3rd regional conference on public
procurement for ENP East countries
Contract award criteria
Dariusz Koba, KCG, Poland
Tbilisi, 6-7 November 2019
Two types of requirements
Procuring authority sets in tender documents many different
requirements concerning:
 subject matter
 contractor’s credibility
 contract
 costs or prices
All requirements may be set as:
 conditions, minimum standards which must be met,
fulfilled, evaluated on „yes/no” manner
 criteria evaluated by a scale, „to what extend is fulfilled”
Problem: Directives call minimum requirements (conditions)
concerning contractor’s credibility selection criteria (better
use this term to prequalification).
1
Conditions vs. criteria
You can indicate several general relationships:
 the better the contracting authority can define its needs,
the more requirements can be set as conditions;
 the more precisely conditions are defined, the smaller the
need to use technical criteria or the less their importance;
 the higher requirements, the greater the danger that they
may violate the principles of fair competition, which can
be resolved by formulating requirements by means of
criteria.
We use criteria not to hinder competiton but to support it.
2
Legal obligations
• Disclosure of criteria
To ensure compliance with the principle of equal treatment in the award
of contracts, contracting authorities should be obliged to create the
necessary transparency to enable all tenderers to be reasonably
informed of the criteria and arrangements which will be applied in the
contract award decision. (p. 90 of the preamble of the Directive
2014/24/EU).
• Determining the importance of criteria
The contracting authority shall specify, in the procurement documents,
the relative weighting which it gives to each of the criteria chosen to
determine the most economically advantageous tender, except where
this is identified on the basis of price alone. Those weightings may be
expressed by providing for a range with an appropriate maximum spread.
Where weighting is not possible for objective reasons, the contracting
authority shall indicate the criteria in decreasing order of importance.
(art. 67 para. 5 of the Directive 2014/24/EU).
3
Legal obligations
• Applying verifiable criteria
The criteria shall ensure the possibility of effective competition and shall
be accompanied by specifications that allow the information provided by
the tenderers to be effectively verified in order to assess how well the
tenders meet the award criteria. In case of doubt, contracting authorities
shall verify effectively the accuracy of the information and proof provided
by the tenderers. (art. 67 para. 4 of the Directive 2014/24/EU).
• Criteria linked to the subject-matter
Award criteria must be linked to the subject-matter of the procurement.
(art. 67 para. 3 of the Directive 2014/24/EU).
• Prohibition of criteria concerning contractor’s credibility
The exceptions to this rule are procurements for social services and non-
priority services in the field of defense and security.
4
Legal obligations
• Objective criteria
Contracts should be awarded on the basis of objective criteria that
ensure compliance with the principles of transparency, non-
discrimination and equal treatment, with a view to ensuring an objective
comparison of the relative value of the tenders in order to determine, in
conditions of effective competition, which tender is the most
economically advantageous tender. (p. 90 of the preamble of the
Directive 2014/24/EU).
• Does that mean criteria must me measurable?
• Degree of precision of criteria – freedom of choice
Award criteria shall not have the effect of conferring an unrestricted
freedom of choice on the contracting authority. (art. 67 para. 4 of the
Directive 2014/24/EU).
• measurable ---------------------- unrestricted freedom
5
Examples of criteria
Criteria may comprise, for instance:
 quality, including technical merit, aesthetic and functional
characteristics, accessibility, design for all users, social,
environmental and innovative characteristics and trading
and its conditions;
 organisation, qualification and experience of staff assigned
to performing the contract, where the quality of the staff
assigned can have a significant impact on the level of
performance of the contract; or
 after-sales service and technical assistance, delivery
conditions such as delivery date, delivery process and
delivery period or period of completion.
(art. 67 para. 2 of the Directive 2014/24/EU).
6
Types of criteria
Taking into account the principle that all criteria must be
related to the subject of the contract, it seems appropriate to
distinguish the following types of criteria:
 economic criteria, the most important, though not the
only, price;
 qualitative criteria referring to the quality of the subject
of the contract;
 contractual criteria referring to the manner of contract
performance;
 criteria for responsible development including social,
environmental and innovation issues;
 contractor’s credibility criteria - allowed only when
ordering social services and non-priority services in the
field of defense and security. 7
Strategies for selecting MEAT
Contracting authorities shall base the award of public
contracts on the most economically advantageous tender
(art. 67 para.1 of the Directive 2014/24/EU).
Most economically advantageous tender (MEAT) is now the
sole criterion and operates as an ‘umbrella criterion’ for the
award of the contract.
Directives seem to suggest the application of MEAT may
include three different options:
 the price only
 cost only (including life-cycle-costing)
 the best price/quality ratio
8
Strategies for selecting MEAT
I believe that cost only option is not a separate strategy, but a
type of strategy which tends to the minimization of costs, like
price only option. The difference is if you take into account
only initial cost of purchase or total cost of ownership or
even life-cycle-costing.
From an economic point of view, the choice of an offer may
follow one of three strategies:
 the lowest price/cost
 the best price-quality ratio
 the highest quality.
9
Minimization of cost
The choice of the offer is only based on the price or cost
criterion. This strategy requires that all other requirements
are precisely defined in terms of conditions:
 technical specifications, functional requirements, technical
standards of subject-matter
 contractual clauses determining time for execution of
contract, warranty requirements and so on.
The ordering party does not care about exceeding the set
requirements, but on their fulfillment at the lowest possible
price.
Good strategy for:
 printing paper / other office supplies?
 construction works (build)?
 …………………………….. 10
Minimization of cost
Variants or the strategy
 Price only - the only cost is the price to be paid
 Total cost of ownership (TCO) - when there are additional
costs to be paid in future (e.g. printers or copiers, when
the costs of consumables (inks, toners) are more
important for printing costs than the price of the devices
themselves).
 Life-cycle-costing (LCC) approach demands to take into
account not only TCO costs, but also costs imputed to
environmental externalities linked to the product, service
or works during its life cycle (art. 68 para. 2 of the
Directive 2014/24/EU)
11
Maximization of quality
In this strategy the price- or cost-related criteria are not
taken into account when selecting the offer. This does not
mean lack of interest in amount of expenditure, it means
only lack of preferences "the cheaper, the better".
The strategy demands informing contractors about planned
expenses or maximum budget which may be appropriate
especially in procurement of of intellectual services, when
