou.docxMGT 3302, Introduction to Project Management 1 Cou.docx
MGT 3302, Introduction to Project Management 1 Cou.docx
 
Building a-project-schedule
Building a-project-scheduleBuilding a-project-schedule
Building a-project-schedule
 
Pm chapter 5...
Pm chapter 5...Pm chapter 5...
Pm chapter 5...
 
Fundamentals of project planning and scheduling
Fundamentals of project planning and schedulingFundamentals of project planning and scheduling
Fundamentals of project planning and scheduling
 
Wbs & Project Scheduling
Wbs & Project SchedulingWbs & Project Scheduling
Wbs & Project Scheduling
 
2007 MS Project Training Instructors Manual (sample)
2007 MS Project Training Instructors Manual (sample)2007 MS Project Training Instructors Manual (sample)
2007 MS Project Training Instructors Manual (sample)
 
Pm chapter 5
Pm chapter 5Pm chapter 5
Pm chapter 5
 
Pm chapter 5
Pm chapter 5Pm chapter 5
Pm chapter 5
 
Construction Project Schedule Template- Residential Building
Construction Project Schedule Template- Residential BuildingConstruction Project Schedule Template- Residential Building
Construction Project Schedule Template- Residential Building
 
MS Project 2010 Training
MS Project 2010 TrainingMS Project 2010 Training
MS Project 2010 Training
 
MBA 6941, Managing Project Teams 1 Course Learning Outco.docx
MBA 6941, Managing Project Teams 1 Course Learning Outco.docxMBA 6941, Managing Project Teams 1 Course Learning Outco.docx
MBA 6941, Managing Project Teams 1 Course Learning Outco.docx
 
Free float and total float - PMP/CAPM from PMI
Free float and total float - PMP/CAPM from PMIFree float and total float - PMP/CAPM from PMI
Free float and total float - PMP/CAPM from PMI
 
Advanced project management mod 3
Advanced project management mod 3Advanced project management mod 3
Advanced project management mod 3
 
Project Implementation.pdf
Project Implementation.pdfProject Implementation.pdf
Project Implementation.pdf
 
Project control tools by Samuel obino mokaya
Project control tools by Samuel obino mokayaProject control tools by Samuel obino mokaya
Project control tools by Samuel obino mokaya
 
Critical Path MethodIntroductionOnce you have the network diag.docx
Critical Path MethodIntroductionOnce you have the network diag.docxCritical Path MethodIntroductionOnce you have the network diag.docx
Critical Path MethodIntroductionOnce you have the network diag.docx
 
Summer Internship Report by waqar ahmed javed
Summer Internship Report by waqar ahmed javedSummer Internship Report by waqar ahmed javed
Summer Internship Report by waqar ahmed javed
 
Project schedule- What, How, Tools & Techniques
Project schedule- What, How, Tools & TechniquesProject schedule- What, How, Tools & Techniques
Project schedule- What, How, Tools & Techniques
 
Planning and scheduling Techniques.ppt
Planning and scheduling  Techniques.pptPlanning and scheduling  Techniques.ppt
Planning and scheduling Techniques.ppt
 

Plus de SHAZEBALIKHAN1

Plus de SHAZEBALIKHAN1 (20)

Critical Path Explained With 7 Q&As and a Free Excel Template
Critical Path Explained With 7 Q&As and a Free Excel TemplateCritical Path Explained With 7 Q&As and a Free Excel Template
Critical Path Explained With 7 Q&As and a Free Excel Template
 
5 Project Risk Identification Tools I Use & How You Can Use Them Too
5 Project Risk Identification Tools I Use & How You Can Use Them Too5 Project Risk Identification Tools I Use & How You Can Use Them Too
5 Project Risk Identification Tools I Use & How You Can Use Them Too
 
Top 20 Standard Contract Clauses Every Manager Should Know
Top 20 Standard Contract Clauses Every Manager Should KnowTop 20 Standard Contract Clauses Every Manager Should Know
Top 20 Standard Contract Clauses Every Manager Should Know
 
Residential Building Preliminary Cost Estimate- Excel Template
Residential Building Preliminary Cost Estimate- Excel TemplateResidential Building Preliminary Cost Estimate- Excel Template
Residential Building Preliminary Cost Estimate- Excel Template
 
3 Most Important In-situ Soil Tests for Construction Works
3 Most Important In-situ Soil Tests for Construction Works3 Most Important In-situ Soil Tests for Construction Works
3 Most Important In-situ Soil Tests for Construction Works
 
5 Must Know Types of Concrete Testing for Civil Engineers
5 Must Know Types of Concrete Testing for Civil Engineers5 Must Know Types of Concrete Testing for Civil Engineers
5 Must Know Types of Concrete Testing for Civil Engineers
 