the provision of this information is desirable and even
necessary.
The cost element may also take the form of a fixed price or
cost on the basis of which economic operators will compete
on quality criteria only (art. 67 para. 2 of the Directive
2014/24/EU).
Good strategy for intellectual services… 12
Quality – concept of fulfilment
The concept of order fulfilment is an „umbrella criterion”.
The contractor should be able to convince the contracting
authority that he is able to properly perform the contract.
The assessment may cover various aspects of the concept
that affect the expected quality and timeliness of the
contract, e.g.
 understanding the essence of the contract and the role of
the contractor;
 way to achieve the established goals, methods and means
of reaching the goals;
13
Quality – concept of fulfilment
 understanding the risks associated with the
implementation of the contract, the ability to neutralize
them and minimize the impact of risk on the
implementation of the contract;
 ability to plan actions over time, implementation
schedule;
 quality assurance plan, way of monitoring work progress,
reporting, implementation of repair plans;
 composition and organization of the team performing the
order, ways of coordinating the work.
14
Objectiveness
The concept of order fulfilment is non-measurable criterion.
Is it objective?
One of the rules of public procurement is that criteria should
be objective to ensure an objective comparison of the
relative value of the tenders (p. 90 of the preamble of the
Directive 2014/24/EU).
How to ensure objectivity of commission members?
15
Objectiveness
I believe, that in order to ensure maximum impartiality and
objectivity, the contracting authority should not disclose (if
possible) to the persons making the evaluation of offers:
 identity, name of the contractor;
 the name, brand of the product offered, the author of the
offer;
 offer price.
16
Fair competition
The concept of order fulfillment is non-measurable criterion.
Doesn’t it confer an unrestricted freedom of choice?
The chosen award criteria should not confer an unrestricted
freedom of choice on the contracting authority and they
should ensure the possibility of effective and fair competition
(p. 92 of the preamble of the Directive 2014/24/EU).
How to ensure effective and fair competition?
17
Fair competition
The criteria should be precise to the extent that ensures
uniform interpretation by ‘reasonably well informed and
normally diligent’ tenderer.
The criterion shall be interpreted in the same way by
practitioners involved in the type of activities covered by the
procurement in question.
The description of the criteria should communicate the
preferences of the procuring entity to the contractors and be
unambiguous enough to allow the contractor to adjust the
offer to these preferences.
18
Scoring offers in non-
measurable criteria
Very good example is the way used by Highways England.
19
Approach
offered
How well do the proposals meet the contract requirements and
demonstrate an understanding of the risks to the work?
Mark
Weak
The approach has not considered fully the requirements of the
contract and fails to demonstrate appropriate cost and risk control.
1-4
Acceptable
The proposed resources and programme are adequate for the
methodology described, and risk management procedures are
acceptable.
5
Good
The proposals show a well thought out balance between the
resources required to carry out the work and the resources and
approach proposed to mitigate the risks to the work.
6-7
Very Good
The proposals include specific project initiatives which give a high
degree of confidence of completing the project within the time and
budget constraints and mitigating risks
8-9
Excellent
The proposals include highly innovative and specific project
initiatives which give a high confidence of completing the project
within the time and budget constraints and minimising risks.
10
Scoring offers in non-
measurable criteria
Good criterion for intellectual services may be „Critical analysis of the
assumptions” (which are developed by procuring entity and attached to ToR):
20
Approach
tendered
How well does the offer meet the requirements of proper
implementation of the contract and maximises the probability
of achieving results?
No of
points
Weak
The offer does not fully take into account the requirements of the
ToR, does not identify errors in the assumptions or proposee actions
that would create them.
1-4
Acceptable
The offer is correct, confirms the analysis, but does not bring added
value to the assumptions.
5
Good
The offer shows a thorough analysis and contains some proposals
that add value to the project.
6-7
Very Good
The offer includes project-specific proposals based on the
contractor's experience, which add a significant value to the project.
8-9
Excellent
The offer includes highly innovative and project-specific proposals
based on the contractor's experience, which add a significant value
to the project.
10
Quality as measurable criterion
The quality of products can be understood in a different
ways, especially as technical or functional parameters.
To describe the criterion consisting of many sub-criteria
being technical and functional parameters, a table may be
used:
The description of the criterion formulated in the above
manner causes that technical parameters and functionality
become a measurable criterion. 21
parameter
description
growing /
decreasing
minimum
value
optimum
value
maximum number
of points
Measurable criteria
The evaluation of offers in measurable criteria is carried out
by using a formula, an algorithm that allows for automatic
evaluation of offers. In the case of criteria described
numerically, e.g. the price of the offer is a necessary way of
assessing the offers.
There are many formulas that can be used to evaluate offers,
especially regarding the price of the offer.
The formula should reflect the ordering party's preferences
as faithfully as possible.
Not only the scoring of the offers depends on the adopted
formula, but above all the bid strategies adopted by the
contractors.
22
Scoring prices
23
How to develop weights
The contracting party may use one of methods supporting of
decision-making. Many methods are being developed that
could be used:
1) substitution method
2) The Analytical Hierarchy Process (AHP)
3) Electre methods (ELimination Et Choix Traduisant la Realia)
4) Promethee methods (Preference Ranking Organization
METHod for Enrichment Evaluations)
5) TOPSIS (Technique for Order Preference by Similarity to
Ideal Solution)
6) EVAMIX
The Analytic Hierarchy Process is a simple method that is
perfectly suitable for determining the weightings of criteria.24
10 steps to the MEAT
Step 1. The criteria and their weights should be adjusted to
the justified needs of the procuring authority.
Step 2. The criteria based on non-verifiable contractors'
declarations should be avoided.
Step 3. Non-price criteria should be applied where it is
needed to select the MEAT.
Step 4. You should compare the Total Cost of Ownership (TCO)
rather than the purchase price.
Step 5. The criteria should differentiate.
25
10 steps to the MEAT
Step 6. To evaluate tenders in measurable criteria,
appropriate formulas should be used.
Step 7. Non-quantifiable criteria should be used if needed to
select the MEAT.
Step 8. Bids below the set minimum quality level should be
rejected.
Step 9. The weightings of criteria should be carefully selected,
preferably using decision support methods.
Step 10. Each time, the criteria and their weights should be
adjusted to the market conditions.
26
Thank You.
I wish You better procurements. In another way.
Dariusz Koba
27

Contenu connexe

Tendances

Manual on Market Examinations
Manual on Market ExaminationsManual on Market Examinations
Manual on Market ExaminationsOECD Governance
 
Ppp w.a. janssen - ippc6 -dublin 2014
Ppp   w.a. janssen - ippc6 -dublin 2014Ppp   w.a. janssen - ippc6 -dublin 2014
Ppp w.a. janssen - ippc6 -dublin 2014Dr. Paul Davis
 

Tendances (20)

PPT, B Garcia Porras, EC, Third ENP East public procurement conference, Tbili...
PPT, B Garcia Porras, EC, Third ENP East public procurement conference, Tbili...PPT, B Garcia Porras, EC, Third ENP East public procurement conference, Tbili...
PPT, B Garcia Porras, EC, Third ENP East public procurement conference, Tbili...
 
Implementation of selected principles of the OECD recommendation on public pr...
Implementation of selected principles of the OECD recommendation on public pr...Implementation of selected principles of the OECD recommendation on public pr...
Implementation of selected principles of the OECD recommendation on public pr...
 
Methodologies to measure market competition – Stephen Davies – Feb 2021 OECD ...
Methodologies to measure market competition – Stephen Davies – Feb 2021 OECD ...Methodologies to measure market competition – Stephen Davies – Feb 2021 OECD ...
Methodologies to measure market competition – Stephen Davies – Feb 2021 OECD ...
 
Obstacles to international enforcement co-operation
Obstacles to international enforcement co-operationObstacles to international enforcement co-operation
Obstacles to international enforcement co-operation
 
Presentation, Niels Schuster, 7th Regional Public Procurement Conference, Vlo...
Presentation, Niels Schuster, 7th Regional Public Procurement Conference, Vlo...Presentation, Niels Schuster, 7th Regional Public Procurement Conference, Vlo...
Presentation, Niels Schuster, 7th Regional Public Procurement Conference, Vlo...
 
OECD Gender inclusive competition policy – Key findings from William Kovacic ...
OECD Gender inclusive competition policy – Key findings from William Kovacic ...OECD Gender inclusive competition policy – Key findings from William Kovacic ...
OECD Gender inclusive competition policy – Key findings from William Kovacic ...
 
Market study methodologies for competition authorities – Chinese Taipei Fair ...
Market study methodologies for competition authorities – Chinese Taipei Fair ...Market study methodologies for competition authorities – Chinese Taipei Fair ...
Market study methodologies for competition authorities – Chinese Taipei Fair ...
 
Methodologies to Measure Market Competition – CHINESE TAIPEI – June 2021 OECD...
Methodologies to Measure Market Competition – CHINESE TAIPEI – June 2021 OECD...Methodologies to Measure Market Competition – CHINESE TAIPEI – June 2021 OECD...
Methodologies to Measure Market Competition – CHINESE TAIPEI – June 2021 OECD...
 
Economic Analysis in Merger Investigations – Break-out Session 1 - Surveys an...
Economic Analysis in Merger Investigations – Break-out Session 1 - Surveys an...Economic Analysis in Merger Investigations – Break-out Session 1 - Surveys an...
Economic Analysis in Merger Investigations – Break-out Session 1 - Surveys an...
 
Methodologies to measure market competition – Chiara Criscuolo – Feb 2021 OEC...
Methodologies to measure market competition – Chiara Criscuolo – Feb 2021 OEC...Methodologies to measure market competition – Chiara Criscuolo – Feb 2021 OEC...
Methodologies to measure market competition – Chiara Criscuolo – Feb 2021 OEC...
 
OECD Workshop Legal Models Enforcement Co-operation
OECD Workshop Legal Models Enforcement Co-operationOECD Workshop Legal Models Enforcement Co-operation
OECD Workshop Legal Models Enforcement Co-operation
 
Methodologies to measure market competition – DG COMP – Feb 2021 OECD Workshop
Methodologies to measure market competition – DG COMP – Feb 2021 OECD WorkshopMethodologies to measure market competition – DG COMP – Feb 2021 OECD Workshop
Methodologies to measure market competition – DG COMP – Feb 2021 OECD Workshop
 
Manual on Market Examinations
Manual on Market ExaminationsManual on Market Examinations
Manual on Market Examinations
 
Methodologies to Measure Market Competition – UKRAINE – June 2021 OECD discus...
Methodologies to Measure Market Competition – UKRAINE – June 2021 OECD discus...Methodologies to Measure Market Competition – UKRAINE – June 2021 OECD discus...
Methodologies to Measure Market Competition – UKRAINE – June 2021 OECD discus...
 
Economic analysis and evidence in abuse cases – Break-out Session 1 – Techniq...
Economic analysis and evidence in abuse cases – Break-out Session 1 – Techniq...Economic analysis and evidence in abuse cases – Break-out Session 1 – Techniq...
Economic analysis and evidence in abuse cases – Break-out Session 1 – Techniq...
 
Ppp w.a. janssen - ippc6 -dublin 2014
Ppp   w.a. janssen - ippc6 -dublin 2014Ppp   w.a. janssen - ippc6 -dublin 2014
Ppp w.a. janssen - ippc6 -dublin 2014
 
Economic Analysis in Merger Investigations – Break-out Session 2 – Quantitati...
Economic Analysis in Merger Investigations – Break-out Session 2 – Quantitati...Economic Analysis in Merger Investigations – Break-out Session 2 – Quantitati...
Economic Analysis in Merger Investigations – Break-out Session 2 – Quantitati...
 
Competition law and state-owned enterprises – OECD Secretariat – November 201...
Competition law and state-owned enterprises – OECD Secretariat – November 201...Competition law and state-owned enterprises – OECD Secretariat – November 201...
Competition law and state-owned enterprises – OECD Secretariat – November 201...
 
Fighting Rigging in the Energy Sector in Ukraine – A review of Public Procure...
Fighting Rigging in the Energy Sector in Ukraine – A review of Public Procure...Fighting Rigging in the Energy Sector in Ukraine – A review of Public Procure...
Fighting Rigging in the Energy Sector in Ukraine – A review of Public Procure...
 
Presentation by Malgorzata Stachowiak, Poland (ENG) Second SIGMA Regional ENP...
Presentation by Malgorzata Stachowiak, Poland (ENG) Second SIGMA Regional ENP...Presentation by Malgorzata Stachowiak, Poland (ENG) Second SIGMA Regional ENP...
Presentation by Malgorzata Stachowiak, Poland (ENG) Second SIGMA Regional ENP...
 

Similaire à OECD Public Procurement Conference: Contract Award Criteria

Aarhus+Frameworks+Conference_Semple.pdf
Aarhus+Frameworks+Conference_Semple.pdfAarhus+Frameworks+Conference_Semple.pdf
Aarhus+Frameworks+Conference_Semple.pdfssuser5fc33a
 
Pm0018 contracts management in projects
Pm0018 contracts management in projectsPm0018 contracts management in projects
Pm0018 contracts management in projectssmumbahelp
 
TUDARCO-PROCUREMENT ISSUES IN OIL AND GAS CONTRACTS
TUDARCO-PROCUREMENT ISSUES IN OIL AND GAS CONTRACTSTUDARCO-PROCUREMENT ISSUES IN OIL AND GAS CONTRACTS
TUDARCO-PROCUREMENT ISSUES IN OIL AND GAS CONTRACTSProf Handley Mpoki Mafwenga
 
Pm0018 contracts management in projects
Pm0018  contracts management in projectsPm0018  contracts management in projects
Pm0018 contracts management in projectssmumbahelp
 
Framework Days
Framework DaysFramework Days
Framework Daysvindma
 
Joao Costa, Legal and Compliance Counsel, Medtronic
Joao Costa, Legal and Compliance Counsel, MedtronicJoao Costa, Legal and Compliance Counsel, Medtronic
Joao Costa, Legal and Compliance Counsel, MedtronicIMSTA
 
Tender evaluation-strategy-template317
Tender evaluation-strategy-template317Tender evaluation-strategy-template317
Tender evaluation-strategy-template317dooooooost
 