All About Construction Labour Planning- Excel Template
All About Construction Labour Planning- Excel TemplateAll About Construction Labour Planning- Excel Template
All About Construction Labour Planning- Excel Template
 
10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation Steps10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation Steps
 
Construction Material Estimate with MS Excel file
Construction Material Estimate with MS Excel fileConstruction Material Estimate with MS Excel file
Construction Material Estimate with MS Excel file
 
Managing the Construction Claims Effectively
Managing the Construction Claims EffectivelyManaging the Construction Claims Effectively
Managing the Construction Claims Effectively
 
Most Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management TermsMost Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management Terms
 
Top 5 Concrete Quality Control Methods at Site
Top 5 Concrete Quality Control Methods at SiteTop 5 Concrete Quality Control Methods at Site
Top 5 Concrete Quality Control Methods at Site
 
My 5 Learnings of Waterfall Project Management
My 5 Learnings of Waterfall Project ManagementMy 5 Learnings of Waterfall Project Management
My 5 Learnings of Waterfall Project Management
 
Construction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential BuildingConstruction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential Building
 
Project Time Estimation 6 Powerful Tips & Tricks
Project Time Estimation 6 Powerful Tips & TricksProject Time Estimation 6 Powerful Tips & Tricks
Project Time Estimation 6 Powerful Tips & Tricks
 
Types of Building Foundations- Shallow and Deep
Types of Building Foundations- Shallow and DeepTypes of Building Foundations- Shallow and Deep
Types of Building Foundations- Shallow and Deep
 
DCMA 14-Point Schedule Quality Check
DCMA 14-Point Schedule Quality CheckDCMA 14-Point Schedule Quality Check
DCMA 14-Point Schedule Quality Check
 
Basics of Contract Management
Basics of Contract ManagementBasics of Contract Management
Basics of Contract Management
 
Bamboo Reinforced Concrete - Criteria & Performance
Bamboo Reinforced Concrete - Criteria & PerformanceBamboo Reinforced Concrete - Criteria & Performance
Bamboo Reinforced Concrete - Criteria & Performance
 
Bricks- Size, Classification, Composition & Quality Control
Bricks- Size, Classification, Composition & Quality ControlBricks- Size, Classification, Composition & Quality Control
Bricks- Size, Classification, Composition & Quality Control
 

Dernier

FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
dollysharma2066
 
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night StandCall Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
amitlee9823
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
ankushspencer015
 
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Christo Ananth
 

Dernier (20)

FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night StandCall Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
NFPA 5000 2024 standard .
NFPA 5000 2024 standard                                  .NFPA 5000 2024 standard                                  .
NFPA 5000 2024 standard .
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank  Design by Working Stress - IS Method.pdfIntze Overhead Water Tank  Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
 
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
 
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdf
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELLPVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 