IRJET- Importance of Proper Cost Management in Construction Industry
IRJET-  	  Importance of Proper Cost Management in Construction IndustryIRJET-  	  Importance of Proper Cost Management in Construction Industry
IRJET- Importance of Proper Cost Management in Construction IndustryIRJET Journal
 
Insurance tendering, is it such a challenge? London - May 2016
Insurance tendering, is it such a challenge? London - May 2016Insurance tendering, is it such a challenge? London - May 2016
Insurance tendering, is it such a challenge? London - May 2016Browne Jacobson LLP
 
Archiver omc stansted_tendering_procedure_and_requirements_final
Archiver omc stansted_tendering_procedure_and_requirements_finalArchiver omc stansted_tendering_procedure_and_requirements_final
Archiver omc stansted_tendering_procedure_and_requirements_finalArchiver
 
Procurement_Planinng.pptx
Procurement_Planinng.pptxProcurement_Planinng.pptx
Procurement_Planinng.pptxHussainRiazAli1
 

Similaire à OECD Public Procurement Conference: Contract Award Criteria (20)

Aarhus+Frameworks+Conference_Semple.pdf
Aarhus+Frameworks+Conference_Semple.pdfAarhus+Frameworks+Conference_Semple.pdf
Aarhus+Frameworks+Conference_Semple.pdf
 
Pm0018 contracts management in projects
Pm0018 contracts management in projectsPm0018 contracts management in projects
Pm0018 contracts management in projects
 
I0372044048
I0372044048I0372044048
I0372044048
 
TUDARCO-PROCUREMENT ISSUES IN OIL AND GAS CONTRACTS
TUDARCO-PROCUREMENT ISSUES IN OIL AND GAS CONTRACTSTUDARCO-PROCUREMENT ISSUES IN OIL AND GAS CONTRACTS
TUDARCO-PROCUREMENT ISSUES IN OIL AND GAS CONTRACTS
 
Public Sector Procurement
Public Sector ProcurementPublic Sector Procurement
Public Sector Procurement
 
Chapter -Two (2).pdf
Chapter -Two (2).pdfChapter -Two (2).pdf
Chapter -Two (2).pdf
 
Peter Kunzlik
Peter KunzlikPeter Kunzlik
Peter Kunzlik
 
TENDERS.pptx
TENDERS.pptxTENDERS.pptx
TENDERS.pptx
 
Pm0018 contracts management in projects
Pm0018  contracts management in projectsPm0018  contracts management in projects
Pm0018 contracts management in projects
 
EU procurement for non procurement professionals
EU procurement for non procurement professionalsEU procurement for non procurement professionals
EU procurement for non procurement professionals
 
Framework Days
Framework DaysFramework Days
Framework Days
 
Presentation, SIGMA workshop on tendering of PPP projects and contract signat...
Presentation, SIGMA workshop on tendering of PPP projects and contract signat...Presentation, SIGMA workshop on tendering of PPP projects and contract signat...
Presentation, SIGMA workshop on tendering of PPP projects and contract signat...
 
Albano_Nicholas_chapter 3
Albano_Nicholas_chapter 3Albano_Nicholas_chapter 3
Albano_Nicholas_chapter 3
 
Joao Costa, Legal and Compliance Counsel, Medtronic
Joao Costa, Legal and Compliance Counsel, MedtronicJoao Costa, Legal and Compliance Counsel, Medtronic
Joao Costa, Legal and Compliance Counsel, Medtronic
 
Tender evaluation-strategy-template317
Tender evaluation-strategy-template317Tender evaluation-strategy-template317
Tender evaluation-strategy-template317
 
Def ppt ippc vogel
Def ppt ippc vogelDef ppt ippc vogel
Def ppt ippc vogel
 
IRJET- Importance of Proper Cost Management in Construction Industry
IRJET-  	  Importance of Proper Cost Management in Construction IndustryIRJET-  	  Importance of Proper Cost Management in Construction Industry
IRJET- Importance of Proper Cost Management in Construction Industry
 
Insurance tendering, is it such a challenge? London - May 2016
Insurance tendering, is it such a challenge? London - May 2016Insurance tendering, is it such a challenge? London - May 2016
Insurance tendering, is it such a challenge? London - May 2016
 
Archiver omc stansted_tendering_procedure_and_requirements_final
Archiver omc stansted_tendering_procedure_and_requirements_finalArchiver omc stansted_tendering_procedure_and_requirements_final
Archiver omc stansted_tendering_procedure_and_requirements_final
 
Procurement_Planinng.pptx
Procurement_Planinng.pptxProcurement_Planinng.pptx
Procurement_Planinng.pptx
 

Plus de Support for Improvement in Governance and Management SIGMA

Plus de Support for Improvement in Governance and Management SIGMA (20)

PPT - SIGMA-GIZ Academies - Stage 1 - CAF Ukraine roadmap.pdf
PPT - SIGMA-GIZ Academies - Stage 1 - CAF Ukraine roadmap.pdfPPT - SIGMA-GIZ Academies - Stage 1 - CAF Ukraine roadmap.pdf
PPT - SIGMA-GIZ Academies - Stage 1 - CAF Ukraine roadmap.pdf
 
PPT - SIGMA-GIZ Academies - Stage 1 - CAF Moldova roadmap.pdf
PPT - SIGMA-GIZ Academies - Stage 1 - CAF Moldova roadmap.pdfPPT - SIGMA-GIZ Academies - Stage 1 - CAF Moldova roadmap.pdf
PPT - SIGMA-GIZ Academies - Stage 1 - CAF Moldova roadmap.pdf
 
PPT - SIGMA-GIZ Academies - Stage 1 -CAF Armenia roadmap.pdf
PPT - SIGMA-GIZ Academies - Stage 1 -CAF Armenia roadmap.pdfPPT - SIGMA-GIZ Academies - Stage 1 -CAF Armenia roadmap.pdf
PPT - SIGMA-GIZ Academies - Stage 1 -CAF Armenia roadmap.pdf
 
PPT - SIGMA-GIZ Academies - Stage 1 - Financial support tu PAR in Montenegro....
PPT - SIGMA-GIZ Academies - Stage 1 - Financial support tu PAR in Montenegro....PPT - SIGMA-GIZ Academies - Stage 1 - Financial support tu PAR in Montenegro....
PPT - SIGMA-GIZ Academies - Stage 1 - Financial support tu PAR in Montenegro....
 
PPT - SIGMA-GIZ Academies - Stage 1 - SIGMA opening.pdf
PPT - SIGMA-GIZ Academies - Stage 1 - SIGMA opening.pdfPPT - SIGMA-GIZ Academies - Stage 1 - SIGMA opening.pdf
PPT - SIGMA-GIZ Academies - Stage 1 - SIGMA opening.pdf
 
Photo gallery - SIGMA-GIZ Academies on QM - Stage 1.pdf
Photo gallery - SIGMA-GIZ Academies on QM - Stage 1.pdfPhoto gallery - SIGMA-GIZ Academies on QM - Stage 1.pdf
Photo gallery - SIGMA-GIZ Academies on QM - Stage 1.pdf
 
PPT - SIGMA-GIZ Academies - Stage 1 - prezentacija gsb podgorica.pdf
PPT - SIGMA-GIZ Academies - Stage 1 - prezentacija gsb podgorica.pdfPPT - SIGMA-GIZ Academies - Stage 1 - prezentacija gsb podgorica.pdf
PPT - SIGMA-GIZ Academies - Stage 1 - prezentacija gsb podgorica.pdf
 
PPT - SIGMA-GIZ Academies - Stage 1 - CAF-MONTENEGRO-29-FEB.pdf
PPT - SIGMA-GIZ Academies - Stage 1 - CAF-MONTENEGRO-29-FEB.pdfPPT - SIGMA-GIZ Academies - Stage 1 - CAF-MONTENEGRO-29-FEB.pdf
PPT - SIGMA-GIZ Academies - Stage 1 - CAF-MONTENEGRO-29-FEB.pdf
 
PPT - SIGMA-GIZ Academies - Stage 1 - CAF Georgia.pdf
PPT - SIGMA-GIZ Academies - Stage 1 - CAF Georgia.pdfPPT - SIGMA-GIZ Academies - Stage 1 - CAF Georgia.pdf
PPT - SIGMA-GIZ Academies - Stage 1 - CAF Georgia.pdf
 
PPT - SIGMA-GIZ Academies - Stage 1 - QM Roadmapping Day 2 and 3.pdf
PPT - SIGMA-GIZ Academies - Stage 1 - QM Roadmapping Day 2  and 3.pdfPPT - SIGMA-GIZ Academies - Stage 1 - QM Roadmapping Day 2  and 3.pdf
PPT - SIGMA-GIZ Academies - Stage 1 - QM Roadmapping Day 2 and 3.pdf
 
Academies-QM_Stage1_Ministry of Higher Education CAF.pdf
Academies-QM_Stage1_Ministry of Higher Education CAF.pdfAcademies-QM_Stage1_Ministry of Higher Education CAF.pdf
Academies-QM_Stage1_Ministry of Higher Education CAF.pdf
 
PPT - SIGMA-GIZ Academies - Stage 1 - ReSPA and CAF.pdf
PPT - SIGMA-GIZ Academies - Stage 1 - ReSPA and CAF.pdfPPT - SIGMA-GIZ Academies - Stage 1 - ReSPA and CAF.pdf
PPT - SIGMA-GIZ Academies - Stage 1 - ReSPA and CAF.pdf
 
PPT - SIGMA-GIZ Academies - Stage 1 -Bosnia Herzegovina CAF.pdf
PPT - SIGMA-GIZ Academies - Stage 1 -Bosnia Herzegovina CAF.pdfPPT - SIGMA-GIZ Academies - Stage 1 -Bosnia Herzegovina CAF.pdf
PPT - SIGMA-GIZ Academies - Stage 1 -Bosnia Herzegovina CAF.pdf
 
PPT - SIGMA-GIZ Academies - Stage 1 -Montenegro CAF.pdf
PPT - SIGMA-GIZ Academies - Stage 1 -Montenegro CAF.pdfPPT - SIGMA-GIZ Academies - Stage 1 -Montenegro CAF.pdf
PPT - SIGMA-GIZ Academies - Stage 1 -Montenegro CAF.pdf
 
PPT - SIGMA-GIZ Academies - Stage 1 - North Macedonia CAF.pdf
PPT - SIGMA-GIZ Academies - Stage 1 - North Macedonia CAF.pdfPPT - SIGMA-GIZ Academies - Stage 1 - North Macedonia CAF.pdf
PPT - SIGMA-GIZ Academies - Stage 1 - North Macedonia CAF.pdf
 
PPT - SIGMA-GIZ Academies - Stage 1 - CAF in Ukraine.pdf
PPT - SIGMA-GIZ Academies - Stage 1 - CAF in Ukraine.pdfPPT - SIGMA-GIZ Academies - Stage 1 - CAF in Ukraine.pdf
PPT - SIGMA-GIZ Academies - Stage 1 - CAF in Ukraine.pdf
 
PPT - SIGMA-GIZ Academies - Stage 1 -Serbia CAF.pdf
PPT - SIGMA-GIZ Academies - Stage 1 -Serbia CAF.pdfPPT - SIGMA-GIZ Academies - Stage 1 -Serbia CAF.pdf
PPT - SIGMA-GIZ Academies - Stage 1 -Serbia CAF.pdf
 
PPT - SIGMA-GIZ Academies - Stage 1 - SIGMA opening.pdf
PPT - SIGMA-GIZ Academies - Stage 1 - SIGMA opening.pdfPPT - SIGMA-GIZ Academies - Stage 1 - SIGMA opening.pdf
PPT - SIGMA-GIZ Academies - Stage 1 - SIGMA opening.pdf
 
Omnichannel management, by Willem Pieterson - SIGMA Webinars on service desig...
Omnichannel management, by Willem Pieterson - SIGMA Webinars on service desig...Omnichannel management, by Willem Pieterson - SIGMA Webinars on service desig...
Omnichannel management, by Willem Pieterson - SIGMA Webinars on service desig...
 
eZdravlje, by Vladimir Raickovic - SIGMA Webinars on service design and deliv...
eZdravlje, by Vladimir Raickovic - SIGMA Webinars on service design and deliv...eZdravlje, by Vladimir Raickovic - SIGMA Webinars on service design and deliv...
eZdravlje, by Vladimir Raickovic - SIGMA Webinars on service design and deliv...
 

Dernier

Russian Call Girl Hebbagodi ! 7001305949 ₹2999 Only and Free Hotel Delivery 2...
Russian Call Girl Hebbagodi ! 7001305949 ₹2999 Only and Free Hotel Delivery 2...Russian Call Girl Hebbagodi ! 7001305949 ₹2999 Only and Free Hotel Delivery 2...
Russian Call Girl Hebbagodi ! 7001305949 ₹2999 Only and Free Hotel Delivery 2...narwatsonia7
 
call girls in Narela DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Narela DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️call girls in Narela DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Narela DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️saminamagar
 
call girls in Punjabi Bagh DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Punjabi Bagh DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️call girls in Punjabi Bagh DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Punjabi Bagh DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️saminamagar
 
Call Girls Near Surya International Hotel New Delhi 9873777170
Call Girls Near Surya International Hotel New Delhi 9873777170Call Girls Near Surya International Hotel New Delhi 9873777170
Call Girls Near Surya International Hotel New Delhi 9873777170Sonam Pathan
 
2024: The FAR, Federal Acquisition Regulations - Part 26
2024: The FAR, Federal Acquisition Regulations - Part 262024: The FAR, Federal Acquisition Regulations - Part 26
2024: The FAR, Federal Acquisition Regulations - Part 26JSchaus & Associates
 