MS Project Terminology -Top 20 terms everyone must know

  • 1. 1/7 Civilverse Admin 4 October 2020 MS Project Terminology- Top 20 Terms Everyone Must Know civilverse.org/ms-project-terminology Microsoft Project is one of the most used project scheduling and planning tool. The project schedule with the Gantt Chart is helpful in visualizing the timeline of the project. The critical path can also be visualized through the same. This article covers the top 20 MS Project terminology. One of the important features of Microsoft Project is to create resource loaded schedules. The resources can be defined and then can be allotted to the activities. This helps in the planning of the resources and their required duration. The MS Project terminology covers the task, summary task, milestone, calendar in MSP, recurring task, task dependencies, manually and auto-scheduled tasks, baseline schedule and baseline cost etc. Following are 20 must-know MS Project terminology. The understanding of these terms will help to learn the MS Project effectively. 1. Task The activity defined in the project schedule is called ‘task’ in MS Project. 2. Summary Task
  • 2. 2/7 Task, Summary Task and Milestone The summary task is the one which summarises a task or a group of tasks. The duration of the summary task depends on its sub-tasks. The start date of the summary task is the earliest start of its sub-tasks and finish date is the last finish date of its sub-tasks. The summary tasks indicate a higher level of WBS than its sub-tasks. The summary tasks are highlighted by the bold text. 3. Milestone A milestone indicates a task of zero duration. It is used as entry milestone, exit milestone, completion of certain activity whose process of completion is not included in the task. For example, the handover of the site to the contractor for starting the work can be marked as entry milestone in the schedule. The mobilisation of equipment to a construction site can be marked as a milestone and handover to the client after construction as exit milestone. 4. Manually Scheduled Task The manually-scheduled task gives the steering wheel to the user. The user defines the duration, work and the start date of the activity. The manually scheduled task is denoted with a blue pin. The manually scheduled task is to be used when the duration, work or the start date are not known and to be decided later. 5. Auto-Scheduled Task Manually Scheduled and Auto-Scheduled Tasks
  • 3. 3/7 The auto-scheduled task itself schedules the start date on the project start date or the current date as per the predefined settings. It also assumes the duration of the activity as 1 day which can be changed as per the requirement. It is denoted by a blue box with a grey right arrow. 6. Predecessor and Successor The predecessor and successor follow their usual meaning. For example, activity ‘A’ is followed by activity ‘B’, then ‘A’ is called the predecessor to ‘B’ and ‘B’ is called the successor to ‘A’. 7. Calendar The calendar in MS Project defines the working and non-working days along with working and non-working time for each day. The calendars are of two types- task calendar that controls the task and the resource calendar that controls the resource. The MS Project has three pre-defined calendars- a. Standard (Project Calendar) with 8 hours working on working days and Saturday and Sunday as non-working days b. Night Shift Calendar with 12 am to 8 am working with Sunday off. c. 24 Hour Calendar with 7 days for 24 hours working every day. The new calendar can also be created with the desired working days and time along with keeping provision for holidays, leave etc. 8. Duration The duration of an activity is the time to complete the activity. The duration of an activity can be suitably be defined in days, week or month. The task calendar controls the duration in terms of excluding the non-working days.
  • 4. 4/7 9. Work The MS Project calculates the finish date, and cost etc. by the work. The work is calculated by duration and the working time. For example, an activity has 1-day duration and Standard Project Calendar assigned to it, the MS Project considers the activity as 8 hours of work. 10. Unit In MS Project unit means the unit resource. The task can be assigned to a unit. The unit can also be assigned 50% or 80% or in any desired percentage of its actual value to a task depending on the work requirement. The 50% assignment of a unit to a task means that the resource works half of its total work. 11. WBS WBS Code Definition Dialog Box The Work Breakdown Structure (WBS) is the breakdown of a project into manageable and deliverable parts. For More on WBS click here. The MS Project assigns a WBS Code to every task. The WBS Code of a task can be modified as per the organisation. 12. Project Start Date The MS Project allows us to mention the project start date. This function is helpful in aligning the auto-scheduled tasks to the project start date. Further, the whole project can be postponed just by changing the project start date.
  • 5. 5/7 Project Start Date & Status Date 13. Status Date The status date is used in the schedule update and monitoring. It is the date of a project progress update. For example, a 10-day activity was to finish on 31 January, but you update the progress as on 28 January, then 28 January is to be set as the status date. The status date shouldn’t be confused as today date. 14. Recurring Tasks Recurring Task Recurring Task Dialog Box st th th
  • 6. 6/7 The recurring task is used for the activity that is repeated during the project life. For example, review meetings held at the end of every month is a recurring task and it can be defined just once under recurring task with the desired recurring time. 15. Task Dependencies The tasks are interlinked with each other through task dependencies. The task dependencies are of four types- 1. Start to Start (SS)– Two activities start together. 2. Start to Finish (SF)– First activity starts after the second activity finishes. 3. Finish to Finish (FF)– Two activities finish together. 4. Finish to Start (FS)– First activity finishes when first starts. 16. Lead and Lag Time The lead and lag times are used in conjugation with the task dependencies. The lead time is positive and the lag time is negative. For example, activity ‘B’ starts 1 day after activity ‘A’ then it can be said that activity ‘B’ has 1-day lead with Start to Start. Similarly, if activity ‘B’ finishes one day before activity ‘A’ then, ‘A’ is linked to ‘B’ with Finish to Finish with 1-day lag. 17. Respect Link The respect link option is used for the manually scheduled tasks. The respect link function enables the MS Project to reschedule the task as per task dependencies when the project is being manually scheduled. 18. Resource Resource Sheet The resource in MS project can be defined as work, material or cost. The manpower is a work resource, concrete used in the project is a material resource and the mobilisation advance given to the contractor at the project start is the cost resource. The amount of these resources can be accrued to the resource on the start of their usage duration, end of the usage duration or prorated (distributed throughout the duration). 19. Baseline Schedule
  • 7. 7/7 Baseline Schedule The project schedule agreed between the client and the contractor is called Baseline Schedule. All the progress, delay, planned vs actual analysis, etc. are measured with respect to the Baseline Schedule. 20. Baseline Cost The cost of the project that is to be incurred as per the Baseline Schedule is called Baseline Cost. The cost variation is measured against the Baseline Cost of the project. Read the Part-2 of this article. Click MS Project Terminology-Top 20 Terms- Part 2. Want to move ahead with MS Project? Click here for Changing Working days and Time in MS Project. For more on Project Schedules click here. Liked the MS project terminology post? Or do you have a suggestion or a doubt? Let me know in the comment below. Happy Engineering!