Panet vs.Plastics - Earth Day 2024 - 22 APRIL
Panet vs.Plastics - Earth Day 2024 - 22 APRILPanet vs.Plastics - Earth Day 2024 - 22 APRIL
Panet vs.Plastics - Earth Day 2024 - 22 APRILChristina Parmionova
 
2023 Ecological Profile of Ilocos Norte.pdf
2023 Ecological Profile of Ilocos Norte.pdf2023 Ecological Profile of Ilocos Norte.pdf
2023 Ecological Profile of Ilocos Norte.pdfilocosnortegovph
 
Madurai Call Girls 7001305949 WhatsApp Number 24x7 Best Services
Madurai Call Girls 7001305949 WhatsApp Number 24x7 Best ServicesMadurai Call Girls 7001305949 WhatsApp Number 24x7 Best Services
Madurai Call Girls 7001305949 WhatsApp Number 24x7 Best Servicesnajka9823
 
Call Girls Service AECS Layout Just Call 7001305949 Enjoy College Girls Service
Call Girls Service AECS Layout Just Call 7001305949 Enjoy College Girls ServiceCall Girls Service AECS Layout Just Call 7001305949 Enjoy College Girls Service
Call Girls Service AECS Layout Just Call 7001305949 Enjoy College Girls Servicenarwatsonia7
 
Powering Britain: Can we decarbonise electricity without disadvantaging poore...
Powering Britain: Can we decarbonise electricity without disadvantaging poore...Powering Britain: Can we decarbonise electricity without disadvantaging poore...
Powering Britain: Can we decarbonise electricity without disadvantaging poore...ResolutionFoundation
 
call girls in Tilak Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Tilak Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️call girls in Tilak Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Tilak Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️saminamagar
 
call girls in Model Town DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Model Town  DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️call girls in Model Town  DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Model Town DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️saminamagar
 
call girls in sector 22 Gurgaon 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in sector 22 Gurgaon  🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️call girls in sector 22 Gurgaon  🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in sector 22 Gurgaon 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️saminamagar
 
call girls in Mukherjee Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝...
call girls in Mukherjee Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝...call girls in Mukherjee Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝...
call girls in Mukherjee Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝...saminamagar
 
call girls in Mayapuri DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Mayapuri DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️call girls in Mayapuri DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Mayapuri DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️saminamagar
 
Action Toolkit - Earth Day 2024 - April 22nd.
Action Toolkit - Earth Day 2024 - April 22nd.Action Toolkit - Earth Day 2024 - April 22nd.
Action Toolkit - Earth Day 2024 - April 22nd.Christina Parmionova
 
Call Girl Benson Town - Phone No 7001305949 For Ultimate Sexual Urges
Call Girl Benson Town - Phone No 7001305949 For Ultimate Sexual UrgesCall Girl Benson Town - Phone No 7001305949 For Ultimate Sexual Urges
Call Girl Benson Town - Phone No 7001305949 For Ultimate Sexual Urgesnarwatsonia7
 
Earth Day 2024 - AMC "COMMON GROUND'' movie night.
Earth Day 2024 - AMC "COMMON GROUND'' movie night.Earth Day 2024 - AMC "COMMON GROUND'' movie night.
Earth Day 2024 - AMC "COMMON GROUND'' movie night.Christina Parmionova
 
Jewish Efforts to Influence American Immigration Policy in the Years Before t...
Jewish Efforts to Influence American Immigration Policy in the Years Before t...Jewish Efforts to Influence American Immigration Policy in the Years Before t...
Jewish Efforts to Influence American Immigration Policy in the Years Before t...yalehistoricalreview
 

Dernier (20)

Russian Call Girl Hebbagodi ! 7001305949 ₹2999 Only and Free Hotel Delivery 2...
Russian Call Girl Hebbagodi ! 7001305949 ₹2999 Only and Free Hotel Delivery 2...Russian Call Girl Hebbagodi ! 7001305949 ₹2999 Only and Free Hotel Delivery 2...
Russian Call Girl Hebbagodi ! 7001305949 ₹2999 Only and Free Hotel Delivery 2...
 
call girls in Narela DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Narela DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️call girls in Narela DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Narela DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
 
call girls in Punjabi Bagh DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Punjabi Bagh DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️call girls in Punjabi Bagh DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Punjabi Bagh DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
 
Call Girls Near Surya International Hotel New Delhi 9873777170
Call Girls Near Surya International Hotel New Delhi 9873777170Call Girls Near Surya International Hotel New Delhi 9873777170
Call Girls Near Surya International Hotel New Delhi 9873777170
 
2024: The FAR, Federal Acquisition Regulations - Part 26
2024: The FAR, Federal Acquisition Regulations - Part 262024: The FAR, Federal Acquisition Regulations - Part 26
2024: The FAR, Federal Acquisition Regulations - Part 26
 
Panet vs.Plastics - Earth Day 2024 - 22 APRIL
Panet vs.Plastics - Earth Day 2024 - 22 APRILPanet vs.Plastics - Earth Day 2024 - 22 APRIL
Panet vs.Plastics - Earth Day 2024 - 22 APRIL
 
2023 Ecological Profile of Ilocos Norte.pdf
2023 Ecological Profile of Ilocos Norte.pdf2023 Ecological Profile of Ilocos Norte.pdf
2023 Ecological Profile of Ilocos Norte.pdf
 
Madurai Call Girls 7001305949 WhatsApp Number 24x7 Best Services
Madurai Call Girls 7001305949 WhatsApp Number 24x7 Best ServicesMadurai Call Girls 7001305949 WhatsApp Number 24x7 Best Services
Madurai Call Girls 7001305949 WhatsApp Number 24x7 Best Services
 
Call Girls Service AECS Layout Just Call 7001305949 Enjoy College Girls Service
Call Girls Service AECS Layout Just Call 7001305949 Enjoy College Girls ServiceCall Girls Service AECS Layout Just Call 7001305949 Enjoy College Girls Service
Call Girls Service AECS Layout Just Call 7001305949 Enjoy College Girls Service
 
Powering Britain: Can we decarbonise electricity without disadvantaging poore...
Powering Britain: Can we decarbonise electricity without disadvantaging poore...Powering Britain: Can we decarbonise electricity without disadvantaging poore...
Powering Britain: Can we decarbonise electricity without disadvantaging poore...
 
call girls in Tilak Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Tilak Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️call girls in Tilak Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Tilak Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
 
call girls in Model Town DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Model Town  DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️call girls in Model Town  DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Model Town DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
 
9953330565 Low Rate Call Girls In Adarsh Nagar Delhi NCR
9953330565 Low Rate Call Girls In Adarsh Nagar Delhi NCR9953330565 Low Rate Call Girls In Adarsh Nagar Delhi NCR
9953330565 Low Rate Call Girls In Adarsh Nagar Delhi NCR
 
call girls in sector 22 Gurgaon 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in sector 22 Gurgaon  🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️call girls in sector 22 Gurgaon  🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in sector 22 Gurgaon 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
 
call girls in Mukherjee Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝...
call girls in Mukherjee Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝...call girls in Mukherjee Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝...
call girls in Mukherjee Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝...
 
call girls in Mayapuri DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Mayapuri DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️call girls in Mayapuri DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Mayapuri DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
 
Action Toolkit - Earth Day 2024 - April 22nd.
Action Toolkit - Earth Day 2024 - April 22nd.Action Toolkit - Earth Day 2024 - April 22nd.
Action Toolkit - Earth Day 2024 - April 22nd.
 
Call Girl Benson Town - Phone No 7001305949 For Ultimate Sexual Urges
Call Girl Benson Town - Phone No 7001305949 For Ultimate Sexual UrgesCall Girl Benson Town - Phone No 7001305949 For Ultimate Sexual Urges
Call Girl Benson Town - Phone No 7001305949 For Ultimate Sexual Urges
 
Earth Day 2024 - AMC "COMMON GROUND'' movie night.
Earth Day 2024 - AMC "COMMON GROUND'' movie night.Earth Day 2024 - AMC "COMMON GROUND'' movie night.
Earth Day 2024 - AMC "COMMON GROUND'' movie night.
 
Jewish Efforts to Influence American Immigration Policy in the Years Before t...
Jewish Efforts to Influence American Immigration Policy in the Years Before t...Jewish Efforts to Influence American Immigration Policy in the Years Before t...
Jewish Efforts to Influence American Immigration Policy in the Years Before t...
 

OECD Public Procurement Conference: Contract Award Criteria

  • 1. © OECD 3rd regional conference on public procurement for ENP East countries Contract award criteria Dariusz Koba, KCG, Poland Tbilisi, 6-7 November 2019
  • 2. Two types of requirements Procuring authority sets in tender documents many different requirements concerning:  subject matter  contractor’s credibility  contract  costs or prices All requirements may be set as:  conditions, minimum standards which must be met, fulfilled, evaluated on „yes/no” manner  criteria evaluated by a scale, „to what extend is fulfilled” Problem: Directives call minimum requirements (conditions) concerning contractor’s credibility selection criteria (better use this term to prequalification). 1
  • 3. Conditions vs. criteria You can indicate several general relationships:  the better the contracting authority can define its needs, the more requirements can be set as conditions;  the more precisely conditions are defined, the smaller the need to use technical criteria or the less their importance;  the higher requirements, the greater the danger that they may violate the principles of fair competition, which can be resolved by formulating requirements by means of criteria. We use criteria not to hinder competiton but to support it. 2
  • 4. Legal obligations • Disclosure of criteria To ensure compliance with the principle of equal treatment in the award of contracts, contracting authorities should be obliged to create the necessary transparency to enable all tenderers to be reasonably informed of the criteria and arrangements which will be applied in the contract award decision. (p. 90 of the preamble of the Directive 2014/24/EU). • Determining the importance of criteria The contracting authority shall specify, in the procurement documents, the relative weighting which it gives to each of the criteria chosen to determine the most economically advantageous tender, except where this is identified on the basis of price alone. Those weightings may be expressed by providing for a range with an appropriate maximum spread. Where weighting is not possible for objective reasons, the contracting authority shall indicate the criteria in decreasing order of importance. (art. 67 para. 5 of the Directive 2014/24/EU). 3
  • 5. Legal obligations • Applying verifiable criteria The criteria shall ensure the possibility of effective competition and shall be accompanied by specifications that allow the information provided by the tenderers to be effectively verified in order to assess how well the tenders meet the award criteria. In case of doubt, contracting authorities shall verify effectively the accuracy of the information and proof provided by the tenderers. (art. 67 para. 4 of the Directive 2014/24/EU). • Criteria linked to the subject-matter Award criteria must be linked to the subject-matter of the procurement. (art. 67 para. 3 of the Directive 2014/24/EU). • Prohibition of criteria concerning contractor’s credibility The exceptions to this rule are procurements for social services and non- priority services in the field of defense and security. 4
  • 6. Legal obligations • Objective criteria Contracts should be awarded on the basis of objective criteria that ensure compliance with the principles of transparency, non- discrimination and equal treatment, with a view to ensuring an objective comparison of the relative value of the tenders in order to determine, in conditions of effective competition, which tender is the most economically advantageous tender. (p. 90 of the preamble of the Directive 2014/24/EU). • Does that mean criteria must me measurable? • Degree of precision of criteria – freedom of choice Award criteria shall not have the effect of conferring an unrestricted freedom of choice on the contracting authority. (art. 67 para. 4 of the Directive 2014/24/EU). • measurable ---------------------- unrestricted freedom 5
  • 7. Examples of criteria Criteria may comprise, for instance:  quality, including technical merit, aesthetic and functional characteristics, accessibility, design for all users, social, environmental and innovative characteristics and trading and its conditions;  organisation, qualification and experience of staff assigned to performing the contract, where the quality of the staff assigned can have a significant impact on the level of performance of the contract; or  after-sales service and technical assistance, delivery conditions such as delivery date, delivery process and delivery period or period of completion. (art. 67 para. 2 of the Directive 2014/24/EU). 6
  • 8. Types of criteria Taking into account the principle that all criteria must be related to the subject of the contract, it seems appropriate to distinguish the following types of criteria:  economic criteria, the most important, though not the only, price;  qualitative criteria referring to the quality of the subject of the contract;  contractual criteria referring to the manner of contract performance;  criteria for responsible development including social, environmental and innovation issues;  contractor’s credibility criteria - allowed only when ordering social services and non-priority services in the field of defense and security. 7
  • 9. Strategies for selecting MEAT Contracting authorities shall base the award of public contracts on the most economically advantageous tender (art. 67 para.1 of the Directive 2014/24/EU). Most economically advantageous tender (MEAT) is now the sole criterion and operates as an ‘umbrella criterion’ for the award of the contract. Directives seem to suggest the application of MEAT may include three different options:  the price only  cost only (including life-cycle-costing)  the best price/quality ratio 8
  • 10. Strategies for selecting MEAT I believe that cost only option is not a separate strategy, but a type of strategy which tends to the minimization of costs, like price only option. The difference is if you take into account only initial cost of purchase or total cost of ownership or even life-cycle-costing. From an economic point of view, the choice of an offer may follow one of three strategies:  the lowest price/cost  the best price-quality ratio  the highest quality. 9
  • 11. Minimization of cost The choice of the offer is only based on the price or cost criterion. This strategy requires that all other requirements are precisely defined in terms of conditions:  technical specifications, functional requirements, technical standards of subject-matter  contractual clauses determining time for execution of contract, warranty requirements and so on. The ordering party does not care about exceeding the set requirements, but on their fulfillment at the lowest possible price. Good strategy for:  printing paper / other office supplies?  construction works (build)?  …………………………….. 10
  • 12. Minimization of cost Variants or the strategy  Price only - the only cost is the price to be paid  Total cost of ownership (TCO) - when there are additional costs to be paid in future (e.g. printers or copiers, when the costs of consumables (inks, toners) are more important for printing costs than the price of the devices themselves).  Life-cycle-costing (LCC) approach demands to take into account not only TCO costs, but also costs imputed to environmental externalities linked to the product, service or works during its life cycle (art. 68 para. 2 of the Directive 2014/24/EU) 11
  • 13. Maximization of quality In this strategy the price- or cost-related criteria are not taken into account when selecting the offer. This does not mean lack of interest in amount of expenditure, it means only lack of preferences "the cheaper, the better". The strategy demands informing contractors about planned expenses or maximum budget which may be appropriate especially in procurement of of intellectual services, when the provision of this information is desirable and even necessary. The cost element may also take the form of a fixed price or cost on the basis of which economic operators will compete on quality criteria only (art. 67 para. 2 of the Directive 2014/24/EU). Good strategy for intellectual services… 12
  • 14. Quality – concept of fulfilment The concept of order fulfilment is an „umbrella criterion”. The contractor should be able to convince the contracting authority that he is able to properly perform the contract. The assessment may cover various aspects of the concept that affect the expected quality and timeliness of the contract, e.g.  understanding the essence of the contract and the role of the contractor;  way to achieve the established goals, methods and means of reaching the goals; 13
  • 15. Quality – concept of fulfilment  understanding the risks associated with the implementation of the contract, the ability to neutralize them and minimize the impact of risk on the implementation of the contract;  ability to plan actions over time, implementation schedule;  quality assurance plan, way of monitoring work progress, reporting, implementation of repair plans;  composition and organization of the team performing the order, ways of coordinating the work. 14
  • 16. Objectiveness The concept of order fulfilment is non-measurable criterion. Is it objective? One of the rules of public procurement is that criteria should be objective to ensure an objective comparison of the relative value of the tenders (p. 90 of the preamble of the Directive 2014/24/EU). How to ensure objectivity of commission members? 15
  • 17. Objectiveness I believe, that in order to ensure maximum impartiality and objectivity, the contracting authority should not disclose (if possible) to the persons making the evaluation of offers:  identity, name of the contractor;  the name, brand of the product offered, the author of the offer;  offer price. 16
  • 18. Fair competition The concept of order fulfillment is non-measurable criterion. Doesn’t it confer an unrestricted freedom of choice? The chosen award criteria should not confer an unrestricted freedom of choice on the contracting authority and they should ensure the possibility of effective and fair competition (p. 92 of the preamble of the Directive 2014/24/EU). How to ensure effective and fair competition? 17
  • 19. Fair competition The criteria should be precise to the extent that ensures uniform interpretation by ‘reasonably well informed and normally diligent’ tenderer. The criterion shall be interpreted in the same way by practitioners involved in the type of activities covered by the procurement in question. The description of the criteria should communicate the preferences of the procuring entity to the contractors and be unambiguous enough to allow the contractor to adjust the offer to these preferences. 18
  • 20. Scoring offers in non- measurable criteria Very good example is the way used by Highways England. 19 Approach offered How well do the proposals meet the contract requirements and demonstrate an understanding of the risks to the work? Mark Weak The approach has not considered fully the requirements of the contract and fails to demonstrate appropriate cost and risk control. 1-4 Acceptable The proposed resources and programme are adequate for the methodology described, and risk management procedures are acceptable. 5 Good The proposals show a well thought out balance between the resources required to carry out the work and the resources and approach proposed to mitigate the risks to the work. 6-7 Very Good The proposals include specific project initiatives which give a high degree of confidence of completing the project within the time and budget constraints and mitigating risks 8-9 Excellent The proposals include highly innovative and specific project initiatives which give a high confidence of completing the project within the time and budget constraints and minimising risks. 10
  • 21. Scoring offers in non- measurable criteria Good criterion for intellectual services may be „Critical analysis of the assumptions” (which are developed by procuring entity and attached to ToR): 20 Approach tendered How well does the offer meet the requirements of proper implementation of the contract and maximises the probability of achieving results? No of points Weak The offer does not fully take into account the requirements of the ToR, does not identify errors in the assumptions or proposee actions that would create them. 1-4 Acceptable The offer is correct, confirms the analysis, but does not bring added value to the assumptions. 5 Good The offer shows a thorough analysis and contains some proposals that add value to the project. 6-7 Very Good The offer includes project-specific proposals based on the contractor's experience, which add a significant value to the project. 8-9 Excellent The offer includes highly innovative and project-specific proposals based on the contractor's experience, which add a significant value to the project. 10
  • 22. Quality as measurable criterion The quality of products can be understood in a different ways, especially as technical or functional parameters. To describe the criterion consisting of many sub-criteria being technical and functional parameters, a table may be used: The description of the criterion formulated in the above manner causes that technical parameters and functionality become a measurable criterion. 21 parameter description growing / decreasing minimum value optimum value maximum number of points
  • 23. Measurable criteria The evaluation of offers in measurable criteria is carried out by using a formula, an algorithm that allows for automatic evaluation of offers. In the case of criteria described numerically, e.g. the price of the offer is a necessary way of assessing the offers. There are many formulas that can be used to evaluate offers, especially regarding the price of the offer. The formula should reflect the ordering party's preferences as faithfully as possible. Not only the scoring of the offers depends on the adopted formula, but above all the bid strategies adopted by the contractors. 22
  • 25. How to develop weights The contracting party may use one of methods supporting of decision-making. Many methods are being developed that could be used: 1) substitution method 2) The Analytical Hierarchy Process (AHP) 3) Electre methods (ELimination Et Choix Traduisant la Realia) 4) Promethee methods (Preference Ranking Organization METHod for Enrichment Evaluations) 5) TOPSIS (Technique for Order Preference by Similarity to Ideal Solution) 6) EVAMIX The Analytic Hierarchy Process is a simple method that is perfectly suitable for determining the weightings of criteria.24
  • 26. 10 steps to the MEAT Step 1. The criteria and their weights should be adjusted to the justified needs of the procuring authority. Step 2. The criteria based on non-verifiable contractors' declarations should be avoided. Step 3. Non-price criteria should be applied where it is needed to select the MEAT. Step 4. You should compare the Total Cost of Ownership (TCO) rather than the purchase price. Step 5. The criteria should differentiate. 25
  • 27. 10 steps to the MEAT Step 6. To evaluate tenders in measurable criteria, appropriate formulas should be used. Step 7. Non-quantifiable criteria should be used if needed to select the MEAT. Step 8. Bids below the set minimum quality level should be rejected. Step 9. The weightings of criteria should be carefully selected, preferably using decision support methods. Step 10. Each time, the criteria and their weights should be adjusted to the market conditions. 26
  • 28. Thank You. I wish You better procurements. In another way. Dariusz Koba 27